SUPPLEMENTAL NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT. ACEforward Notice of Additional Project Element Niles Junction Connections
|
|
- Lesley Logan
- 5 years ago
- Views:
Transcription
1 SUPPLEMENTAL NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT DATE: May 9, 2016 FROM: TO: SUBJECT: San Joaquin Regional Rail Commission Agencies, Organizations, and Interested Parties ACEforward Notice of Additional Project Element Niles Junction Connections SUMMARY: This is a notice soliciting scoping input concerning an additional project element for the ACEforward Project/Program, which is currently in environmental review. The San Joaquin Regional Rail Commission (SJRRC) issued a Notice of Preparation (NOP) to advise agencies, organizations, and interested parties, that it is preparing an Environmental Impact Report (EIR) for the ACEforward Project/Program (proposed project/program) in June The original NOP is provided as an attachment to this notice. The EIR will analyze improving and expanding existing Altamont Corridor Express (ACE) rail service between Stockton and San Jose and extending new ACE rail service to Modesto and Merced (refer to Figure 1). SJRRC is the owner and operator of the ACE rail service, and will serve as the lead agency for the preparation of the EIR in compliance with the requirements of the California Environmental Quality Act (CEQA). SJRRC is issuing this Supplemental NOP to alert interested parties and solicit public and agency input regarding an additional element of the project that would establish new rail line connections at Niles Junction that would allow freight rail traffic to better utilize the Niles subdivision as a direct connection to the Port of Oakland. This Supplemental NOP is seeking comment on the scope and content of the EIR in regards to this additional element and to advise the public that outreach activities conducted by the SJRRC and its representatives will be considered in the preparation of the EIR. Originally, SJRRC and the Federal Railway Administration (FRA) were preparing a combined EIR/EIS with FRA as the federal lead agency for the preparation of the EIS in compliance with the National Environmental Policy Act (NEPA). At this time, no federal funds have been identified to fund the project elements. Thus, SJRRC and the FRA have decided that the appropriate NEPA document will be a Program EIS to be released following the completion of the CEQA process. DATES: Public scoping meetings will be held at the times and dates listed below. The Project/Program s purpose and need and the description of alternatives currently under consideration for the proposed project/program will be presented at these meetings along with the description of the additional project element between Fremont and Oakland. Scoping materials and information concerning the scoping Page 1
2 meetings will be made available through the SJRRC s website: Comments may be provided orally or in writing at the scoping meetings scheduled at the following dates and locations: Hayward/San Leandro Area Scoping Meeting Tuesday, May 24, :30 pm Ashland Community Center, th Ave, San Leandro, CA Fremont/ Union City Area Scoping Meeting Thursday, May 26, :30 pm Union City Council Chambers, City Hall Alvarado-Niles Rd, Union City, CA The meeting facilities will be accessible to persons with disabilities. If special translation or signing services or other special accommodations are needed, please contact Ms. Yanna Badet at (415) or yanna.badet@aecom.com at least 48 hours before the scoping meeting. COMMENTS: Written comments on the scope and content of the ACEforward EIR concerning the additional project element including the program s purpose and need, the alternatives to be considered, the impacts to be evaluated and the methodologies to be used in the evaluations should be provided to SJRRC by June 9, WRITTEN COMMENTS SHOULD BE SENT TO: Mr. Dan Leavitt, Manager of Regional Initiatives ATTN: ACEforward EIR SJRRC/ ACE Headquarters 949 East Channel Street Stockton, CA or via with the Subject line ACEforward EIR to: aceforward@acerail.com. FOR FURTHER INFORMATION CONTACT: Yanna Badet, ACEforward Community Engagement Lead AECOM, 300 California Street, Suite 400, San Francisco, CA Tel: Yanna.Badet@aecom.com SUPPLEMENTARY INFORMATION: SJRRC is preparing a combined Project/Program EIR to identify and understand impacts associated with improvements to the ACE rail services. Past Planning Efforts Past planning efforts are described further in the original NOP, which is available here: Purpose and Need of the Proposed Project/Program The purpose of the ACEforward Project/Program is to implement a series of projects to reduce travel time, increase service reliability and frequency, improve passenger facilities and extend the reach of the ACE rail system to downtown Modesto and Merced. The need for the ACEforward Project/Program is for enhanced intercity and commuter rail service in the northern San Joaquin Valley in the ACE corridor Page 2
3 connecting the southern Bay Area with the Tri-Valley and the San Joaquin Valley. This need stems from the social and economic ties and travel demand that bind together the Northern San Joaquin Valley, the Tri-Valley and the Southern Bay Area, as well as the high levels of existing traffic and future anticipated growth, travel demand, and congestion that will cause environmental degradation and higher safety risks if not addressed. This need cannot be met by the existing ACE service or infrastructure which has significant operating limitations: including limited-capacity single track for much of the route, slow average operating speeds, service limitations and lack of existing service to Modesto and Merced. The purpose and need are described further in the original NOP. ACEforward Proposed Project/Program ACEforward overall is a phased improvement program to increase frequency, improve service reliability, improve safety, and reduce travel times along the existing Stockton to San Jose corridor and to extend ACE rail service to Modesto and to Merced. This program would provide the foundation for the long-term vision of SJRRC to provide both commuter and intercity passenger rail services. The program overall would improve the existing ACE service managed by SJRRC by delivering safety and operational improvements that enable expansion of service to Modesto and up to 6 daily round trips between the San Joaquin Valley and San Jose, which could occur as early as Following that, the program would extend ACE service to Merced and service frequency from the San Joaquin Valley to San Jose would increase to as many as 10 or more daily round trips, perhaps as soon as The EIR for ACEforward will include both a project- and programmatic-level analysis as discussed below. Project-Level Analysis The EIR will assess the environmental effects of at least the following improvements at a project level of detail: Improvements necessary to increase service to Modesto and expand service between the San Joaquin Valley and San Jose up to 6 daily round trips by as early as 2019, including the following: o Upgrade of the track and structures along the former Southern Pacific line through Niles Canyon to accommodate freight traffic or addition of sidings at Hearst (north of Sunol), in Niles Canyon, and in Centerville (in Fremont west of Niles Junction). o New connections to the former Southern Pacific line at Niles Junction and at Hearst. o Upgrading of the Altamont siding in the Altamont Hills. o Potential shift in service to a new passenger route along Union Pacific Railroad (UPRR) through downtown Tracy: This improvement would allow for a downtown Tracy station with improved transit connections located close to urban infill/mixed-use development in Tracy. o Potential new station in West Tracy at several different locations, River Islands in Lathrop, downtown Tracy and downtown Manteca. o New connection between the Oakland subdivision and the Fresno subdivision in Lathrop/Manteca area. o Expansion of service to Modesto using existing UPRR track, new track built within the UPRR right of way or new track outside the UPRR right of way, or some combination thereof. o Parking improvements at various existing ACE stations. Changes since the NOP include the following: o The potential shift of service to an alignment connecting to River Islands and downtown Tracy were described as being analyzed at a program-level of detail in the original NOP are now being analyzed at a project-level of detail. o The West Tracy station options were not included in the prior NOP. Page 3
4 Programmatic Analysis The programmatic analysis will describe impacts at a conceptual level of detail focused on the selection of corridors for new service and general environmental impacts associated with that selection. The EIR will programmatically analyze the following: San Joaquin Valley to San Jose o Increase of service to up to 10 trains or more in the future including corridor improvements necessary to support such increases. This may include improvements of potential pinch points identified by the UPRR in the Altamont Hills, between Newark and Alviso, and between Santa Clara and San Jose. o Potential improved connection to Bay Area Rapid Transit (BART) service in the Tri-Valley area that would increase connectivity. o Potential connection to the Union City Intermodal Station. New extension to Merced o Expansion of service to Merced using existing UPRR track, new track built within the UPRR right of way or new track outside the UPRR right of way, or some combination thereof. o Up to 10 or more daily round-trip trains and new downtown stations in Turlock and Merced and potential stations in Ripon, Ceres, and Livingston/Atwater. Additional connections and stations would increase ridership and allow greater opportunities for alternatives to vehicle travel for San Joaquin Valley residents. Changes since the NOP include the following: o The potential shift of service to an alignment connecting to River Islands and downtown Tracy were described as being analyzed at a program-level of detail in the original NOP are now being analyzed at a project-level of detail. The programmatic analysis will also address all project elements included in the project-level analysis as described above. New Project Element: Niles Junction Connections There are three different existing rail lines between Oakland and Fremont; all owned by UPRR (see Figure 2). The Niles subdivision proceeds from the Port of Oakland toward Niles Junction in Fremont generally on the east side of the coastal plain. The Oakland subdivision splits from the Niles subdivision in southern Oakland and is located to the east of the Niles subdivision until Hayward at which point it transitions to the west of the Niles subdivision (at Industrial Road), then traverses through Union City and Fremont through the Quarry Lakes area and then turns eastward through Niles Junction and then eastward into Niles Canyon. The Coast subdivision departs from the Niles subdivision in southern Oakland and then runs south in the area west of I-880 to Newark where it meets the Centerville line. From Niles Junction, freight trains and ACE passenger service utilize the Oakland subdivision to travel through Niles Canyon. There is a second rail line through Niles Canyon called the Niles Canyon Railway, which is owned by Alameda County, but is not used for freight rail and is only used for a small excursion service at present. The Niles Canyon Railway would require track upgrades in order to be used for regular freight service (as well as permission from Alameda County). The Alameda County rail network has a connectivity issue whereby trains heading between the Central Valley and the Port of Oakland cannot make a direct connection from the Oakland Subdivision to the Niles subdivision at Niles Junction. This gap results in many freight trains being routed via the Coast Subdivision (see Figure 2). The most direct route to and from the Port of Oakland for freight using Niles Canyon is the Niles subdivision. A key objective of the ACEforward Project/Program is to increase passenger rail service from the San Joaquin Valley to San Jose. Since ACE operates on rail lines owned by UPRR, the capacity on the lines Page 4
5 is influenced by both freight and passenger rail traffic. In order to be able to obtain permission from UPRR to operate additional passenger trains from the San Joaquin Valley to San Jose, UPRR has identified that there must be sufficient capacity for both freight and passenger trains. In order to manage freight operations to and from the Port of Oakland, UPRR has identified that a better connection from Niles Canyon to the Niles subdivision is necessary. This project element will include two different alternatives, both of which would allow a more direct connection from the Port of Oakland to Niles Canyon (and vice-versa) via the Niles subdivision. The connection alternatives are depicted in Figure 3. The first alternative would include a bridge over Alameda Creek west of Mission Boulevard that would connect the Oakland subdivision to the Niles subdivision. The second alternative would include a connection of the Niles Canyon Railway north of Alameda Creek to the Niles subdivision which would also allow for a direct connection. According to the recently (2016) released Alameda County Goods Movement Study prepared by the Alameda County Transportation Commission (ACTC), rail traffic on the Niles subdivision is expected to be 26 daily trains by 2020 (including freight and Capitol Corridor). Rail traffic on the Coast subdivision for 2020 is expected to be 18 daily trains (including freight and the Amtrak Coast Starlight). The Oakland subdivision from Fremont to Oakland only has limited freight service at present, no passenger rail service and is not expected to have substantial rail increases in the future (except that one of the ACE alternatives is to extend ACE service to the Union City Intermodal Station). A direct connection from the Niles subdivision to either the Oakland subdivision or the Niles Canyon Railway at Niles Junction would allow freight traffic to be routed on both the Niles and the Coast subdivision optimally. The changes in freight traffic on the Niles subdivision versus the Coast subdivision will be identified in the EIR. For trains that would have previously used the Coast subdivision that would use the Niles subdivision, the distance would be shortened by approximately 10 miles. Capitol Corridor presently uses the Niles subdivision from Oakland to Niles Junction and then turns westward to Newark on the Centerville line and then the Coast subdivision south to Santa Clara. The proposed new connection at Niles Junction included in this project would not change the routing for the Capitol Corridor. Choices about routing for the Capitol Corridor are under the control of the Capitol Corridor Joint Powers Authority (CCJPA) as well as UPRR, since UPRR owns all of the railroad lines between Oakland and Fremont. Changes in Capitol Corridor service or routing are not part of the proposed project/program. Apart from the bridge over Alameda Creek or the connection to the Niles Canyon Railway, no other physical improvements at or north of Niles Junction are included in the proposed project/program. Potential Environmental Effects Based on review of the project/program area and in consideration of the proposed project/program activities, SJRRC has determined that the proposed project/program overall may result in potential significant impacts related to the following: aesthetics; agricultural resources; air quality, biological resources; cultural and paleontological resources; geology, soils and seismicity; greenhouse gas emissions and climate change; hydrology and water quality; land use; noise and vibration; population and housing; public services and utilities; and transportation and traffic. Potential construction period effects of construction of a connection between the Oakland subdivision and the Niles subdivision (or the Niles subdivision and the Niles Canyon Railway) could include disturbance to biological or cultural resources and temporary air quality, noise, water quality, and traffic effects or other construction-period disruption. Operationally, the shift of some freight trains from the Coastal subdivision to the Niles subdivision would result in shifting localized noise, air quality and traffic impacts from the areas along the Coastal subdivision (and along the Centerville line) to areas along the Niles subdivision. The reduction of train miles travelled would reduce regional criteria air pollutants and greenhouse gas emissions as well as fuel consumption. All potential environmental effects will be analyzed in the EIR. Page 5
6 The EIR Process and the Role of Participating Agencies and the Public The purpose of the EIR process is to explore in a public setting the potentially significant effects of the proposed project on the environment. The SJRRC will assess the site characteristics, size, nature, and timing of the improvements to determine whether the impacts are potentially significant and whether impacts can be avoided or mitigated. The EIR will identify and evaluate reasonable and feasible sitespecific alignment alternatives, evaluate the impacts from construction, operation, and maintenance and identify mitigation measures. Information and documents regarding the ACEforward environmental review process will be made available through the ACE website: Scoping and Comments SJRRC encourages broad participation in the EIR process during scoping and review of the resulting environmental document. Comments and suggestions are invited from all interested agencies and the public at large to insure the full range of issues related to the proposed project/program and all reasonable alternatives are addressed and that all significant issues are identified. In particular, SJRRC is interested in learning whether there are areas of environmental concern where there might be a potential for significant impacts. Public agencies with jurisdiction are requested to advise SJRRC of the applicable permit and environmental review requirements of each agency, and the scope and content of the environmental information that is germane to the agency s statutory responsibilities in connection with the proposed program. Public agencies are requested to advise SJRRC if they anticipate taking a major action in connection with the proposed program and if they wish to cooperate in the preparation of the EIR. Public scoping meetings have been scheduled as an important component of the scoping process for both the state and federal environmental review. The scoping meetings described in this NOP will be advertised locally and additional public notice will be provided separately with the dates, times, and locations of these scoping meetings. Page 6
7 Figure 1: Project Location Map Page 7
8 Page 8
9 Page 9
Executive Summary. ES.1 Project Background
This executive summary presents the key findings of this environmental impact report (EIR) for the San Joaquin Regional Rail Commission s (SJRRC) ACEforward plan. SJRRC proposes to expand service and connections
More informationRail Strategy Study. ACTAC October 9, 2017
5.1 Rail Strategy Study ACTAC October 9, 2017 Agenda Overview 1. Overview of rail system issues and growth scenarios 2. Capacity and operations analysis and improvement options 3. Grade crossing improvements
More informationThis section summarizes federal, state, regional, and local regulations related to energy resources and energy use and applicable to ACEforward.
4.6 4.6.1 Introduction This section describes the regulatory and environmental setting for energy resources and energy use in the vicinity of ACEforward s near-term and longer-term improvements. It also
More informationCentral Valley Rail Working Group 1. INTRODUCTIONS
CVRWG Meeting: February 24, 2017 Central Valley Rail Working Group 1. INTRODUCTIONS Central Valley Rail Working Group 2. SJJPA Update Dan Leavitt, SJJPA CVRWG Meeting: February 24, 2017 Morning Express
More informationRevised Scoping Report
Revised Scoping Report For the ACEforward Program/Project EIR/EIS February 2014 Prepared for the: San Joaquin Regional Rail Commission and Prepared by: ICF International, Inc. 620 Folsom Street, Suite
More information1.1 Overview. 1.2 Project History. Chapter 1 Introduction
Chapter 1 1.1 Overview The an Joaquin Regional Rail Commission (JRRC) is the designated owner, operator, and policymaking body for the Altamont Corridor Express (ACE) service which presently focuses on
More informationStockton Freight & Passenger Rail Mobility Enhancement
Stockton Freight & Passenger Rail Mobility Enhancement 2017 $10.34 million in 2017 FASTLANE Grant funding to complete engineering design, permitting, and construction of the Stockton Track Extension and
More informationCHAPTER 2.0: INTRODUCTION
CHAPTER 2.0: INTRODUCTION 2.1 INTRODUCTION The Federal Transit Administration (FTA) and the Santa Clara Valley Transportation Authority (VTA) have prepared this Environmental Impact Statement/Environmental
More informationTier 2 Environmental Impact Statement for the High-Speed Rail Project from Granite
This document is scheduled to be published in the Federal Register on 02/18/2014 and available online at http://federalregister.gov/a/2014-03324, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION
More informationNotice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report
Notice of Preparation For Link Union Station (Link US) Project Joint Environmental Impact Statement and Environmental Impact Report Date: May 27, 2016 To: Subject: Project Title: From: All Interested Agencies,
More informationCHAPTER 2 INTRODUCTION
CHAPTER 2 INTRODUCTION 2.1 INTRODUCTION The Santa Clara Valley Transportation Authority (VTA) has prepared this Second Supplemental Environmental Impact Report (SEIR-2) in accordance with the California
More informationEnvironmental Impact Statement for the California High-Speed Rail System Burbank to Los Angeles Section, CA
This document is scheduled to be published in the Federal Register on 07/24/2014 and available online at http://federalregister.gov/a/2014-17384, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION
More informationCapitol Corridor Vision Implementation Plan Vision for the Megaregion. CCJPA November 2017
Capitol Corridor Vision Implementation Plan Vision for the Megaregion CCJPA November 2017 1990 s: Prop 116/108 SR3T Ph 1 2006 Electrified, very frequent passenger rail service plateau Europe Asia 3 CCJPA
More information1.1 Overview. 1.2 Project History. Chapter 1 Introduction
. Overview Chapter The an Joaquin Regional Rail Commission (JRRC) is the designated owner, operator, and policymaking body for the Altamont Corridor Express (ACE) service that presently focuses on connecting
More informationTier 1 Environmental Impact Statement for the Chicago, Illinois, to Detroit-Pontiac,
This document is scheduled to be published in the Federal Register on 08/31/2012 and available online at http://federalregister.gov/a/2012-21587, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION
More informationOakland to San Jose Phase 2A Planning Studies, Environmental Documentation, and Final Design RFSOQ Pre-Submittal Meeting
Oakland to San Jose Phase 2A Planning Studies, Environmental Documentation, and Final Design RFSOQ Pre-Submittal Meeting October 16, 2018 Capitol Corridor Joint Powers Authority (CCJPA) Agenda RFSOQ Overview
More informationEnvironmental Impact Statement for the Green Line to the Airport Project. ACTION: Notice of Intent to Prepare an Environmental Impact Statement (EIS).
This document is scheduled to be published in the Federal Register on 11/18/2015 and available online at http://federalregister.gov/a/2015-29418, and on FDsys.gov DEPARTMENT OF TRANSPORTATION Federal Transit
More informationadvertising opportunities
advertising opportunities With over 1.3 million passengers annually and growing, the Altamont Corridor Express (ACE) provides a unique audience and affordable opportunities to advertise your business,
More informationINCREASING CAPACITY ON THE SAN JOAQUIN CORRIDOR A PUBLIC-PRIVATE PARTNERSHIP
INCREASING CAPACITY ON THE SAN JOAQUIN CORRIDOR A PUBLIC-PRIVATE PARTNERSHIP Presented By Ken Galt, Caltrans Division of Rail John Fleming, Burlington Northern Santa Fe Railway William Brewster, Hanson-Wilson
More informationEnvironmental Impact Statement; Lone Star Regional Rail Project Williamson, Travis, Bastrop, Hays, Caldwell, Comal, Guadalupe, and Bexar Counties, TX
This document is scheduled to be published in the Federal Register on 10/06/2014 and available online at http://federalregister.gov/a/2014-23711, and on FDsys.gov [4910-22] DEPARTMENT OF TRANSPORTATION
More information4.18 Utilities and Service Systems
4.18 4.18.1 Introduction This section describes the regulatory and environmental setting for utilities and service systems in the vicinity of ACEforward s near-term and longer-term improvements. It also
More informationNOTICE OF PREPARATION
City of Ceres City of Hughson City of Modesto City of Newman City of Oakdale City of Patterson City of Riverbank City of Turlock City of Waterford County of Stanislaus Date: January 4, 2013 NOTICE OF PREPARATION
More informationWest Santa Ana Branch Transit Corridor. Draft EIS/EIR Scoping Interagency Meeting June 19, 2017
West Santa Ana Branch Transit Corridor Draft EIS/EIR Scoping Interagency Meeting June 19, 2017 Agenda > Welcome and Introductions > Purpose of Interagency Scoping > Timeline and Process > Agency Coordination
More information2018 advertising opportunities
2018 advertising opportunities With over 1.3 million passengers annually and growing, the Altamont Corridor Express (ACE) train provides a unique audience with affordable opportunities to advertise your
More informationIntent to Prepare a Supplemental Draft Environmental Impact Statement for the Capitol
Federal Register DEPARTMENT OF TRANSPORTATION Federal Transit Administration Intent to Prepare a Supplemental Draft Environmental Impact Statement for the Capitol Expressway Light Rail Project in the City
More informationWelcome! Overview Agenda: 6:00 pm 6:30 pm: Welcome & Sign-In. 6:30 pm 7:00 pm: Link US Presentation. 7:00 pm 8:00 pm: Open House
Welcome! Overview Agenda: 6:00 pm 6:30 pm: Welcome & Sign-In 6:30 pm 7:00 pm: Link US Presentation 7:00 pm 8:00 pm: Open House 1 Link Union Station (Link US) (formerly SCRIP) Scoping Meeting & Open House
More informationGoods Movement COLLABORATIVE AND PLAN. Arthur L. Dao, Alameda CTC Executive Director ALAMEDA COUNTY TRANSPORTATION COMMISSION. September 17, 2015
ALAMEDA COUNTY TRANSPORTATION COMMISSION Goods Movement COLLABORATIVE AND PLAN A presentation to the California Marine Affairs and Navigation Conference Arthur L. Dao, Alameda CTC Executive Director 1
More information7.1 Cumulative Impacts under NEPA and CEQA
Chapter 7 This chapter includes the following discussions required by the National Environmental Policy Act (NEPA) and California Environmental Quality Act (CEQA). Cumulative Impacts under NEPA and CEQA
More informationLONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17
LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17 1 PROJECT TEAM & COLLABORATORS 2 OPEN HOUSE SERIES Tuesday, May 16, 2017 6-8:00 pm La Verne City Council Chambers 3660 D Street La
More informationNOTICE OF PREPARATION OF A MASTER ENVIRONMENTAL IMPACT REPORT AND SCOPING MEETING FOR THE 2040 GENERAL PLAN UPDATE AND CLIMATE ACTION PLAN
NOTICE OF PREPARATION OF A MASTER ENVIRONMENTAL IMPACT REPORT AND SCOPING MEETING FOR THE 2040 GENERAL PLAN UPDATE AND CLIMATE ACTION PLAN PUBLIC COMMENT PERIOD January 28, 2019 to February 28, 2019 Scoping
More informationSupplemental Environmental Impact Statement/Environmental Impact Report (SEIS/EIR)
Supplemental Environmental Impact Statement/Environmental Impact Report (SEIS/EIR) The Project Transformative! Project Milestones 2004 Transbay Terminal/Caltrain Downtown Extension/Redevelopment Project
More informationNOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT
Date: September 19, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal Utility District 6201 S Street, MS B203 Sacramento,
More informationAPPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED
APPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED Date: September 19, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal
More informationRegional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report
Los Angeles County Metropolitan Transportation Authority Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report Public Scoping Meeting 1 Agenda!
More informationEnvironmental Impact Statement for the Southeast High Speed Rail Project from
This document is scheduled to be published in the Federal Register on 10/23/2014 and available online at http://federalregister.gov/a/2014-25219, and on FDsys.gov DEPARTMENT OF TRANSPORTATION Federal Railroad
More informationWest Santa Ana Branch Transit Corridor. Draft EIS/EIR Scoping Meeting June 2017
West Santa Ana Branch Transit Corridor Draft EIS/EIR Scoping Meeting June 2017 Agenda > Welcome and Introductions > Purpose of Scoping > Timeline and Process > Environmental Approach and Methodology >
More informationSouth Bay Metro Green Line Extension
Meeting Agenda Project overview and update Recap of the Scoping Meetings Progress on the project alternative and proposed station locations Meeting Schedule 6:00 Open House 6:30 Presentation 7:15 Public
More informationDatabase and Travel Demand Model
Database and Travel Demand Model 7 The CMP legislation requires every CMA, in consultation with the regional transportation planning agency (the Metropolitan Transportation Commission (MTC) in the Bay
More informationCalifornia High-Speed Train Program FEIR/EIS
Page 2-30 Page 2-31 Page 2-32 Page 2-33 Page 2-34 Page 2-35 Page 2-36 of Enrique Manzanilla, Director U.S. Environmental Protection Agency, August 31, 2004 (Letter AF008) AF008-1 Acknowledged. AF008-2
More informationChapter 5. Congestion Management Program. Chapter 5
Chapter 5 Congestion Management Program Chapter 5 67 Chapter 5 Congestion Management Program Enacted in the early 1990s, California s Congestion Management Program (CMP) statutes encourage local jurisdictions
More informationDraft Environmental Impact Report
Revised Draft Environmental Impact Report San Francisquito Creek Flood Protection, Ecosystem Restoration, and Recreation Project Upstream of Highway 101 This notice announces that a Draft Environmental
More informationTECHNICAL MEMORANDUM
TECHNICAL MEMORANDUM Concept Level Operational Feasibility Study TM 4.1 Prepared by: Signed document on file Paul Mosier _21 July 08 _ Date Checked by: Signed document on file 21 July 08 Ken Jong, PE Date
More informationLong Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need
Environmental Impact Statement (EIS) Revised Purpose and Need June 23, 2017 1.0 What is the Proposed Action? The consists of potential improvements to the Long Bridge and related railroad infrastructure
More informationCHAPTER 1 INTRODUCTION REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY
CHAPTER 1 INTRODUCTION REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY CHAPTER 1 INTRODUCTION CREATING A SUSTAINABLE COMMUNITIES STRATEGY FOR THE SAN JOAQUIN REGION This chapter describes
More informationFrequently Asked Questions (FAQs) For Communications Based Overlay Signal System (CBOSS) Positive Train Control (PTC)
(FAQs) For Communications Based Overlay Signal System (CBOSS) Positive Train Control (PTC) 1. What is CBOSS PTC? CBOSS PTC stands for Communications Based Overlay Signal System (CBOSS) Positive Train Control
More informationProject Overview. A Collaborative Effort
Project Overview A Collaborative Effort DRPT and FRA are working closely with CSX, which owns and operates the corridor, as well as with passenger operators Amtrak and Virginia Railway Express (VRE), the
More informationDevelopment and Engineering Services Parties. 333 Civic Center Plaza Tracy, CA State Clearinghouse
Notice of Preparation (NOP) Date: November 30, 2011 To: Responsible and Trustee From: Agencies and Other Interested Development and Engineering Services Parties 333 Civic Center Plaza Tracy, CA 95376 State
More informationDRAFT ENVIRONMENTAL IMPACT STATEMENT FOR HOUSTON DALLAS HIGH SPEED RAIL (TEXAS CENTRAL)
DRAFT ENVIRONMENTAL IMPACT STATEMENT FOR HOUSTON DALLAS HIGH SPEED RAIL (TEXAS CENTRAL) Background On June 25, 2014, the Federal Railroad Administration (FRA) issued a Notice of Intent to Prepare an Environmental
More informationNotice of Preparation of a Draft Environmental Impact Report Vallco Special Area Specific Plan
COMMUNITY DEVELOPMENT DEPARTMENT CITY HALL 10300 TORRE AVENUE CUPERTINO, CA 95014-3255 (408) 777-3308 FAX (408) 777-3333 of a Draft Environmental Impact Report File Number EA-2017-05 February 9, 2018 To:
More informationPROJECT DESCRIPTION...
TABLE OF CONTENTS Volume I Chapter Page 1. INTRODUCTION... 1-1 1.1 Introduction... 1-1 1.2 Project Description... 1-1 1.3 Purpose of the EIR... 1-2 1.4 EIR Process... 1-3 1.5 Scope of the Draft EIR...
More information1. Evaluation of route and service alternatives; 2. Tier 1 Environmental Impact Analysis; and 3. Service Development Plan.
Rail Rail plays a significant role in transportation planning, especially when considering economic development, safety, freight, and intermodal connectivity. Jackson has two rail lines serving the area,
More informationPeninsula Corridor Electrification Project. Draft Environmental Impact Report
Peninsula Corridor Electrification Project Draft Environmental Impact Report Public Meeting Purpose of Tonight s Meeting Provide an overview of Draft Environmental Impact Report (Draft EIR) Receive comments,
More informationTHIS PAGE INTENTIONALLY LEFT BLANK.
THIS PAGE INTENTIONALLY LEFT BLANK. DRAFT ENVIRONMENTAL IMPACT STATEMENT/ENVIRONMENTAL IMPACT REPORT LEAD AGENCIES: Federal Transit Administration, U.S. Department of Transportation and Los Angeles County
More informationGULF COAST RAIL DISTRICT VISION FOR REGIONAL RAIL
GULF COAST RAIL DISTRICT VISION FOR REGIONAL RAIL OCTOBER 2014 Cover photographs courtesy of Top left - Mike Bates TABLE OF CONTENTS MISSION... 1 INTRODUCTION... 1 VISION STATEMENT... 1 BACKGROUND... 2
More informationES.0 EXECUTIVE SUMMARY. ES.1 Los Angeles to San Diego via the Inland Empire Section HST Project Background
ES.0 EXECUTIVE SUMMARY The California High Speed Rail Authority (the Authority) and the Federal Railroad Administration (FRA) are studying alternative alignments and stations for a high-speed train (HST)
More informationPurpose and Organization PROGRAM ENVIRONMENTAL IMPACT REPORT. Native American Consultation Workshop
PROGRAM ENVIRONMENTAL IMPACT REPORT Native American Consultation Workshop A Presentation by the Southern California Association of Governments October, 2015 Purpose and Organization Introduction Draft
More informationCaltrain Rapid Rail Plan
TRANSPORTATION RESEARCH RECORD 1677 Paper No. 99-1328 31 Caltrain Rapid Rail Plan ANDREW BUTLER NASH The results of Caltrain s Rapid Rail Study are described. The purpose of the study was to develop a
More informationWHILE LOCAL COMMUNITIES MAY NOT BE ABLE TO DIRECTLY INFLUENCE THE EQUIPMENT USED ON NEARBY RAIL CORRIDORS, LOCAL COMMUNITIES
WHILE LOCAL COMMUNITIES MAY NOT BE ABLE TO DIRECTLY INFLUENCE THE EQUIPMENT USED ON NEARBY RAIL CORRIDORS, LOCAL COMMUNITIES CAN TAKE STEPS TO REDUCE THE EXPOSURE OF LOCAL RESIDENTS TO LOCOMOTIVE EXHAUST.
More informationNOTICE OF PREPARATION AND NOTICE OF A PUBLIC SCOPING WORKSHOP FOR AN ENVIRONMENTAL IMPACT REPORT
NOTICE OF PREPARATION AND NOTICE OF A PUBLIC SCOPING WORKSHOP FOR AN ENVIRONMENTAL IMPACT REPORT Monday, January 7 th, 2013 at 6:00 PM PST Oakland International Airport In-Transit Lounge, Terminal 1, 2
More informationIntent to Prepare an Environmental Impact Statement for the South Bay Metro
DEPARTMENT OF TRANSPORTATION Federal Transit Administration Intent to Prepare an Environmental Impact Statement for the South Bay Metro Green Line Extension Transit Corridor, Southwestern Portion of Los
More information3.14 Public Services Physical Setting. Methodology
3.14 Public Services This section of the Draft Environmental Impact Statement/Report (EIS/R) describes the existing public services within the Eden Landing Phase 2 area of the South Bay Salt Pond (SBSP)
More informationLong Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need
Environmental Impact Statement (EIS) Revised Purpose and Need November 9, 2017 1.0 What is the Proposed Action? The consists of potential improvements to the Long Bridge and related railroad infrastructure
More informationSERVICE DEVELOPMENT PLAN - CAPITOL CORRIDOR:
SERVICE DEVELOPMENT PLAN for FRA Grant Applications 2010 SERVICE DEVELOPMENT PLAN - CAPITOL CORRIDOR: Oakland to San Jose and Sacramento to Auburn Capitol Corridor Joint Powers Authority August 5, 2010
More informationRail Freight and Passenger
Take Care of the System Critical Investments in the areas of: Rail Freight rehabilitate rail bridges o Rail Bridge Inventory Database... $0.5 - $1.0 million (one time) Rail Freight rail replacement and
More informationSubject: Notice of Preparation of a Draft Environmental Impact Report
NOTICE OF PREPARATION From: Santa Clara Valley Water District 5750 Almaden Expressway San Jose, CA 95118 Subject: Notice of Preparation of a Draft Environmental Impact Report Project Title: Guadalupe Dam
More information3.6 GROUND TRANSPORTATION
3.6.1 Environmental Setting 3.6.1.1 Area of Influence The area of influence for ground transportation consists of the streets and intersections that could be affected by automobile or truck traffic to
More informationExecutive Summary... v
Table of Contents Executive Summary... v Chapter 1: Introduction/Purpose and Need. 1 Section 1.1 Introduction and Background.. 1 1.1.1 Evaluation of Previously Approved Changes to the Project.. 1 1.1.2
More informationSubject: Notice of Preparation of a Draft Environmental Impact Report
NOTICE OF PREPARATION From: Santa Clara Valley Water District 5750 Almaden Expressway San Jose, CA 95118 Subject: Notice of Preparation of a Draft Environmental Impact Report Project Title: Calero Dam
More informationTexas A&M Transportation Short Course
Texas A&M Transportation Short Course Joseph Black Rail Director October 16, 2013 What are the Challenges? Public Safety Issues with trains of up to 2 miles in length running through the urban cores of
More information[FWS R8 R 2016 N061; FXRS282108E8PD0 167 F ] South Bay Salt Pond Restoration Project, Phase 2 at the Eden Landing Ecological
This document is scheduled to be published in the Federal Register on 06/20/2016 and available online at http://federalregister.gov/a/2016-14565, and on FDsys.gov Billing Code: 4333 15 DEPARTMENT OF THE
More informationCity and County of San Francisco San Francisco Planning Department. Summary Presentation on
City and County of San Francisco San Francisco Planning Department Summary Presentation on Draft Program Environmental Impact Report for the San Francisco Public Utilities Commission s Water System Improvement
More informationI-580 Interregional Multi-Modal Corridor Study
Final Report for: I-580 Interregional Multi-Modal Corridor Study IMAGE FROM GOOGLE EARTH PRO Submitted by: Dowling Associates, Inc. Transportation Engineering Planning Research Education 428 J Street,
More informationPOSITION ANNOUNCEMENT CUSTOMER RELATIONS SUPERVISOR $25 - $35 PER HOUR ($52,000 - $72,800 ANNUALLY)
POSITION ANNOUNCEMENT CUSTOMER RELATIONS SUPERVISOR Agency Background Information The San Joaquin Regional Rail Commission manages the Altamont Corridor Express (ACE) passenger rail service in Northern
More informationPreparation of an Environmental Impact Statement for High Capacity Transit
This document is scheduled to be published in the Federal Register on 11/19/2013 and available online at http://federalregister.gov/a/2013-27583, and on FDsys.gov DEPARTMENT OF TRANSPORTATION Federal Transit
More informationRichard Clarke Executive Director Program Management. Capital Program Management
Richard Clarke Executive Director Program Management Capital Program Management Department Overview > Transit, Highway Programs, and Regional Rail o Transit Deliver construction projects on-time and within
More informationCommunity Development Department Telephone: (650)
Community Development Department Telephone: (650) 780-7234 Planning & Housing Services Facsimile: (650) 780-0128 1017 Middlefield Road TDD: (650) 780-0129 P.O. Box 391 Redwood City, CA 94064 Website: www.redwoodcity.org
More informationPreapplication for HSIPR Program OMB No
U.S. Department of Transportation Federal Railroad Administration Preapplication for HSIPR Program OMB No. 2130 0583 Preapplication instructions: For each question, enter the appropriate information in
More informationNotice of Preparation
Notice of Preparation Date April 23, 2015 To: Subject: Project: Lead Agency: California Office of Planning and Research, Responsible and Trustee Agencies and Interested Parties Notice of Preparation of
More informationAutomated Ticket Validation for the Capitol Corridor Trains
APTA 2010 Fare Collection Workshop San Diego, California March 30, 2010 Automated Ticket Validation for the Capitol Corridor Trains Presented by: John Wright Project Services Manager, CCJPA What is Capitol
More informationAppendix C Presentation Slides with Script
Appendix C Presentation Slides with Script 32 Grand Crossing Rail Project 10 S. Riverside Plaza, Suite 400 Chicago, IL 60606 www.grandcrossingrail.com info@grandcrossingrail.com [title slide no narration]
More informationEnvironmental Impact Statement for the Baltimore-Washington Superconducting Maglev (SCMAGLEV) Project, between Baltimore, Maryland and Washington, DC
This document is scheduled to be published in the Federal Register on 11/25/2016 and available online at https://federalregister.gov/d/2016-28285, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION
More informationSECTION 5: ALTERNATIVES TO THE PROPOSED PROJECT
City of American Canyon Broadway District Specific Plan Alternatives to the Proposed Project SECTION 5: ALTERNATIVES TO THE PROPOSED PROJECT 5.1 Introduction In accordance with CEQA Guidelines Section
More informationSandpoint Junction Connector
Sandpoint Junction Connector BNSF Railway MAY 23, 2018 BNSF is a Leading Railroad A Berkshire Hathaway, Inc. company 32,500 route miles in 28 states and 3 Canadian provinces 42,000 employees Approximately
More informationMichael Gillam Deputy Program Director - Southern California
International Right of Way Association Los Angeles Chapter: C A L I F O R N I A H I G H - S P E E D R A I L Michael Gillam Deputy Program Director - Southern California January 25, 2011 A Statewide System
More informationRegional Transportation Studies Management Committee
Pima Association of Governments 1 E. Broadway, Tucson, Arizona Santa Rita Conference Room Regional Transportation Studies Management Committee March 8, 2017 North-South Corridor Study (Pinal County) Staff
More informationRail Division 2012 Annual Summary
Rail Division 2012 Annual Summary Overview The Rail Division oversees rail planning and inspection, highway rail crossings, management of stateowned lines (such as the South Orient Rail line (SORR) and
More informationCHAPTER 2 DESIGN REFINEMENTS
CHAPTER 2 DESIGN REFINEMENTS 2.1 INTRODUCTION Since publication of the Draft 2 nd Supplemental Environmental Impact Report (SEIR-2), additional design refinements have been identified. Some of these refinements
More information3.12 NOISE Regulatory Setting Environmental Setting EXISTING NOISE SOURCES AND SENSITIVE LAND USES
3.12 NOISE This section assesses the potential for implementation of the West Village Expansion component to result in impacts related to short-term construction, long-term operational noise sources, and
More informationSection IMPLEMENTATION PLAN. 7. Implementation Plan
Section 7 IMPLEMENTATION PLAN 7. Implementation Plan 7.0 Implementation Plan The Tier 1 Final EIS has presented several improvements along the Chicago to St. Louis corridor to meet the purpose and need
More informationNORTHERN CALIFORNIA PROGRAM UPDATE
NORTHERN CALIFORNIA PROGRAM UPDATE Boris Lipkin, Northern California Regional Director Local Policy Maker Group Thursday, September 27, 2018 AGENDA 2018 Sustainability Report San Francisco to San Jose
More informationCHAPTER 13.0: BIBLIOGRAPHY
CHAPTER 13.0: BIBLIOGRAPHY Alameda, County of, 2000 Alameda County Measure B, April Alameda, County of, East County Area Plan: A Portion of the Alameda County General Plan, May 2002. Alameda County Water
More informationDavid Brockbank, Senior Planner Contra Costa County Department of Conservation and Development 30 Muir Road Martinez, CA, 94553
WRITTEN COMMENTS: Interested agencies and the public may also submit written comments to the County. Please submit your comments at the earliest possible date, but no later than 5 p.m. on Friday, November
More informationENGINEERING AND INFORMATION TECHNOLOGY COMMITTEE MEETING SUMMARY MINUTES Wednesday, August 8, :15 p.m.
ENGINEERING AND INFORMATION TECHNOLOGY COMMITTEE MEETING SUMMARY MINUTES Wednesday, August 8, 2018 4:15 p.m. ATTENDANCE Director: John Weed (Chair), Aziz Akbari ftdr2_. Staff: Ed Stevenson, Toni Lyons,
More informationMemorandum. FROM: Jim Ortbal Rosalynn Hughey Barry Ng TO: HONORABLE MAYOR, CITY COUNCIL. DATE: June 16, 2017
CITY OF SANjOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR, CITY COUNCIL SUBJECT: TRANSPORTATION POLICY UPDATE REQUIRED BY STATE LAW - LOS TO VMT Memorandum FROM: Jim Ortbal Rosalynn Hughey Barry Ng
More informationSoutheastern Minnesota Freight Rail Capacity Study
P U R P O S E A N D N E E D S T A T E M E N T Southeastern Minnesota Freight Rail Capacity Study Feasibility and Alternatives Analysis Study Prepared for: Prepared by: July 2012 Kimley-Horn and Associates,
More informationCaltrain Business Plan
Caltrain Business Plan O CTO BER 2018 November 15, 2018 Bicycle Advisory Committee How Should Caltrain Grow? Business Plan Overview Business Plan Overview A Vision for Growth Crafting the Vision Next Steps
More informationCaltrain Business Plan
Caltrain Business Plan OCTOBER 2018 Quarterly Update PCJPB How Should Caltrain Grow? Business Plan Overview Business Plan Overview A Vision for Growth Crafting the Vision Next Steps What is the Caltrain
More informationSECTION 6.0 Alternatives to the Proposed Project
SECTION 6.0 Alternatives to the Proposed Project 6.0 ALTERNATIVES TO THE PROPOSED PROJECT CEQA requires that an EIR include an analysis of a range of project alternatives that could feasibly attain most
More informationRegional Goods Movement Planning in the Bay Area
M E T R O P O L I T A N T R A N S P O R T A T I O N C O M M I S S I O N Regional Goods Movement Planning in the Bay Area Matt Maloney, Principal September 17, 2015 Metropolitan Transportation Commission
More information