1 Presented To: San Diego County Regional Airport Authority Strategic Planning Committee Lindbergh Field Alternatives Considered May 22,

2 Alternatives Considered - Outline Lindbergh Field Site Constraints Terrain Obstructions 2001 Master Plan Concepts Concepts A to G Airport Site Selection Program (ASSP) Concept Concepts 1 to 6 Findings 2001 Master Plan Concept F ASSP Concept 6 Future Technology Summary Comparison 2

3 3 Lindbergh Field Development Constraints

4 Master Plan Concepts

5 2001 Master Plan Concept A Source: HNTB, June Advantages: Builds on existing terminal facilities Implementation and phasing Minimal cost Disadvantages: Does not provide enhanced airfield No enhanced access (no connection to I-5 or rail line) 5

6 2001 Master Plan Concept B1 Source: HNTB, June Advantages: Builds on existing terminal, access and parking facilities Implementation and phasing One of the least expensive concepts Disadvantages: Does not provide enhanced airfield capacity or reliability No enhanced access (no connection to I- 5 or rail line) 6

7 2001 Master Plan Concept B2 Source: HNTB, June Advantages: Takes advantage of access to I-5 and rail line Builds on existing terminal facilities Implementation and phasing Disadvantages: Does not provide enhanced airfield capacity or reliability Split terminal complex scenario 7

8 2001 Master Plan Concept C Source: HNTB, June Advantages: Provides increase in airfield capacity with parallel runways Takes advantage of I-5 and rail line Implementation and phasing Disadvantages: Does not build on existing terminal, access and parking facilities Requires acquisition of Teledyne-Ryan property 8

9 2001 Master Plan Concept D2 Source: HNTB, June Advantages: Provides increase in airfield capacity Takes advantage of access to I-5 and rail line Builds on existing terminal facilities Minimal disruption of operations during implementation Disadvantages: Relatively higher development costs (2 new runways and APM) Requires acquisition of MCRD property 9

10 2001 Master Plan Concept E Source: HNTB, June Advantages: Provides increase in airfield capacity with parallel runways Builds on existing terminal, access and parking facilities Implementation and phasing Disadvantages: No enhanced access (no connection to I-5 or rail line) Requires relocation of ATCT and fuel farm Requires acquisition of Teledyne-Ryan property 10

11 2001 Master Plan Concept E2 Source: HNTB, June Advantages: Provides increase in airfield capacity Takes advantage of access to I-5 and rail line Builds on existing terminal facilities Implementation and phasing Disadvantages: Relatively higher development costs (2 new runways and APM) Requires acquisition of MCRD property 11

12 2001 Master Plan Concept F Source: HNTB, June Advantages: Provides greatest increase in airfield capacity Avoids some existing Point Loma obstructions/residential areas Takes advantage of access to I-5 and rail line Disadvantages: Does not build on existing terminal, access and parking facilities Requires relocation of ATCT and fuel farm Requires closure of MCRD 12

13 2001 Master Plan Concept G (SDIA) Source: HNTB, June Connection to NAS North Island Advantages: Provides increase in airfield capacity with North Island airfield Takes advantage of access to I-5 and rail line Redirects departures and arrivals over the water Disadvantages: Requires split operation Higher development and implementation costs Acquisition of Naval property and joint use operation authorization 13

14 2001 Master Plan Concept G (NAS North Island) Connection to Lindbergh Field Source: HNTB, June Advantages: Provides increase in airfield capacity with North Island airfield Takes advantage of access to I-5 and rail line Redirects departures and arrivals over the water Disadvantages: Requires split operation Higher development and implementation costs Acquisition of Naval property and joint use operation authorization 14

15 15 ASSP Concepts

16 Lindbergh Field - Concept 1 - Rejected by Board Disadvantages Airfield capacity unmet Obstructions severely limit runway use Environmental/coastal impacts Land acquisition Community impacts Harbor Drive/traffic impacts 16

17 Lindbergh Field - Concept 2 - Rejected by Board Disadvantages Airfield capacity unmet Obstructions severely limit runway use Land acquisition Community impacts 17

18 Lindbergh Field - Concept 3 - Rejected by Board Disadvantages Airfield capacity unmet Obstructions severely limit runway use Land acquisition Community impacts 18

19 Lindbergh Field - Concept 4 - Rejected by Board Disadvantages Airfield capacity unmet Obstructions severely limit runway use Environmental/coastal impacts Land acquisition Community impacts Harbor Drive/traffic impacts 19

20 Lindbergh Field - Concept 5 - Rejected by Board Disadvantages NAS North Island airspace interaction Land acquisition Community Impacts Wind coverage Impact to shipping channel 20

21 Lindbergh Field - Concept 6 Eliminated by the Board Advantages: Meets operational demand Use of existing airside, terminal and access facilities Limited impacts to MCRD Disadvantages: Land acquisition Community disruptions Environmental impacts Payload range limitations (terrain obstructions) 21

22 Findings Concept F Operational Requirement Partially meets PAL 30 requirements Does not provide dual, independent approaches Does not provide 12,000-ft departure runway Community Disruption 135 housing units 317 residents Land Acquisition Land acquisition area of 472 acres Total site area of 1,133 acres Infrastructure Impacts MCRD Acquisition Noise Impacts 65 db CNEL impacts 26,743 people versus 19,560 in existing conditions 65 db CNEL impacts 12,194 housing units versus 9,794 in existing conditions 22

23 Findings Concept F Operational Requirement Partially meets PAL 30 requirements Does not provide dual, independent approaches Community Disruption 588 housing units 1,537 residents Land Acquisition Land acquisition area of 603 acres Total site area of 1,264 acres Infrastructure Impacts MCRD Acquisition Noise Impacts 65 db CNEL impacts 26,743 people versus 19,560 in existing conditions 65 db CNEL impacts 12,194 housing units versus 9,794 in existing conditions 23

24 Findings ASSP Concept 6 Operational Requirement Meets PAL 30 requirements Dual independent IFR approaches in east flow only Community Disruption 5,512 housing units 21,119 residents Land Acquisition Land acquisition area of 1,967 acres Total site area of 2,628 acres Infrastructure Impacts Access to Point Loma and areas west of airport Noise Impacts 65 db CNEL impacts 31,068 people versus 19,560 in existing conditions 65 db CNEL impacts 10,615 housing units versus 9,794 in existing conditions 24

25 Future Technology The Next Generation Air Transportation System (NGATS) Initiatives The FAA s Joint Planning and Development Office (JPDO) Integrated Product Teams (IPT) The Agile Air Traffic System (AATS) IPT is developing the following capacity enhancement concepts: Super Density Operations Arrival/Arrival & Departure/Departure Equivalent Visual Operations Virtual Tower/Sense & Avoid 25

26 Technology Implications for Lindbergh Field Potential Application at SDIA Future potential reductions in separation criterion and improved traffic flows could: Allow for an increased peak arrivals, but it would require a decrease in departures. Conversely, as the number of departures increase, the number of arrivals will decrease. Fundamentally, technology cannot measurably increase the physical capacity of a single runway airfield. In the two-runway alternatives, new technology, when applied to dedicated arrival and departure runways, could increase throughput by approximately 10%. 26

27 Summary Comparison 2001 Master Plan - Concept F Evaluation Factor Existing Base Concept 12,000' Rwy 12,000' Rwy & New Technology ASSP Concept 6 Planning Parameters Target Activity Level (PAL 30) Payload/Range Capability ADG V Capability ADG VI Capability Aeronautical Airfield Requirements Land Area Requirements Approach Capability Wind Coverage Airspace Design Expansion Environmental Noise Community Disruption Land Acquisition Market Accessibility & Demand Military Impact Financial Affordability Legend Meets Requirement / Acceptable / Feasible Partially Meets Requirement / Somewhat Acceptable / Feasible with Issues Does Not Meet Requirement / Not Acceptable / Not Feasible 27

Airport Development Plan Update

Airport Development Plan Update Airport Development Plan Update Prepared by: SAN DIEGO COUNTY REGIONAL AIRPORT AUTHORITY SDIA Planning Timeline 2 Where Is SDIA Today? The Airport is implementing the recommendations from the 2008 master

More information

Phoenix Sky Harbor People Mover. ❸ Financial Considerations

Phoenix Sky Harbor People Mover. ❸ Financial Considerations Phoenix Sky Harbor People Mover ❸ Financial Considerations Phoenix Sky Harbor People Mover ❸ Financial Considerations Key Elements: A people mover that accesses the terminals and parking structures at

More information

Airport Master Plan Update June 14, 2017

Airport Master Plan Update June 14, 2017 Airport Master Plan Update June 14, 2017 www.harveyfield.com The Master Plan is a 20-year plan to understand the needs of current and future users of the Airport. This is important to ensure that safe

More information

NextGen Implementation Plan An Update

NextGen Implementation Plan An Update NextGen Implementation Plan An Update Presented to: Illuminating Engineering Society Aviation Lighting Committee Government Contacts Subcommittee By: Pamela Whitley, Acting Director for NextGen Integration

More information

JPDO Systems Modeling and Analysis

JPDO Systems Modeling and Analysis JPDO Systems Modeling and Analysis Dr. George Hunter Presented on behalf of Yuri Gawdiak JPDO Systems Modeling and Analysis Division (SMAD) September 5, 2007 JPDO Organizational Changes Yuri Gawdiak has

More information

FINAL ENVIRONMENTAL IMPACT REPORT. CHAPTER ONE: EXECUTIVE SUMMARY with RESPONSES TO COMMENTS

FINAL ENVIRONMENTAL IMPACT REPORT. CHAPTER ONE: EXECUTIVE SUMMARY with RESPONSES TO COMMENTS FINAL ENVIRONMENTAL IMPACT REPORT SDCRAA # EIR-06-01 State Clearinghouse No. 2005091105 CHAPTER ONE: EXECUTIVE SUMMARY with RESPONSES TO COMMENTS Lead Agency: SAN DIEGO COUNTY REGIONAL AIRPORT AUTHORITY

More information

Executive Summary. January 2015

Executive Summary. January 2015 Executive Summary January 2015 NAS Patuxent River Joint Land Use Study Naval Air Station Patuxent River JLUS Overview The Naval Air Station (NAS) Patuxent River (PAX) Joint Land Use Study (JLUS) was conducted

More information

Runway Protection Zones: Incompatible Land Use Alternatives Analysis & Risk Assessment

Runway Protection Zones: Incompatible Land Use Alternatives Analysis & Risk Assessment March 3rd, 2015 Runway Protection Zones: Incompatible Land Use Alternatives Analysis & Risk Assessment Matt Lee Vice President Landrum & Brown Cincinnati, OH Cody Meyer Consultant Landrum & Brown Cincinnati,

More information

Port Everglades Master/Vision Plan Update Stakeholder Meeting. January 28, 2010

Port Everglades Master/Vision Plan Update Stakeholder Meeting. January 28, 2010 Port Everglades Master/Vision Plan Update Stakeholder Meeting January 28, 2010 1 2 Agenda Updated Market Assessments determine. Master Plan Facility/Infrastructure Needs requiring. Berth Expansion into.

More information

Collaborative Decision Making (CDM), Air Traffic Flow Management (ATFM), and Surface CDM

Collaborative Decision Making (CDM), Air Traffic Flow Management (ATFM), and Surface CDM Collaborative Decision Making (CDM), Air Traffic Flow Management (ATFM), and Surface CDM Presented to: A-CDM Conference, Lima, Peru By: Bob Varcadipane, Manager, Airport Surface Efficiency Group, AJR-E,

More information

EXECUTIVE SUMMARY ES.1 BACKGROUND ES.2 PURPOSE AND NEED FOR THE PROPOSED PROJECT

EXECUTIVE SUMMARY ES.1 BACKGROUND ES.2 PURPOSE AND NEED FOR THE PROPOSED PROJECT EXECUTIVE SUMMARY ES.1 BACKGROUND The purpose of this Draft Environmental Report (DEIR) is the implementation of improvement projects at Charles M. Schulz Sonoma County Airport (the Airport). The improvement

More information

Pangborn Memorial Airport I One Pangborn Drive I East Wenatchee, WA 98802

Pangborn Memorial Airport I One Pangborn Drive I East Wenatchee, WA 98802 TO: Planning Advisory Committee (PAC) Members RE: Pangborn Airport Master Plan PAC Kickoff Meeting #1 DATE: August 22, 2016 On behalf of the Pangborn Memorial Airport, I would like to invite you to serve

More information

NextGen ATM Concept of Operations: ASAS-Reliant

NextGen ATM Concept of Operations: ASAS-Reliant NextGen ATM Concept of Operations: ASAS-Reliant See http://www.jpdo.gov for the latest JPDO info Doug Arbuckle, Rose Ashford NextGen Joint Planning & Development Office 18-Sep-2007 Joint 5th ASAS TN2 Workshop

More information

VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK

VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE 6604 - RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK UNIT 1 RAILWAY PLANNING 1. Define Permanent way. 2. List out the elements

More information

Noise Compatibility Program Update

Noise Compatibility Program Update Table of Contents 1.0 Introduction Pg. 1 2.0 Purpose and Need Pg. 1 3.0 Airport Environs Pg. 1 4.0 Land Use Compatibility Pg. 1 5.0 Study Methodology Pg. 2 6.0 2008 Existing Baseline Pg. 2 Noise Exposure

More information

3.9 Land Use and Agriculture

3.9 Land Use and Agriculture 3.9 Land Use and Agriculture 3.9.1 Land Use Regional Setting Sonoma County has a total area of approximately 1,768 square miles and is the most northerly of the nine counties in the San Francisco Bay Region.

More information

Updates on FAA Order F. Agenda. Communicate FAA Order Updates. Educate attendees on the changes to FAA Order

Updates on FAA Order F. Agenda. Communicate FAA Order Updates. Educate attendees on the changes to FAA Order Updates on FAA Order 1050.1F Rhonda Solomon March 3, 2015 Airports Conference 2015 Agenda Communicate FAA Order 1050.1 Updates Educate attendees on the changes to FAA Order 1050.1 1 1 Overview of NEPA

More information

Subject matter and scope

Subject matter and scope PCP Active APT AOP05 REG ASP MIL APO USE INT IND NM Subject matter and scope Implement Airport CDM (A-CDM) to enhance the operational efficiency of airports and improve their integration into the Air Traffic

More information

Chapter 5.0 Alternatives Analysis

Chapter 5.0 Alternatives Analysis Chapter 5.0 Alternatives Analysis The Master Plan process thus far has accumulated the baseline of existing airport data, presented the outlook for the future in terms of operational activity, and defined

More information

1. Introduction Noise Analysis Results Figures. List of Tables

1. Introduction Noise Analysis Results Figures. List of Tables Traffic Noise Technical Report FM 2218 Widening (From US 59 to SH 36) Fort Bend County Prepared by: Houston District Date: July 2017 CSJ: 2093-01-010 The environmental review, consultation, and other actions

More information

The existing land use surrounding North Perry Airport can be described as follows:

The existing land use surrounding North Perry Airport can be described as follows: 7.1 INTRODUCTION This land use evaluation will accomplish the following: Identify existing and future land uses in the Airport environs; Document existing land use, future land use, and zoning around the

More information

CMPA Campus Wide Solar Array Installation 2 of 4

CMPA Campus Wide Solar Array Installation 2 of 4 Reference 27 This Campus Master Plan Amendment was adopted by the Board of Regents Facilities and Land Management Committee at the June 2013 Board of Regents meeting and placed on the consent agenda for

More information

Potential Benefits of Operations

Potential Benefits of Operations Destination Green ICAO Symposium on Aviation and Climate Change, Destination Green, 14 16 May 2013 Potential Benefits of Operations John-Paul B. Clarke Associate Professor Daniel Guggenheim School of Aerospace

More information

BNA Master Plan Update

BNA Master Plan Update BNA Master Plan Update Community Advisory Committee Meeting No. 6 January 31, 2013 Introductions MNAA Staff RW Armstrong Team Albersman & Armstrong, Ltd. Atkins North America, Inc. Gresham, Smith and Partners

More information

6.0 TERMINAL REQUIREMENTS AND ALTERNATIVES

6.0 TERMINAL REQUIREMENTS AND ALTERNATIVES 6.0 TERMINAL REQUIREMENTS AND ALTERNATIVES The projected activity levels at Sacramento International Airport as described in Chapter 3 are the basis for determining the terminal facilities that will be

More information

Boston Overflight Noise Study. Phase 1 PROJECT CONSULTANT SCOPE OF SERVICES

Boston Overflight Noise Study. Phase 1 PROJECT CONSULTANT SCOPE OF SERVICES Phase 1 PROJECT CONSULTANT SCOPE OF SERVICES March 8, 2004 Project Consultant Phase 1 Scope of Services 3/8/2004 TABLE OF CONTENTS INTRODUCTION... 2 1 STUDY DESIGN... 3 2 PROJECT MANAGEMENT... 4 2.1 Project

More information

Dallas/Fort Worth International Airport ASCE Presentation. Terminal Development Program. November, 2009

Dallas/Fort Worth International Airport ASCE Presentation. Terminal Development Program. November, 2009 Dallas/Fort Worth International Airport ASCE Presentation Terminal Development Program November, 2009 ASCE PRESENTATION, NOVEMBER 2009 Background Objective The objective of today s presentation 1. Review

More information

Appendix H Support Facilities Preliminary and Intermediate Alternatives Analysis

Appendix H Support Facilities Preliminary and Intermediate Alternatives Analysis Appendix H SUPPORT FACILITIES PRELIMINARY AND INTERMEDIATE ALTERNATIVES ANALYSIS H TABLE OF CONTENTS EXHIBITS TABLES H.1 Evaluation Criteria... 1 H.1.1 Meeting the Base Constrained Demand Level... 1 H.1.2

More information

CHAPTER 4 IDENTIFICATION AND EVALUATION OF ALTERNATIVES

CHAPTER 4 IDENTIFICATION AND EVALUATION OF ALTERNATIVES CHAPTER 4 IDENTIFICATION AND EVALUATION OF ALTERNATIVES Chapter 4, Identification and Evaluation of Alternatives presents the various alternatives considered to address the facility requirements presented

More information

Visual Guidance. Research and Development. By: Holly Cyrus, Project Manager Date: August 23, Federal Aviation Administration

Visual Guidance. Research and Development. By: Holly Cyrus, Project Manager Date: August 23, Federal Aviation Administration Visual Guidance Research and Development By: Holly Cyrus, Project Manager Date: August 23, 2010 Signs Markings Lighting Ground Surveillance Mission Improve Visual Aids on Airports to reduce runway Incursions

More information

Rail Service at Brookley Aeroplex

Rail Service at Brookley Aeroplex WHAT The Mobile Airport Authority, hopes to attain improved rail infrastructure to advance economic performance and job growth. I. Background The Mobile Airport Authority s goal for Brookley Aeroplex is

More information

Parking Control System for Automated Gate Management

Parking Control System for Automated Gate Management Leading you safely to the gate Parking Control System for Automated Gate Management Honeywell Airports Business Increases in passenger traffic require higher gate efficiency and optimized throughput -

More information

Coordinated Arrival Departure Management

Coordinated Arrival Departure Management Coordinated Arrival Departure Management Dietmar Böhme, Ralph Brucherseifer, Lothar Christoffels German Aerospace Center (DLR) Institute of Flight Guidance Content Motivation & Objectives AMAN-DMAN Coordination:

More information

CHAPTER 14. ROADWAYS AND MARINE TRANSPORTATION

CHAPTER 14. ROADWAYS AND MARINE TRANSPORTATION CHAPTER 14. ROADWAYS AND MARINE TRANSPORTATION 14.1 AFFECTED ENVIRONMENT 14.1.1 Definition of Resource This section describes the existing transportation facilities, specifically roads, the Tinian International,

More information

DEVELOPMENT OF A MASTER PLAN FOR

DEVELOPMENT OF A MASTER PLAN FOR DEVELOPMENT OF A MASTER PLAN FOR AIRPORTS WITH VISSIM SUPPORT VISSIM USER S GROUP MEETING May 1 st 2009 Portland, Or Luis E. Maumejean Multiservicios Integrales de America S.A. de C.V. lmn@mia.com.mx OUR

More information

Airport Master Plan Update (AMPU) Phase 2. Scope of Work

Airport Master Plan Update (AMPU) Phase 2. Scope of Work BST AMPU Phase 2 Scope of Work Page 1 of 19 Belfast Municipal Airport Belfast, Maine Airport Master Plan Update (AMPU) Phase 2 Scope of Work The intent of this project is to update the 1999 Belfast Municipal

More information

California State Auditor

California State Auditor California State Auditor B U R E A U O F S T A T E A U D I T S San Diego International Airport at Lindbergh Field: Local Government, Including the San Diego Unified Port District, Can Improve Efforts to

More information

Master Plan Study Public Workshop #3. June 1-2, 2016

Master Plan Study Public Workshop #3. June 1-2, 2016 Master Plan Study Public Workshop #3 June 1-2, 2016 Agenda Master Plan Status Alternatives Process Development Screening Vision2040 Next Steps Alternatives (Boards) Master Plan Study Progress COMPLETED

More information

City of North Royalton Ohio Turnpike 3 rd Lane Expansion Investigation Study

City of North Royalton Ohio Turnpike 3 rd Lane Expansion Investigation Study City of North Royalton Ohio Turnpike 3 rd Lane Expansion Investigation Study Followup Neighborhood Meeting November 10, 2005 1 Agenda Study Objectives and Methodology Evaluation of Flooding Problems Relationship

More information

Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements

Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements JUNE 2016 RONALD REAGAN WASHINGTON NATIONAL AIRPORT Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements PREPARED BY: Ricondo & Associates, Inc. IN

More information

Mitigation Monitoring and Reporting Program for Final Environmental Impact Report No. 617 John Wayne Airport Settlement Agreement Amendment

Mitigation Monitoring and Reporting Program for Final Environmental Impact Report No. 617 John Wayne Airport Settlement Agreement Amendment Mitigation Monitoring and Reporting Program for Final Environmental Impact Report No. 617 John Wayne Airport Settlement Agreement Amendment SCH No. 2001111135 COUNTY OF ORANGE John Wayne Airport 3160 Airway

More information

An Analysis Mechanism for Automation in Terminal Area

An Analysis Mechanism for Automation in Terminal Area NASA/CR-2001-211235 ICASE Report No. 2001-32 An Analysis Mechanism for Automation in Terminal Area Stavan M. Parikh University of Virginia, Charlottesville, Virginia ICASE NASA Langley Research Center

More information

DSNA Services. Implementation Y 158 FL 1 PIGOS 8 MIKRU R 138 TA M PIRAM 18FL14 RAPED DIVUL 098 FL 5 FL5 MERLU FL 60 4 LERMA.

DSNA Services. Implementation Y 158 FL 1 PIGOS 8 MIKRU R 138 TA M PIRAM 18FL14 RAPED DIVUL 098 FL 5 FL5 MERLU FL 60 4 LERMA. G 97 6 00 10 149 00 122 30 PETUR USANO 4 37 35 1 FL Y 158 5 FL 14 8 MIKRU PIGOS R 138 5 5 6 0 TA Y 1 23315 M 111.4 53 0 R 50 XAMAL Consultancy PIRAM 114 services with operational expertise 3 1 512 FL 1

More information

What s New in Airport Curbside Management?

What s New in Airport Curbside Management? PRESENTATION What s New in Airport Curbside Management? Prepared for ACI-NA Operations and Technical Affairs Conference April 6, 2011 Agenda Outline Commercial Vehicles Current technologies Emerging technologies

More information

Environmental Assessment May 2007

Environmental Assessment May 2007 jurisdictional waters. It is assumed that, at a minimum, a USACE Section 404 Nationwide Permit would be necessary to construct these features. The impacts of the fill into the floodplain cannot be fully

More information

ARP SOP No SOP for CATEX Determinations Effective Date: Oct. 01, Federal Aviation Administration

ARP SOP No SOP for CATEX Determinations Effective Date: Oct. 01, Federal Aviation Administration ARP SOP No. 5.00 SOP for CATEX Determinations Effective Date: Oct. 01, 2014 February 2016 Important Points to Note: FAA recently established Standard Operating Procedures (SOP) for CatEx Determinations

More information

Planned Procurement Opportunities Report. May 2017

Planned Procurement Opportunities Report. May 2017 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

Time-Based Arrival Management for Dual Threshold Operation and Continuous Descent Approaches

Time-Based Arrival Management for Dual Threshold Operation and Continuous Descent Approaches Time-Based Arrival Management for Dual Threshold Operation and Continuous Descent Approaches Hartmut Helmke, Ronny Hann, Maria Uebbing-Rumke: German Aerospace Center (DLR) Institute of Flight Guidance

More information

Concept Symposium 2016 Governing the Front End of Major Projects

Concept Symposium 2016 Governing the Front End of Major Projects Concept Symposium 2016 Governing the Front End of Major Projects The governance of mega airport construction projects in China Dr. Guangshe Jia Professor Tongji University China We will introduce the governance

More information

Airport Asset Management

Airport Asset Management Airport Investment Assessment Page Airport Asset Management M2P PRODUCT OFFERING GmbH Bockenheimer Landstrasse 94-96 60323 Frankfurt am Main Germany Airport Asset Management M2P Product Offering First

More information

August 8, 2017 Community Engagement Panel Meeting #3 Alternatives Evaluation Process & Identification of Preferred Alternatives

August 8, 2017 Community Engagement Panel Meeting #3 Alternatives Evaluation Process & Identification of Preferred Alternatives Lake Elmo Airport Environmental Assessment (EA)/ Environmental Assessment (EAW) Worksheet August 8, 2017 Community Engagement Panel Meeting #3 Alternatives Evaluation Process & Identification of Preferred

More information

CEF Transport Info day 2016 Greece

CEF Transport Info day 2016 Greece Calls for proposal CEF-T 2016 CEF Transport Info day 2016 Greece Athens- 02 December 2016 Gaspare L'Episcopia- Innovation and Networks Executive Agency (INEA) Summary - - - - CEF Transport Priorities CEF

More information

BOCA RATON AIRPORT Airspace Obstruction Clearance Atlas

BOCA RATON AIRPORT Airspace Obstruction Clearance Atlas BOCA RATON AIRPORT Airspace Obstruction Clearance Atlas JULY 206 Introduction As the owner and operator of the Boca Raton Airport (BCT or the Airport), the Boca Raton Airport Authority (BRAA) is responsible

More information

Guidance for Modeling Noise for Non-Standard Aircraft Profiles

Guidance for Modeling Noise for Non-Standard Aircraft Profiles ACRP Problem Statement No. 14-02-34 Recommended Allocation: $300,000 Guidance for Modeling Noise for Non-Standard Aircraft Profiles ACRP Staff Comments: Several ACRP studies are focused on enhancing the

More information

A-CDM: Integrated working Stefan Beitelsmann, Head of Aviation and Central Infrastructure Management, Düsseldorf Airport

A-CDM: Integrated working Stefan Beitelsmann, Head of Aviation and Central Infrastructure Management, Düsseldorf Airport www.internationalairportreview.com Issue 1 2014 IAR proud to support: A-CDM: Integrated working Stefan Beitelsmann, Head of Aviation and Central Infrastructure Management, Düsseldorf Airport Winter operations

More information

2.0 DESCRIPTION OF PROPOSED ACTION AND ALTERNATIVES

2.0 DESCRIPTION OF PROPOSED ACTION AND ALTERNATIVES 2.0 DESCRIPTION OF PROPOSED ACTION AND ALTERNATIVES 2.0 DESCRIPTION OF PROPOSED ACTION AND ALTERNATIVES 2.1 PROPOSED ACTIONS, FORT GREELY, ALASKA The additional GMD VOC activities analyzed in this supplemental

More information

Wake Mitigation in the Terminal Area

Wake Mitigation in the Terminal Area Center for Advanced Aviation System Development Wake Mitigation in the Terminal Area Marshall Koch November 18, 2014 Approved for Public Release; Distribution Unlimited. Case Number 14-3930 2014 The MITRE

More information

American Society of Military Engineers

American Society of Military Engineers Presentation to American Society of Military Engineers Runway 9-27 Rehabilitation Project POHNPEI INTERNATIONAL AIRPORT, FSM Presented by Wadgy A. Guirguis, P.E. President August 14, 2012 PROJECT SCOPE

More information

2004 Initiative Land Use Policy Coordination

2004 Initiative Land Use Policy Coordination 2004 Initiative Land Use Policy Coordination 2004 Initiative Land Use Policy Coordination 2005 Initiative Airport Land Use Compatibility Objective 2005 Initiative Airport Land Use Compatibility Objective

More information

POLICY AND PROCEDURES MEMORANDUM - AIRPORTS DIVISION. General Processing of Modifications to Agency Airport Design and Construction Standards

POLICY AND PROCEDURES MEMORANDUM - AIRPORTS DIVISION. General Processing of Modifications to Agency Airport Design and Construction Standards U. S. Department of Transportation Federal Aviation Administration Great Lakes Region Illinois, Indiana, Michigan Minnesota, North Dakota, Ohio, South Dakota, Wisconsin 2300 East Devon Avenue Des Plaines,

More information

Air Traffic Management Capacity-Driven Operational Concept Through 2015

Air Traffic Management Capacity-Driven Operational Concept Through 2015 2 nd USA/EUROPE AIR TRAFFIC MANAGEMENT R&D SEMINAR Orlando,1 st - 4 th December 1998 Air Management Capacity-Driven Operational Concept Through 2015 Aslaug Haraldsdottir Robert W. Schwab Monica S. Alcabin

More information

Chapter 2 Performance Measures

Chapter 2 Performance Measures Transportation Decision-making Principles of Project Evaluation and Programming Chapter 2 Performance Measures K. C. Sinha and S. Labi Purdue University School of Civil Engineering 1 Performance Measures

More information

AIR INSTALLATION COMPATIBLE USE ZONE STUDY CALIFORNIA

AIR INSTALLATION COMPATIBLE USE ZONE STUDY CALIFORNIA AIR INSTALLATION COMPATIBLE USE ZONE STUDY TRAVIS AIR FORCE BASE, CALIFORNIA DECEMBER 2009 TABLE OF CONTENTS LIST OF APPENDICES... ii LIST OF FIGURES... iii LIST OF TABLES... iii LIST OF ACRONYMS... iv

More information

Athens International Airport

Athens International Airport Athens International Airport Developing Airport Business: the key role of pavements in airfield investments BCRRA 2017, International Conference in Athens Dimitrios J. DIMITRIOU Professor Asst, DUTh BoD

More information

Collaborative Decision Making (CDM) Update

Collaborative Decision Making (CDM) Update Collaborative Decision Making (CDM) Update 1 FAA CDM Office CDM Domestic combined with International Operations, includes International Data Sharing One Manager Two Full Time Team Leads, Two Part-Time

More information

DEPARTMENT OF TRANSPORTATION FEDERAL AVIATION ADMINISTRATION STANDARD PRACTICE FACILITY CONFIGURATION MANAGEMENT

DEPARTMENT OF TRANSPORTATION FEDERAL AVIATION ADMINISTRATION STANDARD PRACTICE FACILITY CONFIGURATION MANAGEMENT FAA-STD-058 November 8, 2002 DEPARTMENT OF TRANSPORTATION FEDERAL AVIATION ADMINISTRATION STANDARD PRACTICE FACILITY CONFIGURATION MANAGEMENT DISTRIBUTION STATEMENT A. Approved for public release; distribution

More information

Draft Environmental Assessment for Phoenix Sky Harbor International Airport Sky Train Stage 2

Draft Environmental Assessment for Phoenix Sky Harbor International Airport Sky Train Stage 2 Draft Environmental Assessment for Phoenix Sky Harbor International Airport Sky Train Stage 2 Prepared for: City of Phoenix Aviation Department and U.S. Department of Transportation Federal Aviation Administration

More information

SESAR development and deployment

SESAR development and deployment SESAR development and deployment Global Challenges to Improve Air Navigation Performance Asilomar Conference Grounds, Pacific Grove, CA 13 February 2015 Rolf TUCHHARDT European Commission, DG MOVE SESAR

More information

actions and approvals by the Federal Aviation Administration ( FAA) and the Federal

actions and approvals by the Federal Aviation Administration ( FAA) and the Federal METROPOLITAN AIRPORTS COMMISSION In re MSP 2020 Improvements Final Environmental Assessment/Environmental Assessment Worksheet, Adequacy Determination, and Negative Declaration on the Need for an Environmental

More information

Columbia Regional Airport (COU) Columbia, Missouri. Draft Environmental Assessment Airside, Landside, and Surface Transportation Developments

Columbia Regional Airport (COU) Columbia, Missouri. Draft Environmental Assessment Airside, Landside, and Surface Transportation Developments (COU) Columbia, Missouri Draft Environmental Assessment Airside, Landside, and Surface Transportation Developments RS&H No. 226-1077-000 Prepared for the: City of Columbia and U.S. Department of Transportation

More information

Airport Collaborative Decision Making Enhancing Airport Efficiency

Airport Collaborative Decision Making Enhancing Airport Efficiency Airport Collaborative Decision Making Enhancing Airport Efficiency David Gamper Director, Safety & Technical ACI World SWIFT Conference, Banff 18 September 2012 1 Airports are facing challenges Capacity

More information

Final Project Report. Abstract. Document information

Final Project Report. Abstract. Document information Final Project Report Document information Project Title QM-6 - ASAS Sequencing and Merging (TMA-8)) Project Number 05.06.06 Project Manager C-LVNL/ENAV Deliverable Name Final Project Report Deliverable

More information

FORGESOLAR GLARE ANALYSIS

FORGESOLAR GLARE ANALYSIS FORGESOLAR GLARE ANALYSIS Project: Delta County Airport (ESC) Escanaba Glare Assessment Site configuration: Delta Ariport Sim_35 Degree Analysis conducted by Brad Norling (Bradley.norling@westwoodps.com)

More information

Performance Based Approach for ASBUs Implementation

Performance Based Approach for ASBUs Implementation Performance Based Approach for ASBUs Implementation Air Navigation Bureau AN Implementation Section Cairo/23 26 November 2015 2000 2002 2003 2005 2007 2008 2009 2012 2013 PERFORMANCE BASED APPROACH AVIATION

More information

A Best Practice for the Implementation of a Pavement Management System For Small and Medium Airports

A Best Practice for the Implementation of a Pavement Management System For Small and Medium Airports A Best Practice for the Implementation of a Pavement Management System For Small and Medium Airports Architectural & Engineering Services Civil Engineering Directorate Airport Engineering ATR-045 Real

More information

M2P Airport Investment Assessment. Airport Asset Management M2P PRODUCT OFFERING

M2P Airport Investment Assessment. Airport Asset Management M2P PRODUCT OFFERING M2P Airport Investment Assessment Airport Asset Management M2P PRODUCT OFFERING 1 M2P Airport Asset Management 2/7 SUCCESSFULLY MANAGING AIRPORT ASSETS The aviation industry is faced with changing requirements

More information

Noise Tall Structures

Noise Tall Structures The objective of this inventory is to document all environmentally-sensitive areas governed by the National Environmental Policy Act (NEPA) of 1969 within the existing Airport property boundaries; however,

More information

Port Capacity Analysis in Long Beach. Matt Plezia, POLB and Vaibhav Govil, AECOM TRB Irvine, CA June 29, 2010

Port Capacity Analysis in Long Beach. Matt Plezia, POLB and Vaibhav Govil, AECOM TRB Irvine, CA June 29, 2010 Port Capacity Analysis in Long Beach Matt Plezia, POLB and Vaibhav Govil, AECOM TRB Irvine, CA June 29, 2010 1 About the Port of Long Beach 2 Second busiest container port in N. America 7 container terminals

More information

September 12, Dear Mr. Gallo:

September 12, Dear Mr. Gallo: HOPE HALLECK CLERK TO THE COUNTY BOARD September 12, 2016 Mr. Carmine Gallo Eastern Regional Administrator Federal Aviation Administration United States Department of Transportation 1 Aviation Plaza Jamaica,

More information

3.0 CUMULATIVE PROJECTS SCENARIO

3.0 CUMULATIVE PROJECTS SCENARIO 3.0 CUMULATIVE PROJECTS SCENARIO The CEQA Guidelines define cumulative impacts as two or more individual effects that, when considered together, are considerable or which compound or increase other environmental

More information

Click to edit Master title style. Port of Everett Data Overview

Click to edit Master title style. Port of Everett Data Overview Port of Everett Data Overview PSRC FAST Committee Lisa Lefeber December 13, 2017 1 About the Port of Everett The Port District and boundaries formed in 1918; serves nearly 100,000 people Not a countywide

More information

ICAT MIT. Increase Milestone Prediction Accuracy in. Potential Approaches to. NAS Movements. Georg Theis, Francis Carr, Professor JP Clarke

ICAT MIT. Increase Milestone Prediction Accuracy in. Potential Approaches to. NAS Movements. Georg Theis, Francis Carr, Professor JP Clarke M I T I n t e r n a t i o n a l C e n t e r f o r A i r T r a n s p o r t a t i o n M I T I n t e r n a t i o n a l C e n t e r f o r A i r T r a n s p o r t a t i o n Potential Approaches to Increase

More information

Preserving Indiana s Agricultural Heritage Activity

Preserving Indiana s Agricultural Heritage Activity Name: Activity The situation: You are a participant in a committee for the Industrial Widget Corporation, which is trying to find a suitable location to build a widget factory in this state. The committee

More information

5.D.1 HISTORIC, ARCHITECTURAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES

5.D.1 HISTORIC, ARCHITECTURAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES 5.D.1 HISTORIC, ARCHITECTURAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES Section 106 of the National Historic Preservation Act (NHPA) of 1966, as amended (16 U.S.C. Section 470(f)) protects properties that

More information

Caltrain Rapid Rail Plan

Caltrain Rapid Rail Plan TRANSPORTATION RESEARCH RECORD 1677 Paper No. 99-1328 31 Caltrain Rapid Rail Plan ANDREW BUTLER NASH The results of Caltrain s Rapid Rail Study are described. The purpose of the study was to develop a

More information

CONDITIONAL USE PERMITS (CUP):

CONDITIONAL USE PERMITS (CUP): April 2, 2001 Memo To: From: Re: Telecommunication Service Providers David Less, City Planner CITY REQUIREMENTS FOR TELECOM TOWERS AND ANTENNAS Effective March 2001, the City s new telecommunication ordinance

More information

PUBLIC DISCLOSURE AUTHORISED

PUBLIC DISCLOSURE AUTHORISED PUBLIC DISCLOSURE AUTHORISED CARIBBEAN DEVELOPMENT BANK EXECUTIVE SUMMARY WITH MANAGEMENT RESPONSE PROJECT COMPLETION VALIDATION REPORT EXPANSION OF THE GRANTLEY ADAMS INTERNATIONAL AIRPORT - BARBADOS

More information

Port Everglades. is South Florida s Powerhouse Port. Presented to American Association of Port Authorities Environment Committee. September 17, 2015

Port Everglades. is South Florida s Powerhouse Port. Presented to American Association of Port Authorities Environment Committee. September 17, 2015 Port Everglades is South Florida s Powerhouse Port Presented to American Association of Port Authorities Environment Committee Port Everglades Baseline Emissions Inventory EPA Partnership Emission Modeling

More information

GIS Mapping Tool to Sustain Military Mission Joint Services Environmental Management (JSEM) Conference - Session 3314 March 22, 2006

GIS Mapping Tool to Sustain Military Mission Joint Services Environmental Management (JSEM) Conference - Session 3314 March 22, 2006 GIS Mapping Tool to Sustain Military Mission Joint Services Environmental Management (JSEM) Conference - Session 3314 March 22, 2006 DeEllen Brasher Department of Defense Regional Environmental Coordinator

More information

Effects of Wind Turbines Wake Turbulence on General Aviation Aircraft and Airports

Effects of Wind Turbines Wake Turbulence on General Aviation Aircraft and Airports ACRP Problem Statement: 15-03-05 Effects of Wind Turbines Wake Turbulence on General Aviation Aircraft and Airports Recommended Funding Amount: $400,000 ACRP Staff Comments FAA has completed numerous studies

More information

Homeland Counter UAV Architecture Development

Homeland Counter UAV Architecture Development Homeland Counter UAV Architecture Development Francesca D Arcangelo 27 October 2015 Sponsor: David Masters, DHS Science and Technology Directorate, HSARPA Distribution Statement A. Approved for public

More information

Future Noise Contour

Future Noise Contour The area within each 5 db noise exposure contour is shown in Table 5-2, Area Exposed to Various Noise Levels 2008 Proposed Action. The 65 Day-Night Average Sound Levels (DNL) of the 2008 Proposed Action

More information

Airport Construction Project Risk Management. Presented by: Mindy Price- Direct Effect Solutions

Airport Construction Project Risk Management. Presented by: Mindy Price- Direct Effect Solutions Airport Construction Project Risk Management Presented by: Mindy Price- Direct Effect Solutions Topics ACRP 01-22 Research Background Research Findings and Conclusions Project Risk Management Recommendations

More information

Chapter 11. Climate & Greenhouse Gases

Chapter 11. Climate & Greenhouse Gases Chapter 11 Climate & Greenhouse Gases Table of Contents 11. Climate and Greenhouse Gases... 11-1 11.1 Introduction... 11-1 11.2 Scoping the Assessment... 11-1 11.2.1 Relevant Legislation and Guiding Documents...

More information

Chapter 4: Transportation and Land Use

Chapter 4: Transportation and Land Use Chapter 4: Transportation and Land Use Transportation and land use together make possible the wide range of destination opportunities in the region. Transportation provides the connections, and, in turn,

More information

New Passenger Terminal Zagreb International Airport October 2014

New Passenger Terminal Zagreb International Airport October 2014 New Passenger Terminal Zagreb International Airport October 2014 Contents: 1. Project Overview 2. Zagreb Airport Presentation 3. Work Progress & Site Photos 4. NPT Key Dates Project Overview 1 Introduction

More information

Currituck County Moyock Mega-Site Market Feasibility Study March 28, 2016

Currituck County Moyock Mega-Site Market Feasibility Study March 28, 2016 Currituck County Moyock Mega-Site Market Feasibility Study March 28, 2016 Presentation Outline Project Background Demographic and Economic Data Review Competitive Market Analysis Feasibility Assessment

More information

SESAR. M. STANDAR Chief Strategy & External Affairs. Forsknings-och innovationsdagen inom luftfartsområdet Stockholm, March 23 rd, 2017

SESAR. M. STANDAR Chief Strategy & External Affairs. Forsknings-och innovationsdagen inom luftfartsområdet Stockholm, March 23 rd, 2017 SESAR M. STANDAR Chief Strategy & External Affairs Forsknings-och innovationsdagen inom luftfartsområdet Stockholm, March 23 rd, 2017 SESAR Why? Who? How? What it means for Europe? GLOBAL MOBILITY CHALLENGES

More information

Transportation Research Board Airport Cooperative Research Program (TRB-ACRP) Project Number Enhancing Airport Land Use Compatibility

Transportation Research Board Airport Cooperative Research Program (TRB-ACRP) Project Number Enhancing Airport Land Use Compatibility This annotated bibliography contains over 300 entries which have relevance to airport land use compatibility. The references relate to a number of topics which include airport land use compatibility planning,

More information

The AIRPORT CDM. Bahrain October 2015

The AIRPORT CDM. Bahrain October 2015 The AIRPORT CDM Bahrain 11-13 October 2015 Airport CDM a definition Airport CDM is a proven concept which aims at improving predictability, reducing delays, optimally utilizing the available capacities

More information