Darlington Refurbishment Project Update

Size: px
Start display at page:

Download "Darlington Refurbishment Project Update"

Transcription

1 Darlington Refurbishment Project Update Pickering Community Advisory Council November 18, 2014 Roy Martin, Project Director Refurbishment Execution

2 Contents Key Initiatives: Regulatory Approvals Productivity Improvements Projects: Tooling Fuel Handling Turbine Generator Work Other Updates: Cost Estimate/Labour Profile Community Updates What s Next 2

3 PHASE 1 Initiation Phase SCOPE OF WORK Initial determination of refurbishment scope through completion of: -Technical assessments of all major components -Condition assessments of balance of plant components -Initiation of regulatory processes; Integrated Safety Review and Environmental Assessment Develop reference plans for cost and schedule Complete economic feasibility assessment Establish project management approach and governance Establish overall contracting strategy OPG Board and Shareholder agree with recommendation to proceed with preliminary planning within the Definition Phase of the project Darlington Refurbishment: Phased Project Management Execution Preparation Phase PHASE 2 SCOPE OF WORK Obtain regulatory approvals: -Environmental Assessment -Integrated Safety Review -Integrated Implementation Plan Implement project management and oversight Complete infrastructure upgrades, i.e. Darlington Energy Complex Implement safety improvements Award major contracts Finalize project scope and complete engineering work Procure long lead materials Complete unit prerequisite work Construct reactor mock-up and fabricate and test tooling Develop release quality cost and schedule estimate Obtain all permits and licences Mobilize and train Trades staff PHASE 3 Outage Execution Phase SCOPE OF WORK Unit shutdown and defueling Island unit and lay up systems Execute all refurbishment scope: -Reactor components -Fuel handling systems -Turbine / generator -Steam generators -Balance of plant Meet all regulatory commitments Plant maintenance and inspection activities Manage plant configuration Load fuel Commissioning Unit start-up Apply lessons learned to subsequent unit refurbishments Project close-out Q2 2014R 3

4 Regulatory Approvals: Transparent Disclosure Canadian Nuclear Safety Commission (CNSC) July CNSC approved Darlington s request for a extension to current operating licence to December Public hearing on longer term licence application will take place Summer and Fall New: Stakeholder sessions on licence application. Discussion New hearing webpage with documentation posted. Ontario Energy Board (OEB) Application Refurbishment costs very small percentage of OPG s rate application. Proactive and transparent disclosure of contracting strategies. Aligned with the principles stated in the Government of Ontario s Long Term Energy Plan for nuclear refurbishment. 4

5 Safe and Efficient Worksite Access Improved local traffic flow and worksite access: New Holt Road/401 roundabouts and realignment of the South Service and Holt Roads. Separate access for Operations (Holt Road) and Refurbishment (Park Road) workers. New parking lot near the Refurbishment Project Office provides direct and nearby access to the work site. RPO separate entrance ensures no conflict of time or space with operations staff. 5

6 6 Refurbishment Project Office Secure entry point for Refurbishment workers. Go straight to the refurbishment island job site, punch the clock, begin work at the set start time. Vehicle Screening Facility Expedites vehicle traffic through security into the plant. Worksite Improvements Higher priority vehicles bypass traffic queues during periods of high construction traffic volume. RFR Island Support Annex RFR office, meeting and shop space. Perform pre-rfr fabrication and preparatory work activities. Retube Waste Processing Building Remote volume reduction of components. Minimizes interferences/disruption at reactor face. Site Services (Water and Sewer; Electrical Power Distribution System) Assures workers have a safe environment and facilities needed to do the work.

7 Tooling and Warehousing Tooling: Retube tooling platform delivered September, All tooling designed, prototypes manufactured and delivered to DEC by December Warehousing: 65,000 square feet of space available. Work ongoing to establish shelving, storage, clean room for pre-assembly of RFR components. 7

8 Fuel Handling Project GE-Hitachi designed, manufactured, supplied key parts: Dummy Fuel Bundles: mimic the characteristics of fuel bundles, used in a process called push defueling. FROBS (Flow restriction device) prevent bypass of coolant once a channel has been defueled. 8

9 Turbine Generator Project OPG staff interact with a life size, 3D model of the Hydraulic Control Rack Identify usability issues and mitigate discrepancies Incorporate user feedback in design, prior to Engineering completion and start of fabrication Prevents rework in final product 9

10 Project Cost Estimate Current project estimate is less than $10.0B (2013 overnight $): Assessments show project is economic. Work ongoing to refine estimate. As of June 30, 2014, actual costs are $1Billion and include: In-service of the Darlington Energy Complex (DEC) and the R&FR Mockup Progression of all other projects. 10

11 11 Preliminary Labour Profile 2016/2019

12 Labour Stability BTU/Nuclear Project Agreements provide labour stability and clarity on work rules. Stability to trade unions and workers that long term employment opportunities are available. Workers begin their tasks as soon as their pre-job brief is complete: The job begins at the job site, not at the site gate or parking lot. The pre-job brief takes place at the specific job site (e.g. RFR - at the RFRISA, TG - on the turbine floor; etc.). BTU will have Nuclear Qualified Workers ready: Qualified workers will be available for Refurbishment Workers will come to site with their Nuclear qualifications up to date. This will reduce the costs to OPG. Qualifications will be acceptable for both OPG and Bruce Power. Workers can be used at both sites without the risk of qualifications expiring or requiring refresher training. 12

13 Community Updates Continue Refurbishment Project Community Newsletter Summer 2014 and Fall 2014 New Darlington Refurbishment website News, reports, FAQs, etc. Video s Community briefings/updates Spring and Fall 2014 Semi-Annual Performance Report Posted on the web site Reactor Mock-up Training Area/Tours Scheduled tours - one day per quarter? Annual Open House? Virtual tours? 13

14 Darlington Refurbishment Open Doors: 3,500 visitors First week of November Self-guided tour New Visitor Information Centre Reactor Mock Up Training Area OPG staff on hand to explain/discuss the project Darlington Refurbishment Open Doors (November 4 8) 14

15 What s Next? Definition Planning Phase Complete Engineering Regulatory approvals Tool testing complete Release Quality, Cost and Schedule Estimate (RQE) Execution Preparation Phase Completion of pre-requisites Comprehensive work planning and final Unit 2 Execution Plan Staff/trades mobilization and training Unit 2 Refurbishment Outage Refurbishment commences in October 2016 Transition of Unit from Station to Project Defuel, drain and dry the reactor Establish Construction Island Remove Feeders/Fuel Channels, Balance of Plant scope Planning, Pre-requisites and Execution Engineering Complete Board Approval RQE Board Approval Unit 2 Unit 2 Breaker Open Defueling Complete Feeder Removal Complete Regulatory Approvals Hearing Part 1 Hearing Part 2 Infrastructure Installed/In Service CNSC Approval of Integrated Implementation Plan and Global Assessment Report Auxiliary Heating Building Operations Support Building Retube Feeder Replacement Annex Safety Improvement Projects Used Fuel Dry Storage Building Holt Road Interchange Complete Refurbishment Project Office D20 * Storage Capacity Available Retube Waste Storage and Processing Buildings Shield Tank Overpressure Protection Unit 3 Emergency Service Water Emergency Power Generator 3 Powerhouse Steam Venting System Containment Filter Venting System Shield Tank Overpressure Protection Unit 4 Shield Tank Overpressure Protection Unit 1 Shield Tank Overpressure Protection Unit 2 Mock-Up Training and Tool Testing Retube Tooling Platform #2 Installed Retube Feeder Replacement Class 2 estimate Training Material Complete Tooling Testing and Performance Guarantee Complete Training Readiness Complete for Shutdown Segment * Schedule for Heavy Water (D2O) Storage Capacity when Available for Service under review

16 OPG/Government Joint Objectives for Darlington Refurbishment Provide 30 years of GHG free base-load energy from high performing asset. Minimize ratepayer impact and taxpayer exposure. Support the Ontario nuclear industry, including its supply chain, and grow Ontario s capability to support nuclear industry. Make fact-based decisions as we proceed, to maintain high comfort level that project continues to meet business objectives. Maintain community and stakeholder support with open, transparent reporting and interaction. 16

17 Thank You/Questions?