Cartersville-Bartow County Metropolitan Planning Organization. Long-Range Regional Transportation Plan Project Evaluation Process

Size: px
Start display at page:

Download "Cartersville-Bartow County Metropolitan Planning Organization. Long-Range Regional Transportation Plan Project Evaluation Process"

Transcription

1 Cartersville-Bartow County Metropolitan Planning Organization Long-Range Regional Transportation Plan Project Evaluation Process Joint Policy Committee & Transportation Coordinating Committee Meeting September 16, 2015

2 LRTP Development

3 LRTP Development Completed Goals & Objectives 2010 Socio-Economic Data Existing Conditions 2040 Socio-Economic Data Evaluation Methodology & Performance Measures Needs Assessment Project Evaluation Underway Draft Recommendations & Constrain Plan Upcoming 30-Day Public Comment Period - Jan 2016 LRTP Adoption - Feb 2016

4 Performance-Based Planning Evaluate Projects

5 Project-Level Evaluation Process E+C Collect Clean Up Evaluate Constrain Began with Existing + Committed network E+C evaluation Previous plans GDOT project database Local jurisdiction & MPO project nominations Overlaps Feasibility Completed Logical termini Utilized evaluation measures Projects grouped into tiers based on technical score Technical score/tier Cost Known support

6 Project-Level Evaluation Project evaluation measures link directly back to adopted goals and objectives Evaluated by project type: Roadway Capacity Roadway Operations, Maintenance & Safety Bicycle & Pedestrian Transit - no projects evaluated Projects placed into tiers based on overall score Technical evaluation was objective did not take into account constructability, political support/priorities or public support

7 Roadway Capacity Project-Level Evaluation GOAL/ OBJECTIVE G1A1 G1A2 G1C1 G1D1 G2B1 G2C1 G4A2 G4B1 G4C1 MEASURE Is the proposed project on or parallel to a facility with a poor LOS? Ratio of congested travel time to free flow travel time Is the proposed project on a NHS highway or a freight corridor identified in previous plans? Is the proposed project on a segment or an intersection with a high number of crashes, or are there a high number of injury and fatal crashes? Does the proposed project improve existing facilities between community resources? Does the proposed project come within 200 feet of national hydrography dataset, historic facilities/areas, or state parks. Population served by the proposed project Does the project connect to a state or national highway either directly or indirectly? Does the project match the goals and objectives of these plans? SCORING Difference in V/C ratio from 2040 no build. Top 33% - 3 points, 33-66% - 2 points, 0-33% - 1point Difference in VHD from 2040 no build. Top 33% - 3 points, 33-66% - 2 points Proposed project is on an NHS highway and freight corridor or potential freight corridor - 3 points, on the NHS or a freight corridor - 2 points, on neither - 1 point Proposed project is at or intersects high crash locations developed by Arcadis and CBMPO. Yes - 3 points, No - 1 point Project is within.5 mile of: city, Cartersville Medical Center, Avatron, LakePoint, Schools, Allatoona Resource Center, or North Bartow Community Services Center. >= 3-3 points, 2-2 points, <=1-1 point No potential impacts identified - 3 points, limited potential impacts (1) - 2 points, significant potential impacts (>=2) - 1 point. If the total population within 1 mile of the project in the top 1/3 rd - 3 points, middle 1/3 rd - 2 points, lowest 1/3 rd - 1 point. On a state or national highway - 3 points, 2 points for connecting with a state or national highway, 1 connection to facility that connects to it. Mostly - 3 points, somewhat - 2, points, not at all - 1 point.

8 Roadway Ops, Maint, Safety Project-Level Evaluation GOAL/ OBJECTIVE G1A1 G1A2 G1C1 G1D1 G2C1 G4A2 G4C1 MEASURE Is the proposed project on or parallel to a facility with a poor LOS? Ratio of congested travel time to free flow travel time Is the proposed project on a NHS highway or a freight corridor identified in previous plans? Is the proposed project on a segment or an intersection with a high number of crashes, or are there a high number of injury and fatal crashes? Does the proposed project come within 200 feet of national hydrography dataset, historic facilities/areas, or state parks. Population served by the proposed project Does the project match the goals and objectives of these plans? SCORING Proposed project is on or adjacent to a facility with (2040 No Build): LOS of F - 3 points, LOS E or D - 2 points, LOS C or better - 1 point. Is the ratio of congested to free flow travel time? >=3-3 points, between 2 and 3-2 points, 1 or less - 1 point Proposed project is on an NHS highway and freight corridor or potential freight corridor - 3 points, on the NHS or a freight corridor - 2 points, on neither - 1 point Proposed project is at or intersects high crash locations developed by Arcadis and CBMPO. Yes - 3 points, No - 1 point No potential impacts identified - 3 points, limited potential impacts (1) - 2 points, significant potential impacts (>=2) - 1 point. If the total population within 1 mile of the project in the top 1/3 rd - 3 points, middle 1/3 rd - 2 points, lowest 1/3 rd - 1 point. Mostly - 3 points, somewhat - 2, points, not at all - 1 point.

9 Bicycle & Pedestrian Project-Level Evaluation GOAL/ OBJECTIVE G1B1 G1D1 G2B1 G2C1 G4A2 G4C1 MEASURE Does the proposed project connect with any existing bike/ped trails or schools? Is the proposed project on a segment or an intersection with a high number of crashes, or are there a high number of injury and fatal crashes? Does the proposed project improve existing facilities between community resources? Does the proposed project come within 200 feet of national hydrography dataset, historic facilities/areas, or state parks. Population served by the proposed project Does the project match the goals and objectives of these plans? SCORING Does Bike/Ped project connect to current bike paths/trails, schools? >= 2-3 points, =1-2 points, =0-1 point Proposed project is at or intersects high crash locations developed by Arcadis and CBMPO. Yes - 3 points, No - 1 point Project is within. 5 mile of: city, Cartersville Medical Center, Avatron, LakePoint, Schools, Allatoona Resource Center, or North Bartow Community Services Center. >= 3-3 points, 2-2 points, <=1-1 point No potential impacts identified - 3 points, limited potential impacts (1) - 2 points, significant potential impacts (>=2) - 1 point. If the total population within 1 mile of the project in the top 1/3 rd - 3 points, middle 1/3 rd - 2 points, lowest 1/3 rd - 1 point. Mostly - 3 points, somewhat - 2, points, not at all - 1 point.

10 Constraining the LRTP ARCADIS developed preliminary draft recommendations based on: Objective technical evaluation Project costs Projected revenue Known support MPO staff then consulted with local jurisdictions and adjusted draft recommendations

11 Feedback & Questions

MPO Member Communities:

MPO Member Communities: MPO Member Communities: The MPO is federally required to update its long-range transportation plan every five years. Efforts are currently underway to develop a new plan: Mobilizing Tomorrow. Mobilizing

More information

Mobility and System Reliability Goal

Mobility and System Reliability Goal Mobility and System Reliability Goal Provide surface transportation infrastructure and services that will advance the efficient and reliable movement of people and goods throughout the state. Background:

More information

Livability 2050 Regional Transportation Plan Update. Transportation Policy Board (TPB) August 23, 2018

Livability 2050 Regional Transportation Plan Update. Transportation Policy Board (TPB) August 23, 2018 Livability 2050 Regional Transportation Plan Update Transportation Policy Board (TPB) August 23, 2018 1 Oct. 2017 Plan Kick-Off Sept. 2019 Plan Adoption Timeline Livability 2050 Regional Transportation

More information

Long Range Transportation Plan Project Status Update

Long Range Transportation Plan Project Status Update HEPMPO Webinar Meeting Long Range Transportation Plan Project Status Update Michael Baker Jr., Inc. Foursquare Integrated Transportation Planning December 4, 2013 1 Meeting Agenda 1. Project Overview 2.

More information

CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK

CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK MTP VISION In order to create a framework for the 2040 Metropolitan Transportation Plan (MTP), a vision statement was drafted by the Vision/Goals Committee and

More information

2040 Long Range Transportation Plan

2040 Long Range Transportation Plan 2040 Long Range Transportation Plan Presented by Iowa Northland Regional Council of Governments October 22, 23, and 24, 2013 Liaison for federal transportation funding that goes to local cities and counties

More information

Livability 2050 Regional Transportation Plan Update. RTPAC #4 October 16, 2018

Livability 2050 Regional Transportation Plan Update. RTPAC #4 October 16, 2018 Livability 2050 Regional Transportation Plan Update RTPAC #4 October 16, 2018 1 Meeting Agenda Timeline Financial Plan Update o Adopted Funding Scenario o Revenue Projections Prioritization Process Round

More information

PERFORMANCE-BASED PLANNING AND PROGRAMMING

PERFORMANCE-BASED PLANNING AND PROGRAMMING February 2017 performance-based planning and programming Boston Region MPO PERFORMANCE-BASED PLANNING AND PROGRAMMING WHAT IS PERFORMANCE-BASED PLANNING AND PROGRAMMING? Performance-based planning and

More information

PERFORMANCE-BASED PLANNING AND PROGRAMMING

PERFORMANCE-BASED PLANNING AND PROGRAMMING February 2017 performance-based planning and programming Boston Region MPO PERFORMANCE-BASED PLANNING AND PROGRAMMING WHAT IS PERFORMANCE-BASED PLANNING AND PROGRAMMING? Performance-based planning and

More information

Utilizing Transportation Data for Low Cost Safety Improvements

Utilizing Transportation Data for Low Cost Safety Improvements Utilizing Transportation Data for Low Cost Safety Improvements Samuel Sturtz Transportation Planner Iowa Department of Transportation samuel.sturtz@dot.iowa.gov Photo Credits: Ken West- Kenneth G. West

More information

Highway and Freight Current Investment Direction and Plan. TAC August 2, 2017

Highway and Freight Current Investment Direction and Plan. TAC August 2, 2017 Highway and Freight Current Investment Direction and Plan TAC August 2, 2017 Today s Topics Highway & Freight Where are we now? The Highway Story What are the issues? How is the system performing? Where

More information

Joint House and Senate Transportation Committee Update to the Ten Year Plan

Joint House and Senate Transportation Committee Update to the Ten Year Plan Joint House and Senate Transportation Committee 2019 Update to the Ten Year Plan Federal and State Funding Sources 2 AFY19 Budget Revenue Estimates 3 FY19 Federal & State Funds Federal Funds 38% State

More information

Safety Performance Management Targets. Transportation Policy Board January 11, 2018

Safety Performance Management Targets. Transportation Policy Board January 11, 2018 Safety Performance Management Targets Transportation Policy Board January 11, 218 Federal Requirements - Background MAP-21/FAST Act established new emphasis on performance and outcome based planning Required

More information

Appendix O Level of Service Standard and Measurements

Appendix O Level of Service Standard and Measurements July 8, 2016 Appendix O. Appendix O Standard and Measurements Definition Level of service (LOS) is a mechanism used to determine how well a transportation facility is operating from a traveler s perspective.

More information

TBARTA 2015 Regional Transportation Master Plan 2040 Regional Long Range Transportation Plan AUGUST 2015

TBARTA 2015 Regional Transportation Master Plan 2040 Regional Long Range Transportation Plan AUGUST 2015 TBARTA 2015 Regional Transportation Master Plan AUGUST 2015 Table of Contents 1.0 Introduction... 2 1.1 Updating the Master Plan... 2 1.2 About this Document... 2 2.0 Regional Long Range Transportation

More information

Winston-Salem Urban Area Metropolitan Planning Organization (WSUAMPO) Prioritization 3.0 Evaluation Criteria and Point Assignment Process

Winston-Salem Urban Area Metropolitan Planning Organization (WSUAMPO) Prioritization 3.0 Evaluation Criteria and Point Assignment Process The following methodology has been developed by the Winston-Salem Urban Area Metropolitan Planning Organization (WSUAMPO) for the purpose of determining priorities for transportation funding, as carried

More information

Contents i Contents Page 1 A New Transportation Plan Community Involvement Goals and Objectives... 11

Contents i Contents Page 1 A New Transportation Plan Community Involvement Goals and Objectives... 11 Contents i Contents 1 A New Transportation Plan... 1 Why develop a new plan?... 1 What area does the LRTP focus on?... 2 Why is this LRTP important?... 3 Meeting Requirements for Transportation Planning...

More information

1: INTRODUCTION AND PROCESS OVERVIEW

1: INTRODUCTION AND PROCESS OVERVIEW GPATS Long-Range Transportation Plan 1: INTRODUCTION AND PROCESS OVERVIEW INTRODUCTION affects everyone in many ways and plays a critical role in shaping a region s physical and social infrastructure.

More information

The following list of questions guided the stakeholder interview discussion:

The following list of questions guided the stakeholder interview discussion: Bartow County Transit Development Plan Stakeholder Interview Summary January 2017 Introduction The consultant team, in coordination with Bartow County Transit (BCT) and Cartersville-Bartow Metropolitan

More information

Long Range Transportation Plan

Long Range Transportation Plan Charlotte County-Punta Gorda Metropolitan Planning Organization Long Range Transportation Plan Adopted October 2015 Board Charlotte County Commissioner Christopher G. Constance (Chair) Commissioner Stephen

More information

MPO/RPO Briefings. MPO/RPO Briefing. Briefing Topics Plan framework o NCDOT Policy to Projects process o Relationship to local/regional plans

MPO/RPO Briefings. MPO/RPO Briefing. Briefing Topics Plan framework o NCDOT Policy to Projects process o Relationship to local/regional plans 7/7/2011 MPO/RPO Briefings July 2011 MPO/RPO Briefing Briefing Topics 1. 2040 Plan framework o NCDOT Policy to Projects process o Relationship to local/regional plans 2. Study process o Schedule o Public

More information

Charlottesville Albemarle MPO:

Charlottesville Albemarle MPO: Charlottesville Albemarle MPO: Applying The Eco-Logical Approach To Small MPOs September 21, 2015 Charlottesville Albemarle Metropolitan Planning Organization (CAMPO) and The Thomas Jefferson Planning

More information

CITY OF DEERFIELD BEACH SCOPE OF WORK

CITY OF DEERFIELD BEACH SCOPE OF WORK CITY OF DEERFIELD BEACH SCOPE OF WORK Deliverable 1: Data Compilation and Map Preparation 1.1: Recipient shall prepare a compendium of existing data and information necessary to produce the Complete Streets

More information

Sustainable Transportation Performance Measures

Sustainable Transportation Performance Measures Sustainable Transportation Performance Measures Christopher Forinash EPA Office of Sustainable Communities Conference on Performance Measures for Transportation and Livable Communities Austin, Texas 7

More information

Highway and Freight Current Investment Direction and Plan. TAB September 20, 2017

Highway and Freight Current Investment Direction and Plan. TAB September 20, 2017 Highway and Freight Current Investment Direction and Plan TAB September 20, 2017 Today s Topics Where are we now, what are the current issues? Where do we want to go? How will we get there? What are the

More information

2040 Addendum Performance-Based Planning November 2018

2040 Addendum Performance-Based Planning November 2018 2040 Long Range Transportation Plan 2040 Addendum Performance-Based Planning November 2018 Adopted June 13, 2018 250 S. Orange Ave, Suite 200, Orlando, FL 32801 407-481-5672 www.metroplanorlando.org MetroPlan

More information

Free Bridge Congestion Relief Project: Using FHWA s Eco-Logical Process

Free Bridge Congestion Relief Project: Using FHWA s Eco-Logical Process Free Bridge Congestion Relief Project: Using FHWA s Eco-Logical Process An Ecosystem Approach to Developing Infrastructure Projects June 27, 2014 Charlottesville Albemarle Metropolitan Planning Organization

More information

Winston-Salem Urban Area Metropolitan Planning Organization (WSMPO) Prioritization 4.0 Evaluation Criteria and Point Assignment Process

Winston-Salem Urban Area Metropolitan Planning Organization (WSMPO) Prioritization 4.0 Evaluation Criteria and Point Assignment Process The following methodology was developed by the Winston-Salem Urban Area Metropolitan Planning Organization (WSMPO) for the purpose of determining priorities for transportation funding, as carried out through

More information

Proposed Comprehensive Update to the State of Rhode Island s Congestion Management Process

Proposed Comprehensive Update to the State of Rhode Island s Congestion Management Process Proposed Comprehensive Update to the State of Rhode Island s Statewide Planning Program January 2018 Summary Outline of of Action Steps 1. Develop Objectives for Congestion Management What is the desired

More information

CITY OF JACKSONVILLE 2030 MOBILITY PLAN STUDY UPDATE GOALS, OBJECTIVES, AND PERFORMANCE MEASURES PREPARED FOR: CITY OF JACKSONVILLE

CITY OF JACKSONVILLE 2030 MOBILITY PLAN STUDY UPDATE GOALS, OBJECTIVES, AND PERFORMANCE MEASURES PREPARED FOR: CITY OF JACKSONVILLE CITY OF JACKSONVILLE 2030 MOBILITY PLAN STUDY UPDATE GOALS, OBJECTIVES, AND PERFORMANCE MEASURES 3.20.2017 PREPARED FOR: CITY OF JACKSONVILLE 55 Railroad Row White River Junction, VT 05001 802.295.4999

More information

Shoulder Widening Prioritization Discussion

Shoulder Widening Prioritization Discussion Shoulder Widening Prioritization Discussion Lindsey Bruer Planning Director March 2, 2018 District 8 ATP Meeting mndot.gov District 4 Shoulder Widening Study Evaluation Criteria: 3/8/2018 2 Evaluation

More information

Freight and Rail Stakeholder Webinar. January 7, 2014

Freight and Rail Stakeholder Webinar. January 7, 2014 Freight and Rail Stakeholder Webinar January 7, 2014 Agenda Modal Needs Baseline Revenue Modal Scenarios Website Statewide Freight Plan Statewide Rail Plan Jeff Carroll MULTIMODAL TRANSPORTATION NEEDS

More information

FHWA s Eco-Logical Process: Uses in Performance-Based planning

FHWA s Eco-Logical Process: Uses in Performance-Based planning FHWA s Eco-Logical Process: Uses in Performance-Based planning August 25, 2014 Charlottesville Albemarle Metropolitan Planning Organization (CAMPO) and The Thomas Jefferson Planning District Commission

More information

Congestion Management Process. Procedures and Responsibilities Report

Congestion Management Process. Procedures and Responsibilities Report Congestion Management Process Procedures and Responsibilities Report Durham-Chapel Hill-Carrboro Metropolitan Planning Organization June 2011 The Congestion Management Process Procedures and Responsibilities

More information

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement 2 Purpose and Need 2.1 Study Area Interstate 81 (I-81) is relied upon for local and regional travel and interstate travel in the eastern United States. It extends 855 miles from Tennessee to New York at

More information

MEETING SUMMARY FOR APRIL 13, 2017

MEETING SUMMARY FOR APRIL 13, 2017 SARASOTA/MANATEE METROPOLITAN PLANNING ORGANIZATION Performance Measures/Project Prioritization Process Ad Hoc Committee 7632 15 th Street East Sarasota, Florida 34243 3:00-5:00 PM MEETING SUMMARY FOR

More information

Florida Department of Transportation. Lane Elimination

Florida Department of Transportation. Lane Elimination Florida Department of Transportation Lane Elimination FDOT D6 Lane Elimination Review and Approval Process Developed to assure consistency in FDOT D6 s handling of the Lane Elimination Review and Approval

More information

Section 5: Performance-Based Planning

Section 5: Performance-Based Planning Section 5: Performance-Based Planning Mapping the Future: The Southwestern PA Plan establishes a performance-based foundation for regional transportation investment decisions consistent with MAP-21 1 guidance.

More information

APPENDIX A PLANNING PROCESS FOR RURAL AREAS OF THE STATE

APPENDIX A PLANNING PROCESS FOR RURAL AREAS OF THE STATE APPENDIX A PLANNING PROCESS FOR RURAL AREAS OF THE STATE Background SCDOT Statewide Transportation Planning Process Consultation Cooperation with Local Officials in Non-Metropolitan (Rural) Areas SCDOT

More information

Alternatives Evaluation Methodology

Alternatives Evaluation Methodology Alternatives Evaluation Methodology www.vision54 56.com B 1 Phase 2 Alternatives Evaluation Methodology PASCO COUNTY METROPOLITAN PLANNING ORGANIZATION 8731 Citizens Drive New Port Richey, FL 34654 Ph

More information

Tier 1 Recommendations October 30, 2017

Tier 1 Recommendations October 30, 2017 Tier 1 Recommendations October 30, 2017 Page Left Intentionally Blank Culpeper District C.2 C.3 Need Tier 1 District Needs Need Description Within the CA-MPO, regional Urban Development Areas (UDAs) and

More information

BRUNSWICK AREA TRANSPORTATION STUDY UNIFIED PLANNING WORK PROGRAM. For Fiscal Year July 1, 2014 through June 30, 2015

BRUNSWICK AREA TRANSPORTATION STUDY UNIFIED PLANNING WORK PROGRAM. For Fiscal Year July 1, 2014 through June 30, 2015 BRUNSWICK AREA TRANSPORTATION STUDY UNIFIED PLANNING WORK PROGRAM For Fiscal Year 2015 July 1, 2014 through June 30, 2015 Prepared by: Brunswick Area Transportation Study In Cooperation With: Georgia Department

More information

NORTH I-75 MASTER PLAN Summary Report

NORTH I-75 MASTER PLAN Summary Report NORTH I-75 MASTER PLAN Summary Report Interstate 75 (SR 93) From the Florida s Turnpike Interchange to the I-10 Interchange Alachua, Bradford, Clay, Citrus, Columbia, Duval, Levy, Marion, and Sumter Counties,

More information

Introduction. Performance Measurement. Pg. 01

Introduction. Performance Measurement. Pg. 01 Pg. 01 Introduction The Alamo Area recognizes the importance of transportation performance tracking, goal setting and measurement to provide greater accountability and transparency and to achieve a more

More information

Driveway Permits Following Guidelines PLANNING REQUIREMENTS CAPABILITIES ASSISTANCE ACCESS MANAGEMENT LAND USE CONTROLS ECONOMIC DEVELOPMENT

Driveway Permits Following Guidelines PLANNING REQUIREMENTS CAPABILITIES ASSISTANCE ACCESS MANAGEMENT LAND USE CONTROLS ECONOMIC DEVELOPMENT CHAPTER 5 Access Management PASSIVE Driveway Permits Following Guidelines Comprehensive Access Management PLANNING REQUIREMENTS Access Restrictions CAPABILITIES Process ASSISTANCE ACCESS MANAGEMENT LAND

More information

Transportation Improvement Program (TIP) Relationship to 2040 Metropolitan Transportation Plan (MTP) - Goals and Performance Measures

Transportation Improvement Program (TIP) Relationship to 2040 Metropolitan Transportation Plan (MTP) - Goals and Performance Measures Mid-Region Metropolitan Planning Organization Mid-Region Council of Governments 809 Copper Avenue NW Albuquerque, New Mexico 87102 (505) 247-1750-tel. (505) 247-1753-fax www.mrcog-nm.gov Transportation

More information

MONITORING IMPLEMENTATION AND PERFORMANCE

MONITORING IMPLEMENTATION AND PERFORMANCE 12 MONITORING IMPLEMENTATION AND PERFORMANCE The FAST Act continues the legislation authorized under MAP-21, which created a data-driven, performance-based multimodal program to address the many challenges

More information

Summary of transportation-related goals and objectives from existing regional plans

Summary of transportation-related goals and objectives from existing regional plans SMTC 2050 Long Range Transportation Plan Appendix A: Summary of transportation-related goals and objectives from existing regional plans SMTC 2050 Long Range Transportation Plan Summary of transportation-related

More information

INTERSTATE CORRIDOR PLANNING

INTERSTATE CORRIDOR PLANNING INTERSTATE CORRIDOR PLANNING Prioritization of Corridor Studies July 29, 2015 Importance of the Interstate System Texas is an integral part of the national interstate system. The interstate system provides

More information

Table of Contents. Visit our website for the most up-to-date information and downloadable documents at:

Table of Contents. Visit our website for the most up-to-date information and downloadable documents at: Table of Contents INTRODUCTION AND BACKGROUND... 1 COMMITTEES... 3 SECTION I: PROGRAM ADMINISTRATION... 4 1.1 MPO Administration... 4 1.2 Training/Professional Development... 5 1.3 Equipment/Supplies/Technical

More information

Optimizing Performance and Investment Decisions through Scenario Planning

Optimizing Performance and Investment Decisions through Scenario Planning Optimizing Performance and Investment Decisions through Scenario Planning OTEC 2016 70 Years of Innovation & Beyond Session 30 Columbus, Ohio October 25, 2016 Erin Dean, PE, AICP, Senior Consultant, High

More information

Regional Transportation Performance Measures

Regional Transportation Performance Measures Regional Transportation Performance Measures March 5, 2014 Presented by Tom Murtha Regional Transportation Performance 2 Measures: Introduction Regional Transportation Performance Measures address needs

More information

PINELLAS COUNTY MOBILITY PLAN SUMMARY REPORT

PINELLAS COUNTY MOBILITY PLAN SUMMARY REPORT PINELLAS COUNTY MOBILITY PLAN SUMMARY REPORT In September, 2013, the Pinellas County Mobility Plan Report was approved by the Metropolitan Planning Organization (MPO). This action endorsed a countywide

More information

Performance Dashboard

Performance Dashboard Unified Corridor Investment Study Performance Dashboard Step 2 Analysis Results DRAFT Revised 10/15/18 October 2018 Project Description Three parallel routes - Highway 1, Soquel/Freedom and the Santa Cruz

More information

Funding Intelligent Transportation Systems in the Los Angeles Region

Funding Intelligent Transportation Systems in the Los Angeles Region Funding Intelligent Transportation Systems in the Los Angeles Region 2017 ITS California Annual Meeting Ed Alegre, PTP Los Angeles County Metropolitan Transportation Authority (Metro) Los Angeles Region

More information

TTAC STAFF REPORT. State Targets for the MAP-21/FAST Act National Highway Performance Program. MEETING DATE: August 2, 2018 AGENDA ITEM: 5

TTAC STAFF REPORT. State Targets for the MAP-21/FAST Act National Highway Performance Program. MEETING DATE: August 2, 2018 AGENDA ITEM: 5 TTAC STAFF REPORT SUBJECT: State Targets for the MAP-21/FAST Act National Highway Performance Program MEETING DATE: August 2, 2018 AGENDA ITEM: 5 STAFF CONTACT: Andrew Orfila, Jared Carvalho RECOMMENDATION:

More information

There are two (2) amendments for which staff is requesting recommendation to the Transportation Policy Council this month:

There are two (2) amendments for which staff is requesting recommendation to the Transportation Policy Council this month: TAC Agenda Item 6A Mailout 02/08/19 RECOMMENDATION FOR TRANSPORTATION POLICY (TPC) APPROVAL OF AMENDMENTS TO THE 20192022 TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AND 2040 REGIONAL TRANSPORTATION PLAN

More information

Presentation Six February 2012

Presentation Six February 2012 Presentation Six February 2012 Today s Presentation: Revenue Recap Project Prioritization Process DRAFT 2040 Project List Revenue Estimation Based on data provided by each state Includes transit formula

More information

SBCAG STAFF REPORT. MAP-21/FAST Act Performance Measures and Targets. MEETING DATE: September 20, 2018 AGENDA ITEM: 4H

SBCAG STAFF REPORT. MAP-21/FAST Act Performance Measures and Targets. MEETING DATE: September 20, 2018 AGENDA ITEM: 4H SBCAG STAFF REPORT SUBJECT: MAP-21/FAST Act Performance Measures and Targets MEETING DATE: September 20, 2018 AGENDA ITEM: 4H STAFF CONTACT: Andrew Orfila, Jared Carvalho RECOMMENDATION: Approve and accept

More information

CHAPTER 1: INTRODUCTION/ GOALS AND OBJECTIVES

CHAPTER 1: INTRODUCTION/ GOALS AND OBJECTIVES CHAPTER 1: INTRODUCTION/ GOALS AND OBJECTIVES 1.1: INTRODUCTION ABOUT THE FREDERICKSBURG AREA METROPOLITAN PLANNING ORGANIZATION (FAMPO) Established in 1992, the Fredericksburg Area Metropolitan Planning

More information

Chapter 3 - Goals, Objectives, & Strategies

Chapter 3 - Goals, Objectives, & Strategies Chapter 3 - This chapter presents goals, objectives, and strategies that have been developed as part of the Richmond Area MPO 2026 Long-Range Transportation Plan (LRTP) update. Strategies have been developed

More information

Des Moines Area MPO. MPO Planning Subcommittee Meeting March 3, Des M oines Area M etropolitan Planning Organization

Des Moines Area MPO. MPO Planning Subcommittee Meeting March 3, Des M oines Area M etropolitan Planning Organization Des Moines Area MPO MPO Planning Subcommittee Meeting March 3, 2014 2014 Des M oines Area M etropolitan Planning Organization Agenda 1. Call To Order 2. VOTE: Approval of Agenda 3. VOTE: Approval of Meeting

More information

RE Request for FY 2018 UPWP Budget Adjustments

RE Request for FY 2018 UPWP Budget Adjustments November 30, 2017 William Eastin Southeast Georgia Branch Chief GDOT Office of Planning 600 W. Peachtree St. NW, 5th Floor Atlanta, GA 30308 RE Request for FY 2018 UPWP Budget Adjustments Dear Mr. Easton:

More information

What is the Dakota County Principal Arterial Study?

What is the Dakota County Principal Arterial Study? What is the Dakota County Principal Arterial Study? The Dakota County is underway and will address future designations of certain highways as Principal Arterials. What Are Principal Arterials? Principal

More information

Performance Dashboard

Performance Dashboard Unified Corridor Investment Study Performance Dashboard Step 2 Analysis Results DRAFT Revised 11/08/18 October 2018 Project Description Three parallel routes - Highway 1, Soquel/Freedom and the Santa Cruz

More information

Project Evaluation Criteria

Project Evaluation Criteria Project Evaluation Criteria Goals and Objectives were developed to guide Envision 35 Long Range Transportation Plan (LRTP) Update. These guiding principles were based on the requirements included in the

More information

Indianapolis MPO. Transportation Improvement Program Project Selection Criteria

Indianapolis MPO. Transportation Improvement Program Project Selection Criteria Indianapolis MPO Transportation Improvement Program Project Selection Criteria May, 2018 The Indianapolis MPO receives and administers an annual allocation of federal funds totaling roughly $47 million

More information

MADISON ATHENS-CLARKE OCONEE REGIONAL TRANSPORTATION STUDY UNIFIED PLANNING WORK PROGRAM FY

MADISON ATHENS-CLARKE OCONEE REGIONAL TRANSPORTATION STUDY UNIFIED PLANNING WORK PROGRAM FY MADISON ATHENS-CLARKE OCONEE REGIONAL TRANSPORTATION STUDY UNIFIED PLANNING WORK PROGRAM FY - 2018 Final April 12, 2017 Amended November 8, 2017 Prepared by: Athens-Clarke County Planning Department In

More information

Performance Planning Target Setting Procedures

Performance Planning Target Setting Procedures Performance Planning Target Setting Procedures Version: 1.1 Effective Date: November 29, 2017 Contact: Bobbi Retzlaff, Office of Transportation System Management, MPO Coordinator; bobbi.retzlaff@state.mn.us;

More information

Presentation to DATA on VTrans 2040 / HB2. October 21, 2015

Presentation to DATA on VTrans 2040 / HB2. October 21, 2015 Presentation to DATA on VTrans 2040 / HB2 October 21, 2015 Life Cycle of a Candidate Project How it s planned. How it s scored. How it s funded. 2 How it s planned. VTrans2040 VTRANS 2040 serves two functions,

More information

PERFORMANCE-BASED PLANNING AND PROGRAMMING

PERFORMANCE-BASED PLANNING AND PROGRAMMING September 2018 performance-based planning and programming Boston Region Metropolitan Planning Organization: PERFORMANCE-BASED PLANNING AND PROGRAMMING WHAT IS PERFORMANCE-BASED PLANNING AND PROGRAMMING?

More information

CHARTING PROGRESS TO 2040 RESULTS OF MINI-SURVEYS

CHARTING PROGRESS TO 2040 RESULTS OF MINI-SURVEYS CHARTING PROGRESS TO RESULTS OF MINI-SURVEYS A series of mini-surveys was released between May and July, to collect input on investment strategies for Charting Progress to, the Boston Region s long-range

More information

Recommended Roadway Plan Section 3 Existing Facilities & System Performance

Recommended Roadway Plan Section 3 Existing Facilities & System Performance Recommended Roadway Plan Section 3 Existing Facilities & System Performance RECOMMENDED ROADWAY PLAN SECTION 3 Existing Facilities and System Performance 3.1 Introduction An important prerequisite to transportation

More information

Chapter 12: Transportation Safety & Security CHARLOTTE COUNTY PUNTA GORDA MPO 2035 LONG RANGE TRANSPORTATION PLAN

Chapter 12: Transportation Safety & Security CHARLOTTE COUNTY PUNTA GORDA MPO 2035 LONG RANGE TRANSPORTATION PLAN Chapter 12: Transportation Safety & Security CHARLOTTE COUNTY PUNTA GORDA MPO 2035 LONG RANGE TRANSPORTATION PLAN CHARLOTTE COUNTY PUNTA GORDA MPO 2035 LONG RANGE TRANSPORTATION PLAN Transportation Safety

More information

2040 Transportation Policy Plan Conversion to Performance Based Planning Basis. 25 th Annual CTS Transportation Research Conference May 21, 2014

2040 Transportation Policy Plan Conversion to Performance Based Planning Basis. 25 th Annual CTS Transportation Research Conference May 21, 2014 2040 Transportation Policy Plan Conversion to Performance Based Planning Basis 25 th Annual CTS Transportation Research Conference May 21, 2014 1 About the plan Long-range transportation plan for the Twin

More information

RESOLUTION NO

RESOLUTION NO RESOLUTION NO. 2018-12 RESOLUTION OF THE SOUTHEASTERN WISCONSIN REGIONAL PLANNING COMMISSION AMENDING THE TRANSPORTATION IMPROVEMENT PROGRAM FOR SOUTHEASTERN WISCONSIN: 2017-2020 WHEREAS, the Southeastern

More information

Interstate and Strategic Corridor Plans. January 9, :30 AM

Interstate and Strategic Corridor Plans. January 9, :30 AM Interstate and Strategic Corridor Plans January 9, 2014 9:30 AM Agenda Modal Needs Baseline Revenue Modal Scenarios Website Interstate Plan Strategic Corridor Plan Jeff Carroll MULTIMODAL TRANSPORTATION

More information

Appendix O Congestion Management Program REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY

Appendix O Congestion Management Program REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY Appendix O Congestion Management Program REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY 2014 REGIONAL CONGESTION MANAGEMENT PROGRAM 2014 RTP/SCS APPENDIX O SAN JOAQUIN COUNCIL OF GOVERNMENTS

More information

CHAPTER 8. Congestion Management

CHAPTER 8. Congestion Management CHAPTER 8 Congestion Management CHAPTER 8: Congestion Management The CMP is a management system and process conducted to improve traffic operations and safety through operational improvements and strategies

More information

FDOT PROJECT INFORMATION APPLICATION FORM

FDOT PROJECT INFORMATION APPLICATION FORM THIS FORM SHALL BE SUBMITTED FOR ALL PROJECTS NOT CURRENTLY IN THE FDOT WORK PROGRAM. FDOT PROJECT INFORMATION APPLICATION FORM DATE: APPLICANT: FDOT LIAISON: 1. MPO/TPO Project Priority Number: 2. Contact

More information

Unified Corridor Investment Study Performance Dashboard

Unified Corridor Investment Study Performance Dashboard Unified Corridor Investment Study Performance Dashboard October 2018 Project Description Three parallel routes - Highway 1, Soquel/Freedom and the Santa Cruz Branch Rail Line - link the communities along

More information

HORIZON 2030: Plan Projects November 2005

HORIZON 2030: Plan Projects November 2005 Horizon PROJECTS 2030 Projects 10-1 10-2 The Horizon 2030 Project Information section is comprised of individual project information in alphabetical order by project name. The information provided for

More information

3.0 REVIEW OF PREVIOUS STUDIES

3.0 REVIEW OF PREVIOUS STUDIES 3.0 REVIEW OF PREVIOUS STUDIES This section of the highlights the significant features from previous plans and studies that could impact the development of the I-20 East Transit Initiative. Much of the

More information

Congestion Management Process 2013 Update

Congestion Management Process 2013 Update OVERVIEW OF THE DALLAS-FORT WORTH CONGESTION MANAGEMENT PROCESS Traffic Congestion In The Dallas-Fort Worth Region With the Dallas-Fort Worth (DFW) urban area as its center, the North Central Texas region

More information

Table Table 7.2 Potential Environmental Impacts and Mitigation Measures

Table Table 7.2 Potential Environmental Impacts and Mitigation Measures 7.2 Natural Environment/Environmental Planning Executive Summary/Key Points The Environmental Consultation and Mitigation Plan establishes: o A process for consultation with environmental resource agencies

More information

Sarasota/Manatee Metropolitan Planning Organization. Performance Targets/Project Priorities Process September 2018

Sarasota/Manatee Metropolitan Planning Organization. Performance Targets/Project Priorities Process September 2018 Sarasota/Manatee Metropolitan Planning Organization Performance Targets/Project Priorities Process September 2018 Performance Target Setting Timeline February November February 27 14 27 2018 2018 2019

More information

Incorporating Health in Regional Transportation Planning

Incorporating Health in Regional Transportation Planning Mayor Karl Dean, Chairman Incorporating Health in Regional Transportation Planning Leslie A. Meehan, AICP Tennessee Public Health Association Conference September 15, 2011 Metropolitan Planning Organizations

More information

Pasco County MPO: Congestion Management Process PROCEDURES HANDBOOK

Pasco County MPO: Congestion Management Process PROCEDURES HANDBOOK : Congestion Management Process PROCEDURES HANDBOOK Final: March 2016 TABLE OF CONTENTS CONGESTION MANAGEMENT PROCEDURES HANDBOOK OVERVIEW... i Chapter 1: INTRODUCTION... 1-1 Causes of Congestion... 1-2

More information

BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT FOR EXISTING AND PLANNED SECTIONS OF US 19

BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT FOR EXISTING AND PLANNED SECTIONS OF US 19 BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT FOR EISTING AND PLANNED SECTIONS OF US 19 September 2015 A JOINT EFFORT OF THE PINELLAS METROPOLITAN PLANNING ORGANIZATION AND THE FLORIDA DEPARTMENT

More information

Regional Transit System Plan

Regional Transit System Plan Policy, Program Development & Intergovernmental Relations Committee Item III-A October 14, 2010 Regional Transit System Plan Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

MOBILITY AND ALTERNATIVES ANALYSIS

MOBILITY AND ALTERNATIVES ANALYSIS 6 MOBILITY AND ALTERNATIVES ANALYSIS BACK OF SECTION DIVIDER 6.0 Mobility and Alternatives Analysis Travel demand analysis provides a framework for the identification of transportation facilities and services

More information

2004 FEASIBILITY STUDY UPDATE

2004 FEASIBILITY STUDY UPDATE Austin-San Antonio Intermunicipal Commuter Rail District 2004 FEASIBILITY STUDY UPDATE December 2004 EXECUTIVE SUMMARY INTRODUCTION Almost 3 million people in Central Texas, living and working between

More information

Alameda Countywide Transportation Plan Update Evaluation Outcomes

Alameda Countywide Transportation Plan Update Evaluation Outcomes TAWG Meeting 07/14/11 Attachment 06 Handout Alameda Countywide Transportation Plan Update Evaluation Outcomes presented to Technical Advisory Working Group presented by Cambridge Systematics, Inc. July

More information

SMART SCALE Technical Guide

SMART SCALE Technical Guide prepared for Commonwealth Transportation Board date REVISED November 13, 2017 Table of Contents 1.0 Introduction... 1 1.1 SMART SCALE Legislation Requirements... 2 Funding Programs... 2 1.2 Roles and Responsibilities...

More information

University of Virginia Master Planning Committee November 17 th Charlottesville Albemarle Metropolitan Planning Organization

University of Virginia Master Planning Committee November 17 th Charlottesville Albemarle Metropolitan Planning Organization University of Virginia Master Planning Committee November 17 th 2010 Charlottesville Albemarle Metropolitan Planning Organization 1 Who are we? What is an MPO A Metropolitan Planning Organization is a

More information

Corridor Modernization

Corridor Modernization Corridor Modernization 2013 Transportation Engineering Safety Conference December 13, 2013 Agenda Introduction to Corridor Modernization (CM) Goals, Objectives, Strategies, Tactics (GOST) Performance Metrics

More information

Webinar Series for Comprehensive Plan Updates. Transportation Overview

Webinar Series for Comprehensive Plan Updates. Transportation Overview Webinar Series for Comprehensive Plan Updates Transportation Overview Presented by Michael Larson and Mark Filipi August 18, 2016 2040 Transportation Policy Plan Adopted January 14 th, 2015 Multimodal

More information

Overview of Changes Made to CMAQ & System Performance Measures. Presented by: Jason Pavluchuk Association for Commuter Transportation

Overview of Changes Made to CMAQ & System Performance Measures. Presented by: Jason Pavluchuk Association for Commuter Transportation Overview of Changes Made to CMAQ & System Performance Measures Presented by: Jason Pavluchuk Association for Commuter Transportation Agenda CMAQ Overview Changes Made by FAST ACT 2013 Guidance Performance

More information

IDOT PERFORMANCE BASED PROJECT METRICS. February 2018

IDOT PERFORMANCE BASED PROJECT METRICS. February 2018 IDOT PERFORMANCE BASED PROJECT METRICS February 2018 March 5, 2018 2 What is Performance Management? Performance Management of the Federal Highway Program is a systematic approach to making investment

More information

Traffic. Community Planning and Development. Traffic Administration Traffic Engineering. Paint and Signs

Traffic. Community Planning and Development. Traffic Administration Traffic Engineering. Paint and Signs Community Planning and Development Administration 101-7710 Transportation Planning 101-7720 Engineering Paint and Signs 141-7750 Communications 101-7740 Data 141-7760 Signals 141-7770 Safety and Signals

More information