Exhibit MSD 84W ENGINEERING TIME AND MATERIALS CONTRACT REVIEW

Size: px
Start display at page:

Download "Exhibit MSD 84W ENGINEERING TIME AND MATERIALS CONTRACT REVIEW"

Transcription

1 Exhibit MSD 84W ENGINEERING TIME AND MATERIALS CONTRACT REVIEW February 2011

2 February 11, 2011 Audit Committee Metropolitan Sewer District 2350 Market Street St. Louis, MO Re: Dear Audit Committee Members: In conjunction with our overall engagement to provide internal audit services to the Metropolitan Sewer District ( District ), we have completed our Engineering Time and Materials Contract review. Our services were performed in accordance with the Professional Framework for the professional practice of Internal Auditing, as promulgated by the Institute of Internal Auditors (IIA). The accompanying report includes an Executive Summary and Project Overview, including our Findings and Recommendations. Because the procedures performed in conjunction with the review are more limited than would be necessary to provide an opinion on the system of internal accounting controls taken as a whole, such an opinion is not expressed. In addition, the engagement did not include a detailed audit of transactions that would be required to discover fraud, defalcations or other irregularities. This report is intended solely for the information and use of management and the audit committee and is not intended to be, and should not be, used by anyone other than the specified parties. The District s external auditors may be provided with a copy of this report in connection with fulfilling their responsibilities. We would like to express our gratitude to all employees involved with this project. Each person involved was accessible and responsive to our requests for information. Sincerely, RUBINBROWN LLP Chelle F. Adams, CPA Partner Direct Dial Number: chelle.adams@rubinbrown.com CFA; NEC Enclosures cc: Mr. Brian Hoelscher Mr. Karl Tyminski

3 Table of Contents Page Executive Summary 1 Findings and Recommendations 3 Management Acknowledgement 16 Appendix - A. Conte nts of the Observation and Recommendations 17 B. Consu ltant/invoice Selection 18

4 Project Objectives & Scope METROPOLITAN SEWER DISTRICT The objectives of this engagement were to: EXECUTIVE SUMMARY Identify and evaluate the internal controls over Engineering Time and Materials contracts by conducting interviews of key personnel and reviewing documented District policies and procedures. Perform detailed testing of consultant invoices to determine that all costs submitted are properly supported and accounted for per the contract terms. Present the findings and recommendations to the District for review. The scope of this engagement included: A population of all consultants that have been appropriated Engineering time and materials contracts since A sample of consultants based on the total dollars the District expended to them since A selection of one contract per consultant based on the contract size and duration of the project. A sample of approximately consultant invoices based on factors including, but not limited to: o Number of invoices o Number/timing of contract amendments o Invoice amount and composition (labor and direct cost) See Appendix for Consultant/Invoice population and sample selection statistics. 1

5 EXECUTIVE SUMMARY Findings and Recommendations The fieldwork for this review was completed in two phases: Phase I Gather the detail for testing and make requests from the applicable consultants by exercising the District s right to audit contract clause. See Appendix A for the selected consultants and contract information. Phase II Testing of submitted consultant invoices against source documentation, which the District does not currently require to be submitted, for review and approval. Based on our review, the items below highlight the significant findings: The District has standardized contract terms and conditions that address its accepted consultant invoicing practices. However, the consultants overhead and labor burden rate methodologies vary significantly. The rates reviewed for the nine selected consultants ranged from 120% to 200%. The range of rates falls within standards in the engineering / construction industry, but they appear to be inconsistently documented and enforced within the District. Four of nine consultants selected submitted invoices for direct labor in which the employee titles did not comply (match) with titles specified in the District s contract and/or amendments. The District accepted and paid these invoices despite the non-conformance to the contract terms without documentation supporting the decision to allow the payments. The current standard District engineering contract is not designed to closely control other direct costs charged by the consultants, such as technology and vehicle expenses. All findings and recommendations were discussed with management. Details are noted in the report attached immediately hereafter. 2

6 1 The overhead and labor burden rates vary significantly among consultants. The rates reviewed for the nine (9) selected consultants ranged from 120% to 200%. The range of rates falls within standards in the engineering / construction industry. While the District has standardized contract terms and conditions that address its accepted practices, these appear to be inconsistently enforced. Examples of the variation in the overhead and labor burden rates are as follows: 1) Seven (7) of the nine (9) consultants selected had audited overhead labor burden rates. Of these seven (7), six (6) consultants did not adjust their rates on the invoices per the District s standard contract. 2) One (1) of the nine (9) consultants selected used an audited Federal Acquisition Rate (FAR) overhead and labor burden rate, while the remaining consultants used a fully loaded rate. 3) Five (5) of the nine (9) consultants selected used a single overhead and labor burden rate. However, four (4) consultants used two to three varying rates (e.g., field, office). Moderate The District standard contract states: "Once an audited overhead rate becomes available, it shall be used to adjust any past billings for the period for which the audited overhead rate applies. The audited overhead rate shall become the new provisional rate until such time that the audited overhead rate for the next period becomes available." Establish consistent administration and application of the standard District contract terms and condition by considering the following: 1. Evaluate the current District standard contract language to ensure that the contract terms and actual District practices are consistent and meet the expectations of the District. 2. Ensure overhead labor burden rates are adjusted per the standard contract language. 3. Consider setting an overhead rate cap to preventatively control overhead rate fluctuations among the consultants. The items found in 1a through 1g below summarize the various overhead and; labor burden rate methodologies found during fieldwork. The District will adjust the contract language to address these issues while still providing flexibility to execute cost-effective contracts. Audited overhead values (if available) will be documented at the start of the contract and will be used to assist in development of documentation establishing the contract multiplier(s). Annually, the District will require a statement from contractor on status of the audited overhead rate and determine and document if any changes justify adjusting the multiplier for past year's invoices or future year's invoices. The District views this as a low risk finding. 3

7 1a HDR Engineering, Inc.: The overhead and labor burden rates invoiced were not in accordance with the contract. The standard District engineering contract stipulates that, as new/updated overhead and labor burden rates become available, these revised percentages are to be applied in the calculation of the consultants' invoices. Per review of HDR's invoices #3 and #13, HDR used the audited FAR for the year ended December 25, However, HDR did not update this rate in subsequent years' invoices. If the revised rates were properly used, this would not have affected invoice #3, but would have reduced the billings to the District on invoice #13 in the amount of $ However, the District contract does not specify the rate to be used. Depending on the interpretation of the contract, HDR potentially should have been using the fully loaded audited overhead rates (vs. FAR). If HDR used the fully loaded audited rates, and revised the rates as applicable, this would have resulted in an increase in billings to the District of $5, and $3, on invoices # 3 and #13, respectively. Moderate 1. Evaluate the current District standard contract language to ensure the contract language is meeting the expectations of the District. 2. Ensure all overhead and labor burden rates are managed per the District standard contract. 3. Define the appropriate overhead and labor burden rate to be used throughout the life of each individual consultant contract (and subsequent amendments). 4. Review supporting documentation (e.g., audited labor burden rate detail) for all overhead and labor burden rates contracted. 5. Monitor the overhead and labor burden rates charged to the District via the monthly review process. Reject or short pay invoices for inaccurate consultant invoicing practices (i.e., not following the contract terms). 4 See #1 on page 3.

8 1b CH2M Hill, Inc.: The consultant used un-audited overhead and labor burden rates. The consultant used three different overhead rates (Office Engineering, Field, and Field Operations) relating to a different category of work performed; this policy is approved by the contract. Moderate Same recommendations as #1a on page 4. See #1 on page 3. The commercial overhead rate audited by KPMG (163.2%) was 0.2% higher than the Office Engineering rate used on the invoice. Had the actual audited rate been used, this would have resulted in an additional charge to the District of $7.40 and $14.44 on invoices #1 and #2, respectively. We were unable to obtain support for the Field Rate (132%). The Field Operations Rate (192%) was supported by an internal schedule that was not audited or otherwise approved by an independent third party. 5

9 1c RJN Group, Inc.: An audited overhead and labor burden rate was not available at the inception of the contract. Per the RJN CFO, documentation is not available to confirm the accuracy of the 175% overhead rate that RJN currently (as of 2004) charges the District (since the rate was not audited by an external auditor). Moderate Same recommendations as #1a on page 4. See #1 on page 3. The CFO provided an IDOT/MODOT rate of % that was reviewed (not audited) by DiGiovanni, McLaren & Associates in January The overhead and labor burden rate used on the District contracts was not adjusted to the current rate of % and remains at 175%. 6

10 1d Parson Water & Infrastructure, Inc.: Adjusted overhead and labor burden rates were not used. The standard District engineering contract stipulates that, as new audited indirect cost percentages become available, the revised percentages are to be used in the calculation of invoices. Moderate Same recommendation as #1a on page 4. See #1 on page 3. Per the samples selected, Parsons billed the District from 10/16/2006 to 1/7/2010 at the overhead rate of 174% (as stated in the original contract). Audited rates during the contract years were as follows: 2006: Office %; Field % 2007: Office %; Field % 2008: Office %; Field % 2009: Office %; Field % RubinBrown applied these rates to the sampled invoices (6 of 54 total invoices selected) and found a potential over billing of $9,382. 7

11 1e Black & Veatch Corporation: The overhead and labor burden rate per the original contract was used for all billings in subsequent years. The standard District engineering contract stipulates that, as new audited overhead and labor burden rates become available, these revised percentages are to be used in the calculation of invoices. For 2006 and 2008 invoices #7 and #19, the invoice rate was 181%. However, the audited rate used should have been % and %, respectively. Had the adjusted rates been used, this would have resulted in an increase in the amounts invoiced to the District of $ and $1, on invoices #7 and #19, respectively. Moderate Same recommendations as #1a on page 4. See #1 on page 3. 8

12 1f Jacobs Engineering Groups, Inc.: The consultant charged the District overhead and labor burden rates below their audited rates. The standard District engineering contract stipulates that, as new audited overhead and labor burden rates become available, these revised percentages are to be used in the calculation of invoices. The consultant adjusted their rates, but not to the audited amounts. RubinBrown applied the audited rates to the sampled invoices (8 of 36 total invoices selected) and found a potential under billing of $75,105. Moderate Same recommendation as #1a on page 4. See #1 on page 3. 9

13 1g Kennedy Associates/Architects, Inc.: The consultant used un-audited overhead and labor burden rates. KAI switched from using a single overhead and labor burden rate to two separate rates for field and office work. However, in 2006 and 2009, the overall rate used in the calculation of the field and office rates that were used to bill the District did not agree to the audited overhead rate: Moderate Same recommendations as #1a on page 4. See #1 on page Audited rate = %; KAI used % Audited rate = %; KAI used % Per KAI s Controller, the variances are due to a difference in how expenses were classified by the auditors as direct versus indirect/overhead. KAI's general ledger agreed to the audited financial statements in total and the classification difference was deemed immaterial by KAI, so no further investigation was performed. KAI is properly preparing retroactive adjustments to invoices when the most recent audited overhead rates (for the previous calendar year) are obtained, as per the contract. 10

14 2a Jacobs Engineering Groups, Inc.: The consultant submitted invoices with employee titles that did not comply (match) with those specified in the District contract and/or amendments. Jacobs Engineering submitted payroll system reports in which the employees' titles did not match those in the executed contract. The District accepted the incorrect titles. Jacobs provided RubinBrown with employee information that could be used to justify the rates charged, however, a direct mapping to the contract was not possible for all titles submitted to the District. Low 1. Ensure proper procedures are in place to adequately identify and validate that all rates charged to the District are appropriate and within the approved contracted terms. 2. Determine the severity of the invoice inaccuracy and then either a) communicate with the consultant the invoice error noted and the credit that will be taken against their next invoice, or b) reject the consultant invoice submitted for payment if it determined to be grossly noncompliant with the executed District contract and amendments. The District will formally request any adjustment to the billing rate schedules and issue appropriate contract amendments annually. This is a clerical procedure. Note that monthly reviews by The District staff did not allow for any inappropriate billings by the consultants. The District views this as a low risk finding. 11

15 2b RJN Group, Inc.: The consultant submitted invoices with employee titles that did not comply (match) with those specified in the District contract and/or amendments. In addition, in certain cases, the contract maximum rates were exceeded. RJN submitted the job titles listed in the contract, however, when they were compared to the rates in the contract, exceptions were noted. RubinBrown investigated these differences at the RJN office and found that due to a lack of accurate reporting, employee titles were incorrectly applied to the contract. This caused fluctuations with the employee s cost-rate (i.e., a field technician listed on the invoice with a maximum contracted rate of $20 was actually a field supervisor with a cost of $21. The $21 rate was billed to the District and paid). Rob Segar of The District reported this issue to RJN after the completion of RubinBrown's Phase 1 review. RJN reviewed each invoice submitted since contract inception and updated the titles to the actual employee titles. After the RJN update, RubinBrown noted $1, of over-charges on five (5 of 54 total) invoices reviewed, mostly attributable to the office administration job title. Low Same recommendations as #2a on page See #2a on page 11.

16 2c Kennedy Associates/Architects, Inc.: The consultant submitted invoices with employee titles that did not comply (match) with those specified in the District contract and/or amendments. KAI submitted payroll system reports with the employees' titles. The District accepted the titles, although they did not match those in the executed contract. Also, four project managers were invoiced at a direct labor rate above the contract or amendment rate. Five Admin I s were listed at a rate above the contract or amendment rate. The total over charged amount paid by the District was $ Low Same recommendations as #2a on page 11. See #2a on page

17 2d URS Corporation: Unauthorized direct labor rates appeared to be billed and paid. The URS contract did not have 2009 direct labor rates. URS billed the District using the 2008 rates plus a 5% increase. Sean Devoy of URS, provided the following explanation, "we do not have an approved direct labor rate table beyond The original rate table was based upon a maximum annual 5% increase which is the manner in which we viewed work in both 2009 and 2010." Low Same recommendations as #2a on page 11. See #2a on page 11. 3a HDR Engineering, Inc.: Hours billed do not agree to hours worked in accordance with the supporting documentation. Two HDR employees (Todd Williams, Project Engineer, and Terry McArthur, Quality Control) were invoiced for four (4) more hours than were logged on the Employee Labor Distribution Reports related to invoice #13. This resulted in a total of $ in over-billings to the District. It should be noted, however, that several other employees were under-billed during this invoice period. Low 1. Ensure all invoices received are properly supported (i.e., details of hours billed and the rates applied to each employee). 2. Assess the materiality of consultant invoices that do not provide adequate support of hours and rates charged to the District and either a) communicate with the consultant that information was missing and, unless presented with appropriate documentation, a credit will be taken in that amount on a subsequent invoice, or b) reject the consultant invoice submitted for payment if it is determined to be grossly unsupported by valid documentation. Due to lack of impact to The District and the relative high cost of any corrective action, no procedural action will be taken other than to make project managers aware of this issue. 14

18 3b RJN Group, Inc.: Low Same recommendations as #3a on page See #3a on page 14. Billed employees do not match the 14. support. On invoice #26, RJN employee R. Fodge submitted 40 hours worked during the invoice period that was billed under A. Kirkpatrick; and M. Wood submitted 80 hours worked during the invoice period that was billed under E. McKeal. In each case, the rates were equal (Fodge/Kirkpatrick- $13, Wood/McKeal- $12.) Per the RJN Project Manager and CFO, this was due to the manual District invoicing process. As the rates were the same, there was no dollar impact to the District. 15

19 4 Four (4) of the eleven (11) consultants sampled charged for vehicle expenses. These expenses were not supported by documentation to defend the need for specialized equipment. In addition, the vehicle expenses were inconsistently charged, using either daily or monthly rates. Typically, normal vehicle charges should not be included as direct cost components on invoices since these costs are included in the overhead rate. In the event that specialized equipment is required to complete a contract (e.g., survey vehicles, core sampling, etc.), then it may be charged as direct costs. Low 1. Specify in the standard contract language the circumstances in which vehicle charges are allowable as a reimbursable other direct cost. 2. Require supporting documentation stating the purpose of any vehicle charges submitted for reimbursement and the reason that they are not accounted for in the overhead rate. 3. Consider limiting the rate that the District will allow for vehicle charges by using the Blue Book rental rates. The District agrees with this statement. However, the reason, need, and types of vehicles can vary greatly from project to project. Instead of just having undocumented negotiations with the consultants, The District will formally document the reason why and how vehicle charges are being allowed and require annual reviews per project. 16

20 5 Four (4) of the eleven (11) consultants sampled charged technology charges ranging from $1,000 to $3,500 per month without providing supporting documentation. Typically, technology charges are allowable as other direct costs when the technology (e.g., specialized or specific software) is outside the normal expectations of the industry. Therefore, standard and customary costs are included in the overhead rate and should not be passed through as additional direct cost. 6 Woolpert's maximum allowable rates contracted with the District were nearly four times higher than rates for the other contractors reviewed. Woolpert was unable to provide an explanation for the discrepancy in the maximum rates in the contract other than the District "approved" the rates. RubinBrown reviewed a sample of selected invoices and subsequent charges and found the actual rates charged appeared reasonable when compared to other projects/contractors. Low Low 1. Specify in the standard contract language the circumstances in which technology charges are allowable as a reimbursable other direct cost. 2. Require supporting documentation stating the purpose of any technology charges submitted for reimbursement and the reason that they are not accounted for in the overhead rate. 3. Consider limiting / capping the rate that the District will allow for technology charges. 1. Review and approval all maximum rate allowances for validity and consistency in the contract execution phase. 2. Ensure maximum rate allowances are appropriate to protect the District from abuse and fraud. The District agrees with this statement. How companies recover technology and communication charges and whether or not they are addressed in the overhead rate vary greatly among companies. Instead of just having undocumented negotiations with the consultants, The District will formally document the reason why and how communication, technology, and other unusual charges are being allowed and require annual reviews. See #3a on page 13. Note that no inappropriate billing was found because of this issue. 17

21 7 Stantec (Fixed Fee consultant): RubinBrown was unable to verify time card hours due to the lack of supporting documentation. Stantec was missing payroll system support for one (1) of three (3) invoices reviewed (invoice #3 for $12,540 of labor expense.) Per the Stantec Project Manager, no information was available due to the company's buy-out and accounting system change. The Stantec buy-out, formerly FMSM Engineering, occurred in The other sampled invoices were reviewed and no inconsistencies were noted. While there was no actual dollar exposure found in the samples reviewed, there is potential exposure to the District. Low Require that the consultants supply supporting documentation for all of the hours billed and rates applied to those employees. Due to lack of impact to The District and the relative high cost of any corrective action, no procedural action will be taken other than to make project managers aware of this issue. 18

22 MANAGEMENT ACKNOWLEDGEMENT I have reviewed the report including management responses. I agree with the observations and recommendations, unless otherwise indicated, and will take the appropriate measures and responsibility for implementing the corrective actions with the specified timeframes. Process owner s signature Brian Hoelscher, Director of Engineering 19

23 APPENDIX A CONTENTS OF THE OBSERVATION AND RECOMMENDATIONS Contents of the Observations & Recommendations The following is an overview of the content of the observations and recommendations contained in this report. Observation: Presentation of key operational and/or service issue. Exposure & Risk Rating: Assessment of the issue implications and value assignment of likelihood and impact of the identified issue / risk. The three categories are as follows: High: Observations that pose a significant risk to the District Moderate: Observations that pose a moderate risk to the District Low: Observations that pose a minor risk to the District Recommendation: Suggestions to assist management in formulating an action plan to address the issue / risk. Management Response: To be submitted to Internal Audit Services within 10 business days of receipt of final draft report by assigned stakeholders. Internal Audit will present this information to the District s Audit Committee until the issue / risk is resolved or sufficiently mitigated. 20

24 APPENDIX B CONSULTANT/INVOICE SELECTION # Consultant Engineering Consultants/Projects Selected CIPRO Number Eng. Number Approximate Contract Amount Project Manager % of Total Total Invoices # of Invoice Reviewed 1 Jacobs Engineering Groups Inc E ,300,000 Karen Janson 28.84% Woolpert Consultants, Inc E ,000,000 Rob Segar 16.62% RJN Group Inc E ,499,975 Rob Segar 14.84% Black & Veatch Corporation E ,461 Dan Hornick 1.18% HDR Engineering, Inc E ,000 Michelle Meier 1.07% Parson Water & Infrastructure Inc E ,955,000 Mark Koester 9.44% Kennedy Associates/Architechs Inc E ,234,433 Greg Rebman 10.96% URS Corporation A E ,248,522 Greg Rebman 9.79% CH2M Hill, Inc E ,000,000 Dave Friedrich 7.12% Stantec (Fixed Fee Consultant) E ,471 John Shrewsbury 0.15% Horner & Shifrin* 46 2 * This firm was removed from sampling. Total: 84,254,

Internal Audit Report. Contract Administration: 601CT Contracts TxDOT Internal Audit Division

Internal Audit Report. Contract Administration: 601CT Contracts TxDOT Internal Audit Division Internal Audit Report Contract Administration: 601CT Contracts TxDOT Internal Audit Division Objective Review contract administration and governance of 601CT contracts for structural compliance with laws

More information

INDEPENDENT ACCOUNTANT'S REPORT ON APPLYING AGREED-UPON PROCEDURES BACKGROUND

INDEPENDENT ACCOUNTANT'S REPORT ON APPLYING AGREED-UPON PROCEDURES BACKGROUND INDEPENDENT ACCOUNTANT'S REPORT ON APPLYING AGREED-UPON PROCEDURES Board of County Commissioners and Department Heads Ramsey County BACKGROUND In October 1996, a newspaper article reported that the now

More information

Horizontal Audit of the Acquisition Cards Process

Horizontal Audit of the Acquisition Cards Process Horizontal Audit of the Acquisition Cards Process Final Report December, 2012 Office of Internal Audit and Evaluation Report submitted to the Parks Canada Audit Committee: January 17, 2013 Approved by

More information

Managing Fraud Risks. Procurement & Contacting. John J. Hall, CPA (970)

Managing Fraud Risks. Procurement & Contacting. John J. Hall, CPA (970) Managing Fraud Risks in Procurement & Contacting The IIA Los Angeles Chapter October 2, 2017 John J. Hall, CPA (970) 926-0355 John@JohnHallSpeaker.com 1 Four Categories 1. Theft 2. Results Manipulation

More information

Seattle Public Schools The Office of Internal Audit

Seattle Public Schools The Office of Internal Audit Seattle Public Schools The Office of Internal Audit Internal Audit Report September 1, 2014 through Current Issue Date: June 21, 2016 Executive Summary Background Information The function is centralized

More information

Sheena Tran, CPA May 19, 2014

Sheena Tran, CPA May 19, 2014 Internal Controls Review 2012/13 Sheena Tran, CPA May 19, 2014 TO: ACCCA BOARD OF DIRECTORS This is considered to be a financial review and recommendations for the Association of California Community College

More information

Audit of. Boynton Beach Community High School

Audit of. Boynton Beach Community High School Audit of Boynton Beach Community High School January 19, 2007 Report 2007-01 Audit of Boynton Beach Community High School Table of Contents Page PURPOSE AND AUTHORITY 1 SCOPE AND METHODOLOGY 1 INVESTIGATIONS

More information

Department of Transportation Maryland Aviation Administration

Department of Transportation Maryland Aviation Administration Audit Report Department of Transportation Maryland Aviation Administration November 2012 OFFICE OF LEGISLATIVE AUDITS DEPARTMENT OF LEGISLATIVE SERVICES MARYLAND GENERAL ASSEMBLY This report and any related

More information

CITY OF CORPUS CHRISTI

CITY OF CORPUS CHRISTI CITY OF CORPUS CHRISTI CITY AUDITOR S OFFICE Audit of Purchasing Program Project No. AU12-004 September 20, 2012 City Auditor Celia Gaona, CIA CISA CFE Auditor Nora Lozano, CIA CISA Executive Summary In

More information

October 22, Internal Audit Report Reimbursable Work Orders Anchorage Water and Wastewater Utility

October 22, Internal Audit Report Reimbursable Work Orders Anchorage Water and Wastewater Utility Internal Audit Report 2008 11 Introduction. The (AWWU) performs various services for the State of Alaska Department of Transportation and Public Facilities and for the Anchorage School District (ASD).

More information

OBSERVATIONS, RECOMMENDATIONS, AND RESPONSES

OBSERVATIONS, RECOMMENDATIONS, AND RESPONSES PROJECT SUMMARY Overall, financial and management controls at Texas A&M University provide reasonable assurance that payroll expenditures are accurate and complete and in compliance with laws, policies,

More information

K-State Athletics, Inc. Report on Internal Controls related to the Contracting, Travel, and Expenditure processes.

K-State Athletics, Inc. Report on Internal Controls related to the Contracting, Travel, and Expenditure processes. K-State Athletics, Inc. Report on Internal Controls related to the Contracting, Travel, and Expenditure processes. October 30, 2009 October 30, 2009 Mr. John Currie Director of Athletics K-State Athletics,

More information

Master Document Master Document. Version 4.28, dated December 2017 B-1 Planning Considerations

Master Document Master Document. Version 4.28, dated December 2017 B-1 Planning Considerations Activity Code 17100 B-1 Planning Considerations Termination, Total Cost Basis Type of Service - Attestation Examination Engagement Audit Specific Independence Determination Members of the audit team and

More information

Department of Transportation Maryland Transit Administration

Department of Transportation Maryland Transit Administration Audit Report Department of Transportation Maryland Transit Administration February 2012 OFFICE OF LEGISLATIVE AUDITS DEPARTMENT OF LEGISLATIVE SERVICES MARYLAND GENERAL ASSEMBLY This report and any related

More information

LA16-19 STATE OF NEVADA. Performance Audit. Department of Motor Vehicles Legislative Auditor Carson City, Nevada

LA16-19 STATE OF NEVADA. Performance Audit. Department of Motor Vehicles Legislative Auditor Carson City, Nevada LA16-19 STATE OF NEVADA Performance Audit Department of Motor Vehicles 2016 Legislative Auditor Carson City, Nevada Audit Highlights Highlights of performance audit report on the Department of Motor Vehicles

More information

Brutoco Engineering Construction, Incorporated Contracts 1673 and 1677 Audit Report

Brutoco Engineering Construction, Incorporated Contracts 1673 and 1677 Audit Report Report Office of the General Auditor Internal Audit Report for November 2010 Summary Three reports were issued during the month: Brutoco Engineering Construction, Incorporated Contracts 1673 and 1677 Audit

More information

Minnesota State Community and Technical College

Minnesota State Community and Technical College Office of Internal Auditing Minnesota State Community and Technical College Internal Control and Compliance Audit Reference Number 2017-01 Report Classification: Public Dear Members of the Minnesota State

More information

Office of the City Auditor. Committed to increasing government efficiency, effectiveness, accountability and transparency

Office of the City Auditor. Committed to increasing government efficiency, effectiveness, accountability and transparency Office of the City Auditor Committed to increasing government efficiency, effectiveness, accountability and transparency Issue Date: TABLE OF CONTENTS Executive Summary... ii Recommendation... iv Background...1

More information

Master Document Audit Program. Activity Code Compliance Audit CAS 407 Version 5.19, dated December 2017 B-1 Planning Considerations

Master Document Audit Program. Activity Code Compliance Audit CAS 407 Version 5.19, dated December 2017 B-1 Planning Considerations Activity Code 19407 Compliance Audit CAS 407 B-1 Planning Considerations Type of Service - Attestation Examination Engagement Audit Specific Independence Determination Members of the audit team and internal

More information

Charges to sponsored projects are classified as either non-salary or salary.

Charges to sponsored projects are classified as either non-salary or salary. EXPENDITURE APPROVAL AND CONTROL INITIATING CHARGES TO SPONSORED PROJECTS Charges to sponsored projects are classified as either non-salary or salary. Non-salary charges are initiated via: 1. Pcard; 2.

More information

Bluewaters Power 1 Pty Ltd

Bluewaters Power 1 Pty Ltd Bluewaters Power 1 Pty Ltd Electricity Generation Licence (EGL 4) 2014 Performance Audit (Independent Assurance) Report June 2014 Deloitte Touche Tohmatsu ABN 74 490 121 060 Woodside Plaza Level 14 240

More information

INTERNAL AUDIT REPORT

INTERNAL AUDIT REPORT REPORT CENTRALIZED INTERNATIONAL SUPPORT SERVICES AGREEMENT LIMITED OPERATIONAL AUDIT ISSUE DATE: JUNE 27, 2017 REPORT NO. 2017-04 EXECUTIVE SUMMARY AUDIT OBJECTIVES AND SCOPE The purpose of the audit

More information

AUDIT OF KEY FINANCIAL PROCESSES AT MAINLAND NOVA SCOTIA FIELD UNIT FINAL REPORT PREPARED BY PROGESTIC INTERNATIONAL INC.

AUDIT OF KEY FINANCIAL PROCESSES AT MAINLAND NOVA SCOTIA FIELD UNIT FINAL REPORT PREPARED BY PROGESTIC INTERNATIONAL INC. AUDIT OF KEY FINANCIAL PROCESSES AT MAINLAND NOVA SCOTIA FIELD UNIT FINAL REPORT PREPARED BY PROGESTIC INTERNATIONAL INC March 2005 Report tabled and approved by A&E Committee TABLE OF CONTENTS 1. BACKGROUND...

More information

CORP Appendix A CORPORATE POLICY. Attachments: Related Documents/Legislation: Revenue Administrative Policy

CORP Appendix A CORPORATE POLICY. Attachments: Related Documents/Legislation: Revenue Administrative Policy CORP2014-085 Appendix A CORPORATE POLICY Policy Title: Cash Handling Policy Policy Category: Financial Control Policy Policy No.: FC-016 Department: Corporate Services Approval Date: Revision Date: Author:

More information

City and County of San Francisco

City and County of San Francisco City and County of San Francisco Office of the Controller City Services Auditor OFFICE OF CONTRACT ADMINISTRATION: Office Depot Did Not Comply With Its Contract and Has Overcharged the City at Least $5.75

More information

Internal Audit Report. Facilities Services Contract Management

Internal Audit Report. Facilities Services Contract Management Internal Audit Report Report Number: 2017-01 Report Date: March 10, 2017 Executive Summary Audit Report No.: 2017-01 March 10, 2017 WE AUDITED the Facilities Division s management controls over the management

More information

RBA Validated Audit Program (VAP) Operations Manual Revision January 2018

RBA Validated Audit Program (VAP) Operations Manual Revision January 2018 RBA Validated Audit Program (VAP) Operations Manual Revision 6.0.0 January 2018 Organizations working with and in the Responsible Business Alliance (RBA) www.responsiblebusiness.org are working to improve

More information

Govt. Contracting, Dynamics 365 Operations Implementing Dynamics 365 Operations for Govt. Contractors PVBS

Govt. Contracting, Dynamics 365 Operations Implementing Dynamics 365 Operations for Govt. Contractors PVBS Implementing Dynamics 365 Operations for Govt. Contractors PVBS Contents Background... 4 Setups... 4 Project Management and Accounting... 4 Ledger Posting Setup... 4 Category Groups... 4 Category Group

More information

Maryland School for the Deaf

Maryland School for the Deaf Audit Report Maryland School for the Deaf December 2015 OFFICE OF LEGISLATIVE AUDITS DEPARTMENT OF LEGISLATIVE SERVICES MARYLAND GENERAL ASSEMBLY For further information concerning this report contact:

More information

Contract and Procurement Fraud. Fraud in Procurement without Competition

Contract and Procurement Fraud. Fraud in Procurement without Competition Contract and Procurement Fraud Fraud in Procurement without Competition Sole-Source Awards Noncompetitive procurement process through the solicitation of only one source Procurement through sole-source

More information

PART 3.4 DEPARTMENT OF TRANSPORTATION AND WORKS USE OF GOVERNMENT VEHICLES

PART 3.4 DEPARTMENT OF TRANSPORTATION AND WORKS USE OF GOVERNMENT VEHICLES PART 3.4 DEPARTMENT OF TRANSPORTATION AND WORKS USE OF GOVERNMENT VEHICLES Summary Introduction The Department of Transportation and Works (the Department) is responsible for monitoring and managing Government

More information

University System of Maryland University of Baltimore

University System of Maryland University of Baltimore Audit Report University System of Maryland University of Baltimore January 2018 OFFICE OF LEGISLATIVE AUDITS DEPARTMENT OF LEGISLATIVE SERVICES MARYLAND GENERAL ASSEMBLY For further information concerning

More information

STATE OF NORTH CAROLINA

STATE OF NORTH CAROLINA STATE OF NORTH CAROLINA DEPARTMENT OF AGRICULTURE & CONSUMER SERVICES STANDARDS DIVISION LIQUEFIED PETROLEUM GAS SECTION FINANCIAL RELATED AUDIT VIOLATION ENFORCEMENT INVESTIGATION FOLLOW-UP OCTOBER 2013

More information

AN AUDIT OF INTERNAL CONTROL THAT IS INTEGRATED WITH AN AUDIT OF FINANCIAL STATEMENTS: GUIDANCE FOR AUDITORS OF SMALLER PUBLIC COMPANIES

AN AUDIT OF INTERNAL CONTROL THAT IS INTEGRATED WITH AN AUDIT OF FINANCIAL STATEMENTS: GUIDANCE FOR AUDITORS OF SMALLER PUBLIC COMPANIES 1666 K Street, NW Washington, D.C. 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8430 www.pcaobus.org PRELIMINARY STAFF VIEWS AN AUDIT OF INTERNAL CONTROL THAT IS INTEGRATED WITH AN AUDIT OF FINANCIAL

More information

Request for Proposal For: 2018 American Bar Association Temporary Services

Request for Proposal For: 2018 American Bar Association Temporary Services Table of Contents Bid Timetable [2] 1.0 General Bid Information [3] 2.0 Proposal Requirements [5] 3.0 Criteria for Selection [7] 4.0 Specifications and Work Statement [7] Appendix A: Bidder Response Sheet

More information

OFFICE OF FLEET MANAGEMENT AUDITOR S REPORT FISCAL YEARS

OFFICE OF FLEET MANAGEMENT AUDITOR S REPORT FISCAL YEARS OFFICE OF FLEET MANAGEMENT AUDITOR S REPORT FISCAL YEARS 2007 2009 June 21, 2010 Mr. James F. Muller, Fleet Manager Office of Fleet Management 100 South Broad Street, 3 rd Floor Philadelphia, PA 19110

More information

Uncompensated Overtime. Next Slide

Uncompensated Overtime. Next Slide Uncompensated Overtime Table of Contents Risk Assessment Research and Planning Risk Assessment Labor System Entrance Conference Preliminary Analytical Procedures Audit Team Brainstorming for Fraud Risk

More information

Audit Report. Audit of Contracting and Procurement Activities

Audit Report. Audit of Contracting and Procurement Activities Audit Report August 2012 Recommended for Approval to the Deputy Minister by the Departmental Audit Committee on October 12, 2012 Approved by the Deputy Minister on October 18, 2012 Table of Contents Table

More information

Procurement Management Internal Audit

Procurement Management Internal Audit INTERNAL AUDIT REPORT Procurement Management Internal Audit R-17-11 October 9, 2017 Executive Summary Introduction Internal Audit (IA) has been directed by the Board to perform an internal audit on the

More information

Office of Internal Audit

Office of Internal Audit Office of Internal Audit February 26, 2013 Dr. Kirk A. Calhoun, M.D. The University of Texas Health Science Center at Tyler 11937 U. S. Hwy 271 Tyler, TX 75708 Dr. Calhoun: In October 2012, Chancellor

More information

Audit of. Accounts Payable Procedures

Audit of. Accounts Payable Procedures Audit of Accounts Payable Procedures November 20, 2015 Report #2015-16 MISSION STATEMENT The School Board of Palm Beach County is committed to providing a world class education with excellence and equity

More information

Oracle ERP Cloud Period Close Procedures

Oracle ERP Cloud Period Close Procedures Oracle ERP Cloud Period Close Procedures Release 13 O R A C L E W H I T E P A P E R A U G U S T 2 0 1 7 Table of Contents Introduction 8 Chapter 1 Period Close Dependencies 9 Chapter 2 Subledger Accounting

More information

Internal Control Evaluation

Internal Control Evaluation INTERNAL CONTROL EVALUATION Adapted from a checklist created by Jackie F. Breland, CPA (www.jackiebreland.com) Organization: Date Prepared or Updated: Prepared by: Introduction The purpose of this checklist

More information

Loch Lomond and The Trossachs National Park Authority. Key Controls Report

Loch Lomond and The Trossachs National Park Authority. Key Controls Report Loch Lomond and The Trossachs National Park Authority Key Controls Report Prepared for Loch Lomond and The Trossachs Park Authority April 2015 Audit Scotland is a statutory body set up in April 2000 under

More information

Eric Anderson, City Manager. Scottie Nix, Internal Auditor

Eric Anderson, City Manager. Scottie Nix, Internal Auditor City of Tacoma Internal Audit Office Memorandum TO: FROM: SUBJECT: Eric Anderson, City Manager Scottie Nix, Internal Auditor Improving SAP Roles Assignment and Monitoring at the City of Tacoma Follow Up

More information

Quality Sign off for Internal Audit Engagement. Name of Audit

Quality Sign off for Internal Audit Engagement. Name of Audit This is a sample of a quality sign off form for an internal audit engagement and is intended as a practical example. It should be reviewed and modified to suit the operations of your Internal Audit function.

More information

Understanding the DCAA Audit Process and How to Prepare for Success

Understanding the DCAA Audit Process and How to Prepare for Success Understanding the DCAA Audit Process and How to Prepare for Success Breakout Session #: C11 Presented by: Beverly Arviso, CPA, Fellow, CPCM, CFCM Date: July 22, 2013 Time: 4:00-5:15 DCAA s Mission Compliance

More information

RBA Validated Audit Program (VAP) Operations Manual Revision January 2018

RBA Validated Audit Program (VAP) Operations Manual Revision January 2018 RBA Validated Audit Program (VAP) Operations Manual Revision 6.0.0 January 2018 Organizations working with and in the Responsible Business Alliance (RBA) www.responsiblebusiness.org are working to improve

More information

FLORIDA DEPARTMENT OF TRANSPORTATION

FLORIDA DEPARTMENT OF TRANSPORTATION FLORIDA DEPARTMENT OF TRANSPORTATION 6-month Follow-up to the Office of the Auditor General Information Technology Operational Audit-Department of Transportation Electronic Estimate Disbursement System

More information

Internal Audit Policy and Procedures Internal Audit Charter

Internal Audit Policy and Procedures Internal Audit Charter Mission Statement Internal Audit Policy and Procedures Internal Audit Charter The mission of the Internal Audit Department is to provide independent and objective reviews and assessments of the business

More information

2017 Archaeology Audit Program Procedure Manual. April 2017

2017 Archaeology Audit Program Procedure Manual. April 2017 2017 Archaeology Audit Program Procedure Manual April 2017 Table of Contents Contents Table of Contents... 2 1.0 Introduction and Scope... 3 2.0 Audit Objectives... 3 3.0 Audit Procedures... 4 3.1 Audit

More information

Comptroller of the Treasury Central Payroll Bureau

Comptroller of the Treasury Central Payroll Bureau Audit Report Comptroller of the Treasury Central Payroll Bureau June 2006 OFFICE OF LEGISLATIVE AUDITS DEPARTMENT OF LEGISLATIVE SERVICES MARYLAND GENERAL ASSEMBLY This report and any related follow-up

More information

CLERK OF THE CIRCUIT COURT

CLERK OF THE CIRCUIT COURT Collier County Clerk of the Circuit Court Internal Audit Department Audit Report 2003 8 Water & Sewer Revenue Audit Collier County CLERK OF THE CIRCUIT COURT Collier County Clerk of the Circuit Court

More information

A REPORT FROM THE OFFICE OF INTERNAL AUDIT

A REPORT FROM THE OFFICE OF INTERNAL AUDIT A REPORT FROM THE OFFICE OF INTERNAL AUDIT PRESENTED TO THE CITY COUNCIL CITY OF BOISE, IDAHO AUDIT / TASK: #12-08S1, Purchasing Compliance AUDIT CLIENT: Purchasing / Cross-Functional REPORT DATE: August

More information

The University of Texas at Tyler. Contract Administration Audit

The University of Texas at Tyler. Contract Administration Audit November 2016 THE UNIVERSITY OF TEXAS AT TYLER OFFICE OF AUDIT AND CONSULTING SERVICES 3900 UNIVERSITY BOULEVARD TYLER, TEXAS 75799 BACKGROUND This audit was conducted to determine if The University of

More information

Audit and Advisory Services Integrity, Innovation and Quality. Audit of Internal Controls over Financial Reporting

Audit and Advisory Services Integrity, Innovation and Quality. Audit of Internal Controls over Financial Reporting Audit and Advisory Services Integrity, Innovation and Quality Audit of Internal Controls over Financial Reporting October 2015 Table of Contents i Audit of Internal Controls over Financial Reporting EXECUTIVE

More information

Auditing Standards and Practices Council

Auditing Standards and Practices Council Auditing Standards and Practices Council PHILIPPINE STANDARD ON AUDITING 330 THE AUDITOR S PROCEDURES IN RESPONSE TO ASSESSED RISKS PHILIPPINE STANDARD ON AUDITING 330 THE AUDITOR S PROCEDURES IN RESPONSE

More information

Fiscal Year 2014 Internal Audit Annual Report

Fiscal Year 2014 Internal Audit Annual Report Fiscal Year 2014 Internal Audit Annual Report Prepared by Tarrant County College District Internal Audit Department TABLE OF CONTENTS I. Compliance with House Bill 16 (Texas Government Code, Section 2102.015):

More information

6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents

6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents Document (00 21 13) Rudolph/Libbe Inc. www.rlcos.com 6494 Latcha Rd. Walbridge, Ohio 43465 v: 419.241-5000 f: 419.837.9373 Table of Contents 1.0 General Instructions 1.1 Document Hierarchy 1.2 Safety 1.3

More information

STUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems

STUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems January 2017 CON170, Unit 5 Lesson 1 Cost Analysis Process and Players

More information

Request For Proposal Of Printing and Design Services. Marketing Department

Request For Proposal Of Printing and Design Services. Marketing Department Request For Proposal Of Printing and Design Services Marketing Department Released on June 3, 2016 Mosaic Youth Theatre of Detroit Printing and Design Services REQUEST FOR PROPOSAL (RFP) BACKGROUND Mosaic

More information

Make or Buy Decisions in a Proposal Audit. Next Slide

Make or Buy Decisions in a Proposal Audit. Next Slide Make or Buy Decisions in a Proposal Audit Table of Contents Risk Assessment Research and Planning Risk Assessment Initial Review of Proposal Risk Assessment Coordination with the PCO and ACO Preliminary

More information

Internal Audit Report

Internal Audit Report Internal Audit Report C u y a h o g a C o u n t y, O h i o D e p a r t m e n t o f I n t e r n a l A u d i t i n g Benford s Law Audit 2016 Cuyahoga County Fiscal Office Accounts Payable January 1, 2016

More information

The Auditor s Responses to Assessed Risks

The Auditor s Responses to Assessed Risks SINGAPORE STANDARD SSA 330 ON AUDITING The Auditor s Responses to Assessed Risks SSA 330, The Auditor s Responses to Assessed Risks superseded SSA 330, The Auditor s Procedures in Response to Assessed

More information

INVOICE DEVELOPMENT AND SUBMITTAL PROCESS

INVOICE DEVELOPMENT AND SUBMITTAL PROCESS INVOICE DEVELOPMENT AND SUBMITTAL PROCESS Tamika Griffin November 3, 2017 Table of Contents 1 2 3 4 5 6 7 Standard Operating Procedure Roles and Responsibilities Invoice Submittal Payment Types and Required

More information

Engagements to Perform. Agreed-Upon Procedures. Regarding Financial Information

Engagements to Perform. Agreed-Upon Procedures. Regarding Financial Information Issued November 2004 Effective upon issue Hong Kong Standard on Related Services 4400 Engagements to Perform Agreed-Upon Procedures Regarding Financial Information ENGAGEMENTS TO PERFORM AGREED-UPON PROCEDURES

More information

BOM/BSD 2/November 1994 BANK OF MAURITIUS. Guideline on Maintenance of Accounting and other Records and Internal Control Systems

BOM/BSD 2/November 1994 BANK OF MAURITIUS. Guideline on Maintenance of Accounting and other Records and Internal Control Systems BOM/BSD 2/November 1994 BANK OF MAURITIUS Guideline on Maintenance of Accounting and other Records and Internal Control Systems November 1994 Revised November 2013 Revised December 2017 TABLE OF CONTENTS

More information

Understanding Internal Controls Office of Internal Audit

Understanding Internal Controls Office of Internal Audit Understanding Internal Controls Office of Internal Audit July 2015 Objectives for this manual Provide guidance to help management understand their responsibility to ensure that internal controls are established,

More information

Contractor Business Systems Earned Value Management, Material Management and Accounting, and Property Management

Contractor Business Systems Earned Value Management, Material Management and Accounting, and Property Management McKenna Government Contracts, continuing excellence in Dentons Contractor Business Systems Earned Value Management, Material Management and Accounting, and Property Management Michael McGuinn, Dentons

More information

Queen Anne s County. ADDENDUM NO. 1 July 31, 2015

Queen Anne s County. ADDENDUM NO. 1 July 31, 2015 Queen Anne s County County Commissioners: James J. Moran, At Large Jack N. Wilson, Jr., District 1 Stephen Wilson, District 2 Robert Charles Buckey, District 3 Mark A. Anderson, District 4 OFFICE OF BUDGET,

More information

Using Transactional Analysis for

Using Transactional Analysis for Using Transactional Analysis for Effective Fraud Detection Date: 15 th January 2009 Nishith Seth Seth Services.P. Ltd. www.sspl.net.in Cost Indirect costs: image, morale Fraud Issues & Impact Direct costs:

More information

College of Engineering and Computer Science Dean's Office

College of Engineering and Computer Science Dean's Office THE UNIVERSITY OF TEXAS-PAN AMERICAN OFFICE OF AUDITS & CONSULTING SERVICES College of Engineering and Computer Science Dean's Office Report No. 13-16 OFFICE OF INTERNAL AUDITS THE UNIVERSITY OF TEXAS

More information

AUDIT STATUS. Continuous Auditing Ideas and Priority Ranking Draft: 8/7/2012

AUDIT STATUS. Continuous Auditing Ideas and Priority Ranking Draft: 8/7/2012 Compliance Identify single day stays and subsequent re-admissions Identify inappropriate unbundling of lab tests Identify frequent use of high risk organizations Match OIG-excluded providers list with

More information

INTERNATIONAL STANDARD ON AUDITING (NEW ZEALAND) 520

INTERNATIONAL STANDARD ON AUDITING (NEW ZEALAND) 520 Issued 07/11 Compiled 11/13 INTERNATIONAL STANDARD ON AUDITING (NEW ZEALAND) 520 Analytical Procedures (ISA (NZ) 520) This compilation was prepared in October 2013 and incorporates amendments up to and

More information

The University of Texas at Tyler. Procurement and Travel Card Audit

The University of Texas at Tyler. Procurement and Travel Card Audit February 2016 THE UNIVERSITY OF TEXAS AT TYLER OFFICE OF AUDIT AND CONSULTING SERVICES 3900 UNIVERSITY BOULEVARD TYLER, TEXAS 75799 BACKGROUND The University of Texas at Tyler (UT Tyler) offers University

More information

Quality Control Review Checklist

Quality Control Review Checklist Institute of Cost and Management Accountants of Pakistan Quality Control Review Checklist For Cost Audit Engagements Issued By Quality Assurance Board Table of Contents 1. PRE ENGAGEMENT ACTIVITIES...

More information

TTC AUDIT COMMITTEE REPORT NO.

TTC AUDIT COMMITTEE REPORT NO. Form Revised: February 2005 TTC AUDIT COMMITTEE REPORT NO. MEETING DATE: January 23, 2011 SUBJECT: INTERNAL AUDIT PLANT MAINTENANCE DEPARTMENT BUILDING EQUIPMENT, FACILITIES, AND PLANT MAINTENANCE ENGINEERING

More information

Price Analysis and Reasonable Pricing. government contracting

Price Analysis and Reasonable Pricing. government contracting Price Analysis and Reasonable Pricing 1 Bill Walter, CPA Managing Director DHG GovCon Advisory Bill.Walter@dhgllp.com 1410 Spring Hill Road, Suite 500 Tysons, VA 22102 (703) 970.0509 Steve Masiello Partner

More information

A udit R eport. Office of the Inspector General Department of Defense. Report No. D October 19, 2001

A udit R eport. Office of the Inspector General Department of Defense. Report No. D October 19, 2001 A udit R eport CONTROLS OVER THE COMPUTERIZED ACCOUNTS PAYABLE SYSTEM AT DEFENSE FINANCE AND ACCOUNTING SERVICE KANSAS CITY Report No. D-2002-008 October 19, 2001 Office of the Inspector General Department

More information

HFTP Hospitality Financial and Technology Professionals

HFTP Hospitality Financial and Technology Professionals About our Sample Accounting Jobs Descriptions for Clubs: The HFTP Americas Research Center, with guidance from members of the HFTP Club Advisory Council, has developed example job descriptions for accounting

More information

SRI LANKA STANDARD ON RELATED SERVICES 4400 ENGAGEMENTS TO PERFORM AGREED-UPON PROCEDURES REGARDING FINANCIAL INFORMATION

SRI LANKA STANDARD ON RELATED SERVICES 4400 ENGAGEMENTS TO PERFORM AGREED-UPON PROCEDURES REGARDING FINANCIAL INFORMATION SRI LANKA STANDARD ON 4400 ENGAGEMENTS TO PERFORM AGREED-UPON PROCEDURES REGARDING FINANCIAL INFORMATION (This Standard is effective for all the audits commencing on or after 01 April 2010) CONTENTS Paragraph

More information

STATE OF NORTH CAROLINA

STATE OF NORTH CAROLINA STATE OF NORTH CAROLINA PERFORMANCE AUDIT NORTH CAROLINA DEPARTMENT OF TRANSPORTATION FERRY DIVISION JULY 2011 OFFICE OF THE STATE AUDITOR BETH A. WOOD, CPA STATE AUDITOR PERFORMANCE AUDIT NORTH CAROLINA

More information

C H E C K L I S T F O R O R G A N I S A T I O N A L C A P A C I T Y A S S E S S M E N T ( C O C A )

C H E C K L I S T F O R O R G A N I S A T I O N A L C A P A C I T Y A S S E S S M E N T ( C O C A ) C H E C K L I S T F O R O R G A N I S A T I O N A L C A P A C I T Y A S S E S S M E N T ( C O C A ) Introduction The Checklist for Organisational Capacity Assessment (COCA) is an essential instrument when

More information

A U D I T R E P O R T. Audit of Lee County Utilities

A U D I T R E P O R T. Audit of Lee County Utilities A U D I T R E Audit of Lee County Utilities P O R T Internal Audit Department Audit Number 2012.17 October 2012 October 04, 2012 Linda Doggett, COO Re: Audit of Lee County Utilities Dear Mrs. Linda Doggett:

More information

CPA REVIEW SCHOOL OF THE PHILIPPINES M a n i l a. AUDITING THEORY Risk Assessment and Response to Assessed Risks

CPA REVIEW SCHOOL OF THE PHILIPPINES M a n i l a. AUDITING THEORY Risk Assessment and Response to Assessed Risks Page 1 of 7 CPA REVIEW SCHOOL OF THE PHILIPPINES M a n i l a Related PSAs: PSA 400, 315 and 330 AUDITING THEORY Risk Assessment and Response to Assessed Risks 1. Which of the following is correct statement?

More information

TxDOT Internal Audit Travel Division Operations Audit (1405-1) Department-wide Report

TxDOT Internal Audit Travel Division Operations Audit (1405-1) Department-wide Report Travel Division Operations Audit (1405-1) Department-wide Report Introduction This report has been prepared for the Transportation Commission, TxDOT Administration and Management. The report presents the

More information

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Government Purchase Cards

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Government Purchase Cards DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Government Purchase Cards Contracts Directorate DCMA-INST 117 CPR: DCMA-AQ Validated current, March 10, 2014 1. PURPOSE. This Instruction:

More information

CLAIMS AND DISBURSEMENTS

CLAIMS AND DISBURSEMENTS CLAIMS AND DISBURSEMENTS LEGAL COMPLIANCE MANUAL CLAIMS AND DISBURSEMENTS Introduction Municipal transactions involving an account, claim, or demand made for any property or service which can be itemized

More information

Leading KPIs of Positive Financial Performance. Presented by: Hugh Shaw, Ventera Corporation Bill Riviere, Unanet

Leading KPIs of Positive Financial Performance. Presented by: Hugh Shaw, Ventera Corporation Bill Riviere, Unanet Leading KPIs of Positive Financial Performance Presented by: Hugh Shaw, Ventera Corporation Bill Riviere, Unanet Introduction Hugh Shaw (Ventera Corporation) Bill Riviere (Unanet) 2 KPI Introduction Monitoring

More information

Accounting and Auditing for Government Contractors

Accounting and Auditing for Government Contractors Accounting and Auditing for Government Contractors Presented By: C. P. Krishnan Newport Beach (CA) Dallas (TX) Washington (D.C) New Delhi (India) For more info - www.sba.gov Who is DCAA? The Defense Contract

More information

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO.

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO. Request for Proposals (RFP) Information Technology Independent Verification and Validation ADDENDUM NO. 2 Questions and Answers RFP Amendments September 2015 Contained herein are the responses to the questions

More information

Guide to Internal Controls

Guide to Internal Controls Guide to Internal Controls Updated January 2017 The Guide to Internal Controls was developed to help you establish and maintain effective internal controls in your department/division. This guide summarizes

More information

Air Quality Peer Exchange Support Services. From the: American Association of State Highway and Transportation Officials

Air Quality Peer Exchange Support Services. From the: American Association of State Highway and Transportation Officials REQUEST FOR PROPOSAL FOR Air Quality Peer Exchange Support Services From the: American Association of State Highway and Transportation Officials October 11, 2013 A. INTRODUCTION: The American Association

More information

Utilities Department Capital Projects Contract Audit

Utilities Department Capital Projects Contract Audit City Auditor s Office Utilities Department Capital Projects Contract Audit Report Issued: March 3, 2017 Audit Report No. # 16 A 2 P O Box 150027 815 Nicholas Pkwy. Cape Coral, FL 33915-0027 Phone 239-242-3383

More information

Contracting for Goods and Services

Contracting for Goods and Services Contracting for Goods and Services Northwest Territories Office of the Auditor General of Canada Bureau du vérificateur général du Canada Ce document est également publié en français. This document is

More information

AAT(SA) RECOGNITION OF PRIOR LEARNING SKILLCHECK QUESTIONNAIRE

AAT(SA) RECOGNITION OF PRIOR LEARNING SKILLCHECK QUESTIONNAIRE Skillcheck Questionnaire The Skillcheck Questionnaire will help you to decide which level of the AAT membership framework you should apply for. Choosing the right level of membership If you already have

More information

SEMINOLE COUNTY OFFICE OF MANAGEMENT AND BUDGET PURCHASING DIVISION BLANKET PURCHASE ORDER PROCESS AUDIT. March 31, 1998

SEMINOLE COUNTY OFFICE OF MANAGEMENT AND BUDGET PURCHASING DIVISION BLANKET PURCHASE ORDER PROCESS AUDIT. March 31, 1998 SEMINOLE COUNTY OFFICE OF MANAGEMENT AND BUDGET PURCHASING DIVISION BLANKET PURCHASE ORDER PROCESS AUDIT March 31, 1998 March 31, 1998 The Honorable Randall C. Morris Chairman The Board of County Commissioners

More information

ACTION REQUIRED. Date: September 27, TTC Audit & Risk Management Committee. Auditor General

ACTION REQUIRED. Date: September 27, TTC Audit & Risk Management Committee. Auditor General ACTION REQUIRED Date: September 27, 2017 To: From: Subject: TTC Audit & Risk Management Committee Auditor General Auditor General s Report Review of Toronto Transit Commission Accounts Payable Functions:

More information

Is the request amount $5000 or less and under guidelines for small purchase orders? Yes. Purchase needed

Is the request amount $5000 or less and under guidelines for small purchase orders? Yes. Purchase needed Purchase needed Process requisition via ishop selects form type for requisition. Is the request amount $5000 or less and under guidelines for small purchase orders? Workflow receives and evaluates bids

More information

Master Document Master Document. Version 8.13, dated December 2017 B-1 Planning Considerations

Master Document Master Document. Version 8.13, dated December 2017 B-1 Planning Considerations Activity Code 11015 Version 8.13, dated December 2017 B-1 Planning Considerations Testing of Paid Vouchers Type of Service - Attestation Examination Engagement Audit Specific Independence Determination

More information