1 GB regulatory approach RIIO price controls and distributed generation October 2016 James Veaney Head of Connections and Constraints Management

2 Background Much of network installed in 1950s and 60s with some assets over 80 years old 14 licenses owned by six companies 16% of the average domestic electricity bill 4bn paid annually by GB customers Combined asset value of 18bn *In Scotland, 132kV is part of the transmission system

3 Background Price Controls Network Companies are natural monopolies In line with our principle statutory duty to protect energy customers we regulate energy network companies. We have several regulatory mechanisms and tools at our disposal. Price controls are a very important part of our regulatory arrangements. In a price control review we set a limit on the amount of revenue that companies can collect during the price control period. If companies costs are lower than the allowed revenue, then the company gets to keep a share of the profits and vice versa. Companies can also earn rewards or penalties through their delivery of set outputs (versus set targets).

4 RIIO: A new approach to price controls RPI-X used as basis for regulating energy networks for since early 1990s delivered significant benefits for consumers: 20% reduction in 30% reduction in 60bn More efficient Improved quality network charges power cuts Investment financing of service Networks focused on short term BUT stakeholders suggested framework led to: Networks focused on Ofgem not customers Limited innovation Limited appetite for risk Bias for capex solutions Limited focus on crosssectoral interactions RPI-X was not broken, but RIIO introduced as new fit for purpose framework

5 RIIO: A new approach to price controls Constraint set up front to ensure: Revenue = Incentives + Innovation + Outputs Timely and efficient delivery Network companies are financeable Transparency and predictability Deliver outputs efficiently over time with: Balance between costs faced by current and future consumers 8 yr control Rewards/penalties for delivery Upfront efficiency rate Core price control incentives Technical and commercial innovation encouraged through: Option to give third parties a greater role in delivery Innovation stimulus package Outputs set out in clear contract, reflecting expectations of current and future consumers

6 Stakeholder engagement DNOs must demonstrate engagement in developing their business plans Ofgem-led elements: Price Control Review Forum (PCRF): high level stakeholder group which will provide input to Ofgem and the DNOs about a range of aspects of the price control Consumer Challenge Group (CCG): This is a small group of consumer experts which act as a critical friend to Ofgem in ensuring that the views of consumers are considered fully in the review Working groups: A range of groups where Ofgem, DNOs and other stakeholders discussed specific issues in depth. Detailed design of outputs and incentives. Flexibility and capacity; Environment; Innovation; Reliability and safety; Connections; Customer and social issues; Finance; Cost assessment And of course, consultation throughout the process

7 RIIO-ED1 Process Initial Strategy consultation: Sept - Oct Business plans submitted: July Fast track Decision: Feb Draft determination: July Launch consultation: Feb 2012 Strategy Decision: March Fast track Consultation: Oct Final Determination: Nov policy development business plan assessment business plan assessment Throughout: Effective stakeholder engagement by us and network companies 8 year price control: 1 April March 2023 Process built on learning from transmission and gas distribution price controls (RIIO-T1 and RIIO-GD1) Policies built on previous electricity distribution price control (DPCR5)

8 RIIO-ED1 Key Challenges Driving factors Government policy and subsidy regime Other incentive mechanisms Local planning rules Technological developments & reductions in cost Facilitating factors Investment to expand and reinforce the distribution network Greater use of smart grid technology & DSR to maximise network flexibility at minimum cost ED targets Uncertainty around the characteristics, rate and location of take-up of these technologies Standard asset life ED2 Ensure low carbon technologies can connect in appropriate time at appropriate cost

9 RIIO Outputs strong focus on what network companies will deliver Environmental impact Customer satisfaction Six Output Categories Connections Safety Reliability and availability Social obligations Developed through extensive stakeholder engagement The delivery of these outputs linked to DNOs allowed revenue amount. The DNOs incur rewards and penalties for out/under performance of these outputs

10 Innovation Stimulus Package RIIO has a number of elements that drive innovation: Longer price control periods, Equalised opex and capex No with hindsight adjustments Focus on delivery of outputs. Network Innovation Competition Network Innovation Allowance Replace Innovation Funding Incentive and Low Carbon Network Fund. Single annual competition covering elec transmission & distribution. The amount available for and is 90m per year. It will be reviewed going forwards. Fund innovation within DNOs allowed revenue (use it or lose it). Fund small projects that meet published criteria. Size of funding is based on the quality of the Innovation Strategy in the DNO business plans (0.5 to 1% of base revenue). Innovation Roll-out Mechanism DNOs can apply for additional funding to roll-out a proven innovation. Where the innovation meets pre-defined environmental criteria but there are not sufficient benefits for DNO to fund roll-out.

11 Uncertainty Mechanisms Some factors are outside of the DNO s control. The risk should be shared equitably between DNO and customers Protects customers Allows DNOs to provide outputs Reduced cost of capital and therefore cost to customers Different types of uncertainty mechanism, depending on the type of uncertainty, eg: Load related reopener Smart meter volume driver Indexation of allowed revenues

12 Business plans Companies required to develop well-justified business plans setting out How they will deliver in the interests of current and future consumers How they will meet the challenge of moving to a low carbon economy A strategy for dealing with risks and uncertainties Companies will need to: justify their strategy for output delivery against an understanding of the long-term trends they face show they have considered a range of stakeholder views and opportunities for innovative approaches include a holistic view of the price control package including financeability metrics A high quality business plan can be fast-tracked and have the price control concluded early. In RIIO-ED1 one company was fast-tracked, the others had 2bn of cuts made to their plans

13 The growth of DG

14 10GW of PV now connected over 6GW in last 2 years Forecasting is challenging

15 With growth comes system issues Connections to Distribution network in South West Total MW - connected, accepted and offered Biomass and energy crops (not CHP) 111,050 CHP 68,648 Offshore wind 181,351 Onshore wind 202,433 Photovoltaic 2,593,920 Waste incineration 115,765 Other generation 649,522 Total 3,922,689 Winter Maximum Demand 2,530,000 Summer Minimum Demand 980,000 Fundamental changes to flows of energy regions built to handle demand now net export Network capacity exhausted - Grid constraints are becoming more severe DG can reduce demand on the network (ie.excess generation at times of low demand). Challenge to keep system voltages within limits - resulting in restrictions on transmission-connected generation and what the DNO can connect

16 . and customer service challenges 5 years ago, generators had a lengthy list of complaints Application process was long winded Little information available up front to inform connection choice Customer service was patchy Hard to know what you were paying for Different arrangements in different DNO regions No innovation or desire to find ways around a problem At times, far too expensive At times, far too long to connect Ofgem-led DG Forum events and RIIO-ED1 Incentive on Connections Engagement (ICE) introduced to focus DNOs on customer needs or face financial penalties Progress has been made

17 DNOs have responded Online application and access to data DG surgeries Connection guides Consortium arrangements to share cost Heat maps DG-DNO steering group established Transmission-Distribution Steering Group established

18 Innovation has enabled smarter approaches We ve invested nearly 100m of customer money funding innovative projects to release capacity/improve connections for DG Flexible Plug and Play (UKPN) Low carbon hub (WPD) Active Network Management (SSE) Real time thermal ratings (NPG) Kent Area System Management (UKPN) Accelerating Renewable Connections (ARC) (SP) FlexDGrid (WPD) Capacity to Customers (ENWL) Low Voltage Network Templates (WPD) Network Equilibrium (WPD) These are now becoming business as usual. Customers should have a choice between firm and a viable non-firm offer or an explanation why not.

19 Change and the need for flexibility We need new forms of flexibility and we want to maintain service and reliability while keeping costs down for consumers

20 The need for more flexibility in the system Last year we published a position paper Making the electricity system more flexible and delivering the benefits for consumers Our five priorities: o Storage o Expanded role for Distribution Network Operators DSOs o Role of aggregators o Industrial and Commercial consumers potential to offer flexibility o Network charging Working with government

21 Forthcoming call for evidence structure 1. Removing policy and regulatory barriers Storage Aggregators 2. Providing price signals for flexibility 3. A system for the consumer Smart appliances Electric vehicles Consumer protection 4. The role of different parties in system and network operation The potential move to DSOs and the DSO-TSO relationship 5. Innovation

22

How to incentivise utilities to adopt low carbon technologies

How to incentivise utilities to adopt low carbon technologies How to incentivise utilities to adopt low carbon technologies Dora Guzeleva Head of Network Policy, Ofgem Metering Billing / CRM 9-11 October 2012 Amsterdam Contents 1. Innovation in Next Price Control

More information

OVERVIEW OF GB RIIO FRAMEWORK. Approccio totex nel settore elettrico

OVERVIEW OF GB RIIO FRAMEWORK. Approccio totex nel settore elettrico OVERVIEW OF GB RIIO FRAMEWORK Approccio totex nel settore elettrico Milan, 15 November 2017 ONLY ONE EXAMPLE OF A TOTEX APPROACH EXISTS IN EUROPE Comparison of EU Regulatory Systems Comments Ex ante incentive

More information

Implementation of RIIO-GD1

Implementation of RIIO-GD1 Implementation of RIIO-GD1 Paul Branston, Ofgem IGEM London & Southern Section 30 April 2013 2 Agenda Introduction to RIIO Principles Introduction to RIIO-GD1 Cost allowances Outputs Incentives Innovation

More information

National Farmers Union 28 February Connecting to the electricity and gas networks

National Farmers Union 28 February Connecting to the electricity and gas networks National Farmers Union 28 February 2013 Connecting to the electricity and gas networks Olivia Powis Senior Manager Smarter Grids and Governance, Ofgem 2 Content Connecting to the electricity and gas network

More information

UK Power Networks Innovation and future energy systems. Neil Madgwick & Giulia Privitera 3 March 2017

UK Power Networks Innovation and future energy systems. Neil Madgwick & Giulia Privitera 3 March 2017 UK Power Networks Innovation and future energy systems Neil Madgwick & Giulia Privitera 3 March 2017 Agenda Key forces influencing future energy systems The changing role of the Distribution Network Operator

More information

RIIO ED1 BUSINESS PLAN Stakeholder Executive Summary July 2013

RIIO ED1 BUSINESS PLAN Stakeholder Executive Summary July 2013 RIIO ED1 BUSINESS PLAN Stakeholder Executive Summary July 2013 1 Foreword from Robert Symons, CEO, Western Power Distribution Our business is a simple one. Our purpose is to make sure the electricity network

More information

Electricity Charging Seminar Level Playing Field

Electricity Charging Seminar Level Playing Field Electricity Charging Seminar Level Playing Field Electricity Charging Seminar Level Playing Field Radisson Blu, Glasgow 21 st July 2016 Overview of Transmission Charging Damian Clough, Senior Commercial

More information

Opportunities & challenges in current markets & gearing up for the future

Opportunities & challenges in current markets & gearing up for the future Session 2: Opportunities & challenges in current markets & gearing up for the future Rosie McGlynn Sara Vaughan Nigel Turvey Peter Bance Energy UK E.ON Western Power Distribution Origami Energy Opportunities

More information

Operational and technical challenges for D3: Lessons from FENIX

Operational and technical challenges for D3: Lessons from FENIX Operational and technical challenges for D3: Lessons from FENIX Gary Keane D3 Expert Stakeholder Workshop 3 March 2011 Pöyry what do we do? 2 7000 employees across 49 countries Pöyry is Europe s leading

More information

Introduction to local flexibility markets What are flexibility services and how can I get involved? Jodie Giles Senior Project Manager

Introduction to local flexibility markets What are flexibility services and how can I get involved? Jodie Giles Senior Project Manager Introduction to local flexibility markets What are flexibility services and how can I get involved? Jodie Giles Senior Project Manager Regen s recent work on flexibility Feb May 2018 November 2017 May-Aug

More information

Incentivising the connection of DG: Promoting efficient connection and appropriate benefit sharing

Incentivising the connection of DG: Promoting efficient connection and appropriate benefit sharing Incentivising the connection of DG: Promoting efficient connection and appropriate benefit sharing Michael G. Pollitt* and Karim L. Anaya EPRG, University of Cambridge 06 June 2014 Contents 1. Introduction

More information

RIIO-ED1 BUSINESS PLAN Summary of draft Business Plan for stakeholder consultation April 2013

RIIO-ED1 BUSINESS PLAN Summary of draft Business Plan for stakeholder consultation April 2013 RIIO-ED1 BUSINESS PLAN Summary of draft Business Plan for stakeholder consultation April 2013 1 WPD Draft Business Plan - Overview Our business plan covers the period 2015-2023 and has been developed with

More information

RIIO-T2 Central and Southern Scotland Electricity Scenarios 2018

RIIO-T2 Central and Southern Scotland Electricity Scenarios 2018 RIIO-T2 Central and Southern Scotland Electricity Scenarios 2018 RIIO-T2 Contents 1. Introduction 2. Future Challenges for the Network 3. The Role of the Transmission Network 4. How are we considering

More information

RIIO-T2 Central and Southern Scotland Electricity Scenarios 2018

RIIO-T2 Central and Southern Scotland Electricity Scenarios 2018 RIIO-T2 Central and Southern Scotland Electricity Scenarios 2018 RIIO-T2 Contents 1. Introduction 2. Future Challenges for the Network 3. The Role of the Transmission Network 4. How are we considering

More information

Office of Gas and Electricity Markets, 9 Millbank, London SW1P 3GE

Office of Gas and Electricity Markets, 9 Millbank, London SW1P 3GE Target audience: Consumers and their representatives, transmission and distribution companies, generators and offshore gas producers/importers, suppliers, shippers, debt and equity investors, environmental

More information

North of Scotland Future Energy Scenarios. August ssen-transmission.co.uk

North of Scotland Future Energy Scenarios. August ssen-transmission.co.uk North of Scotland Future Energy Scenarios August 2018 ssen-transmission.co.uk North of Scotland Future Energy Scenarios This publication The Great Britain (GB) energy landscape has undergone significant

More information

Upgrading Our Energy System. Smart Systems and Flexibility Plan

Upgrading Our Energy System. Smart Systems and Flexibility Plan Upgrading Our Energy System Smart Systems and Flexibility Plan July 2017 2 Upgrading Our Energy System Upgrading Our Energy System 3 Contents Smart Systems and Flexibility Plan Executive Summary 4 Introduction

More information

SO incentives from February 2012

SO incentives from February 2012 SO incentives from 2013 23 February 2 Context We published a consultation on the principles and policy for SO regulation on 31 January The document set out our views at a high level on regulation of the

More information

CBI Response to BEIS Call for Evidence

CBI Response to BEIS Call for Evidence CBI Response to BEIS Call for Evidence Smart, Flexible Power System The CBI welcomes the opportunity to respond to the BEIS Call for Evidence on A Smart, Flexible Energy System. Across the UK, the CBI

More information

UK Power Networks Becoming a Next Generation DNO. Nick Heyward

UK Power Networks Becoming a Next Generation DNO. Nick Heyward UK Power Networks Becoming a Next Generation DNO Nick Heyward About UK Power Networks UK Power Networks is a Distribution Network Operator (DNO), providing power to a quarter of the UK s population through

More information

Electricity System Operator Forward Plan 2018/19

Electricity System Operator Forward Plan 2018/19 Electricity System Operator Forward Plan 2018/19 Contents 1. Our vision 2. An ambitious plan 3. A changing landscape 4. Value for consumers 5. A plan built with our customers and stakeholders 6. Our roles,

More information

Energy Networks Association

Energy Networks Association The Voice of the Networks Energy Networks Association TDI Stakeholder Engagement Workshop TDI Stakeholder Engagement Workshop Objectives To engage with and disseminate information to the energy community,

More information

Electricity North West Future Challenges. Dr Geraldine Bryson Innovation Implementation Engineer

Electricity North West Future Challenges. Dr Geraldine Bryson Innovation Implementation Engineer Electricity North West Future Challenges Dr Geraldine Bryson Innovation Implementation Engineer 1 Agenda Introducing Electricity North West Low carbon future Innovation & the energy challenge Summary and

More information

The Smart Grid Challenge March

The Smart Grid Challenge March Overview UK and Ireland Energy Market the challenge Smart Grids and Smart Metering a definition Smart Metering and Smart Grids the opportunity An example of Smart Grids technical and commercial end to

More information

APGTF Workshop: Managing the Grid of the Future

APGTF Workshop: Managing the Grid of the Future APGTF Workshop: Managing the Grid of the Future Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

National Infrastructure Assessment: Call for Evidence

National Infrastructure Assessment: Call for Evidence National Infrastructure Assessment: Call for Evidence Energy Networks Association (ENA) represents the wires and pipes transmission and distribution network operators for gas and electricity in the UK

More information

UK Generation. BAML lunch - 29 th March Alison Kay Commercial Director Transmission

UK Generation. BAML lunch - 29 th March Alison Kay Commercial Director Transmission UK Generation BAML lunch - 29 th March 2012 Alison Kay Commercial Director Transmission Cautionary statement This presentation contains certain statements that are neither reported financial results nor

More information

Future Electricity Demand Growth in the East Midlands

Future Electricity Demand Growth in the East Midlands Future Electricity Demand Growth in the East Midlands Stakeholder workshop 30 March 2017 East Midlands licence area Today Scope Distributed generation and demand technology growth scenarios to 2030 o Methodology

More information

Modelo de regulação do setor elétrico na Inglaterra. Paul Whittaker Diretor de Regulação da National Grid

Modelo de regulação do setor elétrico na Inglaterra. Paul Whittaker Diretor de Regulação da National Grid Modelo de regulação do setor elétrico na Inglaterra Paul Whittaker Diretor de Regulação da National Grid São Paulo, 18 de março de 2015 A brief history of UK electricity State control (1948 1992) Technocratic

More information

Karim L. Anaya and Michael G. Pollitt. Keywords cost benefit analysis, distributed generation, interruptible connections (non-firm)

Karim L. Anaya and Michael G. Pollitt. Keywords cost benefit analysis, distributed generation, interruptible connections (non-firm) Finding the Optimal Approach for Allocating and Realising Distribution System Capacity: Deciding between Interruptible Connections and Firm DG Connections EPRG Working Paper 1320 Cambridge Working Paper

More information

Efficient Rules for Planning and Regulating a Smart Grid

Efficient Rules for Planning and Regulating a Smart Grid Efficient Rules for Planning and Regulating a Smart Grid Presentation to the NERA/EPRG Winter Conference Richard Druce Senior Consultant Cambridge 11 December 2015 Overview Defining a smart grid, and why

More information

Open Networks Project

Open Networks Project Open Networks Project Charging Scenarios 16 August 2017 Document Ref: ON-WS4-P1 Charging Scenarios-170816 Restriction: None Document Control Version Control Version Issue Date Author Comments 2.0 16/08/17

More information

Strategic Investment Options for Low Carbon Economy in the South Wales. 15th June 2016

Strategic Investment Options for Low Carbon Economy in the South Wales. 15th June 2016 Strategic Investment Options for Low Carbon Economy in the South Wales 15th June 2016 WPD Our Area 4 of 14 Distribution UK Licence Areas 7.8 Million Customers Covers 55,500 Sq Km 220,000km of Network 185,000

More information

Energy Networks Association

Energy Networks Association Energy Networks Association Transmission and Distribution Interface Steering Group Report May 2016 Contents Contents... 2 1. Introduction... 3 2. Challenges and Opportunities... 3 3. Governance... 3 General...

More information

Energy Law Group. Electricity storage

Energy Law Group. Electricity storage Energy Law Group Electricity storage John Grady September 2017 Electricity storage Discussion points. The UK approach. Ofgem, Upgrading Our Energy System Smart Systems and Flexibility Plan, July 2017.

More information

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review:

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: 1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: encourage generators and suppliers to balance their own positions before gate closure, thus reducing the call

More information

The Electricity System Operator Who we are and what we do September 2018 CONFICONFIDNEITA

The Electricity System Operator Who we are and what we do September 2018 CONFICONFIDNEITA The Electricity System Operator Who we are and what we do September 2018 CONFICONFIDNEITA Who we are As the Electricity System Operator (ESO), we operate the National Electricity Transmission System in

More information

UK Power Networks Annex 1: Historic Outputs

UK Power Networks Annex 1: Historic Outputs UK Power Networks Annex 1: Historic Outputs UKPN_Historic_Outputs Contents 1 Executive Summary 4 1.1 Current performance for ED1 4 2 Purpose of the Document 5 3 Safety 6 3.1 Overview 6 3.2 Employee and

More information

SSEN Consultation: Unlocking Orkney s renewable potential

SSEN Consultation: Unlocking Orkney s renewable potential SSEN Consultation: Unlocking Orkney s renewable potential February 2018 Consultation closing date: 12 March 2018 Scottish and Southern Electricity Networks is a trading name of: Scottish and Southern Energy

More information

Energy UK response to the Electricity System Operator Forward Plan

Energy UK response to the Electricity System Operator Forward Plan ECC 09-18 Energy UK response to the Electricity System Operator Forward Plan 09 March 2018 About Energy UK Energy UK is the trade association for the GB energy industry with a membership of over 100 suppliers,

More information

Investor Webinar. UK Transmission Incentives. October 2010

Investor Webinar. UK Transmission Incentives. October 2010 Investor Webinar UK Transmission Incentives October 2010 1 Introduction and objectives Why this webinar topic? What are we aiming to do for you today? How we intend to do this? 2 Why incentives? Incentives

More information

Charging Futures Forum. 15 January 2019

Charging Futures Forum. 15 January 2019 Charging Futures Forum 15 January 2019 Welcome Gareth Davies, Industry Codes Governance Manager, National Grid SO The Charging Futures ecosystem Do we have the original image so that we could lose the

More information

Sunshine Tariff Summary report. Western Power Distribution and Regen SW

Sunshine Tariff Summary report. Western Power Distribution and Regen SW Sunshine Tariff Summary report Western Power Distribution and Regen SW February 2017 1 Contents The trial The challenge The trial...3 The challenge...3 The solution...3 The trial...4 The tariff...5 Feasibility...5

More information

Energy Storage Workshop 07/12/2015

Energy Storage Workshop 07/12/2015 Energy Storage Workshop 07/12/2015 Housekeeping Fire evacuation Toilets Phones Feedback Register in Reception UK Power Networks Hosts Asset Management Sotiris Georgiopoulos Matt White Dr José Barros Itayi

More information

Energy Networks Association

Energy Networks Association The Voice of the Networks Energy Networks Association Open Networks Project Advisory Group 19 th July 2017 Welcome & Introductions Nigel Turvey ENA Open Networks Project Steering Group and Advisory Group

More information

Consulting on our Business Plan

Consulting on our Business Plan Consulting on our Business Plan Critical Friends Stakeholder Panel Session 3 24 January 2013 2011. UK Power Networks. All rights reserved Safety and Housekeeping No planned fire alarms Emergency exits

More information

Responding to the challenge of RIIO-ED1 : a DNO perspective. 15 May 2014 AMT-Sybex conference Jonathan Booth

Responding to the challenge of RIIO-ED1 : a DNO perspective. 15 May 2014 AMT-Sybex conference Jonathan Booth Responding to the challenge of RIIO-ED1 : a DNO perspective 15 May 2014 AMT-Sybex conference Jonathan Booth Introducing Electricity North West Regulated electricity distributor Distribute >23 million megawatt

More information

Are the 2020 renewables targets (for electricity and heat) achievable? If not, why not?

Are the 2020 renewables targets (for electricity and heat) achievable? If not, why not? SUBMISSION BY NATIONAL GRID PLC Introduction to National Grid National Grid owns and operates the high voltage electricity transmission system in England and Wales and, as National Electricity Transmission

More information

OVERVIEW OF RIIO FRAMEWORK A report to AEEGSI. October 2017

OVERVIEW OF RIIO FRAMEWORK A report to AEEGSI. October 2017 A report to AEEGSI OVERVIEW OF RIIO FRAMEWORK Contact details Name Email Telephone Gareth Davies gareth.davies@poyry.com +44 (0)1865 812204 Paolo Marino paolo.marino@poyry.com +39 02 36 59 69 07 Ece Sayin

More information

Ofgem Incentive on Connections Engagement 2017/18 Key Performance Indicators

Ofgem Incentive on Connections Engagement 2017/18 Key Performance Indicators Ofgem Incentive on Connections Engagement 2017/18 Key Performance Indicators Q2 April-June 2017 Contents Key Performance Area Availability of Information Customer Service Connection Offers & Agreements

More information

Low Carbon Networks Fund Review and Synthesis

Low Carbon Networks Fund Review and Synthesis Low Carbon Networks Fund Review and Synthesis Damien Frame Keith Bell and Stephen McArthur University of Strathclyde damien.frame@strath.ac.uk The Low Carbon Network Fund 500m 5 Years Ofgem DNOs Electricity

More information

Future challenges for UK electricity storage

Future challenges for UK electricity storage Future challenges for UK electricity storage Laura Morris - Energy Policy Analyst Energy Technologies Institute Laura.morris@eti.co.uk 2013 Energy Technologies Institute LLP The information in this document

More information

Current rules and incentives: innovation in the energy system and emerging governance themes

Current rules and incentives: innovation in the energy system and emerging governance themes Current rules and incentives: innovation in the energy system and emerging governance themes Conference on Progressive Energy Governance 21 May 2014, London Placing energy demand at the centre Minimising

More information

Annex E: Energy supplementary material

Annex E: Energy supplementary material Annex E: Energy supplementary material E.1 Model formulat i o n For these three variables, energy demand is calculated using elasticities as follows: Q = Q 0 [N N / N 0 ] EN [P N / P 0 ] EP [Y N / Y 0

More information

Delivering outputs in innovative and lower cost ways REORGANISING RENEGOTIATING REENGINEERING

Delivering outputs in innovative and lower cost ways REORGANISING RENEGOTIATING REENGINEERING August 2013 REORGANISING RENEGOTIATING REENGINEERING Delivering outputs in innovative and lower cost ways Opportunity through innovative approach to planning and delivery Enabled by new process driven

More information

Installed power by end 2015, depending on connection point and technology

Installed power by end 2015, depending on connection point and technology Europe s power system is undergoing a profound change. Most of the new generation capacity is being connected to distribution networks. Distributed generation could provide valuable services today to the

More information

Open Networks Workstream 1 (T-D Processes)

Open Networks Workstream 1 (T-D Processes) The Voice of the Networks Open Networks Workstream 1 (T-D Processes) Product 5: Whole System FES December 2018 Energy Networks Association Document Ref: WS1P5DEC Restriction: Published 0 Document Control

More information

Performance Incentive Mechanisms

Performance Incentive Mechanisms Performance Incentive Mechanisms National Governors Association Learning Lab on New Utility Business Models & the Electricity Market Structures of the Future July 28, 2015 Melissa Whited Background Report

More information

Response to Energy and Climate Change Committee Call for Evidence on Local Energy

Response to Energy and Climate Change Committee Call for Evidence on Local Energy Response to Energy and Climate Change Committee Call for Evidence on Local Energy Summary 1. The Energy Technologies Institute (ETI), a public-private partnership between global energy and engineering

More information

Recommendations for incentivising innovation in the gas DSO sector

Recommendations for incentivising innovation in the gas DSO sector October 2016 Position Paper Recommendations for incentivising innovation in the gas DSO sector This paper sets out the status and challenges facing gas DSOs when investing in innovation. It describes a

More information

DSR follow on final presentation

DSR follow on final presentation DSR follow on final presentation A presentation to DECC Andrew Nind, Oliver Pearce, Kostas Theodoropoulos 4 April 2011 Agenda 1. Objectives 2. Scenario assumptions 3. Scenario results 4. Next steps 2 Objectives

More information

Distributed Generation

Distributed Generation Distributed Generation November 2014 November 6, 2014 1 Forward-Looking Statements Leading the Way in Electricity SM Statements contained in this presentation about future performance, including, without

More information

Energy Regulation in Great Britain

Energy Regulation in Great Britain INOGATE ITS Project Energy Regulation in Great Britain Alena Aliakseyeva, Office of Gas and Electricity Markets Capacity building for the Regulatory Authorities of the INOGATE Partner Countries Vienna

More information

Facilitating Whole Electricity System Outcomes

Facilitating Whole Electricity System Outcomes Facilitating Whole Electricity System Outcomes How the ESO is working with stakeholders to transform the energy landscape The way we generate and use electricity is changing, driven by the challenges of

More information

Future regulatory options Workshop slides

Future regulatory options Workshop slides Future regulatory options Workshop slides 23 June 2016 Agenda 1 2 3 4 5 6 7 8 Introduction Regulatory frameworks (structure, process and revenue setting) Assessment criteria Case studies RIIO, NY REV and

More information

5a. Grid Connection Codes

5a. Grid Connection Codes 5a. Grid Connection Codes Requirements for Generators Demand Connection Code HVDC Network Code 1 2 3 4 5 6 7 8 9 10 JESG in Edinburgh 20 August 2013 The Third Energy Package 3 regulations and 2 directives.

More information

Decarbonization pathways and the new role of DSOs

Decarbonization pathways and the new role of DSOs Decarbonization pathways and the new role of DSOs Kristian Ruby Secretary General Eurelectric 3 April 2019 We have modelled 3 deep decarbonization scenarios based on electrification of key economic sectors

More information

Smarter Grid Solutions Case History

Smarter Grid Solutions Case History Smarter Grid Solutions Case History Graham Ault Investor Ready Workshop session All Energy 22 nd May 2013 Overview Company development Active Network Management Market Technologies and Products Aspects

More information

Invitation for Expression of Interest to provide Flexible Services 3 April 2018

Invitation for Expression of Interest to provide Flexible Services 3 April 2018 Invitation for Expression of Interest to provide Flexible Services 3 April 2018 Flexible Services Expression of Interest/3 April 2018 Page 1 of 21 VERSION HISTORY Version Date Author Status Comments 1.0

More information

Back to contents. Executive Summary. Flexibility Roadmap. FutureSmart. A smart grid for all: Our transition to Distribution System Operator

Back to contents. Executive Summary. Flexibility Roadmap. FutureSmart. A smart grid for all: Our transition to Distribution System Operator Executive Summary Back to contents Flexibility Roadmap FutureSmart A smart grid for all: Our transition to Distribution System Operator 1 Contents Foreword 2 Executive Summary 3 1.0 Introduction 1.1 UK

More information

Long-term forecasting of reactive power demand in distribution networks Dr Christos Kaloudas / Dr Rita Shaw. 3 rd November 2017

Long-term forecasting of reactive power demand in distribution networks Dr Christos Kaloudas / Dr Rita Shaw. 3 rd November 2017 Long-term forecasting of reactive power demand in distribution networks Dr Christos Kaloudas / Dr Rita Shaw 3 rd November 2017 Introducing Electricity North West 4.9 million 2.4 million 25 terawatt hours

More information

Future arrangements of the System Operator. Cathy McClay Head of Commercial Operations

Future arrangements of the System Operator. Cathy McClay Head of Commercial Operations Future arrangements of the System Operator Cathy McClay Head of Commercial Operations The electricity industry is changing +10GW wind Demand Side Response Onshore comp. Electricity storage -8GW coal +10GW

More information

RIIO-ED1 BUSINESS PLAN Business Plan Commitments Report Glossary. 31 October 2016

RIIO-ED1 BUSINESS PLAN Business Plan Commitments Report Glossary. 31 October 2016 2015-2023 RIIO-ED1 BUSINESS PLAN Business Plan Commitments Report 2015-16 31 October 2016 Glossary Glossary A Accident Frequency Rate The number of accidents that occur annually divided by the number of

More information

WPD Innovation. Paul Jewell Policy Manager

WPD Innovation. Paul Jewell Policy Manager WPD Innovation Paul Jewell Policy Manager Who are WPD? Distribution Network Operator Midlands, South West and Wales 7.8 million customers 55,500 square kilometres 220,000km of lines & cable 185,000 substations

More information

Charging Delivery Body. 8 th August 2018

Charging Delivery Body. 8 th August 2018 Charging Delivery Body 8 th August 2018 Agenda Item Lead Timing 1 Introductions Chair 10.00 10.10 2 Review of Action log All 10.10 10.15 3 Targeted Charging Review update Next Charging Futures Forum meeting

More information

Energy Networks Association - Response to Call for Evidence from BEIS/Ofgem

Energy Networks Association - Response to Call for Evidence from BEIS/Ofgem The Voice of the Networks A Smart, Flexible Energy System Energy Networks Association - Response to Call for Evidence from BEIS/Ofgem Background Please find below the response from Energy Networks Association

More information

Good morning everyone. I'm Fintan Slye, director of the UK System. Operator. Thank you very much for joining us today as we continue the

Good morning everyone. I'm Fintan Slye, director of the UK System. Operator. Thank you very much for joining us today as we continue the CHECK AGAINST DELIVERY Continuing the Conversation Fintan Slye 22 February 2018 Introduction Good morning everyone. I'm Fintan Slye, director of the UK System Operator. Thank you very much for joining

More information

Modelling of Smart Low-Carbon Electricity Systems

Modelling of Smart Low-Carbon Electricity Systems Modelling of Smart Low-Carbon Electricity Systems Goran Strbac, Maysam Quadrdan, Dimitrios Papadaskalopoulos, Rodrigo Moreno, Ioannis Konstantelos, Predrag Djapic, Fei Teng, Marko Aunedi, Danny Pudjianto

More information

The EU-DEEP project. Gilles Bourgain, GDF SUEZ, Research & Innovation Coordinator of the project

The EU-DEEP project. Gilles Bourgain, GDF SUEZ, Research & Innovation Coordinator of the project The EU-DEEP project Gilles Bourgain, GDF SUEZ, Research & Innovation Coordinator of the project Coordinator : G. Bourgain, GDF SUEZ, Research & Innovation Technical Director : J. Deuse, Tractebel Engineering

More information

Consultation on the Electricity System Operator forward plan

Consultation on the Electricity System Operator forward plan Charlotte Ramsey Future of SO Programme Director National Grid Warwick, CV34 6DA United Kingdom Date: 5 th March 2018 Contact / Extn: Alan Kelly 0141 614 1736 Dear Charlotte Consultation on the Electricity

More information

Review of Analysis of Network Benefits from Smart Meter Message Flows

Review of Analysis of Network Benefits from Smart Meter Message Flows Review of Analysis of Network Benefits from Smart Meter Message Flows (Including RIIO ED1 and ED2 phasing and categorisation of benefits) 1 st July 2013 Version 1.0 1 Page 2 of 15 Review of Analysis of

More information

Supporting a smarter electricity system: Your response

Supporting a smarter electricity system: Your response Supporting a smarter electricity system: Your response Introduction Following SSEN s publication of the Supporting a Smarter Electricity System report, which set out the priorities and principles guiding

More information

INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS

INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS Christos KALOUDAS The University of Manchester UK christos.kaloudas@manchester.ac.uk Ben MARSHALL National Grid UK ben.marshall@nationalgrid.com

More information

14 May 2015

14 May 2015 Highlands and Islands Enterprise Fraser House, Friar's Lane, Inverness IV1 1BA olivia.powis@ofgem.gov.uk 14 May 2015 Dear Olivia, Introduction Thank you for providing the opportunity to respond to this

More information

Overview of the financing framework for the German Energiewende

Overview of the financing framework for the German Energiewende Overview of the financing framework for the German Energiewende Dr. Urban Rid Director General Energy Policy electricity and grids Federal Ministry for Economic Affairs and Energy Berlin, 13 November 2014

More information

SSE Research, Development and Demonstration

SSE Research, Development and Demonstration SSE Research, Development and Demonstration A partnership approach Marta Smart Head of Partnership Funding SSE 33rd largest company in the FTSE 100* 14.64bn market capitalisation* Around 19,500 employees

More information

Transactive Energy Challenge Kickoff Workshop: Tata Consultancy Services Ltd. (TCS)

Transactive Energy Challenge Kickoff Workshop: Tata Consultancy Services Ltd. (TCS) Transactive Energy Challenge Kickoff Workshop: Tata Consultancy Services Ltd. (TCS) Area of Interest: Functionality / Capabilities: Proposed Scenario: Impacts/Why: Partners Needed: Integrated What-if Analyzer

More information

Kintyre Hunterston Link. The upgrade of grid access in Kintyre

Kintyre Hunterston Link. The upgrade of grid access in Kintyre The upgrade of grid access in Kintyre About us Scottish Hydro Electric Transmission plc (SHE Transmission), part of Scottish and Southern Energy Power Distribution (SSEPD), is the licensed electricity

More information

Grid Modernization and Distributed Resource Integration. Malcolm Woolf NASEO Annual Conference

Grid Modernization and Distributed Resource Integration. Malcolm Woolf NASEO Annual Conference Grid Modernization and Distributed Resource Integration Malcolm Woolf NASEO Annual Conference February 6, 2019 0 A revolution waiting to come to the power grid? 1 The grid of the future: more dynamic and

More information

Critical Friends Panel 11 - EPN. 12th November 2015

Critical Friends Panel 11 - EPN. 12th November 2015 Critical Friends Panel 11 - EPN 12th November 2015 Simon Gray, CEO, East of England Energy Group (EEEGR) and Independent Chairman of EPN Panels Welcome from the Chairman 2 Safety and housekeeping No planned

More information

Network Code on Electricity Balancing DSO Associations views on the final version of 23 December 2013

Network Code on Electricity Balancing DSO Associations views on the final version of 23 December 2013 Network Code on Electricity Balancing DSO Associations views on the final version of 23 December 2013 Jorge Tello Guijarro Member of DSOs Expert Group ACER Workshop, Ljubljana, 30th January 2014 DSOs acknowledge

More information

Introducing the SSE Virtual Power Plant. A new, innovative approach to help you reduce your energy costs and earn additional revenue.

Introducing the SSE Virtual Power Plant. A new, innovative approach to help you reduce your energy costs and earn additional revenue. Introducing the SSE Virtual Power Plant A new, innovative approach to help you reduce your energy costs and earn additional revenue. Unlocking the value of energy flexibility The electricity system is

More information

Responses to our RIIO-ED1 Customer Service and Connection Consultation

Responses to our RIIO-ED1 Customer Service and Connection Consultation Responses to our RIIO-ED1 Customer Service and Connection Consultation Overview We consulted on the detailed designs of four incentives: Customer Satisfaction Complaints Metric Time to Connect Incentive

More information

CIGRE STRATEGY Prelude to next Century

CIGRE STRATEGY Prelude to next Century CIGRE STRATEGY 2017-2022 Prelude to next Century Rob Stephen President of CIGRE CIGRE MISSION AND VISION To be the world s foremost collaborative technical reference organization for all aspects of electric

More information

Northumbria Research Link

Northumbria Research Link Northumbria Research Link Walker, S. L. et al. (2005) 'Potential for microgeneration : study and analysis'. London: DTI, with Energy Saving Trust, Element Energy and E- Connect This report is available

More information

Tim Roughan Director of Distributed Resources National Grid, MA USA

Tim Roughan Director of Distributed Resources National Grid, MA USA Tim Roughan Director of Distributed Resources National Grid, MA USA Agenda National Grid Company Overview Market Evolution Market Drivers National Grid s Program Approach Overview of Our Smart Grid Pilot

More information

CAN YOU RELY ON A RELIABILITY OPTION?

CAN YOU RELY ON A RELIABILITY OPTION? CAN YOU RELY ON A RELIABILITY OPTION? Andy Kelly National Power Summit, February 2017 OVERVIEW OF PRESENTATION TOPICS New capacity mechanism is complex but aim today to focus on some key topics RO price

More information

Overview of National Grid s Balancing Services

Overview of National Grid s Balancing Services Overview of National Grid s Balancing Services Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

What are your general views on the idea of a Scottish publicly owned energy company (POEC)?

What are your general views on the idea of a Scottish publicly owned energy company (POEC)? ECONOMY, ENERGY AND FAIR WORK COMMITTEE PUBLICLY OWNED ENERGY COMPANY INQUIRY SUBMISSION FROM SSE What are your general views on the idea of a Scottish publicly owned energy company (POEC)? SSE is one

More information

Global Climate Change: Scotland Taking the Lead. Sue Kearns Head of Renewables Policy Scottish Government

Global Climate Change: Scotland Taking the Lead. Sue Kearns Head of Renewables Policy Scottish Government Global Climate Change: Scotland Taking the Lead Sue Kearns Head of Renewables Policy Scottish Government Overview! Climate Change: Scottish policy context! Main theme: Renewables highlighting marine! Not

More information