Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS

Size: px
Start display at page:

Download "Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS"

Transcription

1

2 Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) # , under the SaskPower Open Access Transmission Tariff (OATT). The purpose of TSR # and the corresponding MH TSR # is to transfer power from Island Falls Hydroelectric Station in the northern SaskPower (SPC) system to the southern SPC system. The northern SPC system is connected to the southern SPC system through the Manitoba Hydro (MH) system and therefore, the power needs to be wheeled through MH. TSR # consists of a request for 20 MW firm transmission service from SaskPower generation at Island Falls hydroelectric station (POR IFHS) to the MH-SPC 110 kv interface. The MH-SPC 110 kv interface consists of the two 110 kv tie-lines (I1F and I2F) between Island Falls station (in SPC) and Border station (in MH). The corresponding MH TSR # requests a 20 MW transfer through the MH system, from the MH-SPC 110 kv interface to the MH-SPC 230 kv interface. The MH-SPC 230 kv interface consists of the three 230 kv tie-lines between MH and SPC. There is no corresponding TSR for the southern SPC system requesting a transfer of the power from the 230 kv MH-SPC interface to the southern SPC system. The TSR indicates that it will use the service under TSR # to complete the path. TSR # is owned by SPC and is Network Integrated Transmission Service associated with Island Falls under a grandfathered agreement with MH. This study only addresses the transmission service from Island Falls Hydro Station (POR) to Manitoba Hydro 110 kv interface (POR). It does not grant any service beyond that, or grant service to TSR # Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: SPC TSR # Point of Point of Service Start Date Stop Date Queue Date Receipt Delivery Requested IFHS MH MW, firm :00:00 CS :00:00 CS :00:48 CS Table ES.1: Summary Details for SPC TSR # MH TSR # Point of Point of Service Start Date Stop Date Queue Date Receipt Delivery Requested MHEB.IF SPC 20 MW, firm :00:00 CS :00:00 CS :25:46 CS Table ES.2: Summary Details for MH TSR #

3 ES.1 System Impacts of TSR # on SPC System Based on a pre-existing study done for 105 MW transfer from IFHS to SPC-MH 110 kv interface, system impacts were not identified in SPC system due to the requested 20 MW transfer of TSR # from the designated POR to POD (from Island Falls Hydroelectric Station to MH-SPC 110 kv interface). The study for 105 MW transfer from Island Falls to SPC-MH 110 kv interface identified 20 MW transmission service reservation on top of 60 MW service is within the identified partial interim service. TSR # requests 60 MW and TSR # requests 20 MW service through the same transmission path (i.e., from IFHS to SPC-MH 110 kv interface). System Impact Study for TSR # recommended granting the service for 60 MW. ES.1.2 Conclusion The study identified that full service of firm point-to-point 20 MW of transmission capacity associated with Transmission Service Request # may be granted with roll-over. The service under TSR # cannot however be redirected to any other POD/sink on a firm basis. A separate TSR would be required for redirection.

4 Table of Contents 1.0 INTRODUCTION STUDY OBJECTIVES STUDY SCOPE STUDY CRITERIA STUDY METHODOLOGY BASE CASE DEVELOPMENT IDENTIFIED IMPACTS EQUIPMENT OVERLOAD ANALYSIS FOR TSR # CONCLUSIONS OTHER TRANSMISSION SERVICE CONSIDERATIONS... 9

5 1.0 Introduction This study determines the system impacts associated with Transmission Service Request (TSR) # , as per the SaskPower Open Access Transmission Tariff (OATT). Firm point to point transmission service has been requested by Transmission Service Request (TSR) # , under the SaskPower Open Access Transmission Tariff (OATT). The purpose of TSR # and the corresponding MH TSR # is to transfer power from generation in the northern SaskPower (SPC) system to serve load in the southern SPC system. The northern SPC system is connected to the southern SPC system through the Manitoba Hydro (MH) system and therefore, the power needs to be wheeled through MH. TSR # consists of a request for 20 MW firm transmission service from SaskPower generation at Island Falls hydroelectric station to the MH-SPC 110 kv interface. The MH-SPC 110 kv interface consists of the two 110 kv tie-lines (I1F and I2F) between Island Falls station (in SPC) and Border station (in MH). The corresponding MH TSR # requests a 20 MW transfer through the MH system, from the MH-SPC 110 kv interface to the MH-SPC 230 kv interface. The MH-SPC 230 kv interface consists of the three 230 kv tie-lines between MH and SPC. There is no corresponding TSR for the southern SPC system requesting a further transfer of power from the 230 kv MH- SPC interface to the southern SPC system. The TSR indicates that it will use the service under TSR # TSR # is owned by SPC and is Network Integrated Transmission Service associated with Island Falls under a grandfathered agreement with MH. The study agreement for TSR # identifies that the source for the power transfer is generation in the northern SPC system (POR of Island Falls Hydroelectric Station) and the sink for the transfer is load in the southern SPC system. This study only addresses the transmission service from Island Falls Hydro Station (POR) to Manitoba Hydro 110 kv interface (POR). It does not grant any service beyond that, or grant service to TSR # Summary details for SPC TSR # and MH TSR # are shown in Tables 1.1 and 1.2: SPC TSR # Point of Point of Service Start Date Receipt Delivery Requested IFHS MH MW, firm :00:00 CS Stop Date Queue Date :00:00 CS :00:48 CS Table 1.1: Summary Details for SPC TSR # MH TSR # Point of Receipt Point of Delivery Service Requested Start Date MHEB.IF SPC 20 MW, firm :00:00 CS Stop Date Queue Date :00:00 CS :25:46 CS Table 1.2: Summary Details for MH TSR #

6 2.0 Study Objectives The System Impact Study for TSR # has the following objectives: To assess the impact of TSR # on the SaskPower (SPC) Far North and Manitoba Hydro (MH) transmission systems, including tie-lines. To determine if any identified impacts results in violation of SPC and MH performance criteria. To determine if a level of partial service is available, given that identified impacts for the requested power transfer levels are unacceptable. To identify mitigation options, given that identified impacts for the requested power transfer levels are unacceptable. To determine if rollover of the TSR is possible. The System Impact Study Agreement for TSR # defines the following objectives: To determine the adequacy of the SPC north transmission systems to accommodate the TSR. To determine whether any additional costs may be incurred in order to provide transmission service. The System Impact Study will not address the cost of the system additions or upgrades outside of SPC. To identify partial service, if applicable. To identify the system constraints. To identify the potential re-dispatch options, potential direct assignment facilities, or potential network upgrades required to provide the requested transmission service. 3.0 Study Scope The System Impact Study considers: Applicable SPC system topology and load levels using the latest available modeling information for the time frame studied.

7 Most-likely stressed summer and winter load and generation scenarios for the SPC system. Applicable planned system modifications, or additions to primary facilities or operations for the time frame studied. Previously queued requests for interconnection studies and reserved transmission service that stress system conditions. Applicable planned SPC generation outages for the time frame studied. SPC system performance for steady-state system-intact normal operating conditions. SPC system performance for applicable events resulting in the loss of a single (N-1) SPC bulk electric system element, or the loss of two (N-2) or more SPC bulk electric system elements. Impacts on the SPC tie-lines to Manitoba. Impacts on MH facilities. This System Impact Study does not consider: Impacts on facilities outside of the SPC and MH systems, unless otherwise noted. System performance following extreme events resulting in the loss of two or more bulk electric system elements. Previously queued requests for interconnection studies and reserved transmission service that stress system conditions. Applicable planned SPC generation outages for the time frame studied. SPC system performance for steady-state system-intact normal operating conditions. 4.0 Study Criteria SPC and NERC transmission planning standards were used to assess the system impacts of TSR # on system performance (system-intact and post-contingency).

8 5.0 Study Methodology Simulations to assess the impacts to the SPC system due to TSR # were conducted using the PSS/E software package. 1 The following methodology process was used to assess the system impacts of TSR # : Conduct contingency analysis to identify impacts on the SPC system due to TSR # , for applicable N-1 and N-2 contingencies. Identify facilities required to mitigate the system impacts of TSR # TSR # identifies the point of receipt (POR) as the Island Falls station and the point of delivery (POD) as the MH-SPC 110 kv interface. The corresponding MH TSR # requests a 20 MW transfer from the MH-SPC 110 kv interface to the MH-SPC 230 kv interface. There is no corresponding TSR for the southern SPC system requesting a further transfer of the power from MH-SPC 230 kv interface into the southern SPC system. To assess the intended purpose of TSR # to transfer power through the I1F/I2F lines from Island Falls to MH-SPC 110 kv interface, power flow cases capturing wide range of scenarios for the requested and further out years were analyzed. In order to represent stressed conditions for power transfer on the 110 kv interface between MH and the northern SPC system, Island Falls Return was modeled at 105 MW. A transmission reliability margin (TRM) of 75 MW for the MH-SPC 230 kv interface was used to account for SPC load variations and area control impacts on this interface. The TRM was held constant at 75 MW for this study. A transmission reliability margin (TRM) of 10 MW was assumed in this study for the MH-SPC 110 kv interface. Applicable N-1 and N-2 contingencies for the 110 kv SPC systems were used for the postcontingency assessment of TSR # These include: Tripping of SPC generators (N-1). Loss of a single-circuit SPC grid transmission line or tie-line (N-1). N-2 contingency analysis was not required as loss of both I1F/I2F circuits would take the facilities out-of-service to provide the requested transmission service. 1 PSS/E is a software package by Siemens PTI (Power Technologies International). It is widely used by power utilities to perform steady-state, transient, and dynamic simulation of power system operation.

9 6.0 Base Case Development Base case development is intended to produce a range of operating cases to ensure that potential system impacts and associated mitigation requirements across a wide range of operating conditions are identified, and to provide for an acceptable level of firm transmission service by minimizing transmission loading relief (TLR). For this study, the following cases were assessed: 2015 Summer Off-Peak, Summer Peak, and Winter Peak cases for analysis of requested reservations in the near-term Summer Off-Peak, Summer Peak, and Winter Peak cases for analysis of rollover potential. 7.0 Identified Impacts For this analysis, the SPC and MH bulk-electric systems and tie-lines were assessed. The contingency analysis included the following applicable N-1 contingencies: Generator tripping (N-1). Loss of a single-circuit grid transmission line (N-1). 7.1 Equipment Overload Analysis for TSR # Based on a pre-existing study for 105 MW of transfer from the designated POR to POD (from Island Falls Hydroelectric Station to the MH-SPC 110 kv interface), overloads on SPC equipment were identified for the northern SPC system. These overloads are summarized in Table Overload Equipment I1F 110 kv Line I2F 110 kv Line Contingencies Resulting in Overloads N-1 loss of I2F 110 kv line N-1 loss of I1F 110 kv line Table 7.1.1: Summary of Overload Issues that occurred Due to 105 MW TSR The overloads of the I1F and I2F 110 kv tie-lines (between Island Falls station and MH) occurred for N-1 contingencies of the adjacent line (i.e I1F overloads occurred for trips of I2F, and vice-versa) as shown in Table The lines are not overloaded beyond the thermal rating of the conductor for 80 MW transfer from Island Falls to SPC-MH 110 kv interface for such contingencies. The study for 105 MW transfer from Island Falls to SPC-

10 MH 110 kv interface identified 20 MW transmission service reservation on top of 60 MW service is within the identified partial interim service. TSR # requests 60 MW and TSR # requests 20 MW service through the same transmission path (i.e., from IFHS to SPC-MH 110 kv interface). System Impact Study for TSR # recommended granting the service for 60 MW. Impacts on the Manitoba Hydro system were identified for SPC TSR # Manitoba portion of I1F and I2F were overloaded beyond the MH facility ratings and are assumed to be addressed by the System Impact Study for the corresponding MH TSR # Conclusions The study identified that full service of firm point-to-point 20 MW of transmission capacity associated with Transmission Service Request # may be granted with roll-over. 9.0 Other Transmission Service Considerations The results of the System Impact Study will be deemed invalid 3 months after the completion of the System Impact Study. Completion of the System Impact Study is deemed to occur upon signing and issuing of the System Impact Study. The Customer must execute a Service Agreement for TSR # within 15 days of receipt of the completed System Impact Study. If the Customer does not execute the Service Agreement within 15 days, the results of the System Impact Study will be deemed invalid, and TSR # shall be deemed terminated and withdrawn. SPC, at its discretion, may elect to augment the proposed options or develop other options that would meet the technical requirements. However, any additional associated costs would not be allocated to TSR # Any roll-over granted will need to be conditioned by third party impacts or constraints. That is, third party impacts or constraints not known at the time of this study may be reevaluated at the time of roll-over to determine if service can still be granted. Firm service for TSR # may not be available for extreme load and dispatch patterns in Manitoba and Saskatchewan that were not assessed as part of this study. Firm service for TSR # is dependent upon system-intact operation of the SPC system. If SPC facilities that have an impact on the transfer capability of TSR # are not available due to maintenance or repair, curtailment of the TSR may be required. For example: loss of I1F or I2F circuits may require curtailment of TSR # and loss of generation from Island Falls Hydro Station may impact the service under TSR #

11 The Study Agreement for TSR # identified that the source for TSR # was Island Falls Hydro Station and the sink for TSR # was load in the southern SPC system. Firm service for TSR # should be conditioned on the source and sink remaining as previously identified, otherwise a request for re-direct or potential reassessment of the transmission service may be required.

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80439788, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of

More information

System Impact Study and Facilities Study Process Manual For Cleco Power LLC

System Impact Study and Facilities Study Process Manual For Cleco Power LLC System Impact Study and Facilities Study Process Manual For Cleco Power LLC Version 3 March 2010 System Impact Study and Facilities Study Manual for Cleco Power LLC 1.0 Introduction.3 1.1 Purpose.3 1.2

More information

Methodology for Calculating Operating Limits for Generators

Methodology for Calculating Operating Limits for Generators Page 1 of 6 Methodology for Calculating Operating Limits for Generators I. Generator Operating Limit Definition The Generator Operating Limit (GOL) for a generator establishes a pathspecific, directional,

More information

December 20, Amendment to Attachment C to the Southern Companies OATT Docket No. ER14-

December 20, Amendment to Attachment C to the Southern Companies OATT Docket No. ER14- PIYANKA GHOSAL t: (205) 226-3454 f: (205) 488-5839 e: pghosal@balch.com December 20, 2013 BY ELECTRONIC FILING Ms. Kimberly D. Bose, Secretary Mr. Nathaniel J. Davis, Sr., Deputy Secretary Federal Energy

More information

Southwest Power Pool CRITERIA

Southwest Power Pool CRITERIA Southwest Power Pool CRITERIA LATEST REVISION: April 28, 2015 FOREWORD... i INTRODUCTION... ii 1.0 LOAD AND ENERGY FORECASTS...1-1 2.0 CAPACITY MARGIN...2-1 2.1 Definitions...2-1 2.1.1 Load Serving Member...2-1

More information

Requirements For Generation and Transmission Interconnections

Requirements For Generation and Transmission Interconnections Requirements For Generation and Transmission Interconnections Table of Contents 1.0 INTRODUCTION... 1 2.0 INTERCONNECTION POLICY... 2 3.0 STANDARD INTERCONNECTION PROCESS... 3 3.1 ASSUMPTIONS... 3 3.2

More information

INTEGRATED TRANSMISSION PLANNING MANUAL

INTEGRATED TRANSMISSION PLANNING MANUAL INTEGRATED TRANSMISSION PLANNING MANUAL Published on July 20, 2017 Pending FERC approval of Tariff language By SPP staff REVISION HISTORY DATE OR VERSION NUMBER AUTHOR CHANGE DESCRIPTION COMMENTS 10/13/2010

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents Appendix N... 2 Pseudo-Tie Protocol... 2 1. Pseudo-Ties of Generating Units to the CAISO Balancing Authority Area... 2 1.1 Consistency with NERC/WECC Requirements... 2 1.2 CAISO Operating,

More information

ISO New England Available Transfer Capability. Implementation Document. Version 1.0

ISO New England Available Transfer Capability. Implementation Document. Version 1.0 ISO New England Available Transfer Capability Implementation Document Version 1.0 1 Effective: 04/01/2011 Table of Contents 1. Introduction... 3 2. Transmission Service in the New England Markets... 6

More information

Methodology PLG-METH-0002-V4

Methodology PLG-METH-0002-V4 Methodology Department: Document No: System Planning and Strategic Projects PLG-METH-0002-V4 Title: Transmission Planning Assessment Practices Issue Date: August 3, 2015 Previous Date: December 10, 2014

More information

Business Practices for. Schedule 21-ES. (Modifications Issued on August 11, 2016)

Business Practices for. Schedule 21-ES. (Modifications Issued on August 11, 2016) (Modifications Issued on August 11, 2016) 1 List of Contents Introduction Purpose of Document Overview of Transmission Services in New England Definitions Applicable Schedules Services Applicable to these

More information

LOAD SERVING ENTITIES PJM REGION

LOAD SERVING ENTITIES PJM REGION Intra-PJM Tariffs --> RELIABILITY ASSURANCE AGREEMENT PJM Interconnection, L.L.C. Rate Schedule FERC No. 44 RELIABILITY ASSURANCE AGREEMENT Among LOAD SERVING ENTITIES in the PJM REGION Effective Date:

More information

Northwest Power Pool Processes

Northwest Power Pool Processes Northwest Power Pool Processes Background The Northwest Power Pool membership (NWPP) was founded in 1941 to promote efficient production of electrical energy. The NWPP is the geographic area encompassed

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

South Carolina Public Service Authority Transmission Reliability Margin Implementation Document (TRMID) April 1, Version 5.0

South Carolina Public Service Authority Transmission Reliability Margin Implementation Document (TRMID) April 1, Version 5.0 South Carolina Public Service Authority Transmission Reliability Margin Implementation Document (TRMID) April 1, 2017 Version 5.0 Document Change History Version Date of Change Description of Change 0.0

More information

ATTACHMENT K TRANSMISSION PLANNING PROCESS

ATTACHMENT K TRANSMISSION PLANNING PROCESS ATTACHMENT K TRANSMISSION PLANNING PROCESS 1.0 Introduction This Attachment K addresses the rights and obligations of Transmission Customers, relevant stakeholders and the Transmission Provider related

More information

Federal Energy Regulatory Commission Working Paper on Standardized Transmission Service and Wholesale Electric Market Design

Federal Energy Regulatory Commission Working Paper on Standardized Transmission Service and Wholesale Electric Market Design Federal Energy Regulatory Commission Working Paper on Standardized Transmission Service and Wholesale Electric Market Design To enhance competition in wholesale electric markets and broaden the benefits

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

RE: Initiating Near Term Transmission Components of the Central Toronto Integrated Regional Resource Plan

RE: Initiating Near Term Transmission Components of the Central Toronto Integrated Regional Resource Plan ONTARIO 120 Adelaide Street West Suite 1600 Toronto, Ontario M5H 1T1 POWER AUTHORITY\Jr T 416-967-7474 F 416-967-1947 www.powerauthority.on.ca December 27, 2013 Mr. Bing Young Director, Transmission System

More information

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, 2017 Prepared by Interconnection Planning Department PJM 2017 Table of Contents Table of Contents Table of Exhibits...7

More information

Con Ed/PSEG Wheel Replacement Proposal A joint white paper from the New York Independent System Operator and PJM Interconnection

Con Ed/PSEG Wheel Replacement Proposal A joint white paper from the New York Independent System Operator and PJM Interconnection Con Ed/PSEG Wheel Replacement Proposal A joint white paper from the New York Independent System Operator and PJM Interconnection DRAFT For Discussion Purposes Only V 4.0 December 19, 2016 Table of Contents

More information

Business Practice Manual for Managing Full Network Model. Version 1011

Business Practice Manual for Managing Full Network Model. Version 1011 Business Practice Manual for Managing Full Network Model Version 1011 Last Revised: November 16, 2016January 31, 2017 Approval History Approval Date: October 1, 2009 Effective Date: October 1, 2009 BPM

More information

Dispatch Signal & Locational Marginal Pricing (LMP)

Dispatch Signal & Locational Marginal Pricing (LMP) Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP Dispatch Rate Economic control signal

More information

Internal NYISO HVDC Controllable Line Scheduling. Concept of Operation. LECG Staff

Internal NYISO HVDC Controllable Line Scheduling. Concept of Operation. LECG Staff ConOp Internal NYISO HVDC Controllable Line Scheduling Concept of Operation Author: Scott Harvey, LECG Reviewers: ISO Staff LECG Staff Project Sponsor: Point of Contact: C. King B. Kranz Document Locator:

More information

System Impact Study E001 Moon Lake 230 kv 200 MW Plant

System Impact Study E001 Moon Lake 230 kv 200 MW Plant System Impact Study E001 Moon Lake 230 kv 200 MW Plant Prepared by: Midcontinent Independent System Operator Independent Coordinator of Transmission 720 City Center Drive Carmel, IN 46032 Rev Issue Date

More information

SPP at a Glance. Located in Little Rock. Approximately 600 employees

SPP at a Glance. Located in Little Rock. Approximately 600 employees SPP at a Glance Located in Little Rock Approximately 600 employees Primary jobs electrical engineering, operations, settlements, and IT 24 x 7 operation Full redundancy and backup site 2 Regulatory Environment

More information

Transmission Expansion and Interconnection Manual. June 2017

Transmission Expansion and Interconnection Manual. June 2017 MANUAL 23 Transmission Expansion and Interconnection Manual June 2017 Version: 3.0 Effective Date: 06/30/2017 Committee Acceptance: BIC 06/14/2017 OC 06/15/2017 This document was prepared by: NYISO Interconnection

More information

MOD Steady-State and Dynamic System Model Validation

MOD Steady-State and Dynamic System Model Validation MOD-033-1 Steady-State and Dynamic System Model Validation A. Introduction 1. Title: Steady-State and Dynamic System Model Validation 2. Number: MOD-033-1 3. Purpose: To establish consistent validation

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Regional Transmission and Energy Scheduling Practices

Regional Transmission and Energy Scheduling Practices Open Access Same - Time Information System Regional Transmission and Energy Scheduling Practices Version 25: Effective March 31, 2016 Table of Contents CHAPTER 1: Transmission Reservation... 3 1.1 Requesting

More information

Methodology PLG-METH-0002-V1

Methodology PLG-METH-0002-V1 Methodology Department: Document No: System Planning and Strategic Projects PLG-METH-0002-V1 Title: Transmission Planning Assessment Practices Issue Date: September 27, 2012 Previous Date: Nov. 18, 2011

More information

NBP (ATG) IR 01 March 5, Reference: NBP 18.01

NBP (ATG) IR 01 March 5, Reference: NBP 18.01 NBP (ATG) IR 01 March 5, 2015 Reference: NBP 18.01 a. Who does NB Power intend to have testify with respect to the evidence? b. In preparing the evidence, who has reviewed or prepared portions of the evidence

More information

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours Background The class will be delivered over a 3-day period. The class is comprised of three training modules covering the areas of: Communications, Critical Thinking, and Restoration. The course consists

More information

Load RSG Exemptions Emergency Procedures. October 29, 2013

Load RSG Exemptions Emergency Procedures. October 29, 2013 Load RSG Exemptions Emergency Procedures October 29, 2013 Presentation Summary Purpose Summarize the outcome of discussions in the RSC regarding exemption of Load during Emergencies Key Takeaways The RSC

More information

XXXX. Bremner Trio Small Hydro Project. Interconnection System Impact Study

XXXX. Bremner Trio Small Hydro Project. Interconnection System Impact Study XXXX Bremner Trio Small Hydro Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY, LIMITATION

More information

Wes Yeomans Vice President Operations Management Committee May 31, 2017 COPYRIGHT NYISO ALL RIGHTS RESERVED

Wes Yeomans Vice President Operations Management Committee May 31, 2017 COPYRIGHT NYISO ALL RIGHTS RESERVED Ramapo Phase Angle Regulator Cost Recovery Wes Yeomans Vice President Operations Management Committee May 31, 2017 Agenda Background Benefits of Two Ramapo Phase Angle Regulators Annual Cost Projections

More information

LEER/TLR 5 Drill Procedure General Coordination Procedures and Drill Scenario

LEER/TLR 5 Drill Procedure General Coordination Procedures and Drill Scenario LEER/TLR 5 Drill Procedure General Coordination Procedures and Drill Scenario General The participants of the Lake Erie Emergency Redispatch (LEER) procedure will perform drills of various scenarios of

More information

PJM M2M Market Flow Proposal. October 2014

PJM M2M Market Flow Proposal. October 2014 PJM M2M Market Flow Proposal October 2014 Table of Contents 1. Introduction... 1 2. M2M Market Flow... 1 3. Real-Time Balancing Congestion and M2M payments... 3 4. Firm Flow Entitlement Impact of Market

More information

Methodology for Determining and Communicating System Operating Limits for the Planning Horizon (FAC-010 & -014) Revision Log

Methodology for Determining and Communicating System Operating Limits for the Planning Horizon (FAC-010 & -014) Revision Log Revision Log Page 2 of 13 Revision or Change Number Effective Date Affected Page Numbers Description of Revision/Change 0000 03-26-2011 All Converted TPD document to SPP format 0001 03-26-2012 All Annual

More information

Outage Coordination Training MISO Training

Outage Coordination Training MISO Training MISO Last material update: 05/19/2015 Course Content and Disclaimer 2 1 2 3 4 Course Description This course will review MISO's outage study processes and the coordination opportunities with TOs and MPs.

More information

PJM PROMOD Overview. August 1, PJM

PJM PROMOD Overview. August 1, PJM PJM PROMOD Overview August 1, 2017 Market Analysis Software PROMOD PROMOD is a fundamental electric market simulation solution It incorporates future demand, generating unit operating characteristics,

More information

TPL Transmission System Planned Performance for Geomagnetic Disturbance Events

TPL Transmission System Planned Performance for Geomagnetic Disturbance Events A. Introduction 1. Title: Transmission System Planned Performance for Geomagnetic Disturbance Events 2. Number: TPL-007-1 3. Purpose: Establish requirements for Transmission system planned performance

More information

2750 Monroe Blvd Audubon, PA

2750 Monroe Blvd Audubon, PA 2750 Monroe Blvd Audubon, PA 19403-2497 October 21, 2014 Mr. Jonathan Feipel Executive Director Illinois Commerce Commission 527 East Capitol Avenue Springfield, Illinois 62701 Dear Mr. Feipel: This report

More information

Overview of Control Area / Balancing Authority Functional Requirements Matt Wolf Manager Operations Support May 5, 2010

Overview of Control Area / Balancing Authority Functional Requirements Matt Wolf Manager Operations Support May 5, 2010 Overview of Control Area / Balancing Authority Functional Requirements Matt Wolf Manager Operations Support May 5, 2010 1 Outline of Presentation Importance of balancing power production with power demand.

More information

Operational Constraints Update 13/07/2017

Operational Constraints Update 13/07/2017 Operational Constraints Update 13/07/2017 Key Updates No updates Disclaimer EirGrid plc, the Transmission Operator (TSO) for, and SONI Limited, the TSO for Northern, make no warranties or representations

More information

Incremental Black Start RFP Response Template & General Information

Incremental Black Start RFP Response Template & General Information Revision 2: 7/28/2015 Incremental Black Start RFP Response Template & General Information Overview This document is divided into three sections: Section 1: An incremental RFP response template Section

More information

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

the Real-Time Market will be based on the system marginal costs produced by the Real-Time 17.1 LBMP Calculation The Locational Based Marginal Prices ( LBMPs or prices ) for Suppliers and Loads in the Real-Time Market will be based on the system marginal costs produced by the Real-Time Dispatch

More information

EIPC Roll-Up Powerflow Model

EIPC Roll-Up Powerflow Model EIPC Roll-Up Powerflow Model Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG Meeting November 25, 2013 2013 New York Independent System Operator, Inc. All Rights

More information

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING April 17, 2014 Training Objectives To Provide an Overview of: The Market Efficiency proposal window process The critical modeling inputs

More information

Written comments with CAISO reply Submitted after the April 10 Stakeholder Meeting regarding the 2009 Local Capacity Requirement (LCR) Results

Written comments with CAISO reply Submitted after the April 10 Stakeholder Meeting regarding the 2009 Local Capacity Requirement (LCR) Results Written comments with CAISO reply Submitted after the April 10 Stakeholder Meeting regarding the 2009 Local Capacity Requirement (LCR) Results COMMENTS OF THE ALLIANCE FOR RETAIL ENERGY MARKETS ON THE

More information

ConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator:

ConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator: ConOp Internal NYISO Controllable Lines Concept of Operation Author: Reviewers: Scott Harvey, LECG Project Sponsor: Point of Contact: Document Locator: Revision History Date Additions, deletions, modifications

More information

Southern Company Transmission General Business Practices

Southern Company Transmission General Business Practices Table of Contents General Guidelines and Requirements... 1 Applying for Transmission Service... 2 Firm Point-to-Point Transmission Service... 2 Non-Firm Point-to-Point Transmission Service... 2 Network

More information

FRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS. Reliability Coordinator Processes and Tools

FRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS. Reliability Coordinator Processes and Tools FRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS Reliability Coordinator Processes and Tools Objectives Describe how the FRCC Security Process addresses planning/coordination of the Bulk Electric System Describe

More information

Energy Markets - The Basics

Energy Markets - The Basics Disclaimer This training presentation is provided as a reference for preparing for the PJM Certification Exam. Note that the following information may not reflect current PJM rules and operating procedures.

More information

Operating Procedure PURPOSE... 2

Operating Procedure PURPOSE... 2 No. 3100 Table of Contents PURPOSE... 2 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 3 2.1. Background... 3 2.2. Scope/ Applicability... 3 3. PROCEDURE DETAIL... 4 3.1. Acceptable System Performance

More information

MISO 2018 Series Dispatch Update. MOD-032 Users Group October 3, 2017

MISO 2018 Series Dispatch Update. MOD-032 Users Group October 3, 2017 MISO 2018 Series Dispatch Update MOD-032 Users Group October 3, 2017 1 Objective MTEP17 Dispatch Process MTEP18 Dispatch Updates Reminder Station Service Load Modeling Enhancements Wind Capacity Credit

More information

the most promising locations for new renewables in the Imperial CREZ.

the most promising locations for new renewables in the Imperial CREZ. March 3, 2016 Imperial Irrigation District (IID) appreciates the opportunity to comment on the California Independent System Operator (CAISO) presentation during its 2/18/16 Stakeholder meeting discussing

More information

Gas-Electric Coordination A NYISO Perspective

Gas-Electric Coordination A NYISO Perspective Gas-Electric Coordination A NYISO Perspective Rana Mukerji Senior Vice President Market Structures New York Independent System Operator Energy in the Northeast Boston, MA September 9, 2013 Generation Capacity

More information

Analysis of Three Recent Blackouts

Analysis of Three Recent Blackouts Analysis of Three Recent Blackouts San Diego Gas & Electric -09/08/2011 Indian Northern Grid 07/30/2012 Indian Northern & Eastern Grids 07/31/2012 Bharat Bhargava Advanced Power System Technologies, Inc.

More information

ESP ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Cons ulting Group

ESP ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Cons ulting Group ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Suite 2B, 08 Arnold Road, Rosebank, 2196, Johannesburg, South Africa Tel: +27 11 447 9852; Website: http://www.espcg.com Transaction advisory

More information

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation. Section 3 Operating Reserve Operating Reserve Day-ahead and real-time operating reserve credits are paid to market participants under specified conditions in order to ensure that resources are not required

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014 No. Comment Submitted ISO Response Date Q&A Posted 1 Can the CAISO provide a line rating methodology (similar to a NERC FAC-008 standard) or include a requirement of using any The ISO does not provide

More information

N-1-1 AC Contingency Analysis as a Part of NERC Compliance Studies at Midwest ISO

N-1-1 AC Contingency Analysis as a Part of NERC Compliance Studies at Midwest ISO 1 N-1-1 AC Contingency Analysis as a Part of NERC Compliance Studies at Midwest ISO D. Chatterjee, Member, IEEE, J. Webb, Member, IEEE, Q. Gao, Member, IEEE, M. Y. Vaiman, Member, IEEE, M. M. Vaiman, Member,

More information

Small Generator Interconnection Procedures (SGIP) Customer Guide

Small Generator Interconnection Procedures (SGIP) Customer Guide Customer Guide SCE&G utilizes a FERC mandated and approved process, known as the Small Generator Interconnection Procedure (SGIP), to evaluate the interconnection of small generators to the SCE&G transmission

More information

ATTACHMENT C Methodology to Assess Available Transmission Capability

ATTACHMENT C Methodology to Assess Available Transmission Capability Improvement and Power District Revised Sheet No. 107 ATTACHMENT C Methodology to Assess Available Transmission Capability This methodology is excerpted from the report Determination of Available Transfer

More information

7. Electrical Facility Ratings

7. Electrical Facility Ratings 7. Electrical Facility Ratings 7.1 Accredited Net Generating Capacity This Section shall be used to determine the annual and seasonal accredited net generating capacity of generators in calculating the

More information

TSR Modeling in Reliability Planning. Planning Subcommittee October 17, 2017

TSR Modeling in Reliability Planning. Planning Subcommittee October 17, 2017 TSR Modeling in Reliability Planning Planning Subcommittee October 17, 2017 1 Objective TSR Modeling in MISO Series Base Models TSR Modeling in Reliability Planning Studies 2 TSR Modeling in MISO Series

More information

PJM Manual 37: Reliability Coordination Revision: 14 Effective Date: April 1, Prepared by Systems Operation Division

PJM Manual 37: Reliability Coordination Revision: 14 Effective Date: April 1, Prepared by Systems Operation Division PJM Manual 37: Reliability Coordination Revision: 14 Effective Date: April 1, 2017 Prepared by Systems Operation Division PJM 2017 Table of Contents Table of Contents Approval...4 Current Revision...5

More information

Open Access Transmission Tariff ATTACHMENT K

Open Access Transmission Tariff ATTACHMENT K ATTACHMENT K PART I Introduction The Transmission Provider s (herein referred to as Tacoma Power) local transmission planning process will include open planning meetings that Tacoma Power will conduct

More information

BC Hydro Revenue Requirements Application Information Request #1

BC Hydro Revenue Requirements Application Information Request #1 BC Hydro Revenue Requirements Application Information Request #1 C28-2 By: Ludo Bertsch, Horizon Technologies Inc. For: ESVI Energy Solutions for Vancouver Island Society Date: July 5, 2006 1.0) Reference:

More information

Transmission Reliability Margin Implementation Document TP-PL-002-r10 Effective Date: JUL Purpose. 2 Scope.

Transmission Reliability Margin Implementation Document TP-PL-002-r10 Effective Date: JUL Purpose. 2 Scope. 1 Purpose This document describes the terms and methodologies used in the calculation of Transmission Reliability Margin (TRM). Specifically, the document describes the following: The Methodology For Calculation

More information

Survey of Modeling Capabilities and Needs for the Stationary Energy Storage Industry

Survey of Modeling Capabilities and Needs for the Stationary Energy Storage Industry Survey of Modeling Capabilities and Needs for the Stationary Energy Storage Industry Prepared for: Energy Storage Association 1155 15th Street, NW Suite 500 Washington, DC 20005 202.293.0537 energystorage.org

More information

Generator Deactivation Assessment Indian Point Energy Center. A Report by the New York Independent System Operator

Generator Deactivation Assessment Indian Point Energy Center. A Report by the New York Independent System Operator Generator Deactivation Assessment Indian Point Energy Center A Report by the New York Independent System Operator December 13, 2017 Purpose On November 13, 2017 the New York Independent System Operator,

More information

Jan Strack and Huang Lin March 14, 2017

Jan Strack and Huang Lin March 14, 2017 SDG&E Request for Economic Planning Study of the Renewable Energy Express Transmission Project as part of CAISO s 2017-2018 Transmission Planning Process (TPP) Jan Strack (jstrack@semprautilities.com)

More information

Anchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th DRAFT Proposal only

Anchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th DRAFT Proposal only Anchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th 2016 DRAFT Proposal only Formal stakeholder review will begin August 24 th and remain open through September 12

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 103 FERC 61,270 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; William L. Massey, and Nora Mead Brownell. Entergy Services, Inc. Docket No.

More information

ATTACHMENT P. Transmission Planning Process

ATTACHMENT P. Transmission Planning Process ATTACHMENT P Transmission Planning Process Overview of Western s Transmission Planning Processes The Western Area Power Administration (Western) is a Federal agency under the Department of Energy that

More information

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY 1 1. Summary When one part of the grid is facing security of supply risk where local generation in one region of the grid is not enough for

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Frequently Asked Questions August 2013

Frequently Asked Questions August 2013 Frequently Asked Questions August 2013 General What is the Bulk-Power System or Bulk Electric System? NERC defines the Bulk-Power System as the electricity power generation facilities combined with the

More information

Calculation of transmission capacities between partner-grids

Calculation of transmission capacities between partner-grids Translation for information purposes only. See especially the German version approved by the German Federal Networks Agency (BNetzA). Calculation of transmission capacities between partner-grids 20th May

More information

Consultation on Connecting Further Generation in Northern Ireland. Call for Evidence

Consultation on Connecting Further Generation in Northern Ireland. Call for Evidence Consultation on Connecting Further Generation in Northern Ireland Call for Evidence 12 Table of Contents 1 Executive Summary... 3 2 Introduction... 6 2.1 Purpose of this Paper... 6 3 Alternative Connection

More information

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED PREPARED BY: Network Development VERSION: 2.0 RELEASE DATE: 30 May 2012 Version Release History Version Date By Changes 1.0 6 Oct 11 Transmission

More information

S P P 2016 TPL a n d FA C

S P P 2016 TPL a n d FA C S P P 2016 TPL-001-4 a n d FA C - 014-2 C o m p l i a n c e A s s e s s m e n t C o m p r e h e n s i v e R e p o r t 12/15/2016 Compliance and Advanced Studies Southwest Power Pool, Inc. Revision History

More information

Summary of Studies on Rate of Change of Frequency events on the All-Island System

Summary of Studies on Rate of Change of Frequency events on the All-Island System Summary of Studies on Rate of Change of Frequency events on the All-Island System August 212 Authored by: Salim Temtem & Karen Creighton Checked by: David Cashman & Raymond Skillen Approved by: Jonathan

More information

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations Technical Bulletin 2009-06-03 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations June 15, 2009 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

More information

Introduction to the PJM Markets

Introduction to the PJM Markets Introduction to the PJM Markets PJM 2015 1 Objectives Students will be able to: Describe some of the basic functions of PJM PJM 2015 The History of PJM EKPC joins PJM 2013 PJM 2015 3 Our Responsibility

More information

Eastside System Energy Storage Alternatives Screening Study. Prepared for:

Eastside System Energy Storage Alternatives Screening Study. Prepared for: Eastside System Energy Storage Alternatives Screening Study Prepared for: MARCH, 2015 1 Eastside System Energy Storage Alternatives Screening Study Prepared by: Mark Higgins Jim Eyer Randy Fish Prepared

More information

ORLANDO UTILITIES COMMISSION Open Access Transmission Tariff Original Sheet 91 SCHEDULE 7 Long-Term Firm and Short-Term Firm Point-To-Point Transmission Service The Transmission Customer shall compensate

More information

2018/2019 RPM Base Residual Auction Planning Period Parameters

2018/2019 RPM Base Residual Auction Planning Period Parameters Introduction The planning parameters for the 2018/2019 RPM Base Residual Auction (BRA) that is to be conducted in May of 2015 were posted on the PJM RPM website on January 30, 2015. Two versions of the

More information

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals Loss of Load Expectation (LOLE) Fundamentals March 13, 2014 Last material update: 03/12/2014 LOLE Agenda 2 Loss of Load Expectation (LOLE) Fundamentals Sections LOLE Background LOLE Study Connections to

More information

PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO

PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO This Proposal outlines the terms and conditions in a proposed Appendix to the Southwest Power Pool's ("SPP's") Membership Agreement

More information

Revision to ISO Transmission Planning Standards

Revision to ISO Transmission Planning Standards Revision to ISO Transmission Planning Standards Market and Infrastructure Policy Straw Proposal REVISED DRAFT May 28, 2014 Revision to ISO Transmission Planning Standards May 28, 2014 Straw Proposal Table

More information

PJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan

PJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan PJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan David Schweizer Manager, Generation OC Meeting June 6, 2017 Overview PJM target for issuing next 5-Year RTO Wide Black Start RFP

More information

MISO SPP Interregional Stakeholder Advisory Committee. April 8 th, 2014 Carmel, IN

MISO SPP Interregional Stakeholder Advisory Committee. April 8 th, 2014 Carmel, IN MISO SPP Interregional Stakeholder Advisory Committee April 8 th, 2014 Carmel, IN 1 Agenda Introductions Discussion on Draft Coordinated System Plan (CSP) Study Scope Lunch Continue Discussion on Draft

More information

PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017

PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017 PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017 Prepared by System Planning Department PJM 2017 Table of Contents Table of Contents

More information

A. Introduction Balancing Authority Reliability Coordinator Transmission Operator. 5. Effective Date:

A. Introduction Balancing Authority Reliability Coordinator Transmission Operator. 5. Effective Date: A. Introduction 1. Title: Emergency Operations 2. Number: EOP-011-1 3. Purpose: To address the effects of operating Emergencies by ensuring each Transmission Operator and Balancing Authority has developed

More information

Click to edit Master title style. Click to edit Master title style Active Network Management Workshop

Click to edit Master title style. Click to edit Master title style Active Network Management Workshop Click to edit Master title style Click to edit Master title style Active Network Management Workshop David van Kesteren System Planning Topics Click to to edit Master title style What is ANM Why do we

More information

Southern California Edison Company SOUTHERN CALIFORNIA EDISON COMPANY WHOLESALE DISTRIBUTION ACCESS TARIFF

Southern California Edison Company SOUTHERN CALIFORNIA EDISON COMPANY WHOLESALE DISTRIBUTION ACCESS TARIFF SOUTHERN CALIFORNIA EDISON COMPANY WHOLESALE DISTRIBUTION ACCESS TARIFF Original Sheet No. TABLE OF CONTENTS. Applicability.... Definitions.... Nature of Distribution Service.... Term.... Distribution

More information

STATEMENT OF WORK. Use the PJM AFC / ATC tool to calculate and post ATC values to the ComEd (MAIN) OASIS.

STATEMENT OF WORK. Use the PJM AFC / ATC tool to calculate and post ATC values to the ComEd (MAIN) OASIS. STATEMENT OF WORK SCOPE OF WORK PJM will provide tariff administration services as follows: Administration of the (MAIN) node, analysis, evaluation, granting / rejection of transmission service and response

More information