2016 ANNUAL VRL ANALYSIS

Size: px
Start display at page:

Download "2016 ANNUAL VRL ANALYSIS"

Transcription

1 2016 ANNUAL VRL ANALYSIS Published on 08/01/2016 By Ops Market Support/Forensics Chris Davis Ricky Finkbeiner

2 REVISION HISTORY DATE OR VERSION NUMBER AUTHOR CHANGE DESCRIPTION COMMENTS 7/11/2016 Ricky Finkbeiner First Draft

3 CONTENTS Revision History... i Executive Summary... 1 Recommendations... 2 Background... 3 Analysis of Current VRLs... 5 Binding in the Integrated Marketplace... 6 OC Breach Instances for RTBM... 8 OC Breach Instances for Day Ahead Market Economic and Continuously Breaching Flowgates Sensitivity Analysis Methodology Summary Take-Aways of Sensitivity Analysis Appendix Explanation of M2M breached Intervals Example of VRL Application Binding Breaching Summary Example of Continuously Breaching Flowgate... 30

4 EXECUTIVE SUMMARY This report will provide the annual analysis on the Integrated Marketplace Violation Relaxation Limits (VRLs), including the effectiveness of the VRLs and their values on reliability and pricing, as well as sensitivity analysis with recommendations for changes. The primary focus of the analysis will be on the period July 2015 June VRLs are applied when the shadow price to meet a constraint exceeds the defined Violation Relaxation Limit. The five VRL constraint/categories are Spinning Reserve Requirement Operating Constraint including Manual, Pnode, Watch List, Flowgate, and Real-Time Contingency Analysis (RTCA) constraints Resource Ramp Constraint Global Power Balance Constraint Resource Capacity Constraint The table below shows the summary of VRL instances in the Real-Time Balancing Market (RTBM) and Day Ahead Market (DAMKT) for the SPP Integrated Marketplace. Note that RTBM instances account for a 5-minute interval, DAMKT instances account for a 1-hour interval, and multiple VRL instances can occur per interval if there is more than one constraint with a VRL application in that interval. Analysis in this report will primarily focus on the application of the Operational Constraint VRLs, due to the large number of instances of that category s application. July June 2015 DAY AHEAD July June 2016 July June 2015 REAL-TIME July June 2016 Spinning Reserve Operating Constraint* ,507 40,674 Resource Ramp Constraint Global Power Balance Resource Capacity Constraint *Includes 1,664 M2M Breached instances in first year of data and 12,501 M2M Breached instances in second (recent) year of data. For more details on M2M Breached intervals, refer to the Appendix SPP Annual VRL Analysis 1

5 RECOMMENDATIONS SPP recommends no changes to the VRLs related to Resource Capacity, Power Balance, Ramp, and Spinning Reserve Requirements. These VRLs are employed rarely (if at all) and do not account for a large share of VRL applications in Day Ahead Market and RTBM. Based on the historical data and sensitivity analysis presented in this report, SPP is recommending to set the first VRL block value for Operational Constraints to be equal to $750. This value has been shown through the analysis to provide a better combination of reliability and cost, reducing the number of flowgate breach instances, with only small impacts to system costs. SPP also believes further changes to the Operational Constraint VRLs may be warranted. SPP will continue analysis to identify improvements to reduce the large number of breach instances. Observations: Observations of longer duration events when SPP has a large amount of relief available, yet has to breach in the solution because due to resource shift factors, offer prices, and system pricing, that relief cannot be realized at a shadow price <$500. Changing conditions since these VRL blocks were first set appear to have contributed to the increase in these events, such as o resource fleet (more wind), o gas prices, o o resource offer curves, unit commitment patterns (fewer resources online, requiring relief from resources with lower shift factors). Put more emphasis on solving transmission constraints to the set limit (binding); SPP has observed a substantial rise in breached interval occurrences in the real-time market. This is especially more pertinent with NERC reliability standards addressing facility limits and maintaining System Operating Limits. Bring more transparency to the congestion management process, requiring fewer Effective Limit offsets, which are currently required due to continuously breaching constraints SPP Annual VRL Analysis 2

6 BACKGROUND In certain situations, attempting to enforce all constraints may result in a solution that is not feasible at a Shadow Price less than an appropriately priced VRL. In those cases, SPP will apply the VRLs in the Market Clearing Engine (MCE) solution. VRLs and their associated values are intended to achieve the following objectives: 1. Mitigate the occurrence of price excursions or other extreme prices 2. Remove the portion of a loading violation attributed to market flow on a flowgate within 30 minutes of the start of a VRL violation 3. Mitigate the regulation burden placed on the Resources providing regulation services 4. Limit contribution to CPS violations 5. Minimize the need for Manual Dispatch Instructions. Table 2 contains the current VRL constraints and values currently in place. CONSTRAINT TYPE DESCRIPTION VRL [$/MW] Resource Capacity Global Power Balance Resource Ramp Operating Constraint The minimum and maximum MW dispatchable output of a Resource as indicated in a Resource Offer. Energy needed to balance Resources and load. The ramp capability of a Resource as indicated in the Resource plan. A MW limit that can be imposed on SPP related to MW flow across a market node, a manuallyidentified transmission constraint, a Watch List transmission constraint, a flowgate constraint, or a transmission constraint identified by SPP s real-time contingency analysis. 100,000 50,000 5,000 $500 when the loading is greater than 100% and less than or equal to 101% at each network constraint at each Operating Constraint. $750 when >101% and <= 102% $1,000 when >102% and <= 103% $1,250 when >103% and <= 104% $1,500 when >104% Spinning Reserve Constraint A MW value representing the Spinning Reserve requirement SPP Annual VRL Analysis 3

7 In the Marketplace there also exists unavoidable trade-offs in applying VRLs of the constraint type categories where a higher VRL value is an indication of the relative priority for enforcing the constraint type. The SCED solution for the Day-Ahead and Real-Time interprets: Spinning Reserve Requirement is relaxed before an OC constraint An OC constraint is relaxed before a resource ramp constraint A resource ramp constraint is relaxed before the global power balance constraint The global power balance constraint is relaxed before a resource capacity constraint SPP has requirements to provide (by November 1 st each year) analysis as well as a set of proposed Violation Relaxation Limits ( VRLs ) for review by the applicable working groups and committees as described in the Market Protocols. The report, analysis, sensitivities, and recommendations are due to the appropriate working groups by August 1 st. Sources for these requirements are currently found in Integrated Marketplace Protocols , , SPP Tariff Attachment AE section SPP Annual VRL Analysis 4

8 ANALYSIS OF CURRENT VRLS The following section provides and overview and analysis on the VRL usage in the SPP Integrated Marketplace, focused on Operational Constraint VRLs due to the small usage of the other VRL types. Consideration should be given, when interpreting this data, that SPP added the Integrated Systems to the market footprint as of October 1, So some general increase in congestion would be expected due to managing a larger transmission territory SPP Annual VRL Analysis 5

9 BINDING IN THE INTEGRATED MARKETPLACE The charts below illustrate the relative distribution of the binding constraints in RTBM and Day Ahead Market, grouped by shadow price. Day Ahead Market has a majority of binding occurrences in the $0-$100/MWhr shadow price range, while RTBM has a wider distribution. This is to be expected, as RTBM would have additional price volatility with changing real-time conditions and shorter ramping intervals (five minutes in RTBM versus one hour in Day Ahead Market). Total Binding Instances 200, , ,000 50,000 0 RTBM OC Binding Instances by Shadow Price July June % 11.9% 4.6% 3.1% 2.2% $0 - $100 $100 - $200 $200 - $300 $300 - $400 $ % 80% 60% 40% 20% 0% % OC Total Binding Instances Binding Instances Percentage Total Binding Instances 60,000 50,000 40,000 30,000 20,000 10,000 0 DAMKT OC Binding Instances by Shadow Price July June % 4.4% 0.5% 0.1% 0.0% $0 - $100 $100 - $200 $200 - $300 $300 - $400 $ % 80% 60% 40% 20% 0% % OC Total Binding Instances Binding Instances Percentage 2016 SPP Annual VRL Analysis 6

10 Charts below show the reporting year-to-year changes in binding instances, grouped by shadow price range. Both RTBM and DAMKT saw similar, large increases in binding instances, relative to the previous year, with most of the increase occurring in $0-$100 shadow price ranges. Total Binding Instances 200, , ,000 50,000 0 RTBM OC Binding Instances by Reporting Year $0 - $100 $100 - $200 $200 - $300 $300 - $400 $ Total Binding Instances 60,000 50,000 40,000 30,000 20,000 10,000 0 DAMKT OC Binding Instances by Reporting Year $0 - $100 $100 - $200 $200 - $300 $300 - $400 $ SPP Annual VRL Analysis 7

11 OC BREACH INSTANCES FOR RTBM SPP saw a substantial rise in breached constraint occurrences, in both Day Ahead Market and RTBM. The RTBM breached instances were higher this past year in every category of the percent of limit exceedance. You can see from the second chart that SPP observed a wider range of breached intervals occurring at various percentages of the limit set in RTBM. 36.9% of the breached instances occurred at an overload of 1% or less of the effective limit, which is a drop from the 54% for the same value observed in last year s data. This means that a higher portion of SPP s breached instances occurred at levels >1% of the effective limit, relative to the previous reporting year. OC Breach Instances 12,000 10,000 8,000 6,000 4,000 2,000 0 RTBM Breach Instances by Reporting Year OC Breach Instances 12,000 10,000 8,000 6,000 4,000 2, % RTBM OC Breaches July June % 10.1% 6.9% 7.4% 4.6% 3.7% 3.0% 5.0% 2.4% 2.0% 2.0% 40% 35% 30% 25% 20% 15% 10% 5% 0% % OC Total Breaches OC Breach % Beyond Flowgate Limit 2016 SPP Annual VRL Analysis 8

12 The third chart here splits out the M2M Breaches from the data for both years. This helps isolate the effects seen from breaching constraints due to Market-to-Market logic, where SPP may breach/apply a VRL at a much lower shadow price than the first penalty block of $500. More information on M2M breaches can be found in the appendix. OC Breach Instances 12,000 10,000 8,000 6,000 4,000 2,000 0 RTBM Breach Instances by Reporting Year M2m Breached Intervals 2015 Breached 2016 Breached 2015 M2M Breached 2016 M2M Breached When excluding the M2M breached instances, we still see a noticeable (but smaller) gap across reporting years in the distribution of VRL applications by percentage of the limit overload. The data from the 2015 reporting year showed 56% of breach instances occurring at 1% of less of the limit, while the 2016 reporting year showed 44% of breach instances at the same overloads. Percent OC Breach Instances 60% 50% 40% 30% 20% 10% 0% RTBM Breach Instance Distribution by Reporting Year (excluding M2M Breaches) 56.4% 44.0% SPP Annual VRL Analysis 9

13 OC BREACH INSTANCES FOR DAY AHEAD MARKET SPP saw a substantial jump in breached instances in Day Ahead Market in July 2015-June 2016, relative to the previous year of data. This is a bit misleading, as roughly 90% of the breached instances here were breach instances on phase-shifter constraints, where the MCE could not resolve the phase angle gap due to an outage on the phase shifter (no amount of tap-changing on a phase shifter will converge angles on both sides of it if the phase shifter is out of service). These resulted in no shadow price and no price split-up, so could most likely be omitted from the results. With the exclusion of these phase shifter constraint violations, the total breaches in Day Ahead Market was roughly the same as the previous reporting year % DAMKT OC Breaches July June % OC Breach Instances % 0.4% 0.4% 0.4% 1% or less 1-2% 2-3% 3-4% 4-5% 100% 80% 60% 40% 20% 0% % OC Total Breaches OC Breach % Beyond Flowgate Limit DAMKT Breach Instances by Reporting Year OC Breach Instances % or less 1-2% 2-3% 3-4% 4-5% 15-20% SPP Annual VRL Analysis 10

14 ECONOMIC AND CONTINUOUSLY BREACHING FLOWGATES One trend that has been observed in the past few years of data is the occurrence of continuously breaching flowgates and/or instances where a flowgate breached at the first $500/MWhr penalty block, though there was plenty of relief to bind the flowgate if a higher VRL block was used. To see an example of a continuously breaching constraint, refer to the Appendix. Below is a time-based scatter plot showing all of the occurrences of 6 consecutive breached intervals on a single RTBM constraint. Both the number of occurrences and maximum amount of occurrences has increased slightly since Integrated Marketplace start on 3/1/2014. Consecutive Intervals Breached Instances of >=6 Consecutive RTBM Intervals breached on a Constraint 2016 SPP Annual VRL Analysis 11

15 One of the reasons for this increase has been instances where a flowgate breached at the first $500/MWhr penalty block, though there was plenty of relief to bind the flowgate if a higher VRL block was used. These are referred to here as economic breaches. This data is difficult to separate out without re-running all market solutions, but below is an attempt to show these occurrences. These are the times when there was a breached flowgate in RTBM and there was either Not enough relief at shadow prices <$1,500/MWhr meaning we would not be able to redispatch to bind this flowgate within the 5-minute RTBM interval Enough relief available at shadow prices <$1,500/MWhr meaning we breached the flowgate s limit in RTBM, but there was enough redispatch capability present to bind the flowgate if we allowed the constraint to increase to a shadow price of $1,500/MWhr. Again, these are difficult to truly separate out without rerunning the entire year of RTBM solutions (due to the impact of reserve requirements and competing constraints). There are some times where it may appear we have enough rampable relief to resolve the constraint, but another constraint may be locking up relief MWs or we may be using that capacity for regulation or contingency reserve. However, observations have been that those complicating factors only have an impact on a smaller number of instances. Instances Reporting Year Breakdown of Instaces of "Economic" Breaches 20,000 14,866 15,000 10,799 10,339 10,000 5,760 5,000 0 Breach Instances where there is not enough relief at shadow prices <$1,500 Breach Instances where there is enough relief available to solve the constraint at shadow prices <$1, SPP Annual VRL Analysis 12

16 Finally, here is a breakdown (by constraint) of the last two years of data (July 2014 June 2016) with an attempt to separate out the economic breaches, showing the top 20 breached constraints in RTBM for those two years. You can see some of the most breached flowgates have this problem, where there is enough relief to resolve the flowgate loading with shadow prices less than the maximum VRL, but we breach due to not being able to bind at shadow prices >$500/MWhr. There are also other constraints (FG3-FG7) that see relatively few instances of this situation, and we primarily breach on those flowgates due to not having enough dispatchable relief to solve the flowgate. Constraint Breakdown of Instances of "Economic" Breaches 4,000 Enough relief available to solve the constraint at shadow prices <$1,500 Not enough relief at shadow prices <$1,500 3,500 3,000 2,500 2,000 1,500 1, SPP Annual VRL Analysis 13

17 The data in this section, along with the sensitivity analysis in the next section, are drivers for the recommendation to change the implementation of the VRL blocks to bind these flowgates more often. Here are some options that have been considered: Implement a time function in the VRL blocks such that a constraint will using increasing higher VRL blocks the longer it has been breaching the limit, up until it reaches the maximum VRL block of $1,500/MWhr. Make VRL blocks configurable by flowgate, so that with analysis, SPP could select flowgates to start at a higher base VRL block, when conditions and data show that binding is rarely possible except at shadow prices between $500 and $1,500. Implement higher base/starting VRL blocks for lower voltage facilities. An example would be to remove the first two VRL blocks for sub-200kv facilities, so that those flowgates will relax to >100% and <=101% of the limit with shadow prices in excess of $1,000, relax to >101% and <=102% with shadow prices in excess of $1,250, and relax to >102% with shadow prices in excess of $1, SPP Annual VRL Analysis 14

18 SENSITIVITY ANALYSIS METHODOLOGY SPP ran a large sensitivity analysis on the impact of changing the Operational Constraint VRL values. The intervals analyzed included 6 scenarios on >20,000 RTBM intervals (>120,000 RTBM solutions total) o The base solutions used were direct re-runs of Approved SPP RTBM studies from March June 2016 (includes IS entities) Load ranging from ~20 GW to ~48 GW Wind ranging ~200 MW to ~11,000 MW, including peak wind penetration of 49.2% Net interchange ranging between +/- 1,600 MW The sensitivities performed were 5 additional scenarios (from base) where the VRL values were scaled up at each block percentage value, so that each block was increased another 20% from the base VRLs. Here are what the final scenario VRL blocks looked like: o o o o o o Base VRL blocks ranging $500-$1,500 with $250 steps Scenario #1 VRL blocks ranging $600-$1,800 with $300 steps Scenario #2 VRL blocks ranging $700-$2,100 with $350 steps Scenario #3 VRL blocks ranging $800-$2,400 with $400 steps Scenario #4 VRL blocks ranging $900-$2,700 with $450 steps Scenario #5 VRL blocks ranging $1,000-$3,000 with $500 steps These VRL changes were the only input changes to the cases. $4,000 Sensitivity Analysis VRL blocks Base ($500 first block) Scen. 2 ($700 first block) Scen. 4 ($900 first block) Scen. 1 ($600 first block) Scen. 3 ($800 first block) Scen. 5 ($1000 first block) VRL Value $3,000 $2,000 $1,000 $0 99% 100% 101% 102% 103% 104% 105% 106% % Constraint Flow 2016 SPP Annual VRL Analysis 15

19 SUMMARY Summary results are presented below. Unless otherwise indicated, M2M breached instances are omitted from these results, as they are not considered truly breached intervals. See the Appendix for a description of M2M breached instances. Since these re-run scenarios had only one change (the increased VRL blocks), the results should be understood in the context of that. This means for example, that Effective Limits on the constraints were not adjusted in the re-run scenarios. This is important when considering constraints that continuously breached at % of the Effective Limit in the original RTBM. In these instances, the effective limit had already been lowered in the base solution to account for the breaching constraint, with the offset necessary to ensure real-time flowgate flow did not exceed its limit. If VRL blocks are increased, then the Effective Limit could be increased again, so that we are binding the RTBM flow of the constraint at the correct limit, rather than needing an offset built in. See the Appendix for details. So for these scenarios, even though it may show that system costs increase with the increased VRL block, in practice this would be paired with an increase in the Effective Limit, which would reduce the constraints on the system. Increasing the VRL blocks did result in a decrease in the number of Breached instances, with a drop of almost 30% in breached occurrences between the base set of VRLs ($500) and the scenario with the highest base VRL ($1,000). A majority of the reduction in breached instances occurred with the first 2-3 scenarios where the first VRL block ranged from $600 to $800. It can also be noted that there was a slight reduction in the total number of congested (Binding and Breached) instances, for a drop of approximately 0.5%. Constraint-Intervals of Congestion $1, First Penalty Value $900 $800 $700 $ $500 base ,000 20,000 30,000 40,000 50,000 60,000 Binding Breached 2016 SPP Annual VRL Analysis 16

20 Increasing the VRL blocks also resulted in a slight increase in the average Marginal Energy Cost (up $0.45) in the solutions, as well as the average operating cost (up $21). This is due to tradeoffs between Energy and Ancillary Service clearing and congestion impacts for resources. The Marginal Energy Cost and congestion costs are not completely independent, so allowing the solution to redispatch further (with higher VRL blocks) can result in an increase in MEC. Additionally, the average Minimum and Maximum LMPs for the solutions were spread out more. This is also expected, due to allowing the system to redispatch to a greater extent to bind on the flowgate, rather than relaxing at the lower base VRL of $500. RTBM averages, by scenario MEC Min LMP Max LMP Operating Cost $200 $25,080 $150 $25,060 LMPs and MECs $100 $50 $0 $19.15 $19.20 $19.28 $19.36 $19.42 $19.60 $25,040 $25,020 $25,000 Operating Cost -$50 $24,980 -$100 $500 base $600 $700 $800 $900 $1,000 $24,960 First VRL Penalty Value 2016 SPP Annual VRL Analysis 17

21 Similar effects were seen in the Ancillary Services, where there were typically increases in the Marginal Clearing Price (MCP) of the Regulation and Contingency Reserve products as the base VRL was increased. The change was most evident in the Regulation Up Product, which saw an increase of $0.41 from the current $500 base VRL blocks to the final scenario with $1,000 base VRL blocks. This is in line with the same increase observed in the MEC. There were also more shortage intervals for the AS products (though no additional OR shortages). Most of the increased shortages occurred with the final two scenarios that had $900 and $1,000 as their starting VRL block. Average Product MCPs $500 base $600 $700 $800 $900 $1,000 Average MCP $8 $7 $6 $5 $4 $3 $2 $1 $0 $6.80 $6.13 $6.24 $6.39 $3.61 $3.71 $0.75 $0.74 Reg Down Reg Up Spin Supp Intervals with Product Shortage First VRL Penalty Value $1,000 $900 $800 $700 $600 $500 base OR Scarce AS Up Scarce AS Down Scarce 2016 SPP Annual VRL Analysis 18

22 When the constraints are separated out by the kv level of the monitored element (low-side kv is used for transformer constraints), the benefits are shown to mostly impact the lower voltage facilities, 115kV, 138kV, and to a lesser extent, 161kV. This again matches specific observations and general expectations, due to the shadow price being a function of shift factors on the constraint. Resources tend to have lower magnitude shift factors on the lower-voltage facilities, so this can drive the shadow prices up on these constraints high enough that a true binding level may not be achievable with a shadow price less than the first VRL block of $500. Much of the reduction in breached occurrences occurs with the increase of the base VRL block by only $100 or $200. Flowgate Breaches by Monitored Element kv Level $1,000 $900 $800 $700 $600 $500 base kv level of Monitored Element 345 kv 230 kv 161 kv 138 kv 115 kv # of Flowgate Breach Instances Based on the equation for the Marginal Congestion Component of the LMP, a larger shadow price is required to move LMP up by the same amount if the shift factor is reduced. In the example below, we reduce the shift factor by 50% to show the required shadow price increase to maintain an MCC/LMP comparable to the first scenario. In this example, the MCC needs to be $24 to move the resource. It starts with a shift factor of -8% (increment resource), so only a $-300 shadow price is required. When the shift factor is reduced to 4%, the shadow price magnitude has to be doubled to $-600 to get the MCC back to $24. MMMMMM ii,ffff = SSSS FFFF GGGGGG ii,ffff Scenario 1 (shift factor 8%): $24 = ($ 300) ( 8%) Scenario 2 (shift factor 4%): $24 = ($ 600) ( 4%) 2016 SPP Annual VRL Analysis 19

23 As a continuation from the previous section, here is a further breakdown on the effects of increasing the VRLs on just the 138kV flowgates that experienced more than two hours of breached intervals in the base (approved RTBM) data. The names of the flowgates were removed, but the large gap in breach instances between the base VRL blocks and the scenario VRL blocks is not evident on all flowgates. For example, Flowgate1 saw an almost 90% reduction in breached instances (from base) when the base shadow price was increased to $700/MWhr. On the other hand, constraints like Flowgate7 and Flowgate9 saw little to no improvement in the breached instances at the various VRL scenarios. So for operational control of the constraints, increasing the VRL blocks would provide much more benefit for Flowgate1 than Flowgate9. Increasing the VRL blocks on Flowgate9 does not reduce the breached instances, but only serves to increase the price split-up capability across the constraint. Flowgate Breaches by Scenario (138kV flowgates) kv level of Monitored Element Flowgate11 Flowgate10 Flowgate9 Flowgate8 Flowgate7 Flowgate6 Flowgate5 Flowgate4 Flowgate3 Flowgate2 Flowgate # of Flowgate Breach Instances 2016 SPP Annual VRL Analysis 20

24 Here we look at the results of the sensitivity analysis, distributed by Net Load level. Net Load is calculated as the non-wind generation obligation (Load+NSI-Wind). For this chart, note that many of the reduced constraint breach instances occur in the first two scenarios, where the starting VRL blocks are increased only $100 or $200. Flowgate Breach Instances by Net Load Level $500 base $600 $700 $800 $900 $1,000 Flowgate Breach Instances Net Load Level This is a similar look at the same data from above, this time showing the results as a percentage reduction in breached instances from the current/base VRL blocks. This is to attempt to illustrate any relationship between the VRL improvements and the system s net load level. On the whole, the relationship is not too strong on one side or the other, and there may not be enough data to draw conclusions about the net load levels above 40,000. % Reduction in Breaches 50% 40% 30% 20% 10% 0% % Reduction in Flowgate Breaches (from base $500 VRL scenario) by Net Load Level $600 $700 $800 $900 $1,000 Net Load Level 2016 SPP Annual VRL Analysis 21

25 TAKE-AWAYS OF SENSITIVITY ANALYSIS To summarize the data and results presented in this section: Raising the VRL values did result in a reduction in breached occurrences, and thus increased the amount of time flowgates were under control within their limit. This relationship was strongest with the lower voltage facilities (115kV, 138kV, and to a lesser extent 161kV). However, the benefit was not seen uniformly across all flowgates at each voltage level (i.e. some 138kV flowgates saw a drastic reduction in breached intervals with higher VRLs while other 138kV flowgates saw no reduction in breached intervals). Raising the VRL values did increase overall production costs and system prices slightly, as well as contribute to a handful more ancillary service shortages. This is expected to some extent, but the results have to be understood in their context: that effective limits were not adjusted in these solutions and probably could have been raised (which would drop costs and prices) quite often in the sensitivity analysis due to actually being able to bind to the effective limit. The sensitivities with VRL values starting at $700 and $800 appeared to perform the best, with respect to reducing the number of breached instances while also minimizing price spikes and increases to system costs SPP Annual VRL Analysis 22

26 APPENDIX EXPLANATION OF M2M BREACHED INTERVALS M2M breaches are times when the constraint was reported as Breached in the solution, but the Penalty value it breached at was less than $500 (which is currently SPP s first VRL block). These instances are part of the design of Market-to-Market (M2M) flowgate coordination. When SPP is the Non-Monitoring RTO (NMRTO) on an M2M flowgate, the maximum shadow price that SPP will use in achieving its relief on the constraint is the shadow price of the Monitoring RTO (MRTO) of the constraint. An explanation of this logic is contained in Section 3.1 and Section 7 of the MISO-SPP Joint Operating Agreement, Attachment 2. In normal M2M flowgate coordination, when the Monitoring RTO is congested on its flowgate, it will calculate a relief request to send to the NMRTO in real-time. The NMRTO is to activate this constraint in its dispatch system to meet the relief request until either of these conditions is met: The Non-Monitoring RTO has provided the relief requested by the Monitoring RTO. The Non-Monitoring RTO has provided relief at a cost as high as the current shadow price from the Monitoring RTO. So in the case where SPP is the NMRTO and the MRTO has the flowgate under control at a low shadow price (such as $-30), the MRTO will send a relief request amount to SPP and SPP will attempt to bind to meet the relief request. The shadow price of the MRTO will replace the VRL blocks of SPP, such that $-30 is the largest magnitude shadow price SPP can be constrained on before it relaxes the constraint limit in its solution. If SPP is able to meet the relief request at shadow price magnitude less than that of the MRTO, then the constraint is reported as Binding in SPP s RTBM solution. However, when the MRTO has a low shadow prices (such as the $-30), SPP may not be able to bind to meet the relief request and the constraint will be reported as Breached in SPP s RTBM solution. The Breach events are not the same as a typical interval Breached constraint for SPP, so it creates a reporting/consistency issue. In order to help mitigate this, we consider those constraints where SPP is breaching a flowgate in RTBM at a Penalty Value less than SPP s first VRL block ($500), to be M2M breached and those instances are excluded from most analysis on breached intervals in RTBM SPP Annual VRL Analysis 23

27 EXAMPLE OF VRL APPLICATION Below is a walkthrough, explaining on a simple, loss-less system with one constraint, how the VRL is applied in the RTBM solution. The example has No losses, so there is no Marginal Loss Component to the LMP One constraint binding (this simplifies math and the example, so we do not have to demonstrate the impact of competing constraints) Abundant resources to replace generation for Energy purposes, so any redispatch does not result in a significant change in the Marginal Energy Cost of $ Four resources, with shift factors and offers like RESOURCE SHIFT FACTOR* MARGINAL OFFER COST A -6% $65/MWh B -6% $20/MWh C 8% $0/MWh D 8% $-30/MWh *Note that a positive shift factor means increasing the resource s generation will increase constraint flow and a negative shift factor means increasing the resource s generation will decrease constraint flow. These values are plotted on the graph below SPP Annual VRL Analysis 24

28 In this lossless, single constraint system, the congestion on the flow can be shown as causing a shadow price represented by the black dotted line. The slope of this path is linear, following the base equation of LLLLLL ii,ffff = SSSS FFFF GGGGGG ii,ffff + MMMMMM Note this is the standard equation for a line, where The slope of the line is SP FG, the shadow price of the flowgate constraint (FG) The x value is GSFi,FG, the shift factor of generator at location i on constraint FG The y-intercept is MEC, the Marginal Energy Cost in the solution The y-value is LMP i, the Locational Marginal Price for location i Note the portion of the right-hand-side of the equation SP FG * GSFi,FG, is actually the MCC, the Marginal Congestion Component of the LMP due to constraint FG In the case of an unconstrained system, it looks like the chart below. The shadow price of the constraint is $0 (flat line). Resource B, C, and D all have offer prices less than the Marginal Energy Cost, so they will be dispatched up. Resource A has an offer price greater than the Marginal Energy Cost, so it will be dispatched down SPP Annual VRL Analysis 25

29 The congestion impacts on the resource and shadow prices of the constraint can be visualized in the next steps by assuming the shadow price line to pivot clock-wise around the MEC (shown by the red arrows. The shaded regions of the chart represent Gray Binding: The constraint is binding in this range, with a slope/shadow price <$500. Resources with shift factor/offer prices in this region can be dispatched for this flowgate and the flowgate will still bind. Yellow Breached: This is the first VRL block, covering shadow prices between $500 and $750. In order to move resources in this shaded region, we will have to exceed the $500 shadow price and relax the constraint limit above 100% to no more than 101% Orange Breached: Second VRL block, covering shadow prices between $750 and $1,000. We will have to relax the constraint limit to >101% and <=102% to move resources here. Red Breached: Third VRL block, covering shadow prices between $1,000 and $1,250. We will have to relax the constraint limit to >102% and <=103% to move resources here. Maroon Breached: Fourth VRL block, covering shadow prices between $1,250 and $1,500. We will have to relax the constraint limit to >103% and <=104% to move resources here. Purple/hatched Breached: Last VRL block, covering shadow prices above $1,500. We cannot dispatch resources in this range for this constraint SPP Annual VRL Analysis 26

30 BINDING During times of congestion, the shadow price line can begin pivoting around the MEC. In the example below, the constraint is binding with a shadow price of $-307. Resource A would still not be dispatched up in this case, because although it has increment relief available (negative shift factor), its offer price is too high to be moved up with only a $-307 constraint shadow price. Resource B was already economic for energy and provides increment relief for this flowgate, so it is already dispatched up, regardless of the constraint. Resource C is marginal for this constraint (highlighted green), as the congestion drove their LMP low enough to hit its marginal cost of $0. Resource C s LMP can be calculated as LLLLLL CC,FFFF = SSSS FFFF GGGGGG CC,FFFF + MMMMMM LLLLLL CC,FFFF = ($ )(0.08) + $ LLLLLL CC,FFFF = $0 Resource D would still be dispatched up in this case, because although it has decrement relief available (positive shift factor), its offer price is too low to be moved down with only a $-307 constraint shadow price SPP Annual VRL Analysis 27

31 BREACHING During times of even higher congestion, we may run out of relief from those resources in the binding (gray) region. In the example below, we are breaching to a $-682 shadow price because the constraint requires more flow relief than can be provided by Resources B and C alone. Resource A is dispatched up in this scenario, due to the constraint increasing the MCC (and thus LMP) enough to overcome its high offer price of $65. Resource B was already economic for energy and provides increment relief for this flowgate, so it is already dispatched up, regardless of the constraint. Resource C is dispatched down in this scenario, due to the constraint decreasing the MCC (and thus LMP) enough to overcome its low offer price of $0. Resource D is marginal for this constraint (highlighted green), as the congestion drove their LMP low enough to hit its marginal cost of $-30. Resource D s LMP can be calculated as LLLLLL DD,FFFF = SSSS FFFF GGGGGG DD,FFFF + MMMMMM LLLLLL DD,FFFF = ($ )(0.08) + $ LLLLLL DD,FFFF = $ SPP Annual VRL Analysis 28

32 SUMMARY The key takeaways from these examples are that the MEC, resource shift factors and resource offer prices can play a significant role in the shadow price needed to resolve a constraint. At some MEC/resource combinations (such as if resource B and C were out of dispatchable relief), the only options for relieve may come after the shadow price has increased into the VRL ranges. Just looking at Resource C, the following effects could be understood: If Resource C reduced its offer (moving down on chart), it would take larger magnitude shadow prices to dispatch the resource down for congestion, and potentially even require entering a VRL block before the resource is dispatched. If Resource C increased its offer price, it would get dispatched down sooner, with lower magnitude shadow prices. If Resource C s shift factor were to decrease, it would take a larger magnitude shadow price to dispatch the resource down for congestion, and potentially even require entering a VRL block before the resource is dispatched down. If its shift factor were to increase, it would get dispatched down sooner, with lower magnitude shadow prices. If the Marginal Energy Cost (pivot point) were to increase, it would take larger magnitude shadow prices to dispatch the resource down for congestion, and potentially even require entering a VRL block before the resource is dispatched. If the Marginal Energy Cost decreased, the resource would get dispatched down sooner, with lower magnitude shadow prices SPP Annual VRL Analysis 29

33 EXAMPLE OF CONTINUOUSLY BREACHING FLOWGATE The chart below illustrates a real-time example of a flowgate that was under control, but breached continuously above the Effective Limit set in the RTBM solution. This was due to the combination of marginal resource offers, shift factors, and energy costs at the time, which required a shadow price around $-600 for most of the day in order to redispatch generation on the system. For this purpose, the original flow in the RTBM solution was relaxed to 101% of the Effective Limit, based on current SPP VRL blocks. In order to maintain real-time flowgate flow under the flowgate limit (SOL) when the flowgate breaches the Effective Limit to 101%, the Effective Limit has to be set lower. When the sensitivity analysis was run which increased the VRL blocks to start at $800, it resulted in almost exactly the same shadow prices on the constraint, but solving in a Binding state. This is because the shadow price required to maintain control of the flowgate was less than the first VRL block of $800. In that scenario, the Effective Limit could be raised in the RTBM solution, because an offset is no longer required, now that the RTBM flow is solving to the limit set for it. Real-Time Flowgate Comparison (Original VRL blocks w/ $500 Base vs Test w/ $800 Base VRLs) FG Flow FG Limit (SOL) Effective Limit Original RTBM Flow Test RTBM Flow Original Shadow Price Test Shadow Price 125 $0 Flowgate Flow $100 -$200 -$300 -$400 -$500 -$600 -$700 Shadow Price 2016 SPP Annual VRL Analysis 30

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations Technical Bulletin 2009-06-03 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations June 15, 2009 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

More information

Transmission Constraint Relaxation Parameter Revision ISO Straw Proposal

Transmission Constraint Relaxation Parameter Revision ISO Straw Proposal Transmission Constraint Relaxation Parameter Revision ISO Straw Proposal October 18, 2012 Prepared by: Market and Infrastructure Development Version: 1.0 California Independent System Operator Contents

More information

MISO-PJM Interface Pricing Post Implementation Metrics and Criteria

MISO-PJM Interface Pricing Post Implementation Metrics and Criteria MISO-PJM Interface Pricing Post Implementation Metrics and Criteria Contents 1 Introduction... 2 2 Real-Time Market Interchange Price Signal Effectiveness Metrics... 2 2.1 Post Implementation Pricing Monitoring

More information

Managing Flexibility in MISO Markets

Managing Flexibility in MISO Markets Managing Flexibility in MISO Markets Clean Energy Regulatory Forum November 9, 2012 Outline Impacts of Variable Generation on Ancillary Services Dispatchable Intermittent Resources Introduction to Proposed

More information

Stepped Constraint Parameters. Issue Paper

Stepped Constraint Parameters. Issue Paper Stepped Constraint Parameters May 5, 2016 Table of Contents 1. Introduction... 3 2. Plan for Stakeholder Engagement... 4 3. Transmission constraint relaxation parameter... 5 4. Shift factor effectiveness

More information

Dispatch Signal & Locational Marginal Pricing (LMP)

Dispatch Signal & Locational Marginal Pricing (LMP) Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. PJM 2017 Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP PJM 2017 2 Dispatch Rate Definition:

More information

Interface Pricing Approach Whitepaper May 2015

Interface Pricing Approach Whitepaper May 2015 Interface Pricing Approach Whitepaper May 2015 This white paper represents MISO's current progress and assessment on the Interface Pricing issue. Additional analysis is underway and will be shared with

More information

Price Formation Education Session Day 1 Economic Dispatch

Price Formation Education Session Day 1 Economic Dispatch Slide 1 Price Formation Education Session Day 1 Economic Dispatch Anthony Giacomoni Melissa Maxwell Laura Walter December 4, 2017 Slide 2 Disclaimer Slide This is not a committee meeting. This session

More information

Dispatch Signal & Locational Marginal Pricing (LMP)

Dispatch Signal & Locational Marginal Pricing (LMP) Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP Dispatch Rate Economic control signal

More information

NYISO/PJM Market-to-Market Coordination

NYISO/PJM Market-to-Market Coordination NYISO/PJM Market-to-Market Coordination Joint Stakeholders Meeting July 21, 2011 / Rensselaer, NY Agenda Joint Operating Agreement (JOA) Overview Project Timeline & Progress Report Key Concepts Real-Time

More information

Coordination with PJM

Coordination with PJM Market-to-Market Coordination with PJM Mike DeSocio Market Product Specialist New York Independent System Operator MIWG October 27, 2011 Rensselaer, New York Agenda M2M and NYISO Markets Examples Tariff

More information

RTO Overview and Day 2 Markets. EAI Technical Conference May 26, 2011

RTO Overview and Day 2 Markets. EAI Technical Conference May 26, 2011 RTO Overview and Day 2 Markets EAI Technical Conference May 26, 2011 1 Agenda RTO Day 2 markets and Locational Marginal Pricing (LMP) Why RTO Day 2 markets may benefit Entergy s customers Quantifiable

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 27 CAISO Markets And Processes... 2 27.1 LMPs And Ancillary Services Marginal Prices... 2 27.1.1 Locational Marginal Prices For Energy... 3 27.1.2 Ancillary Service Prices... 4 27.1.3

More information

Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation

Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation MRTU Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation CRR Educational Class #2 CAISO Market Operations Why are LMPs important to the CRR Allocation & Settlement Process The CRR revenue

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 34. Real-Time Market... 3 34.1 Inputs To The Real-Time Market... 3 34.1.1 Day-Ahead Market Results as Inputs to the Real-Time Market... 3 34.1.2 Market Model and System Information...

More information

Opportunity Cost of Flexible Ramping Constraint. Draft Final Proposal

Opportunity Cost of Flexible Ramping Constraint. Draft Final Proposal Opportunity Cost of Flexible Ramping Constraint Draft Final Proposal July 20, 2011 Opportunity Cost of Flexible Ramping Constraint Draft Final Proposal Table of Contents 1 Introduction... 3 2 Changes from

More information

Joint and Common Market ITEM 4 PSEUDO TIES

Joint and Common Market ITEM 4 PSEUDO TIES Joint and Common Market ITEM 4 PSEUDO TIES Agenda 1. Overview 2. Background 3. PJM Update 4. MISO Update 5. Congestion Overlap Solution 6. Next Steps 2 Overview Purpose Provide a status update on MISO-PJM

More information

IMM Quarterly Report: Fall 2017

IMM Quarterly Report: Fall 2017 IMM Quarterly Report: Fall 2017 MISO Independent Market Monitor David Patton, Ph.D. Potomac Economics December 5, 2017 Highlights and Findings: Fall 2017 The MISO markets performed competitively this fall,

More information

Constraint Specific Transmission Shortage Pricing. Study Approach

Constraint Specific Transmission Shortage Pricing. Study Approach Constraint Specific Transmission Shortage Pricing Study Approach Jennifer Boyle Energy Market Design MIWG April 10, 2018, Krey Corporate Center Today s Agenda Project Plan/Deliverables Scope of Study Proposed

More information

Joint and Common Market PSEUDO TIE UPDATE AUGUST 22, 2017

Joint and Common Market PSEUDO TIE UPDATE AUGUST 22, 2017 Joint and Common Market PSEUDO TIE UPDATE AUGUST 22, 2017 Agenda 1. Overview 2. MISO Update 3. PJM Update 4. JOA Changes Joint Filing 5. Congestion Overlap 6. Next Steps Appendix 2 Overview Purpose Provide

More information

Price Formation Education 4: Shortage Pricing and Operating Reserve Demand Curve

Price Formation Education 4: Shortage Pricing and Operating Reserve Demand Curve Price Formation Education 4: Shortage Pricing and Operating Reserve Demand Curve Patricio Rocha Garrido Lisa Morelli Laura Walter Disclaimer This is not a committee meeting. This session is for educational

More information

2. Market Operations Overview

2. Market Operations Overview 2. Market Operations Overview 2.5 Market Information This section summarizes and describes the common information that is used by the Day-Ahead and Real-Time processes. 2.5.1 Resource Static Data Static

More information

California ISO. Q Report on Market Issues and Performance. July 10, Prepared by: Department of Market Monitoring

California ISO. Q Report on Market Issues and Performance. July 10, Prepared by: Department of Market Monitoring California Independent System Operator Corporation California ISO Q1 2017 Report on Market Issues and Performance July 10, 2017 Prepared by: Department of Market Monitoring TABLE OF CONTENTS Executive

More information

Power System Economics and Market Modeling

Power System Economics and Market Modeling Power System Economics and Market Modeling 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com PowerWorld Simulator OPF and Locational Marginal

More information

California ISO. Q Report on Market Issues and Performance. February 10, Prepared by: Department of Market Monitoring

California ISO. Q Report on Market Issues and Performance. February 10, Prepared by: Department of Market Monitoring California Independent System Operator Corporation California ISO Q4 2013 Report on Market Issues and Performance February 10, 2014 Prepared by: Department of Market Monitoring Department of Market Monitoring

More information

Single Schedule Market Pricing Issues

Single Schedule Market Pricing Issues Single Schedule Market Pricing Issues Presented by Scott Harvey and Susan Pope Phase 1 - Session 3 Module G: Market Power Mitigation June 29, 2017 Toronto, Ontario TOPICS June 2: Module A: Energy Pricing

More information

3. Overview of Market Instruments

3. Overview of Market Instruments 3. Overview of Market Instruments 3.2 Ancillary Services Bids Four types of Ancillary Services are used by CAISO in its markets Regulation Up, Regulation Down, Spinning Reserve, and Non-Spinning Reserve.

More information

Exhibit A. Reliability Standards Proposed for Approval

Exhibit A. Reliability Standards Proposed for Approval Exhibit A Reliability Standards Proposed for Approval Proposed New Standard IRO-006-5 Standard IRO-006-5 Reliability Coordination Transmission Loading Relief A. Introduction 1. Title: Reliability Coordination

More information

NERC Reliability Functional Model Technical Document Version 5

NERC Reliability Functional Model Technical Document Version 5 Reliability Functional Model Technical Document Version 5 Prepared by the Functional Model Working Group This document is a companion to Version 5 of the Functional Model. It provides context, explanations,

More information

MISO ELMP. Goals & Experience. Jeff Bladen Executive Director, Market Development

MISO ELMP. Goals & Experience. Jeff Bladen Executive Director, Market Development MISO ELMP Goals & Experience Jeff Bladen Executive Director, Market Development HARVARD ELECTRICITY POLICY GROUP EIGHTY-NINTH PLENARY SESSION JANUARY 25-26, 2018 1 MISO saw gaps with legacy LMP market

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission

More information

FirstEnergy Solutions Energy Market Update AEE Meeting March 20, John Ogurchak PE/CEM Manager, Commercial/Industrial Energy Sales

FirstEnergy Solutions Energy Market Update AEE Meeting March 20, John Ogurchak PE/CEM Manager, Commercial/Industrial Energy Sales FirstEnergy Solutions Energy Market Update AEE Meeting John Ogurchak PE/CEM Manager, Commercial/Industrial Energy Sales FirstEnergy Solutions Corp. (FES) Retail subsidiary of FirstEnergy Corp. and headquartered

More information

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal September 8, 2015 Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal Table of Contents 1 Introduction... 3

More information

Contingency Modeling Enhancements Issue Paper

Contingency Modeling Enhancements Issue Paper Contingency Modeling Enhancements Issue Paper March 11, 2013 California ISO Contingency Modeling Enhancements Issue Paper Table of Contents I. Executive Summary... 3 II. Plan for Stakeholder Engagement...

More information

Pivotal Supplier Analysis Internal Interfaces

Pivotal Supplier Analysis Internal Interfaces Pivotal Supplier Analysis Internal Interfaces FERC June 23, 2005 Market Monitoring Unit Local Markets In an LMP-based market, constraints create smaller, local markets with different structural characteristics

More information

Self-Schedules Bid Cost Recovery Allocation and Lower Bid Floor

Self-Schedules Bid Cost Recovery Allocation and Lower Bid Floor Summary Self-Schedules Bid Cost Recovery Allocation and Lower Bid Floor Draft Final Proposal Comments by Department of Market Monitoring August 23, 2016 The ISO proposal to lower the energy bid floor from

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 34. Real-Time Market... 2 34.1 Inputs To The Real-Time Market... 3 34.2 Real-Time Unit Commitment... 3 34.2.1 Commitment Of Fast Start And Short Start Units... 4 34.2.2 Real-Time Ancillary

More information

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

the Real-Time Market will be based on the system marginal costs produced by the Real-Time 17.1 LBMP Calculation The Locational Based Marginal Prices ( LBMPs or prices ) for Suppliers and Loads in the Real-Time Market will be based on the system marginal costs produced by the Real-Time Dispatch

More information

Opinion on Reserve Scarcity Pricing Design

Opinion on Reserve Scarcity Pricing Design Opinion on Reserve Scarcity Pricing Design by Frank A. Wolak, Chairman James Bushnell, Member Benjamin F. Hobbs, Member Market Surveillance Committee of the California ISO November 26, 2009 Executive Summary

More information

Congestion Revenue Rights

Congestion Revenue Rights Congestion Revenue Rights CRR Basics for Market Redesign and Technologies Upgrade (MRTU) Presentation #2 Roger Treinen June 7 th and 8 th 2007 Congestion Revenue Rights Training This non-hands-on training

More information

Pricing Enhancements Issue Paper and Straw Proposal

Pricing Enhancements Issue Paper and Straw Proposal Pricing Enhancements Issue Paper and Straw Proposal Guillermo Bautista Alderete, Ph.D. Manager, Market Validation and Quality Analysis July 10, 2014 ISO Stakeholder Initiative Process POLICY AND PLAN DEVELOPMENT

More information

Industry Perspectives on FERC Standard Market Design

Industry Perspectives on FERC Standard Market Design Industry Perspectives on FERC Standard Market Design By Dr. Roberto F. Paliza Midwest Independent Transmission System Operator, Inc. IEEE Summer Meeting July 23, 2002 Chicago, IL Overview MISO Markets

More information

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

the Real-Time Market will be based on the system marginal costs produced by the Real-Time 17.1 LBMP Calculation The Locational Based Marginal Prices ( LBMPs or prices ) for Suppliers and Loads in the Real-Time Market will be based on the system marginal costs produced by the Real-Time Dispatch

More information

Energy Imbalance Market Year 1 Enhancements

Energy Imbalance Market Year 1 Enhancements Energy Imbalance Market Year 1 Enhancements Don Tretheway Lead Market Design and Regulatory Policy Developer February 18, 2015 Agenda Time Topic Presenter 10:00 10:15 Introduction Kristina Osborne 10:15

More information

Market Trials Structured/Unstructured Test Scenario Detail: 16.2 RUC Offer Curve Subject to Mitigation

Market Trials Structured/Unstructured Test Scenario Detail: 16.2 RUC Offer Curve Subject to Mitigation Market Trials Structured/Unstructured Test Scenario Detail: 16.2 RUC Offer Curve Subject to Mitigation Revision History Date or Version Number 1.0 July 1, 2013 1.1 July 24, 2013 Author Change Description

More information

FINAL REPORT PHASE IV MARKET TRIALS

FINAL REPORT PHASE IV MARKET TRIALS October 26, 1999 FINAL REPORT PHASE IV MARKET TRIALS Scott M. Harvey, William W. Hogan, Susan L. Pope, Andrew Hartshorn and Kurt Zala EXECUTIVE SUMMARY On behalf of the Member Systems of the New York Power

More information

Coordination of MRN-NEEM Modeling and High Level Transmission Analysis in Task 5

Coordination of MRN-NEEM Modeling and High Level Transmission Analysis in Task 5 Coordination of MRN-NEEM Modeling and High Level Transmission Analysis in Task 5 December 30 Revision of the presentation at Macro Future Workshop November 8-9, 2010 Project Objectives Phase I The Roll-Up

More information

U. S. SPOT MARKET REGULATION

U. S. SPOT MARKET REGULATION U. S. SPOT MARKET REGULATION NARUC ENERGY REGULATORY PARTNERSHIP WITH GEORGIAN NATIONAL ENERGY AND WATER SUPPLY REGULATORY COMMISSION & MICHIGAN PUBLIC SERVICE COMMISSION TBILISI, GEORGIA November 30,

More information

Price Formation. PJM Market Participants February 14, Joe Bowring Catherine Tyler

Price Formation. PJM Market Participants February 14, Joe Bowring Catherine Tyler Price Formation PJM Market Participants February 14, 2019 Joe Bowring Catherine Tyler ISSUES WITH PJM ORDC 2019 www.monitoringanalytics.com 2 PJM ORDC Shape PJM s ORDCs persistently raise prices and procure

More information

Future Market Implementation

Future Market Implementation SPP.org 1 Future Market Implementation Requirements - way forward MWG June 29 th, 2009 SPP.org WebEx Instructions Please submit questions to host. If it is a long question you can type a summary until

More information

10.1 Scope of CMRI Reports available to SCs

10.1 Scope of CMRI Reports available to SCs 10.1 Scope of CMRI Reports available to SCs Exhibit 10-1.1 summarizes the reports that are available to SCs through the CAISO Market Results Interface (CMRI). Details of the report contents are provided

More information

Published on January 16, By Operations Engineering

Published on January 16, By Operations Engineering AN EVOLUTIONARY APPROACH TO ADVANCING TECHNOLOGIES How Southwest Power Pool is incorporating emerging technology to benefit our stakeholders and their customers Published on January 16, 2018 By Operations

More information

Flexible Ramping Products

Flexible Ramping Products Flexible Ramping Products Revised Draft Final Proposal August 16, 2012 Lin Xu, Ph.D. Senior Market Development Engineer Don Tretheway Senior Market Design and Policy Specialist Agenda Time Topic Presenter

More information

2.1.1 Market Power Mitigation & Reliability Requirements Determination Market Power Mitigation & Reliability Requirements Determination

2.1.1 Market Power Mitigation & Reliability Requirements Determination Market Power Mitigation & Reliability Requirements Determination 2.1.1 Market Power Mitigation & Reliability Requirements Determination The Market Power Mitigation and Reliability Requirements Determination (MPM-RRD) function consists of two processes. The MPM is to

More information

Price Inconsistency Market Enhancements. Draft Final Proposal

Price Inconsistency Market Enhancements. Draft Final Proposal Price Inconsistency Market Enhancements Draft Final Proposal August 31, 2012 Price Inconsistency Market Enhancements Table of Contents 1 Introduction... 4 2 Plan for Stakeholder Engagement... 4 3 Background...

More information

Pricing Logic Under Flexible Modeling of Constrained Output Generating Units

Pricing Logic Under Flexible Modeling of Constrained Output Generating Units Draft Final Proposal Pricing Logic Under Flexible Modeling of Constrained Output Generating Units April 14, 2008 This is the third CAISO paper on this issue. An Issue Paper was posted on February 1, 2008

More information

Outage Coordination Training MISO Training

Outage Coordination Training MISO Training MISO Last material update: 05/19/2015 Course Content and Disclaimer 2 1 2 3 4 Course Description This course will review MISO's outage study processes and the coordination opportunities with TOs and MPs.

More information

Applying PROBE for Congestion Analysis and Grid Planning

Applying PROBE for Congestion Analysis and Grid Planning Applying PROBE for Congestion Analysis and Grid Planning August 1, 2003 Jim Mitsche JMitsche@power-gem.com 518 393 3834 1 Topics Analysis Objectives Nature of Congestion Cost & Cost Calculation What is

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 31. Day-Ahead Market... 2 31.1 Bid Submission and Validation in the Day-Ahead Market... 2 31.2 Day-Ahead MPM Process... 2 31.2.1 The Market Power Mitigation Process... 3 31.2.2 Bid Mitigation

More information

Load Granularity Refinements. Pricing Study Results and Implementation Costs and Benefits Discussion

Load Granularity Refinements. Pricing Study Results and Implementation Costs and Benefits Discussion Pricing Study Results and Implementation Costs and Benefits Discussion January 14, 2015 Table of Contents I. Executive Summary... 3 II. Introduction... 3 III. Stakeholder Process... 4 IV. Pricing Study

More information

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004 Glossary of Terms Used in Standards Preliminary Draft Version 0 Standards September 1, 2004 Source References (Noted in draft only will not be part of final glossary) Functional Model () Glossary (GL)

More information

PJM s Implementation of the Three-Pivotal Supplier Test

PJM s Implementation of the Three-Pivotal Supplier Test PJM s Implementation of the Three-Pivotal Supplier Test MIC July 25, 2007 Joe Bowring Paul Scheidecker Market Monitoring Unit www.pjm.com Context of TPS Test Results TPS test is triggered in real time

More information

Joint and Common Market ITEM 4 PSEUDO TIES

Joint and Common Market ITEM 4 PSEUDO TIES Joint and Common Market ITEM 4 PSEUDO TIES Agenda 1. Overview 2. Background 3. Common Issues 4. PJM Update 5. MISO Update 6. Double-Counting 7. Next Steps 2 Overview Purpose Provide a status update on

More information

Status Update Assessment of ICT/RTO Options and Issues

Status Update Assessment of ICT/RTO Options and Issues JULY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESS Session 5 Status Update Assessment of ICT/RTO Options and Issues Kurt Castleberry July 15, 2010 1 JULY 2010 PRELIMINARY TECHNICAL CONFERENCE

More information

2007 State of the Market Report Midwest ISO. Midwest ISO

2007 State of the Market Report Midwest ISO. Midwest ISO 2007 State of the Market Report Midwest ISO Prepared by: Midwest ISO Independent Market Monitor David B. Patton, Ph.D. Potomac Economics June 2008 Executive Summary: Introduction As the Independent Market

More information

New Brunswick Electricity Business Rules. Chapter 3 Reliable Operations

New Brunswick Electricity Business Rules. Chapter 3 Reliable Operations New Brunswick Electricity Business Rules Chapter 3 Reliable Operations TABLE OF CONTENTS CHAPTER 3 RELIABLE OPERATIONS... 2 3.0 System Operator Roles and Responsibilities... 2 3.1 Reliability Assessments...

More information

PJM M2M Market Flow Proposal. October 2014

PJM M2M Market Flow Proposal. October 2014 PJM M2M Market Flow Proposal October 2014 Table of Contents 1. Introduction... 1 2. M2M Market Flow... 1 3. Real-Time Balancing Congestion and M2M payments... 3 4. Firm Flow Entitlement Impact of Market

More information

Straw Proposal. Post-Release 1 MRTU Functionality for Demand Response

Straw Proposal. Post-Release 1 MRTU Functionality for Demand Response California Independent System Operator Corporation Executive Summary Straw Proposal Post-Release 1 MRTU Functionality for Demand Response The (CAISO) has a goal of helping to develop demand response resources

More information

MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 12, 2007

MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 12, 2007 MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 12, 2007 Report submitted to NERC on: July 26, 2007. This report is submitted

More information

Summary of 2016 MISO State of the Market Report

Summary of 2016 MISO State of the Market Report Summary of 2016 MISO State of the Market Report Presented to: MISO Board Markets Committee David B. Patton, Ph.D. MISO Independent Market Monitor July 20, 2017 Introduction As the Independent Market Monitor

More information

Power Flow Control Through Topology Optimization Software: Applications and Case Studies

Power Flow Control Through Topology Optimization Software: Applications and Case Studies 1 Power Flow Control Through Topology Optimization Software: Applications and Case Studies Pablo A. Ruiz IEEE PES Transmission & Distribution Conference and Expo Denver, CO, April 17, 2018 2 Current Congestion

More information

Seminar on African Electrical Interconnection. Module 7 - Market Operational Structures

Seminar on African Electrical Interconnection. Module 7 - Market Operational Structures Seminar on African Electrical Interconnection Module 7 - Market Operational Structures Module 7 - Market Operational Structures Contents 1) Power Market Principles 2) Major Operational Issues 3) Transmission

More information

Key Issues and Consideration in Market Design, Operational and Oversight

Key Issues and Consideration in Market Design, Operational and Oversight Key Issues and Consideration in Market Design, Operational and Oversight Patrick Donlon Amanda Gordon Kathryn Sophy Kenneth Villwock Public Utilities Commission of Ohio & Pennsylvania Public Utilities

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Section 11 Congestion and Marginal Losses Congestion and Marginal Losses The locational marginal price (LMP) is the incremental price of energy at a bus. The LMP at a bus is made up of three components:

More information

PJM s Implementation of the Three-Pivotal Supplier Test Update

PJM s Implementation of the Three-Pivotal Supplier Test Update PJM s Implementation of the Three-Pivotal Supplier Test Update TPSTF August 20, 2007 Joe Bowring Paul Scheidecker Market Monitoring Unit www.pjm.com Context of TPS Test Results TPS test is triggered in

More information

IDC Regional Congestion Management Training Plan. Revision 0.9. March 22, 2004

IDC Regional Congestion Management Training Plan. Revision 0.9. March 22, 2004 IDC Regional Congestion Management Training Plan Revision 0.9 March 22, 2004 Change Record Version Person Date Change Record 0.0 0.9 IDCWG IDCWG February 12, 2004 March 22, 2004 IDCWG Created Document

More information

Midwest ISO TDU Sector October 2010 Midwest ISO Advisory Committee Hot Topic Adequate Price Signals

Midwest ISO TDU Sector October 2010 Midwest ISO Advisory Committee Hot Topic Adequate Price Signals Midwest ISO TDU Sector October 2010 Midwest ISO Advisory Committee Hot Topic Adequate Price Signals October 13, 2010 The Municipal, Cooperative and Transmission Dependent Utilities (TDUs) welcome the opportunity

More information

MISO-PJM JOA Biennial Review

MISO-PJM JOA Biennial Review MISO-PJM JOA Biennial Review Midcontinent ISO PJM Interconnection 1/20/2016 1. Background On January 4, 2011, Midwest 1 Independent Transmission System Operator, Inc. (MISO) and PJM Interconnection, LLC

More information

PJM Wholesale Markets. Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia

PJM Wholesale Markets. Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia PJM Wholesale Markets Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia PJM RTO Functions Grid Operation Non-discriminatory treatment Monitoring transmission system Reliability

More information

MIDWEST ISO UPDATE. Sherman Elliott Manager State Regulatory Affairs

MIDWEST ISO UPDATE. Sherman Elliott Manager State Regulatory Affairs MIDWEST ISO UPDATE Sherman Elliott Manager State Regulatory Affairs June 2, 2006 RTO Services Monitor flow of power over the high voltage transmission system Schedule transmission service Security analysis

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Briefing on stepped constraint parameters initiative

Briefing on stepped constraint parameters initiative Briefing on stepped constraint parameters initiative Market Impacts of Shift Factor Truncation Scott Harvey Market Surveillance Committee Member Market Surveillance Committee Meeting General Session June

More information

2014 State of the Market

2014 State of the Market 2014 State of the Market 24 August 2015 SPP Market Monitoring Unit Disclaimer The data and analysis in this report are provided for informational purposes only and shall not be considered or relied upon

More information

Wind Update. Renewable Energy Integration Lessons Learned. March 28, 2012

Wind Update. Renewable Energy Integration Lessons Learned. March 28, 2012 Wind Update Renewable Energy Integration Lessons Learned March 28, 212 Contents Summary Review of Historical Wind Growth and Output Impact of Wind on Operations Wind Curtailments Dispatchable Intermittent

More information

Parameter Tuning for Uneconomic Adjustments. Lorenzo Kristov, Principal Market Architect

Parameter Tuning for Uneconomic Adjustments. Lorenzo Kristov, Principal Market Architect Parameter Tuning for Uneconomic Adjustments Lorenzo Kristov, Principal Market Architect Stakeholder Meeting May 13, 2008 Topics for Discussion Objectives of Current Parameter Tuning Effort Parameter Tuning

More information

Analysis of the Broader Regional Markets Initiatives

Analysis of the Broader Regional Markets Initiatives Analysis of the Broader Regional Markets Initiatives Presented to: Joint NYISO-IESO-MISO-PJM Stakeholder Technical Conference on Broader Regional Markets David B. Patton, Ph.D. Potomac Economics September

More information

Ancillary Service Markets

Ancillary Service Markets Section 9 Ancillary Services Ancillary Service Markets The United States Federal Energy Regulatory Commission (FERC) defined six ancillary services in Order No. 888: 1) scheduling, system control and dispatch;

More information

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project PJM White Paper PJM Interconnection November 15, 2018 This page is intentionally left blank. PJM 2018 www.pjm.com i P a g e Contents Highlights... 1 Executive Summary... 1 I. Introduction... 2 Reliability

More information

Congestion Cost Metrics

Congestion Cost Metrics Congestion Cost Metrics DRAFT One of the features of a locational marginal price (LMP) based market is the ability to identify grid locations that are difficult to serve with economic generation due to

More information

DRAFT STUDY PLAN FOR 2018

DRAFT STUDY PLAN FOR 2018 DRAFT STUDY PLAN FOR 2018 Introduction The Ten-year transmission planning process is intended to facilitate a timely, coordinated and transparent process that fosters the development of electric infrastructure

More information

RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization

RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization - 1 - Introduction The North American Electric Reliability Council (NERC) requires every

More information

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering 2017 ITPNT 2 0 1 7 I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e June 15, 2016 Engineering Revision History Date or Version Number Author Change Description Comments

More information

Market Simulation Structured Scenarios. Energy Imbalance Market Implementation Arizona Public Service and Puget Sound Energy

Market Simulation Structured Scenarios. Energy Imbalance Market Implementation Arizona Public Service and Puget Sound Energy Market Simulation Structured s Energy Imbalance Market Implementation Arizona Public Service and Puget Sound Energy Version: 1.1 June 1, 2016 Location of Document Link Revision History Date Version Author

More information

Issue Paper. Modifying the DEC Bidding Activity Rule on Day-Ahead Schedules

Issue Paper. Modifying the DEC Bidding Activity Rule on Day-Ahead Schedules Issue Paper Modifying the DEC Bidding Activity Rule on Day-Ahead Schedules February 1, 2008 Modifying the DEC Bidding Activity Rule on Day Ahead Schedules Table of Contents 1 Introduction...3 2 Background:

More information

Energy Imbalance Market Design Straw Proposal and Issue Paper. Stakeholder Meeting April 11, 2013

Energy Imbalance Market Design Straw Proposal and Issue Paper. Stakeholder Meeting April 11, 2013 Energy Imbalance Market Design Straw Proposal and Issue Paper Stakeholder Meeting April 11, 2013 Agenda Time Topic Presenter 10:00 10:10 Introduction Mercy Parker-Helget 10:10 10:45 Opening Remarks Don

More information

Pricing Enhancements Revised Straw Proposal

Pricing Enhancements Revised Straw Proposal Pricing Enhancements Revised Straw Proposal Guillermo Bautista Alderete, Ph.D. Manager, Market Validation and Quality Analysis October 3, 2014 ISO Stakeholder Initiative Process POLICY AND PLAN DEVELOPMENT

More information

IMM Quarterly Report: Spring 2018

IMM Quarterly Report: Spring 2018 IMM Quarterly Report: Spring 2018 MISO Independent Market Monitor David Patton, Ph.D. Potomac Economics June 19, 2018 Highlights and Findings: Spring 2018 The MISO markets performed competitively this

More information

Eligible Intermittent Resource Dispatch Operating Target EIR DOT

Eligible Intermittent Resource Dispatch Operating Target EIR DOT Eligible Intermittent Resource Dispatch Operating Target EIR DOT CSSA Training August 2018 Stakeholder Learning Objectives Explain the difference between an Operating Instruction and a Dispatch Instruction

More information

Influence of Natural Gas Price and Other Factors on ISO-NE Electricity Price

Influence of Natural Gas Price and Other Factors on ISO-NE Electricity Price Influence of Natural Gas Price and Other Factors on ISO-NE Electricity Price Final Report for Undergraduate Research Opportunities Program Prepared by: Christiane Adcock, Milos Cvetkovic, Anuradha Annaswamy

More information

Integrating High Levels of Variable Renewable Energy Sources

Integrating High Levels of Variable Renewable Energy Sources Integrating High Levels of Variable Renewable Energy Sources Erik Ela EPRI Grid Ops and Planning eela@epri.com NYISO Environmental Advisory Council Troy, NY May 6, 2016 EPRI Grid Operations & Planning

More information