2. What are the typical problems with Manufacturing Resources Planning (MRP)? Indicate how one can overcome each problem. 4 points

Size: px
Start display at page:

Download "2. What are the typical problems with Manufacturing Resources Planning (MRP)? Indicate how one can overcome each problem. 4 points"

Transcription

1 EXAM: PRODUCTIO MAAGEMET -- 35V6A5 Date: 12 May 2010 Part 1: Closed Book You have ± 45 minutes to answer the following questions. Write your answers short, clear and to the point (max. 8 lines per question). Please write readable. Total 25 points 1. Discuss under which conditions assembly layout and line balancing is viable option. Indicate also alternative solution when conditions are not met. 4 points Assembly line is a good choice when (a) product design does not change often, (b) the volume is large and stable, (c) process times are relatively stable and do OT vary. When process times are variable, then it is better to arrange the layout based on the sequence of operations and instead of line balancing we use TOC (Theory of Constraint), which tolerates variable process times. When both process time and design are variable Job-Shop or Group Tech layout are preferred. 2. What are the typical problems with Manufacturing Resources Planning (MRP)? Indicate how one can overcome each problem. 4 points Fixed lead times: This problem can be eased by regularly observing and collecting statistics on waiting times (Activation and Availability) in system (using queueing) and by correcting or adjusting then the leadtimes in MRP system. Wrong Priorities: Backward planning based on fixed leadtimes this can be improved when leadtimes are frequently corrected or buffer times are allowed for the variability (similar to TOC). Infinite capacity: This can be improved by using mathematical programming models. Fixed (large) batch sizes: This can be improved by using mathematical programming models to optimize lotsizes. Buffering (Inventories): The usually fixed buffer sizes (safety stocks or times) can be linked to forecast accuracy of demand, improvement of production processes, and the performance improvement of suppliers. Lack of short term planning: This can be improved by using heuristic techniques or mathematical programming models. 3. Define Capacity Planning in MRP. What are the factors that should be considered in Capacity Planning? 4 points Capacity planning is the process of determining capacity. The process checks the planned order processing and when overloads occur for the work center(s), the process tries to level the overload periods and shift the capacity to earlier periods. When is not shift and not feasible to subcontract extra load, the order delivery must be delayed. Two levels are long-term, RCCP where roughly only few machines capacities are checked, mid-term where all machines checked. Short-term does not exist in MRP, where machines are loaded and scheduled. Factors: in capacity planning, time available is a corrected by two factors: Availability (fraction of time due to machine breakdown and / or absenteeism), Activation

2 (fraction of time down due to lack of work). ever load up to capacity, otherwise this creates long leadtimes. 4. Specify the determinants of JIT. Describe the need and role of Load-Leveling. 4 points The determinants are: Product Design; Process Design; Human & Organizational Elements; Manufacturing Planning & Control. Load Leveling is planning to build the same product mix every single day during a given month. It is required to bring stability in the production planning process and introduce pull system. 5. Describe tactical planning decisions in Flexible Manufacturing (FMS) systems and indicate the production management objectives. 4 points Tactical planning problems in flexible manufacturing systems integrates batching, loading, and routing problems with their critical aspects related to a system's performance. The idea is to load the FMS system economically and bring stability in the production planning process and avoid creating bottleneck in the system. 6. Which manufacturing planning technique(s) such as MRPII, JIT, TOC, would be suitable for a manufacturer of Brass? why? 5 points (ote: Brass is an alloy of copper and zinc; it also includes small amounts of other metals such as tin, lead, nickel, iron, aluminum, antimony. The production is continuous flow process and consists of a) melt down, b) purify the resulting molten alloy, c) pouring a portion of the molten into molds. Melting operations require long process time. The melting process time is dependent on the input materials; it could be as pure copper and zinc and scraps materials or as scrap brass parts and scrap cables. Scrap materials are much cheaper than pure materials; using them allows a significant reduction in material costs, but also poses a challenge to meet specification limits, because scrap materials contain different metals with varying percentages and require longer melting time. Given the fact that input mix (raw material) changing and the output is of make-tostock nature, the planning of finished goods inventory is a necessity. MRP front-end is perfect choice if it is integrated with an optimization model, because the melting time is long can cannot be reduced, a decision must made on selecting the right orders, raw materials, and their production sequence. Please write your name on the answer sheets GOOD LUCK!

3 EXAM: PRODUCTIO MAAGEMET -- 35V6A5 Date: 12 May 2010 Part 2 : Open Book You have ± 135 minutes to answer the following questions. Write your answers short, clear and to the point. Please write readable. Exercise points Delta Equipment, Inc., (DEI) is an implement manufacturer operating out of Jonesboro, AR. Some of the items manufactured by DEI include lawn tractors, wheelbarrows, hand trucks, and concrete buggies. DEI's primary customers are several large hardware stores, a couple of high volume discount retailers, and numerous wholesalers. Currently, DEI is putting together a materials plan for the wheelbarrows it manufactures (i.e., assembles). The plan is to be based upon a 10 week planning horizon. Over the course of this horizon, DEI has firm orders for 40 wheelbarrows to be available at the beginning of week 2, 60 each at the beginnings of weeks 5 and 7, and 50 at the beginning of week 9. These wheelbarrows are assembled in-house by DEI from three major components: handles (2 per wheelbarrow), wheel assembly packs, and barrows. DEI orders the handles from outside suppliers and assembles the wheel assembly packs in-house. Each wheel assembly pack has two subcomponents, a tire and an axle assembly, both of which are acquired from outside suppliers. Basic inventory data for the SKUs involved in the wheelbarrow operation are given by the following table: SKU On- Hand Lot Size Leadtime Wheelbarrow 0 LFL 1 week Handle weeks Wheel * weeks Assembly Barrow week Axle Assembly weeks Tire week * Tractors require 90 wheel assemblies in week 5 Use the above data and the enclosed worksheets to determine a 10 week materials requirement plan for all SKUs associated with the wheelbarrow operation. See the last two pages. Exercise 2: 6 points A forging department is feeding parts to a U-shaped manufacturing cell (see following figure). It takes the forging area about 30 minutes to hammer out a container of 10 forgings. There is additional waiting time between processing steps of approximately 15 minutes, and moving a container to the U-Shaped cell takes 15 minutes. It is desired to set up a pull system between the U-shaped cell and the forging area. Using JIT concepts, answer the following questions: a) Under the rules of kanban, what would be the maximum container capacity? b) What would be the proper number of kanban cards, assuming 10 forgings per container? c) What is the maximum allowable WIP in this case?

4 a) The maximum capacity is either a cost trade-off (similar to EOQ) or time trade-off, minimizing the waiting time for a full container of forged items for work-cells. The information provided is not sufficient to make the necessary computation! b) Lead for full container: = 1 hour Assuming 8 working hours per day, 1/8=0.125 day at full capacity forging area supply is 10 per half an hour and assuming equal demand coming to forging (leveled production) then we have 8 * 20/hr = 160 forgings per day. Assume no safety SS=0 # Kanban = D * L (1+SS)/C = 160 * / 10 = 2 c) Max. WIP == # Kanban * Container Capacity = 20

5 Exercise 3: 12 points In the PQ problem we went over in class, we have added a third product, product R, to the company that makes Ps and Qs. The new product requires 15 minutes on the B machine and a total of 20 minutes on the C machine (5 minutes at one operation and 15 minutes at another C operation that is not shown on the original PQ problem diagram see the revised diagram below), and requires one unit of RM 2 to produce. R sells for $70 per unit and the demand is 25 units per week. a. Calculate the maximum net profit the company can make in a week. b. Assume that we have the opportunity to purchase a component from a supplier rather than make it ourselves. The component starts out as RM 1 and would already have operation A (15 minutes) done when we buy it. The price is $25 per unit. Should we purchase this component? Why or why not? Show your calculation that supports your answer. c. ow assume that we have the opportunity to purchase another B machine for $50,000 and hire an additional B worker for $400 per week. Assume also that we did not purchase the component described in above. What is the payback period for this investment based on the initial market demand of 100 Ps, 50 Qs and 25 Rs? d. Assume that we buy the new B machine and hire the additional worker. Our VP of marketing has just told us that there is a potential customer in Japan that is interested in buying 25 units of R every week for the foreseeable future but is only willing to pay $63 per unit (i.e., 10% less than our US price). This demand is in addition to our existing demand of 100 Ps, 50 Qs, and 25 Rs in the US. Decide whether we should sell any of product R in Japan, what the new product mix should be if we decide to sell to the customer in Japan, and what the maximum profit we can make in a week is considering this new opportunity. Given: A, B, C, D: 1 of each resource w/ one employee each Available time: One shift per week (2,400 minutes) Operating expenses: $6,000 per week (including direct labor) Overhead rate: 200% of direct labor Labor cost: $10 per hour

6 Products P Demand R Demand Q Demand Total Utilization Process 100 Process 25 Process 50 Machine A B C D Profit per 45/15 50/15 60/30 unit of time Product R is most profitable, thus we follow the capacity on B -- a) Profit == 45* * *17 = = 770 b) if we don't produce component starting with RM1 -- o Bottleneck time is saved -- total saving is then only on A = 1/4(15')*10$/hr=2.5$/hr if we produce we pay 20$/unit+2.5$/unit = 22.5$ per unit up to machine C The saving is less thus we don't purchase. ote: overhead cannot be saved as machine A is still in use for other products. c) Extra machine allows full production, thus total profit is 8750$ -6000$-1200$(labor & OH for new machine) = 1550$ net The difference with case (a) is: 1550$-770$=780$ ==> 50000$ investment / 780$ = 64.1 == or almost 64 weeks d) checking the capacities -- once the B is not bottleneck, the next bottleneck is C! ew profit per unit should be calculated, P R Rj Profit per 45/15 50/20 43/20 60/5 unit of time ow Q is priority, then P, R, then Rj So we should sell because we got capacity -- thus we sell 2400'-2250'=150'/20' per Rj ==> 7 units of Rj Exercise points The manager of a pigment factory is considering implementing a hierarchal model to optimize the production planning. The plant of interest produces a variety of resin products, which are ultimately used for the paint manufacturing industry. The company produces over 100 finished products. These products are divided into twenty families, 10 products for Family 1-5 respectively, 8 products for Family 6-10 respectively and 1 product for Family respectively. The plant operates with two production lines. Products compatibility criteria is observed and considered as a planning constraint since changing from one product family to another involves significant cleaning time and setup cots. Therefore, management practices product families dedication in which one line is dedicated to Family 1-3 and the second production line dedicated to Family Working capacity is 815 tons and 728 tons per month for line one and line two respectively. These estimates are based on bottleneck known as filling equipment. Production department operates on three shifts, 7 days a week. Demand level is very high (between 95 % and 100 % of available capacity), which means that not all demand is satisfied from production since some of the available capacity is consumed for set-up. The firm has restrictions on finished products ending inventory levels due to storage limitations and therefore there is no provision for safety stock policies. It is estimated that the available maximum storage capacity per month was approximately 5950 tons. Workforce involved on the production is very limited due the characteristics of the manufacturing environment, each shift requires 7 persons to run the plant, and therefore, workforce stability exists and the company does not practice workforce variations policies. The management adopts chase demand strategy and strives to avoid inventory of finished products. Likewise, stiff competition limits the firm s ability to adjust delivery dates for confirmed orders. This situation leads to a very high level of plant utilization giving the production manager no alternative but to allow backordering of unfulfilled demands. Propose a hierarchal model, and the mathematical model formulation for the first level of this problem. The model should be linear. (10 points) Indicate in words the objectives and constraints of other levels of planning. (5 points)

7 MODEL FORMULATIO This is an example of classical planning. There are two levels in this model. The first level is the aggregate planning level where it is formulated as a mixed integer-programming problem where total costs of production, inventory, setup and workforce are being minimized. Aggregate planning: Decision Variables P = Production quantity of product family i during period t in production line l. itl I = Inventory level of product family i at the end of period t in production line l. itl W = Regular workforce level in period t. t itl = φ Binary setup variable for product family i during period t in production line l. φ itl = itl itl itl 1 if P > 0; φ = 0 if P = 0 Parameters H it = = = Total number of product family. Length of planning Horizon. Z Unit production cost for family i in period t. V = Production setup cost for family i in period t; it h = Unit inventory holding cost for family i in period t. it k = Regular workforce cost for in period t. t D itl = et demand for product family i in period t in production line l.. ( SC) tl = Maximum storage capacity in period t in production line l. Q = Capacity available for production line l in period t. tl a = Unit process time for product family i in production line l. il b = Production setup time required for product family i in production line l. il TR = Total Regular time available in period t. t Objective Function Minimize the sum of production cost, setup cost, inventory cost and workforce cost. Min H 2 i= 1 t= 1 l= 1 [( Zit Pitl + Vitφ itl )] + hit Iitl + ktwt H i= 1 t= 1 H t= 1 Constraints Constraint (1) is the basic inventory identity relationship for each product family, which calls for the demand to be fulfilled by the production or inventory for each period at each production line. 2 Ditl = Pitl + I i, t 1, l I itl i, t (1) l= 1 Constraint (2) is to ensure that the total inventory does not exceed the storage capacity available for each period at each production line. I itl ( SC) tl t (2) i=1

8 Constraint (3) ensures that total production for each period does not exceed the production line capacity. Pitl Qtl t, l (3) i= 1 Constraint (4) is the regular workforce level in that period. [ ail Pitl ] = Wt t (4) i=1 Constraint (5) ensures that the regular workforce capacity for each period is sufficient for production and setup activities. Wt + [ bilφ itl ] TRt t (5) i=1 The last constraints represent the non-negativity constraints. P itl, I it, Wt 0 (6) φ itl = 0 or φitl = 1 (7) The second level is the disaggregate planning problem where for each family one model is formulated as the minimization of sum of backordering cost and inventory cost for items within the family. The constraints make sure that item production is equal to family production of level one model.

9 Item: Wheelbarrows On-hand inventory:.0 Lot size: LFL Lead time:...1wk et requirement On-hand inventory Planned receipts Planned releases Item:.Handles... On-hand inventory:.100 Lot size:..300 Lead time:...2wks et requirement On-hand inventory Planned receipts Planned releases Item:...Barrows... On-hand inventory: 60 Lot size: Lead time:...1wk et requirement On-hand inventory Planned receipts Planned releases

10 Item: Wheelass. packs On-hand inventory:.220 Lot size: 200 Lead time:...3wks required for tractor et requirement 30 On-hand inventory Planned receipts 200 Planned releases 200 Item:.Tires... On-hand inventory:.50 Lot size:..400 Lead time:...1wk 200 et requirement 150 On-hand inventory Planned receipts 400 Planned releases 400 Item:...Axie assembly... On-hand inventory: 50 Lot size:...50 Lead time:...2wks 200 et requirement 150 On-hand inventory Planned receipts 150 Planned releases 150

PRODUCTION PLANNING ANDCONTROL AND COMPUTER AIDED PRODUCTION PLANNING Production is a process whereby raw material is converted into semi-finished products and thereby adds to the value of utility of products,

More information

Introduction to Principles of Production Management WS 2012/2013 Chapter 14 Aggregate sales and Operations Planning Presented by Dr. Eng.

Introduction to Principles of Production Management WS 2012/2013 Chapter 14 Aggregate sales and Operations Planning Presented by Dr. Eng. Introduction to Principles of Production Management WS 2012/2013 Chapter 14 Aggregate sales and Operations Planning Presented by Dr. Eng.Abed Schokry Learning Outcomes Explain business planning Explain

More information

APICS PRINCIPLES OF OPERATIONS MANAGEMENT TOPIC OUTLINE CONCEPTS AND APPLICATIONS

APICS PRINCIPLES OF OPERATIONS MANAGEMENT TOPIC OUTLINE CONCEPTS AND APPLICATIONS APICS PRINCIPLES OF OPERATIONS MANAGEMENT TOPIC OUTLINE CONCEPTS AND APPLICATIONS About this Topic Outline This outline details the concepts and applications coved in all five of the APICS Principles of

More information

ISE480 Sequencing and Scheduling

ISE480 Sequencing and Scheduling ISE480 Sequencing and Scheduling INTRODUCTION ISE480 Sequencing and Scheduling 2012 2013 Spring term What is Scheduling About? Planning (deciding what to do) and scheduling (setting an order and time for

More information

JIT and Lean Operations. JIT/Lean Operations

JIT and Lean Operations. JIT/Lean Operations 5/7/2011 16 JIT and Lean Operations By : Sa Ed M. Salhieh, Salhieh, Ph.D. 16-1 JIT/Lean Operations Good production systems require that managers address three issues that are pervasive and fundamental

More information

Outline. Push-Pull Systems Global Company Profile: Toyota Motor Corporation Just-in-Time, the Toyota Production System, and Lean Operations

Outline. Push-Pull Systems Global Company Profile: Toyota Motor Corporation Just-in-Time, the Toyota Production System, and Lean Operations JIT and Lean Operations Outline Push-Pull Systems Global Company Profile: Toyota Motor Corporation Just-in-Time, the Toyota Production System, and Lean Operations Eliminate Waste Remove Variability Improve

More information

What is ERP? Source: Wikipedia

What is ERP? Source: Wikipedia Brad Staats What is ERP? Enterprise resource planning (ERP) systems integrate internal and external management information across an entire organization. The purpose of ERP is to facilitate the flow of

More information

Operations Management

Operations Management 12-1 Aggregate Planning Operations Management William J. Stevenson 8 th edition 12-2 Aggregate Planning CHAPTER 12 Aggregate Planning McGraw-Hill/Irwin Operations Management, Eighth Edition, by William

More information

Principles of Production & Inventory Management PPIM

Principles of Production & Inventory Management PPIM Principles of Production & Inventory Management PPIM PPIM course sessions. 1. Manufacturing Strategies & Resource Management 2. Product Development Cycle 3. Forecasting and Forecasting Techniques 4. Production

More information

The entire presentation kit is having 2 main directories as below. Just in Time. 01 Introduction

The entire presentation kit is having 2 main directories as below. Just in Time. 01 Introduction M118 DEMO OF JIT- JUST IN TIME DEMO OF TRAINING PRESENTATION KIT Price 160 USD Buy: http://www.globalmanagergroup.com/just-in-timetraining-presentation.htm Chapter-1.0 CONTENTS OF JIT JUST IN TIME TRAINING

More information

Chapter 16 Sl Sales and doperations Planning

Chapter 16 Sl Sales and doperations Planning Chapter 16 Sl Sales and doperations Planning Aggregate Planning Pure and Mixed Strategies Yield Management for Services Operations Planning Activities Long range Intermediate range Manufacturing Short

More information

"Value Stream Mapping How does Reliability play a role in making Lean Manufacturing a Success " Presented by Larry Akre May 17, 2007

Value Stream Mapping How does Reliability play a role in making Lean Manufacturing a Success  Presented by Larry Akre May 17, 2007 "Value Stream Mapping How does Reliability play a role in making Lean Manufacturing a Success " Presented by Larry Akre May 17, 2007 LAKRE 2007 1 Lean Manufacturing What is Lean Manufacturing? A philosophy

More information

PLUS VALUE STREAM MAPPING

PLUS VALUE STREAM MAPPING LEAN PRINCIPLES PLUS VALUE STREAM MAPPING Lean Principles for the Job Shop (v. Aug 06) 1 Lean Principles for the Job Shop (v. Aug 06) 2 Lean Principles for the Job Shop (v. Aug 06) 3 Lean Principles for

More information

Material Requirements Planning (MRP) and ERP 14. Outline

Material Requirements Planning (MRP) and ERP 14. Outline Material Requirements Planning (MRP) and ERP 14 1 Outline Global Company Profile: Wheeled Coach Dependent Demand Dependent Inventory Model Requirements MRP Structure MRP Management 2 1 Outline - Continued

More information

Optimizing Inplant Supply Chain in Steel Plants by Integrating Lean Manufacturing and Theory of Constrains through Dynamic Simulation

Optimizing Inplant Supply Chain in Steel Plants by Integrating Lean Manufacturing and Theory of Constrains through Dynamic Simulation Optimizing Inplant Supply Chain in Steel Plants by Integrating Lean Manufacturing and Theory of Constrains through Dynamic Simulation Atanu Mukherjee, President, Dastur Business and Technology Consulting,

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION 1 CHAPTER 1 INTRODUCTION 1.1 MANUFACTURING SYSTEM Manufacturing, a branch of industry, is the application of tools and processes for the transformation of raw materials into finished products. The manufacturing

More information

Just-In-Time (JIT) Manufacturing. Overview

Just-In-Time (JIT) Manufacturing. Overview Just-In-Time (JIT) Manufacturing Overview The Just-in-Time (JIT) Manufacturing Philosophy Prerequisites for JIT Manufacturing Elements of JIT Manufacturing Benefits of JIT Manufacturing Success and JIT

More information

Production Activity Control

Production Activity Control Production Activity Control Here the progress of manufacturing operations in the workshop is recorded. Also the material transactions tied to the Open WO s are entered. Open Work Order Maintenance Window

More information

Make-to-Stock under Drum-Buffer-Rope and Buffer Management Methodology

Make-to-Stock under Drum-Buffer-Rope and Buffer Management Methodology I-09 Elyakim M. Schragenheim Make-to-Stock under Drum-Buffer-Rope and Buffer Management Methodology WHY MAKE-TO-STOCK? At least from the theory of constraints (TOC) perspective this is a valid question.

More information

Master Production Scheduling - Is it still relevant?

Master Production Scheduling - Is it still relevant? Master Production Scheduling - Is it still relevant? In the 1980s and 1990s Master Production Scheduling was a big thing. Practically all serious manufacturing companies has a Master Production Scheduler,

More information

Drum Buffer-Rope. Skorkovský. Based on : R. Holt, Ph.D., PE

Drum Buffer-Rope. Skorkovský. Based on : R. Holt, Ph.D., PE Drum Buffer-Rope Skorkovský Based on : R. Holt, Ph.D., PE Traditional Approach: Divide and Conquer Division of Labor breaks down linkages complex systems into manageable chunks. Which is harder to manage?

More information

LOT SIZING IN MRP. Week Gross requirements Scheduled receipts Projected available balance Net Requirements

LOT SIZING IN MRP. Week Gross requirements Scheduled receipts Projected available balance Net Requirements LOT SIZING IN MRP The net data is subjected lot sizing Lot sizes developed can satisfy the net for one or more weeks The basic trade-off involves the elimination of one or more setups at the expense of

More information

Session 5 - MECHANICAL ENGINEERING PROFILE, ITS IMPORTANCE AND APPLICATION

Session 5 - MECHANICAL ENGINEERING PROFILE, ITS IMPORTANCE AND APPLICATION INTRO TO INDUSTRIAL ENGINEERING SESSION 5 1 Session 5 - MECHANICAL ENGINEERING PROFILE, ITS IMPORTANCE AND APPLICATION Definition of Industrial Engineering The formal definition of industrial engineering

More information

Inventory Management

Inventory Management Inventory Management Materials planning AGGREGATE PLANNING Master Production Schedule (MPS) MATERIALS PLANNING The planning of materials requirements consists of the determination of: What How much and

More information

Value Stream Mapping Train the Trainer

Value Stream Mapping Train the Trainer Value Stream Mapping Train the Trainer Information For A Process Data Box (to be collected on the shop floor) Cycle time Changeover time Process reliability (uptime) Scrap/Rework/Defect rate Number of

More information

Copyright 2000 Society of Manufacturing Engineers MANUFACTURING INSIGHTS. An Introduction to Lean Manufacturing

Copyright 2000 Society of Manufacturing Engineers MANUFACTURING INSIGHTS. An Introduction to Lean Manufacturing MANUFACTURING INSIGHTS An Introduction to Lean Manufacturing WARNING federal law provides severe civil and criminal penalties for the unauthorized reproduction, distribution or exhibition of copyrighted

More information

Chapter 05 Strategic Capacity Planning for Products and Services

Chapter 05 Strategic Capacity Planning for Products and Services Chapter 05 Strategic Capacity Planning for Products and Services Multiple Choice Questions 21. Outsourcing some production is a means of a capacity constraint. A. Identifying B. Modifying C. Supporting

More information

Operations & Supply Planning

Operations & Supply Planning Operations & Supply Planning PGDM 2017-19 Sales & Operations Planning Vinay Kumar Kalakbandi Assistant Professor Operations Management Survey No. 38, Cherlaguda Village, Shamshabad Mandal, RR District,

More information

Optimization in Supply Chain Planning

Optimization in Supply Chain Planning Optimization in Supply Chain Planning Dr. Christopher Sürie Expert Consultant SCM Optimization Agenda Introduction Hierarchical Planning Approach and Modeling Capability Optimizer Architecture and Optimization

More information

Finished goods available to meet Takt time when variations in customer demand exist.

Finished goods available to meet Takt time when variations in customer demand exist. Delaware Valley Industrial Resource Center 2905 Southampton Road Philadelphia, PA 19154 Tel: (215) 464-8550 Fax: (215) 464-8570 www.dvirc.org Term Batch-and-Queue Processing Buffer Stock Catchball Cell

More information

Aggregate Planning and S&OP

Aggregate Planning and S&OP Aggregate Planning and S&OP 13 OUTLINE Global Company Profile: Frito-Lay The Planning Process Sales and Operations Planning The Nature of Aggregate Planning Aggregate Planning Strategies 1 OUTLINE - CONTINUED

More information

AVANTUS TRAINING PTE LTD

AVANTUS TRAINING PTE LTD Manufacturing II in Microsoft Dynamics NAV 2009 Course 80261A: 3 Days; Instructor-Led About this Course This three-day course explores the advanced manufacturing functionality of Microsoft Dynamics NAV

More information

Outline. Pull Manufacturing. Push Vs. Pull Scheduling. Inventory Hides Problems. Lowering Inventory Reveals Problems

Outline. Pull Manufacturing. Push Vs. Pull Scheduling. Inventory Hides Problems. Lowering Inventory Reveals Problems Outline Pull Manufacturing Why Pull Manufacturing? The Problem of Inventory Just In Time Kanban One Piece Flow Demand / Pull Standard Work & Takt Time Production Smoothing 1 2 Why Pull Manufacturing? Push

More information

INVENTORY AND ECONOMIC ORDER QUANTITY MODELS

INVENTORY AND ECONOMIC ORDER QUANTITY MODELS INVENTORY AND ECONOMIC ORDER QUANTITY MODELS Types of Demand Retailers and distributors must manage independent demand items-that is, items for which demand is influenced by market conditions and isn t

More information

(Assignment) Master of Business Administration (MBA) PGDPM Subject : Management Subject Code : PGDPM

(Assignment) Master of Business Administration (MBA) PGDPM Subject : Management Subject Code : PGDPM (Assignment) 2017-2018 Master of Business Administration (MBA) PGDPM Subject : Management Subject Code : PGDPM Subject Title : Operation Research Course Code : PGDPM-01 Maximum Marks: 30 Note: Long Answer

More information

Shop Control Guide DBA Software Inc.

Shop Control Guide DBA Software Inc. Contents 3 Table of Contents 1 Introduction 4 2 Why You Need Shop Control 5 3 Total Control Workflow 8 4 Shop Control Overview 10 5 Setup - Work Center Capacities 13 6 Setup - Job Labor Options 16 7 Setup

More information

Hybrid Manufacturing Methods

Hybrid Manufacturing Methods Hybrid Manufacturing Methods The following manufacturing execution and costing methods are supported in SyteLine. These methods can be combined in a single environment so that the optimal method is used

More information

The lead-time gap. Planning Demand and Supply

The lead-time gap. Planning Demand and Supply Planning Demand and Supply The lead-time gap Reducing the gap by shortening the logistics lead time while simultaneously trying to move the order cycle closer through improved visibility of demand. Copyright

More information

Supply Chain Inventory Management. Multi-period Problems. Read: Chap Chap 11.

Supply Chain Inventory Management. Multi-period Problems. Read: Chap Chap 11. Supply Chain Inventory Management Multi-period Problems Read: Chap 10.1-10.2. Chap 11. Push vs. Pull Processes PUSH: Order decision initiated in anticipation to customer orders A newspaper vendor orders

More information

Role of Inventory in the Supply Chain. Inventory categories. Inventory management

Role of Inventory in the Supply Chain. Inventory categories. Inventory management Inventory management Role of Inventory in the Supply Chain Improve Matching of Supply and Demand Improved Forecasting Reduce Material Flow Time Reduce Waiting Time Reduce Buffer Inventory Economies of

More information

Manufacturing Efficiency Guide DBA Software Inc.

Manufacturing Efficiency Guide DBA Software Inc. Contents 3 Table of Contents 1 Introduction 5 2 What Is Manufacturing Efficiency? 7 3 The Seven Essential Processes 8 4 Essential #1 - Plan a Strategic Inventory 1 Strategic Inventory - Overview 10 11

More information

Table of Contents A. Organization Production MRP Controller Person Responsible for the Supply Area... 5 B. Master Data...

Table of Contents A. Organization Production MRP Controller Person Responsible for the Supply Area... 5 B. Master Data... Table of Contents A. Organization... 4 1. Production... 4 1.1. MRP Controller... 4 1.2. Person Responsible for the Supply Area... 5 B. Master Data... 5 1. Production... 6 1.1. Discrete Production... 6

More information

Numerical investigation of tradeoffs in production-inventory control policies with advance demand information

Numerical investigation of tradeoffs in production-inventory control policies with advance demand information Numerical investigation of tradeoffs in production-inventory control policies with advance demand information George Liberopoulos and telios oukoumialos University of Thessaly, Department of Mechanical

More information

PRACTICE PROBLEM SET Topic 1: Basic Process Analysis

PRACTICE PROBLEM SET Topic 1: Basic Process Analysis The Wharton School Quarter II The University of Pennsylvania Fall 1999 PRACTICE PROBLEM SET Topic 1: Basic Process Analysis Problem 1: Consider the following three-step production process: Raw Material

More information

Johan Oscar Ong, ST, MT

Johan Oscar Ong, ST, MT INVENTORY CONTROL Johan Oscar Ong, ST, MT I.1 DEFINITION Inventory are material held in an idle or incomplete state awaiting future sale, use, or transformation. (Tersine) Inventory are a stock of goods.

More information

Selling Price 60 Direct material 28 Direct Rs. 3 p. hr. 12 Variable overheads 6 Fixed cost (Total) 1,05,500

Selling Price 60 Direct material 28 Direct Rs. 3 p. hr. 12 Variable overheads 6 Fixed cost (Total) 1,05,500 Question 1 (a) PAPER 5 : ADVANCED MANAGEMENT ACCOUNTING Answer all questions. Working notes should form part of the answer. E Ltd. is engaged in the manufacturing of three products in its factory. The

More information

Operations Management

Operations Management Operations Management Chapter 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer/Render Operations Management, 11ed Some additions and deletions have been made by Ömer Yağız to this

More information

Chapter 11. In-Time and Lean Production

Chapter 11. In-Time and Lean Production Chapter 11 Just-In In-Time and Lean Production What is JIT? Producing only what is needed, when it is needed A philosophy An integrated management system JIT s mandate: Eliminate all waste Basic Elements

More information

Inventory Control Model

Inventory Control Model Inventory Control Model The word 'inventory' means simply a stock of idle resources of any kind having an economic value. In other words, inventory means a physical stock of goods, which is kept in hand

More information

Cover-Time Planning, An alternative to Material Requirements Planning; with customer order production abilities and restricted Work-In-Process *

Cover-Time Planning, An alternative to Material Requirements Planning; with customer order production abilities and restricted Work-In-Process * International Conference on Industrial Engineering and Systems Management IESM 2007 May 30 - June 2, 2007 BEIJING - CHINA Cover-Time Planning, An alternative to Material Requirements Planning; with customer

More information

Mechanical Engineering 101

Mechanical Engineering 101 Mechanical Engineering 101 University of alifornia, Berkeley Lecture #17 1 Today s lecture apacity planning Kanban intro 2 MRP Last lecture: MRP scheduling Materials Requirements Planning: MRP This lecture:

More information

AGGREGATE PLANNING (SCM) Bijay Lal Pradhan, Ph.D.

AGGREGATE PLANNING (SCM) Bijay Lal Pradhan, Ph.D. AGGREGATE PLANNING (SCM) Bijay Lal Pradhan, Ph.D. What is Aggregate Planning? DEFINITION WHAT IS AGGREGATE PLAN The aggregate production plan (APP) is a long-range materials plan. Since capacity expansion

More information

Operations and Production Management GPO300

Operations and Production Management GPO300 Operations and Production Management GPO300 8th January 2013 1 first semester 2012 13 GPO300 Operations and Production Management CLASSROOM CODE OF CONDUCT GROUND RULES: Start and end time No cell phones

More information

Lecture 9 MBF2213 Operations Management Prepared by Dr Khairul Anuar. L9: Lean synchronization

Lecture 9 MBF2213 Operations Management Prepared by Dr Khairul Anuar. L9: Lean synchronization Lecture 9 MBF2213 Operations Management Prepared by Dr Khairul Anuar L9: Lean synchronization 1 Lean operations Operations strategy Design Improvement Lean operations Planning and control The market requires

More information

History IE 376 PRODUCTION INFORMATION SYSTEMS. Course Notes Lecture #2.A Material Requirements Planning

History IE 376 PRODUCTION INFORMATION SYSTEMS. Course Notes Lecture #2.A Material Requirements Planning IE PRODUCTION INFORMATION SYSTEMS Course Notes Lecture #.A Material Requirements Planning IE Bilkent University Manufacturing Planning and Control System Routing file Resource planning Bills of material

More information

SCM Workshop, TU Berlin, October 17-18, 2005

SCM Workshop, TU Berlin, October 17-18, 2005 H.-O. Günther Dept. of Production Management Technical University of Berlin Supply Chain Management and Advanced Planning Systems A Tutorial SCM Workshop, TU Berlin, October 17-18, 2005 Outline Introduction:

More information

Note 8: Materials Requirements Planning

Note 8: Materials Requirements Planning Note 8: Materials Requirements Planning In materials requirements planning (MRP), orders for component parts are timed to coincide with the production schedule of the products in which they are used. We

More information

Oman College of Management and Technology

Oman College of Management and Technology Oman College of Management and Technology Course 803303 PIS Chapter 7 Material Requirements Planning (MRP) CS/MIS Department What is MRP? (Material Requirements Planning) Is a basic tool for performing

More information

ID Class MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question.

ID Class MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. Exam: Operations Management Name Total Scors: ID Class MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. 1) Planning is the process of coping with changes

More information

PRODUCTION PLANNING PROBLEMS IN CELLULAR MANUFACTURE

PRODUCTION PLANNING PROBLEMS IN CELLULAR MANUFACTURE PRODUCTION PLANNING PROBLEMS IN CELLULAR MANUFACTURE J. Riezebos Assistant professor Production systems design, University of Groningen, P.O.Box 800, 9700 AV Groningen, The Netherlands, email J.Riezebos@Bdk.Rug.NL,

More information

Lot-Sizing in MRP. Lot Sizing in MRP IE 376 PRODUCTION INFORMATION SYSTEMS. Course Notes Lecture #3 Lot sizing in MRP Systems

Lot-Sizing in MRP. Lot Sizing in MRP IE 376 PRODUCTION INFORMATION SYSTEMS. Course Notes Lecture #3 Lot sizing in MRP Systems PRODUCTION INFORMATION SYSTEMS Course Notes Lecture #3 Lot sizing in MRP Systems Bilkent University Lot-Sizing in MRP Lot-size is the quantity ordered/produced at one time Large lots are preferred because:

More information

Online Course Manual By Craig Pence. Module 12

Online Course Manual By Craig Pence. Module 12 Online Course Manual By Craig Pence Copyright Notice. Each module of the course manual may be viewed online, saved to disk, or printed (each is composed of 10 to 15 printed pages of text) by students enrolled

More information

Antti Salonen KPP227 KPP227 1

Antti Salonen KPP227 KPP227 1 KPP227 KPP227 1 What is Aggregate Planning? Aggregate (or intermediate-term) planning is the process of determining a company s aggregate plan = production plan. The aggregate plan specifies how the company

More information

LINEAR PROGRAMMING APPROACHES TO AGGREGATE PLANNING. Linear programming is suitable to determine the best aggregate plan.

LINEAR PROGRAMMING APPROACHES TO AGGREGATE PLANNING. Linear programming is suitable to determine the best aggregate plan. LINEAR PROGRAMMING APPROACHES TO AGGREGATE PLANNING Linear programming is suitable to determine the best aggregate plan. Recall that linear programming assumes all variables are continuously divisible.

More information

Chapter 3 Global Supply Chain Management. Book: International Logistics: Global Supply Chain Management by Douglas Long Slides made by Ta-Hui Yang

Chapter 3 Global Supply Chain Management. Book: International Logistics: Global Supply Chain Management by Douglas Long Slides made by Ta-Hui Yang Chapter 3 Global Supply Chain Management Book: International Logistics: Global Supply Chain Management by Douglas Long Slides made by Ta-Hui Yang 1 Outline The supply chain concept Efficiency in the supply

More information

Planning Optimized. Building a Sustainable Competitive Advantage WHITE PAPER

Planning Optimized. Building a Sustainable Competitive Advantage WHITE PAPER Planning Optimized Building a Sustainable Competitive Advantage WHITE PAPER Planning Optimized Building a Sustainable Competitive Advantage Executive Summary Achieving an optimal planning state is a journey

More information

Chapter 13. Lean and Sustainable Supply Chains

Chapter 13. Lean and Sustainable Supply Chains 1 Chapter 13 Lean and Sustainable Supply Chains 2 OBJECTIVES Lean Production Defined The Toyota Production System Lean Implementation Requirements Lean Services Lean Production 3 Lean Production can be

More information

Version 3.2 February 2007

Version 3.2 February 2007 Features Guide 1 Version 3.2 February 2007 Copyright 2005-2007 DBA Software Inc. All rights reserved. 2 Features Guide Table of Contents 1. Why DBA? 7 Our Mission Statement 8 Our Sales & Support Model

More information

Production Scheduling

Production Scheduling Production Scheduling MRP, TOC & Lean Arthur Greef Software Architect Dynamics AX Production Microsoft Corporation Outline 2 Product & production classification MRP, CRP and job dispatching TOC scheduling

More information

Chapter 3--Product Costing: Manufacturing Processes, Cost Terminology, and Cost Flows

Chapter 3--Product Costing: Manufacturing Processes, Cost Terminology, and Cost Flows Chapter 3--Product Costing: Manufacturing Processes, Cost Terminology, and Cost Flows Student: 1. Which of the following types of organizations is most likely to have a raw materials inventory account?

More information

Product cost & variance in a manufacturing process Specialty alloy manufacturer Situation

Product cost & variance in a manufacturing process Specialty alloy manufacturer Situation Product cost & variance in a manufacturing process Specialty alloy manufacturer Situation This client is a world leader in the development and manufacture of high performance nickel and cobalt-based alloys

More information

Chapter 6. The Production Process

Chapter 6. The Production Process Chapter 6 The Production Process 1 Learning Objectives 1. Describe the master data associated with the production process. 2. Identify the key steps in the production process and the data, documents, and

More information

Lean manufacturing concept: the main factor in improving manufacturing performance a case study

Lean manufacturing concept: the main factor in improving manufacturing performance a case study Int. J. Manufacturing Technology and Management, Vol. 17, No. 4, 2009 353 Lean manufacturing concept: the main factor in improving manufacturing performance a case study N. Zakuan* Lecturer, UTHM, Parit

More information

THE VALUE OF DISCRETE-EVENT SIMULATION IN COMPUTER-AIDED PROCESS OPERATIONS

THE VALUE OF DISCRETE-EVENT SIMULATION IN COMPUTER-AIDED PROCESS OPERATIONS THE VALUE OF DISCRETE-EVENT SIMULATION IN COMPUTER-AIDED PROCESS OPERATIONS Foundations of Computer Aided Process Operations Conference Ricki G. Ingalls, PhD Texas State University Diamond Head Associates,

More information

THE "OPERATIONS RESEARCH METHOD" Orientation. Problem Definition. Data Collection. Model Construction. Solution. Validation and Analysis

THE OPERATIONS RESEARCH METHOD Orientation. Problem Definition. Data Collection. Model Construction. Solution. Validation and Analysis THE "OPERATIONS RESEARCH METHOD" Orientation Problem Definition F E E D B A C K Data Collection Model Construction Solution Validation and Analysis Implementation & Monitoring An OR Problem - A Simple

More information

Lecture 6. Capacity and Facilities. Lecture Outline. Capacity. Maximum capability to produce Capacity planning

Lecture 6. Capacity and Facilities. Lecture Outline. Capacity. Maximum capability to produce Capacity planning MGS4700 Operations Management Capacity and Facilities ecture 6 ecture Outline Capacity Planning Facility ayout Basic ayouts Designing Process ayouts Designing Service ayouts Designing Product ayouts Hybrid

More information

Best Practices in Demand and Inventory Planning

Best Practices in Demand and Inventory Planning W H I T E P A P E R Best Practices in Demand and Inventory Planning for Chemical Companies Executive Summary In support of its present and future customers, CDC Software sponsored this white paper to help

More information

Cost Analysis and Estimating for Engineering and Management

Cost Analysis and Estimating for Engineering and Management Cost Analysis and Estimating for Engineering and Management Chapter 3 Material Analysis Ch 3-1 Overview Look at Material in Manufacturing Determine the Material Cost Finding the Amount of Material Needed

More information

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Lecture - 24 Sequencing and Scheduling - Assumptions, Objectives and Shop

More information

Pull Systems: Overview, Challenges and Success Factors

Pull Systems: Overview, Challenges and Success Factors Pull Systems: Overview, Challenges and Success Factors Mike Osterling 619-572-3632 mike@mosterling.com 1 Session Objectives Cover the most common types of pull systems See some examples of application

More information

Value Stream Mapping

Value Stream Mapping Value Stream Mapping Dr. Bob Gee Dean Scott Bonney Professor William G. Journigan American Meridian University 1 Learning Objectives Upon successful completion of this module, the student should be able

More information

SYLLABUS PRODUCTION & OPERATIONS MANAGEMENT

SYLLABUS PRODUCTION & OPERATIONS MANAGEMENT SYLLABUS PRODUCTION & OPERATIONS MANAGEMENT MBA 2nd SEMESTER, M.D.U., ROHTAK External Marks : 70 Time : 3 hrs. Internal Marks : 30 UNIT-I Meaning, nature, scope and major decision areas of production management;

More information

Inventory Control Models

Inventory Control Models Chapter 6 Inventory Control Models uantitative Analysis for Management, Tenth Edition, by Render, Stair, and Hanna 2008 Prentice-Hall, Inc. Introduction Inventory is any stored resource used to satisfy

More information

ABS Software Brochure

ABS Software Brochure Brochure The is a fully integrated, linear programming software package that will optimize site specific melting economics. Your customized solution could include the following: Least Cost Charge Design

More information

Acct 1B Week 8, Chap 7

Acct 1B Week 8, Chap 7 Acct 1B Week 8, Chap 7 Activity Based Costing (ABC) Instructor: Michael Booth Cabrillo College Activity Based Costing: A Tool to Aid Decision Making Global Business Situation Using technology and productivity

More information

Allocating work in process in a multiple-product CONWIP system with lost sales

Allocating work in process in a multiple-product CONWIP system with lost sales Allocating work in process in a multiple-product CONWIP system with lost sales S. M. Ryan* and J. Vorasayan Department of Industrial & Manufacturing Systems Engineering Iowa State University *Corresponding

More information

Abstract number: SUPPORTING THE BALANCED SCORECARD FROM THE MANUFACTURING SYSTEM

Abstract number: SUPPORTING THE BALANCED SCORECARD FROM THE MANUFACTURING SYSTEM Abstract number: 002-0538 SUPPORTING THE BALANCED SCORECARD FROM THE MANUFACTURING SYSTEM Second World Conference on POM and 15 th Annual POM Conference Cancun, Mexico, April 30 May 3, 2004 Authors Rafael

More information

For more information, please contact: Andrew Setter randy Peck

For more information, please contact: Andrew Setter randy Peck BABBITT ALLOYS For more information, please contact: Andrew Setter asetter@behrim.com 815-987-2723 randy Peck rpeck@behrim.com 815-987-2708 The Babbitt Division of Behr Iron & Metal is one of North America

More information

Sven Axsäter. Inventory Control. Third Edition. Springer

Sven Axsäter. Inventory Control. Third Edition. Springer Sven Axsäter Inventory Control Third Edition Springer Contents 1 Introduction 1 1.1 Importance and Objectives of Inventory Control 1 1.2 Overview and Purpose of the Book 2 1.3 Framework 4 2 Forecasting

More information

Dennis Bricker Dept of Mechanical & Industrial Engineering The University of Iowa. JIT --Intro 02/11/03 page 1 of 28

Dennis Bricker Dept of Mechanical & Industrial Engineering The University of Iowa. JIT --Intro 02/11/03 page 1 of 28 Dennis Bricker Dept of Mechanical & Industrial Engineering The University of Iowa JIT --Intro 02/11/03 page 1 of 28 Pull/Push Systems Pull system: System for moving work where a workstation pulls output

More information

Operation Process Charting: How It s Made Here. APICS Fraser Valley November 2016 Presented by: Richard Ranftl (BCIT)

Operation Process Charting: How It s Made Here. APICS Fraser Valley November 2016 Presented by: Richard Ranftl (BCIT) Operation Process Charting: How It s Made Here APICS Fraser Valley November 2016 Presented by: Richard Ranftl (BCIT) Manufacturing Systems What do we need to have in place to make the system functional?

More information

Chapter 2--Product Costing: Manufacturing Processes, Cost Terminology, and Cost Flows

Chapter 2--Product Costing: Manufacturing Processes, Cost Terminology, and Cost Flows Chapter 2--Product Costing: Manufacturing Processes, Cost Terminology, and Cost Flows Student: 1. Which of the following types of organizations is most likely to have a raw materials inventory account?

More information

Lean Means Speed. Alessandro Anzalone, Ph.D Hillsborough Community College, Brandon Campus

Lean Means Speed. Alessandro Anzalone, Ph.D Hillsborough Community College, Brandon Campus Lean Means Speed Alessandro Anzalone, Ph.D Hillsborough Community College, Brandon Campus 1. Is This Lean? 2. The Essentials of Lean 3. The Lean Metric: Cycle Efficiency 4. Velocity of Any Process 5. Knowing

More information

Supply Chain Redesign Employing Advanced Planning Systems

Supply Chain Redesign Employing Advanced Planning Systems Supply Chain Redesign Employing Advanced Planning Systems Jim Andersson and Martin Rudberg Jim Andersson, Lawson Sweden, Propellergatan 1, SE-211 19 Malmö, Sweden Martin Rudberg, Department of and Engineering,

More information

LEAN PRODUCTION FACILITY LAYOUT.

LEAN PRODUCTION FACILITY LAYOUT. LEAN PRODUCTION FACILITY LAYOUT www.fourprinciples.com BACKGROUND The production facility layout is as important as the technology it houses and has a significant impact on business performance. The layout

More information

Chapter 3 Formulation of LP Models

Chapter 3 Formulation of LP Models Chapter 3 Formulation of LP Models The problems we have considered in Chapters 1 and 2 have had limited scope and their formulations were very straightforward. However, as the complexity of the problem

More information

Financial Transfer Guide DBA Software Inc.

Financial Transfer Guide DBA Software Inc. Contents 3 Table of Contents 1 Introduction 4 2 Why You Need the Financial Transfer 6 3 Total Control Workflow 10 4 Financial Transfer Overview 12 5 Multiple Operating Entities Setup 15 6 General Ledger

More information

Chapter 6 RESOURCE PLANNING SYSTEMS. Prepared by Mark A. Jacobs, PhD

Chapter 6 RESOURCE PLANNING SYSTEMS. Prepared by Mark A. Jacobs, PhD Chapter 6 RESOURCE PLANNING SYSTEMS Prepared by Mark A. Jacobs, PhD LEARNING OBJECTIVES You should be able to: Describe the hierarchical operations planning process in terms of materials planning (APP,

More information

Parwadi Moengin, Member IAENG

Parwadi Moengin, Member IAENG International Journal of Mechanical & Mechatronics Engineering IJMME-IJENS Vol:16 No:5 23 Mathematical Model and Algorithm of Integrated Production-Inventory-Distribution System for Billet Steel Manufacturing

More information

Simulation of Lean Principles Impact in a Multi-Product Supply Chain

Simulation of Lean Principles Impact in a Multi-Product Supply Chain Simulation of Lean Principles Impact in a Multi-Product Supply Chain M. Rossini, A. Portioli Studacher Abstract The market competition is moving from the single firm to the whole supply chain because of

More information