AESO Practices for System Access Service. May 31, 2013

Size: px
Start display at page:

Download "AESO Practices for System Access Service. May 31, 2013"

Transcription

1 AESO Practices for System Access Service May 31, 2013

2 Table of Contents 1 Purpose Introduction Practices for System Access Service Conditions for System Access Service Rationale for Conditions for System Access Service Application of the Practices for System Access Service Constraints Managed Under Abnormal Operating Conditions Constraints Managed by a Connection Remedial Action Scheme Constraints Under Normal Operating Conditions... 8

3 1 Purpose This document describes the practices for system access service that the AESO uses when planning the transmission system and when providing a reasonable opportunity for system access to generation and load market participants ( Practices ). The AESO has incorporated these Practices within the AESO s Connection Process. The AESO may amend these Practices from time to time and will advise market participants of any amendments via the AESO Stakeholder Newsletter. The AESO will consistently apply these Practices to ensure that the AESO meets its legislative obligations and the intent of the Alberta government s policy documentation. 2 Introduction The Electric Utilities Act, Transmission Regulation and Alberta government policy documents, including the Transmission Development Policy, establish the Alberta transmission and market framework and impose obligations that the AESO fulfils through ISO rules, Alberta Reliability Standards, practices and processes. Relevant to these Practices are the following obligations: a) the AESO is the sole provider of system access service on the transmission system 1, and must provide such access in a timely 2, efficient, reliable and non-discriminatory manner 3 that gives all market participants wishing to exchange electrical energy and ancillary services a reasonable opportunity to do so 4 ; b) the AESO is required to manage transmission constraints 5 ( constraints ), and provides system access service in a manner that is consistent with section 15(1) of the Transmission Regulation; c) the AESO has the duty to: i) plan the capability of the transmission system to meet the needs of market participants 6, ii) direct the safe reliable and economic operation of the Alberta interconnected electric system 7, and iii) facilitate the operation of the market in a fair, efficient and openly competitive manner that gives all market participants a reasonable opportunity to participate 8. When a market participant requests system access service, the AESO seeks to determine and clearly communicate anticipated constraints. In order to resolve identified constraints, the AESO proposes transmission capacity enhancements when and where appropriate. All new and existing market participants need to be aware of and consider constraints and, in particular, the resulting conditions under which all market participants will be participating in the market. In Alberta's market and transmission framework, there are no explicit or implicit transmission rights. While an area may be unconstrained at the time a new market participant connects, conditions may change and new transmission system constraints on the system may arise. In such cases, these Practices and sections of the ISO rules related to transmission constraint management govern all market participants access to the transmission system and electricity market. 1 EUA s. 17(g) and s EUA s. 16. See also s. 28(2) of the Treg which requires the AESO to make reasonable efforts to ensure that the interconnection of a generating unit to the transmission system is undertaken in a timely manner 3 EUA s EUA s. 16, s. 17(b) and s EUA s. 34, TReg s EUA s. 17(i) 7 EUA s. 17(h) 8 EUA s. 17(b) Page 3

4 The current market and transmission framework relies on an uncongested transmission system, particularly under normal operating conditions 9. System studies may determine that a system access service request will result in constraints in an area. While the AESO plans the transmission system to accommodate all system access service requests, the AESO makes decisions related to the timing and specific conditions for connections in constrained areas. To that end, the AESO has considered, as part of this document, constraints under different system operating conditions related to requests for system access service, and the application of these Practices to the same. In applying the Practices, the AESO notes that all constraints that arise in real-time are treated in the same manner under section of the ISO rules, Real Time Transmission Constraint Management, no matter what the cause of the constraint or if a remedial action scheme has been activated. 3 Practices for System Access Service 3.1 Conditions for System Access Service The following three (3) conditions must all be met before a market participant will be connected in a constrained area: 1. Where the AESO has determined that a single contingency event will result in a constraint that requires a connection remedial action scheme or that the constraint arises under normal operating conditions 10, the AESO must make publicly available a plan to remove the constraint 11. The Alberta reliability standards obligate the AESO to plan a system that avoids single contingency event constraints The AESO must have determined that new and existing market participants that are connected and that are affected by a constraint have the ability to utilize energy market offers and bids which can reasonably be used to determine competitive access to the market through the transmission system or have the operational flexibility to comply with directives. 3. The AESO must have determined that it will be able to operate the system in a safe, reliable and practical manner after the connection of the new market participant. The AESO is of the view that the first condition above is required to provide reasonable system access to existing connected market participants. Given the AESO s legislated duties, the AESO has determined that when it imposes system access service restrictions, such as a connection remedial action scheme for single contingency events, the AESO must also provide a plan to remove those restrictions in a timely manner. Such plans are made public before or at the same time as the AESO s submission of the connection need identification document to the Alberta Utilities Commission ( Commission ). The public documentation of a plan to remove a connection-related constraint may take several forms. The AESO currently provides information on transmission facility projects the AESO proposes to initiate, or has proposed, in: the AESO Long-term Transmission Plan, the AESO Long-term Transmission Plan Progress Report, and need identification documents 9 TReg s. 15(1)(e)(i) and (f) 10 Note that a publicly available plan is not required where constraints arise under abnormal conditions and the AESO can manage the constraint using procedures in real time, and where constraints arise under abnormal operating conditions that involve multiple contingencies where a connection remedial action scheme is required. 11 EUA s. 34(1), Transmission Regulation s TPL-002-AB-0 System Performance Following Loss of a Single BES Element Page 4

5 All of these documents are public and specify the transmission facilities that are proposed to be built and the planned in-service date for those facilities. The AESO must ensure that the transmission facilities proposed in these documents are sufficient to remove any identified connection-related constraints. When the AESO determines that constraints will arise under normal operating conditions after a connection, the AESO may determine it is appropriate to file an exception, for approval by the Commission, under section 15(2) of the Transmission Regulation. In these circumstances, the AESO may document the plan to remove the constraint within an exception study, which will be filed with the Commission at the same time as the AESO s connection need identification document is submitted. The exception study will identify constraints, the transmission facilities that are needed to remove the constraints, and provide an estimate of the in-service date for those facilities. The AESO may also determine that a broader local area study is needed when there are several new connections proceeding in the same general time frame in an area. In these circumstances, the AESO will document the transmission development related to the group of connections within the local area capability study. The local area capability study examines the AESO s ability to provide system access under market dispatch conditions when certain abnormal operating conditions exist on the transmission system. The local area capability study identifies the constraints that arise and sets out an acceptable transmission facility solution with a proposed in-service date for that solution. The local area capability study results will be made publicly available and referenced in one or more of the need identification document filings related to the study. Exception studies and local area capability studies are documents used only to provide sufficient information to market participants to allow a system access service request to temporarily proceed through the connection process. When these studies are referenced as part of an AESO connection need identification document submission, then, in advance of energizing the connection, the AESO will identify the transmission facility enhancements required to remove the constraint in a Long-term Transmission Plan or a Long-term Transmission Plan Progress Report or a related system need identification document submitted to the Commission. 3.2 Rationale for Conditions for System Access Service The AESO provides the following commentary on the conditions set out above to aid market participants in understanding the high level rationale used by the AESO in developing these Practices. The rationale for the first condition is that it: (a) provides new investors with greater certainty around the approval process related to system access service requests; (b) grants investors and all market participants the ability to consider the potential curtailment risks related to future connections beyond their own project(s); and (c) gives existing market participants clarity regarding the impacts of new connections and the alignment of the AESO processes with the Transmission Regulation 13 requirements. The rationale for the second condition is that it: (a) ensures market participants have the ability to compete in the market; (b) provides exceptions for load based upon operational flexibility; and 13 TReg s 15 Page 5

6 (c) supports the efficient use of the transmission system and the timely provision of system access service. The second condition encourages new generation investment and avoids unreasonable market participant curtailment. The AESO is of the view that if a market participant s energy market offers or bids can be reasonably used to determine competitive system access, then it is also reasonable to allow a related connection to proceed even when constraints arise. If market participants offers represent their willingness to participate in the electricity market when there are no constraints, then it follows that it is also reasonable to use those same offers as a basis to curtail during a constraint. Load market participants, in particular, may not be able to bid or may not have the operational flexibility to significantly vary consumption to provide a competitive response to system changes. In those situations where market participants are restricted from providing offers or bids due to the nature of the constraint, or where the market participant does not have operational flexibility, the AESO will advise the market participant of the timing of planned transmission facilities, giving the market participant the opportunity to align their development plans with the planned transmission capability of the transmission system. The rationale for the third condition is that it: (a) outlines a practical approach which recognizes operational limitations; (b) enables the AESO to deal with complex transmission system issues that may arise over time; and (c) provides for safe, reliable and economic operation of the interconnected electric system to the benefit of both new and existing market participants in an area. The third condition reflects the AESO s legislated duties with regard to the safe, reliable and economic operation of the system, which includes a consideration of practicality of operation. When deciding whether a connection should proceed, the AESO is obligated to consider the impact of the connection on its ability to operate the system given existing constraints and potential other new constraints in the area or on the transmission system generally. An important consideration is the ability of a new market participant facility to comply with directives and, in particular, the ability to curtail. 14 When new connections impact the AESO s ability to operate the system in a safe, reliable and practical manner, the AESO provides a plan which aligns with the availability of transmission system enhancements or provides other solutions, where possible, that alleviate the concern. The affected market participant may consider staging the proposed connection in a way that utilizes the existing and planned transmission capacity. 4 Application of the Practices for System Access Service The AESO applies the Practices to all system access service requests. The AESO individually assesses each system access service request and develops a specific and appropriate connection proposal. System access service requests may lead to the AESO s determination that constraints will arise under one or more operating conditions, including (i) under normal operating conditions, (ii) under abnormal operating conditions and (iii) under operating conditions where a connection remedial action scheme is required. The application of the Practices to each of these operating conditions is discussed in the sections below. It is important to note that there are operating conditions where condition one of the Practices is not relevant. Specifically, condition one does not need to be met when constraints are anticipated to arise: under abnormal operating conditions and the AESO can manage the constraint using procedures in real time, and under abnormal operating conditions that involve multiple contingencies where a connection remedial action scheme is required 14 ISO Rules Section 301.2: ISO Directives Page 6

7 For clarity, conditions two and three of the Practices must be met in all circumstances where constraints are anticipated to arise. 4.1 Constraints Managed Under Abnormal Operating Conditions System studies related to a system access service request may indicate that constraints will exist under abnormal operating conditions. If the AESO can manage such constraints by following procedures aligned with the constraint management sections of the ISO rules and market participants energy market offers and bids can be reasonably used to determine competitive system access, the AESO allows the connection to proceed through the AESO Connection Process once it has determined that conditions 2 and 3 of the Practices are met. A plan under condition 1 of the Practices to relieve the constraint may not be required if the AESO expects the threshold set out in section 15 of the Transmission Regulation will be met. The AESO notifies affected market participants of the impact of the constraint as part of the Connection Process. 4.2 Constraints Managed by a Connection Remedial Action Scheme Connection remedial action schemes ensure the reliability of the transmission system under abnormal operating conditions where one or more transmission facilities are out of service and provides for effective and efficient use of the transmission system on a temporary basis until transmission facility enhancements can occur. System studies related to a system access request may indicate that constraints will exist under abnormal operating conditions and the constraint may be such that the system is not adequately protected through system controller action alone until system enhancements are in place. If the AESO can manage system reliability with the use of a connection remedial action scheme(s) and a plan to remove the constraint has been identified and made publicly available, then the AESO gives the market participant the option to connect using a temporary connection remedial action scheme while the permanent wires solutions are being built. The connection remedial action scheme automatically curtails system access when abnormal operating conditions occur. The connecting market participant can choose to accept connection with a temporary connection remedial action scheme or stage the proposed connection development in a way that utilizes the existing transmission capacity or align the project in-service date with the AESO planned transmission enhancements. The connection remedial action scheme is assigned to the connecting market participant only and is not shared with existing connected market participants who may also be effective in managing the constraint. The AESO is of the view that this is a necessary approach which is practical, fair and equitable for all market participants and is consistent with the AESO s legislative obligations 15. When a connection remedial action scheme is a reasonable alternative, the AESO will assign a temporary connection remedial action scheme to the last load or generator connecting to the system in a congested area. This is a practical solution to a temporary constraint condition, and allows the market participant some access to compete. The order of connection is determined by the AESO s connection queue management process in effect at the time. The pro rata assignment of a connection remedial action scheme to multiple generating units that are effective in relieving the constraint is not practical and will not be used. As mentioned above, the AESO will assign the connection remedial action scheme to the new generation market participant, who has the 15 Including the obligation as s. 18(1) of the EUA to operate the power pool in a manner that is fair, efficient and open to all market participants exchanging or wishing to exchange electric energy through the power pool and that gives all market participants a reasonable opportunity to do so. Page 7

8 option to accept the limited system access service conditions, stage the project development, or align the project timeline to when the required facilities are in place. Connection remedial action scheme assignment and the order of connection remedial action scheme activation in a constrained area is determined by the market participant project status in the connection queue that is maintained as part of the AESO Connection Process. For practical reasons, connection remedial action schemes are assigned and utilized on a last on first off basis using the project s relative position in the connection queue in the constrained area. Once the connection remedial action scheme is activated and the system stabilizes, then the normal constraints management protocol is utilized. The curtailment caused by the connection remedial action scheme is only temporary until normal procedures can be employed. If the AESO cannot practically operate the system in this manner, the use of a connection remedial action scheme solution may not be an acceptable solution for the AESO and the connecting market participant must either choose to stage the proposed connection development in a way that utilizes the existing transmission capacity or they must align the project in-service date with the AESO planned transmission enhancements. If a temporary single contingency connection remedial action scheme is required for a connection, the AESO may require the connection remedial action scheme to also have the functionality to manage low probability multiple contingency events on a permanent basis. These Practices provide for increased system access service in post-contingency situations and is permitted provided the AESO continues to meet its obligations under section 15 of the Transmission Regulation. Therefore, condition one of the Practices does not need to be met when constraints are anticipated to arise due to multiple contingencies and a connection remedial action scheme is required. 4.3 Constraints Under Normal Operating Conditions Constraints that are anticipated to arise under normal operating conditions are contemplated in regulation 16 and government policy but are only authorized in specific and limited circumstances when such exceptions are filed with the Commission for approval 17. Normal operating conditions occur when all transmission facilities in an area are in service and the system can be reliably operated without system controller action should any single transmission facility become unavailable. When it is determined that constraints are anticipated to arise under normal operating conditions, the AESO connects market participants and facilitates competition for system access for all market participants. From a system access service point of view, proceeding to connect market participants under normal operating conditions does not create transmission rights, explicit or implicit, for existing market participants and is aligned with government policy. The transmission system is also being used more efficiently and system access service is provided on a timelier basis when connections are advanced in this manner. 16 TReg s.15(1)(e)(i) 17 TReg s.15(2) Page 8

Assessment of Load Shed Service for Import (LSSi) Product

Assessment of Load Shed Service for Import (LSSi) Product Assessment of Load Shed Service for Import (LSSi) Product Date: March 27, 2014 Prepared by: Prepared for: Mike Law Jenny Chen Senior Market Design Specialist Vice President, Market Services Table of Contents

More information

Policy Direction for Alberta s Capacity Market Framework

Policy Direction for Alberta s Capacity Market Framework Policy Direction for Alberta s Capacity Market Framework August 15, 2017 Alberta Department of Energy Table of Contents Executive Summary... 1 1 Introduction... 2 2 Policy Direction for Alberta s Capacity

More information

20 Nov IEEE Chapters Seminar Grid Energy Storage: Policies. John Martin, AESO

20 Nov IEEE Chapters Seminar Grid Energy Storage: Policies. John Martin, AESO By John Martin, P. Eng., Senior Tariff and Special Projects Advisor Alberta Electric System Operator Alberta established the regulatory framework for its electric system when generators and loads were

More information

AESO Stakeholder Update on Mothball Outages. July 25, 2016

AESO Stakeholder Update on Mothball Outages. July 25, 2016 AESO Stakeholder Update on Mothball Outages July 25, 2016 Agenda 1. Background Issues Rationale 2. Mothball Rule Definition of Mothball Outage Overview of Section 306.7 3. Mothball Outages in the Market

More information

Information Document Provision of System Access Service and the Connection Process ID No T

Information Document Provision of System Access Service and the Connection Process ID No T and the Connection Process Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between

More information

AESO Response to Stakeholders Feedback

AESO Response to Stakeholders Feedback AESO Response to Stakeholders Feedback Designing Alberta s Capacity Market stakeholder sessions held January 12 and 16, 2017 To initiate stakeholder consultation on the capacity market design, the AESO

More information

Rule Change Notice: Removal of constrained off compensation for Outages of network equipment (RC_2018_07)

Rule Change Notice: Removal of constrained off compensation for Outages of network equipment (RC_2018_07) Rule Change Notice: Removal of constrained off compensation for Outages of network equipment (RC_2018_07) This notice is given under clause 2.5.7 of the Wholesale Electricity Market Rules (Market Rules).

More information

Alberta Intertie Restoration Initiative Discussion Paper

Alberta Intertie Restoration Initiative Discussion Paper Alberta Intertie Restoration Initiative Discussion Paper March 25, 2010 Table of Contents 1.0 Executive Summary... 2 2.0 Intertie Capacity Restoration Policy Background... 3 2.1 Obligation to Restore Intertie

More information

Energy Storage Integration in Alberta s Energy Only Market. Kevin Dawson Director, Market Design Alberta Electric System Operator

Energy Storage Integration in Alberta s Energy Only Market. Kevin Dawson Director, Market Design Alberta Electric System Operator Energy Storage Integration in Alberta s Energy Only Market Kevin Dawson Director, Market Design Alberta Electric System Operator Outline The AESO and Alberta s Wholesale Electricity Market About the AESO

More information

Principles for Stakeholder Engagement, and a Common Framework, for MSA Public Projects

Principles for Stakeholder Engagement, and a Common Framework, for MSA Public Projects Principles for Stakeholder Engagement, and a Common Framework, for MSA Public Projects TABLE OF CONTENTS PAGE 1 INTRODUCTION... 1 1.1 Reason for this report... 1 1.2 Scope of principles and project framework...

More information

Janine Sullivan Vice President, Finance and Chief Financial Officer

Janine Sullivan Vice President, Finance and Chief Financial Officer Janine Sullivan Vice President, Finance and Chief Financial Officer FortisAlberta Inc 320 17 th Avenue SW Calgary, Alberta T2S 2V1 Telephone: 403-514-4992 (direct) Fax: 403-514-5992 Janine.sullivan@fortisalberta.com

More information

Date of Request for Comment: April 7, 2017 Period of Comment: April 7, 2017 through May 5, 2017

Date of Request for Comment: April 7, 2017 Period of Comment: April 7, 2017 through May 5, 2017 Market Participant Comments and AESO Replies Matrix Proposed Amended Section 304.3, Wind and Solar Power Ramp Up Management ( amended Section 304.3 ) Date of Request for Comment: April 7, 2017 Period of

More information

ATTACHMENT B TECHNICAL AND OPERATIONAL IMPLEMENTATION OF THE TARIFF FOR WHOLESALE DISTRIBUTION LOAD

ATTACHMENT B TECHNICAL AND OPERATIONAL IMPLEMENTATION OF THE TARIFF FOR WHOLESALE DISTRIBUTION LOAD ATTACHMENT B TECHNICAL AND OPERATIONAL IMPLEMENTATION OF THE TARIFF FOR WHOLESALE DISTRIBUTION LOAD 1. Metering And Communications Equipment: Data retrieval requirements, procedures, and schedules shall

More information

APPENDIX B PLANNING FRAMEWORK. This Appendix B describes the process to be used by the Midwest ISO in planning

APPENDIX B PLANNING FRAMEWORK. This Appendix B describes the process to be used by the Midwest ISO in planning FERC Electric Tariff, First Revised Rate Schedule No. 1 Original Sheet No. 103 I. Overview. PLANNING FRAMEWORK This Appendix B describes the process to be used by the in planning the Transmission System.

More information

Appendix 9C1 Transmission Loading Relief Procedure Eastern Interconnection Version 2b

Appendix 9C1 Transmission Loading Relief Procedure Eastern Interconnection Version 2b Appendix 9C1 Transmission Loading Relief Procedure Eastern Interconnection Version 2b [Appendix 9C1B, Interchange Transaction Reallocation During TLR Levels 3a and 5a ] [Appendix 9C1C, Interchange Transaction

More information

Addressing Affected System Impacts of Generator Interconnection: Processes and Principles

Addressing Affected System Impacts of Generator Interconnection: Processes and Principles Addressing Affected System Impacts of Generator Interconnection: Processes and Principles August 5, 2013 Table of Contents 1 Executive Summary... 2 2 Introduction... 2 3 Stakeholder Process and Schedule...

More information

Midwest ISO EIM Start-up and Exiting Issues Todd Ramey, Executive Director Market Administration. March 7-8, 2011

Midwest ISO EIM Start-up and Exiting Issues Todd Ramey, Executive Director Market Administration. March 7-8, 2011 Midwest ISO EIM Start-up and Exiting Issues Todd Ramey, Executive Director Market Administration March 7-8, 2011 Agenda Greetings and Introductions Introduction of the Midwest ISO Overview of the Midwest

More information

Regulatory Approach to Maintaining Local Security of Supply in Electricity

Regulatory Approach to Maintaining Local Security of Supply in Electricity An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Regulatory Approach to Maintaining Local Security of Supply in Electricity Information Paper Reference: CRU17346 Date Published: 18/12/2017

More information

April 28, Filing of CAISO Rate Schedule No. 90 Docket No. ER

April 28, Filing of CAISO Rate Schedule No. 90 Docket No. ER California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 April 28, 2017 Re: California

More information

NYISO Pilot Program Guide

NYISO Pilot Program Guide NYISO Pilot Program Guide October 2017 Table of Contents ABOUT THE NYISO... 4 NYISO PILOT PROGRAM... 5 Overview of the Pilot Program... 5 Value of the Pilot Program to NYISO Stakeholders and Pilot Participants...

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 2009-126 Needs Identification Document Application Southern Alberta Transmission System Reinforcement September 8, 2009 ALBERTA UTILITIES COMMISSION Decision 2009-126: Needs Identification Document

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 22274-D01-2018 Provost to Edgerton and Nilrem to Vermilion Transmission System Reinforcement January 12, 2018 Alberta Utilities Commission Decision 22274-D01-2018 Provost to Edgerton and Nilrem

More information

Distributed Energy Resources (DER) Queue Management

Distributed Energy Resources (DER) Queue Management Distributed Energy Resources (DER) Queue Management FortisAlberta s Distributed Energy Resource (DER) Queue Management stages are applicable to every DER Customer project, whether the project is the only

More information

Alberta Energy-Capacity Market Framework Engagement November 2017

Alberta Energy-Capacity Market Framework Engagement November 2017 Questions for discussion The engagement is seeking feedback on the six questions outlined in the table below. Please provide your input on these questions in Table 1 on the next three pages. Please submit

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service

More information

March Protected area boundary adjustments fall within one of three categories:

March Protected area boundary adjustments fall within one of three categories: PROVINCIAL PROTECTED AREA BOUNDARY ADJUSTMENT POLICY, PROCESS AND GUIDELINES March 2010 1. BACKGROUND: Provincial protected areas 1 are set aside to provide a wide range of opportunities that support tourism

More information

Alberta Capacity Market

Alberta Capacity Market Alberta Capacity Market Comprehensive Market Design (CMD 1) Design Proposal Document Section 1: Overview of the Alberta Capacity Market Prepared by: Alberta Electric System Operator Date: January 26, 2018

More information

Guidance for Handling Policy Initiatives within the Decisional Authority or Advisory Role of the EIM Governing Body

Guidance for Handling Policy Initiatives within the Decisional Authority or Advisory Role of the EIM Governing Body Policy Adopted Policy Adopted I. Introduction Relying on recommendations from the EIM Transitional Committee comprised of stakeholders from throughout the region, the ISO Board of Governors established

More information

Market Rule Amendment Proposal

Market Rule Amendment Proposal Market Rule Amendment Proposal PART 1 MARKET RULE INFORMATION Identification No.: MR-00380-R00 Subject: Congestion Management Settlement Credits (CMSC) Title: Non-transmission Related Constrained Off Payments

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

This process may apply to any Grade 1 9 posts within the University covered by the Framework Agreement.

This process may apply to any Grade 1 9 posts within the University covered by the Framework Agreement. Matching and Slotting Process 1. Aims and application of the process This process aims to reduce the potential negative impact on staff involved in organizational change e.g. re-shaping or restructuring

More information

Transmission Loading Relief Eastern Interconnection

Transmission Loading Relief Eastern Interconnection Transmission Loading Relief Eastern Interconnection Purpose: This standard defines procedures for curtailment and reloading of Interchange Transactions to relieve overloads on transmission facilities modeled

More information

Attachment 1-IRO Transmission Loading Relief Procedure Eastern Interconnection

Attachment 1-IRO Transmission Loading Relief Procedure Eastern Interconnection Standard IRO-006-0 Reliability Coordination Transmission Loading Relief Attachment 1-IRO-006-0 Transmission Loading Relief Procedure Eastern Interconnection Purpose This standard defines procedures for

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL VOLUME NO. III Page No. 655 CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL VOLUME NO. III Page No. 656 ANCILLARY SERVICES REQUIREMENTS PROTOCOL Table of Contents ASRP 1

More information

Standard IRO Reliability Coordination Transmission Loading Relief

Standard IRO Reliability Coordination Transmission Loading Relief Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:

More information

Seminar on African Electrical Interconnection. Module 7 - Market Operational Structures

Seminar on African Electrical Interconnection. Module 7 - Market Operational Structures Seminar on African Electrical Interconnection Module 7 - Market Operational Structures Module 7 - Market Operational Structures Contents 1) Power Market Principles 2) Major Operational Issues 3) Transmission

More information

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:

More information

New Brunswick Electricity Business Rules. Chapter 3 Reliable Operations

New Brunswick Electricity Business Rules. Chapter 3 Reliable Operations New Brunswick Electricity Business Rules Chapter 3 Reliable Operations TABLE OF CONTENTS CHAPTER 3 RELIABLE OPERATIONS... 2 3.0 System Operator Roles and Responsibilities... 2 3.1 Reliability Assessments...

More information

ERGEG Guidelines for Good Practice on Open Season Procedures (GGPOS) Ref: C06-GWG-29-05c 21 May 2007

ERGEG Guidelines for Good Practice on Open Season Procedures (GGPOS) Ref: C06-GWG-29-05c 21 May 2007 ERGEG Guidelines for Good Practice on Open Season Procedures (GGPOS) Ref: C06-GWG-29-05c 21 May 2007 European Regulators Group for Electricity and Gas Contact: Council of European Energy Regulators ASBL

More information

Flexible working policy and procedure Updated June 2014

Flexible working policy and procedure Updated June 2014 Flexible working policy and procedure Updated June 2014 Contents Page Flowchart: Requesting flexible working 2 Scope 3 Statement of commitment 3 Introduction to flexible working 3 The right to request

More information

3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the

3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the FERC ELECTRIC TARIFF First Revised Sheet No. 121 ORIGINAL VOLUME NO. I Replacing Original Sheet No. 121 3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. 3.1 Nature of Relationship. Each Participating

More information

Discussion paper for the stakeholder meeting of 9 December 2014

Discussion paper for the stakeholder meeting of 9 December 2014 Discussion paper for the stakeholder meeting of December Background 1 1 1 0 1 Regulation (EU) No / (hereafter: the basic Regulation) establishes rules governing compliance with access and benefit-sharing

More information

Resource Access Roads Framework

Resource Access Roads Framework Resource Access Roads Framework This framework describes the application, principles, roles and responsibilities, policy parameters and processes that will be used to manage resource access roads. 1 Resource

More information

Generator Contingency & RAS Modeling

Generator Contingency & RAS Modeling Generator Contingency & RAS Modeling Revised Issue Paper & Straw Proposal November 15, 2016 Perry Servedio Sr. Market Design & Regulatory Policy Developer Agenda Time Topic Presenter 9:00-9:05 Introduction

More information

PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO

PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO This Proposal outlines the terms and conditions in a proposed Appendix to the Southwest Power Pool's ("SPP's") Membership Agreement

More information

INTERNATIONAL STANDARD ON AUDITING 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE CONTENTS

INTERNATIONAL STANDARD ON AUDITING 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE CONTENTS Introduction INTERNATIONAL STANDARD ON AUDITING 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE (Effective for audits of financial statements for periods beginning on or after December 15, 2009) +

More information

ISO Rules Updated: September 5, 2017

ISO Rules Updated: September 5, 2017 Updated: September 5, 2017 CONTENTS CONTENTS Division 101 Interpretation Division 101 Interpretation Division 103 Administration Section 103.1 Confidentiality Section 103.2 Dispute Resolution Section 103.3

More information

Standard TPL System Performance Under Normal Conditions

Standard TPL System Performance Under Normal Conditions Standard TPL-001-0.1 System Performance Under rmal Conditions Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when

More information

All Source Request for Proposals Interim Summary

All Source Request for Proposals Interim Summary All Source Request for Proposals Interim Summary Introduction and Request for Proposal Overview Northern Indiana Public Service Company ( NIPSCO ) does business in the State of Indiana as a regulated public

More information

Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets

Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets March 8, 2010 Revised Draft Final Proposal for Participation of Non- Generator Resources

More information

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1) (R1 FAC-010-AB-2.1) 1 Purpose This document sets out the System Operating Limits Methodology the Alberta Electric System Operator ( AESO ) uses for any studies conducted on the interconnected electric

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF Sheet No. 691 ORIGINAL VOLUME NO. III

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF Sheet No. 691 ORIGINAL VOLUME NO. III FERC ELECTRIC TARIFF Sheet No. 691 (a) (b) (c) adjust interchange transaction schedules (ITSs) as required under Existing Contracts in accordance with the procedures in the SBP and the SP for the management

More information

Municipality of Crowsnest Pass Policy

Municipality of Crowsnest Pass Policy Municipality of Crowsnest Pass Policy Policy No.: Policy Title: Department: Council Approval: Reviewed: Revised: Supersedes Policy/Bylaw: 1806-01 Training and Educational Development Policy Human Resources

More information

Using Business Architecture blueprints to mitigate the organizational impact of policy change in Alberta s deregulated electric industry

Using Business Architecture blueprints to mitigate the organizational impact of policy change in Alberta s deregulated electric industry Using Business Architecture blueprints to mitigate the organizational impact of policy change in Alberta s deregulated electric industry Steve Waller Business Architecture Innovation Summit Reston, VA.

More information

TPL 001 AB 0 System Performance Under Normal Conditions

TPL 001 AB 0 System Performance Under Normal Conditions Alberta Reliability Standard System Performance Under rmal Conditions TPL-001-AB-0 TPL 001 AB 0 System Performance Under rmal Conditions 1. Purpose The purpose of this reliability standard is to ensure

More information

Public Consultation Guidelines - Electricity, Gas & Water Licences and Electricity & Gas Standard Form Contracts

Public Consultation Guidelines - Electricity, Gas & Water Licences and Electricity & Gas Standard Form Contracts Public Consultation Guidelines - Electricity, Gas & Water Licences and Electricity & Gas Standard Form Contracts April 2016 Public Consultation Guidelines - Electricity, Gas & Water Licences and Electricity

More information

May 1, To: Parties currently registered on Proceeding Distributed Generation Review Proceeding Application A001

May 1, To: Parties currently registered on Proceeding Distributed Generation Review Proceeding Application A001 May 1, 2017 To: Parties currently registered on Proceeding 22534 Distributed Generation Review Proceeding 22534 Application 22534-A001 Process for Proceeding 22534 1. On March 31, 2017, the Alberta Utilities

More information

Alberta Capacity Market

Alberta Capacity Market Alberta Capacity Market Comprehensive Market Design (CMD 1) Design Proposal Document Section 4: Forward Capacity Auction Prepared by: Alberta Electric System Operator Date: January 26, 2018 Table of Contents

More information

Business Practice Manual for Reliability Requirements. Version 34

Business Practice Manual for Reliability Requirements. Version 34 Business Practice Manual for Reliability Requirements Version 34 Last Revised: January 1, 2009July 28, 2010 Approval History Approval Date: 3/27/09 Effective Date: 3/31/09 BPM Owner: Chetty Mamandur BPM

More information

JCM Drill Down Report -- Draft. March 21, 2014

JCM Drill Down Report -- Draft. March 21, 2014 JCM Drill Down Report -- Draft March 21, 2014 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill

More information

1. Name of Company or Organization. Solas Energy Consulting on behalf of the Renewable Energy Coalition

1. Name of Company or Organization. Solas Energy Consulting on behalf of the Renewable Energy Coalition [print] 1. Name of Company or Organization Solas Energy Consulting on behalf of the Renewable Energy Coalition 8/28/18 12:13:11 PM MDT 2. Alberta Energy intends to post all of the feedback received from

More information

A Common Understanding: Fair, Efficient and Openly Competitive

A Common Understanding: Fair, Efficient and Openly Competitive A Common Understanding: Fair, Efficient and Openly Competitive TABLE OF CONTENTS PAGE INTRODUCTION... 1 FAIR, EFFICIENT AND OPENLY COMPETITIVE... 1 ISSUE 1: CLOVER BAR OFFER STRATEGY (2001)... 4 ISSUE

More information

Dispatching Variable Generation Resources

Dispatching Variable Generation Resources Dispatching Variable Generation Resources A Discussion Paper for Stakeholder Engagement 91 (Renewable Integration) Table of Contents Introduction... 3 IESO Dispatch Processes... 5 Registration... 5 Dispatch

More information

DEPARTMENT OF LABOUR

DEPARTMENT OF LABOUR Notice R. 1394 1 December 1999 DEPARTMENT OF LABOUR EMPLOYMENT EQUITY ACT, 1998 (Act No. 55 of 1998) Code of good practice: Preparation, implementation and monitoring of employment equity plans Notice

More information

Alternative Connection Application and Offer Process Proposal

Alternative Connection Application and Offer Process Proposal Alternative Connection Application and Offer Process Proposal Decision Paper 31 May 2016 Table of Contents 1. Executive Summary... 4 2. Introduction... 7 2.1 Purpose of the Paper... 7 2.2 Structure of

More information

Draft 2011 Long-term Transmission Plan. Stakeholder Session June 20, 2011

Draft 2011 Long-term Transmission Plan. Stakeholder Session June 20, 2011 Draft 2011 Long-term Transmission Plan Stakeholder Session June 20, 2011 Agenda Highlights of draft 2011 Long-term Transmission Plan Discussion of project costs and rate impact Impact of transmission constraints

More information

Capacity Market Regulation Feedback Form

Capacity Market Regulation Feedback Form Capacity Market Regulation Feedback Form ] 1. Name of Company or Organization Cities of Lethbridge and Red Deer 8/7/18 10:45:41 AM MDT 2. Alberta Energy intends to post all of the feedback received from

More information

LFC Block Operational Agreement Ireland and Northern Ireland

LFC Block Operational Agreement Ireland and Northern Ireland LFC Block Operational Agreement Ireland and Northern Ireland For Publication; 05/10/2018 Notice This document, provided by EirGrid and SONI, is the draft for stakeholder consultation of the proposal for

More information

Exhibit A. Reliability Standards Proposed for Approval

Exhibit A. Reliability Standards Proposed for Approval Exhibit A Reliability Standards Proposed for Approval Proposed New Standard IRO-006-5 Standard IRO-006-5 Reliability Coordination Transmission Loading Relief A. Introduction 1. Title: Reliability Coordination

More information

All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for

All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for a common set of requirements, in accordance with Article

More information

SRI LANKA AUDITING STANDARD 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE CONTENTS

SRI LANKA AUDITING STANDARD 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE CONTENTS SRI LANKA AUDITING STANDARD 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE Introduction (Effective for audits of financial statements for periods beginning on or after 01 January 2012) CONTENTS Paragraph

More information

Economics & Markets: Capacity Markets (Presentation to the CIAC) April 17 th, 2018

Economics & Markets: Capacity Markets (Presentation to the CIAC) April 17 th, 2018 Economics & Markets: Capacity Markets (Presentation to the CIAC) April 17 th, 2018 The information contained in this document is for information purposes only, and the AESO is not responsible for any errors

More information

Phase Two Wind Integration

Phase Two Wind Integration Phase Two Wind Integration RECOMMENDATION PAPER Kelly Gunsch, Vice-President, Market Services Date: December 20, 2012 Prepared by: Mariya Goloshchapova, Wind Integration Intern cc: Jacques Duchesne, Wind

More information

Fluid Tailings Management for Oil Sands Mining Projects. 1 Introduction AER Requirements What s New in This Edition...

Fluid Tailings Management for Oil Sands Mining Projects. 1 Introduction AER Requirements What s New in This Edition... Directive 085 Release date: October 12, 2017 Effective date: October 12, 2017 Replaces previous edition issued July 14, 2016 Fluid Tailings Management for Oil Sands Mining Projects The Alberta Energy Regulator

More information

CANADA-NEWFOUNDLAND AND LABRADOR BENEFITS PLAN GUIDELINES (DRAFT)

CANADA-NEWFOUNDLAND AND LABRADOR BENEFITS PLAN GUIDELINES (DRAFT) CANADA-NEWFOUNDLAND AND LABRADOR BENEFITS PLAN GUIDELINES (DRAFT) January 2016 Comments on the proposed draft Guidelines can be submitted in writing to the address below or via email to: information@cnlopb.ca

More information

DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS FACT SHEET

DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS FACT SHEET DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS FACT SHEET FOR DISTRIBUTED GENERATION AND LARGE MICRO-GENERATION Purpose This fact sheet outlines the steps required for you to undertake an interconnection

More information

Energy Imbalance Market Design Straw Proposal and Issue Paper. Stakeholder Meeting April 11, 2013

Energy Imbalance Market Design Straw Proposal and Issue Paper. Stakeholder Meeting April 11, 2013 Energy Imbalance Market Design Straw Proposal and Issue Paper Stakeholder Meeting April 11, 2013 Agenda Time Topic Presenter 10:00 10:10 Introduction Mercy Parker-Helget 10:10 10:45 Opening Remarks Don

More information

Technologies to Enable Wind Power Integration. John Kehler Technical Lead System Performance

Technologies to Enable Wind Power Integration. John Kehler Technical Lead System Performance Technologies to Enable Wind Power Integration John Kehler Technical Lead System Performance Presentation Outline The AESO Overview of Wind Development in Alberta Technologies Wind Power Forecasting System

More information

Storage as a Transmission Asset Stakeholder Comment Template

Storage as a Transmission Asset Stakeholder Comment Template Storage as a Transmission Asset Stakeholder Comment Template Submitted by Company Date Submitted Jan Strack San Diego Gas & Electric June 7, 2018 Please use this template to provide your comments on the

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on June

More information

IN THE MATTER OF THE SECURITIES ACT, R.S.O. 1990, CHAPTER S.5, AS AMENDED (the ACT) AND IN THE MATTER OF CHI-X CANADA ATS LIMITED ORDER

IN THE MATTER OF THE SECURITIES ACT, R.S.O. 1990, CHAPTER S.5, AS AMENDED (the ACT) AND IN THE MATTER OF CHI-X CANADA ATS LIMITED ORDER Ontario Commission des P.O. Box 55, 19 th Floor CP 55, 19e étage Securities valeurs mobilières 20 Queen Street West 20, rue queen ouest Commission de l Ontario Toronto ON M5H 3S8 Toronto ON M5H 3S8 IN

More information

Contents. DRAFT Capacity Deliverability Fact Finding Summary Report

Contents. DRAFT Capacity Deliverability Fact Finding Summary Report DRAFT Capacity Deliverability Fact Finding Summary Report Contents 1 Background... 3 2 Overview of findings... 5 2.1 Implement methods for setting limits that respect the physical topology of the system

More information

Straw Proposal. Post-Release 1 MRTU Functionality for Demand Response

Straw Proposal. Post-Release 1 MRTU Functionality for Demand Response California Independent System Operator Corporation Executive Summary Straw Proposal Post-Release 1 MRTU Functionality for Demand Response The (CAISO) has a goal of helping to develop demand response resources

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Electric Storage Participation in ) Markets Operated by Regional ) Docket Nos. RM16-23; AD16-20 Transmission Organizations and )

More information

Scarcity pricing in Alberta under the new market design

Scarcity pricing in Alberta under the new market design Draft for Discussion Purposes Scarcity pricing in Alberta under the new market design AESO Energy & Ancillary Services Working Group 1 Disclaimer This document is submitted to the Energy and Ancillary

More information

NBP (ATG) IR 01 March 5, Reference: NBP 18.01

NBP (ATG) IR 01 March 5, Reference: NBP 18.01 NBP (ATG) IR 01 March 5, 2015 Reference: NBP 18.01 a. Who does NB Power intend to have testify with respect to the evidence? b. In preparing the evidence, who has reviewed or prepared portions of the evidence

More information

Federal Energy Regulatory Commission Working Paper on Standardized Transmission Service and Wholesale Electric Market Design

Federal Energy Regulatory Commission Working Paper on Standardized Transmission Service and Wholesale Electric Market Design Federal Energy Regulatory Commission Working Paper on Standardized Transmission Service and Wholesale Electric Market Design To enhance competition in wholesale electric markets and broaden the benefits

More information

5.4 Post Contingency Local Load Relief Warning

5.4 Post Contingency Local Load Relief Warning 5.4 Post Contingency Local Load Relief Warning Post Contingency Local Load Relief Warning Non-Market Post Contingency Local Load Relief Warning The purpose of the Post Contingency Local Load Relief Warning

More information

DECISION ON A TEMPORARY REGIME FOR THE PROVISION OF ANCILLARY SERVICES AND BALANCING OF THE POWER SYSTEM OF BOSNIA AND HERZEGOVINA

DECISION ON A TEMPORARY REGIME FOR THE PROVISION OF ANCILLARY SERVICES AND BALANCING OF THE POWER SYSTEM OF BOSNIA AND HERZEGOVINA Pursuant to Articles 4.1, 4.2, 5.3 and 9.7 of the Law on Transmission of Electric Power, Regulator, and System Operator in Bosnia and Herzegovina ( Official Gazette of BIH, 7/02, 13/03, 76/09 and 1/11),

More information

NERC Reliability Functional Model Technical Document Version 5

NERC Reliability Functional Model Technical Document Version 5 Reliability Functional Model Technical Document Version 5 Prepared by the Functional Model Working Group This document is a companion to Version 5 of the Functional Model. It provides context, explanations,

More information

JCM Drill Down Report. February 19, 2015

JCM Drill Down Report. February 19, 2015 JCM Drill Down Report February 19, 2015 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill Down Report

More information

Information Document Regulating Reserve ID # R

Information Document Regulating Reserve ID # R Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

Standard TPL System Performance Following Extreme BES Events

Standard TPL System Performance Following Extreme BES Events A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-1 3. Purpose: System simulations

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on December

More information

March 18, Docket Nos. ER and EL Exceptional Dispatch Informational Report Covering Period up to February 2019

March 18, Docket Nos. ER and EL Exceptional Dispatch Informational Report Covering Period up to February 2019 California Independent System Operator Corporation March 18, 2019 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

ANNEX X REFERRED TO IN ARTICLE 3.20 TELECOMMUNICATIONS SERVICES

ANNEX X REFERRED TO IN ARTICLE 3.20 TELECOMMUNICATIONS SERVICES ANNEX X REFERRED TO IN ARTICLE 3.20 TELECOMMUNICATIONS SERVICES ANNEX X REFERRED TO IN ARTICLE 3.20 TELECOMMUNICATIONS SERVICES Article 1 Scope and Definitions 1. This Annex applies to measures by Parties

More information

BT s response to Ofcom consultation document. Price Rises in Fixed Term Contracts

BT s response to Ofcom consultation document. Price Rises in Fixed Term Contracts BT s response to Ofcom consultation document Price Rises in Fixed Term Contracts 14 March 2013 1 Executive Summary We welcome the opportunity to comment on this consultation on Price Rises in Fixed Term

More information

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours Background The class will be delivered over a 3-day period. The class is comprised of three training modules covering the areas of: Communications, Critical Thinking, and Restoration. The course consists

More information

Occupational Health and Safety (OHS) Regulation and Code Amendments

Occupational Health and Safety (OHS) Regulation and Code Amendments Occupational Health and Safety (OHS) Regulation and Code Amendments Technical Briefing May 22, 2018 Agenda Occupational Health and Safety Act prompted changes Stakeholder consultation OHS Regulation amendments

More information

JCM Drill Down Report. May 27, 2015

JCM Drill Down Report. May 27, 2015 JCM Drill Down Report May 27, 2015 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill Down Report

More information