1 Mario Cavinato On behalf of Antennas and Plasma Engineering group 1

2 Ion Cyclotron Antenna Electron Cyclotron Upper launchers and Ex-Vessel waveguides Plasma Engineering 2

3 Ion Cyclotron Antenna: Component description Faraday screen Internal transmission line Port Plug Radiating element Function Input 20 MW power to the plasma. Concept port-plug base system for final power transmission, radiating elements and plasma facing components to protect from high heat flux. Port plug structure (single and double walled) Removable transmission line Vacuum tight ceramic windows Shimming mechanism to move internal components Faraday Screen (plasma facing) Actively cooled internal shields RF contacts Radiating elements Toolings for partly hand-on maintenance Sensors and instrumentation (in and ex vessel) European Procurement for ITER, M CAVINATO, SOFT2014-Industry Day, 30 Sept

4 Ion Cyclotron Antenna: procurement for short term Task Orders within existing Framework contract RF Window (Material qualification after irradiation) Destructive tests of Faraday screen Engineering support eg. structural analysis European Procurement for ITER, M CAVINATO, SOFT2014-Industry Day, 30 Sept

5 Electron Cyclotron in-vessel & ex-vessel : Component description In-vessel (Launcher) Launcher body In-vessel waveguides Steering mechanisms Mirrors BSM and First Wall Neutron shields Services (coolant, gas) Diagnostics & I&C Ex-vessel waveguides Diamond windows Isolation valves Back-end assembly PHTS in-vessel cooling connections CCWS component cooling services European Procurement for ITER, M CAVINATO, SOFT2014-Industry Day, 30 Sept

6 EC UPPER LAUNCHERS: PROCUREMENT for short term Upcoming activity in 2015 are related to Design, R&D and production of prototypes Design: Task Orders within existing Framework contracts New Framework contract for design of the launcher cooling system (F4E-OFC- 169 under evaluation) R&D and prototypes: Isolation valve prototype Blanket Shield Module prototype and qualification Steering mechanism prototype European Procurement for ITER, M CAVINATO, SOFT2014-Industry Day, 30 Sept

7 Plasma Engineering Procurement Arrangement in negotiation for the design and procurement of: EC plant controller CODAC PSH Parameters and status variables EC Plant Controller Fast protection controller Rearm PIS Slow controller Protection and coordination CIS Fast controller Power generation and distribution Diagnostics PCS SDN Profinet Analog link Digital link PON Fast optical link TCN EC upper launchers Subsystem Control Unit CIN Fast shutdown requests Plant status - state machine Modulation pulse train Real time references and measurements DAN EU Gyrotron Subsystem Control Unit PS set1-12 SCU Gyrotron P1-12 SCU TL SCU Arc detection + Inline switches EL SCU Arc detection + isolation valves UL 1-4 SCU Arc detection + isolation valves (PA strategy still to be confirmed) European Procurement for ITER, M CAVINATO, SOFT2014-Industry Day, 30 Sept

8 EC control: PROCUREMENT for short term Contract for support in EC plant operation (consultancy services) Contract for System Engineering support (consultancy services) Task Orders within existing framework (I&C group) European Procurement for ITER, M CAVINATO, SOFT2014-Industry Day, 30 Sept

9 Plasma engineering: PROCUREMENT for short term Support for the preparation for ITER operation Assessment of the impact of design changes due to design evolution and/or interaction with industry and suppliers Monitoring of interfaces between components via the plasma Evaluation of ADI and PCRs affecting EU procurement and other procurements (focus on interfaces and EU costs impact) Support to Antennas in the field of control system and engineering European Procurement for ITER, M CAVINATO, SOFT2014-Industry Day, 30 Sept

10 Plasma engineering: PROCUREMENT for short term Part of PE activities is difficult to plan because is initiated by: ITER Task Agreements (ITAs) issued by IO either directly to F4E or on a competitive base between DAs (No planning provided by IO) Urgent questions posed by TAP, EU members of STAC or by other F4E groups (related to design changes, PCRs, ) Planned activities in 2015 regard: Heating and Current drive systems operation Engineering support to Antennas Plasma Control and operation European Procurement for ITER, M CAVINATO, SOFT2014-Industry Day, 30 Sept

11 Plasma engineering: PROCUREMENT for short term Framework Contract with a four years duration Scope: Control and System Engineering Plasma physics and tokamak operation LOT 1 Mechanical design LOT 2 The framework will encompass both out-sourcing and in-sourcing schemes European Procurement for ITER, M CAVINATO, SOFT2014-Industry Day, 30 Sept

12 Follow us on: