your guide to completing an application for a new or replacement water connection from your property to an existing water main

Size: px
Start display at page:

Download "your guide to completing an application for a new or replacement water connection from your property to an existing water main"

Transcription

1 your guide to completing an application for a new or replacement water connection from your property to an existing water main If you wish to apply for a new or replacement water connection you should complete the accompanying application form to this guidance note. We understand that completing the application form may at first glance appear to be very complicated, and that for some customers this may be the first, and only time that they will apply for a new or replacement connection. The guidance notes provided below are designed to take you through the step by step process you should follow, and offer advice on the information we will need to design, plan, and connect your new or replacement water supply. Please note that incomplete or incorrectly completed applications, and those received without the relevant application fee may result in a delay to your application being processed. We are committed to getting you connected as quickly as possible, and without any complications or delay. Along with all the Water Companies in the UK, Affinity Water Ltd have voluntarily adopted a set of performance standards for providing new and replacement connections*. However, to meet these performance standards we need you to provide us with as much information as possible about your site and water demand requirements. We ask therefore that you read each section of our guidance on completing the application form carefully to ensure we receive all the necessary information. Remember, if in doubt, it is better to provide more information than not enough. Water Industry Act 1991 (and as amended by Water Act 2003) It is important you note that by completing the application form for a domestic connection, in the absence of information to the contrary, you are serving Affinity Water Ltd with a Notice of Connection under Section 45(1) of the Water Industry Act As the Statutory Undertaker in your region we are bound to comply with the statutory obligations provided for within the Act. Upon receipt of your application we will contact you within 3 working days to advise you: (a) on whether your application and accompanying information is sufficient for us to proceed or whether we require more information or clarifications before proceeding (b) of our obligations as the Statutory Undertaker (c) of your obligations as the party serving a Notice of Connection (d) of the next steps in continuing with your water connection If you still have any queries after reading the guidance notes, our Customer Service Team ( ) will be happy to offer further advice on how to complete the form, or on the information we require. PLEASE COMPLETE THE APPLICATION FORM IN INK AND USE BLOCK CAPITALS * Water UK: Water industry guidance on the requirement of information and levels of service for water mains requisitions and service connections (available from Water UK website at: Section A Applicant Details In this section please provide full name and contact details of the person and/or company making an application for a new or replacement water connection. Please note that this will be the address to which we will send all correspondence about progress of your scheme regardless of whether you specify a different billing or invoice address in Section B. Occasionally it may be necessary for one of our technical experts to contact you by telephone to discuss your proposals in more details. Please ensure that you have provided at least one daytime telephone number so that any queries we have can be resolved quickly. If we are unable to contact you on the telephone number you provide after three attempts, we will write to you advising the nature of our query. Please note that if it is necessary to write to you, until you reply to us (via telephone or in writing) we will not be able to progress your application further. We understand that many customers now wish to use electronic media to communicate with us. Therefore, if you wish to receive communication via , please provide a working address which you regularly check, and ensure you have selected the option. New and Replacement Connections Guidance (Revision: December 2010) Page 1

2 Section B Invoice and Billing Details Some customers prefer billing information and invoices to be sent to a different address from the applicant (e.g. if you are a building company working on behalf of a client who has their own finance department). In this section you can provide an alternative address if you prefer. If you wish all billing information and invoices to be sent to the same address as that specified in Section A then please tick the same as applicant box and continue to Section C. If you wish all billing information and invoices to be sent to a different address to that specified in Section A the please tick the different to applicant box and provide contact name, and address details of the person to whom invoices should be sent. Then continue to Section C. Section C Your Existing Supply We need to gather information about any existing supplies to your site or property as part of our design process to enable us to make an assessment of any disconnections that may be required when your new or replacement supply is installed. Please provide as much information as possible by answering the questions numbered (i) to (xi): (i) (ii) (iii) (iv) If your site or property does not have an existing water supply, or has not had a supply in the last five years, please tick no and continue straight to Section D. If however, your site or property has an existing water supply, or had one within the last five years you should tick yes and answer questions (ii) to (x) as necessary. If you answered yes to (i) above, please advise us whether any of the water supplies are still connected. If you are unsure, please tick don t know and we can make our own assessment when a technical expert visits the site. If you answered yes to (ii) above because you have an existing water supply then please write your Affinity Water Ltd Customer Reference in the box provided. (You can find your Affinity Water Ltd Customer Reference in the top right hand corner of a recent Water Charges Summary for that supply). We need information about the water fittings previously in the property (i.e. what fittings were in the house before you made or plan to make alterations). Please complete the fittings table on the application form to show the number of each fitting you have or had in the property. An example of what a completed fittings table might look like is provided below. If your development comprises of more than 5 properties then please continue on a separate sheet Internal Use Only Type of Fitting Name or Loading Units (LU) Total LU property per Νο 24 w/c flushing 2 2 wash basin in house wash basin elsewhere 3 bath (tap size 20mm) 1 10 bath (tap size > 20mm) 22 shower 1 3 sink (tap size 15mm) 1 3 sink (tap size >15mm) 5 spray tap 0.5 bidet 1.5 domestic appliance 2 3 communal/commercial appliance 10 any other water fitting (including tap but excluding urinal or water softener) 3 (v) If you are demolishing any properties on the site, they may have been previously served by a water supply which needs disconnecting (to protect against future leakage and water quality). If you are planning to, or have demolished properties on your site, please indicate how many. Page 2 of 7

3 (vi) (vii) Some customers prefer, if possible, to retain their existing supply as part of their new development. If you do wish to retain your existing supply then please indicate this using the tick box provided. Please note that we have a statutory duty to ensure the wholesomeness of water up to the point of supply and in some instances after investigation we may not allow you to use the existing water supply, to ensure that this standard can be maintained. In these instances we will write to you advising of this, and the statutory reasons for doing this. If you have specified in (vi) that if possible you wish to keep your existing supply, please indicate your intended use for this supply. This will assist in our assessment of whether your existing supply can be retained. (viii) Please provide information on the current use of any existing water supplies to your site to assist us with our assessment of the existing water supplies (for example, you might be constructing new houses on a site where once there was a factory served by a large commercial supply. In this instance the existing supply might not be suitable for an individual domestic supply). (ix) (x) (xi) Some older properties share their supply with neighbouring properties and to provide you with a new water supply will require termination of your connection to this shared supply. Please indicate in the box provided whether you are connected to a shared supply with your neighbours (If you are unsure if you are on a shared supply please take advice from your plumbing expert or building contractor). Please note that it is your responsibility to ensure that the existing water supply into your property is disconnected from the shared water supply in accordance with the Water Supply (Water Fittings) Regulations Please let us know if your existing supply has a meter. If you are unsure, you can find out by looking at your water utility bill or alternatively you can contact the Affinity Water Ltd Contact Centre on where one of our Customer Service Assistants will be able to advise you. Please advise us of the material type of your existing water supply to your property. If you are unsure of the material of your existing supply pipe please take advice from your plumbing expert or building contractor. Section D (a) New Supply Details To undertake a design of a new or replacement water supply we need to collect as much information about your proposed development to ensure that the supply we provide is adequate to serve your needs. This will also enable us to develop a more accurate cost for the installation works. (i) We have a statutory duty to ensure that customers receive accurate billing information for water charges, and therefore for Developer Services we will require the full postal address for the property. Please ensure that you provide a full postal address for new properties (if necessary please provide this on a separate sheet and attach to the application form). Some examples of postal addresses we are able and unable to accept are provided below: Example of an acceptable Postal Address Examples of Postal Addresses we cannot accept 21a High Street HA24 3DA Land adjacent to 21 High Street HA24 3DA Plot 1 21 High Street HA24 3DA 21a High Street This is an acceptable postal address This is not acceptable as the property is not uniquely identified This is not acceptable as this is the temporary name for the property This is not acceptable as the postcode is missing We understand that sometimes at the time of application it may not be possible to provide the full postal address. In these instances, we will still proceed with your application and issue you a cost, but will not be able to install your connection until we are in receipt of the full postal address. If you do not have this information, please ensure you obtain it promptly to prevent a delay to your connection. If you are applying for a replacement connection for your existing property, please enter the full address of the existing property. (ii) We need this information to ensure that we are aware of who is taking overall responsibility for the property or site. Sometimes, the person applying for a new or replacement connection (the applicant) will be acting on behalf of the owner or current occupier. Please indicate whether you are the property owner, the current occupier, or acting on their behalf, by selecting the appropriate option from the tick boxes provided. Page 3 of 7

4 (iii) (iv) If you specified in (ii) that you are acting on behalf of the owner/occupier of the property in question, please provide the name and postal address of the property owner. Please specify the type of development you are proposing to construct (please tick all that apply and indicate how many of each development type you are planning to build) Type (a) New Build House Description You are building a new single occupancy house either on land either where a previously demolished building stood or where there was no building previously. This will be a water supply for domestic purposes. (b) New Build Flats, Maisonettes or Apartments You are building a new multi-tenanted building which will contain flats, maisonettes, apartments, or a combination of all. This will be a water supply for domestic purposes. (c) New build Industrial units You are building new properties which can be single or multi-tenanted for use by light industry. This water supply could be for domestic or non-domestic purposes. Please specify the purpose of this supply in box provided on the application form. (d) New build Commercial units You are building new properties which can be single or multi-tenanted for use as retail premises or offices. (e) Conversion of existing building You have an existing building which you are not demolishing but intend to undertake structural alterations: either to split into multiple units (e.g. conversion of a house in to flats) or change its use (e.g. change a shop into a residential dwelling) Please specify the nature of the conversion in the box provided on the application form. (f) Separation of your joint supply You currently share your supply with neighbouring properties and wish to have your own dedicated supply to your property. (g) Upsize or replace my existing supply You are extending or altering your property and your existing supply is no longer adequate to serve your water demand, or you wish to renew your existing supply. (h) Field/ Trough supply You require a dedicated supply to serve agricultural purposes (i) Fire supply You are only applying for a dedicated fire supply to be installed to your property (j) Landlord/ Bin store supply You require a dedicated supply to be installed to a common landlord area for cleaning purposes (k) Other You require a water supply which is not covered by any of the above categories. Please specify the nature of this supply in the box provided on the application form (v) (vi) (vii) If you do not have an existing supply to the property or site and require a water supply for building purposes you can apply for a temporary supply to the site, either by applying separately for a temporary supply or by installing one of your permanent connections early as a temporary supply. Answer yes to this question if you require a supply for building purposes which can be later be used for a permanent to serve your future development. If you have answered yes to (v) above and are applying for more than one permanent supply then please provide details of the supply which is to be used initially as a temporary supply. For each of the questions labelled (a) to (g) provide suitable answers based on the proposed plumbing arrangements for your development. In some cases you will definitely know the answer, but in others you may need to take advice from your plumbing contractor or designer. Please note that it is important for you to ensure the information in this section is as accurate as possible as this may have an impact on your water supply requirements. Please note that if you are not intending to use a barrier pipe material for your external supply pipe you should not proceed with its installation until we are able to advise you of which material you need to use. We will not install your connection if you supply pipe is not of an approved material. Page 4 of 7

5 (viii) It is your responsibility to bring external pipework (called the supply pipe) from your property to the site boundary between the edge of your private property and the public highway. To ensure that we can adequately provide pipework from the existing main to your site boundary (called the communication pipe) you will need to tell us where you wish us to make a connection to your supply pipe at the boundary. Use the space provided to draw a sketch plan of your proposed location (refer to the example sketches on the form) As a minimum you should show the following on your sketch: The location of your property The location adjoining properties which may be affected by your development The street name where you require the connection to be made A clearly marked and labelled point of connection at the site boundary Street names of other roads (if your property sits at the corner of a road junction) Please note that we cannot guarantee there will be a water main adjacent to the connection point you specify. In these instances we will contact you to advise of alternative connection points adjacent to the main. However, you will still be responsible for laying the supply pipe from the property to the site boundary, including all costs associated with this work. (ix) Please complete the fittings table on the application form to show the number of each fitting you propose to provide in all properties. An example of what a completed fittings table might look like is provided below. If your development comprises of more than 5 properties then please continue on a separate sheet Internal Use Only Type of Fitting Name or Loading Units (LU) Total LU property per Νο 21 α Νο 21 β Τηε Λοδγε w/c flushing wash basin in house wash basin elsewhere 3 bath (tap size 20mm) bath (tap size > 20mm) 22 shower sink (tap size 15mm) sink (tap size >15mm) 5 spray tap 0.5 bidet domestic appliance communal/commercial appliance 10 any other water fitting (including tap but excluding urinal or water softener) 3 (x) Where you require a water connection for commercial use i.e. factory, golf course we will need to know the demand that the supply will require. This will ensure that we size your new supply correctly. Section D (b) New Supply Site Details Providing information about the site needing a new supply will help us understand the risks of installing a non-barrier pipe service. Barrier pipe provides security against polluting the water supply from many chemicals that are present in the ground, although it is a more expensive product. You may choose to provide a ground condition assessment (soil report) with your application that will assist us in making a judgement about what pipe material to specify. You may also wish to include a photograph of the site with your application as it will help us understand the condition of the site. Please do not lay any pipework until you have completed your application form. The cost advice we shall send you will advise you of the pipe material to lay. Section E Fire Supplies Some properties will require a dedicated supply for sprinkler systems or fire fighting purposes. This must be separate from your supply for domestic purposes. Page 5 of 7

6 Complete this section if you require a sprinkler fire supply connection for your property. If you are unsure of your fire supply requirements please take advice from your plumbing expert or the contractor responsible for the design and installation of your sprinkler system. Section F Additional Information, Checklist and Declaration Once you have completed the application form you should review the additional information checklist to ensure that you provide us with all the information we need to progress your application. Please tick the boxes, as appropriate, to confirm that you have enclosed the information. Please note that applications returned to us without the required information will not be processed until all the necessary information has been received. This will delay your connection. Information you must provide for all applications before we can continue with your connection: 1. If you have specified in Section D that you are working on behalf of owner/occupier of the property then you should enclose with the application a letter from the owner/occupier which authorises you to act (and make commercial decisions, if necessary) on their behalf. 2. For all applications we will require a location plan (ideally to Scale 1:1250) showing the approximate location of the site or property. The location plan should be showing us the street/road your property is in and where your property(s) are in that street/road. 3. Your relevant application fee. (Please be aware that this is not the total cost of your new water service(s) and covers only the associated costs of providing you with an accurate cost advice.) Information you must provide if you are converting an existing, or building a new, property or development: 4. The site plan should be at a suitable scale (suggested, 1:200 or 1:500) to provide sufficient information about your development proposals. As a minimum the site plan should show the proposed property or properties, plot numbers, and building types for each property. This will enable us to verify that our proposals for the new connection(s) meet your design requirements. 5. If you are installing new plumbing, or making significant alteration to any existing plumbing you must enclose a Water Regulation Drawing. You should speak to your plumbing contractor or designer, if you do not have this information. As a minimum the Regulation Drawing should show pipework layouts and proposed water fittings to be used (example below). Page 6 of 7

7 Information you may wish to provide to assist us with designing your connection: 6. As part of the planning and design of new developments and properties, some developers arrange for a soil investigation to be undertaken which may include a ground condition assessment. If you are in possession of a ground condition assessment (conducted by UKAS and MCERT approved laboratories) then you may wish to include this with your application to assist us in making the material selection for the pipework. The soil report must contain as a minimum the following:- Current site conditions Site History/Envirocheck Map of where soil samples taken Laboratory results based on WRAS guidance Please note that if we do not receive a report with the above information from you, or the results from your ground condition assessment are inconclusive then we will adopt a precautionary approach to material selection and install a barrier pipe suitable for potentially contaminated land. We strongly recommend that you do not lay any of your external pipework from the property to the site boundary, before we have confirmed what pipe material you should use (this will be detailed on our cost to you). Please note that we will not install your connection if you have laid pipework using the incorrect material. When you have completed the application form and attached the additional information as required, please confirm that you accept the terms and conditions and then sign and date the application. All completed application forms and accompanying information should be returned to: Or submit your application electronically to: Developer Services Affinity Water Ltd Tamblin Way AL10 9EZ DS@Affinitywater.co.uk Page 7 of 7

your guide to completing an application for a new or replacement water connection from your property to an existing water main

your guide to completing an application for a new or replacement water connection from your property to an existing water main your guide to completing an application for a new or replacement water connection from your property to an existing water main If you wish to apply for a new or replacement water connection you should

More information

Application form AWS2

Application form AWS2 Application form AWS2 For a non-standard (32mm or bigger) connection to an existing water main This form allows you to apply for a non standard (i.e. 32mm or bigger) water service pipe connection. It is

More information

SELF LAY. Application to self lay a water supply (mains and connections) V1 04/17. SECTION 1 Applicant (correspondence address) Page 1 of 14

SELF LAY. Application to self lay a water supply (mains and connections) V1 04/17. SECTION 1 Applicant (correspondence address) Page 1 of 14 V1 04/17 Application to self lay a water supply (mains and connections) This form can be used to apply to self lay a new water main and connections, under Section 51 of the Water Industry Act 1991 and

More information

Application for new or replacement water connections

Application for new or replacement water connections Application for new or replacement water connections This form should be used to make an application for new or replacement water connections to an existing public water main under section 45 and/or 55

More information

Application for New Water Mains & Services Requisition and Self Lay

Application for New Water Mains & Services Requisition and Self Lay Essex & Suffolk Water Reference Number NS/... For office use only Application for New Water Mains & Services Requisition and Self Lay This form is to be used by developers or Self Lay Providers (SLP) when

More information

Water Company Lay Application

Water Company Lay Application WCL FORM 2018/3494 Water Company Lay Application SECTION A CONTACT DETAILS Preferred method of contact: Post Email DEVELOPER DETAILS Company name: For the attention of: Property name / number: Street:

More information

New Water Connection Application (up to 32mm) Article 79 - Water and Sewerage Services (Northern Ireland) Order 2006

New Water Connection Application (up to 32mm) Article 79 - Water and Sewerage Services (Northern Ireland) Order 2006 New Water Connection Application (up to 32mm) Article 79 - Water and Sewerage Services (Northern Ireland) Order 2006 Please note - this form can be used to apply for new or replacement water connections

More information

Water and Sewer connections application form. Section 1. 1a. Applicant details

Water and Sewer connections application form. Section 1. 1a. Applicant details Water and Sewer connections application form Application for new connections to the existing water and/or sewer network. Please use this application to apply for a new water connection(s) and/or sewer

More information

permanent water connection

permanent water connection application for a permanent water connection Form A Important Please note there may have been significant changes to the requirements/process since you last used this form. We only accept electronic submissions

More information

temporary water connection or for building water

temporary water connection or for building water application for a temporary water connection or for building water Form J Important Please note there may have been significant changes to the requirements/process since you last used this form. We only

More information

SELF LAY POINT OF CONNECTION

SELF LAY POINT OF CONNECTION SELF LAY POINT OF CONNECTION ASSESSMENT FORM Water supply capacity assessment for a proposed self lay development. Contents Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7 Applicant

More information

Application for a water connection to a commercial or mixed use development

Application for a water connection to a commercial or mixed use development Application for a water connection to a commercial or mixed use development Providing clean, safe water: It s part of our Blueprint for Yorkshire Your application form for a water connection to a commercial

More information

Form F3 Self Lay Application For Mains and/or Services

Form F3 Self Lay Application For Mains and/or Services p 1 of 9 Form F3 Self Lay Application For Mains and/or Services This form should only be used once a decision to self-lay has been taken. Developers requiring budget information to allow them to choose

More information

LARGE DIAMETER CONNECTIONS

LARGE DIAMETER CONNECTIONS LARGE DIAMETER CONNECTIONS APPLICATION FORM Application to provide a large diameter connection of 50mm and above Sections 45 and 55 of the Water Industry Act 1991 Note - Please ensure all relevant sections

More information

Application for a new commercial water supply connection

Application for a new commercial water supply connection Application for a new commercial water supply connection This application is to be used to apply for a new / replacement commercial water service connection(s) under the Water Industry Act 1991, to Northumbrian

More information

Please complete the application form (preferably electronically) and return it with a site location plan to:

Please complete the application form (preferably electronically) and return it with a site location plan to: Developer services WWDS-DEV 001G Water supply (service connections only) Guidance notes and procedure Application form Please complete the application form (preferably electronically) and return it with

More information

Development enquiry request

Development enquiry request Development enquiry request Water supply and/or drainage capacity assessment for a proposed development NOTE: Please ensure all relevant sections of the application are completed and refer to the attached

More information

Adoption of Sewers Application for the adoption of a sewer under Section 104 of the Water Industry Act 1991

Adoption of Sewers Application for the adoption of a sewer under Section 104 of the Water Industry Act 1991 Adoption of Sewers Application for the adoption of a sewer under Section 104 of the Water Industry Act 1991 NOTE: Please ensure all relevant sections of the application are completed and refer to the attached

More information

Form A Application for a Permanent Water Connection

Form A Application for a Permanent Water Connection Form A Application for a Permanent Water Connection Water Plus are experienced in all technical aspects associated with attaining new water, wastewater and temporary connections. If you require help with

More information

Obtaining water supplies for new developments

Obtaining water supplies for new developments Obtaining water supplies for new developments Guidance notes for developers Issue 1.0 - April 2015 life fow smoothly helping helpin life f ow smoothly hel ping helping life fow smoothly life fow smoothly

More information

New connection to a public sewer

New connection to a public sewer New connection to a public sewer Application form You can go to our website thameswater.co.uk/buildover and apply online or complete this form and return to Thames Water, Developer Services, Clearwater

More information

Development enquiry request

Development enquiry request Development enquiry request Water supply and/or drainage capacity assessment for a proposed development NOTE: Please ensure all relevant sections of the application are completed and refer to the attached

More information

Application to requisition a sewer Section 98 WIA 1991

Application to requisition a sewer Section 98 WIA 1991 Application to requisition a sewer Section 98 WIA 1991 This form should be used if you want to requisition a public sewer under Section 98 of the Water Industry Act 1991. PLEASE COMPLETE ALL SECTIONS USING

More information

Building Standards Customer Journey

Building Standards Customer Journey Building Standards Customer Journey Are you doing building work or home improvements? If so, this guide is for you. Building Standards Customer Journey Contents 2 Contents Building Standards Customer Journey

More information

Policy and Guidance on Contestable and Non-Contestable Work (clean water networks) July 16

Policy and Guidance on Contestable and Non-Contestable Work (clean water networks) July 16 Policy and Guidance on Contestable and Non-Contestable Work (clean water networks) July 16 Yorkshire Water Policy and Guidance on Contestable and Non-Contestable Work (clean water networks) July 16 2 Contents

More information

W R reference S41 reference Property reference Rapid reference. DG2 Yes No Quote reference

W R reference S41 reference Property reference Rapid reference. DG2 Yes No Quote reference Developer services WWDS-DEV 001A Water supply (mains and service connections) Application form (please refer to the guidance notes before completing this form) Wessex Water references (Wessex Water use

More information

Application for the diversion of a Severn Trent Connect sewerage asset under section 185 of the Water Industry Act Note Note. 1.

Application for the diversion of a Severn Trent Connect sewerage asset under section 185 of the Water Industry Act Note Note. 1. Sewer diversion Application for the diversion of a Severn Trent Connect sewerage asset under section 185 of the Water Industry Act 1991 NOTE: Please ensure all relevant sections of the application are

More information

You are also similarly responsible for any part crossing any neighbouring land, including any length of private service pipe in the public highway.

You are also similarly responsible for any part crossing any neighbouring land, including any length of private service pipe in the public highway. Shared supply or lead water pipe replacement connections guidance notes Up to 25mm diameter supplies Introduction Our aim is to deliver an excellent standard of service. In order for us to do this and

More information

SEWER DIVERSION CONNECTIONS

SEWER DIVERSION CONNECTIONS NOTE: Please ensure all relevant sections of the application are completed and refer to the attached support notes. Please ensure you save a completed copy of this application form for your own records.

More information

Environment Canterbury regional council works with the people of Canterbury to manage the region s air, water and land. We are committed to the

Environment Canterbury regional council works with the people of Canterbury to manage the region s air, water and land. We are committed to the How to apply Environment Canterbury regional council works with the people of Canterbury to manage the region s air, water and land. We are committed to the sustainable management of our environment while

More information

PRE-DEVELOPMENT ENQUIRY APPLICATION FORM

PRE-DEVELOPMENT ENQUIRY APPLICATION FORM PRE-DEVELOPMENT ENQUIRY APPLICATION FORM Developer Services Dee Valley Water plc, Packsaddle, Wrexham Road, Rhostyllen, Wrexham, LL14 4EH E-mail: developer.services@deevalleygroup.com In order to progress

More information

Self lay policy. Company specific addendum to Code of Practice for the self laying of Water Mains and Services England and Wales 2 nd Edition May 2009

Self lay policy. Company specific addendum to Code of Practice for the self laying of Water Mains and Services England and Wales 2 nd Edition May 2009 Self lay policy and Company specific addendum to Code of Practice for the self laying of Water Mains and Services England and Wales 2 nd Edition May 2009 Issue 2 - May 2013 Contents Introduction Page 3

More information

Having a. water meter fitted. Will it benefit me?

Having a. water meter fitted. Will it benefit me? Having a water meter fitted Will it benefit me? Contents Introduction Introduction 3 Having a water meter 4 What is a water meter? 4 Why is it beneficial? 4 Do I have to pay to have a meter installed?

More information

Company specific addendum

Company specific addendum Self lay policy and Company specific addendum to Code of Practice for the self laying of Water Mains and Services England and Wales 2 nd Edition May 2009 Issue 1.0 - April 2015 life fl ow smoothly helping

More information

ANGLIAN WATER SERVICES LIMITED MISCELLANEOUS CHARGES STATEMENT

ANGLIAN WATER SERVICES LIMITED MISCELLANEOUS CHARGES STATEMENT ANGLIAN WATER SERVICES LIMITED 2016-2017 MISCELLANEOUS CHARGES STATEMENT This document sets out the Miscellaneous Charges fixed by Anglian Water Services Limited as the water and sewerage undertaker for

More information

Irish Water application guide

Irish Water application guide Irish Water application guide IW/V/B/0814 www.water.ie This publication is available in Braille, on CD and in large text format on request by calling 1890 448 448. If you would like to know more, please

More information

Leakage. Code of Practice for Household Customers PRE 0068

Leakage. Code of Practice for Household Customers PRE 0068 Leakage Code of Practice for Household Customers PRE 0068 Dŵr Cymru Welsh Water 2 Water is a precious resource and it is in all our interests to ensure that we use it wisely. We are committed to ensuring

More information

NEW CONNECTION SMALL WORKS SINGLE DOMESTIC PREMISES

NEW CONNECTION SMALL WORKS SINGLE DOMESTIC PREMISES NEW CONNECTION SMALL WORKS SINGLE DOMESTIC PREMISES APPLICATION FORM Please submit your completed application form to:, Network Connections, Alix House, Falcon Court, Stockton-on-Tees, TS18 3TU If you

More information

St Thomas More Catholic Primary School

St Thomas More Catholic Primary School St Thomas More Catholic Primary School Grievance Policy In the development of this policy consideration has been given to the impact on protected characteristics under the Equality Act and the work life

More information

Application for new water supplies (mains and connections)

Application for new water supplies (mains and connections) Anglian Water reference number (Anglian Water use only) Application for new water supplies (mains and connections) This form is to be used for the application of new water mains and connections, under

More information

Water Supply / Drainage / Vehicle Crossing Service Connection Information Sheet

Water Supply / Drainage / Vehicle Crossing Service Connection Information Sheet Water Supply / Drainage / Vehicle Crossing Service Connection Information Sheet Service details It is important that all of the required details are completed on the Service. Site Plans As well completing

More information

GRIEVANCE POLICY T H I S P O L I C Y W A S S U M M E R A P P R O V E D : T H I S P O L I C Y W I L L B E R E V I E W E D : S U M M E R

GRIEVANCE POLICY T H I S P O L I C Y W A S S U M M E R A P P R O V E D : T H I S P O L I C Y W I L L B E R E V I E W E D : S U M M E R GRIEVANCE POLICY T H I S P O L I C Y W A S S U M M E R 2 0 1 7 A P P R O V E D : T H I S P O L I C Y W I L L B E R E V I E W E D : S U M M E R 2 0 2 0 M E M B E R O F S T A F F W I T H R E S P O N S I

More information

Wholesale charges

Wholesale charges Wholesale charges 2017-18 This is not a Scheme of Charges C ustomers should refer to our Household Scheme of Charges Retailers should refer to our Wholesale Scheme of Charges 1 About this document Wholesale

More information

Charging Arrangements for New Connection Services

Charging Arrangements for New Connection Services Charging Arrangements for New Connection Services 2018-2019 About South East Water Developer Services Developer Services Department For any new connections requests or issues please contact our Developer

More information

QP 02 Audit and Certification Procedure

QP 02 Audit and Certification Procedure 1. AUDIT PROGRAMME [9.1.1] The audit programme shall be conducted in stages within a 3-year certification cycle as follows; Initial audit: Two stage process Surveillance audit: Conducted in the first and

More information

NEW CONNECTION SMALL WORKS 1-4 PREMISES APPLICATION FORM

NEW CONNECTION SMALL WORKS 1-4 PREMISES APPLICATION FORM SMALL WORKS 1-4 PREMISES APPLICATION FORM Please submit your completed application form to:, Network Connections, Alix House, Falcon Court, Stockton-on-Tees, TS18 3TU If you need any help to complete this

More information

Indicative Wholesale Charges Severn Trent Water

Indicative Wholesale Charges Severn Trent Water Indicative Wholesale s 2018-19 Severn Trent Water About this document Indicative wholesale charges (non-households) - 1 April 2018 to 31 March 2019 Ofwat published IN16-02 in March 2016. This set out new

More information

New Connections Services Charging Arrangements

New Connections Services Charging Arrangements New Connections Services Charging Arrangements 2018-19 January 2018 Contents Charging arrangements for new connection services... 3 Introduction to our charges... 3 Who pays for what?... 4 Who can deliver

More information

Developer Services Schedule of Charges

Developer Services Schedule of Charges Developer Services Schedule of Charges 2018-2019 PAB 0122 Dŵr Cymru Welsh Water 2 The not-for-profit story Discover where your money goes at dwrcymru.com/different Developer Services Schedule of Charges

More information

DIRECTIONS ISSUED TO LICENSED PROVIDERS PURSUANT TO STANDARD LICENCE CONDITION B1 THE WATER INDUSTRY COMMISSION FOR SCOTLAND.

DIRECTIONS ISSUED TO LICENSED PROVIDERS PURSUANT TO STANDARD LICENCE CONDITION B1 THE WATER INDUSTRY COMMISSION FOR SCOTLAND. DIRECTIONS ISSUED TO LICENSED PROVIDERS PURSUANT TO STANDARD LICENCE CONDITION B1 BY THE WATER INDUSTRY COMMISSION FOR SCOTLAND 17 May 2007 1 DEFAULT SERVICES, STANDARDS AND MAXIMUM TARIFFS FOR WATER AND

More information

Developer Services. Building over or near a sewer. DEV 005G Guidance notes and procedure. What is a public sewer?

Developer Services. Building over or near a sewer. DEV 005G Guidance notes and procedure. What is a public sewer? Developer Services DEV 005G Guidance notes and procedure Building over or near a sewer If you are thinking of building a structure (for example, a new building, extension, conservatory, garage etc.) you

More information

Application to provide clean water for new developments

Application to provide clean water for new developments Application to provide clean water for new developments Application form and guidance notes Please detach and return this application form and keep our guidance notes for reference. This form should be

More information

New Connections. Information Pack. Everything you need to know about installing a New Supply

New Connections. Information Pack. Everything you need to know about installing a New Supply New Connections Information Pack Everything you need to know about installing a New Supply Introduction a new water connection. It covers how to submit an application, the timescales involved in doing

More information

Keeping drinking water safe at public events

Keeping drinking water safe at public events www.wessexwater.co.uk Keeping drinking water safe at public events Introduction If you re organising a public event or festival you ll want to make sure your visitors have a good time and stay safe. The

More information

THE AODA: UNLOCKING. Landlords Obligations Under The Accessibility For Ontarians With Disabilities Act. A ToolKit For Landlords In Ontario

THE AODA: UNLOCKING. Landlords Obligations Under The Accessibility For Ontarians With Disabilities Act. A ToolKit For Landlords In Ontario UNLOCKING THE AODA: Landlords Obligations Under The Accessibility For Ontarians With Disabilities Act A ToolKit For Landlords In Ontario An EnAbling Change Partnership project with the Government of Ontario

More information

Water Connection Application

Water Connection Application Water Connection This application form is to be used for connections to a public water main for the following: Housing Units Site Accommodation Student Accommodation Building Water Guidance section Water

More information

Adoption of sewers. Application for the adoption of a sewer under Section 104 of the Water Industry Act Section 1A: Applicant s details

Adoption of sewers. Application for the adoption of a sewer under Section 104 of the Water Industry Act Section 1A: Applicant s details Adoption of sewers Application for the adoption of a sewer under Section 104 of the Water Industry Act 1991 NOTE: Please ensure all relevant sections of the application are completed and refer to the attached

More information

WATER REGULATIONS SMALL AND MEDIUM SIZED BUSINESSES FOR. Information guide for your business

WATER REGULATIONS SMALL AND MEDIUM SIZED BUSINESSES FOR. Information guide for your business WATER REGULATIONS FOR SMALL AND MEDIUM SIZED BUSINESSES OFFICE CLOTHES COMPUTERS HOME FLOWERS CAFE HAIR Information guide for your business DOES YOUR PREMISES COMPLY WITH WATER FITTINGS REGULATIONS? The

More information

Pre-Development Enquiry Form

Pre-Development Enquiry Form Pre-Development This application form is to be used to assess if we are able to provide your development with water and/or drainage services for a planned development. It is expected that this is submitted

More information

Business Energy Codes of Practice

Business Energy Codes of Practice Business Energy Codes of Practice Welcome SSE Airtricity entered the Irish Business Energy Electricity supply market in 1998 and the Northern Irish market in 2010 and we have increased our market share

More information

Date of Application. Details of Applicant & Premises (where power supply is required): (Please mark where applicable)

Date of Application. Details of Applicant & Premises (where power supply is required): (Please mark where applicable) (Form A-1) Application Form New Connection/ Load enhancement/ Load reduction/ Reconnection (Agriculture)/ Change of Name/ Shifting/ Temporary Supply/ Conversion of Service/ Change of consumer category

More information

MSP 50 CONTROL OF CONTRACTORS

MSP 50 CONTROL OF CONTRACTORS CONTROL OF CONTRACTORS AUTHORISED BY: PURCHASING MANAGER DATE: 14/03/2011 THIS DOCUMENT WILL FORM PART OF THE PRE-TENDER, TENDER AND CONTRACT PROCESSES FOR EACH CONTRACT AND AS SUCH SHALL BE REQUIRED TO

More information

Guide to applying online

Guide to applying online If you need any more help to complete this form, please contact us: getconnected@northernpowergrid.com 0845 070 2703 Opening hours: Monday - Friday 8:00am - 8:00pm Saturday 9:00am - 5:00pm HELP WITH SECTION

More information

Wholesale water charges scheme 2016/2017 F Page 1 of 31

Wholesale water charges scheme 2016/2017 F Page 1 of 31 F Page 1 of 31 Charges schemes United Utilities Water Limited has published five charges schemes for 2016/2017 charging year. They include the charges to be paid for services provided by us in the course

More information

Form G/02: Trade effluent discharge application

Form G/02: Trade effluent discharge application Form G/02: Trade effluent discharge application Change History Version Number Date of Issue Reason for Change Change Control Reference Sections Affected CPW036 v2.0 6 th June 2018 G/02 & G/03 Trade Effluent

More information

BABT 807. A Guide to the Attestation of Equipment to the Machinery Directive by TUV SUD BABT. TUV SUD BABT is a Certification Body of

BABT 807. A Guide to the Attestation of Equipment to the Machinery Directive by TUV SUD BABT. TUV SUD BABT is a Certification Body of BABT 807 A Guide to the Attestation of Equipment to the Machinery Directive by TUV SUD BABT TUV SUD BABT is a Certification Body of TUV SUD BABT 2018 Issue: 2 Foreword TUV SUD BABT is the Certification

More information

FLEXIBLE TRAINING OPPORTUNITIES APPLICATION FORM

FLEXIBLE TRAINING OPPORTUNITIES APPLICATION FORM FLEXIBLE TRAINING OPPORTUNITIES APPLICATION FORM Instructions for completing this form: To help you complete the application form please read the rules and guidance section and the help notes. Please use

More information

Guide to the application process

Guide to the application process Registration under the Health and Social Care Act 2008 Guide to the application process Guidance for new registered managers July 2011 PoC1C 100743 5.00 Guide to the application process: Guidance for new

More information

Standard terms and conditions

Standard terms and conditions Standard terms and conditions Development Services For the provision of a water service (Water Supply, Wastewater and Drainage) Introduction Under Section 73(2)(a) of the Water Services Act 2012, landowners

More information

Exporting Hazardous Waste New Zealand requirements for exporting hazardous waste under the Basel Convention

Exporting Hazardous Waste New Zealand requirements for exporting hazardous waste under the Basel Convention Exporting Hazardous Waste New Zealand requirements for exporting hazardous waste under the Basel Convention APPLICATION GUIDE 2 Introduction Exports of hazardous waste are controlled and monitored to avoid

More information

ONTARIO LABOUR RELATIONS BOARD

ONTARIO LABOUR RELATIONS BOARD ONTARIO LABOUR RELATIONS BOARD INFORMATION BULLETIN NO. 38 Card Based Certification of Trade Unions in Specified Industries This Information Bulletin describes the procedures that must be followed when

More information

Form G/02: Trade effluent discharge application

Form G/02: Trade effluent discharge application Form G/02: Trade effluent discharge application Form G/02: Notice for a Trade Effluent discharge into the Wholesaler s Sewerage system or for a modification to an existing Consent to Discharge into a Wholesaler

More information

Gas Distribution Connection Services Charges

Gas Distribution Connection Services Charges Gas Distribution Connection Services Charges Standard Charges effective from 1 st May 2018 1 Contents 1 New Domestic Connection Charges 2 Disconnection Standard Charges 3 Domestic Service Alteration Charges

More information

If you have any other specific requirements or require this form in large print or Braille, please contact us on

If you have any other specific requirements or require this form in large print or Braille, please contact us on Northern Powergrid Holdings Companyisawhollyowned subsidiary of Berkshire Hathaway Energy, and operates its electricity distribution business through its subsidiary companies Northern Powergrid (Northeast)

More information

EDF Energy Process Booklet. Everything you need to know in order to successfully sell an EDF Energy contract

EDF Energy Process Booklet. Everything you need to know in order to successfully sell an EDF Energy contract EDF Energy Process Booklet Everything you need to know in order to successfully sell an EDF Energy contract Contents Welcome page 3 Products and Pricing Page 4 Credit Policy More information for customers

More information

Renewable Energy Bonus Scheme - Solar Hot Water Rebate. Guidelines and application form

Renewable Energy Bonus Scheme - Solar Hot Water Rebate. Guidelines and application form Renewable Energy Bonus Scheme - Solar Hot Water Rebate Guidelines and application form Under the Renewable Energy Bonus Scheme Solar Hot Water Rebate, the Australian Government is offering rebates of $1,000

More information

Application To Segregate Water Service

Application To Segregate Water Service Application To Segregate Water Service If two or more existing legally constructed dwellings exist on a property and are connected to a common water meter, installation of additional meter(s) may be permissible

More information

FINANCIALS KEY CONTACTS SITE INFORMATION NEW LEGISLATION A NEW PARTNERSHIP KEY LEGISLATION SITE SIGNAGE

FINANCIALS KEY CONTACTS SITE INFORMATION NEW LEGISLATION A NEW PARTNERSHIP KEY LEGISLATION SITE SIGNAGE 05 07 01 02 06 03 04 01 02 03 04 05 06 07 A NEW PARTNERSHIP KEY CONTACTS FINANCIALS SITE INFORMATION KEY LEGISLATION SITE SIGNAGE NEW LEGISLATION Who is CTIL? How your CTIL agreement works in practice

More information

Western Power Retail Customer Charter.

Western Power Retail Customer Charter. Western Power Retail Customer Charter. 1 Contents Our service commitment to you... 1 Who this Charter applies to... 2 How to contact us... 3 Generation, distribution and retail... 4 What we do for you

More information

E N E R G Y E F F I C I E N T H O M E S PA C K A G E Solar Hot Water Rebate. Guidelines and application form

E N E R G Y E F F I C I E N T H O M E S PA C K A G E Solar Hot Water Rebate. Guidelines and application form E N E R G Y E F F I C I E N T H O M E S PA C K A G E Solar Hot Water Rebate Guidelines and application form The Solar Hot Water Rebate is a key part of the Australian Government s Energy Efficient Homes

More information

The M&G ISA Application for tax year ending 5 April 20 Y

The M&G ISA Application for tax year ending 5 April 20 Y The M&G ISA Application for tax year ending 5 April 20 Y Y INVESTMENTS This form: can be used to invest in The M&G ISA for the first time can be used to make an additional subscription to your M&G ISA,

More information

Option 2 Directing Your Support

Option 2 Directing Your Support Option 2 Directing Your Support Directing your support means you have choice and control over the support you get without having to take on the responsibility of managing or administering the money. You

More information

Retail Contracts Scheme Benchmarks

Retail Contracts Scheme Benchmarks Retail Contracts Scheme s 1 - Clear supply commencement 1.1. The gas supply arrangements must state when the supply of gas is to commence, either by stating a specific commencement date or the circumstances

More information

Multi-level individual metering guide. Version 3: December 2013

Multi-level individual metering guide. Version 3: December 2013 Version 3: December 2013 Contents 1 Introduction 4 2 Approach to introducing individual metering 5 2.1 Stage 1: Preparing the building for individual metering 5 2.2 Stage 2: Requirement for individual

More information

Trade Effluent. 19 th October 2017

Trade Effluent. 19 th October 2017 Trade Effluent 19 th October 2017 Trade Effluent for Open Market Why The wholesale Trade Effluent standard is an integral part of Severn Trent wholesale operations and provides further clarification in

More information

Affinity Water Limited New Supplies

Affinity Water Limited New Supplies 1 of 13 Affinity Water Limited New Supplies Policy and Company Specific Requirements for Water Mains and Service Pipes Constructed by Self-Lay Organisations 2 of 13 CONTENTS 1 Introduction 3 1.1 General

More information

NORTHERN POWER DISTRIBUTION COMPANY OF TELANAGANA LIMITED WARANGAL, TELANAGANA Appendix I APPLICATION FOR SUPPLY OF ELECTRICITY AT LOW TENSION

NORTHERN POWER DISTRIBUTION COMPANY OF TELANAGANA LIMITED WARANGAL, TELANAGANA Appendix I APPLICATION FOR SUPPLY OF ELECTRICITY AT LOW TENSION NORTHERN POWER DISTRIBUTION COMPANY OF TELANAGANA LIMITED WARANGAL, TELANAGANA Appendix I APPLICATION FOR SUPPLY OF ELECTRICITY AT LOW TENSION To, The Asst. Engineer / Operation Photo of the Customer I/

More information

Our charging scheme for Southern Water Wholesale Region 2019/20. Primary Charges

Our charging scheme for Southern Water Wholesale Region 2019/20. Primary Charges Our charging scheme for Southern Water Wholesale Region 2019/20 Primary Charges Contents Introduction Section 1 Primary Charges Part 1 Part 2 Part 3 Part 4 Part 5 Principles for Measured, Unmeasured and

More information

Guide to Part P and Registration

Guide to Part P and Registration Guide to Part P and Registration All you ll ever need for Part P www.elecsa.co.uk Welcome to the ELECSA Part P self-certification scheme If you are involved in domestic electrical installation work, you

More information

Irish Water Business Customer Codes of Practice

Irish Water Business Customer Codes of Practice Irish Water Business Customer Codes of Practice 1 P a g e 02 October 2017 Introduction As Ireland s national water utility, Irish Water aims to meet our customers expectations through the provision of

More information

Residential Recycled Water Household Guide

Residential Recycled Water Household Guide Residential Recycled Water Household Guide Why use recycled water? The use of recycled water in new residential developments is increasing in Australia as we become more water efficient. By using recycled

More information

National Occupational Standards for On Construction Domestic Energy Assessors. Asset Skills July 2007

National Occupational Standards for On Construction Domestic Energy Assessors. Asset Skills July 2007 National Occupational Standards for On Construction Domestic Energy Assessors Asset Skills July 2007 Asset Skills 2 The Courtyard 48 New North road Exeter EX4 4EP Asset Skills Sol House 29 St Katherine's

More information

SAI Global Full Service Team

SAI Global Full Service Team General information regarding elements of the certification process is described below. A degree of flexibility and options in the certification process are available so please feel free to contact us

More information

Requisition a Water Main

Requisition a Water Main Please ensure you have read our guidance notes before completing this application form and include as much information as possible. If mandatory fields (marked with a ) are not completed this could result

More information

Lycamobile Pty Ltd Customer Complaints Handling Policy Table of Contents

Lycamobile Pty Ltd Customer Complaints Handling Policy Table of Contents Lycamobile Pty Ltd Customer Complaints Handling Policy Table of Contents Introduction 1 Definition of complaint 2 Purpose of this policy 3 Our commitment to handling complaints 4 Complaints handling stages

More information

Application Pack 2. Dŵr Cymru Welsh Water s Guidance on how to apply to Requisition Water Mains and Services July 2015

Application Pack 2. Dŵr Cymru Welsh Water s Guidance on how to apply to Requisition Water Mains and Services July 2015 Application Pack 2 Dŵr Cymru Welsh Water s Guidance on how to apply to Requisition Water Mains and Services July 2015 This guidance applies where a developer decides to requisition water mains and services

More information

Your Water Service PLEASE READ AND KEEP SAFE. Your guide for 2017/18. Important information about your water service for the coming year.

Your Water Service PLEASE READ AND KEEP SAFE. Your guide for 2017/18. Important information about your water service for the coming year. Your local supply, on tap Your Water Service Your guide for 2017/18 PLEASE READ AND KEEP SAFE Important information about your water service for the coming year. ALL ABOUT US Hello, we re Affinity Water

More information

SEWAGE SYSTEM PERMIT GUIDELINES

SEWAGE SYSTEM PERMIT GUIDELINES Forms Applicable Law SEWAGE SYSTEM PERMIT GUIDELINES Description Required Submission Status Comments County of Simcoe If applicable Ministry of Transportation (MTO) If applicable Building Permit Application

More information

Water Use In Your Business

Water Use In Your Business Water Use In Your Business Advice & tips for saving water Making your business watertight Water is a valuable resource, yet all too often we take it for granted. Whether your business is large or small

More information

Guide to applying online

Guide to applying online If you need any more help to complete this form, please contact us: getconnected@northernpowergrid.com 0845 070 2703 Opening hours: Monday - Friday 8:00am - 8:00pm Saturday 9:00am - 5:00pm HELP WITH SECTION

More information