Module 9. Robust 8D. Robust 8D. Module 9
|
|
- Suzan Skinner
- 6 years ago
- Views:
Transcription
1 Module 9 1
2 The Purpose of this module is to clearly define Ford Customer Service Division (FCSD) expectations as it relates to completion of 8Ds in response to service quality rejects 2
3 Understand the components of an 8D and FCSD s expectations in terms of 8D content Examples provided Know the importance of containment at each link in the supply chain 3
4 8D is: A Problem-solving methodology for product and process correction and improvement Simple and effective problem solving technique Structured into eight disciplines(d1-d8) Emphasizes team synergy 4
5 5
6 The focus of D1 is to establish the team necessary to solve the problem and implement corrective actions and to begin the team building process When determining team membership: Limit membership to between four and 10 members Choose members with the right skills, knowledge, resources, authority, etc., to solve the problem at hand Choose the right mix of qualifications Change team membership as needed 6
7 A description of the problem provided by Ford. This field can t be modified. The description will provide the following: Statement of the problem found Information for the packaging label Picture of the nonconforming part and if available the correct part If applicable packager information 7
8 When you develop an ICA, you: Protect the customer from the effects of the problem Contain the problem from a cost, quality and timing perspective 8
9 Containment process consists of D1-D3 Enter into QIM within 2 business days of receiving a quality reject D1 Establish the Team Name, Title, and Phone Number, for each team member D2 Problem Description Description created by FCSD and is view only for a Supplier D3 Interim Containment Define, Stock in Facility, Stock In Transit, Stock at Packager, Similar Parts and Other 9
10 Facility In Transit Packager Similar Parts What is the fallout rate of parts inside the manufacturing plant? What is being done immediately to ensure no defective parts leave the plant? Are parts in transit to a Ford facility? Are parts in transit to a Packager facility? Are Like parts affected? Are parts at a Packager? If so, are we certain that they meet spec.? If uncertain, advise disposition of parts at packager Have RH or LH parts been identified with the defect? Are parts of a different color affected? Are parts a level up or down affected? 10
11 Report if any of the rejected part or any like parts are in your facility. Contained 375 door trim panels in house, no problems found. Found and fixed 30 pieces of RH rocker arms identified as LH in warehouse. No headliners to contain, all pats made to order. 500 wheel covers contained, no gloss problems found. 100 crankshafts in finished goods, 50 have corrosion and 50 are rust free. 11
12 Report if any of the rejected part or any like parts are on their way toward FCSD depots or Packagers in a truck. 20 pieces XL3Z-1130-AA, 12 pieces XL#Z-1131-AA, X pieces of similar parts Y & Z are in transit. Conveyance # : LMNOP Contacted packager, all like product in transit contained. No Product in transit. Shipped 1000 pieces of the rejected part on (3/1/15.) 12
13 Report if any of the rejected part or any like parts are at a packager or at FCSD. Informed Packager the parts they have in house are nonconforming. Worked with the Packager to exchange parts for parts to specification This part nor similar parts currently at the Packager. 13
14 Report if Similar Parts are involved with this concern. o Ask yourself and report: What like parts did we ship with the rejected parts? o Parts across different car lines Escape, Focus, Mustang, etc. o Various colors shipped o Model years shipped o RH vs. LH parts o Different engineering levels 14
15 Focus on the process, not the people What has changed? Multiple Root Causes Most likely causes Weight multiple root causes (i.e. 80% or 20% at fault) Utilize Quality Tools 5 Whys Review Process Flow Diagram for Escape Points Is / Is Not Fishbone Diagram 15
16 Used to identify the fault. Cross functional team asks Why 5 times in effort to determine root cause. Built into the QIM system. Example Fault: Wrong part was shipped 1. Why? Parts were labeled incorrectly 2. Why? New service part number launched at supplier 3. Why? Engineering part number changed and it was assumed the Service part number should change 4. Why? Failure to properly manage the change 5. Why? Lack of understanding of Ford Service parts and failed to ship according to their release 16
17 Used to understand how the problem escaped to the customer and identify the escape point: Review the process flow focusing on the location in the process where the root cause occurred. Determine if a control system exists to detect the problem. Are service unique requirements included? 17
18 Is / Is Not Used to develop the correct Problem Statement Ask: What s wrong with what? Ask Next: Do we know why this is happening? 18
19 A graphical representation used to organize and display the interrelationships of various possible root causes of a problem. Possible causes of a potential defect or failure are organized in categories and subcategories in a horizontal tree-structure, with the failure as the root node. 19
20 Current change over process (or lack of change over process) allows mixed product to be shipped to customers Once the part became service only production was moved to a line with no poke-yoke Change implemented internally, but Ford was not notified via proper channels (SREA, WERS Alert) Change was approved via SREA by Ford, but no new notice was issued and no new print was approved 20
21 D5 focuses on decision making and verification. By focusing on these two steps, you can: Make the best decisions based on benefits and risks Verify that the chosen solution will work Any PCA you choose should: Fix the problem at the root cause level Generate no additional problems Be verified to work 21
22 Revised current change over process to include first piece and last piece inspection at each change over Developed a process to ensure that the control plan and PFMEA are followed when an OE part becomes service only to ensure appropriate error proofing is in place Revised Manage the Change process to include validation of revised Ford Notice and print, as well as PPAP approval at level 3 to ensure customer approval pf the change 22
23 D6 is when you implement the PCA to eliminate the root cause of the problem. Validation makes sure the PCA works as intended after implementation. Develop an implementation plan for the PCA Once PCA has been validated to work, remove the Interim Containment Action (ICA) Monitor long-term results 23
24 Since first and Last piece inspection implemented for all changeovers, 2 months ago, no discrepancies have been found Reviewed 3 specific part numbers that moved from OE to service only line. All 3 parts have documented Manage the Change review and original error proofing is still in place Include inspection date(s), part number(s), quantity inspected, and inspection results Verified that new notice number, print, and Fordapproved PSW have been received for the last 3 design changes 24
25 Behind every problem that creates the need to do a G8D, there is at least one system, practice, procedure, or policy that allowed the problem to occur and escape. Document changes to Procedures Policies Work instructions PFMEA, Process Flow Diagram Control Plan Ensure that service specific processes are added to these documents Train employees in the new procedures, etc. Determine whether this PCA should be applied systemically Other manufacturing lines Other Manufacturing plants Document technical lessons learned 25
26 Sincerely recognize both team and individual contributions Celebrate Team Commitment Problem resolution Process improvement Be Creative Be Timely 26
27 D1-Establish Team Reference Desk Procedures QIM-DP-11-Input Supplier 3D Comments QIM-DP-13-Input Supplier 8D Comments *Training Material for QIM can be found on the FCSD Supplier Quality Portal 27
28 D2-Problem Description (Automatically populated) Attachments tab- All supporting Documents including the picture of the nonconforming part and if available the correct part 28
29 D3 - Supplier Containment Note: For K type rejects written by a Packager use the Stock at Packager field below for the 3D Containment and Disposition responses. 29
30 30
31 D4-Root Cause 31
32 D5-Choose & Verify Perm. Corrective Actions 32
33 D6-Implement & Validate Perm. Corrective Actions 33
34 D7-Action(s) to Prevent Reoccurrence 34
35 D8-Congratulate Your Team Note:8Ds closure requirement is 60 days which includes the STA s review. 35
Module 12 Recipe for Service Parts Success
Module 12 1 The goal of this module is to provide actionable steps to implement the Parts Success. This plan of action has been developed over several years of FCSD STA experience with more than 1700 suppliers.
More informationSupplier QR Disposition (QIM)
Supplier QR Disposition (QIM) Module 2 1 The Purpose of this module is to clearly define Ford Customer Service Division (FCSD) expectations as it relates to completion of Supplier Disposition in response
More informationAppendix C: Non Conformance Notification and Corrective Action Request
The purpose is to define Master Lock LLC., and Waterloo Industries Inc. specific requirements for documenting and distributing corrective/preventive actions. This process applies to all Domestic and International
More informationSupplier Quality Manual
Supplier Quality Manual February 2010 Page 1 of 6 Table of Contents 1.0 Purpose 2.0 Scope 3.0 Quality System Requirements 4.0 Supplier Assessments 5.0 Advance Product Quality Planning 6.0 First Article
More informationParts Claims Analysis/Disposition Training
Parts Claims Analysis/Disposition Training http://fcsdpcsclaims.ford.com/supplierhome.aspx PURPOSE The purpose of this module is to provide a high level overview of the Parts Claims System (PCS) website,
More informationSupplier Quality Requirements Manual
Supplier Quality Requirements Manual ISO-020-1 Revision G January 20, 2012 ISO-020-1 Rev G 01/20/12 Page 1 of 17 Table of Contents Quality Commitment and Expectations... 3 SECTION 1- Introduction... 4
More informationHow to perform PPAP Level 1 Level 2 Level 3 Level 4 Level 5
How to perform PPAP The process of completing a PPAP submission is complex. This detailed process is a collection of key elements that must be completed to verify that the production process will produce
More informationSupplier Quality Specification 3DS Document P14 Rock Hill, South Carolina Revision A
Supplier Quality Specification 3DS Document 51000-P14 Rock Hill, South Carolina Revision A Revision History Change Description Revision Date All New Release 6/26/16 A Updated supplier classification section,
More informationSupplier Quality Requirements FSQ01
Supplier Quality Requirements FSQ01 1 Change Revision Level Date Introduced 0 25/06/2013 2 1. Scope 2. Code of Conduct 3. Acronyms and Definitions 4. Prohibited and Restricted Materials Policy 5. Quality
More informationGLOBAL PURCHASING. Supplier Technical Assistance. Phased PPAP
GLOBAL PURCHASING Supplier Technical Assistance Phased PPAP Edition 1, October 2002 Phased Production Part Approval Process Phased PPAP Ford Motor Company Supplier Technical Assistance October, 2002 Table
More informationDaimlerChrysler (Chrysler Group) Customer-Specific Requirements
DaimlerChrysler (Chrysler Group) Customer-Specific Requirements For Use With ISO/TS 16949 Second Edition September, 2005 1. Scope ISO/TS 16949 and this document define fundamental quality system requirements
More informationSupplier Quality Standard
Supplier Quality Standard Sherex Industries & Sherex Fastening Solutions "First Time Quality at the Source" Through Teamwork Supplier Quality Standard Edition: Rel. September 6, 2007 This document is controlled
More informationMetric Manufacturing Supplier Manual
Metric Manufacturing Supplier Manual This Manual applies to all suppliers of Metric Manufacturing Co. Compliance to all requirements within this manual, as well as the general terms and conditions, are
More informationSUPPLIER QUALITY REQUIRMENTS MANUAL (SQRM)
SUPPLIER QUALITY REQUIRMENTS MANUAL (SQRM) 11/3/2008 Page 1 of 12 PURPOSE The purpose of this manual is to provide Suppliers with the DeltaTech Control (DTC) requirements for various items related to the
More informationEdition: Revision 09, February 19, This document is controlled by: Mayco International, LLC. Edited by
Working together as a team QUALITY AT THE SOURCE Page: 2 of 24 Supplier Quality Standard Edition: Revision 09, February 19, 2018 This document is controlled by: Mayco International, LLC Edited by Mayco
More informationPHRED 8D Problem Solving Software. PHRED Solutions Nick Rennie +1 (970)
PHRED 8D Problem Solving Software PHRED Solutions Nick Rennie nick@phredsolutions.com +1 (970) 453-5235 Why use PHRED for Problem Solving? One Single System handle all problems from the customer complaint
More informationNew Global Packaging Reminder To All Service T-Role (Total) Suppliers Shipping In Unitized Packaging
New Global Packaging Reminder To All Service T-Role (Total) Suppliers Shipping In Unitized Packaging Supplier Recognition Corner FCSD now requires all T-role suppliers to use the new global labels and
More informationWelcome to the 2017 Supplier Training and Communication Day
Welcome to the 2017 Supplier Training and Communication Day Presented by the GHSP Supply Chain Management team OBJECTIVES Working Together, Enhancing Value Provide our supplier partners with training relative
More informationNONCONFORMANCE MODULE PROCESS FLOW
NONCONFORMANCE MODULE PROCESS FLOW SUPPLIER DEVIATION REQUEST (SR) TYPE NC SUPPLIER CREATION OF A SR TYPE NC PROCESS FLOW PURPOSE: This document illustrates the process flow and provides the specific screen
More informationSupplier Containment
Page 1 of 14 1. PURPOSE The purpose of supplier containment is to protect the customer by preventing nonconforming material from being shipped to Delphi Technologies or subsequently passed to Delphi Technologies
More informationSupplier Expectation Manual
Supplier Expectation Manual Page 1 Sterling Spring Supplier Philosophy Products and services from external providers (suppliers) are intended for incorporation into Sterling Spring s own products and services
More informationSupplier Improvement Metrics Overview
Module 4 1 The purpose of this module is to provide an overview of the Metrics (SIM) website 2 Understand how to access the Supplier Improvement Metrics website Understand how to retrieve pertinent information
More informationMontaplast of North America, Inc.
Montaplast of North America, Inc. Supplier Quality Manual Page 1 of 20 Table of Contents 1.0 Purpose pg. 3 2.0 Scope pg. 3 3.0 Quality System Requirements pg. 3 4.0 Approved Supplier List pg. 4 5.0 Supplier
More informationChapter 7 Reporting System
Transportation Technology Center, Inc., a subsidiary of the Association of American Railroads Chapter 7 Reporting System Credit AAR/RSI TAG Committee: Joy Cooke Ray Morgan Rick Szromba David Burke Jennifer
More informationSupplier Quality Manual
including subsidiaries of Mexico and Canada Supplier Quality Manual Issue date: March 1, 2010 Revised: April 7, 2011 Page 1 of 14 Corporate Quality Statement Quality plays a vital role in SCHOTT Gemtron
More informationSupplier Quality System Survey
Supplier Division Address Date: Quality Contact: Reports to: Title: Title: Phone Fax e-mail Plant size (ft 2 ): Union: Contract expires: Total Employment: Direct Labor: Shifts: QA employees: This report
More informationSUPPLIER QUALITY MANUAL
SUPPLIER QUALITY MANUAL ASYST Technologies, LLC 5811 99TH AVENUE KENOSHA, WI 53144 PHONE (262) 857-2244 FAX (262) 857-3623 Approval Signatures APPROVAL SIGNATURES Name / Title Contact Information Approval
More informationSupplier Deviation Process Self paced training module Rev:A Revision Date 12/10/2014. A JSJ Business
Supplier Deviation Process Self paced training module Rev:A Revision Date 12/10/2014 Training Objectives Describe what the Supplier Deviation process IS and IS NOT Define when the Supplier Deviation form
More informationSupplier Quality Manual (QQS )
Monticello Spring Corporation Quality Management System Supplier Quality Manual (QQS 100.00) 1.0 Introduction 1.1 Scope The details stipulated in this manual are the minimum mandatory requirements for
More informationSUPPLIER QUALITY ASSESSMENT
Supplier Organization Name: Supplier Number: Street Address: Date of This Audit: City, State, Zip Code: Date of Last Audit: Country: of Employees: Main Phone Number: of Buildings/Size: Fax Number: Principal
More informationSUPPLIER QUALITY MANUAL
SUPPLIER QUALITY MANUAL LM-QU-PA-008 Revision Date:7/13/18 LM-QU-PA-008 Revision Date:7/13/18 Table of Contents 1.0 Purpose 2.0 Scope 3.0 Quality System Requirements 4.0 Approved Supplier List 5.0 Supplier
More information10/24/18. Printed document is uncontrolled after 10/24/2018, unless in a controlled book
10/24/18 Table of Contents Description Page CTA Acoustics Expectations 1 How to submit samples 2 How to process Corrective Action 3-7 How to request a temporary or permanent change 8-9 How your performance
More informationSUPPLIER GUIDELINES MANUAL
1.0 INTRODUCTION 1.1 This guidelines manual defines the minimum requirements for Supreme Machined Products Co.; Inc. LTD (to be referenced as Supreme throughout the document) Supplier s and does not supersede
More informationIntegrated Quality Systems
Integrated Quality Systems Introduction THE PRODUCT IQS provides a powerful and proven solution that offers a unique model for integrating quality systems to achieve superior enterprise-wide performance.
More informationIntegrated Supplier Quality Requirements
Integrated Supplier Quality Requirements April 1, 2013 ISQ-001-QM Revision B The controlled and current version of this document is available on www.navistarsupplier.com. Supplier Quality Lifecycle Management
More informationCase Study. Contract Manufacturer C19 Failure Analysis. CM C19 Failure Analysis 2014 SWC Page!1
Case Study Contract Manufacturer C19 Failure Analysis CM C19 Failure Analysis 2014 SWC Page!1 Contents Introduction............................. Page 2 Document Review........................ Page 3 Process
More informationWestern Diversified Plastics, LLC. Supplier Requirements Manual
Western Diversified Plastics, LLC. Supplier Requirements Manual Revision Date: 12/10/2019 TABLE OF CONTENTS 1.0 Introduction.. 3 2.0 WDP Supplier Policy.. 4 3.0 Scope... 4 4.0 Launch Readiness Measures...
More informationPRODUCTION PART APPROVAL PROCESS. Peter BÓLLO
PRODUCTION PART APPROVAL PROCESS Peter BÓLLO Author: Workplace: Address: E-mail: Peter Bóllo Johnson Controls spol. s r.o., Bratislava Business Centre Sturova 4, 81102 Bratislava, Slovak Republic Peter.Bollo@jci.com
More informationUnion Pacific Railroad. Supplier Excellence Manual. Contents
Union Pacific Railroad Supplier Excellence Manual Contents Union Pacific Railroad... 1 Supplier Excellence Manual... 1 1.0 Doing Business with Union Pacific... 4 1.1 About Union Pacific... 4 1.2 Purpose
More informationDaimlerChrysler Customer Specific Requirements For PPAP 4th Edition March, 2006
1 DaimlerChrysler - Specific Instructions Unless superseded by specific written direction from a DaimlerChrysler Procurement and Supply representative, or by engineering drawing and specification requirements,
More informationRoot Cause Analysis & Systemic Corrective Action
Root Cause Analysis & Systemic Corrective Action Presented by Shannon Craddock of Perry Johnson Registrars, Inc. August 2018 Today s Agenda Why are we doing this? Audit Finding Actions Taken to Correct
More informationRoot Cause Analysis & Systemic Corrective Action
Root Cause Analysis & Systemic Corrective Action Presented by Shannon Craddock of Perry Johnson Registrars, Inc. February 2015 Today s Agenda Why are we doing this? Audit Finding Actions Taken to Correct
More informationCD Supplier Handbook. * Marine Canada Acquisition Limited Partnership DBA Teleflex Canada
* 2 / 8 TABLE OF CONTENTS 1. Section One Introduction 1.1. Objective 1.2. Scope 2. Section Two Quality Expectations 2.1 Change Notification 2.2 Quality Data & Records 2.3 Verification of Supplier's Products
More informationHella 8D Report_ Supplier Training Material. Lippstadt HCC-PU-QM
Hella 8 Report_ Supplier Training Material Lippstadt 07--0 HCC-PU-QM HF-776EN_C (0-0) Motivation to make the 8 Report How to fill out Hella 8 Report 8 Report Evaluation 8 Training suppliers Keppmann HCC-PU-QME
More informationTable of Contents. 1.0 Purpose. 2.0 Scope. 3.0 Quality System Requirements. 4.0 Approved Supplier List. 5.0 Supplier Assessments
Issued 2/6/2009 Revision: 2/13/2017 Table of Contents 1.0 Purpose 2.0 Scope 3.0 Quality System Requirements 4.0 Approved Supplier List 5.0 Supplier Assessments 6.0 Advance Product Quality Planning (APQP)
More informationQRS-107 Management of Non-Conforming Articles
QRS-107 Management of Non-Conforming Articles QRS-107 Issue 01 Page 1/11 QRS-107 Management of Non-Conforming Articles Issue Date: Issue: 01 CHANGES LOG Issue Approval Date Main changes 00 April 2015 First
More informationSupplier. Quality. Manual
DEPARTMENT: Quality Assurance Title: Supplier - Quality Manual ISSUED ON: 29-Jul-09 PAGE 1 of 12 Supplier Quality Manual Distribution to: Electronically controlled. If this document is in hard copy it
More informationLevel & Stable Operations
Getting Started with Lean Manufacturing Principles in Flexible Substrate Coating and Converting Dave Schoellerman Tollcoating.com by Carestream Health, Incorporated info@tollcoating.com Abstract Lean manufacturing
More informationASA ANNUAL CONFERENCE 2014 WASHINGTON, DC THE 8D DISCIPLINE TO EFFECTIVE PROBLEM SOLVING
1 ASA ANNUAL CONFERENCE 2014 WASHINGTON, DC THE 8D DISCIPLINE TO EFFECTIVE PROBLEM SOLVING G. RINGGER CONSULTING, INC. Celebrating 30 years in the aerospace/aviation industry! Providing Engineering, Quality
More informationSupplier Quality Manual
Supplier Quality Manual Document No. F-PM010 Rev 3 Owner Supplier Quality Page 1 OF 11 TABLE OF CONTENTS 1.0 Purpose 3 2.0 Scope... 3 3.0 Quality System Requirements... 3 4.0 Approved Supplier List (ASL).
More informationSupplier Quality Manual CHASSIX Inc.
Supplier Quality Manual CHASSIX Inc. SQM-001 rev 6/26/17 Page 1 TABLE OF CONTENTS 1.0 INTRODUCTION 1.1 CHASSIX QUALITY POLICY 1.2 CHASSIX SUPPLIER QUALITY MANAGEMENT SYSTEM REQUIREMENTS 1.3 CHASSIX SUPPLIER
More informationQuality Manual ISO 9001:2000
Quality Manual ISO 9001:2000 Page 2 of 23 TABLE OF CONTENTS COVER PAGE...1 TABLE OF CONTENTS...2 SIGNATURES...3 QUALITY POLICY...4 INTRODUCTION...5 CORPORATE PROFILE...9 4.O QUALITY MANAGEMENT SYSTEM...10
More informationSupplier Quality System Requirements Manual
Supplier Quality System Requirements Manual This manual available ON-LINE at www.axletech.com website Quality Policy "AxleTech International is committed to exceeding our customers expectations by continually
More informationSUPPLIER MANUAL Released 5/16/2012 Revised 11/12/2016
SUPPLIER MANUAL Released 5/16/2012 Revised 11/12/2016 TABLE OF CONTENTS 1.0 Introduction 1.1 Purpose of Supplier Requirements 1.2 Scope 2.0 Quoting 3.0 Advance Product Quality Planning (APQP) 3.1 APQP
More informationSupplier Quality Manual CHASSIX Inc.
Supplier Quality Manual CHASSIX Inc. SQM-001 rev 8/2/17 Page 1 TABLE OF CONTENTS 1.0 INTRODUCTION 1.1 CHASSIX QUALITY POLICY 1.2 CHASSIX SUPPLIER QUALITY MANAGEMENT SYSTEM REQUIREMENTS 1.3 CHASSIX SUPPLIER
More informationRoot Cause Analysis Problem Identification and Tools. DIOSH March 2016
Root Cause Analysis Problem Identification and Tools DIOSH March 2016 About IMEC Who we are: IMEC is a private, public partnership that operates through the National Institute of Standards and Technology
More informationSupplier Quality Manual. Autoneum Group Supplier Quality Manual
Autoneum Group Supplier Quality Manual Owner: Autoneum Group Quality Revision No.: 1 1 of 21 Table of Contents 1. Introduction 5 1.1. Overview 5 1.2. Purpose of this manual 5 1.3. Supply chain 5 2. Supplier
More informationGlobal Supplier Standards Manual- Supplier Quality September
PURPOSE The purpose of the Global Supplier Standards Manual is to communicate the requirements of Motus Integrated Technologies (Motus) to our suppliers. It is the expectation of Motus that all suppliers
More informationKSS GLOBAL STANDARD. Supplier Request for Engineering Approval (SREA) Procedure KSS 701
KSS GLOBAL STANDARD Supplier Request for Engineering Approval Procedure KSS 701 Document No: 1005107 Author: Alexandru Iedu Christa Kerlin Joachim Verheugen Approved by: Kevin Gillis Todd Gross Rodolfo
More informationSUPPLIER MANUAL. Griffith Rubber Mills - HQ 2625 Northwest Industrial Street Portland, Oregon 97210
SUPPLIER MANUAL Griffith Rubber Mills - HQ 2625 Northwest Industrial Street Portland, Oregon 97210 TABLE OF CONTENTS Page Title 1... Introduction, Purpose, Scope Quality Policy, Certification & Exemptions
More informationVU Manufacturing Supplier Quality Manual
Supplier Quality Manual Revision 08, February 26, 2018 Table of Contents Section Preface Page 3 A. Quality System Page 4 B. Advanced Quality Planning Page 4 C. Continuous Improvement Page 5 D. Production
More informationQUALITY PLANNING II. Study supports
PROJECT IRP Creation of English Study Supports for Selected Subjects of the Follow-up Master Study in the Quality Management Study Field IRP/2015/104 QUALITY PLANNING II Study supports Jiří Plura Language
More informationGlobal Supplier Standards Manual - Quality Standard
Proprietary and Public 01-April-2018 Rev 1.0 Page 1 of 17 1.0 Purpose This standard communicates Adient s minimum set of requirements to suppliers. It is the expectation of Adient that all suppliers -
More informationTable of Contents Table of Contents... 2 Introduction to Manual... 3 Scope... 3
Supplier Quality Manual Original Issue 12 February 2015 Uncontrolled in printed form Page 1 of 8 f Table of Contents Table of Contents... 2 Introduction to Manual... 3 Scope... 3 Supplier Responsibility...3
More informationTable of Contents. 1.0 Introduction 1.1 Overview 1.2 Customer Responsibilities
1400 Lunar Drive Wapakoneta, OH 45895 Supplier Manual Table of Contents 1.0 Introduction 1.1 Overview 1.2 Customer Responsibilities 2.0 Supplier Quality Expectations 2.1 Quality System Requirements 2.2
More informationDocument Routing/Approval Record
Reason for Revisions and Sections Affected: Document Routing/Approval Record Revision A Initial Release Revision B 6.1 Paragraph 3: Added: new or, deleted: of the new facility. 6.1 Paragraph 4: Added:
More informationSupplier Overview of Johnson & Johnson MD&D Supplier Quality Standard Operating Procedures (SOPs)
Supplier Overview of Johnson & Johnson MD&D Supplier Quality Standard Operating Procedures (SOPs) Supplier Responsibilities for Failure Investigations and Problem Solving Purpose of this SOP Establishes
More informationTRICO PRODUCTS PUR-C-P106-A
TRICO PRODUCTS PUR-C-P106-A October 9, 2009 Supplier Guide Page 1 of 14 TRICO PRODUCTS PUR-C-P106-A October 9, 2009 Page 2 of 14 NAME: TRICO Supplier Guide PURPOSE: The purpose of this document is to communicate
More informationSupplier Quality Systems Requirements Manual
Supplier Quality Systems Requirements Manual Brink Towing Systems Version: 2.4 Date: 23-07-2018 Changed text in blue Page 1 / 9 Table of Contents 1. Introduction 3 1.1 Scope 3 1.2 Purpose 3 1.3 Background
More informationIts purpose is to define the approval process of new or revised parts, or parts resulting from new or significantly revised production methods.
SUPPLIER PPAP HANDBOOK NORTH AMERICA Revision D May 24, 2018 Table of Contents Table of Contents 1 Foreword.. 2 Production Part approval Process (PPAP) Purpose.. 3 When is a Submission Required?. 3 Significant
More informationRevcor Supplier Quality Manual
Revcor Supplier Quality Manual Documentation The Revcor is governed by comprehensive documentation as referenced herein. Procedures, work instructions, practices, forms, drawings, and similar documentation
More informationBlue Chip Engineered Products Supplier Quality Manual
Blue Chip Engineered Products Supplier Quality Manual Revision Date 07/09/2013 Page 1 Table of Contents A. Goal B. Purpose C. Approach D. Applicability E. Implementation F. Zero Defects Policy Section
More informationCh.3 Quality Issues.
Module 2 : Supply Environment. Ch.3 Quality Issues. Edited by Dr. Seung Hyun Lee (Ph.D., CPM) IEMS Research Center, E-mail : lkangsan@iems.co.kr Resolving Quality Problems. Documentation of Corrective
More informationSupplier Requirements Manual
Supplier Requirements Manual 1.0 Control Responsibility TABLE OF CONTENTS 1.1 Proprietary Information Sharing 1.2 Purpose & Approval 1.2.1 Scope 1.3 Quality Systems Management & Evaluation 1.3.1 QMS 1.3.2
More informationOverview of Production Part Approval Process PPAP. Factor Quality, Inc.
Overview of Production Part Approval Process PPAP Factor Quality, Inc. Purpose of the PPAP To determine if the supplier understands all customer requirements and if the production process has the potential
More informationSUPPLIER QUALITY MANUAL
Work Instruction Standard Locknut, LLC Supplier Quality Manual Doc. No. SQM-01 Page 1 of 11 Initial Date 11/1/2009 Rev. 4 Prepared By Dwight Beaty Revised By Shannon Smith Rev. Date 9/12/12 Approvals Purchasing
More informationLG SOURCING VENDOR QUALITY MANAGEMENT SYSTEM REQUIREMENTS
LG SOURCING VENDOR QUALITY MANAGEMENT SYSTEM REQUIREMENTS LG Sourcing QMS ver01 03.29.2010 Page 1 of 16 PAGE INTENTIONALLY LEFT BLANK Copyright 2010, LF Corporation - All rights reserved No part of this
More informationSupply Chain Supplier Quality Manual. Creation Date: 19 th September 2012 Last Updated: February 16, 2016 Revision Number: 03 Document Number: AQM005
Supply Chain Supplier Quality Manual Creation Date: 19 th September 2012 Last Updated: February 16, 2016 Revision Number: 03 Document Number: AQM005 1 Introduction Policy Statement Analogic suppliers have
More information0% # of Hrs Required to Complete Audit
Classification Supplier Assessment Cover Sheet Quality Production Location: Summary Visit Date : 1. All check items are NG. Safety/Regulation concerns exist. Impact to M/P. 2. N/G and level-up items exist
More informationSUPPLIER REQUIREMENTS MANUAL Revision 3. SUPPLIER REQUIREMENTS MANUAL Revision 3 GATES CORPORATION
SUPPLIER REQUIREMENTS MANUAL Revision 3 SUPPLIER REQUIREMENTS MANUAL Revision 3 GATES CORPORATION 1 TABLE OF CONTENTS Introduction 3 Social Accountability 4 Purpose 4 Scope 4 Supplier Responsibilities
More informationRENAULT GROUPE Customer-Specific Requirements for use with IATF st Edition version 2016
RENAULT GROUPE Customer-Specific Requirements for use with IATF 16949 1 st Edition version 2016 Renault 2017 - All rights reserved RPIFDQSCF20170011 version 1.0 1/10 Content 1. Scope... 3 2. References...
More informationIndustry Forum. Aerospace Management System Tools Training and Implementation Programmes. Web:
Industry Forum Aerospace Management System Tools Training and Implementation Programmes Web: www.industryforum.co.uk/training Email: courses@industryforum.co.uk Phone: +44(0)121 717 6600 Why choose Industry
More informationFord Customer Service Division (FCSD) North American Quality Office Newsletter
FCSD Supplier Quality Portal Supplier Recognition Corner The FCSD Supplier Quality Portal has been updated in support of the future launch of Quality Issue Management (QIM). The training material and the
More informationVernay Quality System Supplier Quality Manual
Table of Contents Revision: G Approvals: Manager, Quality Systems/Improvements NA Purchasing Manager Section A Overview Revision: G Page Approval 1 Table of Contents 2 Section A Section B Section C Section
More informationSUPPLIER QUALITY MANUAL
SUPPLIER QUALITY MANUAL QD-SUPPLIER-QUALITYMANUAL 1 of 13 02.20.15 TABLE OF CONTENTS Page A. Goal 3 B. Purpose 3 C. Approach 3 D. Applicability 3 E. Implementation 3 F. Zero Defects Policy 3 Section 1:
More informationQuality Management System
Quality Management System 6.1 Quality Q-Codes () 6.1 Quality Q-Codes Quality Clauses The following quality control clauses apply when specifically noted on the Gear Technology purchase order: Q1- Material
More informationCHAPTER 2 COST OF POOR QUALITY
CHAPTER 2 COST OF POOR QUALITY Expected Outcomes Understanding of how quality costs can be used in decision making Identify the interrelationships between and among the different types of quality costs
More informationSUPPLIER QUALITY SYSTEM SURVEY
SUPPLIER QUALITY SYSTEM SURVEY DATE (M/d/yy): 55 Dragon Court Woburn, MA 01801 Tel: (781) 933-7300 Fax: (781) 935-4529 GENERAL INFORMATION Supplier Name: Physical Address: City: State: Zip: Sr. Company
More information4. RELATED DOCUMENTS AND FORMS 4.1. AS ISO Cambridge Valley Machining, Inc. QMS procedures, including, but not limited to:
Approved By: Purchasing Manager Candice Lane (signature on file) Date: 5/26/17 Approved By: Process Owner James D. Moore (signature on file) Date: 5/26/17 1. PURPOSE 1.1. To define Cambridge Valley Machining,
More informationAdient Automotive Experience Global Supplier Standards Manual Chapter 4 Quality October, 2017
Change Log Revision Date Description of Change Rev 1.0 October 2017 New Adient release Rev1.0 PURPOSE The purpose of the is to communicate Adient, Inc. (Adient) requirements to the suppliers in our Automotive
More informationNon Conforming Product Management
Page: 1 of 5 PURPOSE: The control of Non-Conforming Material procedure is designed to ensure all materials are inspected at specific points of the process in order to identify nonconforming product. Where
More informationOverview. PROPF351 (SQA Unit Code - H9KP 04) Set up and control booklet making machinery. Set up and control booklet making machinery
(SQA Unit Code - H9KP 04) Overview This standard is for print finishers using booklet making. This can include in-line booklet making. They will be expected to set up the equipment and control it whilst
More informationPRODUCT ESCAPES HOW AUDITORS CAN HELP TO MINIMIZE
PRODUCT ESCAPES HOW AUDITORS CAN HELP TO MINIMIZE Michelle Barton Director Aerospace Program DQS Inc. WHAT IS A PRODUCT ESCAPE? Any product released by an internal or external supplier that is subsequently
More informationSupplier Quality Manual. QF-SQR001 / Rev. Date: / Rev. Level: D
1 Table of Contents COMMITMENT TO SUPPLIERS 4 SUPPPLIER CERTIFICATION REQUIREMENTS 5 SUBCONTRACTOR DEVELOPMENT 6 CERTIFICATE OF CONFORMANCE 6 ENGINEERING AND PROCESS CHANGES 7 MATERIAL LABELING 8 IMDS
More informationGlobal Supplier Manual Appendix T Ford Customer Specific Requirements for Suppliers. October 26, 2017
Global Supplier Manual Appendix T Ford Customer Specific Requirements for Suppliers October 26, 2017 TABLE OF CONTENTS Contents TABLE OF CONTENTS... 2 Scope of this document:... 3 Responsibility:... 3
More informationSupplier Quality Manual
Supplier Quality Manual 1 1. Introduction Scope Purpose Application Implementation 2. Purchasing Expectations Terms and Conditions Engineering / Technical Support Customer Support Resources Pricing Consistent
More informationSupplier Rating System (SRS)
Supplier Rating System (SRS) Aerojet Rocketdyne March 2017 1 Supplier Rating System As a supplier to Aerojet Rocketdyne, you should know and understand our supplier rating system. Aerojet Rocketdyne uses
More information