Planned Procurement Opportunities Report. December 2017

Size: px
Start display at page:

Download "Planned Procurement Opportunities Report. December 2017"

Transcription

1 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department

2 Overview The Planned Procurement Opportunities Report is updated and posted on the Authority s website each month. The various competitive solicitation methods include: t RFI - Request for Information t RFQ - Request for Qualifications t RFP - Request for Proposals t - Invitation to Bid t ITQ - Invitation to Quote t ITO - Online Bid Event Solicitation information and dates published are subject to change at any time. Dates that have not been determined are noted as <TBD>. Additional information for all advertised solicitations is available at If you are interested in business opportunities with the Aviation Authority it is recommended that you register on the Supplier Registration Database. Registration is a simple, online process. One of the primary benefits is the opportunity to receive notification of Aviation Authority solicitations and contract opportunities. Supplier Registration Online Bid Event is an Invitation to Online Bid, which is made up of two parts: Part 1, Qualification Process and Part 2, Online Bid Event. In Part 1, each Respondent will submit a Response Form that lists all requirements for being deemed qualified to participate in the Online Bid Event. Prior to Part 2, each qualified bidder will be trained on how to participate in the online bid event. During the event, the bidders have the opportunity to lower their prices during a fixed time. At the close of the event, the low bidder receives the award. Please contact the appropriate Procurement Agent if you have questions regarding a particular solicitation. Page 2

3 AD Grease Drainage System Preventive Maintenance for grease drainage and enzyme services at Tampa International Airport. 1-Dec-17 N/A 27-Dec-17 1-Feb-18 Anita Hoover (813) RPZ and Approach Areas Tree Trimming, HCAA Project No to trim trees at all Authority RPZ and Approach Areas. <TBD> <TBD> <TBD> 1-Mar-18 Selection of Design-Builder, Main Terminal Curbside Expansion, Energy Plant and Related Work, HCAA Project Nos , , & RFQ to expand Tampa International Airport's Red and Blue Curbsides and also to provide new energy plant facilities, reconfigure the existing FAA parking lot, provide a replacement facility for the existing loading dock and demolish the administration building. 04-Oct Oct Dec-17 1-Mar-18 RFQ Selection of Design Professional, Airsides Restroom Refurbishment, HCAA Project No RFQ for Design Professional to upgrade Airside A and Airside E restrooms at Tampa International Airport. Landscape Maintenance Services for Landscape Maintenance Services; mowing and landscape bed maintenance at Tampa International Airport locations; Cargo Road, Hoover Blvd., O Brien Street and Spruce Street as well as Peter O. Knight, Tampa Executive and Plant City Airports 15-Nov Nov Dec-17 1-Mar-18 6-Dec Dec Jan-18 1-Mar-18 Tom Thalheimer TThalheimer@TampaAirport.com (813) RFQ Page 3

4 Checked Baggage System Upgrades and Optimization, HCAA Project No for checked baggage system upgrades and optimization at Airside A and Airside C at Tampa International Airport. Commercial Ground Transportation Facility & Main Terminal West Side Ground Transportation Hold Areas, HCAA Project No & for the construction of a commercial ground transportation facility and construction of the main terminal west side ground transportation hold area at Tampa International Airport. AD 17-Nov-17 6-Dec Jan-18 1-Mar Dec Jan-18 1-Feb-18 1-Mar-18 Pest Control Services for pest control services at Tampa International Airport. Plumbing Supplies for the purchase of plumbing supplies for all Authority Airports. Rental Car Fuel Tank Removal, HCAA Project No to perform limited site rehabilitation at the petroleum storage system associated with the RAC quick turn-around facility in the Long Term Parking Garage at Tampa International Airport. 13-Dec-17 4-Jan Feb-18 5-Apr Jan-18 N/A 22-Feb-18 5-Apr Dec Jan Feb-18 5-Apr-18 Damaris Cordova DTorresCordova@TampaAirport.com (813) Anita Hoover AHoover@TampaAirport.com (813) Selection of Firm and Award of Contract, Insurance Consultant Services RFP to provide insurance consulting services at Tampa International Airport. 5-Jan Jan-18 2-Feb-18 3-May-18 Cathy Tefft CTefft@TampaAirport.com (813) RFP Page 4

5 Shuttle Guideway Railing Improvements, HCAA Project No to improve guard railings along the shuttle guideway bridges between the Main Terminal and Airsides at Tampa International Airport. AD <TBD> <TBD> <TBD> 3-May-18 Airside A Boarding Level and Bridges Carpet Replacement, HCAA Project No for the replacement of the passenger boarding level and bridges carpet in addition to some back of house flooring at Airside A. 12-Feb Feb Apr-18 7-Jun-18 Airsides A and F Handler Replacement, HCAA Project No for the replacement of six air handlers at Airside F and two outdoor air handlers at Airside A with modern, high efficiency, modular air handlers with energy saving accessories. 15-Mar Mar Apr-18 7-Jun-18 Glass Cleaning Services for glass cleaning services at Tampa International Airport. 9-Mar Mar Apr-18 7-Jun-18 Amy Flack AFlack@TampaAirport.com (813) Airside A Sort Conveyor Support Structural Rehabilitation, HCAA Project No to rehabilitate the existing steel support structure for the Airside A sort facility conveyors at Tampa International Airport. 14-Mar Mar Apr-18 2-Aug-18 Page 5

6 Runway and Other Pavement Rehabilitation, HCAA Project No to rehabilitate Runway 18-36; Taxiways B, D, F and G; Tie down areas E, H and J; Hangar Taxilanes J, S, T and U; Helicopter parking area; The hangar service road; The FBO terminal parking lot and the east service at Peter O. Knight Airport. AD 2-Apr Apr May-18 2-Aug-18 North Air Cargo Facility Redevelopment, HCAA Project No to renovate approximately 30,000 SF of the existing north cargo building at Tampa International Airport 10-Apr Apr May-18 2-Aug-18 Support Buildings and Pavement Repairs, HCAA Project No for the repair of support buildings and structures including limited remedial repairs at all Authority Airports. 13-Apr Apr May-18 2-Aug-18 Airside F Cooling Tower Refurbishment, HCAA Project No to complete structural, cosmetic, and mechanical refurbishments to the 1985 vintage concrete cooling tower at Airside F. 18-Apr-18 2-May May-18 2-Aug-18 Airfield Maintenance Equipment Storage Building Addition, HCAA Project No to construct two new storage buildings at the Airfield Maintenance Facility. 1-May May Jun-18 2-Aug-18 Selection of Firm and Award of Contract, State Legislative Services Consulting Services RFP to provide state legislative consulting services at Tampa International Airport. <TBD> <TBD> <TBD> 6-Sep-18 Cathy Tefft CTefft@TampaAirport.com (813) RFP Page 6

Planned Procurement Opportunities Report. November 2017

Planned Procurement Opportunities Report. November 2017 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

Planned Procurement Opportunities Report. February 2018

Planned Procurement Opportunities Report. February 2018 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

Planned Procurement Opportunities Report. January 2018

Planned Procurement Opportunities Report. January 2018 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

Planned Procurement Opportunities Report. September 2017

Planned Procurement Opportunities Report. September 2017 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

Planned Procurement Opportunities Report. March 2018

Planned Procurement Opportunities Report. March 2018 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

Planned Procurement Opportunities Report. April 2018

Planned Procurement Opportunities Report. April 2018 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

Planned Procurement Opportunities Report. August 2017

Planned Procurement Opportunities Report. August 2017 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

Planned Procurement Opportunities Report. August 2017

Planned Procurement Opportunities Report. August 2017 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

Planned Procurement Opportunities Report. May 2017

Planned Procurement Opportunities Report. May 2017 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

Planned Procurement Opportunities Report. July 2017

Planned Procurement Opportunities Report. July 2017 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

Planned Procurement Opportunities Report. October 2018

Planned Procurement Opportunities Report. October 2018 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

Aviation Authority Capital Improvement Program Project Status Report

Aviation Authority Capital Improvement Program Project Status Report Aviation Authority Capital Improvement Program Project Status Report June 2018 Prepared by Planning and Development and Development Program Services Capital Improvement Project Status Report Overview The

More information

Aviation Authority Capital Improvement Program Project Status Report April and May 2018

Aviation Authority Capital Improvement Program Project Status Report April and May 2018 Aviation Authority Capital Improvement Program Project Status Report April and May 2018 Prepared by Planning and Development and Development Program Services Capital Improvement Project Status Report Overview

More information

Aviation Authority Capital Improvement Program Project Status Report December 2017

Aviation Authority Capital Improvement Program Project Status Report December 2017 Aviation Authority Capital Improvement Program Project Status Report December 2017 Prepared by Planning and Development and Development Program Services Capital Improvement Project Status Report Overview

More information

Presentation for Business Opportunities & Entrepreneurial Training Summit

Presentation for Business Opportunities & Entrepreneurial Training Summit Welcome to the Presentation for Business Opportunities & Entrepreneurial Training Summit October 9, 2018 Ned Carey, C.M. Chief - Division of Administration & Performance Management Safety Management System

More information

PLANNING & DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGEMENT MICHAEL SHEEHAN SR DIRECTOR OF AIM DEVELOPMENT

PLANNING & DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGEMENT MICHAEL SHEEHAN SR DIRECTOR OF AIM DEVELOPMENT PLANNING & DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGEMENT MICHAEL SHEEHAN SR DIRECTOR OF AIM DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGMENT 2 FACILITY SERVICES Facility Development Capital Projects Management

More information

Aviation Capital Construction Program Update

Aviation Capital Construction Program Update Aviation Capital Construction Program Update 2012 Completed Projects 2013 Active Projects Bern Seals Program Manager Parsons Management Consultants April 2013 0 Discussion Agenda Program Safety Performance

More information

Aviation Authority Capital Improvement Program Project Status Report November and December 2016

Aviation Authority Capital Improvement Program Project Status Report November and December 2016 Aviation Authority Capital Improvement Program Project Status Report November and December 2016 Prepared by Planning and Development and Development Program Services Capital Improvement Project Status

More information

Capability List Document Document QA-TCL

Capability List Document Document QA-TCL Capability List Document FAA Approved Repair Station TAMY352I José María Córdova Int'l Airport Cargo Zone, Tampa Cargo Hangar Rionegro, Ant Colombia APPROVED: YALILE MAHMUD QUALITY CONTROL CHIEF Capability

More information

[ITEMS IN BOLD REQUIRE APPROVAL BY THE AVIATION AUTHORITY BOARD]

[ITEMS IN BOLD REQUIRE APPROVAL BY THE AVIATION AUTHORITY BOARD] CONSTRUCTION COMMITTEE MEETING AGENDA DATE: Tuesday, February 12, 2019 TIME: 8:30 a.m. ~ GREATER ORLANDO V AVIATION AUTHORITY PLACE: GOAA ANNEX BUILDING, 1ST FLOOR - CONFERENCE ROOMS (APOLLO/GEMINI/TAURUS),

More information

Briefing Session: A406 STRATEGIC PROJECTS PROGRAM MANAGEMENT. January 24, 2019

Briefing Session: A406 STRATEGIC PROJECTS PROGRAM MANAGEMENT. January 24, 2019 Briefing Session: A406 STRATEGIC PROJECTS PROGRAM MANAGEMENT January 24, 2019 BRIEFING SESSION 1. Introduction to strategic projects at Logan B to C Roadway Improvements Terminal C Canopy and Curbside

More information

Aviation Authority Capital Improvement Program Project Status Report October and November 2017

Aviation Authority Capital Improvement Program Project Status Report October and November 2017 Aviation Authority Capital Improvement Program Project Status Report October and November 2017 Prepared by Planning and Development and Development Program Services Capital Improvement Project Status Report

More information

Aviation Authority Capital Improvement Program Project Status Report August 2017

Aviation Authority Capital Improvement Program Project Status Report August 2017 Aviation Authority Capital Improvement Program Project Status Report August 2017 Prepared by Planning and Development and Development Program Services Capital Improvement Project Status Report Overview

More information

HILLSBOROUGH COUNTY AVIATION AUTHORITY REQUEST FOR INFORMATION FOR. Commercial Ground Transportation Services Consultant

HILLSBOROUGH COUNTY AVIATION AUTHORITY REQUEST FOR INFORMATION FOR. Commercial Ground Transportation Services Consultant HILLSBOROUGH COUNTY AVIATION AUTHORITY REQUEST FOR INFORMATION FOR Commercial Ground Transportation Services Consultant SOLICITATION NUMBER: 14-534-802 ISSUE DATE: April 11, 2014 1.0 Project Background

More information

Airport Construction Project Risk Management. Presented by: Mindy Price- Direct Effect Solutions

Airport Construction Project Risk Management. Presented by: Mindy Price- Direct Effect Solutions Airport Construction Project Risk Management Presented by: Mindy Price- Direct Effect Solutions Topics ACRP 01-22 Research Background Research Findings and Conclusions Project Risk Management Recommendations

More information

Rail-Volution Roundtable Sustainable Planning & Design

Rail-Volution Roundtable Sustainable Planning & Design Rail-Volution Roundtable Sustainable Planning & Design October 28, 2008 1. Extension of Caltrain 2. New Intermodal Bus and Rail Station 3. New Neighborhood Transbay Transit Center Program Transbay Location

More information

WELCOME. NEW NORTH CONCOURSE PACKAGE #3 Open House 10/20/2017

WELCOME. NEW NORTH CONCOURSE PACKAGE #3 Open House 10/20/2017 WELCOME NEW NORTH CONCOURSE PACKAGE #3 Open House 10/20/2017 Today s with Turner Team Introductions Project Overview Pre-Qualification Requirements & Bid Process Contracting Opportunities Introductions:

More information

Love Field Concessions Options

Love Field Concessions Options Love Field Concessions Options Briefing for the City Council Department of Aviation August 18, 2010 Background 6/11/07 Briefed proposal to TEC to extend existing concession contracts through period of

More information

Metropolitan District Commission

Metropolitan District Commission Metropolitan District Commission Hartford Procurement Department How to Business with the MDC June 4, 2014 Metropolitan District Commission The Metropolitan District (MDC) is a non-profit municipal corporation

More information

CORVALLIS SCHOOL DISTRICT

CORVALLIS SCHOOL DISTRICT RFP 003-2018 Testing & Inspection Services CORVALLIS SCHOOL DISTRICT Request for Proposals RFP 003-2018 Testing & Inspecting Services For 2018-2021 Bond Projects Issued: October 09, 2018 Due: By 4:00 PM,

More information

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor April 9, :30 a.m.

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor April 9, :30 a.m. AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor 9:30 a.m. Minutes Approval of Minutes: Regular Commission Meeting March 12, 2014 Executive Director Approval

More information

Property Insurance Clearinghouse Actuarial & Underwriting Committee Update November 18, 2013

Property Insurance Clearinghouse Actuarial & Underwriting Committee Update November 18, 2013 Property Insurance Clearinghouse Actuarial & Underwriting Committee Update November 18, 2013 Participating Carrier Update Participating Carriers Distributed the Insurer Readiness Questionnaire and the

More information

Greening Buildings at the Dallas/Fort Worth International Airport. Sustainable Communities Conference Dallas, TX. March 10, 2009

Greening Buildings at the Dallas/Fort Worth International Airport. Sustainable Communities Conference Dallas, TX. March 10, 2009 Greening Buildings at the Dallas/Fort Worth International Airport Sustainable Communities Conference Dallas, TX March 10, 2009 Agenda Energy Efficiency in New Construction Energy Efficiency in Retrofits

More information

Presented to: Tampa Bay Applications Group. Presented by: Louis E. Miller Executive Director Tampa International Airport

Presented to: Tampa Bay Applications Group. Presented by: Louis E. Miller Executive Director Tampa International Airport Presented to: Tampa Bay Applications Group Presented by: Louis E. Miller Executive Director Tampa International Airport Hillsborough County Aviation Authority (Who we are and who we aren t) Created as

More information

Dec Board of Education: Approve Educational Specifications. Dec Jan. 2016

Dec Board of Education: Approve Educational Specifications. Dec Jan. 2016 Dec. 2015 Dec. 2015 Jan. 2016 Jan 2016 Fairfield Public Schools Develops Project Team Initial Funding request analysis (including temporary classrooms costs) for services through Design Development Board

More information

Clark County Department of Aviation Purchasing. Purchasing and Contracts 1845 East Russell Road, Suite 300 Las Vegas, NV 89119

Clark County Department of Aviation Purchasing. Purchasing and Contracts 1845 East Russell Road, Suite 300 Las Vegas, NV 89119 Clark County Department of Aviation and Contracts 1845 East Russell Road, Suite 300 Las Vegas, NV 89119 Clark County Department of Aviation Use Clark County Supplier Registration: https://supplierregistration.clarkcountynv.gov//

More information

Doug Kreulen President and CEO Bobby Joslin MNAA Board Chairman BNA Vision Video Chief Operating Officer Robert Ramsey, P.E., A.A.E. Chief Operating Officer Nashville International Airport Vision Update

More information

City of Dallas Dallas Airport System FY Aviation Capital Project Plan As of June 14, 2017 Total Project Description

City of Dallas Dallas Airport System FY Aviation Capital Project Plan As of June 14, 2017 Total Project Description 2017 RIM Project - Removal of portion of 18/36 either side of TWY A - Construction $2.8 Relocate Runway 31R Glideslope - Construction $3.0 Relocate Runway 31R Glideslope - Reimbursable Agreement for Construction

More information

U.S. 281 North Park & Ride Project

U.S. 281 North Park & Ride Project U.S. 281 North Park & Ride Project 2 Adopted in 2009 5 High-Capacity Corridors Identified New Passenger Facilities Urban Circulator System Bus Network Improvements Total Community Need $3.5-$4B 3 Westside

More information

2019 Annual Airfield Pavement Rehabilitation CONTRACT NO ADDENDUM NUMBER ONE

2019 Annual Airfield Pavement Rehabilitation CONTRACT NO ADDENDUM NUMBER ONE February 13, 2019 2019 Annual Airfield Pavement Rehabilitation CONTRACT NO. 201947110 ADDENDUM NUMBER ONE This Addendum Number One supersedes and/or supplements all portions of the Contract Documents with

More information

Voorhees Replacement Facility Schedule Summary Classic WBS Layout 29-Sep-09 13:50 Activity Name Original Start Finish Duration Voorhees Replacement F 1136 17-Nov-06 31-Mar-11 Schematic Design 87 17-Nov-06

More information

Project Budget and Schedule Status Report

Project Budget and Schedule Status Report Item 52 Transit Program Project Budget and Schedule Status Report Construction Committee June 19, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments 3 Crenshaw/LAX

More information

FTP/SIS Steering Committee Work Plan and PPI Update

FTP/SIS Steering Committee Work Plan and PPI Update FTP/SIS Steering Committee Work Plan and PPI Update Work Plan and PPI Update Presented by: Dana Reiding September 30, 2015 FTP and SIS Update Process and Schedule Issues Identification Jan Feb Potential

More information

FACILITY PROJECTS. David Mashburn Director of Facility Services AIRPORT INFRASTRUCTURE MANAGEMENT

FACILITY PROJECTS. David Mashburn Director of Facility Services AIRPORT INFRASTRUCTURE MANAGEMENT FACILITY PROJECTS David Mashburn Director of Facility Services AIRPORT INFRASTRUCTURE MANAGEMENT FIS FINISH IMPROVEMENTS Image Ideas 2 CAPITAL PLAN FIS Finish Improvements - pictures of current condition

More information

Department of Transportation Rapid City Region Office 2300 Eglin Street P.O. Box 1970 Rapid City, SD Phone: 605/ FAX: 605/

Department of Transportation Rapid City Region Office 2300 Eglin Street P.O. Box 1970 Rapid City, SD Phone: 605/ FAX: 605/ Connecting South Dakota and the Nation Department of Transportation Rapid City Region Office 2300 Eglin Street P.O. Box 1970 Rapid City, SD 57709-1970 Phone: 605/394-2244 FAX: 605/394-1904 July 9, 2014

More information

Doing Business with the Metropolitan Washington Airports Authority

Doing Business with the Metropolitan Washington Airports Authority Doing Business with the Metropolitan Washington Airports Authority MWMCA Quarterly Economic Summit Brown Advisory November 7, 2017 Introduction to MWAA Ronald Reagan Washington National Airport Washington

More information

AVIATION AUTHORITY POLICY

AVIATION AUTHORITY POLICY PURPOSE: To establish a policy for the selection of development related professional services firms, including design-build firms for professional services and the Consulting Engineer, pursuant to the

More information

How to do Business with the Cobb County School District. Presented by: CCSD Procurement Services Department

How to do Business with the Cobb County School District. Presented by: CCSD Procurement Services Department How to do Business with the Cobb County School District Presented by: CCSD Procurement Services Department 770-590-4524 2 CCSD Statistics 2nd largest school district in Georgia 23rd largest school district

More information

2018 ARCHITECTURAL, ENGINEERING AND PLANNING OUTREACH. August 9, 2018

2018 ARCHITECTURAL, ENGINEERING AND PLANNING OUTREACH. August 9, 2018 2018 ARCHITECTURAL, ENGINEERING AND PLANNING OUTREACH August 9, 2018 Schedule 8:30 a.m. Check-in & Network 9:00 a.m. Pre-Qualification Program 9:30 a.m. Network Break 10:00 a.m. Terminal and Landside/Land

More information

Supply Chain Risk Management. Contents are subject to change. For the latest updates visit

Supply Chain Risk Management. Contents are subject to change. For the latest updates visit Supply Chain Risk Page 1 of 7 Why Attend Supply chain managers, procurement managers and sourcing professionals manage company's activities and spend with its suppliers, which can be a very significant

More information

HIGHLANDS AND ISLANDS AIRPORTS LIMITED

HIGHLANDS AND ISLANDS AIRPORTS LIMITED HIGHLANDS AND ISLANDS AIRPORTS LIMITED ANNUAL PROCUREMENT REPORT 2017/18 Version 1.0 Date June 2018 Highlands and Islands Airports Ltd Page 1 of 10 Contents Introduction 3 Section 1 - Summary of Regulated

More information

DRAFT MASTER PLAN RICHFIELD HERITAGE PRESERVE. Environmental OCTOBER 2016

DRAFT MASTER PLAN RICHFIELD HERITAGE PRESERVE. Environmental OCTOBER 2016 DRAFT MASTER PLAN RICHFIELD HERITAGE PRESERVE OCTOBER 2016 Environmental DesignGroup STREETSBORO RD SITE BROADVIEW ROAD RICHFIELD HERITAGE PRESERVE 336 ACRES CLEAN OHIO CLEAN OHIO OVIATT RD RECAP FEBRUARY

More information

CAPITAL and STRATEGIC PLANNING

CAPITAL and STRATEGIC PLANNING CAPITAL and STRATEGIC PLANNING Thomas C. Lambert President & CEO Notice and Agenda of a Meeting of the Capital & Strategic Planning Committee of the METRO Board of Directors COMMITTEE MEMBERS Sanjay Ramabhadran,

More information

Route 29 Solutions. October 23, 2014 Rt. 29 Project Delivery Advisory Panel Meeting

Route 29 Solutions. October 23, 2014 Rt. 29 Project Delivery Advisory Panel Meeting October 23, 2014 Rt. 29 Project Delivery Advisory Panel Meeting Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Viewers:

More information

Appendix H Support Facilities Preliminary and Intermediate Alternatives Analysis

Appendix H Support Facilities Preliminary and Intermediate Alternatives Analysis Appendix H SUPPORT FACILITIES PRELIMINARY AND INTERMEDIATE ALTERNATIVES ANALYSIS H TABLE OF CONTENTS EXHIBITS TABLES H.1 Evaluation Criteria... 1 H.1.1 Meeting the Base Constrained Demand Level... 1 H.1.2

More information

Traffic Department Anchorage: Performance. Value. Results.

Traffic Department Anchorage: Performance. Value. Results. Traffic Department Anchorage: Performance. Value. Results. Mission Promote safe and efficient area-wide transportation that meets the needs of the community and the Anchorage Municipal Traffic Code requirements.

More information

REQUEST FOR QUOTES: # LE

REQUEST FOR QUOTES: # LE REQUEST FOR QUOTES: #15-07-1391LE Navajo Division of Transportation Department of Airports Management ADOT GRANT #E5S2R - Independent Fee Estimate - Reconstruct Runway 15/33 (Approximately 2,000 x 75 )

More information

REQUEST FOR PROPOSAL PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM PROGRAM MANAGEMENT SERVICES

REQUEST FOR PROPOSAL PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM PROGRAM MANAGEMENT SERVICES REQUEST FOR PROPOSAL PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM PROGRAM MANAGEMENT SERVICES The Allegheny County Airport Authority (ACAA) is soliciting proposals from interested and

More information

Changi Airport Group Changi eprocure (Powered by Zycus) Frequently Asked Questions for Suppliers Version 2.0

Changi Airport Group Changi eprocure (Powered by Zycus) Frequently Asked Questions for Suppliers Version 2.0 This list of Frequently Asked Questions (FAQs) is meant to help with your transition towards the new Changi eprocure (powered by Zycus). General: 1. Who is Zycus? Zycus is the vendor that CAG has engaged

More information

Potential Public Private Partnership Projects. Miami-Dade Water and Sewer Department

Potential Public Private Partnership Projects. Miami-Dade Water and Sewer Department Potential Public Private Partnership Projects Miami-Dade Water and Sewer Department www.miamidade.gov/water Who We Are Number of People Served by Our Utility Each Day 2.3 Million Residential Monthly Rates

More information

Report to the Finance Committee Comprehensive Annual Financial Report. Prepared by the Office of Finance April 2016

Report to the Finance Committee Comprehensive Annual Financial Report. Prepared by the Office of Finance April 2016 Report to the Finance Committee 2015 Comprehensive Annual Financial Report Prepared by the Office of Finance April 2016 Audit Opinion date April 11, 2016 Unmodified or clean audit opinion on financial

More information

Orange Education Center Project Update. Board of Trustees Meeting February 25, 2019

Orange Education Center Project Update. Board of Trustees Meeting February 25, 2019 Orange Education Center Project Update Board of Trustees Meeting February 25, 2019 1 ORANGE EDUCATION CENTER 2 Topics 1. Need for Adult Education (AE) in Orange 2. Location of AE Center 3. Fiscal Feasibility

More information

Myanmar Disaster Risk Management Project Procurement Plan

Myanmar Disaster Risk Management Project Procurement Plan Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. General Myanmar Disaster Risk Management Project Plan 1. Project information: Myanmar

More information

Energy Efficiency / Conservation Case Studies in Waste Water Treatment Facilities

Energy Efficiency / Conservation Case Studies in Waste Water Treatment Facilities Energy Efficiency / Conservation Case Studies in Waste Water Treatment Facilities Prepared for: Energy Saving Opportunities for Wastewater Treatment Facilities: Energy Efficiency and CHP Workshop May 19

More information

Dulles Corridor Enterprise Financial Update Dulles Corridor Advisory Committee Meeting

Dulles Corridor Enterprise Financial Update Dulles Corridor Advisory Committee Meeting Dulles Corridor Enterprise Financial Update Dulles Corridor Advisory Committee Meeting June 22, 2016 Discussion Outline Finance Plan for the Metrorail Project Financial Developments Since December 2015

More information

Ariba Project Outcomes October 2017 Update. Presented by Procurement Department October 2017

Ariba Project Outcomes October 2017 Update. Presented by Procurement Department October 2017 Ariba Project Outcomes October 2017 Update Presented by Procurement Department October 2017 1 Topics 1. P2P Module Transactional Procurement 2. Purchase Requisition Cycle Time 3. Supplier Enablement and

More information

AFRICAN DEVELOPMENT FUND

AFRICAN DEVELOPMENT FUND AFRICAN DEVELOPMENT FUND PROJECT: JOMO KENYATTA INTERNATIONAL AIRPORT EMERGENCY INTERIM TERMINAL CONSTRUCTION PROJECT COUNTRY: KENYA OITC/EARC DEPARTMENTS October 2013 1. INTRODUCTION 1.1 Management hereby

More information

Houston Airport System

Houston Airport System 05.08.18 214pm CIP 546 rev Houston Airport System May 8, 2018 Infrastructure Industry Day May 8, 2018 Sheraton North Houston At George Bush Intercontinental 15700 John F Kennedy Blvd. Houston, TX 77032

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDA NEW AND REVISED IIM

VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDA NEW AND REVISED IIM VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDA JULY 2015 MAY 2018 May 21, 2018 IIM-LD-195.10 Virginia Stormwater Management Program May 21,

More information

Fiddler's Marsh Cove

Fiddler's Marsh Cove Fiddler's Marsh Cove Tom McLellan 450-0326 Prepared: 6/14/2018 Lot Number D16 D31 D6 D25 D18 D15 D29 D7 D26 D20 Model MADISON2 MADISON2 CHANDLER MADISON2 MADISON2 MADISON2 LYNDON VALE ULYSSA MADISON2 Elevation

More information

Capital Project Tracking Report

Capital Project Tracking Report Bus Shelter Lighting Upgrades Firm: Start: End: Bus Shelter Pad & Installation Phase 6 Firm: GCW, Inc. Funding: $107,500 Start: Jun 2018 End: Jan 2019 % Complete: 33% Continue to submit exhibits for permit

More information

REQUEST FOR QUALIFICATIONS PROFESSIONAL AIRPORT ENGINEERING SERVICES RUNWAY 16R-34L IMPROVEMENTS PROGRAM RENO-TAHOE INTERNATIONAL AIRPORT

REQUEST FOR QUALIFICATIONS PROFESSIONAL AIRPORT ENGINEERING SERVICES RUNWAY 16R-34L IMPROVEMENTS PROGRAM RENO-TAHOE INTERNATIONAL AIRPORT REQUEST FOR QUALIFICATIONS PROFESSIONAL AIRPORT ENGINEERING SERVICES RUNWAY 16R-34L IMPROVEMENTS PROGRAM RENO-TAHOE INTERNATIONAL AIRPORT The Reno-Tahoe Airport Authority (RTAA) Reno, Nevada, is seeking

More information

Materials and Supply Chain Management. Contents are subject to change. For the latest updates visit

Materials and Supply Chain Management. Contents are subject to change. For the latest updates visit Materials and Supply Chain Page 1 of 7 Why Attend Supply Chain (SCM) has been consistently cited as one of the most critical processes in any operational company. The impact SCM has on business is major

More information

Energy Usage Reduction Program

Energy Usage Reduction Program Energy Usage Reduction Program Presented By: Samuel R. Day Earth Recycle Image Source: http://www.pfbsustainability.com/objectives.html Columbus Castings History First batch of steel melted from Parsons

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Construction Committee November 21, 2013 & Schedule Performance Summary Chart 2 1 Crenshaw/LAX Transit 1,749 2,058 2,058

More information

NCDOT s Performance Based Contracting Experience in Charlotte. Jennifer Brandenburg, PE State Road Maintenance Engineer July 21, 2009

NCDOT s Performance Based Contracting Experience in Charlotte. Jennifer Brandenburg, PE State Road Maintenance Engineer July 21, 2009 NCDOT s Performance Based Contracting Experience in Charlotte Jennifer Brandenburg, PE State Road Maintenance Engineer July 21, 2009 Overview Performance Base Contracting in NC Project Scope Contract Development

More information

Traffic Division Public Works Department Anchorage: Performance. Value. Results.

Traffic Division Public Works Department Anchorage: Performance. Value. Results. Mission Promote safe and efficient area-wide transportation that meets the needs of the community and the Anchorage Municipal Traffic Code requirements. Direct Services Design, operate and maintain the

More information

Woking. q business confidence report

Woking. q business confidence report Woking q1 business confidence report Woking q1 report headlines saw a new record in company registrations in Woking when compared to any previous. was a record quarter for company registrations in Woking

More information

City of Deerfield Beach. Internal Logistics Management

City of Deerfield Beach. Internal Logistics Management City of Deerfield Beach Internal Logistics Management Internal Logistics Management Construction and Facilities Management Maintenance and repair of facilities. Management of design, construction, and

More information

da WESTERN SYDNEY AIRPORT INDUSTRY INFORMATION SESSION 5 December 2017

da WESTERN SYDNEY AIRPORT INDUSTRY INFORMATION SESSION 5 December 2017 da WESTERN SYDNEY AIRPORT INDUSTRY INFORMATION SESSION 5 December 2017 Graham Millett Executive General Manager Airport Infrastructure 2 Session agenda 1. Welcome and Acknowledgement of Country 2. Probity

More information

ACEC/MA Annual State Markets John Audi, PhD. Assistant Director

ACEC/MA Annual State Markets John Audi, PhD. Assistant Director ACEC/MA Annual State Markets 2019 John Audi, PhD. Assistant Director PROGRAM STRUCTURE Facility Program Project Project Status Funded Not Funded Complete All Work Complete All payments made Ongoing At

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee February 20, 2014 & Schedule Performance Summary Chart Slide # Project

More information

Project Risk Management Bootcamp. Contents are subject to change. For the latest updates visit

Project Risk Management Bootcamp. Contents are subject to change. For the latest updates visit Bootcamp Page 1 of 7 Why Attend The overall aim of this program is to enable participants to plan, manage and control project risks. Moreover, participants will be able to develop project risk management

More information

Technical Advisory Committee Meeting Minutes/Summary June 4, 2014

Technical Advisory Committee Meeting Minutes/Summary June 4, 2014 Technical Advisory Committee Meeting Minutes/Summary June 4, 2014 The third Technical Advisory Committee (TAC) Meeting for the Sustainable Airport Master Plan Update (MPU) was held on June 4th, 2014 at

More information

CILT Certified Procurement Professional. Contents are subject to change. For the latest updates visit

CILT Certified Procurement Professional. Contents are subject to change. For the latest updates visit CILT Certified Procurement Professional Page 1 of 7 Why Attend Procurement is at the heart of the supply chain function as the purchasing department can spend up to 70% of a company's money. In this course,

More information

Emissions Trading in China Progress on the Path towards a Unified National System

Emissions Trading in China Progress on the Path towards a Unified National System Emissions Trading in China PRESENTED BY Chen Zhibin SinoCarbon Feb. 2016 Bottom - Up ETS in China 1 Led by NDRC (National Reform and Development commission) One registry system ETS Development in China

More information

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted June 21, 2018

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted June 21, 2018 NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted June 21, 2018 The City of Atlanta is providing an opportunity for public comment until July 23, 2018 related to the

More information

GH Phipps Construction Co. OAC 17D Thistle-Valmont Square Interior & Exterior Renovation Thursday, November 2, :00 AM

GH Phipps Construction Co. OAC 17D Thistle-Valmont Square Interior & Exterior Renovation Thursday, November 2, :00 AM GH Phipps Construction Co. OAC 17D5780 - Thistle-Valmont Square Interior & Exterior Renovation Thursday, November 2, 2017 10:00 AM Meeting ID 003 Subject Weekly OAC Meetings Location 6000 Spine Rd #101,

More information

Ongoing and Future Project Work. Construction Management

Ongoing and Future Project Work. Construction Management Ongoing and Future Project Work New Broward County Courthouse Tower 1,000 Car Courthouse Garage Midrise Building Renovations 714,000 square foot, 20-story Civil/Family Courthouse replacing 1950 s era

More information

Rob Wigington President and CEO Juli H. Mosley, P.E. MNAA Board Chair Development and Engineering Robert Ramsey, P.E., A.A.E. Chief Engineer and Vice President of Development & Engineering Traci Holton,

More information

Port of Seattle IAF Overview

Port of Seattle IAF Overview Item No. 9a_supp Meeting Date: March 27, 2018 Port of Seattle IAF Overview March 27, 2018 Project Briefing Benefits of the IAF Construction Progress Photos Project Delivery Strategy Key IAF Project Initiatives

More information

Issued: July 23, Revised: December 16, 2013 July 5, 2014 June 29, 2015 February 7, 2016

Issued: July 23, Revised: December 16, 2013 July 5, 2014 June 29, 2015 February 7, 2016 Issued: July 23, 2013 Revised: December 16, 2013 July 5, 2014 June 29, 2015 February 7, 2016 Rev. 2 7 16 Supplier Guide Page 1 of 12 TABLE OF CONTENTS Who We Are Mission Statement Vision Statement Values

More information

Southport A Unique Perspective on P3s

Southport A Unique Perspective on P3s Southport A Unique Perspective on P3s 1 Snapshot in Time 2014-2015 Expansion Considerations Background Noise Container capacity peaking 3 rd time to market Time for a change of leadership No Plan Energy

More information

MBTA Contract R19PS03 Program Management/Construction Management Amendment Nos. 3 and 4

MBTA Contract R19PS03 Program Management/Construction Management Amendment Nos. 3 and 4 MBTA Contract R19PS03 Program Management/Construction Management Amendment Nos. 3 and 4 Red Line/Orange Line Improvements Program December 12, 2016 OVERVIEW Today s board action will allow the continuation

More information

NYSAWWA 2015 New York s Water Event April 14, 3015

NYSAWWA 2015 New York s Water Event April 14, 3015 Sustainability in Action: The Water-Energy Nexus Farrell Pumping Station Process and Energy Improvements Clay, New York NYSAWWA 2015 New York s Water Event April 14, 3015 To provide clean, safe, reliable,

More information

Public Workshop #9. October 11, 2016

Public Workshop #9. October 11, 2016 Public Workshop #9 October 11, 2016 Agenda Master Plan Status Preferred Alternative Environmental Considerations Vision 2040 Next Steps Master Plan Status Alternatives exploration and evaluation Environmental

More information

OVERALL & CONTRACT DBE GOAL METHODOLOGY. Goal Period FY /01/15 to 9/30/18 AIP Projects Overall DBE Goal: 2.

OVERALL & CONTRACT DBE GOAL METHODOLOGY. Goal Period FY /01/15 to 9/30/18 AIP Projects Overall DBE Goal: 2. OVERALL & CONTRACT GOAL METHODOLOGY Airport Sponsor City of Airport Name Boise Airport Goal Period FY 2016-2018 10/01/15 to 9/30/18 Projects AIP Projects-2016-2018 Name of Preparer John Anderson, T-O Engineers

More information

Welcome to the. Maryland Department of Transportation

Welcome to the. Maryland Department of Transportation Welcome to the Maryland Department of Transportation Maryland Aviation Administration OBJECTIVES Understanding the different procurement methods Highlight the key components of the bid process Common mistakes

More information

Certified Purchasing Professional. Contents are subject to change. For the latest updates visit

Certified Purchasing Professional. Contents are subject to change. For the latest updates visit Certified Purchasing Professional Page 1 of 7 Why Attend Purchasing is at the heart of the supply chain function as the purchasing department can spend up to 70% of a company's money. In this course, we

More information

Project Delivery Method

Project Delivery Method City Green - Project Delivery Method Roswell City Council Work Session September 14, 2016 Agenda Debrief on HPC Work Session Project Schedule Update Alternative Project Delivery Methods Discussion / Direction

More information