1 MISO SPP Interregional Stakeholder Advisory Committee April 8 th, 2014 Carmel, IN 1

2 Agenda Introductions Discussion on Draft Coordinated System Plan (CSP) Study Scope Lunch Continue Discussion on Draft CSP Study Scope Discussion of Proposed Timeline & Next Steps Adjourn 2

3 COORDINATED SYSTEM PLAN STUDY SCOPE DRAFT 3

4 Scope Overview Draft scope presented for stakeholder review SPP & MISO staff initial recommendation IPSAC review and comment Staff refinement of the scope JPC approval 4

5 Study Purpose and Drivers Joint Operating Agreement (JOA) that requires a periodic coordinated system plan study Developed to meet Order 1000 interregional requirement Jointly evaluate seams issues and identify transmission solutions that efficiently address identified issues to the benefit of both regions Economic congestion Assessment of potential reliability violations Provide a common forum for stakeholders to participate in the identification and evaluation of transmission solutions in an open and transparent manner 5

6 Input from Stakeholders on Scope Stakeholder provided potential issues Congestion Integration of Integrated System & MISO South SPP market operation Real time operational issues Reliability issues Public policy requirements Proposed stakeholder issues taken into consideration during scope development 6

7 Task Scope Development Develop scope document Develop detailed schedule Congestion Issues Identification and Verification Future and Model Development Projected Congestion Analysis using BAU Future Historical Congestion Analysis Congestion Transmission Solution Development and Evaluation Solution Development Solution evaluation, robustness testing, reliability analysis, and interregional cost allocation Draft Coordinated System Plan Report Congestion Regional Transmission Justification and Cost Allocation (if needed) Regional transmission evaluation and justification Regional cost allocation and review Coordinated Reliability Assessment Perform reliability assessment using jointly developed powerflow models Identify potential reliability project alternatives 7

8 CONGESTION ISSUES IDENTIFICATION AND VERIFICATION 8

9 Joint Future Development Proposed Joint Future based off MISO and SPP Business as Usual Future (BAU) MISO 2015 MTEP BAU captures all current policies and trends in place at the time of futures development and assumes they continue, unchanged, throughout the duration of the study period. SPP 2015 ITP10 BAU (F1) utilizes inputs provided by SPP stakeholders to develop the modeling inputs based on the assumption that policy requirements will remain constant. Additionally two sensitivities will be performed on the preferred solutions to evaluate impacts of congestion on the two regions Price on carbon emissions High natural gas price forecast 9

10 Regional BAU Future Major Assumptions Regional BAU Futures Demand and Energy Growth Retirements Natural Gas Price RPS (10 year incremental GW) CO₂ DSM (annual reduction in year 10 for EE/DR) MISO 0.8% 12.6 GW Coal $4.30 (2014 $) 3.6 GW wind/ 1.1 GW Solar None 6,000 GWh/ 12 MW SPP 1.3% < 1 GW Coal $5.41 (2014 $) 3.3 GW Wind/ 20.5 MW Solar None Embedde d in Load 10

11 Joint Economic Model Development Foundation: Ventyx Powerbase data Updated with each RTO s modeling assumptions Model years: 2019 & 2024 Modeling Footprint MISO, SPP, AECI, Manitoba, MRO, PJM, SERC, & TVA SPP footprint will include the Integrated System WAPA, Basin, and Heartland with their projected integration of October

12 Joint Economic Model Development Contd. Source Topology Generation Hurdle Rates MISO SPP Both MISO, PJM, SERC, TVA, Manitoba SPP, WAPA, Basin, Heartland AECI region will be enhanced from MISO to include AECI s firm construction plan and any updates in the ITP10 MISO, all other regions SPP, Integrated System, AECI MISO PJM, MISO TVA, MISO MHEB, AECI TVA, TVA PJM, PJM SERC, SERC TVA, SERC AECI MISO SPP, MISO AECI, SPP AECI MISO s modeling of external areas is largely based on the Eastern Reliability Assessment Group (ERAG) Multi Regional Modeling Working Group (MMWG) series models. 12

13 Joint Economic Model Development Contd. Load Forecasts 50/50 case Load shape profiles from same year as wind profiles to ensure synchronization Demand Response and Energy Efficiency will be modeled consistent with how each planning region models it in their respective Business as Usual Futures. 13

14 Joint Economic Model Development Contd. Generation Existing resources come from MTEP 15 and ITP10 for respective regions Retirements based on each RTO s BAU assumptions New generation (including siting) will come from each RTO s BAU expansion plan Hourly profiles for renewables will be developed using data from NREL and will be time synchronized with load shapes. Integrated System and AECI resource plan will come from ITP10; all other external regions from MTEP15 expansion plan 14

15 Joint Economic Model Development Contd. Fuel Prices Coal, Oil, & Uranium fuel prices provided by Ventx Natural gas will come from the MTEP 15 BAU Future Nominal Henry Hub Forecast Price: 2019 = $5.19 and 2024 = $6.50 (Source: Bentek Forecast) Constraint Assessment NERC book of flowgates will be the starting point MISO & SPP will evaluate additional flowgates in the current MTEP and ITP10 models Constraint assessment will be performed to identify any additional flowgates beyond those previously identified Stakeholder input will be requested on identification of congested flowgates to monitor 15

16 Congestion Analysis Historical Identify congested flowgates based on historical TLR congestion March 1, 2012 March 1, 2014 Refreshed after 6 months of SPP market experience Projected 2019 & 2024 Promod BAU simulations Flowgates ranked on following indicators Binding hours number of hours in a year the flowgate is binding Shadow price Reduced production cost for 1 MW increase of thermal rating on the flowgate Congestion costs flowgate shadow price times MW flow on the flowgate 16

17 CONGESTION TRANSMISSION SOLUTION DEVELOPMENT & EVALUATION 17

18 Solution Identification Solution development guided by the congestion analysis and the issues submitted by stakeholders Solutions are not limited to tie line projects Solutions solicited through the IPSAC Transmission solutions proposed by RTO staffs and stakeholders 18

19 Solution Evaluation Preliminary analysis for screening Proposed projects evaluated to determine Adjusted Production Cost (APC) benefit Benefit to Cost ratio (B/C) developed 20 year present value calculation utilizing 2019 & 2024 year simulations Cost utilizing an average carrying charge rate 8% discount rate Projects must provide benefit to both SPP & MISO 19

20 Sensitivities Preferred solutions evaluated utilizing two sensitivities High gas price Carbon price Assumptions for the sensitivities will be reviewed with the IPSAC Not yet developed 20

21 Interregional Cost Allocation Interregional cost allocation methodology specified in the SPP MISO JOA Note that each RTO s respective Order 1000 interregional cost allocation proposals pending at FERC Cost allocated according to APC benefits Projects addressing economic congestion 21

22 Interregional Project Requirements for Interregional Cost Allocation Cost of at least $5,000,000 Provide benefits to both RTOs At least 95% 5% Address economic congestion No interregional B/C ratio requirement Regional requirements Projects can be included in the CSP report without meeting the requirements for cost allocation 22

23 COORDINATED RELIABILITY ASSESSMENT 23

24 Regional Reliability Projects Review Discuss proposed reliability projects identified in respective MTEP and ITP regional transmission planning processes located near the MISO SPP seam Determine if there are interregional alternatives to the currently proposed regional solutions 24

25 Steady State Assessment Steady state reliability assessment using jointly developed power flow models consistent with reliability processes used by each region System intact and N 1 steady state assessment For identified issues evaluate potential transmission solutions to address issues 25

26 Reliability Assessment for Interregional Projects Identified to Address Congestion Evaluate interregional projects identified to address congestion to ensure they do not create reliability issues May result in project modification or identification of additional facilities to mitigate the projected reliability issue(s) 26

27 REGIONAL REVIEW 27

28 Regional Analysis If interregional projects are identified, JPC may recommend projects to the respective RTO s regional process for review and possible Board approval Regional review will be performed consistent with the Tariff provisions of the respective regions Must be completed within 6 months of Interregional Projects recommended from JPC, unless there is agreement through the JPC for an alternative timeline Final report will be produced to include study results 28

29 STAKEHOLDER INVOLVEMENT & COMMUNICATION PLAN 29

30 Stakeholder Communication CSP Study data and information shared via the IPSAC Regional exploder Website posting Additional coordination through regional stakeholder groups 30

31 IPSAC Review Multiple review and comment opportunity throughout the CSP study study scope and analysis approach joint planning models and input assumptions identified seams transmission issues or opportunities proposed transmission solutions and alternatives recommendation on transmission solutions CSP report 31

32 SCHEDULE & NEXT STEPS 32

33 Task Schedule Status Scope Development February April 2014 Develop scope document Develop detailed schedule Congestion Issues Identification and Verification March September 2014 Future and Model Development March June Projected Congestion Analysis using BAU Future July September Historical Congestion Analysis September October Congestion Transmission Solution Development and Evaluation October 2014 June 2015 In Progress In Progress Solution Development Solution evaluation, robustness testing, reliability analysis, and interregional cost allocation Draft Coordinated System Plan Report October January February June Congestion Regional Transmission Justification and Cost Allocation (if needed) June 2015 Dec 2015 Regional transmission evaluation and justification Regional cost allocation and review June December Coordinated Reliability Assessment August 2014 June 2015 Perform reliability assessment using jointly developed powerflow models Identify potential reliability project alternatives 33

34 Next Steps Stakeholder comments on draft scope document due by: April 25, 2014 Updated scope document will be posted with today s meeting materials taking into consideration stakeholder feedback Targeted next IPSAC meeting in August Final date and location to be communicated to stakeholders as we get closer to the date Focus will be to present an update on the historical and projected congestion analysis 34

MISO-SPP Coordinated System Plan Study Report

MISO-SPP Coordinated System Plan Study Report MISO-SPP Coordinated System Plan Study Report June 30, 2015 Table of Contents 1 Executive Summary... 1 2 Introduction... 1 3 Stakeholder Involvement... 2 3.1 Third Party Coordination... 3 4 Scope... 4

More information

ATC Stakeholder Update 2019 PROMOD Study Assumptions. Tom Dagenais Todd Tadych ATC Economic Planning

ATC Stakeholder Update 2019 PROMOD Study Assumptions. Tom Dagenais Todd Tadych ATC Economic Planning ATC Stakeholder Update 2019 PROMOD Study Assumptions Tom Dagenais Todd Tadych ATC Economic Planning 7-10-09 1 Agenda / Introduction MISO RGOS Model Description MISO RGOS Model History and Background MISO

More information

2015 Economic Planning Study Assumptions

2015 Economic Planning Study Assumptions 2015 Economic Planning Study Assumptions Erik Winsand, ATC Economic Planning May 13, 2015 atcllc.com Introduction Process Overview and Timeline MISO MTEP16 Futures Assumptions Next Steps atcllc.com 2 Process

More information

JCM Drill Down Report -- Draft. March 21, 2014

JCM Drill Down Report -- Draft. March 21, 2014 JCM Drill Down Report -- Draft March 21, 2014 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill

More information

Transmission Expansion Advisory Committee Meeting Market Efficiency Analysis Preliminary Input Assumptions

Transmission Expansion Advisory Committee Meeting Market Efficiency Analysis Preliminary Input Assumptions Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis Preliminary Input Assumptions March 6, 2014 Study Years Market Simulation Input Data 2015 and 2019 to study approved RTEP

More information

MISO-PJM Joint and Common Market Drill Down Report

MISO-PJM Joint and Common Market Drill Down Report MISO-PJM Joint and Common Market Drill Down Report August 22, 2017 The purpose of this document is to provide a brief description of each component listed on the Joint and Common Market (JCM) Work Plan

More information

MISO-PJM Joint and Common Market Drill Down Report

MISO-PJM Joint and Common Market Drill Down Report MISO-PJM Joint and Common Market Drill Down Report May 30, 2018 The purpose of this document is to provide a brief description of each component listed on the Joint and Common Market (JCM) Work Plan Timeline

More information

JCM Drill Down Report. February 19, 2015

JCM Drill Down Report. February 19, 2015 JCM Drill Down Report February 19, 2015 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill Down Report

More information

ITP Year 20 Assessment Scope

ITP Year 20 Assessment Scope ITP 20 Year Scope 1 ITP Year 20 Assessment Scope January 6, 2010 Approved by TWG January 5, 2010 Endsored by ESWG January 5, 2010 Table of Contents Overview... 4 Objective... 4 Modeling... 5 1. Economic...

More information

MISO-PJM Joint and Common Market Drill Down Report

MISO-PJM Joint and Common Market Drill Down Report MISO-PJM Joint and Common Market Drill Down Report February 28, 2017 The purpose of this document is to provide a brief description of each component listed on the Joint and Common Market (JCM) Work Plan

More information

JCM Drill Down Report. May 27, 2015

JCM Drill Down Report. May 27, 2015 JCM Drill Down Report May 27, 2015 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill Down Report

More information

Inter-regional Planning Update

Inter-regional Planning Update Inter-regional Planning Update Transmission Expansion Advisory Committee October 12, 2017 EIPC Production Cost Database Assembly Trial 4 results under review Database renewal and potential next steps under

More information

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING December 22, 2014 Training Objectives To Provide an Overview of: The Market Efficiency proposal window process The critical modeling inputs

More information

U.P. Transmission Business Briefing Planning Update. November 29, 2007 Marquette, MI Flora Flygt, Director of Planning

U.P. Transmission Business Briefing Planning Update. November 29, 2007 Marquette, MI Flora Flygt, Director of Planning U.P. Transmission Business Briefing Planning Update November 29, 2007 Marquette, MI Flora Flygt, Director of Planning ATC Planning Drivers Load Generation Market Flows Policy Drivers MISO Cost Sharing

More information

CPP Panel Comments. PSERC Summer Workshop July, 2015

CPP Panel Comments. PSERC Summer Workshop July, 2015 CPP Panel Comments PSERC Summer Workshop July, 2015 SPP s Energy Consumption and Capacity Capacity Consumption 2 EPA s Projected 2016-2020 EGU Retirements *Excludes committed retirements prior to 2016

More information

MISO PJM Cross-Border Planning

MISO PJM Cross-Border Planning MISO PJM Cross-Border Planning July 24, 2014 MISO-PJM JCM Planning Coordination Issues 2 At a previous JCM meeting, several issues related to planning coordination were raised: Market Efficiency Planning

More information

MISO/PJM Joint Modeling and Analysis of State Regulatory and Policy Drivers Case Study: Clean Power Plan Analysis

MISO/PJM Joint Modeling and Analysis of State Regulatory and Policy Drivers Case Study: Clean Power Plan Analysis MISO/PJM Joint Modeling and Analysis of State Regulatory and Policy Drivers Case Study: Clean Power Plan Analysis Muhsin Abdur-Rahman Senior Engineer, Emerging Markets Members Committee March 20, 2017

More information

PJM Market Efficiency Window and Mid-Cycle Update

PJM Market Efficiency Window and Mid-Cycle Update PJM Market Efficiency Window and Mid-Cycle Update Nicolae Dumitriu Sr. Lead Engineer, Market Simulation Market Efficiency Process Enhancement Task Force Education Session September 7 th, 2018 Education

More information

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015 EIPC Interconnection-wide Webinar and Stakeholder Discussion November 17, 2015 Webinar Outline Presentation on 2025 Summer Peak (2025S) and 2025 Winter Peak (2025W) Roll-up Case Development Report to be

More information

MTEP18 Transfer Analysis Scope. PSC June 12 th 2018

MTEP18 Transfer Analysis Scope. PSC June 12 th 2018 MTEP18 Transfer Analysis Scope PSC June 12 th 2018 1 Transfer Analysis Study is driven by NERC standard FAC-013-2 Purpose To ensure that Planning Coordinators have a methodology for, and perform an annual

More information

2018 Economic Planning Study Results

2018 Economic Planning Study Results 2018 Economic Planning Study Results Anna Torgerson, Economic Planning October 25, 2018 atcllc.com Introduction Process Overview and Timeline MTEP18 Futures Refresh Study Area Results Next Steps atcllc.com

More information

Illinois State Institute for Regulatory Policy Studies Conference

Illinois State Institute for Regulatory Policy Studies Conference Illinois State Institute for Regulatory Policy Studies Conference Rob Berntsen 10/20/2011 Overview MISO RTOs What We Do FERC Order 1000 MISO s View of FERC Order 1000 MISO s Planning Process MVPs Benefits

More information

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering 2017 ITPNT 2 0 1 7 I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e June 15, 2016 Engineering Revision History Date or Version Number Author Change Description Comments

More information

Joint and Common Market ITEM 4 PSEUDO TIES

Joint and Common Market ITEM 4 PSEUDO TIES Joint and Common Market ITEM 4 PSEUDO TIES Agenda 1. Overview 2. Background 3. PJM Update 4. MISO Update 5. Congestion Overlap Solution 6. Next Steps 2 Overview Purpose Provide a status update on MISO-PJM

More information

ELECTRIC TRANSMISSION 201: Transmission Planning and Benefits of Transmission. Judy Chang Principal

ELECTRIC TRANSMISSION 201: Transmission Planning and Benefits of Transmission. Judy Chang Principal ELECTRIC TRANSMISSION 201: Transmission Planning and Benefits of Transmission Judy Chang Principal 1 Content Transmission Investment Trends Recent Drivers of Transmission Investments Benefits of Transmission

More information

Joint and Common Market ITEM 4 PSEUDO TIES

Joint and Common Market ITEM 4 PSEUDO TIES Joint and Common Market ITEM 4 PSEUDO TIES Agenda 1. Overview 2. Background 3. Common Issues 4. PJM Update 5. MISO Update 6. Next Steps 2 Overview Purpose Provide a status update on MISO-PJM pseudo ties

More information

Joint and Common Market ITEM 4 PSEUDO TIES

Joint and Common Market ITEM 4 PSEUDO TIES Joint and Common Market ITEM 4 PSEUDO TIES Agenda 1. Overview 2. Background 3. Common Issues 4. PJM Update 5. MISO Update 6. Double-Counting 7. Next Steps 2 Overview Purpose Provide a status update on

More information

Year Assessment. Initial Stakeholder Meeting. October 16,2008 Pewaukee MRA Building

Year Assessment. Initial Stakeholder Meeting. October 16,2008 Pewaukee MRA Building 2009 10-Year Assessment Initial Stakeholder Meeting October 16,2008 Pewaukee MRA Building 1 CDAA This presentation has been posted on the OASIS. It does not contain any market sensitive or critical infrastructure

More information

PJM PROMOD Overview. August 1, PJM

PJM PROMOD Overview. August 1, PJM PJM PROMOD Overview August 1, 2017 Market Analysis Software PROMOD PROMOD is a fundamental electric market simulation solution It incorporates future demand, generating unit operating characteristics,

More information

Wind Integration and Grid Reliability Impacts

Wind Integration and Grid Reliability Impacts Wind Integration and Grid Reliability Impacts Charlton I. Clark Technology Manager, Renewable Systems Interconnection Wind and Water Power Program Office of Energy Efficiency and Renewable Energy U. S.

More information

EIPC Roll-Up Powerflow Model

EIPC Roll-Up Powerflow Model EIPC Roll-Up Powerflow Model Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG Meeting November 25, 2013 2013 New York Independent System Operator, Inc. All Rights

More information

Contents. DRAFT Capacity Deliverability Fact Finding Summary Report

Contents. DRAFT Capacity Deliverability Fact Finding Summary Report DRAFT Capacity Deliverability Fact Finding Summary Report Contents 1 Background... 3 2 Overview of findings... 5 2.1 Implement methods for setting limits that respect the physical topology of the system

More information

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING April 17, 2014 Training Objectives To Provide an Overview of: The Market Efficiency proposal window process The critical modeling inputs

More information

INTEGRATED TRANSMISSION PLANNING MANUAL

INTEGRATED TRANSMISSION PLANNING MANUAL INTEGRATED TRANSMISSION PLANNING MANUAL Published on July 20, 2017 Pending FERC approval of Tariff language By SPP staff REVISION HISTORY DATE OR VERSION NUMBER AUTHOR CHANGE DESCRIPTION COMMENTS 10/13/2010

More information

Joint and Common Market PSEUDO TIE UPDATE AUGUST 22, 2017

Joint and Common Market PSEUDO TIE UPDATE AUGUST 22, 2017 Joint and Common Market PSEUDO TIE UPDATE AUGUST 22, 2017 Agenda 1. Overview 2. MISO Update 3. PJM Update 4. JOA Changes Joint Filing 5. Congestion Overlap 6. Next Steps Appendix 2 Overview Purpose Provide

More information

Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component

Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component Last Revised: May 25, 26 Disclaimer: "MIDWEST ISO MAKES NO REPRESENTATIONS OR WARRANTIES OF ANY KIND, EXPRESS

More information

Regional Planning at Midwest ISO. Mr. Clair Moeller Vice President, Transmission Asset Management

Regional Planning at Midwest ISO. Mr. Clair Moeller Vice President, Transmission Asset Management Regional Planning at Midwest ISO Mr. Clair Moeller Vice President, Transmission Asset Management Midwest ISO Planning Objectives Fundamental Goal The development of a comprehensive expansion plan that

More information

MTEP18 Futures. Planning Advisory Committee June 14, 2017

MTEP18 Futures. Planning Advisory Committee June 14, 2017 MTEP18 Futures Planning Advisory Committee June 14, 2017 Overview Objective: Present final MTEP18 Futures and an overview of stakeholder feedback Key Takeaways: Four Futures to be used in MTEP18 to consider

More information

Interregional Coordination Update

Interregional Coordination Update Interregional Coordination Update Phil D Antonio Manager, Interregional Market Operations MC Webinar June 18, 2018 Recent PJM-MISO Joint Stakeholder Meetings MISO and PJM began hosting a series of Joint

More information

MTEP17 MVP Triennial Review

MTEP17 MVP Triennial Review MTEP17 MVP Triennial Review A 2017 review of the public policy, economic, and qualitative benefits of the Multi-Value Project Portfolio September 2017 1 Table of Contents Executive Summary... 4 1. Study

More information

Mid-Continent Independent System Operator (MISO) Overview. INCMA February 15, 2017

Mid-Continent Independent System Operator (MISO) Overview. INCMA February 15, 2017 Mid-Continent Independent System Operator (MISO) Overview INCMA February 15, 2017 1 2 ISO s/rto s manage flows on the transmission system by directing generator usage 3 North American Electric Grid Operators

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission

More information

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5 Methodology and Assumptions 1.1 Overview These sections describe the process we used to perform a network assessment of the ATC transmission system. The description includes study assumptions, methods

More information

NYISO/PJM Market-to-Market Coordination

NYISO/PJM Market-to-Market Coordination NYISO/PJM Market-to-Market Coordination Joint Stakeholders Meeting July 21, 2011 / Rensselaer, NY Agenda Joint Operating Agreement (JOA) Overview Project Timeline & Progress Report Key Concepts Real-Time

More information

Expanding Transmission Capacity: Options and Implications. Jennifer Curran Director Transmission Strategy April 30, 2009

Expanding Transmission Capacity: Options and Implications. Jennifer Curran Director Transmission Strategy April 30, 2009 Expanding Transmission Capacity: Options and Implications Jennifer Curran (jcurran@midwestiso.org) Director Transmission Strategy April 30, 2009 The Transmission Design Challenge General Problem Statement

More information

DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans

DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans ENTERGY GULF STATES LOUISIANA, L.L.C. & ENTERGY LOUISIANA, LLC LPSC DOCKET NO. I-33014 DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans This version

More information

INCREMENTAL AUCTION REVENUE RIGHTS

INCREMENTAL AUCTION REVENUE RIGHTS Joint and Common Market INCREMENTAL AUCTION REVENUE RIGHTS Brian Chmielewski Manager, Market Simulation November 27, 2018 Overview Purpose Provide stakeholders with an update on the MISO-PJM plan for enhanced

More information

MISO s Analysis of EPA s Final Clean Power Plan Study Report

MISO s Analysis of EPA s Final Clean Power Plan Study Report MISO s Analysis of EPA s Final Clean Power Plan Study Report July 2016 MISO Policy & Economic Studies Department i Contents Executive Summary... 4 1 Introduction... 8 2 Near-Term Analysis... 9 2.1 Sensitivity

More information

Year Assessment Preliminary Study Design

Year Assessment Preliminary Study Design 2018 10-Year Assessment Preliminary Study Design October 24, 2017 Stakeholder and Customer Webcast Jeremy Voigt, System Planning atcllc.com Purpose Summarize ATC s project development processes Solicit

More information

Outage Coordination Training MISO Training

Outage Coordination Training MISO Training MISO Last material update: 05/19/2015 Course Content and Disclaimer 2 1 2 3 4 Course Description This course will review MISO's outage study processes and the coordination opportunities with TOs and MPs.

More information

With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development

With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development www.fourcornerswind.org Photo courtesy of Avangrid Renewables, LLC UNDERSTANDING REGIONAL ELECTRICITY

More information

Summary of 2016 MISO State of the Market Report

Summary of 2016 MISO State of the Market Report Summary of 2016 MISO State of the Market Report Presented to: MISO Board Markets Committee David B. Patton, Ph.D. MISO Independent Market Monitor July 20, 2017 Introduction As the Independent Market Monitor

More information

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report Generator Interconnection Affected System Impact Study Plains & Eastern Clean Line Final Report May 19, 2015 MISO 2985 Ames Crossing Eagan Minnesota - 55121 http://www.misoenergy.org Midcontinent Independent

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee EPA's Clean Power Plan PJM Modeling Approach and Deliverables PJM Interconnection December 3, 2015 www.pjm.com Clean Power Plan Analysis Overview What is it? US

More information

Industry Perspectives on FERC Standard Market Design

Industry Perspectives on FERC Standard Market Design Industry Perspectives on FERC Standard Market Design By Dr. Roberto F. Paliza Midwest Independent Transmission System Operator, Inc. IEEE Summer Meeting July 23, 2002 Chicago, IL Overview MISO Markets

More information

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017 Evolution of the Grid in MISO Region Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017 1 MISO s mission is to ensure reliable delivery of low-cost energy through efficient,

More information

MISO Energy Storage Study DRAFT Scope

MISO Energy Storage Study DRAFT Scope MISO Energy Storage Study DRAFT Scope MISO Energy Storage Study DRAFT Scope July 19, 2011 MISO Page 1 Table of Contents 1. Introduction... 3 2. Study Objectives... 3 3. Study Drivers... 4 4. Study Description...

More information

Methodology PLG-METH-0002-V1

Methodology PLG-METH-0002-V1 Methodology Department: Document No: System Planning and Strategic Projects PLG-METH-0002-V1 Title: Transmission Planning Assessment Practices Issue Date: September 27, 2012 Previous Date: Nov. 18, 2011

More information

Broader Regional Markets

Broader Regional Markets Attachment B Broader Regional Markets, Long-Term Solutions to Lake Erie Loop Flow Slide Presentation from the December 15, 2009 Technical Conference Held in Carmel, Indiana LAKE SUPERIOR LAKE SUPERIOR

More information

Eastern Wind Integration and Transmission Study

Eastern Wind Integration and Transmission Study Eastern Wind Integration and Transmission Study NPCC Governmental/Regulatory Affairs Advisory Group February 23rd, 2010 Dave Corbus National Renewable Energy Lab 1 What is Needed to Integrate 20% Wind

More information

PJM-MISO Stakeholder JCM Briefing June 30, 2005 Joint and Common Market Portal

PJM-MISO Stakeholder JCM Briefing June 30, 2005 Joint and Common Market Portal PJM-MISO Stakeholder Briefing June 30, 2005 Joint and Common Market Portal Version 4.0 6/27/05 Joint and Common Market Four Phases Phase 1: Coordination of operations to ensure proper congestion management

More information

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Effective Date: September 11, 2017 Revision History Date Version Description June 6, 1998 0.0 Initial LGEE document

More information

GRID MODERNIZATION INITIATIVE PEER REVIEW Interconnections Seam Study

GRID MODERNIZATION INITIATIVE PEER REVIEW Interconnections Seam Study GRID MODERNIZATION INITIATIVE PEER REVIEW Interconnections Seam Study 1.3.33 AARON BLOOM April 18-20, 2017 Sheraton Pentagon City Arlington, VA Planning and Design Tools 4/5/2017 1 1.3.33 Project Description

More information

AEP Transmission Local Planning Assumptions, Models, and Criteria

AEP Transmission Local Planning Assumptions, Models, and Criteria AEP Transmission Local Planning Assumptions, Models, and Criteria PJM Sub-Regional RTEP Western Meeting December 5, 2018 Introduction to AEP AEP is among the largest electric utilities in the United States

More information

Eastern Wind Integration and

Eastern Wind Integration and Eastern Wind Integration and Transmission Study Overview NCSL Transmission Policy Institute Denver, CO June 17-18, 2010 Dave Corbus National Renewable Energy Laboratory NREL is a national laboratory of

More information

2010 RTO Metrics Report: NESCOE Data Summary

2010 RTO Metrics Report: NESCOE Data Summary New England States Committee on Electricity NESCOE Phone: 23-38-1477 E-Mail: AllisonSmith@nescoe.com Web: www.nescoe.com 21 RTO Metrics Report: NESCOE Data Summary Allison Smith ABSTRACT Summary of comparative

More information

Renewable Integration Impact Assessment (RIIA)

Renewable Integration Impact Assessment (RIIA) Renewable Integration Impact Assessment (RIIA) Overview Current progress and initial findings Next steps Planning Advisory Committee Jordan Bakke April 18, 18 Updated June 18, 18 Renewable Integration

More information

EPA s Clean Power Plan Proposal Review of PJM Analyses Preliminary Results

EPA s Clean Power Plan Proposal Review of PJM Analyses Preliminary Results EPA s Clean Power Plan Proposal Review of PJM Analyses Preliminary Results Paul Sotkiewicz Chief Economist Muhsin Abdur-Rahman Senior Engineer, Market Simulation Members Committee Webinar November 17,

More information

Review of Data Change Management Processes for RTCA and Planning Models (Recommendation 16) March, 2017

Review of Data Change Management Processes for RTCA and Planning Models (Recommendation 16) March, 2017 Review of Data Change Management Processes for RTCA and Planning Models (Recommendation 16) March, 2017 Background In April 2012, the Federal Energy Regulatory Commission (FERC) and the North American

More information

FTR Modeling Enhancements for Future Transmission Expansions

FTR Modeling Enhancements for Future Transmission Expansions FTR Modeling Enhancements for Future Transmission Expansions Brian Chmielewski Sr. Analyst, Market Simulation FTRMPS October 20, 2017 Problem Statement Recap Current Long-Term FTR modeling practices do

More information

Independent Transmission Organization. Stakeholder s Meeting December 2006

Independent Transmission Organization. Stakeholder s Meeting December 2006 SPP Presentation Independent Transmission Organization Stakeholder s Meeting December 2006 2 Introduction Participants Agenda Facilities 3 ITO Overview EON US (LG&E/KU) Overview EON US Tariff vs MISO Tariff

More information

PJM Wind Integration Initiatives

PJM Wind Integration Initiatives PJM Wind Integration Initiatives West Virginia Wind Forum Davis, WV September 25, 2012 Ken Schuyler Renewable Services PJM Interconnection 1 26% of generation in Eastern Interconnection 28% of load in

More information

Eastern Interconnection Wind Integration & Transmission Study

Eastern Interconnection Wind Integration & Transmission Study Eastern Interconnection Wind Integration & Transmission Study Project Overview Prepared by: Robert Zavadil Enernex Presented by: Charlie Smith UWIG What is Needed to Integrate 20% Wind in the Eastern Interconnect?

More information

Update on Transmission Planning for Wind Power in the Upper Midwest

Update on Transmission Planning for Wind Power in the Upper Midwest Update on Transmission Planning for Wind Power in the Upper Midwest The Road to Market Quarterly Meeting September 15, 2005 Regional Studies that include Significant Amounts of New Wind Power CapX 2020

More information

ENTERGY FACILITY CONNECTION REQUIREMENTS March 2007

ENTERGY FACILITY CONNECTION REQUIREMENTS March 2007 ENTERGY FACILITY CONNECTION REQUIREMENTS March 2007 Rev. No. Revision Description Date Reviewed By Approved By 0 Initial Issue 3/1/2007 - TL 1 Cover Page Updated 10/24/2008 - BKW 2 Revised Format, Updated

More information

PJM/MISO Joint and Common Market Stakeholder Meeting. June 2, 2005 Wilmington, DE

PJM/MISO Joint and Common Market Stakeholder Meeting. June 2, 2005 Wilmington, DE PJM/MISO Joint and Common Market Stakeholder Meeting June 2, 25 Wilmington, DE Agenda Morning Meeting Objectives Review of March 3, 25 FERC Order Market-to-Market Coordination Update Stakeholder Process

More information

Mountain West Transmission Group Frequently Asked Questions Updated through September of 2017

Mountain West Transmission Group Frequently Asked Questions Updated through September of 2017 Mountain West Transmission Group Frequently Asked Questions Updated through September of 2017 This FAQ document was first provided in 2016 and has periodically been updated since that time. The document

More information

PJM s Clean Power Plan Modeling Reference Model and Sensitivities

PJM s Clean Power Plan Modeling Reference Model and Sensitivities PJM s Clean Power Plan Modeling Reference Model and Sensitivities Muhsin K. Abdur-Rahman Senior Market Strategist MC Webinar April 25, 2016 What it is Reference Model Robust modeling representation of

More information

Congestion Assessment and Resource Integration Studies. A Report by the New York Independent System Operator

Congestion Assessment and Resource Integration Studies. A Report by the New York Independent System Operator Congestion Assessment and Resource Integration Studies A Report by the New York Independent System Operator April 2018 2017 Congestion Assessment and Resource Integration Study Comprehensive System Planning

More information

Joint and Common Market II. MISO/PJM FTR COORDINATION UPDATE

Joint and Common Market II. MISO/PJM FTR COORDINATION UPDATE Joint and Common Market II. MISO/PJM FTR COORDINATION UPDATE 1 Background and Status At the September 20 th JCM, MISO and PJM discussed the approach for FTR coordination Outage Coordination Both PJM and

More information

TSR Modeling in Reliability Planning. Planning Subcommittee October 17, 2017

TSR Modeling in Reliability Planning. Planning Subcommittee October 17, 2017 TSR Modeling in Reliability Planning Planning Subcommittee October 17, 2017 1 Objective TSR Modeling in MISO Series Base Models TSR Modeling in Reliability Planning Studies 2 TSR Modeling in MISO Series

More information

Coordination with PJM

Coordination with PJM Market-to-Market Coordination with PJM Mike DeSocio Market Product Specialist New York Independent System Operator MIWG October 27, 2011 Rensselaer, New York Agenda M2M and NYISO Markets Examples Tariff

More information

Methodology PLG-METH-0002-V4

Methodology PLG-METH-0002-V4 Methodology Department: Document No: System Planning and Strategic Projects PLG-METH-0002-V4 Title: Transmission Planning Assessment Practices Issue Date: August 3, 2015 Previous Date: December 10, 2014

More information

NYISO s Integrating Public Policy Project

NYISO s Integrating Public Policy Project NYISO s Integrating Public Policy Project Phase 2: Study Description and Assumption Review Dr. Nicole Bouchez & Mike Swider MIWG Krey Blvd, Rensselaer February 16, 2017 2000-2017 New York Independent System

More information

2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool

2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool 2016 Probabilistic Assessment December 5, 2016 Southwest Power Pool Table of Contents 1. Summary...2 a. SPP Planning Coordinator Footprint...2 b. Seasonal Capacity Totals... Error! Bookmark not defined.

More information

PJM Manual 14B: PJM Region Transmission Planning Process Revision: 40 Effective Date: October 26, Prepared by Transmission Planning Department

PJM Manual 14B: PJM Region Transmission Planning Process Revision: 40 Effective Date: October 26, Prepared by Transmission Planning Department PJM Manual 14B: PJM Region Transmission Planning Process Revision: 40 Effective Date: October 26, 2017 Prepared by Transmission Planning Department PJM 2018 Table of Contents Table of Contents Table of

More information

Renewable Integration Impact Assessment Finding integration inflection points of increasing renewable energy. NCEP Webinar Sept.

Renewable Integration Impact Assessment Finding integration inflection points of increasing renewable energy. NCEP Webinar Sept. Renewable Integration Impact Assessment Finding integration inflection points of increasing renewable energy NCEP Webinar Sept. 13 th, 18 Cumulative Renewable Additions (GW) Renewable energy is growing;

More information

Solar Integration into the PJM Grid

Solar Integration into the PJM Grid Solar Integration into the PJM Grid Ken Schuyler Manager, Renewable Services PJM Interconnection September 14, 2017 Integrating Solar in PJM PJM Background PJM Initiatives to Address Impacts Analysis of

More information

Freeze Date Straw Proposal Draft 5/18/2017

Freeze Date Straw Proposal Draft 5/18/2017 Freeze Date Straw Proposal Draft 5/18/2017 0 Table of Contents 1.0 Introduction... 2 2.0 Executive Summary... 2 3.0 Existing Process Background... 2 4.0 Design Components... 5 4.1.0 4.2.0 4.3.0 4.4.0 4.5.0

More information

MISO/PJM Joint Modeling Case Study: Clean Power Analysis

MISO/PJM Joint Modeling Case Study: Clean Power Analysis MISO/PJM Joint Modeling Case Study: Clean Power Analysis MISO PJM Interconnection March 10, 2017 This page is intentionally left blank. 2 P a g e Executive Summary... 5 Study focus and key observations...

More information

Nebraska Statewide Wind Integration Study: Executive Summary April 2008 January 2010

Nebraska Statewide Wind Integration Study: Executive Summary April 2008 January 2010 University of Nebraska - Lincoln DigitalCommons@University of Nebraska - Lincoln US Department of Energy Publications U.S. Department of Energy 2010 Nebraska Statewide Wind Integration Study: Executive

More information

Market Impact Assessment: Preliminary DAM Results Overview

Market Impact Assessment: Preliminary DAM Results Overview Market Impact Assessment: Preliminary DAM Results Overview Nicole Bouchez, Ph.D. Michael Swider Market Issues Working Group April 24, 2017, Rensselaer NY Agenda Overview of the Integrating Public Policy

More information

Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING June 16, 2011 NET CONFERENCE AGENDA 1:30 3:00 PM

Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING June 16, 2011 NET CONFERENCE AGENDA 1:30 3:00 PM Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING June 16, 2011 NET CONFERENCE AGENDA 1:30 3:00 PM 1. Administrative A. Introductions... All B. SPP Antitrust Guidelines...

More information

May 22, :30 a.m.-12:00 p.m., Eastern Standard Time. PJM 2013

May 22, :30 a.m.-12:00 p.m., Eastern Standard Time.   PJM 2013 Regional Planning Process Task Force Teleconference Toll-free call-in number 866-398-2885 Passcode: 934672 WebEx Link:https://pjm.webex.com Password: Password: rpp0522pjm May 22, 2013 9:30 a.m.-12:00 p.m.,

More information

MISO-PJM JOA Biennial Review

MISO-PJM JOA Biennial Review MISO-PJM JOA Biennial Review Midcontinent ISO PJM Interconnection 1/20/2016 1. Background On January 4, 2011, Midwest 1 Independent Transmission System Operator, Inc. (MISO) and PJM Interconnection, LLC

More information

CARIS Procedure Development and Simulation Model Evaluation

CARIS Procedure Development and Simulation Model Evaluation CARIS Procedure Development and Simulation Model Evaluation Bill Lamanna Manager Long Term Planning New York Independent System Operator ESPWG Meeting NYISO September 16, 2009 Draft 1 for discussion only

More information

Capacity Deliverability. May 27, 2015 MISO-PJM JCM

Capacity Deliverability. May 27, 2015 MISO-PJM JCM Capacity Deliverability May 27, 2015 MISO-PJM JCM Key Takeaways and Objective Capacity deliverability seeks to eliminate barriers for capacity transactions across the seam MISO is evaluating options to

More information

Generation Technology Assessment & Production Cost Analysis

Generation Technology Assessment & Production Cost Analysis SPO Planning Analysis Generation Technology Assessment & Production Cost Analysis EAI Stakeholder Meeting July 31, 212 Technology Life Cycle Technology Deployment Over Time Conceptual Research & Development

More information

MISO-PJM Interface Pricing Post Implementation Metrics and Criteria

MISO-PJM Interface Pricing Post Implementation Metrics and Criteria MISO-PJM Interface Pricing Post Implementation Metrics and Criteria Contents 1 Introduction... 2 2 Real-Time Market Interchange Price Signal Effectiveness Metrics... 2 2.1 Post Implementation Pricing Monitoring

More information

2015 Electric Resource Plan 3rd Public Meeting

2015 Electric Resource Plan 3rd Public Meeting 2015 Electric Resource Plan 3rd Public Meeting August 6, 2015 1 Introduction and Housekeeping WELCOME to Tri-State Keep to schedule Cell phones on silent Location of facilities Webcast Use microphone for

More information