MTG-S Satellite and Platform ITT Items Spanish Industry Day Madrid

Size: px
Start display at page:

Download "MTG-S Satellite and Platform ITT Items Spanish Industry Day Madrid"

Transcription

1 MTG-S Satellite and Platform ITT Items Spanish Industry Day Madrid

2 OHB Presentation Content OHB Supply Chain Management Overview OHB MTG Procurement Approach and Schedule 2011 OHB-SYSTEM AG 2

3 OHB Supply Chain Management Overview

4 Supply Chain Management OHB-System established a multi-project procurement department in 2010 Goals are: Support of projects and relief of system engineering from typical procurement tasks Ensure on-time, on-cost deliveries Realization of multi-program synergies SCM Organisation, Interface and Point of Contacts are OHB-SYSTEM AG 4

5 Supply Chain Management Team Organisation, Interface and Point of Contacts Head of SCM Gerd Heinrich Subcontractor Managers Supply Chain Managers Paolo Apollonio Daniel Bast Luc Verstraeten Project Coordinator Susanne Müller Andre Burzlaff Ole Glöckner Andrea Marchese Dirk Untrieser David Murphy Maik Plenter Procurement Managers Thomas Staiger Matthias Treichel Massimiliano Olivier Andreas Peukert Eric Vansteenberghe Daniele Mattei 2011 OHB-SYSTEM AG 5

6 Supply Chain Management Team Name Telephone Topics M. Plenter Propulsion& Thermal Subsystems P. Apollonio Structure Subsystems D. Bast Payload Subsystems A. Burzlaff O. Glöckner G. Heinrich A. Marchese D. Mattei S. Müller D. Murphy M. Olivier A. Peukert T. Staiger M. Treichel D. Untrieser E. Vansteenberghe L. Verstraeten AOCS Equipment EGSE, MGSE Head of SCM ITTs, Parts procurement AOCS Subsystems Foreign Trade Power Equipment Project Procurement Manager Project Procurement Manager TTR Equipment & Antennas Solar Arrays & Batteries SCM Processes Payload Subsystems Environmental Testing 2011 OHB-SYSTEM AG 6

7 Supply Chain Management Organisation SCM works with Project System Engineering PMO Project Manager OHB-System Coordination of subcontract management activities Project procurement status and control SCM TEAM System Engineer Procurement Manager Subsystem Engineer A Subsystem Engineer S Technical Management Team Subsystem Engineer... Subcontract Subcontract Subcontract Manager Manager Manager A B Supplier A Procurement Administration and management,birectional Supplier B Monitoring and control of technical compliance (Form/Fit/Function), birectional Supplier C 2011 OHB-SYSTEM AG 7

8 Supplier Requirements (1) A Partner on our boat => OHB Success keys flown down to the supply base Strong Compliance status /Sound technical solutions Heritage components Credible project implementations Failure prevention instead of failure correction Lean organisation Commitment to competition Attractive Price 2011 OHB-SYSTEM AG 8

9 Supplier Requirements(2) Large Project envelopes Delta-Quals included Quantifiable flexibility on technical requirements up to PDR included Modular equipment solutions and scalability in performance Lead-times compatible to commercial Satellite delivery Kit -Pricing information EM, EQM + Shock Testing, Recurring FMs ( incl. TVAC), PFMs Mission dedicated Project Documentation Non-recurring Engineering cost details Classical Acceptance testing approach Final FM Sat-level E/V-test, Storage, Maintenance Discharge from piece parts obsolescence consequences 2011 OHB-SYSTEM AG 9

10 OHB MTG Procurement Approach and Schedule

11 OHB MTG Procurement Overview General remarks: Tender Type: ITT Issuing Company: OHB Maximum competition for all MTG ITTs 1 STM +1 EM + 1 AVM + 6 FM + Spares for all Platform Items Long storage of up to 10 years is special MTG requirement for both flight hardware and GSE (maintenance, obsolescence, etc...); proposal of appropriate concepts by suppliers will be requested by ITT OHB-SYSTEM AG 11

12 OHB MTG Procurement Overview Procurement Schedule for STM and EM: First STM Items required Q1/2013 PF STM Design, Procurement PF STM MAIT Sat-I AIT (TAS-F) Sat-S AIT First EM Items required Q4/2012 PF EM Design, Procurement PF EM MAIT Sat-I EM AIT (TAS-F) Sat-S EM AIT 2011 OHB-SYSTEM AG 12

13 OHB MTG Procurement Overview Procurement Schedule for PFM and FMs: PFM Items MTG-I Q4/2013 PF PFM-I Design, Procurement FM Items MTG-S1 FM Items Q4/2014 MTG-I2 FM Items Q3/2015 MTG-I3 Q4/2016 PF PFM-I MAIT PF PFM-S MAIT FM Items MTG-S2 Q1/2017 AIT MTG-S PFM Env. Test Campaign MTG-S PFM (Q1/2 2018) PF FM-I2 AIT FM Items MTG-I4 Q2/2018 PF FM-I3 AIT PF FM-S2 AIT Env. Test Campaign FM-S2 (Q2/3 2019) AIT MTG-S FM2 PF FM-I4 AIT 2011 OHB-SYSTEM AG 13

14 OHB MTG Procurement Overview Planned ITT Releases on EMITS: April 2011: PCDU Gyro Unit Reaction Wheels Coarse Rate Sensors Central Tube SMU May 2011: SADA DDU 2011 OHB-SYSTEM AG 14

15 OHB MTG Procurement Overview Planned ITT Releases on EMITS: June 2011: Coarse Sun Sensors Ka-Band Transmitter Ka-Band Antenna S-Band Transponder S-Band Antenna Star Tracker Battery 2011 OHB-SYSTEM AG 15

16 OHB MTG Procurement Overview Planned ITT Releases on EMITS: Q3 2011: Platform EGSE Structure Panels Platform MGSE Power and Data Harness Thermal Components Q4 2011: Independent Software Verification Q1 2012: MTG-S MGSE Q3 2012: MTG-S EGSE 2011 OHB-SYSTEM AG 16

17 OHB MTG Procurement Overview Planned ITT Releases on EMITS: Q4 2012: MTG-S Environmental Tests Q3 2014: MTG-S OGSE 2011 OHB-SYSTEM AG 17

18 OHB MTG Procurement Overview Point of Contact for OHB MTG Procurements: Name: Frank Ellmers MTG Procurement Manager Tel.: Fax: Address: Universitätsallee Bremen Germany 2011 OHB-SYSTEM AG 18