2 Transport development between Helsinki-Tallinn twin cities Feasibility study of the Helsinki-Tallinn fixed link January 2018 Kari Ruohonen, project director Malla Paajanen, chief adviser

3 FinEst Link

4 Over 8 million passengers /year and growing. The key commuting corridors of the Helsinki- Uusimaa region. Tallinn-Helsinki appr commuters. 4

5 TEN-T in the macroregion Growing role of the Arctic region Suggested extension of core network corridors around the Gulf of Bothnia Scandinavian Mediterranean core network corridor North Sea Baltic core network corridor and Rail Baltica by 2026 Helsinki Tallinn railway tunnel: FinEst Link feasibility study is on-going in

6 The FinEst Link project Feasibility study of the Helsinki-Tallinn fixed link. Comparative Impact Analysis: Social and economic feasibility Regional and spatial development, demographic considerations Cost Benefit Analysis: 1) transport volumes will brow but investments only on HKI-TLN port connections, 2) building of a tunnel. Technical concept and economic assessments of tunnel solution: Train operation concept, locations of terminals, technical planning, detailed investment costs, risk evaluation assessment of future development in transport technologies, financing and governance models in realizing a mega project. A simple environmental impact assessment (not full EIA). Benchmarking, policy frameworks and stakeholder dialogue Benchmarking with fixed link projects in the EU (Öresund, St.Gotthard, Brenner, Fehmarnbelt, Channel Tunnel) Roundtable discussions and stakeholder events 6

7 Volume estimations 2050 Ferry connection 0+ Passenger now 9 and 2050 about 14 milj/a Freight now 3,8 milj.t/year 2050 about 7 milj.t/a Tunnel connection With ferries Passenger 2050 about 10 milj/a Freight 2050 about 4 milj.t/a With trains Passenger 2050 about 13 milj/a Freight 2050 about 4 milj.t/a

8 0+ Description The Basic 0+ option is based on current port terminals. However, three other alternatives have been recognised: 0+ Cargo to Vuosaari 0+ All Ferry Traffic to Vuosaari 0+ Other Ports There is a cargo vessel transporting cargo between Helsinki and Tallinn. This is expecting to continue, but all cargo is unlikely to be shifted to Vuosaari because of synergies with passenger traffic. Moving all ferry traffic to Vuosaari is possible but not considered realistic at the moment. Other ports (especially Hanko an Paldiski ) support traffic but can t replace Helsinki and Tallinn. Train ferry traffic has been ceased generally in the market. Train ferry is not considered a feasible choice to compare in this study.

9 Terminal and Infrastructure Capacity in 0+ New passenger terminals have been built in Helsinki and Tallinn. Current terminal capacity is considered adequate. All ferry terminals are in the city centres, which causes some challenges.

10 Challenges in 0+ Vehicle traffic trough city centres is not an optimal choice and it is contrary to general city planning principles. Possible city boulevards in Helsinki will have an impact on traffic to and from the ferry terminals in Western Harbour, Southern Harbour and Katajanokka. Impacts are related on actual planning solutions and requires more detailed analyses. Impacts caused by the possible centre tunnel requires more detailed analyses

11 Terminal and Infrastructure Investments in 0+ Traffic investments in Helsinki Tyynenmerenkatu 14 M West Harbour Traffic improvements 5 M These investments will be done regardless of the possible Fixed Link. Additional: West Harbour Terminal 1 renovation or rebuilding planned. Mitigation measures if city boulevards proposed in the new City Plan will be established. Traffic investments in Tallinn Masterplan 2030 competition on August 2017 was won by Zaha Hadid Architects. Discussion to move ferry traffic from the Old City Harbour to Muuga; in order to ease congestion issues. Reidi road improvement plan (28,5 M ) is expected to help with congestion. Plans to take tramline or light rail to the Old City Harbour in near future.

12 Geology Tunnel will be situated mostly in crystalline Precambrian bedrock of gneisses and granitoids Good rock quality, high intact rock strength Approaching the Estonian coast, the crystalline bedrock dives gently under younger, weaker sedimentary rocks Ediacaran sandstone (soft, hydraulically conductive aquifer) Blue clay (low water permeability, well suited for tunneling) Quaternary deposits (loose silt, sand and gravel)

13 FinEst Link Artificial islands

14 FinEst Link - Finland

15 Estonia Alignment & Facilities FinEst surface alignment follows the rail corridor presented in Harju County Plan FinEst tunnel portal at Iru junction (can be about 5 km to north) Freight terminal (including car and truck terminal) in same location than possible Rail Baltic freight terminal

16 D) North of Airport ( >22 km from Pasila) A new rail to Hanko- Hyvinkää, 1520 Freight terminals and depots Cross section: Helsinki Pasila Airport Freight terminals and depots Finest Link Airport Link

17 Safety tunnel concept Service tunnel is located below the running tunnels Cross passages for self-rescue purpose every 450m Max. gradient 6% (wheelchair-accessible) Intermediate cross passages for maintenance purpose Not accessible to unauthorized third parties Distance to be defined in respect to maintenance concept Maintenance cross passage Emergency cross passage

18 Artificial islands Water depth approx. 15 m & 20 m Tunnel depth 150m and 215 m Different geological conditions (e.g. depth of crystalline basement)

19 Construction time schedule Assumptions Working hours: 24/7 Working days per month: 28 Working days per year: 336 Advance rates Shield TBM: 15 m per day Mixshield/EPB: 10 m per day Learning curve at the beginning of each tunnel drive is taken into account

20 Key impacts in SEA Tunnel will have positive impact on sea ecosystems due to less pressure on coastal ecosystems presumably commuter trains will replace to some extent fast ferries, that cause waves Building and use of artificial island will have likely negative impacts on marine habitats. Tunnel option will have less traffic impacts in urban system (cargo) indirect and social impacts are still largely positive but need supportive strategic programs to maximise positive effect. Negative effects will be manifested due to considerable impacts to the climate during construction phase.

21 Capacity for passenger and cargo traffic (dim.direction) 1435 mm Time Trains for Maintenance dim.direc.tot Passenger Trains 200/h Slots for 160km/h rolling stock 0 0 Car shuttle Truckshuttle Slots for 120km/h rolling stock 8 8 Cargo With a running speed of 160 km/h for shuttles and 120 km/h for conventional cargo trains, the distribution of trains (train table above) is functional and there is enough capacity. During maintenance hours no need for other train operations Dim direction 40 Passenger trains/day 400m/200km/h 11 Car shuttle trains/day 700 m/160 km/h 17 Truck shuttle trains/day 750 m/160km/h 3 Cargo trains/day 750m/120 km/h

22 Passenger demand just before opening of operating tunnels and current demands on projects under construction or in the project phase Passenger demand just before opening of operating tunnels and current demands on projects under construction or in the project phase

23 Freight demand just before opening of operating tunnels and current demands on projects under construction or in the project phase

24 Economic impacts of FinEstLink Tunnel versus 06 ferry connection Standard Cost- Benefit Analysis (CBA) Analysis of Wider Economic Impacts (WEI) Source: Laakso & Kostiainen & Metsäranta, 2016 (Originally Venables 2016)

25 Assessment levels Land use benefits give added value Wider impact assessments clarify the economic benefits that FEL makes possible The CBA sensitivity analysis provides more information on the uncertainties of the assessment Standard CBA forms a basement for the assessment

26 Open stage Global Challenge: alternative technologies and implementation models. Solution(s) that show practical feasibility will be included in FinEst link project report. Solutions for optimising present system of Tallinn-Helsinki transport-connection. Cooperation with Prototron (EE) and possible financing by Tekes (Finland) for relevant project Best idea euro grant

27 New technologies concepts Hyperloop One Capsules with magnetic levitation in a low pressure tube Finest Bay Area Privat financing, real estate devolopment, and 2 fii 17,4 m tunnels, 1435 mm/1524 mm gauges OÜ Ankurtunnel Underwater concrete anchored tunnel SwissRapide AG Magnetic levitation (Maglev) trains AL Engineering OÜ Inductive linear motors and magnetic levitation capsules Alkutieto Oy Both gauges in same track. Freight terminals and depots in Tallinn

28

29 Thank you! Final Conference in Tallinn

Transport development between Helsinki-Tallinn twin cities

Transport development between Helsinki-Tallinn twin cities Transport development between Helsinki-Tallinn twin cities Feasibility study of the Helsinki-Tallinn fixed link November 2017 Kari Ruohonen, project director Malla Paajanen, chief adviser Strategic standpoints

More information

Study Results of the FinEst link project Impact on Rail Baltica. April 10, 2018 Kari Ruohonen, project director

Study Results of the FinEst link project Impact on Rail Baltica. April 10, 2018 Kari Ruohonen, project director Study Results of the FinEst link project Impact on Rail Baltica April 10, 2018 Kari Ruohonen, project director TEN-T in the macroregion Growing role of the Arctic region Suggested extension of core network

More information

Helsinki-Tallinn Transport Link Feasibility Study of a Railway Tunnel February 2018

Helsinki-Tallinn Transport Link Feasibility Study of a Railway Tunnel February 2018 Helsinki-Tallinn Transport Link Feasibility Study of a Railway Tunnel February 2018 Helsinki-Tallinn Transport Link Feasibility Study of a Railway Tunnel 1 FREIGHT TERMINAL AND DEPOTS Helsinki Helsinki-Vantaa

More information

FinEst Link Feasibility Study Sub-report Alignment alternatives 12/2017

FinEst Link Feasibility Study Sub-report Alignment alternatives 12/2017 FinEst Link Feasibility Study Sub-report Alignment alternatives 12/2017 1 Table of contents 1. Horizontal alignment of FinEst Link... 3 2. Vertical alignment of FinEst Link... 8 3. Horizontal alignment

More information

ORAL PAPER PROCEEDINGS

ORAL PAPER PROCEEDINGS ITA - AITES WORLD TUNNEL CONGRESS 21-26 April 2018 Dubai International Convention & Exhibition Centre, UAE ORAL PAPER PROCEEDINGS Ultra-long subsea tunnel under the Gulf of Finland ABSTRACT Klaus Wachter

More information

Helsinki-Tallinn Transport Link. Feasibility Study Final report

Helsinki-Tallinn Transport Link. Feasibility Study Final report Helsinki-Tallinn Transport Link Feasibility Study Final report Table of Contents 1. Executive Summary...6 1.1. Technical concept...6 1.2. Cost estimation... 7 1.3. Estimation of demand... 7 1.4. Cost-benefit

More information

The Minimum Viable Tunnel between Helsinki and Tallinn

The Minimum Viable Tunnel between Helsinki and Tallinn 1 The Minimum Viable Tunnel between Helsinki and Tallinn Tallinn Alkutieto Oy Antero Alku, Esa Nurkka The Minimum Viable Tunnel 2 A tunnel with enough features to enable feasible operation and optimize

More information

FinEst Bay Area Development The Tallinn Tunnel Project. Financial indicators

FinEst Bay Area Development The Tallinn Tunnel Project. Financial indicators FinEst Bay Area Development The Tallinn Tunnel Project Financial indicators Passenger traffic volumes Current Assumptions 2030 Helsinki Helsinki- Airport 20 M Tallinn Airport 70 M Espoo 125 M Helsinki

More information

FinEst Link Feasibility Study Sub-report Tunnel solution 12/2017

FinEst Link Feasibility Study Sub-report Tunnel solution 12/2017 FinEst Link Feasibility Study Sub-report Tunnel solution 12/2017 1 Table of contents 1. Geological conditions and geotechnical interpretation... 4 2. Fixed Link Tunnel Solution... 10 2.1. Tunnel concept...

More information

Tenders and procurement of Rail Baltica. Indrek Orav 2015

Tenders and procurement of Rail Baltica. Indrek Orav 2015 Tenders and procurement of Rail Baltica Indrek Orav 2015 TEN-T priority project nr 27 TEN-T Core Network Agreement among three Baltic States PM statement signed on November, 10th 2011: Agreed that the

More information

Comparative Impact Analysis Sub-Report

Comparative Impact Analysis Sub-Report Comparative Impact Analysis Sub-Report 1 Table of contents Forewords... 4 1. Ferry Traffic Solution 0+... 5 1.1. Past Development... 5 1.2. Recent Traffic Patterns... 5 1.2.1. Vessel Traffic... 5 1.3.

More information

PROJECT: UNDERWATER CONCRETE, ANCHORED TO SEABED, RAILWAY TUNNEL BETWEEN HELSINKI AND TALLINN

PROJECT: UNDERWATER CONCRETE, ANCHORED TO SEABED, RAILWAY TUNNEL BETWEEN HELSINKI AND TALLINN PROJECT: UNDERWATER CONCRETE, ANCHORED TO SEABED, RAILWAY TUNNEL BETWEEN HELSINKI AND TALLINN A. THE IDEA To build for transport of goods and people between Helsinki and Tallinn a two way underwater, anchored

More information

APPLICATION FORM PART D

APPLICATION FORM PART D Connecting Europe Facility 2014-2020 TRANSPORT CALLS FOR PROPOSALS 2014 APPLICATION FORM PART D Technical and Financial Information Title of the proposed action The Planning of the Core Network Railway

More information

Rail Baltica Growth Corridor Russia T N O R C R D O P R O. Warsaw. Berlin. St. Petersburg. Riga. Tallinn. Kaunas.

Rail Baltica Growth Corridor Russia T N O R C R D O P R O. Warsaw. Berlin. St. Petersburg. Riga. Tallinn. Kaunas. 9.5.2012 Rail Baltica Growth Corridor Russia CT E R I D RT O P NS TRA DOR TO RI R O AL C R T N CE PE O R EU St. Petersburg Helsinki Tallinn Riga Kaunas Warsaw Berlin RBGC Russia PROJECT OBJECTIVES» To

More information

WHAT IS RAIL BALTICA?

WHAT IS RAIL BALTICA? Future direct WHAT IS RAIL BALTICA? Rail Baltica Project of the Century Rail Baltica is a greenfield rail transport infrastructure project aiming to integrate the Baltic States in the European rail network.

More information

Rail Baltic in Harju County

Rail Baltic in Harju County Rail Baltic in Harju County Kaarel Kose Harju County Government 4th of April 2017 www.railbaltic.info Rail Baltic Rail Baltic is an international rail connection that will connect Estonia with Central

More information

FinEst Link New Technologies Challenge

FinEst Link New Technologies Challenge FinEst Link New Technologies Challenge Antero Alku, Esa Nurkka Alkutieto Oy, 8.1.2018, päivitetty versio Table of contents 1. Executive summary 2. Goal 3. Service concept of the tunnel Traffic system level

More information

Rail Baltica Global Project Cost-Benefit Analysis. 24 April 2017

Rail Baltica Global Project Cost-Benefit Analysis. 24 April 2017 Rail Baltica Global Project Cost-Benefit Analysis 24 April 2017 AGENDA 1. What answers does the CBA provide and how they were prepared? 2. What is Rail Baltica? 3. What benefits will Rail Baltica bring?

More information

Reinforcing Eastern Finland-Estonia Transport Corridor (REFEC)

Reinforcing Eastern Finland-Estonia Transport Corridor (REFEC) Reinforcing Eastern Finland-Estonia Transport Corridor (REFEC) Programme Priority: P3 Well-connected region Programme Specific Objective: 3.1. Improved transport flows of people and goods Sub-programme:

More information

Information on Rail Baltica Planned Procurements for the Global Project (indicative)

Information on Rail Baltica Planned Procurements for the Global Project (indicative) Information on Planned Procurements for the Global Project (indicative) 21.04.2017 No Procurement Title (English) Procurement Title (original language) Short Description of the Procurement Subject (in

More information

Supply and Demand Analysis

Supply and Demand Analysis Technical, Socio-economic and Supply/Demand study regarding the transport of the FERRMED Great Rail Network (Scandinavia-Rhine- Rhône-Western Mediterranean) Supply and Demand Analysis Presented by Daniele

More information

Full-text paper MAGLEV REQUIREMENTS FOR TUNNELS

Full-text paper MAGLEV REQUIREMENTS FOR TUNNELS Full-text paper MAGLEV REQUIREMENTS FOR TUNNELS (Emergency Concepts, Security Exits, Cross-section Design, Guideway Types in the tunnel, Sonic-Boom-Effects, Shocks) (*) Author: Dipl.-Ing. Andreas WERTH,

More information

T H E M O S T E A S T E R N P O R T O F T H E E U R O P E A N U N I O N

T H E M O S T E A S T E R N P O R T O F T H E E U R O P E A N U N I O N T H E M O S T E A S T E R N P O R T O F T H E E U R O P E A N U N I O N Global: 175 km to St. Petersburg, Russia 875 km to Moscow, Russia 1230 km to Kiev, Ukraine 100 km to Kotka/ Hamina, Finland 185 km

More information

Helsinki Airport Rail Corridor. Spatial Development Potential, Accessibility Benefits and International Connectivity

Helsinki Airport Rail Corridor. Spatial Development Potential, Accessibility Benefits and International Connectivity Helsinki Airport Rail Corridor Spatial Development Potential, Accessibility Benefits and International Connectivity Final Report January 2018 2 Helsingin kaupunki Contents Summary...5 OUTLINE OF REPORT...

More information

Rail Baltica Global Project Cost-Benefit Analysis Executive summary 24 April 2017

Rail Baltica Global Project Cost-Benefit Analysis Executive summary 24 April 2017 Rail Baltica Global Project Cost-Benefit Analysis Executive summary 24 April 2017 Contents 1. Introduction... 3 2. Background... 4 3. Economic and Sectoral Context... 7 4. Traffic Forecasts... 8 4.1 Overall

More information

LNG fuel distribution strategy for the BSR v5

LNG fuel distribution strategy for the BSR v5 LNG fuel distribution strategy for the BSR v5 Introduction The land-based and the maritime LNG market will be closely connected in the future. With stricter emission restrictions, more ships will be built

More information

INEA. Innovation and Networks Executive Agency. Making implementation happen. Motorways of the Sea Priority funding options

INEA. Innovation and Networks Executive Agency. Making implementation happen. Motorways of the Sea Priority funding options INEA Innovation and Networks Executive Agency Making implementation happen Motorways of the Sea Priority funding options INEA in short European Commission's executive agency Implementing EU funding programmes

More information

Feasibility study on Rail Baltica railways

Feasibility study on Rail Baltica railways European Commission Directorate-General Regional Policy Feasibility study on Rail Baltica railways Main conclusions and recommendations January 2007 The study has been carried out by a consortium led by

More information

Illawarra Business Chamber/Illawarra First. Submission on NSW Draft Freight and Ports Plan

Illawarra Business Chamber/Illawarra First. Submission on NSW Draft Freight and Ports Plan Illawarra Business Chamber/Illawarra First Submission on NSW Draft Freight and Ports Plan Illawarra Business Chamber A division of the NSW Business Chamber Level 1, 87-89 Market Street WOLLONGONG NSW 2500

More information

FINLAND: North Sea-Baltic Corridor Scandinavian-Mediterranean Corridor What are the key benefits? The new infrastructure policy in Europe

FINLAND: North Sea-Baltic Corridor Scandinavian-Mediterranean Corridor What are the key benefits? The new infrastructure policy in Europe FINLAND: Finland has 2 Core Network Corridors crossing its country: The North Sea-Baltic Corridor stretches from the North Sea ports Antwerp, Rotterdam, Amsterdam, Bremen and Hamburg through Poland to

More information

A FEASIBILITY STUDY FOR A STANDARD GAUGE SEPARATE RAILWAY LINE IN ESTONIA, LATVIA AND LITHUANIA. Arnis Kakulis AECOM, Director, Baltic Region

A FEASIBILITY STUDY FOR A STANDARD GAUGE SEPARATE RAILWAY LINE IN ESTONIA, LATVIA AND LITHUANIA. Arnis Kakulis AECOM, Director, Baltic Region A FEASIBILITY STUDY FOR A STANDARD GAUGE SEPARATE RAILWAY LINE IN ESTONIA, LATVIA AND LITHUANIA Arnis Kakulis AECOM, Director, Baltic Region 24 March 2011 Objective of the Feasibility Study The main objective

More information

The Single Window. Solution: X Road. for Logistics. Valdo Kalm Chairman of the Management Board Port of Tallinn

The Single Window. Solution: X Road. for Logistics. Valdo Kalm Chairman of the Management Board Port of Tallinn The Single Window Solution: X Road for Logistics Valdo Kalm Chairman of the Management Board Port of Tallinn Maritime Industry Dynamics MEGATRENDS Larger Vessels Security of borders and assets Safety of

More information

MOBILITY MEETS BIG DATA

MOBILITY MEETS BIG DATA MOBILITY MEETS BIG DATA www.transformingtransport.eu The future of transport for Europe Europe s ever-growing mobility and logistics sector currently represents 15 % of GDP and employs 11.2 million people

More information

FAQ: The New East Coast Line

FAQ: The New East Coast Line FAQ: The New East Coast Line Why is a railway in northern Sweden essential for Europe? Sweden is a vast country with enormous natural resources. Our industry has extremely high standards for environmental

More information

Current arrangements and implementation of the reform. Ms Laura Eiro, Director of Markets Unit

Current arrangements and implementation of the reform. Ms Laura Eiro, Director of Markets Unit Current arrangements and implementation of the reform Ms Laura Eiro, Director of Markets Unit 8 Current passenger rail transport arrangements in Finland Competent authorities the Ministry of Transport

More information

City of Greater Geelong. Response to Infrastructure Victoria s Second Container Port Advice evidence base discussion paper

City of Greater Geelong. Response to Infrastructure Victoria s Second Container Port Advice evidence base discussion paper City of Greater Geelong Response to Infrastructure Victoria s Second Container Port Advice evidence base discussion paper March 2017 Tim Ellis Manager Enterprise Geelong and Events City of Greater Geelong

More information

SEMMERING BASE TUNNEL LOGISTIC CHALLENGES

SEMMERING BASE TUNNEL LOGISTIC CHALLENGES SEMMERING BASE TUNNEL LOGISTIC CHALLENGES Dipl.-Ing. Michael Proprenter ic consulenten ZT GmbH Vienna, Austria Mail: m.proprenter@ic-group.org Dipl.-Ing. Oliver K. Wagner ÖBB - Austrian Federal Railways

More information

PORT OF SILLAMÄE, ESTONIA THE MOST EASTERN PORT OF THE EU

PORT OF SILLAMÄE, ESTONIA THE MOST EASTERN PORT OF THE EU PORT OF SILLAMÄE, ESTONIA THE MOST EASTERN PORT OF THE EU LOCATION port location Global: 2060 km from Hamburg 2246 km from Rotterdam 2000 km from Bremerhaven 2424 km from Antwerp 2598 km from Le Havre

More information

Q&A: The New East Coast Line

Q&A: The New East Coast Line Q&A: The New East Coast Line Why is a railway in northern Sweden essential for Europe? Sweden is a vast country with enormous natural resources. Our industry has extremely high standards for environmental

More information

I-710 Project Committee Meeting

I-710 Project Committee Meeting Los Angeles County Metropolitan Transportation Authority I-710 Project Committee Meeting January 29, 2009 Meeting Expectations Review I-710 planning context Concur on a port cargo forecast scenario to

More information

Exploring A 21 st Century Alternative for Container Transport

Exploring A 21 st Century Alternative for Container Transport Exploring A 21 st Century Alternative for Container Transport Presented to TRB s 2006 Joint Summer Meeting Stephen S. Roop, Ph.D. Assistant Director, Texas Transportation Institute July 2006 21 st Century

More information

TEN-T Corridors, Ports and Motorways of the Sea

TEN-T Corridors, Ports and Motorways of the Sea THE NEW TRANS-EUROPEAN TRANSPORT NETWORK A CORE NETWORK: BLUEPRINT FOR 2030 TEN-T Corridors, Ports and Motorways of the Sea April 24, 2012 European Commission DG MOVE TEN-T Jose Anselmo Transport lifeblood

More information

TRANSPORTATION AND ADAPTATION A Canadian Perspective. Elizabeth Smalley Manager, Adaptation Policy Transport Canada June 7-8, 2018

TRANSPORTATION AND ADAPTATION A Canadian Perspective. Elizabeth Smalley Manager, Adaptation Policy Transport Canada June 7-8, 2018 TRANSPORTATION AND ADAPTATION A Canadian Perspective Elizabeth Smalley Manager, Adaptation Policy Transport Canada June 7-8, 2018 OVERVIEW 1 Canada s Transportation System 2 Climate Risks to the Canadian

More information

Rail Baltica: further steps, challenges and coordination of transport policy actions Jurgita Skritaitė Deputy Director, Transport Policy Department

Rail Baltica: further steps, challenges and coordination of transport policy actions Jurgita Skritaitė Deputy Director, Transport Policy Department Rail Baltica: further steps, challenges and coordination of transport policy actions Jurgita Skritaitė Deputy Director, Transport Policy Department RBGC project: Transnational Roundtable, November 24,

More information

Lord Adonis Minister of State for Transport Department for Transport Great Minster House 76 Marsham Street London SW1P 4DR. 13 th February 2009,

Lord Adonis Minister of State for Transport Department for Transport Great Minster House 76 Marsham Street London SW1P 4DR. 13 th February 2009, Lord Adonis Minister of State for Transport Department for Transport Great Minster House 76 Marsham Street London SW1P 4DR 13 th February 2009, Dear Lord Adonis, Objectives and remit for HS2 I have now

More information

LNG infrastructure in the Baltic Ports

LNG infrastructure in the Baltic Ports LNG infrastructure in the Baltic Ports Bogdan Ołdakowski, Secretary General, Baltic Ports Organization International LNG Congress 14-15 March 2016, London Plan of the presentation Introduction to BPO LNG

More information

Design of Izmir Bay Crossing Bridge

Design of Izmir Bay Crossing Bridge Design of Izmir Bay Crossing Bridge Burak Kurtman Dpt. Manager of Bridge Group, Yüksel Project International, Ankara, Turkey Tel: +90 (312) 4957000 E-mail: bkurtman@yukselproje.com.tr Abstract The Izmir

More information

EU Policy framework and what BPO is doing concerning LNG bunkering infrastructure LNG Training for Port Communities LNG in Baltic Sea Ports II Project

EU Policy framework and what BPO is doing concerning LNG bunkering infrastructure LNG Training for Port Communities LNG in Baltic Sea Ports II Project EU Policy framework and what BPO is doing concerning LNG bunkering infrastructure LNG Training for Port Communities LNG in Baltic Sea Ports II Project 22 nd April 2015 Klaipeda, Lithuania Bogdan Ołdakowski

More information

Project: 1520mm Broad Gauge-Connection Košice-Vienna

Project: 1520mm Broad Gauge-Connection Košice-Vienna August 2017 Project: 1520mm Broad Gauge-Connection Košice-Vienna Executive Summary Results of the Feasibility Studies as of August 2017 Up-date of the traffic forecasts (Prognos AG) Technical Feasibility

More information

Key Questions in International Transport Policy

Key Questions in International Transport Policy Key Questions in International Transport Policy Jari Kauppila, Senior Economist InterTran seminar Helsinki, 30 Nov 2015 Intergovernmental Organisation 57 member countries (23 non-oecd) focussing on transport

More information

NextGen Link. Upgrade of the maritime link with the port interconnections in the ScanMed Corridor 2016-EU-TM-0092-W

NextGen Link. Upgrade of the maritime link with the port interconnections in the ScanMed Corridor 2016-EU-TM-0092-W Markku Alahäme Development Manager Port of Turku NextGen Link Upgrade of the maritime link with the port interconnections in the ScanMed Corridor 2016-EU-TM-0092-W Action information Implementation time

More information

MEGASTAR BUNKERING EXPERIENCES. Sergei Jefimov Klaipeda

MEGASTAR BUNKERING EXPERIENCES. Sergei Jefimov Klaipeda MEGASTAR BUNKERING EXPERIENCES Sergei Jefimov Klaipeda 15.11.2017 CONTENTS 1. Eesti Gaas in brief 2. Why LNG? 3. Bunkering of Megastar 4. LNG supply chain 5. LNG quality 6. Conclusion EESTI GAAS IN BRIEF

More information

Sandpoint Junction Connector

Sandpoint Junction Connector Sandpoint Junction Connector BNSF Railway MAY 23, 2018 BNSF is a Leading Railroad A Berkshire Hathaway, Inc. company 32,500 route miles in 28 states and 3 Canadian provinces 42,000 employees Approximately

More information

European Mobility Network EU TEN-T Policy & CEF Pawel Stelmaszczyk European Commission DG MOVE

European Mobility Network EU TEN-T Policy & CEF Pawel Stelmaszczyk European Commission DG MOVE European Mobility Network EU TEN-T Policy & CEF Pawel Stelmaszczyk European Commission DG MOVE Key elements of the new TEN-T policy Support implementation of White Paper through new infrastructure policy,

More information

DECEMBER This report represents the opinion of the European Coordinator and does not prejudice the official position of the European Commission.

DECEMBER This report represents the opinion of the European Coordinator and does not prejudice the official position of the European Commission. North Sea Baltic Work Plan of the European Coordinator Catherine Trautmann Transport DECEMBER 2014 This report represents the opinion of the European Coordinator and does not prejudice the official position

More information

External costs of traffic in Sweden with a European outlook, Summary Report 2015:4

External costs of traffic in Sweden with a European outlook, Summary Report 2015:4 External costs of traffic in Sweden with a European outlook, 2015 Summary Report 2015:4 External costs of traffic in Sweden with a European outlook, 2015 Summary Report 2015:4 Transport Analysis Address:

More information

Port Cargo Scenarios Reviewed

Port Cargo Scenarios Reviewed Los Angeles County Metropolitan Transportation Authority Overview of Technical Studies Presented to I-710 Corridor Advisory Committee January 21, 2009 Los Angeles County Metropolitan Transportation Authority

More information

TRANSPORT and INFRASTRUCTURE

TRANSPORT and INFRASTRUCTURE The Resource Management Act allows district and regional plans and policy statements to enable people and communities to provide for their economic, cultural and social well being (that is part of the

More information

Appendix 8: Best Practicable Environmental Option (BPEO) Assessment

Appendix 8: Best Practicable Environmental Option (BPEO) Assessment Appendix 8: Best Practicable Environmental Option (BPEO) Assessment ABERDEEN HARBOUR EXPANSION PROJECT BEST PRACTICABLE ENVIRONMENTAL OPTION (BPEO) ASSESSMENT October 2015 Updated April 2016 TABLE OF CONTENTS

More information

1 Non-technical summary

1 Non-technical summary 1 1 Non-technical summary 11 Introduction This report constitutes a brief summary of the Environmental Impact Assessment Statement (EIAS) elaborated as a part of the Feasibility Study on the reconstruction

More information

INVESTMENTS IN PORT OF GDYNIA

INVESTMENTS IN PORT OF GDYNIA Jakub Koczara Port of Gdynia Authority S.A. INVESTMENTS IN PORT OF GDYNIA 1 INVESTMENTS Investments planned by the Port of Gdynia Authority for the years 2016-2022 Deepening of the approach and internal

More information

EUTRAIN Europe Neighbourhood Cooperation Countries (incl. Russia, CIS, Black Sea, Balkan States) 3rd Regional Workshop Moscow, Russia

EUTRAIN Europe Neighbourhood Cooperation Countries (incl. Russia, CIS, Black Sea, Balkan States) 3rd Regional Workshop Moscow, Russia EUTRAIN Europe Neighbourhood Cooperation Countries (incl. Russia, CIS, Black Sea, Balkan States) 3rd Regional Workshop Moscow, Russia 5-6 December 2012 Frank SMIT Directorate Transport "Horizontal aspects"

More information

Improved Accessibility in North-Eastern Baltic Sea Region NSB CoRe project

Improved Accessibility in North-Eastern Baltic Sea Region NSB CoRe project Improved Accessibility in North-Eastern Baltic Sea Region NSB CoRe project Tālis Linkaits Head of VASAB Secretariat 1 December 2016, Riga Europeans on the Move A cooperation of ministers of the 11 Baltic

More information

Current I-5 roadway overpasses need elevation lift, some overpasses need replacing anyway because of problems.

Current I-5 roadway overpasses need elevation lift, some overpasses need replacing anyway because of problems. This Presentation will show the general Salem area and the Salem Hills Oregon part. The Salem Hills are west of Turner, and the grades would be to much for the CHSR to go over the surface. The Cascadia

More information

The EU Transport Policy Leo Huberts, European Commission

The EU Transport Policy Leo Huberts, European Commission The EU Transport Policy Leo Huberts, European Commission Advisor to Mr Pat Cox, European Coordinator Scandinavian-Mediterranean Core Network Corridor Brussels (BE), Alpeuregio Summer School, 04 July 2016

More information

Preliminary Planning Study. New Railway Line Dresden Prague. Task 2 Route Optimization

Preliminary Planning Study. New Railway Line Dresden Prague. Task 2 Route Optimization New Railway Line Dresden Prague Status: 30 th October 2015 Content Task 2 Further qualification of the corridor and optimization of the preferred route...3 Page 2 Task 2 Further qualification of the corridor

More information

Let me know what time frame would be practical for preparing such advice and we can discuss the delivery date for your memo. Thank you.

Let me know what time frame would be practical for preparing such advice and we can discuss the delivery date for your memo. Thank you. From: McGee, Kelly [mailto:kelly.mcgee@cnsc-ccsn.gc.ca] Sent: April 25, 2012 3:00 PM To: Howard, Don; Klassen, Kathleen Cc: Myles,Debra [CEAA]; Francis, Kiza Subject: Information on three foreign waste

More information

INDIANA S INTERMODAL MANAGEMENT SYSTEM Stephen C. Smith Planning Manager, Transportation Planning Division Indiana Department of Transportation

INDIANA S INTERMODAL MANAGEMENT SYSTEM Stephen C. Smith Planning Manager, Transportation Planning Division Indiana Department of Transportation 96 INDIANA S INTERMODAL MANAGEMENT SYSTEM Stephen C. Smith Planning Manager, Transportation Planning Division Indiana Department of Transportation Indiana is in the process of developing an Intermodal

More information

Impact analysis of the TEN-T Core Network Corridors in the Baltic Sea Region Contribution to the discussion

Impact analysis of the TEN-T Core Network Corridors in the Baltic Sea Region Contribution to the discussion TRV 2016/38557 Impact analysis of the TEN-T Core Network Corridors in the Baltic Sea Region Contribution to the discussion Cases: Fehmarnbelt link and Rail Baltica Photo: Mikael Damkier, Mostphotos Abstract

More information

Estonian opportunities

Estonian opportunities Estonian opportunities Estonian capital Tallinn, is the EU memberstate capital that is closest to China. Estonia has a 1229 km rail network with 1520 mm gauge that connects us with the European part of

More information

Intermodal Logistics Centres and Freight Corridors Concepts and Trends

Intermodal Logistics Centres and Freight Corridors Concepts and Trends VII. International Scientific Logistics Conference WSL Forum, Poznan 12th of May 2017 Photo: Lutra GmbH Königs Wusterhausen Intermodal Logistics Centres and Freight Corridors Concepts and Trends Dr.rer.oec.habil.

More information

REPORT SHORT VERSION Survey of road freight through RoRo-ports along the south and west coast of Sweden

REPORT SHORT VERSION Survey of road freight through RoRo-ports along the south and west coast of Sweden REPORT SHORT VERSION Survey of road freight through RoRo-ports along the south and west coast of Sweden Results from interviews with 2 500 truck drivers Trafikverket Address: Trafikverket, 781 89 Borlänge

More information

AMENDMENT N 1 TO AGREEMENT No INEA/CEF/TRAN/M2015/

AMENDMENT N 1 TO AGREEMENT No INEA/CEF/TRAN/M2015/ Innovation and Networks Executive Agency Department C - Connecting Europe Facility (CEF) AMENDMENT N 1 TO AGREEMENT No INEA/CEF/TRAN/M2015/1129482 The Innovation and Networks Executive Agency (INEA) ("the

More information

Following the bananas

Following the bananas Following the bananas Claudio Richardson Trieste 2 nd April 2014-1- The Blue Banana and Beyond The Blue Banana (also known as the European Megalopolis or Manchester-Milan Axis among others) is a discontinuous

More information

18 TRAFFIC AND TRANSPORTATION

18 TRAFFIC AND TRANSPORTATION 18 TRAFFIC AND TRANSPORTATION 18.1 EXISTING ENVIRONMENT 18.1.1 Poole is relatively well connected to the main road network. The most direct access into Poole from the Port is across the lifting bridge

More information

THE BALTIC SEA MOTORWAY - RECENT DEVELOPMENT AND OUTLOOK FOR THE FUTURE

THE BALTIC SEA MOTORWAY - RECENT DEVELOPMENT AND OUTLOOK FOR THE FUTURE Journal of Maritime Research, Vol. IV. No. 2, pp. 21-30, 2007 Copyright 2007. SEECMAR Printed in Santander (Spain). All rights reserved ISSN: 1697-4840 THE BALTIC SEA MOTORWAY - RECENT DEVELOPMENT AND

More information

2016 Connecting Europe Facility (CEF) Transport Calls for Proposals COUNTRY FACTSHEET. Belgium

2016 Connecting Europe Facility (CEF) Transport Calls for Proposals COUNTRY FACTSHEET. Belgium 26 Connecting Europe Facility (CEF) Transport Calls for Proposals COUNTRY FACTSHEET Belgium Key facts and figures Evaluation results Eligible vs Recommended proposals by call proposals were selected for

More information

What is SFT? OÜ ANKURTUNNEL Tõnu Ader FinEst Link Final Conference on 7th of February

What is SFT? OÜ ANKURTUNNEL Tõnu Ader FinEst Link Final Conference on 7th of February What is SFT? OÜ ANKURTUNNEL Tõnu Ader +372 56244712 tonu.ader@gmail.com FinEst Link Final Conference on 7th of February SFT is Submerged Floating Tunnel Why prefer the Submerged Floating Tunnel? Proposed

More information

2nd Commuter Rail Munich A large scale project for Munich and the surrounding region

2nd Commuter Rail Munich A large scale project for Munich and the surrounding region 2nd Commuter Rail Munich A large scale project for Munich and the surrounding region DB Netz AG - Infozentrum 2. Stammstrecke München 20.11.2017 NETLIPSE Agenda Deutsche Bahn / DB Netz AG The 2nd Commuter

More information

October The Most Eastern Freeport of the European Union in the Baltic Sea

October The Most Eastern Freeport of the European Union in the Baltic Sea October 2016 The Most Eastern Freeport of the European Union in the Baltic Sea Location at the busiest sea road KM FROM ST- PETERS- MOSCOW PORT OF BURG HELSINKI 390 1120 KOTKA 270 985 SILLAMÄE 180 855

More information

Logistics center development in Panevėžys: Experiences on finding a balance between business activities and environmental aspects

Logistics center development in Panevėžys: Experiences on finding a balance between business activities and environmental aspects Logistics center development in Panevėžys: Experiences on finding a balance between business activities and environmental aspects 2005 September 29 th, Kaposvar by Tadas Jagminas, Adviser to the Mayor

More information

Briefing for: MOA Freight Advisory Commission. January12,

Briefing for: MOA Freight Advisory Commission. January12, Briefing for: MOA Freight Advisory Commission January12, 2010 www.highway2highway.com Project Team Lead Agencies Federal Highway Administration Federal Transit Administration Alaska Department of Transportation

More information

2015 CEF Transport Calls for Proposals COUNTRY FICHE. Spain

2015 CEF Transport Calls for Proposals COUNTRY FICHE. Spain Millions Millions Millions 2015 CEF Transport Calls for Proposals COUNTRY FICHE Spain Key facts and figures Evaluation results Eligible vs Recommended proposals by call 70 60 50 40 30 20 10 0 64 eligible

More information

Fixed transport connections across the Baltic from Finland to Sweden and Estonia.

Fixed transport connections across the Baltic from Finland to Sweden and Estonia. Usko Anttikoski Memo 14 September 2007 Fixed transport connections across the Baltic from Finland to Sweden and Estonia. Preliminary feasibility assessment. 2(29) Usko Anttikoski Memo 14 September 2007

More information

Executive Summary. Introduction

Executive Summary. Introduction Executive Summary 01 Introduction The City of Southampton lies at the western end of the South Hampshire sub-region. The wider urban South Hampshire area, consisting of Southampton, Eastleigh, Fareham,

More information

AL-AMEEN ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK

AL-AMEEN ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK AL-AMEEN ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE 6604 - RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK UNIT 1 RAILWAY PLANNING PART A 1. Define Permanent way. 2. List out the elements

More information

TEN-T POLICY REVIEW. UNITED NATIONS ECONOMIC COMMISSION FOR EUROPE Geneva, 7-8 September 2010

TEN-T POLICY REVIEW. UNITED NATIONS ECONOMIC COMMISSION FOR EUROPE Geneva, 7-8 September 2010 TEN-T POLICY REVIEW UNITED NATIONS ECONOMIC COMMISSION FOR EUROPE Geneva, 7-8 September 2010 Helmut Adelsberger European Commission, Directorate General for Mobility and Transport (DG MOVE) Transeuropean

More information

The Baltic-Adriatic Corridor. Stefan Ebner Division for Transport and Logistics, director dep. Austrian Federal Economic Chamber

The Baltic-Adriatic Corridor. Stefan Ebner Division for Transport and Logistics, director dep. Austrian Federal Economic Chamber The Baltic-Adriatic Corridor Stefan Ebner Division for Transport and Logistics, director dep. Austrian Federal Economic Chamber 14 November 2016 Austrian Transport Sector - Performance Passenger transport:

More information

The Policy-Related Road Transport Research in MOT

The Policy-Related Road Transport Research in MOT The Policy-Related Road Transport Research in MOT Wang Xiaojing Research Institute of Highway, MOT xj.wang@rioh.cn Content Background Policy-Related Transport Research International Cooperation 1. Background

More information

LANDUSE PLANNING, PUBLIC TRANSPORT AND PERSONAL MOBILITY

LANDUSE PLANNING, PUBLIC TRANSPORT AND PERSONAL MOBILITY 1 LANDUSE PLANNING, PUBLIC TRANSPORT AND PERSONAL MOBILITY Entries propose fundamentally different regional scenarios. A commonly agreed principle is increasing building density near rail stops. Challenging

More information

WP5 UN ECE Working Party on Transport Trends and Economics Geneva, 5 7 September Transport in the Mediterranean region

WP5 UN ECE Working Party on Transport Trends and Economics Geneva, 5 7 September Transport in the Mediterranean region WP5 UN ECE Working Party on Transport Trends and Economics Geneva, 5 7 September 2016 CETMO Centre for Transportation Studies for the Western Mediterranean Geneva, 6 th September 2016 CETMO Organization

More information

Freight Action Plan Summary. A Catalyst for Change The Regional Transport Strategy for the west of Scotland

Freight Action Plan Summary. A Catalyst for Change The Regional Transport Strategy for the west of Scotland Freight Action Plan Summary A Catalyst for Change The Regional Transport Strategy for the west of Scotland 2007-2021 Strathclyde Partnership for Transport Contents Purpose...2 Issues, Constraints and Opportunities...2

More information

INIS - Intermodal Node Information System for the Rail Baltica Growth Corridor (RBGC)

INIS - Intermodal Node Information System for the Rail Baltica Growth Corridor (RBGC) INIS - Intermodal Node Information System for the Rail Baltica Growth Corridor (RBGC) Winter, Mareen 1), Heiland, Martin 2) Kämmerer,Grit 3) 1) IPG Infrastruktur- und Projektentwicklungsgesellschaft mbh,

More information

TR 12 Lahti-Kouvola Impacts on the community structure and employment

TR 12 Lahti-Kouvola Impacts on the community structure and employment TR 12 Lahti-Kouvola Impacts on the community structure and employment Taloustutkimus Oy Pasi Holm and Juho Tyynilä Further information: pasi.holm@taloustutkimus.fi; tel. +358(0) 50 374 7462 1 A second

More information

INTERMODAL TRANSPORT AND THE WHITE PAPER IRU POSITION

INTERMODAL TRANSPORT AND THE WHITE PAPER IRU POSITION GETC/G3311/SPR Geneva, 29 November 2001 INTERMODAL TRANSPORT AND THE WHITE PAPER IRU POSITION INTRODUCTION The White Paper EUROPEAN TRANSPORT POLICY FOR 2010: DECISION TIME published by the European Commission

More information

EU Transport policy in TEN-T

EU Transport policy in TEN-T EU Transport policy in TEN-T CEF and the TEN-T from an Arctic perspective Brussels, 11 October 2018 Martin Zeitler Adviser to ScanMed Corridor Coordinator Pat Cox DG Mobility and Transport, Unit: Transport

More information

VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK

VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE 6604 - RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK UNIT 1 RAILWAY PLANNING 1. Define Permanent way. 2. List out the elements

More information

MOTORWAYS OF THE SEA- CHALLENGES & OPPORTUNITIES FOR CHANGES IN OUR TRANSPORT

MOTORWAYS OF THE SEA- CHALLENGES & OPPORTUNITIES FOR CHANGES IN OUR TRANSPORT MOTORWAYS OF THE SEA- CHALLENGES & OPPORTUNITIES FOR CHANGES IN OUR TRANSPORT «Greening Motorways of the Sea» SYSTEM Stockholm, 21-22 April 2005 Arnaud Revel Unit Motorways of the Sea and Intermodality

More information

Appendix S10 - Airport Business Zone Structure Plan

Appendix S10 - Airport Business Zone Structure Plan S10.1 S10.1.1 S10.1.2 General The Airport Business Zone Structure Plan covers an area of some 157ha surrounding the airport operational area. It contains some existing industrial and service activities

More information

PROPOSAL FOR A HELSINKI - TALLINN TUNNEL PROJECT

PROPOSAL FOR A HELSINKI - TALLINN TUNNEL PROJECT PROPOSAL FOR A HELSINKI - TALLINN TUNNEL PROJECT 14.5.2018 TABLE OF CONTENTS 1 EXECUTIVE SUMMARY... 3 2 VISION... 5 2.1 GLOBAL INNOVATION STATUS... 5 2.2 TUNNEL CAN ENABLE FASTER TRADE BETWEEN EU AND ASIA...

More information