1 Survey of Modeling Capabilities and Needs for the Stationary Energy Storage Industry Prepared for: Energy Storage Association th Street, NW Suite 500 Washington, DC energystorage.org Prepared by: Navigant Consulting, Inc th Street, NW Suite 700 Washington, DC May 2014

2 Table of Contents Acknowledgements... iv Executive Summary... v Study Objectives and Value... v Study Findings... vi System Planning... vi Real-Time Grid Operation... vii Energy Storage Systems... vii Additional Gaps... viii 1 Introduction Study Overview Approach Characterize Existing Models and Tools Define Stakeholder Needs Identify Gaps Characterization of Existing Models and Tools System Planning Portfolio Planning Energy Production Cost Simulation Transmission System Planning Distribution System Modeling Real-Time Grid Operation Energy Storage Systems Definition of Stakeholder Needs Identification of Gaps System Planning Portfolio Planning Energy Production Cost Simulation Transmission System Planning Distribution System Planning Real-Time Grid Operation Energy Storage Systems Additional Gaps and Improvements Energy Storage System Performance Renewable Plant Data Engineering Standards Page i

3 Appendix A Contributing Companies/Entities Appendix B Descriptions of Software Products B.1 Portfolio Planning B.2 Energy Production Cost Simulation B.3 Transmission System Planning B.4 Distribution System Planning B.5 Real-Time Grid Operation B.6 Energy Storage Systems Page ii

4 List of Figures and Tables Figures: Figure 1. Study Objectives... 1 Figure 2. Categories of Models and Tools Surveyed... 4 Figure 3. North American Interconnections Tables: Table 1. Modeling Tools Reviewed by Category... 2 Table 2. Portfolio Planning Models... 5 Table 3. Production Cost Models... 7 Table 4. Transmission Planning Models Table 5. Distribution Planning Models Matrix Table 6. Primary Real Time Grid Operation Vendors Table 7. Energy Storage-Specific Applications Matrix Table 8. Energy Storage Industry Stakeholder and Analysis Needs Page iii

5 Acknowledgements Navigant would like to thank the Energy Storage Association (ESA) for funding this important study. In addition, we would like to express our thanks to the ESA Tools Task Force for their insight, guidance, and review of this study. Members of the Task Force included:» Eva Gardow, FirstEnergy Service Company» Udi Helman, Independent consultant» Praveen Kathpal, AES Energy Storage» Ben Kaun, Electric Power Research Institute» Jim McDowall, Saft» Ali Nourai, DNV GL We also would like to acknowledge the input we received from the individuals who participated in our survey. A full list of contributing organizations is presented in Appendix A. Page iv

6 Executive Summary Study Objectives and Value Energy Storage (ES) can be used to enhance and support the electric distribution and transmission network, and support the integration and operation of intermittent electric generating resources. The first pumped storage hydroelectric project in the United States was developed nearly a century ago. Compressed air energy storage (CAES) plants have been operated commercially for a few decades. Thermal storage integrated with concentrating solar plants has been operated at utility-scale for about eight years. Ice storage is also being used to shift electrical demand and consumption to off-peak periods in commercial deployments. More recently, battery and flywheel based systems have begun commercial operations on the grid to provide ancillary services, and have met performance requirements. Building on this commercial experience as well as technical studies and demonstration projects on these and other storage technologies, such as flow batteries and ultracapacitors, interest in the grid support and transformative potential for these technologies has led to a renewed interest in both distributed and bulk scale ES. An example of this trend is the first U.S. ES mandate resulting from the 2013 California Public Utility Commission (CPUC) Decision requiring the state s three major utilities (Pacific Gas & Electric, Southern California Edison, and San Diego Gas & Electric) to procure a total of 1,325 megawatts of ES capacity by A significant driver for ES is the increasing deployment of solar photovoltaic and wind resources, where the rapid response of ES can mitigate output variability. Even more important is the flexible operating range of ES, ramping from full charge to full discharge during the increasingly severe late afternoon system ramp as the output of solar resources wanes and loads increase. The increasing interest in ES highlights the urgent need to properly value, integrate, and operate ES systems. However, given the limited role that ES historically has played in the electric system, many of the traditional utility planning models were not designed to fully assess ES alternatives. For ES to become widely and cost-effectively adopted, it is critical that stakeholders have the tools and models needed to make informed ES decisions. The Energy Storage Association (ESA) recognized this need and contracted with Navigant Consulting, Inc. (Navigant) to assess the current ES modeling capabilities in the industry. Based on Navigant s investigation, while there has been substantial model development related to ES, there are still a number of key gaps, including: 1) incomplete representation of ES characteristics in many models; 2) stand-alone ES planning tools that are not fully integrated with other utility planning models; 3) a lack of standardization among tools used to evaluate ES; and 4) limits on the data available on ES technologies. Each of these shortcomings will need to be addressed to improve the analysis of ES applications and their associated costs and benefits. This study describes each of the models currently used in the industry to evaluate ES technologies. This study does not evaluate the quality or performance of the specific models and tools but rather describes their current capabilities and future development plans, as expressed by the software developers surveyed and other industry experts. The results will help ES industry stakeholders assess whether a Page v

7 particular model can fulfill their needs. The study also highlights shortcomings in current ES modeling to potentially spur the development of new features and software packages to meet the growing demand. Study Findings Outside of large pumped hydroelectric facilities, ES is an emerging technology and has historically had a limited role in the operation of the bulk power grid. As a result, the widely used system planning models have generally neglected to account for the complex and variable operations of ES systems. Most planning software programs do not concentrate on the unique modeling required to represent ES accurately. The few models that do have the flexibility to incorporate the various characteristics of an ES system are complex and require very long computational runtimes. Importantly, the need to appropriately represent ES technologies and systems coincides with the need to model rapidly changing system operations and reliability due to increasing penetration of variable wind and solar generation, which in itself has presented challenges. Since ES can aid in the reliable operation of generation, transmission, and distribution, particularly under the conditions emerging with growing interconnection of variable energy technologies, further developments are necessary in the existing utility procurement and planning models to properly represent the value of ES. Additionally, the real-time operation of the grid requires software that will fully incorporate ES system operating parameters and dispatch units accordingly. Finally, ES-specific tools are needed to assess and inform the optimal ES system size and control algorithms to maximize economic, reliability, and environmental benefits. The following sections provide an overview of the different categories of planning and operations and their relevance to ES. System Planning Portfolio planning models are used to determine the optimal set of least-cost resources to meet the needs of a utility system or region. Currently, conventional commercially available portfolio planning models are unable to fully co-optimize between the energy and ancillary service markets, where the operational capabilities of ES are particularly valuable. Additionally, these models do not account for the ability of energy storage to minimize ramping constraints compared to traditional technologies. Energy production cost simulation models are used to perform long-term assessments of system and market operations, including forecasts of generation, wholesale electric costs, and locational marginal prices. Energy production cost simulation models incorporate significant system operational detail, but currently have difficulty capturing the comprehensive value of ES systems. Moreover, due to long runtimes, there may be limits to the number of production cost simulations used to evaluate alternative portfolios, including those with different specifications on storage. These models are primarily intended to simulate the hourly level of system operations assuming perfect foresight. On the other hand, ES Page vi

8 provides significant benefits within very short time-frames and by flexibly responding to unexpected occurrences. While sub-hourly dispatch is available or is being developed in many of these models, the capability to model ES operations at the 5-minute level and in response to regulation signals is still in the early stages. Some vendors have developed system models that can simulate frequency response, and use these in conjunction with production cost models, but for limited time-frames. For those models that do have sub-hourly dispatch capability and options for creating specific ES unit parameters, long modeling run times become an issue. Despite longer run times, there are a number of storage valuation studies that conduct sufficient numbers of storage scenarios using production simulation to inform longterm ES planning purposes on the grid by extrapolating representative day s results. Further progress is still needed. Transmission system planning models are used to assess large transmission networks. These software packages help evaluate the operations and reliability of the transmission network under various system conditions. Transmission system planning models have the ability to incorporate ES and quantify the associated contribution to system reliability. However, doing so often requires the user to create ESspecific individualized models, which can be a time-consuming process. It is recommended that the transmission system planning software vendors invest in creating and including ES-specific models in their annual updates. Distribution system models are often used by utilities for short- and long-term distribution planning. The largest gap in modeling ES on distribution systems is that there isn t a tool that can handle optimum dispatch plans for different applications. It s also important to note that the necessary inputs are not available within the model itself and therefore, ES components often have to be designed outside of the model. Also, tools to evaluate the impacts of transmission support applications on distribution circuits are not yet available. Real-Time Grid Operation Real-time grid operation includes software used by independent system operators/regional transmission organizations (ISOs/RTOs) and utilities to develop day-ahead and hour-ahead schedules and market prices for energy and ancillary services, and to operate the grid and markets in real time. Increasingly, conventional grid operational tools and market solutions have been supplemented with tools to forecast ancillary service and ramping needs due to variable energy resources. Many of these tools will affect ES operations, although their details are often not available to ES developers. With respect to transmission level operations, energy management systems (EMS) and market management systems (MMS) may need to be modified to accommodate ES in applications such as frequency regulation. These modifications are achievable and have already been implemented in certain ISOs/RTOs. The industry should press for additional specifications and transparency on these tools. While utility distribution management systems (DMS) offer a potential platform for integrating the results from various system planning software, advanced DMS systems are still evolving to incorporate these capabilities. Energy Storage Systems ES system tools are developed for specific industry needs such as estimating and demonstrating the value of ES, calculating optimal system size, controlling ES systems, and optimizing ES system Page vii

9 performance. These types of models allow for much greater detail in operational specifications, but use fixed historical or simulated data on market prices and system conditions as inputs. The major shortcomings with these tools are the lack of available data on ES system operations and the proprietary nature of many of the existing tools. Shared knowledge would allow developers to create more robust tools that could then be customized for specific needs. An additional linkage is between simulated data on future system conditions to be used as inputs to these types of models, to allow for further analysis of changing system conditions. Additional Gaps The most common gap highlighted by stakeholders is the lack of a single ES tool to integrate the inputs and results of various system planning tools. While an integrated tool may not be feasible due to computational limits and complexity, a standardized approach on how to value ES using available tools is also lacking. The development of such a standardized approach would aid the proper application and value-assessment of ES when compared to traditional resources. Page viii

Bulk Power System Integration of Variable Generation - Program 173

Bulk Power System Integration of Variable Generation - Program 173 Program Description Program Overview Environmentally driven regulations such as state-mandated renewable energy standards and federal air and water standards, along with improved economic viability for

More information

Bulk Power System Integration of Variable Generation - Program 173

Bulk Power System Integration of Variable Generation - Program 173 Bulk Power System Integration of Variable Generation - Program 173 Program Description Program Overview A number of ongoing environmentally driven regulatory issues including greenhouse gas reductions

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Centralized Capacity Markets in Regional ) Transmission Organizations and ) Docket No. AD13-7-000 Independent System Operators )

More information

NORTHWESTERN ENERGY 2018 ELECTRICITY RESOURCE PROCUREMENT PLAN STRAWMAN 1

NORTHWESTERN ENERGY 2018 ELECTRICITY RESOURCE PROCUREMENT PLAN STRAWMAN 1 NORTHWESTERN ENERGY 2018 ELECTRICITY RESOURCE PROCUREMENT PLAN CHAPTER 1. EXECUTIVE SUMMARY STRAWMAN 1 1. Load Service Requirements a. Peaking Capacity (Planning Reserve Margin) b. Dispatchable Capacity

More information

THERMAL ENERGY STORAGE AS AN ENABLING TECHNOLOGY FOR RENEWABLE ENERGY

THERMAL ENERGY STORAGE AS AN ENABLING TECHNOLOGY FOR RENEWABLE ENERGY THERMAL ENERGY STORAGE AS AN ENABLING TECHNOLOGY FOR RENEWABLE ENERGY Paul Denholm National Renewable Energy Laboratory 1617 Cole Blvd. Golden, CO, USA e-mail: paul.denholm@nrel.gov Sean Ong National Renewable

More information

PJM Interconnection, L.L.C. ( PJM ) submits hereby submits its responses to the United

PJM Interconnection, L.L.C. ( PJM ) submits hereby submits its responses to the United PJM Interconnection, L.L.C. 2750 Monroe Boulevard Audubon, PA 19403 Jacqulynn B. Hugee Associate General Counsel T: (610) 666-8208 F: (610) 666-8211 jacqulynn.hugee@pjm.com Via WPTORFI@ee.doe.gov Hoyt

More information

BEFORE THE UTILITIES AND TRANSPORTATION COMMISSION OF WASHINGTON ) ) ) ) ) COMMENTS OF THE ENERGY STORAGE ASSOCIATION

BEFORE THE UTILITIES AND TRANSPORTATION COMMISSION OF WASHINGTON ) ) ) ) ) COMMENTS OF THE ENERGY STORAGE ASSOCIATION BEFORE THE UTILITIES AND TRANSPORTATION COMMISSION OF WASHINGTON IN THE MATTER OF RULEMAKING FOR INTEGRATED RESOURCE PLANNING ) ) ) ) ) DOCKET UE-161024 COMMENTS OF THE ENERGY STORAGE ASSOCIATION The Energy

More information

Energy Storage Integration in Alberta s Energy Only Market. Kevin Dawson Director, Market Design Alberta Electric System Operator

Energy Storage Integration in Alberta s Energy Only Market. Kevin Dawson Director, Market Design Alberta Electric System Operator Energy Storage Integration in Alberta s Energy Only Market Kevin Dawson Director, Market Design Alberta Electric System Operator Outline The AESO and Alberta s Wholesale Electricity Market About the AESO

More information

Demand Response Association of Energy Engineers. Presenter: David Wylie, P.E. ASWB Engineering

Demand Response Association of Energy Engineers. Presenter: David Wylie, P.E. ASWB Engineering Demand Response 2015 Association of Energy Engineers Presenter: David Wylie, P.E. ASWB Engineering National Energy Peak Leveling Program 1977 2 National Energy Peak Leveling Program 1977 3 When Demand

More information

September 25, RE: Docket UE Modeling Energy Storage in Integrated Resource Planning. Dear Mr. King:

September 25, RE: Docket UE Modeling Energy Storage in Integrated Resource Planning. Dear Mr. King: September 25, 2015 Steven King, Executive Director and Secretary Washington Utilities and Transportation Commission Attn: Records Center PO Box 47250 Olympia WA 98504-7250 RE: Docket UE- 151069 - Modeling

More information

1800 M Street NW Suite 400S Washington DC 20036

1800 M Street NW Suite 400S Washington DC 20036 1800 M Street NW Suite 400S Washington DC 20036 October 28, 2016 Hon. David J. Collins Executive Secretary to the Commission Maryland Public Service Commission 6 St. Paul Street Baltimore MD 21202 RE:

More information

Southern California Edison Approach to Renewable Integration June 7, 2011

Southern California Edison Approach to Renewable Integration June 7, 2011 Southern California Edison Approach to Renewable Integration June 7, 2011 Page: 0 SCE s 2010 Resource Mix Natural Gas All Resources 100% = 75 billion kwh/yr Renewable Resources 100% = 14.5 billion kwh/yr

More information

TESTIMONY OF MARK ROTHLEDER ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

TESTIMONY OF MARK ROTHLEDER ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION Application No.: Exhibit No.: Witness: Mark Rothleder Order Instituting Rulemaking to Integrate and Refine Procurement Policies and Consider Long-Term Procurement Plans. TESTIMONY OF MARK ROTHLEDER BEFORE

More information

MISO Energy Storage Study DRAFT Scope

MISO Energy Storage Study DRAFT Scope MISO Energy Storage Study DRAFT Scope MISO Energy Storage Study DRAFT Scope July 19, 2011 MISO Page 1 Table of Contents 1. Introduction... 3 2. Study Objectives... 3 3. Study Drivers... 4 4. Study Description...

More information

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC

More information

RELIABILITY AND SECURITY ISSUES OF MODERN ELECTRIC POWER SYSTEMS WITH HIGH PENETRATION OF RENEWABLE ENERGY SOURCES

RELIABILITY AND SECURITY ISSUES OF MODERN ELECTRIC POWER SYSTEMS WITH HIGH PENETRATION OF RENEWABLE ENERGY SOURCES RELIABILITY AND SECURITY ISSUES OF MODERN ELECTRIC POWER SYSTEMS WITH HIGH PENETRATION OF RENEWABLE ENERGY SOURCES Evangelos Dialynas Professor in the National Technical University of Athens Greece dialynas@power.ece.ntua.gr

More information

Expanding Hydropower and Pumped Storage s Contribution to Grid Resiliency and Reliability RFI#: DE-FOA

Expanding Hydropower and Pumped Storage s Contribution to Grid Resiliency and Reliability RFI#: DE-FOA DATE: February 21, 2018 Expanding Hydropower and Pumped Storage s Contribution to Grid Resiliency and Reliability RFI#: DE-FOA-0001886 SUBJECT: Request for Information (RFI) RESPONSE DUE: April 6, 2018

More information

From: Keith Casey, Vice President, Market and Infrastructure Development

From: Keith Casey, Vice President, Market and Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market and Infrastructure Development Date: August 18, 2011 Re: Briefing on Renewable

More information

SCE s Experience In Energy Storage

SCE s Experience In Energy Storage SCE s Experience In Energy Storage October 19, 2016 Dhaval Dagli Principal Manager, Regulatory Policy Regulatory Affairs Southern California Edison Southern California Edison (SCE) Highlights One of the

More information

RENEWABLE ENERGY SERVICES GRID SOLUTIONS

RENEWABLE ENERGY SERVICES GRID SOLUTIONS RENEWABLE ENERGY SERVICES GRID SOLUTIONS 1 ABOUT US Leaders in Global Services for Renewable Energy UL works to help renewable energy manufacturers, developers, owners, investors, lenders, utilities and

More information

Date of Request for Comment: April 7, 2017 Period of Comment: April 7, 2017 through May 5, 2017

Date of Request for Comment: April 7, 2017 Period of Comment: April 7, 2017 through May 5, 2017 Market Participant Comments and AESO Replies Matrix Proposed Amended Section 304.3, Wind and Solar Power Ramp Up Management ( amended Section 304.3 ) Date of Request for Comment: April 7, 2017 Period of

More information

The Role of Energy Storage with Renewable Electricity Generation

The Role of Energy Storage with Renewable Electricity Generation The Role of Energy Storage with Renewable Electricity Generation Paul Denholm National Renewable Energy Laboratory Presentation to the NARUC Summer Meeting July 18 2010 Outline Current Status of Storage

More information

ENERGY STORAGE INNOVATIONS AT BLACK & VEATCH

ENERGY STORAGE INNOVATIONS AT BLACK & VEATCH 26 March 2013 ENERGY STORAGE INNOVATIONS AT BLACK & VEATCH LUCAS OEHLERKING RENEWABLE ENERGY CONSULTANT ENERGY 26 March 2013 RENEWABLE ENERGY MORE THAN DOUBLES IN THE NEXT 25 YEARS Data Label Legend: Technology,

More information

Stakeholder Comments. San Diego County Water Authority and City of San Diego Comments on Storage as a Transmission Asset Issue Paper

Stakeholder Comments. San Diego County Water Authority and City of San Diego Comments on Storage as a Transmission Asset Issue Paper Stakeholder Comments San Diego County Water Authority and City of San Diego Comments on Storage as a Transmission Asset Issue Paper Submitted by Company Date Submitted Andrea Altmann Email: aaltmann@sdcwa.org

More information

Modeling the Value of Energy Storage

Modeling the Value of Energy Storage Modeling the Value of Energy Storage StorageVET Demonstration Giovanni Damato Technical Leader CESA Webinar 2017-02-16 Agenda 1) Overview of StorageVET (30min) 2) StorageVET Demo (30min) 3) Open Discussion

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION TRACK 2 TESTIMONY

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION TRACK 2 TESTIMONY BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Oversee the Resource Adequacy Program, Consider Program Refinements, and Establish Annual Local and Flexible

More information

First Person A Blueprint to Electrify the Golden State

First Person A Blueprint to Electrify the Golden State EPRI JOURNAL May/June 2018 No. 3 25 First Person A Blueprint to Electrify the Golden State The Story in Brief When it comes to electrification, utilities need to think ahead, think hard, and think fast

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CLEAN COALITION COMMENTS ON INTERIM STAFF REPORT AND ENERGY STORAGE WORKSHOPS

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CLEAN COALITION COMMENTS ON INTERIM STAFF REPORT AND ENERGY STORAGE WORKSHOPS BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Pursuant to Assembly Bill 2514 to Consider the Adoption of Procurement Targets for Viable and Cost-Effective

More information

Reduced Network Modeling of WECC as a Market Design Prototype

Reduced Network Modeling of WECC as a Market Design Prototype PAPER 2011GM0942 1 Reduced Network Modeling of WECC as a Market Design Prototype James E. Price, Member, IEEE, and John Goodin Abstract California s administration, legislature, and energy regulators have

More information

Enabling the Internet of Energy through Network Optimized Distributed Energy Resources. ARPA-E NODES Program. TREIA Webinar June 28 th, 2016

Enabling the Internet of Energy through Network Optimized Distributed Energy Resources. ARPA-E NODES Program. TREIA Webinar June 28 th, 2016 Enabling the Internet of Energy through Network Optimized Distributed Energy Resources ARPA-E NODES Program TREIA Webinar June 28 th, 2016 Michael Kleinberg, PhD Senior Consultant DNV GL 1 SAFER, SMARTER,

More information

RE: Comments on Staff s draft proposed rules for Interconnection of Distributed Generation Facilities (Docket No. RE-00000A )

RE: Comments on Staff s draft proposed rules for Interconnection of Distributed Generation Facilities (Docket No. RE-00000A ) 1800 M Street NW Suite 400S Washington DC 20036 energystorage.org October 4, 2017 Mr. Elijah Abinah Director, Utilities Division Arizona Corporation Commission 1200 West Washington Street Phoenix, AZ 85007

More information

UNM ME 217 Energy, Environment & Society. Renewable Energy and the Need for Energy Storage. November 8, 2011 Steve Willard, P.E

UNM ME 217 Energy, Environment & Society. Renewable Energy and the Need for Energy Storage. November 8, 2011 Steve Willard, P.E UNM ME 217 Energy, Environment & Society Renewable Energy and the Need for Energy Storage November 8, 2011 Steve Willard, P.E Renewable Energy and the Need for Energy Storage Where we get our energy from,

More information

Growing Wind. Final Report of the NYISO 2010 Wind Generation Study. John Adams Principal Electric System Planner New York Independent System Operator

Growing Wind. Final Report of the NYISO 2010 Wind Generation Study. John Adams Principal Electric System Planner New York Independent System Operator Growing Wind Final Report of the NYISO 2010 Wind Generation Study John Adams Principal Electric System Planner New York Independent System Operator National Wind Coordinating Collaborative Transmission

More information

Roadmaps for Demand Response & Storage

Roadmaps for Demand Response & Storage 1 Roadmaps for Demand Response & Storage Jim Price, California ISO Senior Advisor, Market Development & Analysis jprice@caiso.com PSERC Summer Planning Workshop Market Stem July 15, 2015 CAISO markets

More information

Energy Department Report on Electricity Markets and Reliability

Energy Department Report on Electricity Markets and Reliability Quick Insights Energy Department Report on Electricity Markets and Reliability RESEARCH QUESTION What are the key findings and recommendations from the Staff Report to the Secretary on Electricity Markets

More information

PJM Wind Integration Initiatives

PJM Wind Integration Initiatives PJM Wind Integration Initiatives West Virginia Wind Forum Davis, WV September 25, 2012 Ken Schuyler Renewable Services PJM Interconnection 1 26% of generation in Eastern Interconnection 28% of load in

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF NEVADA ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF NEVADA ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF NEVADA Investigation regarding battery storage technologies ) ) ) ) Docket No. 16-01013 COMMENTS OF THE ENERGY STORAGE ASSOCIATION WITH REGARD TO ENERGY STORAGE

More information

Bulk Energy Storage Resource Case Study Update with the 2016 LTPP Assumptions

Bulk Energy Storage Resource Case Study Update with the 2016 LTPP Assumptions Bulk Energy Storage Resource Case Study Update with the 2016 LTPP Assumptions Shucheng Liu Principal, Market Development 2016-2017 Transmission Planning Process Stakeholder Meeting February 28, 2017 Page

More information

CAISO s Plan for Integration of Renewable Resources

CAISO s Plan for Integration of Renewable Resources CAISO s Plan for Integration of Renewable Resources July 21, 2008 CEC 33% Renewables Workshop Presented by David Hawkins Program Tracks 2008-9 CAISO Work Plan Track 1 - Develop Operational Tools Wind and

More information

Air Quality and GHG Emission Impacts of Stationary Fuel Cell Systems

Air Quality and GHG Emission Impacts of Stationary Fuel Cell Systems Air Quality and GHG Emission Impacts of Stationary Fuel Cell Systems An assessment produced by the Advanced Power and Energy Program at UC Irvine Introduction. The increasing percentage of intermittent

More information

Welcome to the California Independent System Operator. August 7, 2015

Welcome to the California Independent System Operator. August 7, 2015 Welcome to the California Independent System Operator August 7, 2015 The California ISO is one of nine independent/regional transmission operators (ISOs/RTOs) in North America Two-thirds of the United

More information

Common Communication Platform for Valuing Energy Storage

Common Communication Platform for Valuing Energy Storage Common Communication Platform for Valuing Energy Storage StorageVET in Action Giovanni Damato Senior Project Manager Capture the Energy 2017 (NY-BEST) 2017-03-09 StorageVET Storage Value Estimation Tool:

More information

Integrating Renewables and Distributed Energy Resources into California s Electricity Markets

Integrating Renewables and Distributed Energy Resources into California s Electricity Markets Integrating Renewables and Distributed Energy Resources into California s Electricity Markets Lorenzo Kristov, Ph.D. Principal, Market & Infrastructure Policy Center for Clean Air Policy Energy Sector

More information

Best Practices in Conducting Grid Integration Studies

Best Practices in Conducting Grid Integration Studies GREENING THE GRID Best Practices in Conducting Grid Integration Studies ENHANCING CAPACITY FOR LOW EMISSION DEVELOPMENT STRATEGIES (EC-LEDS) Agenda and Learning Objectives Part 1: Why conduct a grid integration

More information

Low Carbon Grid Study: Analysis of a 50% Emission Reduction in California

Low Carbon Grid Study: Analysis of a 50% Emission Reduction in California Low Carbon Grid Study: Analysis of a 50% Emission Reduction in California Executive Summary Gregory Brinkman and Jennie Jorgenson National Renewable Energy Laboratory Ali Ehlen and James H. Caldwell Center

More information

Hydroelectric Pumped Storage Potential and Renewable Energy Integration in the Northwest

Hydroelectric Pumped Storage Potential and Renewable Energy Integration in the Northwest Hydroelectric Pumped Storage Potential and Renewable Energy Integration in the Northwest Wind generation on Bonneville Power Administration s (BPA) system in the Northwest grew from almost nothing in 1998

More information

ISO Transmission Planning Process. Supplemental Sensitivity Analysis: Benefits Analysis of Large Energy Storage

ISO Transmission Planning Process. Supplemental Sensitivity Analysis: Benefits Analysis of Large Energy Storage ISO 2016-2017 Transmission Planning Process Supplemental Sensitivity Analysis: Benefits Analysis of Large Energy Storage January 4, 2018 Contents 1. Introduction... 1 2. Background... 1 3. Objectives of

More information

Written Statement of Richard Dewey Executive Vice President New York Independent System Operator

Written Statement of Richard Dewey Executive Vice President New York Independent System Operator Written Statement of Richard Dewey Executive Vice President New York Independent System Operator Senate Standing Committee on Energy and Telecommunications Senator Joseph A. Griffo, Chairman Senate Standing

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF A COMMISSION ) INVESTIGATION INTO THE FEASIBILITY ) OF PUBLIC SERVICE COMPANY OF NEW ) MEXICO BECOMING A MEMBER OF THE ) Case No. 17-00261-UT

More information

Electrification and its Implications for the California Electricity System

Electrification and its Implications for the California Electricity System Electrification and its Implications for the California Electricity System Lorenzo Kristov, Ph.D. Principal, Market & Infrastructure Policy EPRI-IEA Workshop: Challenges in Electricity Decarbonization

More information

California s Solar Buildout: Implications for Electricity Markets in the West

California s Solar Buildout: Implications for Electricity Markets in the West California s Solar Buildout: Implications for Electricity Markets in the West EPIS Electric Market Forecasting Conference Las Vegas, Nevada September 7, 2017 Arne Olson, Partner Agenda Report From the

More information

RENEWABLE ENERGY & ITS IMPLEMENTATION WITH MICROGRID

RENEWABLE ENERGY & ITS IMPLEMENTATION WITH MICROGRID RENEWABLE ENERGY & ITS IMPLEMENTATION WITH MICROGRID Presented By Prof. Dr. S.M Ali Director(Membership) Institute of Engineers, India(IEI) Kolkata & Ritesh Dash PG Scholar School of Electrical Engineering

More information

California ISO. Q Report on Market Issues and Performance. February 10, Prepared by: Department of Market Monitoring

California ISO. Q Report on Market Issues and Performance. February 10, Prepared by: Department of Market Monitoring California Independent System Operator Corporation California ISO Q4 2013 Report on Market Issues and Performance February 10, 2014 Prepared by: Department of Market Monitoring Department of Market Monitoring

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: December 6, 2017 Re: Decision on contingency

More information

Resource planning and operational requirements for the advanced grid: Demand Response Potential Studies

Resource planning and operational requirements for the advanced grid: Demand Response Potential Studies Resource planning and operational requirements for the advanced grid: Demand Response Potential Studies NASEO EMAP Workshop Presented to the Nevada Governor s Office of Energy Jennifer Potter, Senior Scientific

More information

Renewable Resources and Wholesale Price Suppression. August 2013

Renewable Resources and Wholesale Price Suppression. August 2013 Renewable Resources and Wholesale Price Suppression August 2013 INTRODUCTION The study examines the relationship between renewable resource additions and wholesale electricity markets in Ohio. The Staff

More information

CHAPTER 1 EXECUTIVE SUMMARY

CHAPTER 1 EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY The 2016 SD Electricity Supply Resource Procurement Plan The 2016 South Dakota Electricity Supply Resource Procurement Plan ( Plan ) evaluates NorthWestern Energy s ( NorthWestern

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Please fill in the name, e-mail address and contact number of a specific person who can respond to any questions about these comments.

More information

Pumped Storage - The Proven Grid Scale Storage Solution. Presented to: NWPCC GRAC Committee

Pumped Storage - The Proven Grid Scale Storage Solution. Presented to: NWPCC GRAC Committee Pumped Storage - The Proven Grid Scale Storage Solution Presented to: NWPCC GRAC Committee January 27, 2015 Presentation Agenda Part 1 Variable Energy Resources Integration Challenges The Need for Grid

More information

2012 Grid of the Future Symposium. Evolution of the US Power Grid and Market Operations through the next Decade

2012 Grid of the Future Symposium. Evolution of the US Power Grid and Market Operations through the next Decade 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium Evolution of the US Power Grid and Market Operations through the next Decade A. OTT,

More information

1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Durgesh Manjure, MISO Energy September 6, 2017

1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Durgesh Manjure, MISO Energy September 6, 2017 Centralized Energy & Operating Reserves Markets: A MISO perspective 1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Durgesh Manjure, MISO Energy September 6, 2017

More information

Integrating Renewables

Integrating Renewables Integrating Renewables The National RPS Summit Portland, OR October 22, 2010 Timothy C. Burdis Strategist PJM as Part of the Eastern Interconnection 6,038 substations KEY STATISTICS PJM member companies

More information

EVALUATION OF ENERGY STORAGE IN DISTRIBUTION SYSTEMS

EVALUATION OF ENERGY STORAGE IN DISTRIBUTION SYSTEMS EVALUATION OF ENERGY STORAGE IN DISTRIBUTION SYSTEMS Arindam Maitra Jose Carranza Ben Kaun Stella Chen Haresh Kamath Matt Rylander EPRI USA SDG&E USA EPRI USA EPRI USA EPRI USA amaitra@epri.com jcarranza@semprautilities.com

More information

PJM Renewable Integration Study. Ken Schuyler Renewable Energy in West Virginia June 5, 2014

PJM Renewable Integration Study. Ken Schuyler Renewable Energy in West Virginia June 5, 2014 PJM Renewable Integration Study Ken Schuyler Renewable Energy in West Virginia June 5, 2014 PJM as Part of the Eastern Interconnection 27% of generation in Eastern Interconnection 28% of load in Eastern

More information

Is the "duck curve" eroding the value of energy efficiency?

Is the duck curve eroding the value of energy efficiency? Is the "duck curve" eroding the value of energy efficiency? Edward Burgess, Strategen Consulting Jeff Schlegel, Schlegel & Associates/Southwest Energy Efficiency Project (SWEEP) Ellen Zuckerman, Schlegel

More information

The Optimal Approach to Firming Windpower

The Optimal Approach to Firming Windpower 5735 Hollister Avenue, Suite B Goleta, California 93117 T 805.683.9659 F 805.683.9671 www.gravitypower.net The Optimal Approach to Firming Windpower Summary As many regions of the world are staging massive

More information

Update on FERC, NERC, DOE & Congress John P. Hughes President & CEO Electricity Consumers Resource Council Washington DC

Update on FERC, NERC, DOE & Congress John P. Hughes President & CEO Electricity Consumers Resource Council Washington DC Council of Industrial Boiler Owners Technical Focus Group, Energy & Environmental Committee Meetings September 12-13, 2017 Arlington, Virginia Update on FERC, NERC, DOE & Congress John P. Hughes President

More information

Regulation Energy Management Draft Final Proposal

Regulation Energy Management Draft Final Proposal Regulation Energy Management Draft Final Proposal January 13, 2011 Renewable Integration: Market and Product Review Phase 1 Regulation Energy Management (REM) Revised Draft Final Proposal Table of Contents

More information

Modelling Transitions to Robust High-VRE Systems

Modelling Transitions to Robust High-VRE Systems Modelling Transitions to Robust High-VRE Systems Colin Silvester, Christopher Bates and Arjun Chohan Digital Engineering Solutions Uniper Nottingham, UK Colin.Silvester@uniper.energy Abstract Uniper is

More information

DRAFT Work in Progress CAISO Integration of Renewable Resources Program (IRRP) - High-Level Program Plan -

DRAFT Work in Progress CAISO Integration of Renewable Resources Program (IRRP) - High-Level Program Plan - CAISO 2008-2013 Integration of Renewable Resources Program (IRRP) - High-Level Program Plan - Purpose The purpose of this document is to provide an initial high-level scoping and program plan for the CAISO

More information

SCE s Preferred Resources Pilot (PRP) Annual Progress Update

SCE s Preferred Resources Pilot (PRP) Annual Progress Update SCE s Preferred Resources Pilot (PRP) Annual Progress Update December 2014 http://on.sce.com/preferredresources http://edison.com/preferredresources PRP Annual Progress Update Outline Content PRP Overview

More information

Presentation Overview

Presentation Overview Firming Renewables and Alleviating Transmission Constraints The Role of Energy Storage Brad Roberts S&C Electric Company & Jeff Palermo KEMA High Plains Transmission Summit Topeka Lawrence, Kansas November

More information

Distributed Energy Resource Management System (DERMS)

Distributed Energy Resource Management System (DERMS) Distributed Energy Resource Management System (DERMS) EPIC Project 2.02 Overview Alex Portilla, PG&E EPIC Summer Workshop June 22, 2016 READ AND DELETE For best results with this template, use PowerPoint

More information

RENEWABLE ENERGY. California Implements Renewable Auction Mechanism for Distributed Clean Energy NITED STATES OF

RENEWABLE ENERGY. California Implements Renewable Auction Mechanism for Distributed Clean Energy NITED STATES OF RENEWABLE ENERGY California Implements Renewable Auction Mechanism for Distributed Clean Energy NITED STATES OF FACILITATING A SHIFT TO RENEWABLE ENERGY SOURCES California s first-of-its-kind renewable

More information

2020 Strategic Analysis of Energy Storage in California

2020 Strategic Analysis of Energy Storage in California 2020 Strategic Analysis of Energy Storage in California Ethan Elkind University of California, Berkeley & Los Angeles Schools of Law October 5, 2011 Berkeley Law 2020 Strategic Analysis of Energy Storage

More information

NYS Energy Storage Roadmap. March 16, 2018

NYS Energy Storage Roadmap. March 16, 2018 NYS Energy Storage Roadmap March 16, 2018 Agenda 2 New York s Commitment to Energy Storage Jason Doling, NYSERDA Team Lead for Energy Storage Storage study scope Jason Doling Storage study inputs, and

More information

Beacon Power, LLC Response to the New York Energy Highway Request for Information (RFI) May 30, 2012

Beacon Power, LLC Response to the New York Energy Highway Request for Information (RFI) May 30, 2012 Beacon Power, LLC Response to the New York Energy Highway Request for Information (RFI) May 30, 2012 RESPONDENT INFORMATION Beacon Power, LLC ( Beacon Power or the Company ), a manufacturer and merchant

More information

An Introduction to PJM: Focus on its Markets and Opportunities for Demand Resources OHA Annual Energy & Sustainability Conference

An Introduction to PJM: Focus on its Markets and Opportunities for Demand Resources OHA Annual Energy & Sustainability Conference An Introduction to PJM: Focus on its Markets and Opportunities for Demand Resources OHA Annual Energy & Sustainability Conference Andrew Ott Sr. Vice President, Markets March 5, 2013 26% of power generation

More information

Electricity Grid of the Future. Program Director: Dr. Sonja Glavaski

Electricity Grid of the Future. Program Director: Dr. Sonja Glavaski Electricity Grid of the Future Program Director: Dr. Sonja Glavaski Outline ARPA-e Overview US Energy Landscape DERs and Grid Integration Grid of the Future (Vision & Long Term Goals) Going Forward The

More information

SCE Solar Programs Overview SOUTHERN CALIFORNIA EDISON

SCE Solar Programs Overview SOUTHERN CALIFORNIA EDISON SCE Solar Programs Overview Southern California Edison Overview An Edison International company, SCE is one of the nation s largest investor-owned electric utilities, with more than 120 years of service.

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Chapter 2. Direct Testimony of Joseph P. Hoerner and Shayleah J.

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Chapter 2. Direct Testimony of Joseph P. Hoerner and Shayleah J. Investigation No. -0-0 Exhibit No. Witnesses: Joseph P. Hoerner and Shayleah J. LaBray BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP Chapter Direct Testimony of Joseph P.

More information

StorageVET Applications and Demonstration Energy Storage Valuation Workshop

StorageVET Applications and Demonstration Energy Storage Valuation Workshop StorageVET Applications and Demonstration Energy Storage Valuation Workshop Ben Kaun, Program Manager Giovanni Damato, Senior Project Manager CPUC/CEC Joint Workshop November 2, 2017 10:00AM Today s Workshop

More information

Solar Integration Study

Solar Integration Study Solar Integration Study Timothy Duffy Manager, Economic Planning Electric and System Planning Working Group June 7, 2016 2000-2016 New York Independent System Operator, Inc. All Rights Reserved. Key Takeaways

More information

California Grid Operations: Current Conditions and Future Needs

California Grid Operations: Current Conditions and Future Needs California Grid Operations: Current Conditions and Future Needs Jim Detmers Vice President, Operations Global Climate & Energy Project November 1, 2007 STANFORD UNIVERSITY Our objective today is identify

More information

ERO Enterprise Longer-term Strategic Planning Considerations November 2015

ERO Enterprise Longer-term Strategic Planning Considerations November 2015 ERO Enterprise Longer-term Strategic Planning Considerations November 2015 Background The ERO Enterprise strategic planning process provides a three-year outlook for developing NERC and Regional Entity

More information

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017 Evolution of the Grid in MISO Region Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017 1 MISO s mission is to ensure reliable delivery of low-cost energy through efficient,

More information

Energy storage in intelligent energy networks

Energy storage in intelligent energy networks Energy storage in intelligent energy networks Kari Mäki VTT New developments in battery technology Oulu, January 2017 Contents Towards intelligent energy systems Storage status overview Needs for storage

More information

EPRI JOURNAL January/February 2018 No The Need for Large-Scale Energy Storage Grows, but the Business Case Remains Uncertain

EPRI JOURNAL January/February 2018 No The Need for Large-Scale Energy Storage Grows, but the Business Case Remains Uncertain EPRI JOURNAL January/February 2018 No. 1 8 Storing in Bulk The Need for Large-Scale Energy Storage Grows, but the Business Case Remains Uncertain By Brent Barker Energy storage on the electricity grid

More information

BILLING CODE P DEPARTMENT OF ENERGY. Federal Energy Regulatory Commission. [Docket No. RM ]

BILLING CODE P DEPARTMENT OF ENERGY. Federal Energy Regulatory Commission. [Docket No. RM ] This document is scheduled to be published in the Federal Register on 05/04/2018 and available online at https://federalregister.gov/d/2018-09455, and on FDsys.gov BILLING CODE 6717-01-P DEPARTMENT OF

More information

Including Advanced Energy Storage in Integrated Resource Planning: Cost Inputs and Modeling Approaches

Including Advanced Energy Storage in Integrated Resource Planning: Cost Inputs and Modeling Approaches Including Advanced Energy Storage in Integrated Resource Planning: Cost Inputs and Modeling Approaches November 2016 v1.1 Advanced energy storage costs are declining rapidly and large-scale storage deployments

More information

Briefing on How Resource Adequacy Works in ISO s Current Balancing Authority Area

Briefing on How Resource Adequacy Works in ISO s Current Balancing Authority Area Briefing on How Resource Adequacy Works in ISO s Current Balancing Authority Area Regional Resource Adequacy Meeting December 16, 2015 Salt Lake City, Utah Keith Johnson Manager, Infrastructure Policy

More information

CAISO s Flexible Resource Adequacy and Must Offer Obligation Phase 2 Revised Straw Proposal Public Generating Pool and Public Power Council Comments

CAISO s Flexible Resource Adequacy and Must Offer Obligation Phase 2 Revised Straw Proposal Public Generating Pool and Public Power Council Comments CAISO s Flexible Resource Adequacy and Must Offer Obligation Phase 2 Revised Straw Proposal Public Generating Pool and Public Power Council Comments May 22, 2017 Public Generating Pool (PGP) and Public

More information

The Influence of Demand Resource Response Time in Balancing Wind and Load

The Influence of Demand Resource Response Time in Balancing Wind and Load 2013 46th Hawaii International Conference on System Sciences The Influence of Demand Resource Response Time in Balancing Wind and Load Judith Cardell Smith College jcardell@smith.edu Lindsay Anderson Cornell

More information

2018 Summer Loads and Resources Assessment

2018 Summer Loads and Resources Assessment May 9, 2018 Table of Contents I. EXECUTIVE SUMMARY... 2 II. SUMMER 2017 REVIEW... 11 Demand... 11 Generation... 12 Interchange... 12 III. SUMMER 2018 ASSESSMENT... 14 CAISO Loads... 14 Hydro Generation...

More information

Grid-Scale Energy Storage

Grid-Scale Energy Storage Grid-Scale Energy Storage Saurav Mohapatra smohapa2@illinois.edu Department of Electrical and Computer Engineering University of Illinois at Urbana-Champaign NPRE 498: Energy Storage Systems 30 November

More information

2012 Grid of the Future Symposium. Innovations in Bulk Power System Reliability Assessment: A North American View

2012 Grid of the Future Symposium. Innovations in Bulk Power System Reliability Assessment: A North American View 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium Innovations in Bulk Power System Reliability Assessment: A North American View M.G.

More information

Value of Energy Storage in Utility Applications. Ben Kaun Sr. Project Engineer SVLG Energy Committee Meeting November 21, 2013

Value of Energy Storage in Utility Applications. Ben Kaun Sr. Project Engineer SVLG Energy Committee Meeting November 21, 2013 Value of Energy Storage in Utility Applications Ben Kaun Sr. Project Engineer SVLG Energy Committee Meeting November 21, 2013 Overview of Presentation EPRI Introduction Overview of Energy Storage Role

More information

Tucson Electric Power 2017 Integrated Resource Plan. Southern Arizona Regional Solar Partnership Jeff Yockey, PE

Tucson Electric Power 2017 Integrated Resource Plan. Southern Arizona Regional Solar Partnership Jeff Yockey, PE Tucson Electric Power 2017 Integrated Resource Plan Southern Arizona Regional Solar Partnership Jeff Yockey, PE May 2017 Integrated Resource Plan (IRP) Overview Just a Plan Additional steps for specific

More information

State-Federal RPS Collaborative

State-Federal RPS Collaborative State-Federal RPS Collaborative Solar Valuation in Utility Planning Studies Presentation by Andrew Mills, LBNL Hosted by Todd Olinsky-Paul, Project Director, CESA January 16, 2013 Housekeeping All participants

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO PROCEEDING NO. 17M-0694E

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO PROCEEDING NO. 17M-0694E BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO PROCEEDING NO. 17M-0694E IN THE MATTER OF THE COMMISSION'S REVIEW OF ITS RULES GOVERNING ELECTRIC RESOURCE PLANNING, IMPLEMENTING COLORADO

More information