1 White Rose Extension Project - Expression of Interest (EOI)/Prequalification Provision of Topsides Marine Transportation Reference No Husky Energy Inc. (Husky), operator of the White Rose field and satellite extensions, is seeking Expressions of Interest (EOIs) and Prequalification responses from interested experienced companies/groups for the provision of Topsides Marine Transportation. Together with its co-venture partners, Husky Energy is developing the West White Rose Extension with a wellhead platform (WHP) consisting of topsides supported by a concrete gravity structure (CGS). The WHP will serve as a fixed drilling rig and will be located at the White Rose field, approximately 350 kilometres offshore Newfoundland & Labrador. The project is subject to final Husky, partner and regulatory approvals. General Requirements Interested companies/groups must be qualified to conduct the work as outlined in the Scope of Work and are asked to demonstrate their capabilities and experience via a formal response to the Prequalification Questionnaire. The Prequalification Questionnaire is largely based on the Husky Operational Integrity Management System (HOIMS) and contains detailed questions regarding your company s technical, HSE-Q and commercial capabilities. Given the complexity and scope of the services required, consideration will only be given to companies/groups that can provide a total solution. To demonstrate capabilities and experience, interested companies/groups must submit documented evidence of delivering and supplying similar packages in strict accordance with relevant industry regulations, codes and standards and statutory authorities.
2 Scope of Work In support of the White Rose Extension Project, Husky will require the services of qualified and experienced contractors for the provision of Topsides Marine Transportation. 1.0 GENERAL Husky Energy is seeking Expressions of Interest from Marine Transportation Contractors for transportation services to ship its White Rose Extension Project (WREP) wellhead platform topsides (ref. Figure 1) from the topsides fabrication yard (Far East or USA Gulf of Mexico regions, TBD) to Conception Bay, NL, Canada. The wellhead platform topsides will be shipped in a fully integrated condition with the living quarters, drilling equipment set, transition structure, flare boom and other miscellaneous structures installed (ref. Figure 2). Once in Conception Bay, NL, Canada, the successful Contractor will interface with the Topsides Installation Contractor s (TIC) vessel, Pieter Schelte, to transfer the topsides to the installation vessel prior to final transportation to the White Rose field for installation on the pre-installed CGS. The principal particulars for the WHP topsides are below: Estimated Topsides dry transport weight = 23,000 tonnes Estimated grillage and seafastening weight = 2000 tonnes ( additional to the topsides dry transport weight) Length = 72.5m, excluding appurtenances Width = 40m, excluding appurtenances Estimated Vertical Center of Gravity (VCG) elevation above deck of transport barge/vessel = 33.2m Husky anticipates issuing a formal bid package late Q2 2014, with contract award in late Q Transportation of the WHP topsides is anticipated to occur at the beginning of Q
3 Figure 1 Husky WREP Wellhead Platform
4 Figure 2 Topsides Transportation Scope Delineation TRANSPORTATION SCOPE
5 2.0 SCOPE OF WORK SUMMARY 2.1 PROJECT MANAGEMENT Successful Contractor shall provide all project management, environment, health and safety management, quality management, interface management, planning and scheduling, and cost control services for the planned marine operations pertaining to the topsides transportation. Successful Contractor shall develop an organizational structure and define the roles and responsibilities of key personnel involved with the marine operations prior to the execution of any work. Successful Contractor shall develop a logic linked schedule for its scope of work defining activities, durations and deliverable dates for its scope. Also, the successful Contractor is to provide required on site dates for key input or hardware provided by Husky or Husky s contractors. Superintendents shall possess a thorough knowledge and have experience of the entire marine operation. Key personnel shall have knowledge and experience within their own area of responsibility. Successful Contractor is responsible for ensuring that documentation and procedures are produced in sufficient time to allow time for marine personnel to familiarize themselves with the proposed operation. Successful Contractor s procedures will be subject to review and approval by the Marine Warranty Surveyor (MWS) and 3 rd Party Verification Authority as nominated by Husky. Procedures must be produced in a timely matter consistent with the schedule to be agreed upon by Husky and the successful Contractor. 2.2 ENGINEERING General Successful Contractor shall perform all engineering studies, calculations and analyses necessary to verify that the planned marine operations can be performed safely and effectively, to minimize weather related downtime and to comply with all pertinent rules and regulations. All assumptions, methodologies and tools used in these studies shall be approved by Husky prior to successful Contractor commencing the work. More specifically, successful Contractor shall perform the following engineering activities as a minimum: Load-out a) Interface with the Topsides Fabrication Contractor (TFC) and the Topsides Engineering Contractor (TEC) to ensure all requirements and limitations with respect to quay-side water depth, tidal variations, mooring hardware, skid shoe and skid track arrangements, etc. are understood and incorporated into all plans. b) Interface with the MWS to ensure all project, regulatory and class requirements are satisfied. c) Assess the stability of the transport vessel during the load-out operation and identify any additional buoyancy elements, if necessary, to provide the requisite stability. d) Develop the ballasting plan for the load-out operation. e) Assess the global and local structural integrity of the transport vessel during the load-out operation, and design all global and local strengthening, as required. f) Design of grillage and seafastening, including any local reinforcing, based on the grillage and seafastening concept jointly developed with the TEC. g) Design of ship-side link beam connections, including any local reinforcing.
6 h) Design of mooring and fendering arrangement for the load-out operation. Transport a) Interface with the MWS to ensure all project, regulatory and class requirements are satisfied. b) Assess the stability of the transport vessel during the transport operation, and identify any additional buoyancy elements, if necessary, necessary to provide the requisite stability. c) Develop the ballasting plan for the transport operation. d) Assess the global and local structural integrity of the transport vessel during the transport operation, and design all required global and local strengthening. e) Design of seafastening for additional buoyancy elements, if required. Seafastening design shall consider the effects of wave slam if the additional buoyancy elements overhang the transport vessel. f) Perform motions analysis for the tow route and provide the Topsides Engineering Contractor with the data necessary to perform strength and fatigue assessments of the cargo. Transfer a) Interface with the TIC and the TEC to ensure that all requirements and limitations associated with the transfer operation and the installation vessel, Pieter Schelte, are understood and incorporated into all plans b) Interface with the MWS to ensure all project, regulatory and class requirements are satisfied c) Develop plans for removal of seafastening and grillage at the inshore site at Conception Bay, NL, Canada, as required to transfer the cargo from the transportation vessel to the installation vessel. d) Interface with the TIC with respect to the mooring and fendering arrangement for the transportation vessel for the cargo transfer. e) Assess stability of the transport vessel during the transfer operation. f) Develop ballasting plan for the transfer operation, in conjunction with TIC. g) Assess global and local structural integrity of the transport vessel during the transfer operation, and design of all global and local strengthening as required. 2.3 OPERATIONS Successful Contractor shall provide a transport vessel that is fit for purpose for the planned marine operations. Successful Contractor shall demonstrate how the nominated vessel meets the project requirements with respect to payload capacity and cargo deck space, hull strength, stability, propulsion system, control and maneuverability, navigation and communication equipment, ballast water systems, mooring/anchoring equipment, and safety equipment. Successful Contractor shall provide all test reports and certifications related to safety equipment, backup systems, DP systems, and all project-specific equipment, as well as Class and Flag State documentation for compliance with classification, certification, Flag State, Port State and International Maritime Organization (IMO) requirements. Successful Contractor shall be responsible for fabrication and installation of all required vessel modifications, such as the cargo support grillage, supply and installation of any additional buoyancy elements (if required) and local structural reinforcing of the transport vessel as required. Fabrication and installation of the cargo seafastening will be performed by the TFC, under the direct supervision of successful Contractor. Successful Contractor shall be responsible for removal and disposal of the grillage and seafastening.
7 Successful Contractor shall interface with port authorities to ensure all requirements and limitations with respect to vessel maneuvering, interruptions to marine traffic, stand-by locations, installation of temporary moorings, marine pilots and use of harbor tugs are incorporated into all plans. Successful Contractor shall develop an operations plan which covers the following elements as a minimum: a) Transit route (e.g. waypoints, draft requirements, and physical and environmental limitations at departure port, en-route, and arrival port, etc.). b) Ports of refuge. c) Customs and immigration plans for entering and clearing ports, including refueling/resupply ports and ports of refuge. d) Met-ocean data (e.g. vessel performance and capabilities under the extreme met-ocean conditions for the specific transport route and time of year). e) Procedures (e.g. emergency response and incident reporting, weather monitoring and forecasting, mobilization/demobilization/logistics, contingency operations, security/anti-piracy, refueling/resupply, vessel daily report, etc.). Husky strongly supports providing opportunities to Canadian and, in particular Newfoundland and Labrador companies and individuals, on a commercially competitive basis. Pre-qualified companies will be required to complete a Canada/Newfoundland and Labrador Benefits Questionnaire at the bid stage. Husky also encourages the participation of members of designated groups (women; Aboriginal peoples; persons with disabilities; and members of visible minorities) and corporations or cooperatives owned by them, in the supply of goods and services. Please provide one (1) original and one (1) copy of your formal response no later than 3:00 P.M. NST, 19 June 2014 to the address as shown below: Husky Energy Inc. Attn: Angela Vallis, Contract Administrator Suite 901, Scotia Centre Angela.vallis@huskyenergy.com 235 Water Street Phone: (709) St. John s, NL Canada A1C 1B6 Any submission which is not received by 3:00 P.M. NST, 19 June 2014 will be returned to sender, unopened, and will not be given any further consideration as part of this procurement process. Please note that any updates, bulletins and/or clarifications to the above noted Prequalification will be posted on the websites below. Please check regularly during the pre-submission period for any updates that may be posted. and
SAFETY BENEFITS 18. Tide-independence 18 Rapid ballasting 19 Integrated hydraulic Ro-Ro ramps 20 Safety features, the future and engineering 22
HYDRO DECK CONTENTS OVERVIEW 3 DESIGN 4 OVERVIEW OF KEY FEATURES 6 DESIGN BENEFITS 8 Versatile 8 High capacity ballast system 9 High deck strength and space 10 Integrated mooring system 11 Adaptable 12
More informationCODE OF PRACTICE Transportation of Employees by Vessel to or from a Workplace in the Offshore Petroleum Industry - Newfoundland and Labrador
CODE OF PRACTICE Transportation of Employees by Vessel to or from a Workplace in the Offshore Petroleum Industry - Newfoundland and Labrador March 2017 2017-0023 The Canadian Association of Petroleum Producers
More informationTransportation Considerations in Module Design
1771 Transportation Considerations in Module Design Dawar Naqvi P.E. 1, Eric Wey P.E. 2, Justin Morgan P.E. 3, Matthew Miller P.E. 4, Tony Nguyen 5 1 Fluor Corp, One Fluor Daniel Drive, Sugar Land, TX
More information9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction
9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE 9.1.1 Introduction This chapter is the provisional Environmental Management Plan (EMP) for the Jubilee Phase 1 Development project. The elements of
More informationTender #: SAP Business Objects Licenses and Support Release Date: February 26, 2018 Closing Deadline: March 9, :00pm Newfoundland Time
Tender #: 2018-018 SAP Business Objects Licenses and Support Release Date: February 26, 2018 Closing Deadline: March 9, 2018 2:00pm Newfoundland Time Copyright Notice This document is fully copyright protected
More informationTender #: Cisco Enterprise Licensing Agreement Release Date: February 15, 2018 Closing Deadline: March 1, :00pm Newfoundland Time
Tender #: 2018-016 Cisco Enterprise Licensing Agreement Release Date: February 15, 2018 Closing Deadline: March 1, 2018 2:00pm Newfoundland Time Copyright Notice This document is fully copyright protected
More informationArup Interview and Immersion Experience!
Andy Ryan Arup Interview and Immersion Experience! Husky Energy is currently pursuing the option of a Wellhead Platform with drilling capability to expand the White Rose Field. The platform will be designed
More informationCompany Profile. Atlas Offshore Co. No.8, Negar Ave. Vali e Asr St., Tehran, Iran
Company Profile Atlas Offshore Co. No.8, Negar Ave. Vali e Asr St., Tehran, Iran +98 21 88774544 +98 21 88790572 Table of Contents About US........ 2 Our Capabilities.. 3 Work shop / Storage... 4 EPC Services
More informationPort Information. Port of Oxelösund. for. IMO Port facility nr: SEOXE Valid from
Port Information for Port of Oxelösund IMO Port facility nr: SEOXE-0002 Valid from 2016-01-015 Contacts Oxelösunds Hamn AB Skeppargatan 28 P.O. Box 26 SE 613 24 Oxelösund +46-(0)155-25 80 00 customerservice@oxhamn.se
More informationComputer Software for Onboard Stability Calculations
(May 04) (Rev.1 Feb. 2005) (Rev.2 Sept 2006) (Corr.1 Nov 2006) (Rev.3 June 2017) Computer Software for Onboard Stability Calculations Application This Unified Requirement is applicable to software which
More informationWoodfibre LNG Limited Response to SIGTTO LNG Ports and Risk Reduction Options
Woodfibre LNG Limited Response to SIGTTO LNG Ports and Risk Reduction Options Introduction: The following is in response to the Environmental Assessment Office request for the Society of International
More informationRegulations of the People s Republic of China on the Emergency. Prevention and Handling of Marine Pollution Caused by Ships
Regulations of the People s Republic of China on the Emergency Prevention and Handling of Marine Pollution Caused by Ships Chapter One General Principles Article 1 In order to improve the emergency handling
More informationNORSOK STANDARD N-001
NORSOK STANDARD N-001 Edition 7, June 2010 Integrity of offshore structures This NORSOK standard is developed with broad petroleum industry participation by interested parties in the Norwegian petroleum
More informationShip to Ship Transfer (POAC/Superintendent) for Liquefied Natural Gas and Liquefied Petroleum Gas (LNG or LPG) (3 days) (OCIMF)
2017-2018 Ship to Ship Transfer (POAC/Superintendent) for Liquefied Natural Gas and Liquefied Petroleum Gas (LNG or LPG) (3 days) (OCIMF) This training program was created based on the 2013 OCIMF, CDI,
More informationPART 3 TERMINAL INFORMATION
International Safety Guide Part 3 Terminal information PART 3 TERMINAL INFORMATION Edition 1-2010 CCNR/OCIMF 2010 Page 235 International Safety Guide Part 3 Terminal information Edition 1-2010 CCNR/OCIMF
More informationCaspian Energy Group. an EPCI contractor in the Caspian Sea
Caspian Energy Group an EPCI contractor in the Caspian Sea February 2011 Caspian Energy Group Mission: Development of Russian competence in offshore engineering and construction Offshore engineering, procurement,
More informationP&O MARITIME Limassol, Cyprus Position Description
POSITION TITLE Marine Manager DIVISION P&O Maritime Limassol REPORTS TO Reports to the Board with dotted lines reporting to Head of Group Marine P&OM Direct Reports 5+ PRIMARY LOCATION Limassol Port -
More informationUnited Nations Development Programme (UNDP) FOR THE
United Nations Development Programme (UNDP) CALL FOR EXPRESSIONS OF INTEREST AND PREQUALIFICATION FOR THE CONSTRUCTION AND REHABILITATION OF IRRIGATION SYSTEMS IN LEBANON UNDP Lebanon invites interested
More informationPACIFIC MARINE SERVICES
APPR No : PMS/D.A.RSP/ Date : Pages : One (7) /UAE Data Sheet for Approval of Firms Issued within the scope of the Pacific Marine Services General Conditions - Radio Service Supplier for Inspection Services
More informationINFORMATION BULLETIN No. 51
Bulletin No. 51 Revision No. 08 Issue Date 14 Nov 2017 Effective Date 14 Nov 2017 INFORMATION BULLETIN No. 51 ECDIS, Nautical Charts and Publications Guidance and Instructions for Bahamas Recognised Organisations,
More informationRULES. PUBLICATION No. 66/P ONBOARD COMPUTERS FOR STABILITY CALCULATIONS January
RULES PUBLICATION No. 66/P ONBOARD COMPUTERS FOR STABILITY CALCULATIONS 2017 January Publications P (Additional Rule Requirements) issued by Polski Rejestr Statków complete or extended the Rules and are
More informationCITGO PETROLEUM CORPORATION CORPUS CHRISTI MARINE FACILITY REGULATIONS FOR VESSELS
CITGO PETROLEUM CORPORATION CORPUS CHRISTI MARINE FACILITY REGULATIONS FOR VESSELS THE EMERGENCY SIGNAL FOR THIS TERMINAL IS TWO LONG BLASTS SEPARATED BY A SHORT PAUSE ON THE DOCKSIDE PORTABLE AIR HORN.
More informationPort of Al Maqal, Iraq (Information and Requirements)
Port of Al Maqal, Iraq (Information and Requirements) Please find below relevant information and port authorities requirements for Al Maqal port. ADMIRALTY CHARTS a) 1235 (Khawr Abd Allah and Approaches
More informationDeep Panuke. 01U Issued for Use T. MacAdam J. Gillis A. Alleyne K. Tonn Rev Date Reason for Issue Prepared Checked Approved Approved Title
01U 2008-08-19 Issued for Use T. MacAdam J. Gillis A. Alleyne K. Tonn Rev Date Reason for Issue Prepared Checked Approved Approved Title PL08 - DM EN PQ PL 0006 01U Project Originator Info. Category Disc
More informationScope of Work Bid Package C-4 - West Polished Concrete
Scope of Work Bid Package C-4 - West Polished Concrete CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,
More informationMarine Guide for Agents
Marine Guide for Agents May 2016 Version: 2 This page intentionally left blank. TABLE OF CONTENTS Port Operating Company... 1 Harbour Authority... 2 Immobilisation... 2 Hot Work or Dive Permits... 2 Bunkers...
More informationNAVIGATION AND VESSEL INSPECTION CIRCULAR NO BACKGROUND.
NAVIGATION AND VESSEL INSPECTION CIRCULAR NO. 15-14 4. BACKGROUND. a. The STCW Convention and STCW Code set forth standards for training and certification for merchant mariners, including mariners serving
More informationTRAINING CATALOGUE. Academy Korea SAFER, SMARTER, GREENER
TRAINING CATALOGUE Academy Korea SAFER, SMARTER, GREENER 0001 Introduction to Shipbuilding 3 DAYS Shipbuilding, Shipping & Operation statistics Organization of maritime regime, Rules & Regulations, Class
More informationGUIDE FOR APPLICANTS
GUIDE FOR APPLICANTS This guide has been prepared to assist you in applying for a position with Port of Newcastle. Prior to completing your application, please read the following information to gain an
More informationJF (Bangladesh) Limited Topic: Project Cargo and/or Unique/Unusual Task
JF (Bangladesh) Limited Topic: Project Cargo and/or Unique/Unusual Task Presented by Sudatta Barua Lloyd s s Agency Department JF ( Bangladesh) Limited Finlay House Chittagong, Bangladesh at Lloyd s s
More informationThe Effect of Ultra Large Container Vessels on Cranes and Infrastructure
The Effect of Ultra Large Container Vessels on Cranes and Infrastructure Port and Terminal Technology Conference April 2017, Norfolk, Virginia Erik Soderberg, SE Structural Engineer, President Liftech
More informationPorts & Pilotage Authorities Case Studies
Nicom Maritime Suite 8, 6960 Mumford Rd. Halifax, Nova Scotia Canada B3L 4P1 Ph: 877-454-4499 www.nicommaritime.com Ports & Pilotage Authorities Case Studies Halifax Port Authority Vessel Traffic Management
More informationStorage Tank Explosion Frequencies on FPSOs
Storage Tank Explosion Frequencies on FPSOs John Spouge, Principal Consultant, DNV GL, Vivo Building, 30 Stamford Street, London SE1 9LQ Introduction This paper presents a new estimate of the frequency
More informationRecommended Best Practices for TRANSPORTATION of NON ROUTINE or SPECIAL CARGO ITEMS TO OR FROM SITE
Recommended Best Practices for TRANSPORTATION of NON ROUTINE or SPECIAL CARGO ITEMS (This document supersedes "Best Practice Transportation of Project Related Cargo Items - Guidance") ENDORSEMENTS Page
More informatione-navigation Frequently Asked Questions
e-navigation Frequently Asked Questions 1. What is e-navigation? e-navigation is an International Maritime Organization (IMO) led concept based on the harmonisation of marine navigation systems and supporting
More informationHPC for Maritime SMEs
HPC for Maritime SMEs Computational challenges in Maritime Development of new inovative technologies. More precise and accurate design of the higher resolution with results close to real life. Support
More informationHSE Challenges for Construction and Operation in the Sakhalin Offshore Climate
HSE Challenges for Construction and Operation in the Sakhalin Offshore Climate 4 November 2014 Norsk Olje & Gass Pieter Swart Footer here 1 SAKHALIN ISLAND THE ASSETS: A HUGE RESOURCE Sakhalin II oil reserves
More informationWithout having Cost Estimation Model you are putting your Project on a Big RISK
July 2014 Without having Cost Estimation Model you are putting your Project on a Big RISK Drive your project with a appropriate Cost Estimation System to mitigate Risks Plug your project to Our NoDoC Database
More informationFIRST JACK-UP RIG LOAD-OUT IN VIET NAM
FIRST JACK-UP RIG LOAD-OUT IN VIET NAM Ngo Tuan Dung Petrovietnam Marine Shipyard Joint Stock Company (PV Shipyard) Summary This paper presents the design concept and operation results of load-out for
More informationRecommendation on Standards for Training and Certification of VTS Personnel. IALA Recommendation V-103 May 1998
Recommendation on Standards for Training and Certification of VTS Personnel IALA Recommendation V-103 May 1998 2 May 1998 IALA Recommendation on Standards for Training and Certification of VTS Personnel
More informationHeavy Intermodal Lift & Transport Engineering Considerations
Heavy Intermodal Lift & Transport Engineering Considerations Host: Mike Parnell ITI President/CEO ASME B30 Vice Chair (Cranes & Rigging) ASME P30 Chair (Lift Planning) Guest Speaker: Jim Yates, P.E. SVP
More informationShipboard Operational Energy Efficiency: Strategy for Success
Shipboard Operational Energy Efficiency: Strategy for Success Thomas Kirk Director, Environmental Programs Stamford, CT 18 March 2013 INTERTANKO North American Panel Meeting Overview IMO regulations on
More informationSaudi Aramco s Prequalification Process Passport to Opportunity. October 25, 2016
Saudi Aramco s Prequalification Process Passport to Opportunity October 25, 2016 Overview 1. Safety Moment 2. Current Business Demand 3. Prequalification Process 4. The General Bid Slate Program 5. Registration
More informationOUR EXPERIENCE: BALLAST WATER MANAGEMENT SYSTEM (BWMS) RETROFIT
OUR EXPERIENCE: BALLAST WATER MANAGEMENT SYSTEM (BWMS) RETROFIT Presented By: Chandru Sirumal Rajwani (CEO of N-KOM) PREFERRED SHIPYARD DELIVERING SOLUTIONS ERHAMA BIN JABER AL JALAHMA SHIPYARD CONTENTS
More informationECRC~SIMEC Canada's Marine Oil Spill Preparedness Regime
ECRC~SIMEC Canada's Marine Oil Spill Preparedness Regime Paul Pouliotte CFO Introduction In 1993 amendments were made to the Canada Shipping Act (CSA) to strengthen Canada s marine oil spill response capability.
More informationEnergy East Pipeline Ltd. Consolidated Application Volume 7: Construction and Operations. Section 5 Marine Operations 5.0 MARINE OPERATIONS
CA PDF Page 1 of 30 5.0 MARINE OPERATIONS This section provides an overview of marine-based operations of the Canaport Energy East marine terminal located near Saint John, NB. It also includes: a brief
More informationFERRIBY MARINE SHIP SECURITY ASSESSMENT AUDIT CHECKLIST
SHIP SECURITY ASSESSMENT AUDIT CHECKLIST SHIP SECURITY ASSESSMENT AUDIT CHECKLIST 1. A Ship Security Assessment (SSA) is a process that identifies weaknesses in physical structures, personnel protection
More informationMinistry of Energy and Water Government of Lebanon
Ministry of Energy and Water Government of Lebanon Call for Expressions of Interest for a Liquefied Natural Gas Import Project in Lebanon This document has been prepared by Poten & Partners, Inc. ( Poten
More informationARTICLE 4 SPECIFICATIONS AND SCOPES OF WORK
ARTICLE 4 SPECIFICATIONS AND SCOPES OF WORK As discussed in Article 3, all Standard, Simplified, and Sole Source Purchases begin with written Specifications or a written Scope of Work ( SoW ). The importance
More informationCHARLESTON HEAVY LIFT 2, INC.
CHARLESTON HEAVY LIFT 2, INC. DERRICK BARGE OCEAN RANGER TARIFF NO. 1 Hoisting Rates, Charges, Rules and Conditions Governing Use Of 500-ton Capacity Derrick Barge OCEAN RANGER TARIFF THIS TARIFF IS SUBJECT
More informationNotice is hereby given of the following changes to the above-referenced SOLICITAITON:
FLORIDA DEPARTMENT OF TRANSPORTATION Procurement Office 605 Suwannee Street, MS 20 Tallahassee, Florida 32399-0450 Phone: (850) 414-4381 Fax: (850) 414-4951 ADDENDUM NO. 2 DATE: May 10, 2016 RE: BID #:
More informationREQUEST FOR PROPOSAL. Construction Management Services Not at Risk
REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk
More informationUnited States of America Department of Homeland Security United States Coast Guard Certificate of Inspection
United States of America Department of Homeland Security United States Coast Guard Certificate of Inspection Certification Date: 28 Apr 2016 Expiration Date: 28 Apr 2021 For ships on international voyages
More informationThe Enel Vetting system Shipping Safety and Marine risk assessment
The Enel Vetting system Shipping Safety and Marine risk assessment Roma, 07 Novembre 2011 Enel Group Enel is Italy's largest power company, and Europe's second listed utility by installed capacity. It
More informationShip Security Alert System (FMT-SSAS-V1):
Ship Security Alert System (FMT-SSAS-V1): FMT-SSAS-V1 offers a complete and dedicated SSAS solution, meeting all the requirements of the SOLAS regulation XI-2/6 and associated performance standards. The
More informationItem Name Description Unit of Measure Mobilization Per WSDOT Lump Sum
Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of
More informationStowage of Explosives on Vessels and issues noted with Small Ships
Information Sheet (relevant until the 1st of January 2012 only) Stowage of Explosives on Vessels and issues noted with Small Ships INTRODUCTION The purpose of this Information Sheet is to advise all ship
More informationInformation Paper on Oil Tanker In-Service Structural Survey Regimes
Tanker Structure Co-operative Forum Information Paper on Oil Tanker In-Service Structural Survey Regimes SUMMARY This paper reviews the current regime of inspection requirements for oil tankers including
More informationPlatform Construction and Installation
Platform Construction and Installation Platform Construction and Installation UK Construction Yards. Worldwide Construction. Construction Quality and Safety. Construction Risks. Offshore Installation.
More informationBELLOWS FALLS HISTORICAL SOCIETY, INC. Post Office Box 466 Bellows Falls, VT I fax
BELLOWS FALLS HISTORICAL SOCIETY, INC. Post Office Box 466 Bellows Falls, VT 05101 802-376-6789 I fax 802-463-9415 Request for Qualifications Design and Build Services for Nature Observation Platforms
More informationPORT OF PORT HEDLAND - BULK PRODUCT MANAGEMENT PROCEDURE
TABLE OF CONTENTS 1. PURPOSE... 2 2. SCOPE... 2 3. RESPONSIBILITIES... 2 4. SPECIFICATION OF BULK MINERAL PRODUCTS... 3 4.1 PROVISION OF ONGOING INFORMATION...4 4.2 SAMPLING...5 4.3 PRODUCT DEM AND MOISTURE
More informationAbout Cortland in Australia
Marine Services Mooring and Marine Systems Solutions, Mooring Systems, Engineering and Support, Plasma Rope and Specialty Rope Products, Anchors, Chain and Fittings, Mooring and Navigation Buoys, Fenders,
More informationAbout Cortland in Australia
Marine Services Mooring and Marine Systems Solutions, Mooring Systems, Engineering and Support, Plasma Rope and Specialty Rope Products, Anchors, Chain and Fittings, Mooring and Navigation Buoys, Fenders,
More informationTANKER SAFETY ISSUES. Mr Paul Markides Director OCIMF
TANKER SAFETY ISSUES Mr Paul Markides Director OCIMF ITOPF/INTERTANKO/OCIMF International Seminar on Tanker Safety, Pollution Prevention and Spill Preparedness Shanghai, People s Republic of China 8 December
More informationOn Board Use and Application of Computer based systems
(Dec 2006 (Corr.1 Oct 2007) (Rev.1 Sept 2010) (Rev.2 June 2016 Complete Revision) On Board Use and Application of Computer based systems 1. Introduction 1.1 Scope These requirements apply to design, construction,
More informationpproval of rvc upplrsno. 2.9 APRIL 2013
pproval of rvc upplrsno. 2.9 STANDARD FOR CERTIFICATION Approval Programmes Approval of Service Suppliers No. 405 Service Suppliers Engaged in Surveys and Maintenance of Fire Extinguishing Equipment, Systems
More informationANNEX 1 DRAFT RESOLUTION MEPC.140(54) Adopted on 24 March 2006
DRAFT RESOLUTION MEPC.140(54) Adopted on 24 March 2006 GUIDELINES FOR APPROVAL AND OVERSIGHT OF PROTOTYPE BALLAST WATER TREATMENT TECHNOLOGY PROGRAMMES (G10) THE MARINE ENVIRONMENT PROTECTION COMMITTEE,
More informationStrategic Plan for the Canadian Mental Health Association- PEI Division
Strategic Plan for the Canadian Mental Health Association- PEI Division Request for Proposals 1. Objective The objective of this Request for Proposal (RFP) is to solicit proposals from consultants experienced
More informationPRINCE RUPERT PORT AUTHORITY
PRINCE RUPERT PORT AUTHORITY Port of Prince Rupert Proposed 2015 Port Tariff Effective Date: June 1, 2015 Notice to Public This notice is authorized pursuant to Section 49 of the Canada Marine Act. Amendments
More information122 Norwegian Oil and Gas Recommended Guidelines for the Management of Life Extension
122 Norwegian Oil and Gas Recommended Guidelines for the Management of Life Extension Original version No: 122 Established: 2008.06.06 Revision no: 2 Date revised: 2017.08.11 Page: 2 PREFACE These guidelines
More informationAssociation of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017
Company: Prepared By: Date: Changes from previous version highlighted in yellow. Paragraph Element Objective Evidence 2.1 Objective of Quality Assurance Program 2.2 Applicability and Scope 2.3 QA Program
More informationREQUEST FOR PROPOSAL FOR. CONSTRUCTION MANAGER and DESIGN TEAM FOR. Downtown Preservation Project URBAN RE DEVELOPMENT AUTHORITY OF PITTSBURGH
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER and DESIGN TEAM FOR Downtown Preservation Project URBAN RE DEVELOPMENT AUTHORITY OF PITTSBURGH December 2010 I. GENERAL The Urban Redevelopment Authority of
More informationGeneral Shipping Terms and Conditions for Sea Freight
General Shipping Terms and Conditions for Sea Freight established by Mitsubishi Hitachi Power Systems Europe GmbH Supply Chain Management Schifferstr. 80 47059 Duisburg Germany ( named MHPS-EDE below )
More informationTechnical Information
Subject Information of "VESSEL REQUIREMENTS FOR NEW PANAMAX" from Panama Canal Authority To whom it may concern Technical Information No. TEC-0964 Date 3 September 2013 The Panama Canal Authority (ACP)
More informationClassNK Business Planning Department ACADEMY ClassNK Academy Center, South Asia and Oceania
ACADEMY ClassNK Academy s Mission ClassNK Academy was established in 2009 to provide people employed in the maritime industry with a working knowledge of shipping and shipbuilding, focusing specifically
More informationRequest for Proposals. Acoustic Survey to Determine Noise Signature at the Fundy Ocean Research Center for Energy Demonstration Site
Request for Proposals Acoustic Survey to Determine Noise Signature at the Fundy Ocean Research Center for Energy Demonstration Site Release date: April 21, 2011 Fundy Ocean Research Center for Energy (FORCE)
More informationB.C. TOWBOAT INDUSTRY CONFERENCE
LN G T erm inals on C ana da s W est C oast Kitimat LNG LN G T erm inals on C ana da s W est C oast Presentation to 17 th B.C. TOWBOAT INDUSTRY CONFERENCE Whistler, BC Kitimat LNG Alfred Sorensen Kitimat
More informationMediterranean Memorandum of Understanding on Port State Control Alexandria/ Egypt
Mediterranean Memorandum of Understanding on Port State Control Alexandria/ Egypt To : Member Authorities of the Med MoU Med MoU Information Centre CIMED Subject : Concentrated Inspection Campaign (CIC)
More informationUSING BIG DATA & ANALYTICS TO MAKE SMARTER DECISIONS
USING BIG DATA & ANALYTICS TO MAKE SMARTER DECISIONS Capt Rohit Talwar Big Data Frontier for Analytics & Smarter Decisions COMPLEXITY: Big Data refers to datasets whose size is beyond the ability of a
More informationProactive Approaches. To Minimize. Supply Chain Security. Breaches in the Rail, Air, Ocean and Land Environment
Proactive Approaches To Minimize Supply Chain Security Breaches in the Rail, Air, Ocean and Land Environment Top Eight Rail Principles Track and monitor pulls on a 24 hour basis to determine location and
More informationSEAMETRIC INTERNATIONAL AS
FOR ALL THINGS HEAVY SEAMETRIC INTERNATIONAL AS MAXIMIZING FLEXIBILITY AND COST SAVING OF OPERATIONS FOR ALL THINGS HEAVY SeaMetric International aims to be a key international player in the offshore heavy
More informationFULL-CYCLE GLOBAL ENERGY SOLUTIONS
FULL-CYCLE GLOBAL ENERGY SOLUTIONS Opportunities in the global energy market are becoming more exciting yet the challenges continue to increase. In targeting unconventional, technically challenging; or
More informationTECHNICAL STANDARDS COMMITTEE GUIDELINES FOR MARINE LIFTING & LOWERING OPERATIONS
TECHNICAL STANDARDS COMMITTEE GUIDELINES FOR MARINE LIFTING & LOWERING OPERATIONS 0027/ND This document has been replaced by the standard DNVGL-ST-N001 which may be retrieved through https://my.dnvgl.com/
More informationDevelopments in Remote Survey Operations
Developments in Remote Survey Operations Oceaneering International, Inc. APSG 37: Spring Meeting May 5 th, 2017 2015 Oceaneering International, Inc. All rights reserved. Rev B 11. Oceaneering Remote Services
More informationMaritime Intelligence Risk Suite
IHS MARITIME & TRADE Maritime Intelligence Risk Suite Whatever your risk... Whatever your risk... Identifying and evaluating maritime risk is a challenging business for marine insurers, finance, ship owners,
More informationSECTION ELEVATED BLEACHERS (Angle Frame Semi-Closed Deck)
SECTION 13125 ELEVATED BLEACHERS (Angle Frame Semi-Closed Deck) PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
More informationOur Contribution to the Hebron GBS project
Our Contribution to the Hebron GBS project Louis Chapdelaine, President Peter Kiewit Infrastructure Risto Neuvo, Senior Vice President Aker Solutions 2010 Aker Solutions 1 Kiewit Aker Contractors, a Partnership
More informationSpecifications for Asphaltic Paving of Clark Road in Salem Township and Ludlow Road in Union Township both in Champaign County, Ohio.
Specifications for Asphaltic Paving of Clark Road in Salem Township and Ludlow Road in Union Township both in Champaign County, Ohio. General Conditions Scope: It is the intent of these specifications
More informationOIL POLLUTION EMERGENCY PLAN
International Association of Drilling Contractors North Sea Chapter OIL POLLUTION EMERGENCY PLAN Template for Non-Production Mobile Offshore Drilling Units Revision Amendment Date 1. Final revision to
More informationAPTOMAR AS. Fra produktsalg til tjenestesalg, styrets påvirkning for endring av forretningsmodell. 1.November 2016
Fra produktsalg til tjenestesalg, styrets påvirkning for endring av forretningsmodell 1.November 2016 APTOMAR Company overview ABOUT APTOMAR A leading provider of integrated field monitoring systems for
More informationMarginal Field Production Vessel The Solution For Marginal Fields & Early Production!
Marginal Field Production Vessel The Solution For Marginal Fields & Early Production! 1 Presentation in Partnership with SOPETRO Offshore Nigeria Sopetro and IOC have formed a strategic alliance to pursue
More information(6) Crawl boards and ladders used for roof work shall be securely fastened over the ridge of the roof or be otherwise effectively anchored.
Newfoundland & Labrador - Terre-Neuve-et-Labrador Ladder Safety - Sécurité des échelles This material has been extracted from the Acts and Regulations of the Province to help students understand the subject.
More informationKlikk for å redigere tittelstil
Klikk for å redigere tittelstil SCC International Conference 2017: How Big Data can make shipping greener Ola Sekkesaeter September 5th 2017 London Klikk Introduction for å redigere tittelstil Maritime
More informationCASE STUDY LNG SKIKDA S PROJECT
CASE STUDY LNG SKIKDA S PROJECT PROJECT NAME: NEW LNG SKIKDA PROJECT ORIGINS: United States of America, European Economic Community, Korea, Turkey and Far East DESTINATION: Skikda (36 52 34 North, 6 54
More information~~~\ VKAN KAN-TN-LI 05
''\"l"/ 1 1,,,, '-J '/ ~ ~~~\ VKAN KAN-TN-LI 05 il.ac MRA -... _ ~ -:::- Komite Akreditasi Nasional ~,..~'2,./. ~,~' ''!. 1 1/11111 \,,,,, KAN TECHNICAL NOTES FOR THE ACCREDITATION OF INSPECTION BODIES
More informationThe use of the Animate Transfer toolbar and various transportation-related modules will be illustrated in three examples in the sequel.
316 Modeling Transportation Systems button of the Animate toolbar. A graphical Storage T-bar graphically depicts the entities in a storage facility. The Seize button allows the modeler to define a so-called
More informationShip Design and System Integration
Ship Design and System Integration Dipl.-Ing. Christina Vossen (Senior Engineer), Robert Kleppe (Principle Engineer, Electrical Systems), M.Sc. Siv Randi Hjørungnes (Principle Engineer, R&DT), Rolls-Royce
More informationIMO GBS and IACS Harmonised Common Structural Rules
IMO GBS and IACS Harmonised Common Structural Rules TSCF Shipbuilder Meeting 24 25 October 2013 Philippe Baumans, IACS Project Management Team BV Director of Development Department IMO GBS AND IACS HARMONISED
More informationNew Jersey Department of Transportation Bureau of Research RESEARCH PROJECT Request for Proposal Program
Date of RFP 08/18/2015 New Jersey Department of Transportation Bureau of Research RESEARCH PROJECT Request for Proposal 2015-16 Program Closing Date 09/28/2015 Defining the Hudson Bergen Light Rail Catchment
More informationCONTINENTAL FERRY PORT SITE INDUCTION
CONTINENTAL FERRY PORT SITE INDUCTION Port activities As landlord of the Commercial Port, the Port Authority must be informed of all works conducted on these premises The Authority is committed to the