Jacksonville Port Authority Blount Island Marine Terminal Rail Improvements Jacksonville, Florida

Size: px
Start display at page:

Download "Jacksonville Port Authority Blount Island Marine Terminal Rail Improvements Jacksonville, Florida"

Transcription

1 Jacksonville Port Authority Blount Island Marine Terminal Rail Improvements Jacksonville, Florida By: Bryan K. Haye, Senior Project Manager; Michael J. Shostak, P.E., Vice President; and Clinton C. Lalla, P.E., Senior Project Manager HDR Engineering, Inc. 200 West Forsyth Street, Suite 800 Jacksonville, FL, Phone: Fax: Words ABSTRACT The Jacksonville Port Authority (JAXPORT) operates three major marine terminals in Jacksonville, Florida. JAXPORT retained HDR Engineering, Inc. in 2010 to develop a plan for rail infrastructure improvements for their 754-acre Blount Island Marine Terminal (BIMT). BIMT serves roll-on/roll-off, breakbulk, liquid bulk and heavy lift cargos, along with extensive vehicle import/export activities. JAXPORT owns the BIMT track facilities and CSX Transportation (CSXT) provides rail service. Based on HDR s recommendations, JAXPORT was able to secure a grant from the U.S. Department of Commerce to pay for the cost of the improvements. Approximately 19,800 feet of track and 19 turnouts were upgraded from 100# jointed rail on wood ties to 115# welded rail on steel ties. The steel ties are expected to provide a service life of over 20 years. A total of 25 road crossings were upgraded, including six crossings with heavy truck traffic using concrete platform ( tub ) crossings which consist of a large precast concrete slab placed on a prepared crushed concrete roadbed with the rail recessed into and directly fixed to the concrete slab. HDR evaluated various options to replace the rail and fasteners on an existing 1545 concrete deck bridge over the St. John River. The existing fasteners were replaced with larger plates bolted directly to the deck with new clips to provide a more efficient system with a larger bearing surface. The project was completed in October 2012 at a total cost of approximately $7.7 Million. 248

2 INTRODUCTION JAXPORT owns and operates three marine cargo terminals, one passenger cruise terminal, and an automobile ferry terminal in Jacksonville, Florida. JAXPORT markets these publicly-owned facilities to promote the growth of maritime and related industries in Jacksonville and beyond. The port s efforts have generated growth in container volume and total cargo. During 2012, JAXPORT s three terminals handled 923,000 twenty-foot equivalent units (TEUs) and moved a total of approximately 8.2 million tons of cargo. That cargo included 608,000 vehicles which makes JAXPORT the No. 2 vehicle-handling port in the United States. As JAXPORT s largest marine facility, the BIMT plays an important role in the local and regional economies. The 754-acre site serves roll-on/roll-off, break-bulk, liquid bulk and heavy lift cargos and ranks among the top vehicle import/export centers in the country. Ensuring that rail operations at the BIMT keep pace with freight demands is vital to maintaining the facility s advantage in a competitive port industry. HDR worked with CSXT and JAXPORT to develop a plan for rail improvements that will help keep JAXPORT s rail traffic running smoothly for decades to come. JAXPORT s Blount Island Spur connects to CSXT s Dames Point Spur approximately two miles north of the BIMT. The Blount Island Spur was constructed during the early 1960s to serve the wharf and warehouses on the BIMT. Over the years, the facility s rail infrastructure expanded to include two loop tracks in the warehouse area, an additional spur and a number of support yards for loading and unloading automobiles, heavy equipment, military hardware and other materials. While JAXPORT owns the Dames Point Spur and trackage at the BIMT, CSXT has historically maintained the spur, and in 2008, CSXT asked HDR to evaluate BIMT s rail infrastructure. HDR looked at existing conditions and the extent of past modifications to determine what improvements were needed. The investigation revealed that the rail infrastructure at the facility had reached the point where simply performing maintenance was not adequate. It was time for a capital rebuilding program. Figures 1 and 2 show the extent of the improvements. As a result of HDR s study for CSXT, JAXPORT successfully pursued funding assistance from the U.S. Department of Commerce. A $6 million grant was awarded to JAXPORT in the fall of The grant stipulated that all rail improvements must provide for a 20-year service life with minimal maintenance. In 2010, HDR was awarded a General Engineering Contract (GEC) with JAXPORT. JAXPORT asked HDR to prepare a revised report and conceptual plans to include materials and construction requirements necessary to conform to the grant requirements. To increase the service life of the rehabilitated track, HDR recommended replacing the existing concrete and wood ties with steel ties for much of the BIMT s two main segments. The steel ties will provide a service life of over 20 years and offer some advantages in terms of sustainability. In addition to being fabricated from recycled material, the ties will retain salvage value by being recyclable again at the end of their service life. Welded new 115# rail was used for all new steel tie track construction. 249

3 Borate-treated wood ties were used in an area along a mile-long segment that had previously been relocated to make room for Jacksonville Electric Authority s (JEA) St. Johns River Power Park. The 100# welded rail in this segment was in good condition and, along with a proper ballast section and accommodations for drainage, the borate ties will provide the specified service life. Some sections of track were not included in the rehabilitation project. Much of the track on the wharf has not been used for some time, and the track along the wharf has since become part of a separate major wharf renovation project. The 20-year service specification factored in to the design for the repair work for the 1545 long single track rail bridge crossing the St. Johns River. The existing bridge is a concrete structure that was originally constructed with the rail directly fixed to the concrete deck using clips and a single bolt on each side of the rail, with a spacing between clips of about 23 to 30 inches. HDR s original recommendations for the bridge were based on a maintenance approach and included replacing broken bolts and tightening any loose nuts. This strategy clearly would not be sufficient to meet the 20-year service life requirements established by the federal grant. For the revised plan, consideration was given to converting the structure to a ballast deck by adding curbs along the edges of the bridge. The space between the curbs would be filled with ballast, and steel tie track could then be constructed across the bridge without direct fixation to the deck. However, the load rating of the bridge would not permit this type of modification which would have added significant dead load to the structure. As an alternative, Pandrol SRS plates were used to replace all the aging clips. The Pandrol plates still were bolted directly to the deck, but they provide a better clipping system and a much larger bearing surface for the rail and the bridge deck. Figure 3 shows the typical layout for drilling new holes to accommodate the new plates. The extended service requirement also factored significantly in the specifications for atgrade rail/highway crossings. Of the 25 road crossings within the rail system, six were identified as having heavy traffic both in numbers and tonnage. To provide a heavy-duty surface that would last a minimum of 20 years, HDR specified concrete platform tub crossing surfaces for these crossings. A tub crossing consists of a large concrete slab placed on a prepared crushed concrete roadbed. The rail is recessed into and directly fixed to the concrete slab with rubber flange-way material inserted between the rail and the concrete. This type of surface provides a longer service life than standard concrete or rubber surfaces due to its mass and installation. The panels used for the BIMT Island are 20 feet long and 18 inches deep. Figure 4 shows a typical tub section. By contrast, standard full width concrete crossing panels are about 8 feet long and are no deeper than the rail size used; these concrete panels are lagged directly to the wooden ties and are subject to the dynamics of the track expanding and moving under the stresses of traffic. The tub crossing is a more rigid surface, making it an ideal choice for the more heavily used crossings in this project. Proper subgrade compaction is critical for the proper installation of a tub crossing system. For the more lightly used crossings, reconstruction was done with a rubber flange-way material and asphalt paving. PHASING THE WORK In addition to stipulating a 20-year service life, the federal grant also imposed a deadline for commencement of construction. HDR recommended dividing construction into two phases. 250

4 Phase 1 consisted of about two miles of track and the St. Johns River bridge rehabilitation work outside of the BIMT s secured terminal area. Phase 2 encompassed everything inside the secured area. HDR developed the Phase 1 bid documents, and then completed the Phase 2 bid documents while the Phase 1 work was underway. Atlas Railroad Construction began work on Phase 1 in April The Phase 1 work was basically a single track main line rehabilitation project on the Dames Point Spur. Borate-treated wood ties were installed in about 4874 feet of track that had previously been relocated for the JEA power plant; the existing 100# welded rail was retained in this section. For the remainder of the track work included in Phase 1 new 115# rail in 80 lengths was welded into strings using a portable arc welder and then used for the new steel tie track construction. The clip and rail replacement for the Saint Johns River Bridge as well as the replacement of two tub crossings and two rubber flange-way/asphalt crossings rounded out the Phase 1 work. Figure 5 shows the Saint Johns River bridge with new plates and clips. Obtaining track time to do the Phase 1 work was relatively simple. CSXT typically delivered an inbound train to the BIMT in the early morning hours. Switching at the BIMT facility itself was generally done during the daytime, and the outbound train would return north along the Dames Point Spur in late afternoon. This allowed the Phase 1 Contractor to take advantage of eight to 10 hour track outages during daylight hours to do the main line track work. The Phase 1 work was completed in October Southern National Track (SNT) began the Phase 2 work in October The Phase 2 worked proved to be much more challenging to execute on several fronts. SNT was not permitted to leave their equipment within the BIMT secured area overnight. Hence SNT had to ferry equipment and personnel every day from a staging area outside the BIMT. SNT s workers had to either obtain Transportation Worker Identification Credential (TWIC) cards and JAXPORT identification cards, or they were escorted by workers that possessed these documents. CSXT would typically switch the BIMT facility during daylight hours. Switching needs for the various JAXPORT customers is very dependent on schedules for ocean vessels. Hence the switching requirements were not able to be developed well in advance. SNT was able to construct track panels and assemble turnouts clear of active track. Track outages for actually installing these track components were available only at night and on weekends. Scheduling road crossing closures for renewal also proved to be challenging. In addition to truck traffic, considerable traffic is generated from automobiles that are unloaded from railcars that are in transit from staging areas to vessels. Many of the high volume crossings were not able to be closed for extended periods of time. Figure 6 shows a tub crossing and turnout with steel ties. The Phase 2 work was completed in October Beginning in January 2013, track maintenance responsibility was shifted from CSXT to JAXPORT. 251

5 CONCLUSIONS The track and bridge rehabilitation at the JAXPORT BIMT facility was completed in October 2012 at a total cost of approximately $7.7 Million. JAXPORT will benefit from reduced future maintenance costs since the rehabilitated track and bridge components will provide a service life of at least 20 years. The use of federal grant money required the use of materials with a long service life and presented challenges for how the design and construction were staged. In a very competitive business environment, JAXPORT will be able to depend on a reliable upgraded rail infrastructure system for years to come. 252

6 253

7 254

8 255

9 256

10 FIGURE 5: JOHNS RIVER BRIIDGE SHOWING NEW PLATES AND CLIPS FIGURE 6: TYPICAL STEEL TIE TURNOUT AND TUB CROSSING 257

11 Jacksonville Port Authority Blount Island Marine Terminal Rail Improvements Jacksonville, FL Michael Shostak, PE Vice President Clinton Lalla, PE - Sr. Project Manager HDR Engineering, Inc. 258

12 JAXPORT FACTS Three Marine Terminals One Cruise Terminal Mayport Ferry 2012 Statistics 923,000 TEU s 8.2 million tons of cargo 608,000 Autos: 2nd largest in U.S. BLOUNT ISLAND MARINE TERMINAL 754 Acre Site Roll-on/roll- off, break-bulk, liquid bulk and heavy lift cargos Significant auto import/export activities Extensive rail infrastructure constructed in 1960 s BLOUNT ISLAND MARINE TERMINAL RAIL REHABILITATION Served via CSX Transportation Blount Island Spur 2008 Assessment Determined Capital Upgrades Needed vs. Routine Maintenance Jaxport Awarded $6 Million Dept. of Commerce Grant in Fall Year Service Life Required Work Done in 2 Separate Phases BLOUNT ISLAND MARINE TERMINAL - BEFORE RAIL REHABILITATION Interlaced Wood and Concrete Ties BLOUNT ISLAND MARINE TERMINAL - BEFORE RAIL REHABILITATION BLOUNT ISLAND MARINE TERMINAL - BEFORE RAIL REHABILITATION 1545 Bridge Over St. Johns River Main Lead to Right off Bridge 259

13 BLOUNT ISLAND MARINE TERMINAL - BEFORE RAIL REHABILITATION BLOUNT ISLAND MARINE TERMINAL - BEFORE RAIL REHABILITATION Deteriorated Crossing Typical Track and Turnout Condition BLOUNT ISLAND MARINE TERMINAL - BEFORE RAIL REHABILITATION BIMT RAIL REHABILITATION PHASE 1 Phase 1 work outside Jaxport secured area 2300 Track Feet wood tie replacement 2500 Track Feet total replacement with steel ties and 115# rail 2 tub type crossings Typical Auto Unloading Pad Condition BIMT RAIL REHABILITATION PHASE 1 BIMT RAIL REHABILITATION PHASE 1 Bridge rail fasteners replaced Scheduled work during week around CSXT trains Construction completed in October

14 BIMT RAIL REHABILITATION PHASE 1 BIMT RAIL REHABILITATION PHASE 1 Steel Tie Track Panel Steel Tie Track Panel In Place BIMT RAIL REHABILITATION PHASE 1 BIMT RAIL REHABILITATION PHASE 1 Steel Tie Track Construction Switch to USMC Base BIMT RAIL REHABILITATION PHASE 1 BIMT RAIL REHABILITATION PHASE 1 Rail Fasteners on Bridge Completed Rail Fasteners on Bridge 261

15 Phase 2 work inside Jaxport secured area 15,000 track feet replacement with steel ties and 115# rail 24-#10 steel tie turnouts 4 tub type crossings Weekend work to minimize train conflicts Work completed in October rubber flangeway and asphalt crossings Tub Under Construction Completed Tub Type Crossing 262 Steel Tie Track Under Construction

16 Typical Steel Tie Track Auto Unloading Pad Steel Tie Turnout Ready for Installation Steel Tie Turnout Installed BIMT RAIL REHABILITATION SUMMARY Reduced Track Maintenance Durable Grade Crossing Surfaces Bridge Rail and Fasteners Upgraded 20 Year Service Life Total Construction Cost $7.7 Million Turnouts and Crossings 263

17 BIMT RAIL REHABILITATION SUMMARY Questions? 264

Select U.S. Ports Prepare For Panama Canal Expansion

Select U.S. Ports Prepare For Panama Canal Expansion Select U.S. Ports Prepare For Panama Canal Expansion Port of Jacksonville Grace Wang Associate Professor, Maritime Administration Texas A&M University at Galveston Galveston, Texas Anthony M. Pagano Director,

More information

BLACK RIVER RAILROAD SYSTEM 2015 TRACK STANDARDS & SPECIFICATIONS

BLACK RIVER RAILROAD SYSTEM 2015 TRACK STANDARDS & SPECIFICATIONS WOOD TIES 2015 TRACK STANDARDS & SPECIFICATIONS FOR NEW CONSTRUCTION & UPGRADES Ties shall be new 7"x 9" x 8' 6" creosoted grade hardwood. All new ties shall be spiked with four (4) new spikes and box

More information

Sieve Size 2" 1" 3/8" No. 10 No. 40 No. 200 % Passing Size

Sieve Size 2 1 3/8 No. 10 No. 40 No. 200 % Passing Size VII. MATERIALS 7.01 SUBBALLAST Subballast shall be crusher-run stone (dense graded aggregate), preferably limestone or granite material and shall meet the requirements as set out in Chapter 1, Part 2,

More information

Supply Chain Management Summit August 23, 2012

Supply Chain Management Summit August 23, 2012 Supply Chain Management Summit August 23, 2012 Steven J. King, P.E. Managing Director Quonset Business Park 3,207 Total Acres 168 Companies 8,800 Jobs Transportation Facilities Freight Seaport: 2 piers

More information

Norfolk Southern s Online Rebuild of the Coosa River Bridge

Norfolk Southern s Online Rebuild of the Coosa River Bridge Norfolk Southern s Online Rebuild of the Coosa River Bridge Author: Harold Hal E. Lewis, PE, Vice President, HDR Engineering, Inc. 200 West Forsyth Street, Suite 800, Jacksonville, Florida 32202 Telephone:

More information

Please Do Not Copy or Distribute. Visit: for all the latest updates!

Please Do Not Copy or Distribute. Visit:   for all the latest updates! Please Do Not Copy or Distribute Visit: www.nears.org for all the latest updates! The Port of Baltimore The Maryland Port Administration NEARS North East Association of Rail Shippers April 2013 Over 300

More information

1.133 M.Eng. Concepts of Engineering Practice Fall 2007

1.133 M.Eng. Concepts of Engineering Practice Fall 2007 MIT OpenCourseWare http://ocw.mit.edu 1.133 M.Eng. Concepts of Engineering Practice Fall 2007 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Notes on

More information

Kevin Abt Chief Engineer Virginia Port Authority

Kevin Abt Chief Engineer Virginia Port Authority Capital Outlay Program & Facilities Maintenance Overview Board of Commissioners Session 354 September 24, 2013 Kevin Abt Chief Engineer Virginia Port Authority Agenda VPA Projects NIT Gate Improvements

More information

JACKSONVILLE HARBOR DEEPENING MAYOR S TASK FORCE

JACKSONVILLE HARBOR DEEPENING MAYOR S TASK FORCE JACKSONVILLE HARBOR DEEPENING MAYOR S TASK FORCE Presented by: Colonel Alan Dodd Jacksonville District, U.S. Army Corps of Engineers August 7, 2014 47-foot Deepening 2.7 BCR Total Federal Cost: $ 312.7

More information

NorthPort Logistics Center New Berlin Rd Jacksonville, FL 32226

NorthPort Logistics Center New Berlin Rd Jacksonville, FL 32226 NorthPort Logistics Center 11530 New Berlin Rd Jacksonville, FL 32226 ±306,611 SF Warehouse and Distribution Space - FOR LEASE As exclusive agents, we are pleased to offer Florida s largest contiguous

More information

Suggested Guidelines for Hot Mix Asphalt (HMA) Underlayment in Track by AREMA Committee l-sub Committee No. 2 - Ballast.

Suggested Guidelines for Hot Mix Asphalt (HMA) Underlayment in Track by AREMA Committee l-sub Committee No. 2 - Ballast. Suggested Guidelines for Hot Mix Asphalt (HMA) Underlayment in Track by AREMA Committee l-sub Committee No. 2 - Ballast OVERVIEW June 11, 1998 The purpose of these Suggested Guidelines is to provide 1)

More information

SECTION TIMBER FLOATS

SECTION TIMBER FLOATS SECTION 06210 PART 1 - GENERAL 1.01 SUMMARY A. This section covers furnishing and installing the timber float framing for the pile guide area, and all other components not specifically mentioned, necessary

More information

Port Authority of Guam

Port Authority of Guam Port Authority of Guam An Inside Look at the Port Authority of Guam Presented to the: United Nations Economic & Social Commission for Asia and the Pacific High Level Meeting on Strengthening Inter- Island

More information

The work required for this project includes, but is not limited to, the following items, not listed in order of execution.

The work required for this project includes, but is not limited to, the following items, not listed in order of execution. ESTIMATE OF QUANTITIES SPECIFICATIONS Construction Specifications: South Dakota Standard Specifications for Roads and Bridges, 2004 Edition and Required Provisions, Supplemental Specifications and/or Special

More information

TEXAS PORTS STRATEGIC MISSION PLAN & PORT CAPITAL PROGRAM. November 16, 2016 November Transportation Commission Workshop November 16, 2016

TEXAS PORTS STRATEGIC MISSION PLAN & PORT CAPITAL PROGRAM. November 16, 2016 November Transportation Commission Workshop November 16, 2016 TEXAS PORTS STRATEGIC MISSION PLAN & PORT CAPITAL PROGRAM November 16, 2016 Texas Ports Strategic Mission Plan Section 55.007 of the Texas Transportation Code requires the Port Authority Advisory Committee

More information

ENGINEERED SOLUTIONS. Contech Bridge Plank

ENGINEERED SOLUTIONS. Contech Bridge Plank ENGINEERED SOLUTIONS Contech Bridge Plank Contech Bridge Plank for Rehabilitation Make unsound bridges safe with Contech Bridge Plank Every state is faced with the problem of replacing old bridges. In

More information

NC State Ports Authority. 21 st Century Transportation Intermodal Committee February 21, 2008 NC State Ports Authority Tom Eagar, CEO

NC State Ports Authority. 21 st Century Transportation Intermodal Committee February 21, 2008 NC State Ports Authority Tom Eagar, CEO NC State Ports Authority 21 st Century Transportation Intermodal Committee February 21, 2008 NC State Ports Authority Tom Eagar, CEO NC State Ports Authority Facts at a Glance 2 Enterprise agency unique

More information

DIVISION 34 TRANSPORTATION SECTION SPECIAL TRACKWORK ADDENDUM NO. 1

DIVISION 34 TRANSPORTATION SECTION SPECIAL TRACKWORK ADDENDUM NO. 1 PART 1 - GENERAL 1.01 RELATED WORK SPECIFIED ELSEWHERE A. The provisions and intent of the Contract, including the General Conditions and General Requirements, apply to this work as if specified in this

More information

Paying For Port Security. HAL HUDGINS Vice President, Planning and Security Alabama State Port Authority

Paying For Port Security. HAL HUDGINS Vice President, Planning and Security Alabama State Port Authority Paying For Port Security HAL HUDGINS Vice President, Planning and Security Alabama State Port Authority July 28, 2005 The Alabama State Port Authority A Public Corporation Wholly-Owned By The State Created

More information

December 2, Enclosed is Addendum No. 1 to SEPTA's Sealed Bid No AMJP Frazer Shop & Yard Expansion Contract 2 (Re-Bid GC).

December 2, Enclosed is Addendum No. 1 to SEPTA's Sealed Bid No AMJP Frazer Shop & Yard Expansion Contract 2 (Re-Bid GC). December 2, 2016 Dear Sir/Madam Enclosed is Addendum No. 1 to SEPTA's Sealed Bid No. 16-00249-AMJP Frazer Shop & Yard Expansion Contract 2 (Re-Bid GC). The bid opening date and time scheduled for Wednesday,

More information

Steel Railway Bridge Fatigue and the Evolution of Railway Car Loadings

Steel Railway Bridge Fatigue and the Evolution of Railway Car Loadings 1 Steel Railway Bridge Fatigue and the Evolution of Railway Car Loadings The Current State and Future Challenges of Railway Bridges Stephen M. Dick, PE, SE, Ph.D. Hanson Professional Services 2 Discussion

More information

BNSF North SIG Intermodal Improvement Project. Seattle, Washington

BNSF North SIG Intermodal Improvement Project. Seattle, Washington BNSF North SIG Intermodal Improvement Project Seattle, Washington By Charles E. Burnham, P.E. David Evans and Associates, Inc. Trans-Pacific Trade Center Building 3700 Pacific Highway East, Suite 311 Tacoma,

More information

METRO RESPONSE TO PROSPECTIVE BIDDERS QUESTIONS

METRO RESPONSE TO PROSPECTIVE BIDDERS QUESTIONS METRO RESPONSE TO PROSPECTIVE BIDDERS QUESTIONS Wednesday, October 31, 2018 Solicitation No. 4018000193 ROC / Redline Tie Replacement, Drainage & Subgrade Improvements 1. Will the Thickness of Sub ballast

More information

Rail Freight and Passenger

Rail Freight and Passenger Take Care of the System Critical Investments in the areas of: Rail Freight rehabilitate rail bridges o Rail Bridge Inventory Database... $0.5 - $1.0 million (one time) Rail Freight rail replacement and

More information

America s Central Port is the St. Louis region s only full-service, public intermodal port. The 1,200-acre mixed-use business campus offers

America s Central Port is the St. Louis region s only full-service, public intermodal port. The 1,200-acre mixed-use business campus offers America s Central Port is the St. Louis region s only full-service, public intermodal port. The 1,200-acre mixed-use business campus offers development-ready industrial sites, over 1.7 million square feet

More information

3.0 TEMPORARY DETOUR BRIDGES

3.0 TEMPORARY DETOUR BRIDGES 3.0 TEMPORARY DETOUR BRIDGES Table of Contents 3.1 General...1 3.2 STORAGE SITES:...2 3.3 BID ITEMS:...2 3.4 INDEX OF PLAN SHEETS with H-Pile:...3 3.5 INVENTORY SHEET FOR DETOUR BRIDGES WITH H-PILE:...4

More information

New Jersey Department of Transportation. Local Freight Impact Fund Handbook. Procedures and Criteria for Local Freight Impact Fund Grant Program

New Jersey Department of Transportation. Local Freight Impact Fund Handbook. Procedures and Criteria for Local Freight Impact Fund Grant Program New Jersey Department of Transportation Local Freight Impact Fund Handbook Procedures and Criteria for Local Freight Impact Fund Grant Program Page 1 of 10 Overview The New Jersey Department of Transportation

More information

UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management)

UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management) UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management) DESIGN PHASE PROJECTS BCT - Building Program Development and Design for Maintenance and Administration

More information

NORTHPORT LOGISTICS CENTER New Berlin Road Jacksonville, Florida 32226

NORTHPORT LOGISTICS CENTER New Berlin Road Jacksonville, Florida 32226 11530 New Berlin Road Jacksonville, Florida 32226 FOR FOR LEASE LEASE ALTA RD NORTHPORT LOGISTICS FAYE RD 9-A NEW BERLIN RD PROPOSED HANJIN MITSUI 9-A HECKSCHER DR JAXPORT BLOUNT ISLAND TERMINAL 872,627

More information

USE OF HIGH PERFORMANCE STEEL IN TEXAS BRIDGES

USE OF HIGH PERFORMANCE STEEL IN TEXAS BRIDGES David P. Hohmann, P.E., and John M. Holt, P.E. 1 USE OF HIGH PERFORMANCE STEEL IN TEXAS BRIDGES Submission Date: July 31, 2002 Word Count: 2529 David P. Hohmann, P.E. Director, Bridge Design Branch Bridge

More information

3 August 13, 2014 Public Hearing

3 August 13, 2014 Public Hearing 3 August 13, 2014 Public Hearing APPLICANT: PAUL BRADLEY / BRADLEY MARINE, L.L.C. PROPERTY OWNER: CILOU L.L.C. REQUEST: Conditional Use Permit (boat and vessel repair and bulk storage yard) ADDRESS / DESCRIPTION:

More information

Commercial Ties. Cost Effective Solutions for Mainline Track Applications

Commercial Ties. Cost Effective Solutions for Mainline Track Applications Commercial Ties Cost Effective Solutions for Mainline Track Applications Cost Effective Solutions for Mainline Track From the Leader in Pre-stressed Concrete Crossties The Rocla Concrete Tie Advantage

More information

CONTAINERS AND BEYOND Derrick Smith AAPA Spring Conference - March 18, 2013

CONTAINERS AND BEYOND Derrick Smith AAPA Spring Conference - March 18, 2013 CONTAINERS AND BEYOND Derrick Smith AAPA Spring Conference - March 18, 2013 1 What are some of the major trends that are occurring? Increased cargo Significant investments Greater rail usage 2 Many economic

More information

CITY OF TACOMA Tacoma Rail

CITY OF TACOMA Tacoma Rail CITY OF TACOMA Tacoma Rail ADDENDUM NO. 2 DATE: May 11, 2015 REVISIONS TO: Request for Bids Specification No.: TR15-0215F SR-509 TRACK UPGRADES NOTICE TO ALL BIDDERS: This addendum is issued to clarify,

More information

2009 Ohio Conference on Freight

2009 Ohio Conference on Freight 2009 Ohio Conference on Freight September 22, 2009 Hilton Toledo Inn The State of Ohio is an Equal Opportunity Employer and Provider of ADA Services. Mark Barbash Assistant Director and Chief Economic

More information

JOB BB0903 HWY. 71B INTCHNG. IMPVTS. (S) JULY 25, 2018

JOB BB0903 HWY. 71B INTCHNG. IMPVTS. (S) JULY 25, 2018 JOB BB0903 HWY. 71B INTCHNG. IMPVTS. (S) JULY 25, 2018 On Maintenance of Traffic Details Sheet No. 46 there is a note that states I-49 Stage Construction is to be Completed Prior to Beginning Work on Hwy.

More information

STATEWIDE PORTS NEEDS AND MARKETING ASSESSMENT. Port of Amory

STATEWIDE PORTS NEEDS AND MARKETING ASSESSMENT. Port of Amory STATEWIDE PORTS NEEDS AND MARKETING ASSESSMENT Port of Amory OCTOBER, 2014 PORT OF AMORY CONTENTS 3. Port of Amory 3-1 3.1. Location 3-1 3.2. Port Land and Facilities 3-5 3.3. Port Services 3-7 3.4. Typical

More information

Rail Service at Brookley Aeroplex

Rail Service at Brookley Aeroplex WHAT The Mobile Airport Authority, hopes to attain improved rail infrastructure to advance economic performance and job growth. I. Background The Mobile Airport Authority s goal for Brookley Aeroplex is

More information

Notice of Tariff Change Effective January 1, 2014

Notice of Tariff Change Effective January 1, 2014 Notice of Tariff Change Effective January 1, 2014 Port of Seattle Terminals Tariff No. 5 is revised as follows: RATE CHANGES: ITEM 1460 SMALL LOTS FEE A charge of $116.09 increased from $114.33 will be

More information

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure ArchCast Bridge 3-Sided Precast Concrete Bridge Structure Installation Manual Salem Location: 749 West Commercial Ave. Salem, IL 62881 (618) 548-1190 countymaterials.com Email: info@countymaterials.com

More information

Fort Street M-85 Bascule Bridge Looking to the Past to Build Bridge for the Future

Fort Street M-85 Bascule Bridge Looking to the Past to Build Bridge for the Future Fort Street M-85 Bascule Bridge Looking to the Past to Build Bridge for the Future Richard A. Wianecki, PE, Hardesty & Hanover, Okemos, MI Jane Abadir, PE, LEED A P, SOMAT Engineering Detroit, MI Rouge

More information

WHERE GREEN JOBS GROW ON LAND AND WATER THE PORT OF COEYMANS P&M BRICK LLC

WHERE GREEN JOBS GROW ON LAND AND WATER THE PORT OF COEYMANS P&M BRICK LLC WHERE GREEN JOBS GROW ON LAND AND WATER THE PORT OF COEYMANS P&M BRICK LLC A GREEN FACILITY HISTORY The property was formerly a brick manufacturing plant. The plant closed in December 2001 displacing approximately

More information

BOARD OF TRUSTEES OF THE GALVESTON WHARVES Tariff Circular No. 6

BOARD OF TRUSTEES OF THE GALVESTON WHARVES Tariff Circular No. 6 1 st Revised Page 29 ISSUED: MAY 24, 2002 EFFECTIVE: JULY 1, 2002 LOADING AND UNLOADING SERVICES (C) 505 The service of loading and unloading rail cars and motor trucks is performed by freight handlers

More information

Light Duty Ramps. Loadingdocksupply.com PHONE:

Light Duty Ramps. Loadingdocksupply.com PHONE: Light Duty Ramps Light Duty Aluminum Dockplates Designed for use by pallet trucks, carts, and foot traffic the A & B model Aluminum Dockplate is lightweight and portable. Accomodates differentials up to

More information

SECTION PRECAST CONCRETE PAVERS AND PEDESTAL LOK DOWN SYSTEM

SECTION PRECAST CONCRETE PAVERS AND PEDESTAL LOK DOWN SYSTEM SECTION 07555 PRECAST CONCRETE PAVERS AND PEDESTAL LOK DOWN SYSTEM PART ONE: GENERAL 1.1 SUMMARY A. Concrete paver and pedestal support system with Lok Down devices are to be placed over roofing/waterproofing

More information

Port of New Bedford. AAPA Commissioners Seminar May 17, 2011 Prosperity through Economic Development Opportunities

Port of New Bedford. AAPA Commissioners Seminar May 17, 2011 Prosperity through Economic Development Opportunities Port of New Bedford AAPA Commissioners Seminar May 17, 2011 Prosperity through Economic Development Opportunities Port of New Bedford, Massachusetts Niche Port You are here Connected to Global Markets

More information

BOARD OF TRUSTEES OF THE GALVESTON WHARVES Tariff Circular No. 6

BOARD OF TRUSTEES OF THE GALVESTON WHARVES Tariff Circular No. 6 1 st Revised Page 29 ISSUED: MAY 24, 2002 EFFECTIVE: JULY 1, 2002 LOADING AND UNLOADING SERVICES (C) 505 The service of loading and unloading rail cars and motor trucks is performed by freight handlers

More information

Fiber Reinforced Polymer (FRP) Panels for Rail Station Platforms

Fiber Reinforced Polymer (FRP) Panels for Rail Station Platforms Fiber Reinforced Polymer (FRP) Panels for Rail Station Platforms Introduction Scott Reeve, President, Composite Advantage Dayton, Ohio Engineered Solutions and Products for Infrastructure Large parts High

More information

Multi-Fab sells to registered dealers only; however, we can assist in finding you a dealer.

Multi-Fab sells to registered dealers only; however, we can assist in finding you a dealer. ATTACHMENTS This term refers to implements that can be added to a fork truck for handling a load. Attachments such as clamps, slip sheet forks and carpet poles can have an effect on capacity and should

More information

PortMiami Rail Intermodal and Bascule Bridge Rehabilitation Project TIGER II Grant

PortMiami Rail Intermodal and Bascule Bridge Rehabilitation Project TIGER II Grant PortMiami Rail Intermodal and Bascule Bridge Rehabilitation Project TIGER II Grant Quick Facts PortMiami is located in Miami-Dade County, one of the most diverse, multilingual populations in the U.S. making

More information

St. Bernard Port, Harbor & Terminal District

St. Bernard Port, Harbor & Terminal District St. Bernard Port, Harbor & Terminal District 2017 REPORT THE COURSE AHEAD It is an honor, privilege and a great responsibility to be the next executive director of the St. Bernard Port. I humbly would

More information

JAXPORT Overview. JAXPORT Dealing with Legacy Contamination Issues

JAXPORT Overview. JAXPORT Dealing with Legacy Contamination Issues JAXPORT Overview JAXPORT Dealing with Legacy Contamination Issues Scott Skinner JAXPORT Manager, Environmental Compliance Planning and Properties Department November 15, 2011 1 JAXPORT Facilities Dredge

More information

Instructions for 12 and 15 IGT systems (12 pictured)

Instructions for 12 and 15 IGT systems (12 pictured) Instructions for 12 and 15 IGT systems (12 pictured) Step 1: IGT Site Preparation Site Location Several factors must be considered when choosing the site for your new In-Ground Trampoline (IGT) system.

More information

BOARD OF TRUSTEES OF THE GALVESTON WHARVES Tariff Circular No. 6

BOARD OF TRUSTEES OF THE GALVESTON WHARVES Tariff Circular No. 6 1 st Revised Page 29 ISSUED: MAY 24, 2002 EFFECTIVE: JULY 1, 2002 LOADING AND UNLOADING SERVICES (C) 505 The service of loading and unloading rail cars and motor trucks is performed by freight handlers

More information

Addendum 2 Electrical Clarifications. 1. Drawing E2: Delete typical detail references: 3. Drawing E2: Add detail reference at pole A 7: 2 P age

Addendum 2 Electrical Clarifications. 1. Drawing E2: Delete typical detail references: 3. Drawing E2: Add detail reference at pole A 7: 2 P age Addendum 2 Electrical Clarifications 1. Drawing E2: Delete typical detail references: 2. Drawing E2: Add detail reference at pole A 4: 3. Drawing E2: Add detail reference at pole A 7: 2 P age 4. Drawing

More information

NEW JERSEY DEPARTMENT OF TRANSPORTATION. New Jersey Statewide Strategic Freight Rail Plan

NEW JERSEY DEPARTMENT OF TRANSPORTATION. New Jersey Statewide Strategic Freight Rail Plan NEW JERSEY DEPARTMENT OF TRANSPORTATION New Jersey Statewide Strategic Freight Rail Plan OVER-ARCHING PROJECT PURPOSE In short, the plan is intended to: Identify Issues That Constrain Freight Rail Operations

More information

Raised Basement. Mechanical Installation Guide

Raised Basement. Mechanical Installation Guide R Raised Basement Mechanical Installation Guide Ensure masonry work is correct. If recessed, the depth must be 14 inches deep unless otherwise specified for a custom application. Width and length may vary

More information

Rehabilitation of the Blue Ridge Parkway with FDR and AC Overlay. Michael Walters FHWA EFLHD October 7, 2014

Rehabilitation of the Blue Ridge Parkway with FDR and AC Overlay. Michael Walters FHWA EFLHD October 7, 2014 Rehabilitation of the Blue Ridge Parkway with FDR and AC Overlay Michael Walters FHWA EFLHD October 7, 2014 HISTORY Existing pavement on Parkway very deteriorated Repair options were heavy patching and

More information

Mi l l er Pac i fic E N G I N E ERI NG GR O UP 504 Redwood B l vd. Suite 220 Novato, Ca l i f o rnia 94947

Mi l l er Pac i fic E N G I N E ERI NG GR O UP 504 Redwood B l vd. Suite 220 Novato, Ca l i f o rnia 94947 April 8, 2010 File: 739-17bltr.doc CSW/Stuber-Stroeh Engineering Group 45 Leveroni Court Novato, CA 94949 Mi l l er Pac i fic E N G I N E ERI NG GR O UP 504 Redwood B l vd. Suite 220 Novato, Ca l i f o

More information

Intermodal Transportation of Spent Nuclear Fuel from Office of Civilian Radioactive Waste Management Sites 9328

Intermodal Transportation of Spent Nuclear Fuel from Office of Civilian Radioactive Waste Management Sites 9328 Intermodal Transportation of Spent Nuclear Fuel from Office of Civilian Radioactive Waste Management Sites 9328 ABSTRACT Stephen Schmid Bechtel-SAIC Company, LLC Washington, DC Alexander Thrower U.S. DOE,

More information

Pavement Design. TTP Orientation Seminar 2013

Pavement Design. TTP Orientation Seminar 2013 Pavement Design TTP Orientation Seminar 2013 What are Pavements? Engineered structures in contact with the earth's surface built to facilitate movement of people and goods Pedestrians Personal vehicles

More information

Initial Report on the Possibility of a Freight Ferry Service Between Martha s Vineyard and New Bedford. August 10, 2017

Initial Report on the Possibility of a Freight Ferry Service Between Martha s Vineyard and New Bedford. August 10, 2017 Initial Report on the Possibility of a Freight Ferry Service Between Martha s Vineyard and New Bedford August 10, 2017 Flagship Management was hired to further investigate the possibility of a Freight

More information

ZG Scope. 2 Applicable Documents. 3 General. 4 Stock Item Numbers. Padvault Single-Phase Residential, 2.1 PacifiCorp Material Specifications

ZG Scope. 2 Applicable Documents. 3 General. 4 Stock Item Numbers. Padvault Single-Phase Residential, 2.1 PacifiCorp Material Specifications 1 Scope This specification outlines the minimum requirements for a 48 48 padvault for single-phase primary service. Single-phase transformers and sectionalizers (elbow switched cabinets) can be mounted

More information

The NEW New York, Susquehanna and Western Railway. NEARS - Providence, RI - April 30,

The NEW New York, Susquehanna and Western Railway. NEARS - Providence, RI - April 30, The NEW New York, Susquehanna and Western Railway NEARS - Providence, RI - April 30, 2014 1 The NYS&W has been serving the Northeast since 1889 but is today, in many ways, a new railroad. We have taken

More information

DECEMBER 5, 2017 AT 2:00 P.M. (EASTERN TIME) (Estimated Cost: $5,000,000) Bids

DECEMBER 5, 2017 AT 2:00 P.M. (EASTERN TIME) (Estimated Cost: $5,000,000) Bids General Info Number: PROJECT NO. 43-17-04 : BRIDGE DECK REPAIR AND BRIDGE REMOVAL OHIO TURNPIKE OVER QUARRY ROAD, M.P. 138.0 OHIO TURNPIKE OVER INACTIVE RAILROAD, M.P. 138.2 LORAIN COUNTY, OHIO Deadline:

More information

CREATE: Benefits to U.S. Seaports. American Association of Port Authorities Maritime Economic Development Workshop

CREATE: Benefits to U.S. Seaports. American Association of Port Authorities Maritime Economic Development Workshop CREATE: Benefits to U.S. Seaports American Association of Port Authorities Maritime Economic Development Workshop June 27, 2013 CREATE Partners Chicago Terminal Operation and Railroad Daily Activity: 1,300

More information

Mechanical Loading Dock Levelers

Mechanical Loading Dock Levelers Mechanical Loading Dock Levelers With over 30 years of experience manufacturing quality loading dock equipment, Pentalift is your single-source supplier for loading dock levelers, dock lifts, dock seals

More information

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company James P. Hyland Page 1 ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING Kansas City Terminal Railway Company James P. Hyland, P.E. Senior Bridge Engineer TranSystems Corporation James P. Hyland Page 2

More information

COAST LINE CONNECTOR. Facilities Redevelopment Port Commerce Department

COAST LINE CONNECTOR. Facilities Redevelopment Port Commerce Department Title of Project: Name of Applicant: Contact & Job Title: STATEN ISLAND RAILROAD: CHEMICAL COAST LINE CONNECTOR Port Authority of New York and New Jersey Rudy Israel, General Manager Waterways & Facilities

More information

CONSTRUCTION SPECIFICATION FOR GUIDE RAIL ENERGY ABSORBING TERMINALS

CONSTRUCTION SPECIFICATION FOR GUIDE RAIL ENERGY ABSORBING TERMINALS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 554 NOVEMBER 1989 CONSTRUCTION SPECIFICATION FOR GUIDE RAIL ENERGY ABSORBING TERMINALS 554.01 SCOPE 554.02 REFERENCES 554.05 MATERIALS 554.05.01 Concrete.02

More information

Safe, innovative, quality construction since Riding on the Strength

Safe, innovative, quality construction since Riding on the Strength Safe, innovative, quality construction since 1880 Riding on the Strength of EXPERIENCE The Expertise The Experience The People The Equipment The Work Ethic The quality To get your job done safely, on time

More information

Construction Project Briefing. November 14, 2012

Construction Project Briefing. November 14, 2012 Construction Project Briefing November 14, 2012 Today s Presentation Loop Track Purple Line Viaducts North Red Line Stations 2 Project Title: Loop Track Renewal Project Managing Department: Power & Way

More information

Reinforced Earth wall Construction Manual

Reinforced Earth wall Construction Manual COVER PAGE CT-PE-W02 Rev: 5 Reinforced Earth wall Construction Manual Concrete Facing Reinforced Earth Malaysia Sdn Bhd 80-1, Jalan 8/62A Bandar Menjalara 52200 Kuala Lumpur Tel : 03-62746162, Fax : 03-62747212

More information

2017 Facilities Engineering Awards: Design and Construction of Marine Structures. Title of Project Mississippi River Intermodal Terminal Improvements

2017 Facilities Engineering Awards: Design and Construction of Marine Structures. Title of Project Mississippi River Intermodal Terminal Improvements 2017 Facilities Engineering Awards: Design and Construction of Marine Structures Title of Project Mississippi River Intermodal Terminal Improvements Name of Applicant Port of New Orleans Contact Brandy

More information

Switches and Crossings

Switches and Crossings Switches and Crossings Synopsis This document sets out general requirements for the design, inspection and maintenance of switches and crossings (S&C). It also defines particular requirements for fixed

More information

Louisiana Ports: The Industry that Drives all Others. Presented By: Paul G. Aucoin Executive Director, Port of South Louisiana

Louisiana Ports: The Industry that Drives all Others. Presented By: Paul G. Aucoin Executive Director, Port of South Louisiana Louisiana Ports: The Industry that Drives all Others Presented By: Paul G. Aucoin Executive Director, Port of South Louisiana Ports Impact Every Region of LA 1. Central Louisiana Regional Port 2. Avoyelles

More information

Northeast Bridge Preservation Partnership Meeting

Northeast Bridge Preservation Partnership Meeting Northeast Bridge Preservation Partnership Meeting Superstructure Preservation Strategies Aetna Viaduct Superstructure Repairs Route I-84 City of Hartford, CT State Project No. 63-648 David A. Cutler, P.E.

More information

Re: Participation of the Vancouver Fraser Port Authority in Orientation Session #2 for the Roberts Bank Terminal 2 Project Environmental Assessment

Re: Participation of the Vancouver Fraser Port Authority in Orientation Session #2 for the Roberts Bank Terminal 2 Project Environmental Assessment M,;\ PORT of ~~1 vancouver Vancouver Fraser Port Authority 100 The Pointe, 999 Canada Place Vancouver, B.C. Canada V6C 3T 4 portvancouver.com September 9, 2016 Jocelyne Beaudet Chair, Review Panel Roberts

More information

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc. Grade Separation Systems Single-Span Rail Bridge Construction Procedure An innovation from art engineering inc. GSS Single-Span Example Shown: An existing railroad grade crossing. Existing railroad Existing

More information

Passenger/Freight Railroad Projects in Michigan

Passenger/Freight Railroad Projects in Michigan Passenger/Freight Railroad Projects in Michigan Passenger/Freight Railroad Projects in Michigan Topics: Michigan Railroad Network State of Michigan Owned Railroad Corridors Michigan Accelerated Rail Program

More information

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE 412.1 OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA BURLINGTON NORTHERN AND SANTA FE RAILWAY By: John W. Hronek

More information

STRAIL - installation instructions. Subject to technical changes / December STRAIL level crossing systems & STRAILastic track damping systems

STRAIL - installation instructions. Subject to technical changes / December STRAIL level crossing systems & STRAILastic track damping systems STRAIL - installation instructions Subject to technical changes / December 2009 STRAIL level crossing systems & STRAILastic track damping systems Gummiwerk KRAIBURG Elastik Gmbh / D-85429 Tittmoning Goellstrasse

More information

WELCOME TO RAMPMASTER

WELCOME TO RAMPMASTER WELCOME TO RAMPMASTER Thor-Weld Industries was incorporated in 1972. In the early years our core business was steel and aluminum fabrication. After fifteen years of business an industrial caster company

More information

D. L. Gillas U. S. Department of Energy, Savannah River Operations Office P. O. Box A, Aiken, SC 29802

D. L. Gillas U. S. Department of Energy, Savannah River Operations Office P. O. Box A, Aiken, SC 29802 PACKAGING AND TRANSPORTATION OF DEPLETED URANIUM FOR DISPOSITION FROM THE ABSTRACT SAVANNAH RIVER SITE D. L. Gillas U. S. Department of Energy, Savannah River Operations Office P. O. Box A, Aiken, SC 29802

More information

Economical Design / Case Studies

Economical Design / Case Studies Economical Design / Case Studies Alabama Technology Transfer Center Workshop Michael Barker, PE University of Wyoming & SSSBA Bridge Technology Center Outline of Today s Presentation Competitiveness of

More information

Sweet Creek Road Retaining Wall Replacement. Mapleton, OR

Sweet Creek Road Retaining Wall Replacement. Mapleton, OR Sweet Creek Road Retaining Wall Replacement Mapleton, OR Technical Information Project Completion Date: April 30, 2013 Project Location: Mapleton, OR Size of Project: 15,000 SF, 870 CY Concrete Strength

More information

CLASS I RAIL CSX & Norfolk Southern

CLASS I RAIL CSX & Norfolk Southern INDUSTRIAL PARK ±2,700 Acres CLASS I RAIL CSX & Norfolk Southern PORT OF SAVANNAH Rail & Highway Access Updated 3/28/18 Industrial Park & Logistics Hub Highlights & Services SAVANNAH GATEWAY INDUSTRIAL

More information

REHABILITATION PACKAGE 4-a

REHABILITATION PACKAGE 4-a 4-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 4-a Rehab option 4-a is a rehabilitation package whereby all spans of the existing steel truss structure would be rehabilitated and strengthened.

More information

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS Section Page 26-1 GENERAL... 26.1 26-2 PAVEMENT KEYCUTTING... 26.1 26-3 PAVEMENT PLANING... 26.2 26-4 PLANED PAVEMENT CONFORMS... 26.3

More information

SHOULDER DETAIL CONCRETE CURB SHOULDER DETAIL ASPHALT CURB SHOULDER DETAIL PAVEMENT JOINT DETAIL PAVEMENT JOINT DETAIL NORMAL SECTION COMMON AND ASPHALT ALTERNATE NOTES ITEM LEGEND EX. ITEM LEGEND CONCRETE

More information

SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed. Florida Department of Transportation District Five

SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed. Florida Department of Transportation District Five SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed Florida Department of Transportation District Five Project Overview Location SR 600 / US 92, Volusia County FPN:

More information

Bonner Bridge Replacement Update:

Bonner Bridge Replacement Update: Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner

More information

North Carolina Railroad Company Engineering Department. Design and Construction Guidelines

North Carolina Railroad Company Engineering Department. Design and Construction Guidelines North Carolina Railroad Company Engineering Department Design and Construction Guidelines January 2019 Version 2.0 PREFACE These Design and Construcion Guidelines are provided as information only to assist

More information

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR July 12, 2002 A Paper Submitted for the AREMA Annual Conference by: Paul B. Satterly, P.E. HNTB CORPORATION 111 Monument Circle, Suite 1200 Indianapolis,

More information

Railway Alignment Design and Geometry

Railway Alignment Design and Geometry Railway Alignment Design and Geometry Pasi Lautala, Michigan Tech University Tyler Dick, HDR, Inc. Topics Horizontal and Vertical geometry Clearances Turnout design Structures and loading 1 REES Module

More information

Resistance to rail creep what do rail fastenings really have to do?

Resistance to rail creep what do rail fastenings really have to do? Resistance to rail creep what do rail fastenings really have to do? David Rhodes (Technical Director, Pandrol Ltd., UK) and Bob Coats (Vice President Engineering, Pandrol USA LLP) Introduction Rail fastenings

More information

Innovations in Urban Freight. Commercial Challenges for the Port of Seattle February 6, 2011

Innovations in Urban Freight. Commercial Challenges for the Port of Seattle February 6, 2011 Innovations in Urban Freight Commercial Challenges for the Port of Seattle February 6, 2011 1 Pier 90/91 Pier 86 Pier 66 Terminal 46 T-18 On-Dock Rail BNSF (SIG - North) T- 5 On-Dock Rail Terminal 18 Terminal

More information

Appendix E Cost Estimating Methodology for High-Speed Rail on Shared Rightof-Way

Appendix E Cost Estimating Methodology for High-Speed Rail on Shared Rightof-Way Appendix E Cost Estimating Methodology for High-Speed Rail on Shared Rightof-Way Cost Estimating Methodology for High-Speed Rail on Shared Right-of- Way Prepared by: Quandel Consultants, LLC Version: April

More information

SECTION NON-STRUCTURAL METAL FRAMING

SECTION NON-STRUCTURAL METAL FRAMING SECTION 09 22 16 PART 1 - GENERAL 1.1 DESCRIPTION A. This section specifies steel studs wall systems, shaft wall systems, ceiling or soffit suspended or furred framing, wall furring, fasteners, and accessories

More information