1 Rail Division 2012 Annual Summary Overview The Rail Division oversees rail planning and inspection, highway rail crossings, management of stateowned lines (such as the South Orient Rail line (SORR) and Bonham Subdivision), management of statesupported operations (such as the Heartland Flyer passenger service) and rail safety. With over 10,000 total rail miles and over 9,000 public highway rail crossings, the Rail Division continues to fully support TxDOT s strategic goals of maintaining a safe rail system, addressing congestion, connecting Texas communities and becoming a Best in Class state agency. With the rail industry continuing to rebound in 2012, the Rail Division was positioned to respond to the corresponding needs of the State and its rail network and supported its local and regional public partners, as well as its private partners, in achieving numerous successes. All around the State, interest in establishing new passenger rail service and progress in enhancing existing passenger rail services has continued. Freight traffic volumes for most commodity types also continue to increase. Freight railroads continue to invest in rail network capacity improvements and often collaborate with local and regional public partners on projects that have public impacts. Maintaining a Safe System The Rail Division received approval for the Texas Highway Rail Grade Crossing Safety Action Plan from the Federal Railroad Administration (FRA) on November 25, This plan, required by law, identifies specific solutions for improving safety at crossings with an added emphasis for high risk crossings that have experienced multiple accidents. The plan includes a comprehensive five year implementation schedule that focuses on education, enforcement, evaluation, and engineering. Under the Section 130 Program, the Rail Highway Section obligated $27 million in 2012 to install active warning devices at 138 crossings throughout the State. Over the past decade there has been a general downward trend for rail related injuries and fatalities in Texas despite the substantial growth in population, registered vehicles, miles traveled, and rail traffic. FRA Approved Action Plan TxDOT rail safety Investigators are on call 24 hours a day, 7 days aweek, and 365 days a year to respond to rail emergencies including crossing accidents, derailments, and hazardous material releases. The Rail Safety Section, in coordination with Texas Operation Lifesaver, provides an average of 16 to 20 rail safety presentations annually at schools, employers, and communities throughout the State.

2 2 Addressing Congestion FRA, TxDOT, Union Pacific Railroad (UP), BNSF Railway (BNSF), and the City of Fort Worth are investing $101.3 million for rail and roadway improvements at the Tower 55 interlocking in downtown Fort Worth to increase freight rail capacity, reduce train delays, reduce vehicular delays at rail roadway crossings, improve bridges and underpasses, improve air quality and enhance pedestrian safety at one of the most congested rail intersections in the United States. The Rail Division was previously successful in obtaining FRA Aerial View of Tower 55 Interlocking funding through a TIGER II grant application that demonstrated the numerous benefits the proposed improvements provide and the successful development of a public private partnership with all of the stakeholders. The project received environmental clearance and TxDOT, UP, and BNSF executed the project agreement in June Final design plans are currently being completed and construction is anticipated to begin in early Estimated duration for construction is 24 months. The Belt Junction project was identified in TxDOT s Houston Freight Study in Currently an east west BNSF track crosses a north south UP track at grade east of the Hardy Toll Road in Houston. Both lines are double tracked before and after the crossing but are reduced to a single track at the crossing. The project will install 3,900 feet of double track through the West Belt Junction, including four power operated turnouts, realigning quadrant connections and reconstructing the manual interlocking signal system. Working with the Gulf Coast Rail District (GCRD), TxDOT and GCRD secured $6.9 million in Congestion Mitigation and Air Quality (CMAQ) improvement funds with the additional funds provided by UP and BNSF. Working collaboratively with GCRD, BNSF and UP, the Rail Division assisted in obtaining environmental clearance for the Belt Junction project in July Construction is expected to begin in Belt Junction Project Limits Phase II of the El Paso Freight Rail Study was also initiated in 2012 through the Rail Division s Short Term Rail Program Management (STRPM) contract. This phase of the study will focus on evaluating the impacts of increased freight rail traffic within the El Paso District on the public, as well as the existing rail network, and identifying key rail projects that will assist in reducing congestion effects caused by the increased freight rail traffic.

3 3 Also as part of the STRPM contract, the Rail Division will be evaluating and prioritizing the list of over 500 identified rail related projects in the most recent version of the Texas Rail Plan. The prioritization process will first gather additional rail related projects from areas that had not yet been studied by the Rail Division and begin a general screening process that evaluates basic qualitative and quantitative parameters of each project in order to narrow the list of projects to be evaluated more closely. The next step in the prioritization process will utilize the methodology previously established by the Texas A&M Transportation Institute (TTI), reviewed by the Statewide Rail Steering Committee, and accepted by the Rail Division. Project scoring will be provided on this reduced list of projects with the 25 top scoring projects being identified for detailed cost benefit analysis (CBA). The CBA results will support the Rail Division in prioritizing these top projects for local, state or federal financial support opportunities. Connecting Texas Communities The Rail Division successfully managed the third phase of the SORR rehabilitation which was completed in September 2012, resulting in increased train speeds up to 25 mph, improved operations, and an expanded customer base for the West Texas region. The improvements consisted of replacing two bridges, repairing 39 bridges, replacing 13,083 linear feet of rail and 2,792 rail ties, repairing 42 switches, upgrading eight signals, and adding 3,056 tons of ballast. Additional details of the completed improvements are available online at TxDOT s website. For the year ending 2011, the SORR achieved its first ever positive SORR Open Deck Tie Replacement on BR operating income and net profits, since the line was first leased to Texas Pacifico (TXPF), the line operator. Freight traffic continues to increase largely due to the increase in oil and gas exploration in the region. TXPF has also expanded their operation staff due to the increase freight demand, operating 24 hours a day, 7 days a week. Statewide ridership on each of the three Amtrak routes operating within Texas continues to increase. Amtrak s Heartland Flyer route experienced a record level of ridership (78,920 boardings and alightings) in The Rail Division applied for and received $3.47 million in American Recovery and Reinvestment Act (ARRA) funding to be used for signal timing adjustments and improvements at 15 crossings over 63 miles on the BNSF s Fort Worth Subdivision on which the Heartland Flyer operates. This project will reduce travel time on the Texas portion of Amtrak s Heartland Flyer route by approximately 15 minutes by increasing travel speeds from 49 mph to 79 mph. The Rail Division secured the FRA grant cooperative agreement (GCA) in FRA, BNSF and the Rail Division are finalizing details of plans, estimates and improvements which are scheduled for completion near the end of In May 2011, FRA awarded $15 million in High Speed and Intercity Passenger Rail Program (HSIPR) funds to TxDOT to complete preliminary engineering and project level environmental studies for a new highspeed core express service between Houston and Dallas Fort Worth. The Rail Division is currently negotiating with an engineering consultant and developing a detailed work plan. Development of highspeed rail services within this corridor will reduce congestion, improve air quality, and provide an alternate mode of intercity transportation.

4 4 The Rail Division executed an engineering contract in September 2012, to perform a study of passenger rail in a corridor extending from Oklahoma City to South Texas, connecting the metropolitan areas of Dallas/Fort Worth, Austin and San Antonio. The Texas Oklahoma Passenger Rail Study is partially funded by a $5.6 million HSIPR grant from the FRA. The study will investigate different types of service, from improved Amtrak service to true high speed rail service. The study will result in a prioritized business plan for implementing the services identified through the public involvement and service level environmental studies. A state wide ridership analysis program is also currently underway where a ridership forecasting model will be developed to evaluate different levels of passenger rail service between various city pairs. The different levels of service include core express ( 125mph), regional (90 Potential Routes DFW to HOU to 125mph), and emerging ( 90mph). The results from this program will help in determining the types of service to be further developed in the State, provide the basis for more detailed ridership studies, benchmark the start for preparing Service Development Plans (SDPs) and support applications for federal funding to further developed the statewide plans. The Rail Division has also completed its revision to Chapter 4 Passenger Rail of the Texas Rail Plan (TRP). Annual revision of this part of the TRP is required by Texas Transportation Code The updated sections are currently posted online. Texas Rail Plan Revised Nov 2012 The Rail Division continues to coordinate with the Lone Star Rail District (LSRD) on their efforts to complete the alternative alignment analysis on the freight rail bypass between Austin and San Antonio and to advance selected alignments into the federally required NEPA process expected to be underway in This work also includes the required environmental assessment and clearance work necessary to establish passenger rail service along the existing freight rail corridor. Best in Class Agency The Rail Division logs some of the highest mileage usage among divisions of its size. Rail Safety Investigators drive a total average of 20,000 miles every month in state vehicles for investigatory and inspection purposes. The Rail Division maintained an injury free and accident free workplace for FY For the past two years the FRA has rated Texas as having the top State Rail Safety Participation Program of all the 38 participating states. One example that typifies the quality and effectiveness of the Rail Division was in San Marcos. Rail Division inspectors identified significant potential public safety hazards at a highway rail at grade crossing, as well as a separate pedestrian at grade crossing, located between

5 5 the newly constructed stadium at Texas State University (TSU) and its west parking lot. The Rail Division assembled the various local officials and stakeholders to collectively meet with Union Pacific to discuss the public safety issues associated with the crossings and the large number of pedestrians during stadium events. The proactive collaboration between all parties resulted in the development of a communications plan among TxDOT, UP, TSU officials and an agreement to minimize rail operations through this area during TSU football games and to notify the railroad of other special events held at the stadium complex. The Rail Division secured the FRA GCA for both of the federally funded passenger rail studies within the State the Texas Oklahoma City Passenger Rail Study and the Dallas Fort Worth to Houston Preliminary Engineering and NEPA Project. The Rail Division was also able to solicit and award numerous consultant contracts, including both passenger rail studies, as well as the Statewide Ridership Analysis and Short Term Rail Program Management projects. All contracts have been procured with activities underway, except for the DFW to Houston project. Throughout 2012, the Rail Division continued to supplement State funding for its program by pursuing federal funding opportunities. Applications for funding through the 2012 TIGER Discretionary Program for three separate projects were not selected. However, an application for funding through the High Speed Rail Corridor Program was successful. This funding, combined with a previous 1103(c) grant, will be used to improve the signal and safety systems at two at grade crossings along Amtrak s Texas Eagle route in Round Rock, which is part of the federally designated South Central High Speed Rail corridor. Outlook The Rail Division with continue to proactively work with various stakeholders around the State through the Statewide Rail Steering Committee and the Passenger Rail Steering Committee. The primary purpose of both committees is to engage stakeholders throughout the State and leverage their expertise. Collaboration with both groups will continue to promote transparency of the activities of the Rail Division s on going projects and to allow constructive feedback to be considered in improving their end products. The Rail Division has also initiated a Peer Review committee comprised of four national industry experts that will provide insight and assistance to the efforts in advancing development of highspeed rail service within the State. The FRA GCA for the Trinity Railway Express Valley View Double Track project is expected to be executed. The Statewide Ridership Modeling program and the construction of the BNSF Signal Timing project will be completed near the end of With the anticipated improvements in trip time performance for Amtrak s Heartland Flyer, ridership is expected to continue to increase which, in turn, may reduce the required annual subsidy provided by the State to Amtrak. The State s subsidy to Amtrak for the Heartland Flyer service in 2012 was $2,100,000. A focus on all passenger rail projects will continue during Both of the grant funded projects, the Dallas Fort Worth to Houston and Oklahoma City to South Texas, are expected to be fully underway. On March 1, 2012, TxDOT and Amtrak in coordination with the East Texas Corridor Council began a passenger rail feasibility study for new Amtrak service between Dallas Fort Worth and the Bossier City Shreveport, Louisiana, area along the I 20 corridor. The study will analyze potential schedules, train

6 6 operating costs, revenue and ridership, railcar and locomotive requirements, and capital needs for route infrastructure improvements. The feasibility study is expected to be completed in November Collaboration with the freight railroads and their efforts in improving their rail network while minimizing impacts to various modes of public transportation will also continue. Construction of the Tower 55 project is expected to begin in 2013 and continue for approximately two years. The Rail Division will oversee the project for compliance with its agreement with the FRA, as well as each of the railroads. The Belt Junction project construction, with 50% funding from the railroads, will also begin in 2013, pending execution of agreement with GCRD. The Rail Division will remain proactive with TXPF with planned improvements along the South Orient Railroad. TXPF predicts that traffic along the SORR will double in 2013 due to the expansion and development of oil, gas, and energy facilities in West Texas. Existing businesses, such as Hirschfeld Energy Corporation, and new businesses, such as EOG Resources, Enertrade and West Texas Transloading, locating along the rail line are anticipated to support rail traffic growth and provide positive economic impact to the area. The increased traffic is expected to produce a second straight year with an operating profit for this line. The El Paso Phase II Freight Study will also be completed in The results are expected to assist the District and Rail Division in evaluating the impacts of increased rail traffic on the region, and to identify key investments that will assist in mitigating those impacts. These investments will be added to a statewide list of improvement projects to be prioritized within As always, safety remains paramount in all of our efforts. Section 130 funding will continue to be effectively utilized in improving conditions at at grade crossings around the State, with a high priority to those identified in the implementation schedule within the Texas Highway Rail Grade Crossing Safety Action Plan. The Rail Division commits to continuing efforts to educate, evaluate, enforce, and engineer in order to reduce the number of incidents, injuries and deaths at at grade crossings. The Texas Railroad Information Management System (TRIMS) will be completed in 2013 and will improve the accuracy, consistency and accessibility to highway rail crossing data, as well as the efficiency in prioritizing crossing improvement projects. The Rail Division is also refining the Texas Rail Inspection Plan (TRIP) that will establish a process to prioritize inspection activities based on risk assessment and analysis of historical data. The goal of this more proactive approach is to reduce rail incidents and accidents and to focus inspection efforts at high risk locations. The FRA has expressed an interest in adopting this approach with other participating states. Our inspectors and investigators will continue to work safely and diligently to identify and improve safety issues along the rail system with a goal of retaining our status with the FRA as having the top State Rail Safety Participation Program. Lastly, the Rail Division will be updating the required State Safety Oversight (SSO) Program. Findings from the 2012 Federal Transit Administration audit will be addressed and state statutes will be updated to align with MAP 21 requirements. Consultant support will be solicited with the objective of completing the update by October 2013.

Rail Division. Riding the Rails

Rail Division. Riding the Rails Rail Division Riding the Rails Amtrak Ridership within Texas Remains Strong The annual ridership within Texas on all three services (Heartland Flyer, Texas Eagle and Sunset Limited) continues to soar.

More information

E2 D0 U 1 C 3 A E T D IUOCNA A T IL O S N E A R L I E S S E R I E S HUB/DBE/SBE R A I L

E2 D0 U 1 C 3 A E T D IUOCNA A T IL O S N E A R L I E S S E R I E S HUB/DBE/SBE R A I L 2E 0D1U3CEAT D UI O CN ATAI LO NSAELR ISEESR I E S R AIL HUB/DBE/SBE RAIL IN TEXAS OVERVIEW Since its inception, the Texas Department of Transportation (TxDOT) has focused on meeting the transportation

More information

Update on the Texas Rail Plan. Jennifer Moczygemba Texas Department of Transportation Rail Division Rail System Section Director

Update on the Texas Rail Plan. Jennifer Moczygemba Texas Department of Transportation Rail Division Rail System Section Director Update on the Texas Rail Plan Jennifer Moczygemba Texas Department of Transportation Rail Division Rail System Section Director Where We Were 1970 s - Freight Railroads struggling due to restrictive regulation

More information

2017 Educational Series RAIL

2017 Educational Series RAIL 2017 Educational Series RAIL RAIL OVERVIEW The state of Texas has the most rail lines of any state with a total of 10,469 miles of track, and the most public highway-rail grade crossings with a total of

More information

2004 FEASIBILITY STUDY UPDATE

2004 FEASIBILITY STUDY UPDATE Austin-San Antonio Intermunicipal Commuter Rail District 2004 FEASIBILITY STUDY UPDATE December 2004 EXECUTIVE SUMMARY INTRODUCTION Almost 3 million people in Central Texas, living and working between

More information

Texas A&M Transportation Short Course

Texas A&M Transportation Short Course Texas A&M Transportation Short Course Joseph Black Rail Director October 16, 2013 What are the Challenges? Public Safety Issues with trains of up to 2 miles in length running through the urban cores of

More information

INTERSTATE CORRIDOR PLANNING

INTERSTATE CORRIDOR PLANNING INTERSTATE CORRIDOR PLANNING Prioritization of Corridor Studies July 29, 2015 Importance of the Interstate System Texas is an integral part of the national interstate system. The interstate system provides

More information

GULF COAST RAIL DISTRICT VISION FOR REGIONAL RAIL

GULF COAST RAIL DISTRICT VISION FOR REGIONAL RAIL GULF COAST RAIL DISTRICT VISION FOR REGIONAL RAIL OCTOBER 2014 Cover photographs courtesy of Top left - Mike Bates TABLE OF CONTENTS MISSION... 1 INTRODUCTION... 1 VISION STATEMENT... 1 BACKGROUND... 2

More information

Rail Freight and Passenger

Rail Freight and Passenger Take Care of the System Critical Investments in the areas of: Rail Freight rehabilitate rail bridges o Rail Bridge Inventory Database... $0.5 - $1.0 million (one time) Rail Freight rail replacement and

More information

W. W. HAY SEMINAR SERIES. Tower 55 Multimodal Improvements NATIONAL UNIVERSITY RAIL CENTER UNIVERSITY OF ILLINOIS AT URBANA-CHAMPAIGN

W. W. HAY SEMINAR SERIES. Tower 55 Multimodal Improvements NATIONAL UNIVERSITY RAIL CENTER UNIVERSITY OF ILLINOIS AT URBANA-CHAMPAIGN W. W. HAY SEMINAR SERIES NATIONAL UNIVERSITY RAIL CENTER UNIVERSITY OF ILLINOIS AT URBANA-CHAMPAIGN Tower 55 Multimodal Improvements 2015 HDR, Inc., all rights reserved. W. W. HAY SEMINAR SERIES TOWER

More information

DECEMBER P R O G R E S S R E P O R T

DECEMBER P R O G R E S S R E P O R T DECEMBER 201 2 P R O G R E S S R E P O R T The My 35 Plan is a dynamic document and will continue to be re-evaluated and updated by the Committee as needed. The My 35 Plan contains the ideas and recommendations

More information

TEXAS-OKLAHOMA PASSENGER RAIL STUDY

TEXAS-OKLAHOMA PASSENGER RAIL STUDY TEXAS-OKLAHOMA PASSENGER RAIL STUDY Jennifer Moczygemba, P.E. Rail Division Texas-Oklahoma Passenger Rail Study (TOPRS) Study of the feasibility of various passenger rail options that will result in a

More information

Preapplication for HSIPR Program OMB No

Preapplication for HSIPR Program OMB No U.S. Department of Transportation Preapplication for HSIPR Program OMB No. 2130 0583 Preapplication instructions: For each question, enter the appropriate information in the designated gray box; keep text

More information

Preapplication for HSIPR Program OMB No

Preapplication for HSIPR Program OMB No U.S. Department of Transportation Federal Railroad Administration Preapplication for HSIPR Program OMB No. 2130 0583 Preapplication instructions: For each question, enter the appropriate information in

More information

STATEWIDE ANALYSIS MODEL (SAM-V3) June 5, 2014 Janie Temple

STATEWIDE ANALYSIS MODEL (SAM-V3) June 5, 2014 Janie Temple STATEWIDE ANALYSIS MODEL (SAM-V3) June 5, 2014 Janie Temple Introduction Brief SAM History Intro to SAM-V3 functionality Past and Current SAM projects Future additions to SAM Suggestions from model users

More information

Developing New Revenue Streams For Transit

Developing New Revenue Streams For Transit Developing New Revenue Streams For Transit Jennifer Mitchell Agency Director Rail~Volution October 23, 2018 DRPT Role in Transportation DRPT focuses on moving people and goods: Rail Public transportation

More information

Section IMPLEMENTATION PLAN. 7. Implementation Plan

Section IMPLEMENTATION PLAN. 7. Implementation Plan Section 7 IMPLEMENTATION PLAN 7. Implementation Plan 7.0 Implementation Plan The Tier 1 Final EIS has presented several improvements along the Chicago to St. Louis corridor to meet the purpose and need

More information

Environmental Impact Statement; Lone Star Regional Rail Project Williamson, Travis, Bastrop, Hays, Caldwell, Comal, Guadalupe, and Bexar Counties, TX

Environmental Impact Statement; Lone Star Regional Rail Project Williamson, Travis, Bastrop, Hays, Caldwell, Comal, Guadalupe, and Bexar Counties, TX This document is scheduled to be published in the Federal Register on 10/06/2014 and available online at http://federalregister.gov/a/2014-23711, and on FDsys.gov [4910-22] DEPARTMENT OF TRANSPORTATION

More information

Multi-State Planning Proposal

Multi-State Planning Proposal High Speed Intercity Passenger Rail (HSIPR) Program Multi-State Planning Proposal Groups of states seeking FRA-led corridor planning must submit this Proposal Form and other documents as outlined in Section

More information

Texas-Oklahoma Passenger Rail Study. Welcome to the scoping open house!

Texas-Oklahoma Passenger Rail Study. Welcome to the scoping open house! Texas-Oklahoma Passenger Rail Study Welcome to the scoping open house! INTRODUCTION Welcome! At this scoping open house you can provide input to help shape the Texas- Oklahoma Passenger Rail Study (TOPRS).

More information

Stockton Freight & Passenger Rail Mobility Enhancement

Stockton Freight & Passenger Rail Mobility Enhancement Stockton Freight & Passenger Rail Mobility Enhancement 2017 $10.34 million in 2017 FASTLANE Grant funding to complete engineering design, permitting, and construction of the Stockton Track Extension and

More information

Preapplication for HSIPR Program OMB No

Preapplication for HSIPR Program OMB No U.S. Department of Transportation Federal Railroad Administration Preapplication for HSIPR Program OMB No. 2130 0583 Preapplication instructions: For each question, enter the appropriate information in

More information

TEXAS FREIGHT MOBILITY PLAN. Greater Houston Freight Committee Kick-Off Meeting

TEXAS FREIGHT MOBILITY PLAN. Greater Houston Freight Committee Kick-Off Meeting TEXAS FREIGHT MOBILITY PLAN Greater Houston Freight Committee Kick-Off Meeting July 11, 2016 Overview of Texas Freight Mobility Plan The Freight Plan is TxDOT's first multimodal transportation plan that

More information

Freight and Rail Stakeholder Webinar. January 7, 2014

Freight and Rail Stakeholder Webinar. January 7, 2014 Freight and Rail Stakeholder Webinar January 7, 2014 Agenda Modal Needs Baseline Revenue Modal Scenarios Website Statewide Freight Plan Statewide Rail Plan Jeff Carroll MULTIMODAL TRANSPORTATION NEEDS

More information

Texas Transportation Forum The Fast Track: Passenger Rail In Texas. Federal Railroad Administration Karen Rae, Deputy Administrator

Texas Transportation Forum The Fast Track: Passenger Rail In Texas. Federal Railroad Administration Karen Rae, Deputy Administrator US Department of Transportation Federal Railroad Administration Texas Transportation Forum The Fast Track: Passenger Rail In Texas Federal Railroad Administration Karen Rae, Deputy Administrator January

More information

Chapter 1 - Introduction

Chapter 1 - Introduction Chapter 1 - Introduction Since the opening of Texas s first railroad, the Buffalo Bayou on September 7, 1853 (part of the Brazos and Colorado Railway in the Houston region), railroads have been a vital

More information

South Orient Railroad (SORR) Rehabilitation & Presidio- Ojinaga International Bridge Reconstruction Project

South Orient Railroad (SORR) Rehabilitation & Presidio- Ojinaga International Bridge Reconstruction Project South Orient Railroad (SORR) Rehabilitation & Presidio- Ojinaga International Bridge Reconstruction Project Presidio County, Texas TIGER FY16 Grant Application April 2016 CONTENTS Contents... ii i. Project

More information

Dallas City Council Transportation & Environment Committee. May 13, 2013

Dallas City Council Transportation & Environment Committee. May 13, 2013 Dallas City Council Transportation & Environment Committee May 13, 2013 Presentation Outline Technology Definitions Current RTC Policy Families of Alignment/Station Options RTC/NCTCOG Role in Statewide

More information

2.0 ALTERNATIVES. 2.1 Introduction. 2.2 No Build Alternative

2.0 ALTERNATIVES. 2.1 Introduction. 2.2 No Build Alternative 2.0 ALTERNATIVES 2.1 Introduction The alternatives selected for evaluation in this Environmental Assessment (EA) include the No Build Alternative and a Build Alternative that provides for increased HSR

More information

INVESTMENT SCENARIOS CHAPTER Illustrative Investment Approaches Public Outreach 6-1

INVESTMENT SCENARIOS CHAPTER Illustrative Investment Approaches Public Outreach 6-1 CHAPTER 6 As detailed in Chapters 4 and 5, Texas multimodal transportation needs estimated at $21 billion annually (2014 constant dollars) illustrated in Exhibit 4-12 far outstrip the approximately $9.1

More information

DRAFT ENVIRONMENTAL IMPACT STATEMENT FOR HOUSTON DALLAS HIGH SPEED RAIL (TEXAS CENTRAL)

DRAFT ENVIRONMENTAL IMPACT STATEMENT FOR HOUSTON DALLAS HIGH SPEED RAIL (TEXAS CENTRAL) DRAFT ENVIRONMENTAL IMPACT STATEMENT FOR HOUSTON DALLAS HIGH SPEED RAIL (TEXAS CENTRAL) Background On June 25, 2014, the Federal Railroad Administration (FRA) issued a Notice of Intent to Prepare an Environmental

More information

Tier 2 Environmental Impact Statement for the High-Speed Rail Project from Granite

Tier 2 Environmental Impact Statement for the High-Speed Rail Project from Granite This document is scheduled to be published in the Federal Register on 02/18/2014 and available online at http://federalregister.gov/a/2014-03324, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION

More information

7 Transportation Improvement strategies

7 Transportation Improvement strategies 7-1 7 Transportation Improvement strategies Based on analyses conducted during the course of the /I-10 Feasibility Study, it was determined that various alternatives for improving the entire corridor to

More information

summary report West Texas Rail Feasibility Study Texas Department of Transportation Cambridge Systematics, Inc. HNTB August 2011

summary report West Texas Rail Feasibility Study Texas Department of Transportation Cambridge Systematics, Inc. HNTB August 2011 summary report prepared for Texas Department of Transportation prepared by Cambridge Systematics, Inc. with HNTB August 2011 www.camsys.com summary report West Texas Rail Feasibility Study prepared for

More information

Chapter IX Regional Performance

Chapter IX Regional Performance Chapter IX Regional Performance In recent years, performance-based planning and project programming have increasingly been employed by the North Central Texas Council of Governments (NCTCOG) in the development

More information

TECHNICAL MEMORANDUM #1. The Vision, Goals and Objectives for Rail Transportation in Missouri

TECHNICAL MEMORANDUM #1. The Vision, Goals and Objectives for Rail Transportation in Missouri TECHNICAL MEMORANDUM #1 The Vision, Goals and Objectives for Rail Transportation in Missouri April 2012 1 The Vision, Goals and Objectives for Rail Transportation in Missouri Role of Railroads in Missouri

More information

Status Report on the 3 Rail Priorities

Status Report on the 3 Rail Priorities Status Report on the 3 Rail Priorities Presented to the Fort Worth City Council November 16, 2010 1 Review In August/September, the Mayor appointed the Rail Funding Strategies Committee to: Formulate funding

More information

North Central Texas Council of Governments 157

North Central Texas Council of Governments 157 13. Transportation System Safety The goal of the Transportation System Safety Program Area is to improve transportation safety throughout the region by supporting planning efforts to develop safety policies,

More information

Tower 55 At-Grade Improvement Project

Tower 55 At-Grade Improvement Project AMERICAN RECOVERY AND REINVESTMENT ACT OF 2009 TRANSPORTATION INVESTMENT GENERATING ECONOMIC RECOVERY TIGER DISCRETIONARY GRANT APPLICATION Tower 55 At-Grade Improvement Project Project Type: Project Location:

More information

Project Planning Documentation

Project Planning Documentation Project Planning Documentation Overview of Project Project funding will be used to complete necessary preliminary engineering and NEPA for a new 250 mile high-speed core express service between Dallas-Fort

More information

± Legend. Tower 55. Trinity Railway Express Fort Worth & Western Railroad. UP Railroad BNSF Railway

± Legend. Tower 55. Trinity Railway Express Fort Worth & Western Railroad. UP Railroad BNSF Railway Blue Skyways Collaborative Annual Meeting San Antonio, TX October 30, 2008 North Central Texas Council of Governments Transportation Department ± Legend Tower 55 UP Railroad BNSF Railway Trinity Railway

More information

Introduction. Performance Measurement. Pg. 01

Introduction. Performance Measurement. Pg. 01 Pg. 01 Introduction The Alamo Area recognizes the importance of transportation performance tracking, goal setting and measurement to provide greater accountability and transparency and to achieve a more

More information

PURPOSE AND NEED FOR ACTION

PURPOSE AND NEED FOR ACTION Section 2 PURPOSE AND NEED FOR ACTION 2. Purpose and Need for Action 2.0 Purpose and Need for Action This chapter describes the purpose and need for improved high speed passenger rail on the Chicago to

More information

Application Form Track 1a Final Design (FD)/Construction & Track 4 FY 2009 Appropriations Projects

Application Form Track 1a Final Design (FD)/Construction & Track 4 FY 2009 Appropriations Projects FD/Construction and/or Track 4OMB No. 2130-0583 Project Name: TX - Tower 55 At Grade Improvement Project - Ia Date of Submission: 8/24/09 Version Number: v1 High-Speed Intercity Passenger Rail (HSIPR)

More information

LONG BRIDGE CAPACITY NEEDS. Oscar J. Gonzalez Virginia Railway Express Project Manager Alexandria, VA

LONG BRIDGE CAPACITY NEEDS. Oscar J. Gonzalez Virginia Railway Express Project Manager Alexandria, VA LONG BRIDGE CAPACITY NEEDS Oscar J. Gonzalez Virginia Railway Express Project Manager Alexandria, VA 1 TODAY S PRESENTATION VRE Overview Project Location and Partners Challenges and Opportunities Funding

More information

TEXAS TRANSPORTATION PLAN

TEXAS TRANSPORTATION PLAN TEXAS TRANSPORTATION PLAN TxDOT Planning Conference June 5, 2014 Michelle Maggiore, P.E., CH2M HILL Agenda 1 Performance-based planning what is it? 3 2 How is performance-based planning addressed in the

More information

Section IMPLEMENTATION PLAN. 7. Implementation Plan

Section IMPLEMENTATION PLAN. 7. Implementation Plan Section 7 IMPLEMENTATION PLAN 7. Implementation Plan 7.0 Implementation Plan The Tier 1 DEIS has presented several improvements along the Chicago to St. Louis corridor to meet the purpose and need of the

More information

ITEM #11: PHASE 2B SUPPLEMENT HAMPTON ROADS PASSENGER RAIL STUDY: SCOPE OF WORK

ITEM #11: PHASE 2B SUPPLEMENT HAMPTON ROADS PASSENGER RAIL STUDY: SCOPE OF WORK ITEM #11: PHASE 2B SUPPLEMENT HAMPTON ROADS PASSENGER RAIL STUDY: SCOPE OF WORK During FY 2011, in the interest of improving the region s potential for passenger rail service, the HRTPO retained the services

More information

I-35 Corridor Segment Committee NW Loop 410 San Antonio, Texas. March 11, :00 AM to Noon

I-35 Corridor Segment Committee NW Loop 410 San Antonio, Texas. March 11, :00 AM to Noon I-35 Corridor Segment Committee 4 3500 NW Loop 410 San Antonio, Texas March 11, 2010 9:00 AM to Noon Welcome Nancy Parker Facilitator Presentations Presentation on the Texas State Rail Plan Jennifer Moczygemba

More information

Public Participation Plan... II-5

Public Participation Plan... II-5 TABLE OF CONTENTS CHAPTER I CHAPTER II CHAPTER III CHAPTER IV INTRODUCTION/BACKGROUND Purpose of the Transportation Improvement Program... I-1 TIP Objectives... I-1 Understanding the Metropolitan Planning

More information

1.1 Environmental Assessment/Environmental Impact Evaluation for the New Haven, Hartford and Springfield High-Speed Intercity Rail Project

1.1 Environmental Assessment/Environmental Impact Evaluation for the New Haven, Hartford and Springfield High-Speed Intercity Rail Project 1.0 INTRODUCTION 1.1 Environmental Assessment/Environmental Impact Evaluation for the New Haven, Hartford and Springfield High-Speed Intercity Rail Project Connecticut is centrally located in a part of

More information

Pacific Northwest High Speed Rail Corridor Amtrak Cascades Passenger Service Update

Pacific Northwest High Speed Rail Corridor Amtrak Cascades Passenger Service Update Pacific Northwest High Speed Rail Corridor Amtrak Cascades Passenger Service Update John Sibold Cascade Rail Corridor Director State Rail and Marine Director, WSDOT International Mobility Trade Corridor

More information

APPROVAL TO SUBMIT COMMENTS ON I-45 AND MORE DRAFT ENVIRONMENTAL IMPACT STATEMENT

APPROVAL TO SUBMIT COMMENTS ON I-45 AND MORE DRAFT ENVIRONMENTAL IMPACT STATEMENT TAC Agenda Item 09 Mailout 7/12/17 APPROVAL TO SUBMIT COMMENTS ON I-45 AND MORE DRAFT ENVIRONMENTAL IMPACT STATEMENT Background The Texas Department of Transportation, in cooperation with the Federal Highway

More information

1. Evaluation of route and service alternatives; 2. Tier 1 Environmental Impact Analysis; and 3. Service Development Plan.

1. Evaluation of route and service alternatives; 2. Tier 1 Environmental Impact Analysis; and 3. Service Development Plan. Rail Rail plays a significant role in transportation planning, especially when considering economic development, safety, freight, and intermodal connectivity. Jackson has two rail lines serving the area,

More information

Chapter 10 Goals, Objectives + Policies

Chapter 10 Goals, Objectives + Policies Chapter 10 Goals, + Policies Warehouse on Nestle Way near I-78 114 115 10.1 ESTABLISHMENT OF CONSISTENT GOALS 10.2 NATIONAL FREIGHT GOALS The Lehigh Valley s freight transportation investment decisions

More information

CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK

CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK MTP VISION In order to create a framework for the 2040 Metropolitan Transportation Plan (MTP), a vision statement was drafted by the Vision/Goals Committee and

More information

2010 Indiana Logistics Summit

2010 Indiana Logistics Summit 2010 Indiana Logistics Summit Michael B. Cline Commissioner, INDOT October 26, 2010 INDOT 3,912 INDOT employees 1,702 Highway Technicians 594 Managers/Supervisors 325 Engineers 805 District CO 3,106 State

More information

Benefit Cost Analysis Narrative

Benefit Cost Analysis Narrative Chicago Region Environmental and Transportation Efficiency Program (CREATE) Grade Separations of: GS21a - Union Pacific and 95 th Street GS11 - Belt Railway Company of Chicago and Columbus Ave. GS 9 -

More information

Texas Freight Mobility Plan. Chapter 1: Introduction

Texas Freight Mobility Plan. Chapter 1: Introduction Texas Freight Mobility Plan Chapter 1: Introduction Draft August 8, 2014 The Texas Freight Mobility Plan (the Freight Plan) gives Texas a road map for boosting our economic growth potential through a solid

More information

1.0 INTRODUCTION Federal Mandate for State Rail Plans Stakeholder Consultation Ongoing Planning Process...

1.0 INTRODUCTION Federal Mandate for State Rail Plans Stakeholder Consultation Ongoing Planning Process... TABLE OF CONTENTS 1.0 INTRODUCTION... 1-1 1.1 Federal Mandate for State Rail Plans......1-2 1.2 Stakeholder Consultation... 1-3 1.3 Ongoing Planning Process... 1-3 2.0 STATE RAIL ACTIVITY IN OHIO... 2-1

More information

The Metropolitan Transportation Plan. Public Meetings January 2016

The Metropolitan Transportation Plan. Public Meetings January 2016 The Metropolitan Transportation Plan for North Central Texas Public Meetings January 2016 Presentation Agenda Mobility 2040 Draft Recommendations 2016 Transportation Conformity RTC Policy Bundle Concept

More information

Sunrise Project South I-205 Corridor Improvement Project

Sunrise Project South I-205 Corridor Improvement Project Sunrise Project South I-205 Corridor Improvement Project January 24, 2007 Sunrise and I-205 Project Summary Conclusions Sunrise Scoping Study Key Results South I-205 Scoping Study Key Results South I-205

More information

Technical Memorandum MULTIMODAL NEEDS. Prepared for: Oklahoma Department of Transportation. Prepared by:

Technical Memorandum MULTIMODAL NEEDS. Prepared for: Oklahoma Department of Transportation. Prepared by: Technical Memorandum MULTIMODAL NEEDS Prepared for: Oklahoma Department of Transportation Prepared by: May 2015 Technical Memorandum The Technical Memos were written to document early research for the

More information

Regional Performance Measures Annual Progress Report TPO Board - 2/4/2016 Presentation by: Chris Wichman, Senior Planner

Regional Performance Measures Annual Progress Report TPO Board - 2/4/2016 Presentation by: Chris Wichman, Senior Planner 2015 TPO Board - 2/4/2016 Presentation by: Chris Wichman, Senior Planner Overview History and definition of performance-based planning & programming Review of 2015 TPO Board Action Requested 2 History

More information

U.S. Department of Transportation. National Infrastructure Investments Grant Program. TIGER Discretionary GRANT APPLICATION

U.S. Department of Transportation. National Infrastructure Investments Grant Program. TIGER Discretionary GRANT APPLICATION U.S. Department of Transportation National Infrastructure Investments Grant Program TIGER Discretionary GRANT APPLICATION Project Name: Project Type: South Orient Rehabilitation Sulphur Junction to Fort

More information

Union Pacific in Houston: Investing to Meet Freight Demands. Brenda Mainwaring, VP Public Affairs, November 12, 2013

Union Pacific in Houston: Investing to Meet Freight Demands. Brenda Mainwaring, VP Public Affairs, November 12, 2013 Union Pacific in Houston: Investing to Meet Freight Demands Brenda Mainwaring, VP Public Affairs, November 12, 2013 1 Agenda Union Pacific Overview Developing Markets Investing for Capacity The Future

More information

Project Title: South Orient Railroad (SORR) Rehabilitation Project Location: Fort Stockton, Texas, Congressional District 23 Application Type: Capital Rural Freight Rail Project Applicant Name: Texas Department

More information

New Approaches to Public Collaboration

New Approaches to Public Collaboration New Approaches to Public Collaboration Dean Wise Vice President, Network Strategy 2/25/2014 Rail Handles 40% of US Freight U.S. Freight By Mode 2009 Ton-Miles Truck 34% Rail 40% Water 12% Pipeline 14%

More information

Application Form Track 1a Final Design (FD)/Construction & Track 4 FY 2009 Appropriations Projects

Application Form Track 1a Final Design (FD)/Construction & Track 4 FY 2009 Appropriations Projects TX BNSF Fort Worth Sub Capitalized Maintenance Track 1a FD/Construction and/or Track 4OMB No. 2130-0583 Project Name: TX- BNSF Ft Worth Sub Capitalized Maintenance 1a Date of Submission: 8/24/09 Version

More information

2010 Minnesota Comprehensive Statewide Freight and Passenger Rail Plan. Minnesota Department of Transportation

2010 Minnesota Comprehensive Statewide Freight and Passenger Rail Plan. Minnesota Department of Transportation 2010 Minnesota Comprehensive Statewide Freight and Passenger Rail Plan Minnesota Department of Transportation ! First Statewide Comprehensive Rail Plan for MN! Commissioned by 2008 Legislature! Compliant

More information

Mobility 2025 Update: The Metropolitan Transportation Plan

Mobility 2025 Update: The Metropolitan Transportation Plan Mobility 2025 Update: The Metropolitan Transportation Plan May, 2001 North Central Texas Council of Governments Transportation Department MOBILITY 2025 UPDATE FINANCIAL SUMMARY Metropolitan Transportation

More information

MONITORING IMPLEMENTATION AND PERFORMANCE

MONITORING IMPLEMENTATION AND PERFORMANCE 12 MONITORING IMPLEMENTATION AND PERFORMANCE The FAST Act continues the legislation authorized under MAP-21, which created a data-driven, performance-based multimodal program to address the many challenges

More information

I-35 Corridor Segment Committee Bagby Ave. Waco, Texas. March 9, :00 AM to Noon

I-35 Corridor Segment Committee Bagby Ave. Waco, Texas. March 9, :00 AM to Noon I-35 Corridor Segment Committee 2 7479 Bagby Ave. Waco, Texas March 9, 2010 9:00 AM to Noon Welcome Bruce Byron Facilitator Presentations Presentation on the Texas State Rail Plan Presentation on Regional

More information

TEXAS DEPARTMENT OF TRANSPORTATION. Texas Statewide Long-Range Transportation Plan Executive Summary

TEXAS DEPARTMENT OF TRANSPORTATION. Texas Statewide Long-Range Transportation Plan Executive Summary TEXAS DEPARTMENT OF TRANSPORTATION Texas Statewide Long-Range Transportation Plan 2035 Executive Summary Table of Contents Introduction and Overview 5 Our Transportation System and Its Importance to our

More information

TEXAS FREIGHT MOBILITY PLAN: DRAFT KEY POLICY RECOMMENDATIONS

TEXAS FREIGHT MOBILITY PLAN: DRAFT KEY POLICY RECOMMENDATIONS TEXAS FREIGHT MOBILITY PLAN: DRAFT KEY POLICY RECOMMENDATIONS Texas Freight Advisory Committee Midland August 14, 2014 Draft Key Policy Recommendations August 14, 2014 2014 Freight Mobility Plan Recommendations

More information

BENEFIT-COST ANALYSIS AND ECONOMIC IMPACTS

BENEFIT-COST ANALYSIS AND ECONOMIC IMPACTS U.S. Department of Transportation National Infrastructure Investments Grant Program TIGER Discretionary GRANT APPLICATION SUPPORTING DOCUMENTATION BENEFIT-COST ANALYSIS AND ECONOMIC IMPACTS for Project

More information

Technical Methods Part 2

Technical Methods Part 2 Technical Methods Part 2 Performance Measurement in Transportation Planning Leading for results means that performance must be planned, not just reported Learning Objectives Describe a sample technical

More information

2. Establish an Office of Capital Program and Performance Measurement. 3. Retain planners and capital program planning in modal offices

2. Establish an Office of Capital Program and Performance Measurement. 3. Retain planners and capital program planning in modal offices Excerpts from Strengthening Investment Management and Strategic, Multimodal and Intermodal Planning at Mn/DOT: Modal Planning and Program Management Division Restructuring Recommendations (February 2010)

More information

TEXAS-OKLAHOMA PASSENGER RAIL STUDY. TPP Planning Conference 2014

TEXAS-OKLAHOMA PASSENGER RAIL STUDY. TPP Planning Conference 2014 TEXAS-OKLAHOMA PASSENGER RAIL STUDY TPP Planning Conference 2014 Funding for the Project Study is funded through a Federal Railroad Administration (FRA) Grant. Original grant application for the corridor

More information

9 Summary of Findings

9 Summary of Findings 9-1 9 Summary of Findings As mentioned previously, this study does not recommend a preferred alternative, but provides sufficient technical information and comparisons of the impacts and feasibility of

More information

TEXAS TRANSPORTATION PLAN DEVELOPMENT

TEXAS TRANSPORTATION PLAN DEVELOPMENT CHAPTER 2 The Texas Transportation Plan (TTP) advances performance-based planning concepts and integrates existing and ongoing state transportation plans and initiatives. While TxDOT s role as owner-operator,

More information

7 Disciplines of Engineering at Union Pacific Railroad

7 Disciplines of Engineering at Union Pacific Railroad William W. Hay Railroad Engineering Seminar 7 Disciplines of Engineering at Union Pacific Railroad Eric Gehringer Assistant Vice President of Track Programs, Union Pacific Railroad Sponsored by Date: Friday,

More information

(FOR IMMEDIATE RELEASE)

(FOR IMMEDIATE RELEASE) news Texas Department of Transportation (FOR IMMEDIATE RELEASE) July 18, 2007 La Entrada Study Analyzing Trade Corridor Team examining potential impacts on existing highway network The potential of the

More information

Introduction... 1 Florida s Rail System... 1 Rail Freight... 3 Rail Passengers... 5 Conclusions... 9

Introduction... 1 Florida s Rail System... 1 Rail Freight... 3 Rail Passengers... 5 Conclusions... 9 January 2011 Table of Contents Introduction... 1 Florida s Rail System... 1 Rail Freight... 3 Rail Passengers... 5 Conclusions... 9 Table of Figures and Tables Figure 1 Florida Rail System Map... 2 Figure

More information

Appendix C Presentation Slides with Script

Appendix C Presentation Slides with Script Appendix C Presentation Slides with Script 32 Grand Crossing Rail Project 10 S. Riverside Plaza, Suite 400 Chicago, IL 60606 www.grandcrossingrail.com info@grandcrossingrail.com [title slide no narration]

More information

Telling the Freight (trucking/goods movement) story:

Telling the Freight (trucking/goods movement) story: Telling the Freight (trucking/goods movement) story: Urban Mobility Report truck elements Trucks in Texas 100 Connection to Texas Freight Network Improving data for truck analyses Solutions/uses Observations

More information

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement 2 Purpose and Need 2.1 Study Area Interstate 81 (I-81) is relied upon for local and regional travel and interstate travel in the eastern United States. It extends 855 miles from Tennessee to New York at

More information

2016 Texas Rail Plan Update. Chapter 5: Long Range Vision

2016 Texas Rail Plan Update. Chapter 5: Long Range Vision 2016 Texas Rail Plan Update Chapter 5: Long Range Vision May 2016 5.1 Introduction The purpose of this chapter is to provide Texas rail vision, goals, and objectives over the next 25 years and describe

More information

Technical Briefing Report

Technical Briefing Report Technical Briefing Report March 2007 CONGESTION MANAGEMENT PROCESS (CMP) The Congestion Management Process (CMP) seeks a management solution to a growing traffic problem by targeting resources to operational

More information

9.0 Meeting the Challenges

9.0 Meeting the Challenges 9.0 Meeting the Challenges 9.1 SLRTP Goals The SLRTP is built around the six TxDOT Strategic Plan goals. 1. Develop an organizational structure and strategies designed to address the future multimodal

More information

Southeastern Minnesota Freight Rail Capacity Study

Southeastern Minnesota Freight Rail Capacity Study P U R P O S E A N D N E E D S T A T E M E N T Southeastern Minnesota Freight Rail Capacity Study Feasibility and Alternatives Analysis Study Prepared for: Prepared by: July 2012 Kimley-Horn and Associates,

More information

INTEGRATING FREIGHT IN CORRIDOR PLANNING AND PROJECT DEVELOPMENT. Steve Linhart, AICP Caroline Mays, AICP

INTEGRATING FREIGHT IN CORRIDOR PLANNING AND PROJECT DEVELOPMENT. Steve Linhart, AICP Caroline Mays, AICP INTEGRATING FREIGHT IN CORRIDOR PLANNING AND PROJECT DEVELOPMENT Steve Linhart, AICP Caroline Mays, AICP June 17, 2016 The Importance of Freight Transportation in Texas Almost 4 billion tons of freight

More information

LA 23 NOGC Railway Relocation PE/NEPA Project. Public Meeting

LA 23 NOGC Railway Relocation PE/NEPA Project. Public Meeting LA 23 NOGC Railway Relocation PE/NEPA Project Public Meeting LA 23 New Orleans & Gulf Coast Railway (NOGC) Relocation Preliminary Engineering (PE) / National Environmental Policy Act (NEPA) Project RPC/FRA

More information

Twin Cities-Milwaukee-Chicago Intercity Passenger Rail Phase I Study Twin Cities- Milwaukee High Speed Rail to Chicago Corridor Study

Twin Cities-Milwaukee-Chicago Intercity Passenger Rail Phase I Study Twin Cities- Milwaukee High Speed Rail to Chicago Corridor Study Twin Cities-Milwaukee-Chicago Intercity Passenger Rail Phase I Study Twin Cities- Milwaukee High Speed Rail to Chicago Corridor Study Rail Modeling Update May 4, 2017 www.dot.state.mn.us/passengerrail/tc-mil-chi/

More information

Agency Scoping Meeting

Agency Scoping Meeting Agency Scoping Meeting Dallas Fort Worth Core Express Service Drop-in Public Information Open House Tuesday, June 30, 2015 1 WELCOME AND THANK YOU FOR COMING TODAY 2 Meeting Format Open House 3 Purpose

More information

OVERVIEW OF RESEARCH PROJECT INTRODUCTION

OVERVIEW OF RESEARCH PROJECT INTRODUCTION OVERVIEW OF RESEARCH PROJECT 0-5930 TTI recently completed TxDOT Research Project 0-5930 Potential for Development of a Intercity Passenger Transit System in Texas which examined 18 intercity corridors

More information

SECTION III - REGIONAL ARTERIAL SYSTEM. The Regional Arterial System is a subcomponent of a broader regional thoroughfare system.

SECTION III - REGIONAL ARTERIAL SYSTEM. The Regional Arterial System is a subcomponent of a broader regional thoroughfare system. SECTION III - REGIONAL ARTERIAL SYSTEM SYSTEM IDENTIFICATION The Regional Arterial System is a subcomponent of a broader regional thoroughfare system. The NCTCOG Regional Thoroughfare Plan (RTP) recognizes

More information

LA 23 NOGC Railway Relocation PE/NEPA Project

LA 23 NOGC Railway Relocation PE/NEPA Project LA 23 NOGC Railway Relocation PE/NEPA Project LA 23/New Orleans & Gulf Coast Railway Relocation Preliminary Engineering (PE) / National Environmental Policy Act (NEPA) Project Kevin Keller, PE HDR Engineering,

More information

FOR IMMEDIATE RELEASE June 7, ATK Contact: Media Relations

FOR IMMEDIATE RELEASE June 7, ATK Contact: Media Relations FOR IMMEDIATE RELEASE June 7, 2010 ATK-10-080 Contact: Media Relations 202 906.3860 NATIONAL RAIL PLAN NEEDS TO RECOGNIZE THE VALUE OF AMTRAK S INTERCITY PASSENGER RAIL NETWORK Serves as foundation to

More information

SORR Rehabilitation and Presidio International Rail Bridge Reconstruction

SORR Rehabilitation and Presidio International Rail Bridge Reconstruction SORR Rehabilitation and Presidio International Rail Bridge Reconstruction Project: SORR Rehabilitation and Presidio International Rail Bridge Reconstruction Was a FASTLANE application for this project

More information