CHAPTER 26 (FIN MAN); CHAPTER 11 (MAN) COST ALLOCATION AND ACTIVITY-BASED COSTING

Size: px
Start display at page:

Download "CHAPTER 26 (FIN MAN); CHAPTER 11 (MAN) COST ALLOCATION AND ACTIVITY-BASED COSTING"

Transcription

1 (FIN MAN); CHAPTER 11 (MAN) COST ALLOCATION AND ACTIVITY-BASED COSTING DISCUSSION QUESTIONS 1. Management desires accurate product costs so that its decisions regarding products are correct. Managers are concerned about the accuracy of product costs, which are used for decisions such as determining product mix, establishing product price, and determining whether to discontinue a product line. 2. A single plantwide overhead rate will provide accurate product costing if products use production department activity-base quantities in nearly the same ratio across departments. For example, if Product X used 2 hours of Department A and 4 hours of Department B activity-base quantities and Product Y used 1 hour of Department A and 2 hours of Department B activity-base quantities, then a single rate approach would not cause distortion. This is true because the ratio of activity-base usage quantity is 1:2 for both products across the two departments. Additionally, if the production departments have nearly the same factory overhead rate, then there would be no need to use the multiple production department rate method. 3. Under the multiple production department rate method, factory overhead rates are determined for each production department. Factory overhead is allocated to products depending on the amount of allocation base used in each department. Under the single plantwide rate method, one factory overhead rate is determined for the whole factory and is allocated to products depending on the amount of allocation base used in the factory. 4. The multiple production department factory overhead rate method would provide more accurate product costs than the single plantwide factory overhead method when there are significant differences in the factory overhead rates across different production departments, and when the products require different proportions of allocation-base usage in each production department. 5. Under activity-based costing, factory overhead costs are assigned to activity cost pools rather than production departments. The budgeted factory overhead in the activity pools is allocated to products based upon their own unique activity rates. 6. These activities are part of selling and administrative expenses, which must be treated as period expenses under generally accepted accounting principles (GAAP). Thus, they cannot be included as product costs under GAAP. 7. If the costs listed in Discussion Question 6 were included as product costs, then they would be part of the cost of inventory. If inventory increased, then the net income would be more than it would be under GAAP, since these selling and administrative expenses would be capitalized in inventory rather than being expensed as required. 8. Calculating product costs using activity rates may result in greater accuracy than using multiple production department overhead rates when products consume activities in proportions that are unrelated to departmental allocation bases. 9. -based costing would be preferred over the relative sales value method when the products use selling and administrative activities in proportions that are unrelated to their sales volumes. 10. Service companies can use activity-based costing to determine the cost of service offerings. This information can be used to determine customer service profitability, which in turn can be used to guide service pricing and strategy. 26-1

2 Cost Allocation and -Based Costing PE 26 1A (FIN MAN); PE 11 1A (MAN) a. Jeans: 20,000 units 0.10 direct labor hour = 2,000 direct labor hours Khakis: 20,000 units 0.10 direct labor hour = 2,000 4,000 direct labor hours b. Single plantwide factory overhead rate: $180,000 4,000 dlh = $45 per dlh PRACTICE EXERCISES c. Jeans: $45 per direct labor hour 0.10 dlh per unit = $4.50/unit Khakis: $45 per direct labor hour 0.10 dlh per unit = $4.50/unit PE 26 1B (FIN MAN); PE 11 1B (MAN) a. Speedboat: 250 units 12 direct labor hours = 3,000 direct labor hours Bass boat: 250 units 12 direct labor hours = 3,000 6,000 direct labor hours b. Single plantwide factory overhead rate: $600,000 6,000 dlh = $100 per dlh c. Speedboat: $100 per direct labor hour 12 dlh per unit = $1,200/unit Bass boat: $100 per direct labor hour 12 dlh per unit = $1,200/unit PE 26 2A (FIN MAN); PE 11 2A (MAN) a. Cutting: (20,000 jeans 0.04 dlh) + (20,000 khakis 0.06 dlh) = 2,000 direct labor hours Sewing: (20,000 jeans 0.06 dlh) + (20,000 khakis 0.04 dlh) = 2,000 direct labor hours b. Cutting Department rate: $60,000 2,000 dlh = $30 per dlh Sewing Department rate: $120,000 2,000 dlh = $60 per dlh c. Jeans: Cutting Department 0.04 dlh $30 = Sewing Department 0.06 dlh $60 = Total factory overhead per pair of jeans $ $4.80 Khakis: Cutting Department 0.06 dlh $30 = Sewing Department 0.04 dlh $60 = Total factory overhead per pair of khakis $ $

3 Cost Allocation and -Based Costing PE 26 2B (FIN MAN); PE 11 2B (MAN) a. Fabrication: (250 speedboats 8 dlh) + (250 bass boats 4 dlh) = 3,000 direct labor hours Assembly: (250 speedboats 4 dlh) + (250 bass boats 8 dlh) = 3,000 direct labor hours b. Fabrication Department rate: $420,000 3,000 dlh = $140 per dlh Assembly Department rate: $180,000 3,000 dlh = $60 per dlh c. Speedboat: Fabrication Department 8 dlh $140 = $1,120 Assembly Department 4 dlh $60 = 240 Total factory overhead per speedboat $1,360 Bass boat: Fabrication Department 4 dlh $140 = Assembly Department 8 dlh $60 = $ Total factory overhead per bass boat $1,

4 Cost Allocation and -Based Costing PE 26 3A (FIN MAN); PE 11 3A (MAN) a. Cutting: $18,000 2,000 direct labor hours = $9.00 per dlh Sewing: $36,000 2,000 direct labor hours = $18.00 per dlh Setup: $96,000 2,400 setups = $40.00 per setup Inspection: $30,000 5,000 inspections = $6.00 per inspection b. Jeans Khakis - Base - Base Usage Rate = Cost Usage Rate = Cost Cutting 800 dlh $9.00 /dlh $ 7,200 1,200 dlh $9.00 /dlh $10,800 Sewing 1,200 dlh $18.00 /dlh 21, dlh $18.00 /dlh 14,400 Setup 1,400 setups $40.00 /setup 56,000 1,000 setups $40.00 /setup 40,000 Inspections 3,000 insp. $6.00 /insp. 18,000 2,000 insp. $6.00 /insp. 12,000 Total $102,800 $77,200 Budgeted items 20,000 20,000 Factory overhead per unit $ 5.14 $

5 Cost Allocation and -Based Costing PE 26 3B (FIN MAN); PE 11 3B (MAN) a. Fabrication: $204,000 3,000 direct labor hours = $68 per dlh Assembly: $105,000 3,000 direct labor hours = $35 per dlh Setup: $156, setups = $390 per setup Inspection: $135,000 1,500 inspections = $90 per inspection b. Speed Boat Bass Boat - - Base Base Usage Rate = Cost Usage Rate = Cost Fabrication 2,000 dlh $68 /dlh $136,000 1,000 dlh $68 /dlh $ 68,000 Assembly 1,000 dlh $35 /dlh 35,000 2,000 dlh $35 /dlh 70,000 Setup 300 setups $390 /setup 117, setups $390 /setup 39,000 Inspections 1,100 insp. $90 /insp. 99, insp. $90 /insp. 36,000 Total $387,000 $213,000 Budgeted items Factory overhead per unit $ 1,548 $

6 Cost Allocation and -Based Costing PE 26 4A (FIN MAN); PE 11 4A (MAN) a. Sales order processing activity: 5,000 orders $12 per order = $60,000 Shipping activity: 1,400 shipments $20 per shipment = 28,000 Total activity cost $88,000 b. $3.20 per unit ($88,000 27,500 units) PE 26 4B (FIN MAN); PE 11 4B (MAN) a. Sales order processing activity: 750 orders $20 per order = $15,000 Customer return activity: 80 returns $100 per return = 8,000 Total activity cost $23,000 b. $9.20 per unit ($23,000 2,500 units) PE 26 5A (FIN MAN); PE 11 5A (MAN) Teller transaction processing $42.00 (12 transactions $3.50) Check processing (100 checks $0.12) ATM transaction processing 2.00 (20 transactions $0.10) Total activity cost $56.00 PE 26 5B (FIN MAN); PE 11 5B (MAN) Guest check-in $ 8.00 (1 check-in $8.00) Room cleaning (3 nights $25.00) Meal service (3 meals $4.00) Total activity cost $

7 Cost Allocation and -Based Costing EXERCISES Ex (FIN MAN); Ex (MAN) ($560,000 8,000) 5,150 = $360,500 Ex (FIN MAN); Ex (MAN) a. Single Plantwide Factory Overhead Rate = = $188,000 4,700 direct labor hours* $40 per direct labor hour * Total direct labor hours: Direct Labor Hours per Unit = Trumpets 2,100 units 0.8 = Tubas = Trombones 1, = Total Budgeted Production Volume Direct Labor Hours 1,680 1,200 1,820 4,700 b. Single Plant- Direct Labor Hours wide Rate per Direct Labor Hour = Factory Overhead Factory Overhead per Unit (Factory Overhead Budgeted Production Volume) Trumpets 1,680 $40 = $ 67,200 $67,200 2,100 units = $32 Tubas 1, = 48,000 $48, units = $64 Trombones 1, = 72,800 $72,800 1,300 units = $56 Total 4,700 $188,

8 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. Single Plantwide Factory Overhead Rate = = $153,000* 2,550 processing hours** $60 per direct processing hour * $196,000 $18,000 $25,000 The selling and administrative expenses are not factory overhead. ** Total processing hours: Budgeted Production Volume Processing Processing (Cases) Hours per Case = Hours Tortilla chips 4, = 800 Potato chips 5, = 750 Pretzels 2, = 1,000 Total 2,550 b. Single Plantwide Factory Overhead Rate per Factory Overhead per Case Processing Hours Processing Hour = Factory Overhead (Factory Overhead Budgeted Production Volume) Tortilla chips 800 $60 = $ 48,000 $48,000 4,000 cases = $12.00 Potato chips = 45,000 $45,000 5,000 cases = $9.00 Pretzels 1, = 60,000 $60,000 2,500 cases = $24.00 Total 2,550 $153,

9 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. First, determine the total estimated labor hours consumed by the three products: Direct Labor Total Hours per Labor Volume Unit = Hours Pistons 7, = 1,440 Valves 28, = 4,320 Cams 1, = 384 Total estimated direct labor hours 6,144 Next, determine the plantwide overhead rate: Budgeted Factory Overhead Plantwide Allocation Base = $184,320 6,144 direct labor hours = $30.00 per dlh b. Factory Overhead Direct Labor Cost per Unit Hours per ($30.00 Direct Unit Labor Hours per Unit) Pistons 0.20 $6.00 Valves Cams Direct Labor Cost per Unit ($20.00 Direct Labor Hours per Unit) $ c. ORANGE COUNTY ENGINE PARTS INC. Product Line Budgeted Gross Profit Reports For the Year Ended December 31, 2016 Pistons Valves Cams Revenues (price unit volume) Direct materials (direct materials cost per unit unit volume) Direct labor [direct labor cost per unit (b) unit volume] Factory overhead [factory overhead cost per unit (b) unit volume] 1 $360,000 $180, , ,20010 $252,000 2 $288,000 $115, , ,60011 $331,200 $84,0003 $34,8006 7, ,52012 $54,000 Gross profit Gross profit percentage of sales $108, % $ (43,200) 15.0% $30, % 1 7,200 $ ,800 $ ,200 $ ,800 $ ,200 $ ,200 $ ,200 $ ,200 $ ,800 $ ,200 $ ,800 $ ,200 $9.60 d. Valves have the lowest (and negative) gross profit as a percent of sales. Valves may require a higher price or lower cost to manufacture in order to achieve the same profitability as the other two products. 26-9

10 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. Production department factory overhead rates: Pattern Department Cut and Sew Department Total factory overhead $288,000 $412,500 Direct labor hours 2,880 dlh 3,300 dlh Departmental overhead rate $ /dlh $ /dlh b. Product cost allocation: Small Glove Pattern Department 0.10 dir. labor hr. $100/dlh = $10.00 Cut and Sew Department 0.12 dir. labor hr. $125/dlh = Total factory overhead per small glove $25.00 Medium Glove Pattern Department 0.12 dir. labor hr. $100/dlh = $12.00 Cut and Sew Department 0.14 dir. labor hr. $125/dlh = Total factory overhead per medium glove $29.50 Large Glove Pattern Department 0.14 dir. labor hr. $100/dlh = $14.00 Cut and Sew Department 0.16 dir. labor hr. $125/dlh = Total factory overhead per large glove $

11 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. Plantwide overhead rate: Budgeted Factory Overhead = Plantwide Allocation Base $990,000 9,000 direct machine hours = $ per dmh Product costs: Commercial $110 per dir. mach. hr. 4.5 dmh = $495 Residential $110 per dir. mach. hr. 3.0 dmh = $330 b. Department factory overhead rates: Production department overhead $240,000 $750,000 Direct machine hours 3,000 dmh 6,000 Production department overhead rate $ /dmh $ Product cost allocation: Assembly Department Commercial Motor Assembly Department 1.5 dir. mach. hr. $80/dmh = $120 Testing Department 3.0 dir. mach. hrs. $125/dmh = 375 Total factory overhead per commercial motor $495 Residential Motor Assembly Department 1.0 dir. mach. hrs. $80/dmh = $ 80 Testing Department 2.0 dir. mach. hrs. $125/dmh = 250 Total factory overhead per residential motor $330 Testing Department c. The factory overhead determined under the single plantwide factory overhead rate and multiple production department factory overhead rate methods are the same. This is because the ratio of direct machine hours used by each product from the two departments is the same. The commercial motor uses 1.5 direct machine hour in the Assembly Department and 3.0 hours in the Testing Department, or a ratio of 1:2. The residential motor uses 1.0 direct machine hours in the Assembly Department and 2.0 hours in the Testing Department, also for a ratio of 1:2. Thus, even though the two production department overhead rates are different, this is not sufficient for the plantwide rate to cause product cost distortion. Thus, Pineapple should consider remaining with the easier single plantwide rate method in this situation. dmh /dmh 26-11

12 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. Plantwide factory overhead rate: Budgeted Factory Overhead Plantwide Allocation Base = $800,000 10,000 direct labor hours = $80 per dlh Product costs: Gasoline engine $80 per dir. labor hr. 5.0 dlh = $400 Diesel engine $80 per dir. labor hr. 5.0 dlh = $400 b. Department factory overhead rates: Total production department factory overhead $550,000 $250,000 Direct labor hours 5,000 dlh 5,000 Production department overhead rate $ 110 /dlh $ 50 Product cost allocation: Fabrication Department Assembly Department Gasoline engine Fabrication Department 3.0 dir. labor hr. $110/dlh = $330 Assembly Department 2.0 dir. labor hrs. $50/dlh = 100 Total factory overhead per gasoline engine $430 Diesel engine Fabrication Department 2.0 dir. labor hrs. $110/dlh = $220 Assembly Department 3.0 dir. labor hr. $50/dlh = 150 Total factory overhead per diesel engine $370 c. Management should select the multiple department factory overhead rate method of allocating overhead costs. The single plantwide factory overhead rate method indicates that both products have the same factory overhead of $400 per unit. This is because each product uses a total of 5.0 direct labor hours per unit. However, each product uses these 5.0 direct labor hours much differently. The gasoline engine consumes 3.0 hours in the expensive Fabrication Department and 2.0 hours in the less expensive Assembly Department. The opposite is the case for diesel engines. Thus, the multiple production department rate method avoids the cost distortions of the single plantwide rate method by accounting for the overhead in each production department separately. In this case, there are both production department rate differences across the departments and differences in the ratios of allocation-base usage of the products across the departments (3.0:2.0 vs. 2.0:3.0). These conditions will cause the single plantwide rate method to distort product costs. dlh /dlh 26-12

13 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) Accounting reports Customer return processing Electric power Human resources Inventory control Invoice and collecting Machine depreciation Materials handling Order shipping Payroll Production control Production setup Purchasing Quality control Sales order processes Base Number of accounting reports Number of customer returns Kilowatt hours used Number of employees Number of inventory transactions Number of customer orders Number of machine hours Number of material moves Number of customer orders Number of payroll checks processed Number of production orders Number of setups Number of purchase orders Number of inspections Number of sales orders Ex (FIN MAN); Ex (MAN) a. Sales order processing activity rate: $540,000 60,000 sales orders = $9 per sales order b. Sales order processing cost: $9 45,000 sales orders = $405,

14 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) - - Elliptical Machines Treadmills Base Base Usage Rate = Cost Usage Rate = Cost Fabrication 800 mh $30 /mh $24, mh $30 /mh $15,000 Assembly 210 dlh $15 /dlh 3, dlh $15 /dlh 1,350 Setup 24 setups $50 /setup 1, setups $50 /setup 500 Inspecting 140 insp. $25 /insp. 3, insp. $25 /insp. 4,000 Production scheduling 20 prod. ord. $15 /prod. ord prod. ord. $15 /prod. ord. 150 Purchasing 85 purch. ord. $10 /purch. ord purch. ord. $10 /purch. ord. 600 Total activity cost $33,000 $21,600 Number of units cost per unit $ $

15 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. Budgeted Total Cost Base = Rate Casting $127,750 3,650 mh $35 /mh Assembly 63,200 3,160 dlh $20 /dlh Inspecting 21,330 1,185 insp. $18 /insp. Setup 28, setups $125 /setup Materials handling 31, loads $40 /load b. Entry Lighting Fixtures - Dining Room Lighting Fixtures - Base Base Usage Rate = Cost Usage Rate = Cost Casting 2,500 mh $35 /mh $ 87,500 1,150 mh $35 /mh $ 40,250 Assembly 960 dlh $20 /dlh 19,200 2,200 dlh $20 /dlh 44,000 Inspecting 860 insp. $18 /insp. 15, insp. $18 /insp. 5,850 Setup 170 setups $125 /setup 21, setups $125 /setup 7,500 Materials handling 570 loads $40 /load 22, loads $40 /load 8,800 Total activity cost $166,230 $106,400 Number of units cost per unit $ 5, $ 2,

16 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. Product Procurement Scheduling Materials Handling Development Factory overhead $66,000 $4,120 $13,280 $8,100 base 660 purch. ords. 206 prod. ords. 415 moves 108 ECOs* rate $ 100 /purch. ord. $ 20 /prod. ord. $ 32 /move $ 75 /ECOs * Engineering Change Order b. - - Ovens Refrigerators Base Base Usage Rate = Cost Usage Rate = Cost Procurement 400 purch. ords. $100 /purch. ord. $ 40, purch. ords. $100 /purch. ord. $26,000 Scheduling 136 prod. ords. $20 /prod. ord. 2, prod. ords. $20 /prod. ord. 1,400 Materials handling 240 moves $32 /move 7, moves $32 /move 5,600 Product development 68 ECOs $75 /ECO 5, ECOs $75 /ECO 3,000 Total $55,500 $36,000 Unit volume cost per unit $ $

17 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. Single plantwide rate: Indirect Labor Plantwide Allocation Base = $375,000 3,750 direct labor hours = $100 per direct labor hour Direct Labor Hours Plantwide Rate = Indirect Labor Cost Units = Cell phones 1,875 $100 /dlh = $187,500 93,750 = Tablets 1,875 $100 /dlh = $187,500 93,750 = Indirect Labor Cost per Unit $2.00 $2.00 b. -based rates: Production Setup Support Budgeted activity cost* $150,000 $225,000 base 2,000 setups 3,750 dlh rate $ /setup $ /dlh * Setup activity cost = $375,000 40% = $150,000 Production support activity cost = $375,000 60% = $225,

18 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) (Concluded) c. Cell Phones Tablets - - Base Base Usage Rate = Cost Usage Rate = Cost Setup 600 setups $75.00 /setup $ 45,000 1,400 setups $75.00 /setup $105,000 Production support 1,875 dlh $60.00 /dlh 112,500 1,875 dlh $60.00 /dlh 112,500 Total $157,500 $217,500 Units cost per unit $ 93, $ 93, d. The per-unit indirect labor costs in (a) are distorted because setup activity is consumed by the products in a different ratio from the direct labor. Cell phones required 600 setups over a volume of 93,750 units (or 156 units per production run), while tablets required 1,400 setups over the same volume (approximately 67 units per production run). The activity-based costing method properly allocates the setup-related activity so that the tablets, the setup-intensive product, receive a larger portion of the setup activity cost, while the cell phones receive a smaller portion. The single rate system allocates overhead only on the basis of direct labor hours. Since the direct labor hours are equal for each product, the allocated indirect labor will also be equal. Again, this is clearly a distortion, since the setup activity (40% of the indirect labor) is not consumed equally by each product

19 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. Production department factory overhead rates: Assembly Department Test and Pack Department Factory overhead $186,000 $120,000 Direct labor hours 3,000 3,000 Production department factory overhead rate $ 62 /dlh $ 40 /dlh b. Blender Toaster Oven Allocation- Base Allocation- Base Usage Rate = Cost Usage Rate = Cost Assembly Department 750 dlh $62 /dlh $ 46,500 2,250 dlh $62 /dlh $139,500 Test and Pack Department 2,250 dlh $40 /dlh 90, dlh $40 /dlh 30,000 Total $136,500 $169,500 Units 7,500 7,500 Factory overhead cost per unit $ $

20 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. rates: Budgeted activity cost $105,000 1 $39,000 2 $162,000 base 3,000 dlh 3,000 dlh 180 setups rate $ 35 /dlh $ 13 /dlh $ 900 /setup 1 $186,000 $81,000 2 $120,000 $81,000 Assembly Test and Pack Setup b. Blender - - Toaster Oven Base Base Usage Rate = Cost Usage Rate = Cost Assembly activity 750 dlh $35 /dlh $ 26,250 2,250 dlh $35 /dlh $ 78,750 Test and pack activity 2,250 dlh $13 /dlh 29, dlh $13 /dlh 9,750 Setup activity 135 setups $900 /setup 121, setups $900 /setup 40,500 Total $177,000 $129,000 Units 7,500 7,500 Factory overhead cost per unit $ $

21 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) (Concluded) Note to Instructors: If you assigned both Ex and Ex , then you can make the following observations: The activity-based costing approach provides unit factory overhead cost information that is opposite to that of the multiple production department factory overhead rate method. The reason is that the multiple production department factory overhead rate method allocates all factory overhead to the products on the basis of direct labor hours. However, factory overhead includes the setup activity. Setup activity is consumed by the products in ratios that are not equal to their direct labor consumption. Indeed, the blender uses three times as much setup activity as the toaster oven. The activity-based costing method correctly accounts for this difference, while the multiple production department factory overhead rate method incorrectly assumes that this activity is equal to both products (proportional to the direct labor hours or volume of production). Thus, the management of Four Finger Appliance should be encouraged to use activity-based costing information for product-based decisions

22 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. Column A Column B Column C Single Rate Overhead ABC Overhead Percent Change Allocation Allocation in Allocation Product Volume Class per Unit per Unit (Col. B Col. A) Col. A 1 2 Low $30.00 $ % Medium % High % 1 (24 hours $200/hour) 160 units 2 [(24 hours $160/hour) + (14 setups $240/setup) + (38 sales orders $55/sales order)] 160 units 3 (225 hours $200/hour) 1,500 units 4 [(225 hours $160/hour) + (13 setups $240/setup) + (88 sales orders $55/sales order)] 1,500 units 5 (900 hours $200/hour) 6,000 units 6 [(900 hours $160/hour) + (9 setups $240/setup) + (120 sales orders $55/sales order)] 6,000 units b. The machine hour rate is greater under the single rate method than under the activitybased method because all the factory overhead is allocated by machine hours under the single rate method. However, only a portion of the factory overhead is allocated under the machine rate method using activity-based costing. The remaining factory overhead is allocated using the other two activity rates. Thus, the numerator for determining the machine hour rate under activity-based costing must be less than the numerator under the single machine hour rate method. c. Column C indicates that under activity-based costing the low-volume product has a higher per-unit cost than calculated under the single rate method. In contrast, under activity-based costing the high-volume product has a lower per-unit cost than calculated under the single rate method. This result will occur when there are activities that occur in proportions different from their volumes. In this case, lower-volume products have setups and sales orders occurring in higher proportions of total setups and sales orders than their proportion of machine hours to total machine hours. The opposite is the case for the high-volume product. Thus, the lower-volume products are produced and ordered in smaller batch sizes compared to the higher-volume product. This implies that Whirlpool may wish to simplify its product line by eliminating some of the low-volume products or by attempting to reduce the overall cost of setup and sales order processing activities. Note: The sum of the total overhead from Columns A and B is not equal because there are only three representative products, not all of the products

23 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) The selling and administrative expenses should not be allocated on the basis of relative sales dollars. The two product lines have very different attributes. The commercial product is relatively inexpensive to sell, while the home product has a number of additional costs associated with it. As a result, the relative sales dollar method of allocation will distribute too much selling and administrative cost to the commercial product and too little to the home product. The commercial product receives twice as much selling and administrative expense as the home product because it has twice the sales. An activity-based approach would trace the selling and administrative costs to the products based upon their actual consumption of activities. Such an allocation would show the commercial product to be more profitable than indicated and the home product to be less profitable than indicated. Ex (FIN MAN); Ex (MAN) a. Sales order processing activities: Number of Sales Orders Rate = Cost Generators 980 $80 $ 78,400 Air compressors 1, ,800 Total $171,200 Post-sale customer service activities: Number of Service Requests Rate = Cost Generators 150 $300 $ 45,000 Air compressors ,800 Total $181,800 Note to Instructor: $171,200 + $181,800 = $353,000, which is the total selling and administrative expense reported in the exercise

24 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) (Concluded) b. VOLT-GEAR INC. Product Profitability Report For the Year Ended December 31 Air Generators Compressors Total Revenues $2,000,000 $1,400,000 $3,400,000 Cost of goods sold 1,400, ,000 2,380,000 Gross profit $ 600,000 $ 420,000 $1,020,000 Sales order processing $ 78,400 1 $ 92,800 3 $ 171,200 Post-sale customer service 2 45, , ,800 Total selling and administrative expense $ 123,400 $ 229,600 $ 353,000 Income from operations $ 476,600 $ 190,400 $ 667,000 Gross profit as a percentage of sales 30.00% % 7 Income from operations as a percentage of sales 23.83% % 8 1 $78,400 = 980 sales orders $80/sales order 2 $45,000 = 150 service requests $300/service request 3 $92,800 = 1,160 sales orders $80/sales order 4 $136,800 = 456 service requests $300/service request 5 $600,000 $2,000,000 6 $476,600 $2,000,000 7 $420,000 $1,400,000 8 $190,400 $1,400,000 c. The complete product profitability report provides much greater insight than did the original report. The air compressors have the lower income from operations to sales percentage because the product is a heavy user of Volt-Gear s sales and service activities. The air compressors are ordered in small quantities (hence a high number of sales orders) and have a high amount of post-sale service. All of these factors cause the air compressors to have less income from operations as a percent of sales than generators. In contrast, relative to the sales volume, the generators have much less activity and thus have the higher income from operations as a percent of sales. Volt-Gear can respond to this situation by rationing the amount of service to the air compressor product line, charging air compressor customers for some of the services, reducing the number of service requests by improving the product, or raising the price on the air compressors

25 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. SCHNEIDER ELECTRIC Customer Profitability Report For the Year Ended December 31, 2016 (assumed data) Customer 1 Customer 2 Customer 3 Revenue $39,000 $26,000 $31,200 Cost of goods sold 24,180 13,520 15,600 Gross profit $14,820 $12,480 $15,600 Customer service activities: Bid preparation $ 2, $ 1,600 9 $ 5,000 Shipment Support standard items ,120 Support nonstandard items 4 1, , ,050 Total customer service activities $ 4,966 $ 4,994 $10,890 Income from operations after customer service activities $ 9,854 $ 7,486 $ 4,710 Gross profit as a percent of sales 38% 48% 50% Income from operations after customer service activities as a percent of sales 25% 29% 15% 1 $ bid requests 2 $16 16 shipments 3 $20 48 standard items 4 $75 18 nonstandard items 5 $200 8 bid requests 6 $16 24 shipments 7 $20 38 standard items 8 $75 30 nonstandard items 9 $ bid requests 10 $16 45 shipments 11 $20 56 standard items 12 $75 54 nonstandard items b. The gross profit as a percent of sales indicated that Customer 1 was the least profitable, while Customer 3 was the most profitable. After deducting the activity costs associated with customer service activities, Customer 3 became the least profitable, while Customer 1 became nearly as profitable as Customer 2. The reason is because Customer 3 consumed much more customer service activities than did either Customer 1 or Customer 2. Apparently, Customer 3 ordered nonstandard products that required specialized bid requests. In addition, Customer 3 required more shipments, indicating smaller shipments to a customer s location, rather than a few large shipments

26 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. Patient Putin Patient Umit Usage Rate = Cost Usage Rate = Cost Room and meals 6 days $240 /day $ 1,440 4 days $240 /day $ 960 Radiology 4 images $215 /image images $215 /image 645 Pharmacy 6 orders $50 /order orders $50 /order 100 Chemistry lab 5 tests $80 /test tests $80 /test 320 Operating room 8 hrs. $1,000 /hr. 8,000 4 hrs. $1,000 /hr. 4,000 Total cost $11,000 $6,025 b. Patient Putin apparently had a different condition that required more extensive treatment than did Patient Umit. Patient Putin required more operating room hours, more tests and images, and more days to recover than did Patient Umit. Thus, the activity cost to Patient Putin is more than two times that of Patient Umit

27 Cost Allocation and -Based Costing Ex (FIN MAN); Ex (MAN) a. SAFETY FIRST INSURANCE COMPANY Product Profitability Report For the Year Ended December 31 Workers Auto Comp. Homeowners Premium revenue $5,750,000 $6,240,000 $8,160,000 Less estimated claims 4,312,500 4,680,000 6,120,000 Underwriting income $1,437,500 $1,560,000 $2,040,000 Administrative activities:* New policy processing $ 158,400 $ 180,000 $ 489,600 Cancellation processing 84,000 42, ,000 Claim audits 123,200 38, ,200 Claim disbursements processing 49,920 22,464 87,360 Premium collection processing 201,600 43, ,000 Total administrative expenses $ 617,120 $ 326,064 $1,622,160 Income from operations $ 820,380 $1,233,936 $ 417,840 Income from operations as a percent of premium revenue 14% 20% 5% * The activity costs are determined by multiplying the activity rate by the activity-based usage quantity. For example, the administrative activity costs for the Auto line is as follows: $158,400 = $1,320 new policies $120 per new policy $84,000 = $480 cancellations $175 per cancellation $123,200 = $385 audits $320 per claim audit $49,920 = $480 disbursements $104 per disbursement $201,600 = $8,400 premiums collected $24 per collection b. All three insurance lines have the same percentage of underwriting income to premium revenue (25%). The differences among the insurance lines are in the way they consume administrative activities. For example, the Homeowners insurance line has the least profitability due to its high use of administrative activities. Specifically, the Homeowners line has smaller and more frequent claims that require more auditing and disbursement processing than do the other two lines. In addition, the Homeowners line has a much higher rate of cancellation relative to the other two lines (over 50% of new policies). Lastly, the Homeowners line has more premium collections compared to the other two lines. Possibly, the Homeowners line is collected in smaller amounts from more customers than the other two lines. In contrast, the Workers Compensation line consumes the fewest administrative activities, causing it to be very profitable. The Auto line is in between these two

28 Cost Allocation and -Based Costing PROBLEMS Prob. 26 1A (FIN MAN); Prob. 11 1A (MAN) 1. a. Direct labor overhead rate: $220,800 1,725 direct labor hours b. Machine hour overhead rate: $220,800 4,600 machine hours = = $128 per direct labor hour $48 per machine hour 2. Automobile Bumpers Valve Covers Wheels a. Direct labor hours: Stamping Department 560 dlh 300 dlh 340 dlh Plating Department Total direct labor hours 730 dlh 480 dlh 515 dlh Direct labor overhead rate $128 /dlh $128 /dlh $128 /dlh Allocated factory overhead $93,440 $61,440 $65,920 b. Machine hours: Stamping Department 800 mh 560 mh 600 mh Plating Department 1, Total machine hours 1,970 mh 1,270 mh 1,360 mh Machine hour overhead rate $48 /mh $48 /mh $48 /mh Allocated factory overhead $94,560 $60,960 $65,280 Instructor s Note: The allocated factory overhead is the same for both allocation bases because their usage is proportional across product

29 Cost Allocation and -Based Costing Prob. 26 2A (FIN MAN); Prob. 11 2A (MAN) 1. Stamping Plating Dept. Dept. Production department factory overhead totals $115,200 $105,600 rate 1,200 dlh 2,640 mh Production department rate $ 96 /dlh $ 40 /mh 2. Automobile bumpers Stamping Department 560 dir. labor hrs. $96/dlh = $ 53,760 Plating Department 1,170 dir. mach. hrs. $40/dmh = 46,800 Total factory overhead for bumpers $100,560 Valve covers Stamping Department 300 dir. labor hrs. $96/dlh = $ 28,800 Plating Department 710 dir. mach. hrs. $40/dmh = 28,400 Total factory overhead for valve covers $ 57,200 Wheels Stamping Department 340 dir. labor hrs. $96/dlh = $ 32,640 Plating Department 760 dir. mach. hrs. $40/dmh = 30,400 Total factory overhead for wheels $ 63,

30 Cost Allocation and -Based Costing Prob. 26 3A (FIN MAN); Prob. 11 3A (MAN) 1. Production department rates: Cutting Department Finishing Department Factory overhead Direct labor hours $315,000 6,000 $540,000 6,000 Production department rate $ 52.5 /dlh $ 90.0 /dlh 2. Production Direct Department Labor Hours Rate = Snowboards: Cutting Department 4,000 $52.5 /dlh = Finishing Department 2,000 $90.0 /dlh = Total factory overhead Number of units Factory overhead per unit Skis: Cutting Department 2,000 $52.5 /dlh = Finishing Department 4,000 $90.0 /dlh = Total factory overhead Number of units Factory overhead per unit Factory Overhead $210, ,000 $390,000 6,000 $ $105, ,000 $465,000 6,000 $ based rates: Production Materials Cutting Finishing Control Handling Department Department Factory overhead $237,000 $270,000 $156,000 $192,000 base 500 prod. runs 7,500 moves 6,000 dlh 6,000 dlh rate $ /prod. run $ 36.0 /move $ 26.0 /dlh $ 32.0 /dlh 26-30

31 Cost Allocation and -Based Costing Prob. 26 3A (FIN MAN); Prob. 11 3A (MAN) (Concluded) 4. Snowboards Skis Usage Rate = Cost Usage Rate = Cost Production control 430 prod. runs $474 /prod. run $203, prod. runs $474 /prod. run $ 33,180 Materials handling 5,000 moves $36 /move 180,000 2,500 moves $36 /move 90,000 Cutting Department 4,000 dlh $26 /dlh 104,000 2,000 dlh $26 /dlh 52,000 Finishing Department 2,000 dlh $32 /dlh 64,000 4,000 dlh $32 /dlh 128,000 Total Number of units $551,820 6,000 $303,180 6,000 cost per unit $ $ The activity-based overhead allocation reveals that snowboards consume more factory overhead on a per-unit basis than do skis. The multiple production department factory overhead rate method does not show this because all factory overhead is assumed to be proportional to direct labor hours. The activity-based method separately accounts for the production control and materials handling activity costs. Snowboards have more production control and materials handling activities than do skis. This is because snowboards are made in smaller lots, representing a wide variety of styles. Thus, snowboards have higher activity costs per unit than skis

32 Cost Allocation and -Based Costing Prob. 26 4A (FIN MAN); Prob. 11 4A (MAN) Materials 1. Production Setup Handling Inspection Engineering Total activity cost $264,000 $96,000 $9,600 $50,000 $150,000 Total activity base 2,200 mh 400 setups 480 no. parts 1,000 insp. hours 500 eng. hours rate $ 120 /mh $ 240 /setup $ 20 /part $ 50 /hour $ 300 /hour 2. I8 - Base Production Usage 400 mh Rate $120 /mh = Cost $ 48,000 Setup 220 setups $240 /setups 52,800 Material handling 250 parts $20 /part 5,000 Inspection 250 insp. hours $50 /hour 12,500 Engineering 200 eng. hours $300 /hour 60,000 Total activity cost Number of units cost per unit $178, $ Base Usage M5 Rate = Cost Production 1,000 mh $120 /mh $120, mh $120 /mh $ 96,000 Setup 60 setups $240 /setup 14, setups $240 /setups 28,800 Material handling 80 parts $20 /part 1, no parts $20 /part 3,000 Inspection 450 insp. hours $50 /hour 22, insp. hours $50 /hour 15,000 Engineering 125 eng. hours $300 /hour 37, eng. hours $300 /hour 52,500 Total activity cost Number of units cost per unit $196,000 1,250 $ $195,300 1,000 $ Z4 Rate = Cost - Base Usage 26-32

33 Cost Allocation and -Based Costing Prob. 26 4A (FIN MAN); Prob. 11 4A (MAN) (Concluded) 3. The unit costs are different even though each product requires 0.8 machine hour because the products consume many activities in ratios different from the volume. For example, the I8 consumes setup, moving, shipping, and product engineering activities proportionately greater than its volume, while the M5 consumes the same activities proportionately less than its volume

34 Cost Allocation and -Based Costing Prob. 26 5A (FIN MAN); Prob. 11 5A (MAN) 1. Customer Project Engineering Service Bidding Support cost $83,720 $61,360 $86,800 base 322 sr* 104 bids 217 dc* rate $ 260 /sr $ 590 /bid $ 400 /dc 2. Good Knowledge University Customer service 60 sr $260/sr = $15,600 Project bidding 36 bids $590/bid = 21,240 Engineering support 45 dc $400/dc = 18,000 Total nonmanufacturing activity costs $54,840 Hot Shotz Arena Customer service 52 sr $260/sr = $13,520 Project bidding 18 bids $590/bid = 10,620 Engineering support 30 dc $400/dc = 12,000 Total nonmanufacturing activity costs $36,140 Break-a-Leg Hospital Customer service 210 sr $260/sr = $ 54,600 Project bidding 50 bids $590/bid = 29,500 Engineering support 142 dc $400/dc = 56,800 Total nonmanufacturing activity costs $140,900 * sr stands for service request; dc stands for design change

35 Cost Allocation and -Based Costing Prob. 26 5A (FIN MAN); Prob. 11 5A (MAN) (Concluded) 3. COLD ZONE MECHANICAL INC. Customer Profitability Report For the Year Ended December 31 Good Knowledge Hot Shotz Break-a-Leg University Arena Hospital Revenues $1,650,000 $1,050,000 $450,000 Less cost of goods sold 1,320, , ,0006 Gross profit $ 330,000 $ 210,000 $90,000 Less selling and administrative activities: Customer service $ 15,600 $ 13,520 $ 54,600 Project bidding 21,240 10,620 29,500 Engineering support 18,000 12,000 56,800 $ 54,840 $ 36,140 $140,900 Income from operations $ 275,160 $ 173,860 $ (50,900) 1 $75, units 4 $60, units 2 $75, units 5 $60, units 3 $75,000 6 units 6 $60,000 6 units 4. Break-a-Leg Hospital is unprofitable, while the other two customers have acceptable margins. This is because Break-a-Leg Hospital requires many customer service, project bidding, and design change activities. For example, Break-a-Leg Hospital awards contracts on only 12% of the bid efforts (6 contracts 50 bids); it requests a large amount of service; and it requires extensive design change effort. The company's options include: a. Stop bidding Break-a-Leg Hospital projects. This does not necessarily mean that all the costs can be avoided. The costs only will be eliminated if the reduced activity translates into lower headcount (dismissals). Thus, the company should evaluate the contribution margin of this customer relationship before making this decision. b. Reprice Break-a-Leg Hospital work. Charge Break-a-Leg Hospital a higher price to compensate for the higher activities required to serve it. However, the customer may not accept the price increase required to move it to a profitable relationship. c. Encourage Break-a-Leg Hospital to reduce the amount of design changes and customer service requests. The design changes are probably driving the customer service requests. This may be appealing, but there may be no incentive for Breaka-Leg Hospital to change its behavior. d. Charge a price for customer service and design change separately. That is, unbundle the pricing of goods from the support services. This is a good longterm solution. In addition, improve the bidding process in order to improve the hit rate or the percentage of awarded contracts to bids

36 Cost Allocation and -Based Costing Prob. 26 6A (FIN MAN); Prob. 11 6A (MAN) 1. Cost Base = Rate Scheduling and admitting $ 432,000 6,000 patients = $72 /patient Housekeeping 4,212,000 27,000 pds* = $156 /pd Nursing 5,376, ,000 wcus* = $28 /wcu Total $10,020,000 * "pd" stands for patient day; "wcu" stands for weighted care unit 2. Usage Rate = Total Cost by Procedure Procedure A Scheduling and admitting 280 patients $72 /patient Housekeeping 1,680 pds $156 /pd Nursing 19,200 wcus $28 /wcu $ 20, , ,600 $819,840 Procedure B Scheduling and admitting 650 patients $72 /patient Housekeeping 3,250 pds $156 /pd Nursing 6,000 wcus $28 /wcu $ 46, , ,000 $721,800 Procedure C Scheduling and admitting 1,200 patients Housekeeping 4,800 pds Nursing 24,000 wcus $72 /patient $ 86,400 $156 /pd 748,800 $28 /wcu 672,000 $1,507,

37 Cost Allocation and -Based Costing Prob. 26 6A (FIN MAN); Prob. 11 6A (MAN) (Concluded) 3. Procedure A Procedure B Procedure C Reimbursement (patient days reimbursement rate)* $ 682,080 $1,319,500 $1,948,800 Total activity cost (from 2.) 819, ,800 1,507,200 Excess (deficiency) of reimbursement over activity cost $(137,760) $ 597,700 $ 441,600 * 1,680 patient days $406/patient day = $682,080 3,250 patient days $406/patient day = $1,319,500 4,800 patient days $406/patient day = $1,948, Procedure A requires more activity cost than is being reimbursed by the insurance company. As a result, the hospital may wish to determine if the costs of providing Procedure A are too high. Hospital management may wish to investigate the nursing effort, because the weighted average care units are averaging nearly 11.4 (19,200 1,680) wcus per patient day for Procedure A, which compares to 1.8 (6,000 3,250) and 5 (24,000 4,800) wcus per patient day for Procedures B and C, respectively. Alternatively, the hospital may wish to negotiate for a higher reimbursement from the insurance company for Procedure A. Note to Instructors: The total activity costs and activity-base quantities for the three procedures are less than the totals because these are only three selected procedures out of a larger population

38 Cost Allocation and -Based Costing Prob. 26 1B (FIN MAN); Prob. 11 1B (MAN) 1. a. Direct labor overhead rate: $299,700 1,620 direct labor hours b. Machine hour overhead rate: $299,700 2,700 machine hours = = $185 per direct labor hour $111 per machine hour 2. Whole Milk Skim Milk Cream a. Direct labor hours: Blending Department 260 dlh 245 dlh 215 dlh Packing Department Total direct labor hours 730 dlh 545 dlh 345 dlh Direct labor overhead rate $185 /dlh $185 /dlh $185 /dlh Allocated factory overhead $135,050 $100,825 $63,825 b. Machine hours: Blending Department 650 mh 710 mh 260 mh Packing Department Total machine hours 1,150 mh 1,125 mh 425 mh Machine hour overhead rate $111 /mh $111 /mh $111 /mh Allocated factory overhead $127,650 $124,875 $47,

39 Cost Allocation and -Based Costing Prob. 26 2B (FIN MAN); Prob. 11 2B (MAN) 1. Blending Packing Dept. Dept. Production department factory overhead totals $178,200 $121,500 base 1,620 mh 900 dlh Production department rate $ 110 /mh $ 135 /dlh 2. Whole milk Blending Department 650 dir. mach. hrs. $110/dmh = $ 71,500 Packing Department 470 dir. labor hrs. $135/dlh = 63,450 Total factory overhead for whole milk $134,950 Skim milk Blending Department 710 dir. mach. hrs. $110/dmh = $ 78,100 Packing Department 300 dir. labor hrs. $135/dlh = 40,500 Total factory overhead for skim milk $118,600 Cream Blending Department 260 dir. mach. hrs. $110/dmh = $ 28,600 Packing Department 130 dir. labor hrs. $135/dlh = 17,550 Total factory overhead for cream $ 46,

40 Cost Allocation and -Based Costing Prob. 26 3B (FIN MAN); Prob. 11 3B (MAN) 1. Production department rates: Subassembly Department Final Assembly Department Factory overhead Direct labor hours $420,000 1,400 $294,000 1,400 Production department rate $ 300 /dlh $ 210 /dlh 2. Production Direct Department Labor Hours Rate = Receivers: Subassembly Department 875 $300 /dlh = Final Assembly Department 525 $210 /dlh = Total factory overhead Number of units Factory overhead per unit Loudspeakers: Subassembly Department 525 $300 /dlh = Final Assembly Department 875 $210 /dlh = Total factory overhead Number of units Factory overhead per unit Factory Overhead $262, ,250 $372,750 7,000 $ $157, ,750 $341,250 7,000 $ based rates: Quality Subassembly Final Assembly Setup Control Department Department Factory overhead $138,600 $261,800 $198,800 $114,800 base 400 setups 2,200 insp. 1,400 dlh 1,400 dlh rate $ /setup $ 119 /insp. $ 142 /dlh $ 82 /dlh 26-40

41 Cost Allocation and -Based Costing Prob. 26 3B (FIN MAN); Prob. 11 3B (MAN) (Concluded) 4. Receivers Loudspeakers Usage Rate = Cost Usage Rate = Cost Setup 80 setups $ /setup $ 27, setups $ /setup $110,880 Quality control 450 insp. $119 /insp. 53,550 1,750 insp. $119 /insp. 208,250 Subassembly Dept. 875 dlh $142 /dlh 124, dlh $142 /dlh 74,550 Final Assembly Dept. 525 dlh $82 /dlh 43, dlh $82 /dlh 71,750 Total Number of units $248,570 7,000 $465,430 7,000 cost per unit $ $ The activity-based overhead allocation reveals that loudspeakers are more costly on a per-unit basis than are the receivers. The multiple production department rate method determines that the per-unit factory overhead is nearly the same for the two products. The multiple production department factory overhead rate method distorts the unit costs because all factory overhead is assumed to be proportional to direct labor hours. Since each product consumes the same total direct labor hours, the factory overhead allocation is nearly equal. The activity-based method separately accounts for the setup and quality-control activity costs. Loudspeakers have more setups and inspection activities than do receivers. Thus, loudspeakers have higher activity costs per unit than do receivers

42 Cost Allocation and -Based Costing Prob. 26 4B (FIN MAN); Prob. 11 4B (MAN) 1. Production Setup Inspection Shipping Customer Service Total activity cost $500,000 $144,000 $44,000 $115,000 $84,000 Total activity base 10,000 mh 450 setups 1,100 insp. 5,750 cust. ord. 600 req. rate $ 50 /mh $ 320 /setup $ 40 /insp. $ 20 /cust. ord. $ 140 /req. 2. White Sugar Base Usage Rate = Cost - Base Production Usage 2,500 mh Rate $50 /mh = Cost $125,000 Setup 195 setups $320 /setup 62,400 Inspection 550 insp. $40 /insp. 22,000 Shipping 2,000 cust. ord. $20 /cust. ord. 40,000 Customer service 190 requests $140 /request 26,600 Total activity cost $276,000 Units cost per unit $ 5, Brown Sugar Base Usage Rate = Cost Production 5,000 mh $50 /mh $250,000 2,500 mh $50 /mh $125,000 Setup 85 setups $320 /setup 27, setups $320 /setup 54,400 Inspection 220 insp. $40 /insp. 8, insp. $40 /insp. 13,200 Shipping 1,150 cust. ord. $20 /cust. ord. 23,000 2,600 cust. ord. $20 /cust. ord. 52,000 Customer service 60 requests $140 /request 8, requests $140 /request 49,000 Total activity cost $317,400 $293,600 Units cost per unit $ 10, $ 5, Powdered Sugar 26-42

Acct 1B Week 8, Chap 7

Acct 1B Week 8, Chap 7 Acct 1B Week 8, Chap 7 Activity Based Costing (ABC) Instructor: Michael Booth Cabrillo College Activity Based Costing: A Tool to Aid Decision Making Global Business Situation Using technology and productivity

More information

Willow Company produces lawn mowers. One of its plants produces two versions of mowers: a basic model and a deluxe model. The deluxe model has a

Willow Company produces lawn mowers. One of its plants produces two versions of mowers: a basic model and a deluxe model. The deluxe model has a Illustration Problem 2: Production-Based Costing vs. Activity Based Costing Willow Company produces lawn mowers. One of its plants produces two versions of mowers: a basic model and a deluxe model. The

More information

Chapter 3 Activity-Based Costing

Chapter 3 Activity-Based Costing Chapter 3 -Based Costing Solutions to Questions 3-1 The most common methods of assigning overhead costs to products are plantwide overhead rates, departmental overhead rates, and activity-based costing.

More information

MBP1133 Managerial Accounting Prepared by Dr Khairul Anuar

MBP1133 Managerial Accounting Prepared by Dr Khairul Anuar 1 MBP1133 Managerial Accounting Prepared by Dr Khairul Anuar L8 Activity-Based Costing: A Tool to Aid Decision Making www.notes638.wordpress.com 2 Activity Based Costing (ABC) ABC is designed to provide

More information

Overcosting and Undercosting (Example 1 at the end of these notes)

Overcosting and Undercosting (Example 1 at the end of these notes) Chapter 5 Activity-Based Costing Overcosting and Undercosting (Example 1 at the end of these notes) Distortions from inaccurate costing Activities/Resources/Cost Drivers Steps in ABC Identify resources

More information

Chapter 3 Systems Design: Job-Order Costing

Chapter 3 Systems Design: Job-Order Costing Chapter 3 Systems Design: Job-Order Costing Solutions to Questions 3-1 By definition, manufacturing overhead consists of costs that cannot be practically traced to products or jobs. Therefore, if these

More information

CHAPTER 7 Accounting 1B. Activity-Based Costing(ABC): A tool to Aid Decision Making

CHAPTER 7 Accounting 1B. Activity-Based Costing(ABC): A tool to Aid Decision Making CHAPTER 7 Accounting 1B Activity-Based Costing(ABC): A tool to Aid Decision Making Global Business Situation Using technology and productivity More emphasis on cost measurement and control Increasingly

More information

1. Amounts (in thousands) Molding Component Assembly Total

1. Amounts (in thousands) Molding Component Assembly Total 5-32 (30 min.) Plantwide versus department overhead cost rates. 1. Amounts (in thousands) Molding Component Assembly Total Manufacturing department overhead $21,000 $16,200 $22,600 $59,800 Service departments:

More information

Activity Based Costing

Activity Based Costing Activity Based Costing 1 Existing Single Indirect- Cost Pool System Cole Corporation manufactures two types of cell phones a standard type (S) and one complex type with additional functions (C). To cost

More information

Activity-Based Costing Systems

Activity-Based Costing Systems 4 Activity-Based Costing Systems 4-2 Learning Objective 1 4-3 Traditional Costing Systems Traditional cost systems were created when manufacturing processes were labor intensive. A single company-wide

More information

Activity Based Costing: A Decision Making Tool. with Dr. Joseph Ugras December 2017

Activity Based Costing: A Decision Making Tool. with Dr. Joseph Ugras December 2017 Activity Based Costing: A Decision Making Tool with Dr. Joseph Ugras December 2017 1 7-2 Learning Objectives Know the Need for Cost and Profitability Understand how traditional and activity-based costing

More information

An Introduction to Cost Terms and Purposes

An Introduction to Cost Terms and Purposes CHAPTER 2 An Introduction to Cost Terms and Purposes Overview This chapter introduces the basic terminology of cost accounting. Communication among managers and management accountants is greatly facilitated

More information

5-54 Volume-based Costing Versus ABC

5-54 Volume-based Costing Versus ABC 5-54 Volume-based Costing Versus ABC 1. Product A Product B Product C Materials $50.00 $114.40 $65.00 Labor 20.00 12.00 10.00 Overhead* 116.00 69.60 58.00 Total Cost $186.00 $ 196.00 $133.00 *overhead

More information

Activity-Based Costing and Analysis

Activity-Based Costing and Analysis A Look Back Chapters 2 and 3 described costing systems used by companies to accumulate product costing information for the reporting of inventories and cost of goods sold. 4Chapter Learning Objectives

More information

Cost Systems. Terms Cost Accounting Process Cost System Job Order Cost System

Cost Systems. Terms Cost Accounting Process Cost System Job Order Cost System Terms Cost Accounting Process Cost System Job Order Cost System Cost Systems Job-Order Costing Used for custom or unique items Each job is accounted for separately Measures cost based on completed job

More information

Cost Accounting: A Managerial Emphasis, 16e, Global Edition (Horngren) Chapter 5 Activity-Based Costing and Activity-Based Management

Cost Accounting: A Managerial Emphasis, 16e, Global Edition (Horngren) Chapter 5 Activity-Based Costing and Activity-Based Management Cost Accounting: A Managerial Emphasis, 16e, Global Edition (Horngren) Chapter 5 Activity-Based Costing and Activity-Based Management 5.1 Objective 5.1 1) Which of the following statements is true of a

More information

Chapter 02 - Cost Concepts and Cost Allocation

Chapter 02 - Cost Concepts and Cost Allocation Chapter 02 - Cost Concepts and Cost Allocation Student: 1. Product costs for a manufacturing company consist of direct materials, direct labor, and overhead. 2. Period cost and product cost are synonymous

More information

Financial Transfer Guide DBA Software Inc.

Financial Transfer Guide DBA Software Inc. Contents 3 Table of Contents 1 Introduction 4 2 Why You Need the Financial Transfer 6 3 Total Control Workflow 10 4 Financial Transfer Overview 12 5 Multiple Operating Entities Setup 15 6 General Ledger

More information

1. F; I 2. V ; D 3. V ; D 4. F; I 5. F; I 6. F; I 7. V ; D 8. F; I 9. F; I 10. V ; D 11. F; I 12. F; I 13. F; I 14. F; I

1. F; I 2. V ; D 3. V ; D 4. F; I 5. F; I 6. F; I 7. V ; D 8. F; I 9. F; I 10. V ; D 11. F; I 12. F; I 13. F; I 14. F; I SOLUTIONS TO EERCISES EERCISE 2-1 (15 minutes) 1. F; I 2. V ; D 3. V ; D 4. F; I 5. F; I 6. F; I 7. V ; D 8. F; I 9. F; I 10. V ; D 11. F; I 12. F; I 13. F; I 14. F; I EERCISE 2-2 (15 minutes) 1. Product

More information

Cost Accounting, 15e (Horngren/Datar/Rajan) Chapter 2 An Introduction to Cost Terms and Purposes. Objective 2.1

Cost Accounting, 15e (Horngren/Datar/Rajan) Chapter 2 An Introduction to Cost Terms and Purposes. Objective 2.1 Cost Accounting, 15e (Horngren/Datar/Rajan) Chapter 2 An Introduction to Cost Terms and Purposes Objective 2.1 1) An actual cost is. A) is the cost incurred B) is a predicted or forecasted cost C) is anything

More information

rate is used to apply overhead costs to products. Our purpose in this section is to provide a detailed example of cost flows in an ABC system.

rate is used to apply overhead costs to products. Our purpose in this section is to provide a detailed example of cost flows in an ABC system. Appendix 6A Cost Flows in an -Based Costing System 6A-1 Cost Flows in an -Based Costing System In Chapter 4, we discussed the flow of costs in a job-order costing system. The flow of costs through raw

More information

FINANCIAL STATEMENTS

FINANCIAL STATEMENTS FINANCIAL STATEMENTS Key Topics to Know Cost of good sold statement is prepared from the finished goods inventory account. Cost of goods sold statement has the same format as in financial accounting. Cost

More information

Cost Accounting: A Managerial Emphasis, 16e, Global Edition (Horngren) Chapter 2 An Introduction to Cost Terms and Purposes

Cost Accounting: A Managerial Emphasis, 16e, Global Edition (Horngren) Chapter 2 An Introduction to Cost Terms and Purposes Cost Accounting: A Managerial Emphasis, 16e, Global Edition (Horngren) Chapter 2 An Introduction to Cost Terms and Purposes 2.1 Objective 2.1 1) Which of the following would be considered an actual cost

More information

Chapter 2. Job Order Costing and Analysis QUESTIONS

Chapter 2. Job Order Costing and Analysis QUESTIONS Chapter 2 Job Order Costing and Analysis QUESTIONS 1. Factory overhead is not identified with specific units (jobs) or batches (job lots). Therefore, to assign costs, estimates of the relation between

More information

Activity-Based Costing. Managerial Accounting, Fourth Edition

Activity-Based Costing. Managerial Accounting, Fourth Edition Study Objectives Study CHAPTER Objectives 4 Activity-Based Costing Managerial Accounting, Fourth Edition Study Objectives 1. Recognize the difference between traditional costing and activity based costing.

More information

Chapter 17 Job Order Costing Study Guide Solutions Fill-in-the-Blank Equations. Exercises. 1. Estimated activity base. 2. Underapplied. 3.

Chapter 17 Job Order Costing Study Guide Solutions Fill-in-the-Blank Equations. Exercises. 1. Estimated activity base. 2. Underapplied. 3. Chapter 17 Job Order Costing Study Guide Solutions Fill-in-the-Blank Equations 1. Estimated activity base 2. Underapplied 3. Overapplied Exercises 1. An automobile manufacturer produces various lines of

More information

Activity-Based Costing: A Tool to Aid Decision Making

Activity-Based Costing: A Tool to Aid Decision Making Activity-Based Costing: A Tool to Aid Decision Making Chapter 8 McGraw-Hil/Irwin Activity Based Costing (ABC) ABC is designed to provide managers with cost information for strategic and other decisions

More information

Match the activity pool with an appropriate activity measure. Your answers: Customer orders. Product design c-:i ~ Number of product designs

Match the activity pool with an appropriate activity measure. Your answers: Customer orders. Product design c-:i ~ Number of product designs Match the activity pool with an appropriate activity measure. ~ Your answer is correct Your answers: Customer orders IHI ~ Number of customer orders Product design c-:i ~ Number of product designs l J

More information

CHAPTER 2 AN INTRODUCTION TO COST TERMS AND PURPOSES

CHAPTER 2 AN INTRODUCTION TO COST TERMS AND PURPOSES CHAPTER 2 AN INTRODUCTION TO COST TERMS AND PURPOSES 2-1 A cost object is anything for which a separate measurement of costs is desired. Examples include a product, a service, a project, a customer, a

More information

Chapter 4. Systems Design: Process Costing. Types of Costing Systems Used to Determine Product Costs. Job-order Costing.

Chapter 4. Systems Design: Process Costing. Types of Costing Systems Used to Determine Product Costs. Job-order Costing. 4-1 Chapter 4 Systems Design: Process Costing Types of Costing Systems Used to Determine Product Costs Process Costing Job-order Costing F Many units of a single, homogeneous product flow evenly through

More information

Mona Loa Malaysian Manufacturing cost per bag... $6.00 $5.00 Add markup at 30% Selling price per bag... $7.80 $6.50

Mona Loa Malaysian Manufacturing cost per bag... $6.00 $5.00 Add markup at 30% Selling price per bag... $7.80 $6.50 Case 8-24 1. a. The predetermined overhead rate would be computed as follows: Expected manufacturing overhead cost $3,000,000 = Estimated direct labour-hours 50,000 DLHs =$60 per DLH b. The unit product

More information

An Introduction to Cost Terms and Purposes. Dr. Osama Al Meanazel

An Introduction to Cost Terms and Purposes. Dr. Osama Al Meanazel An Introduction to Cost Terms and Purposes Dr. Osama Al Meanazel Lecture 5 Other Cost Concepts Cost driver a variable that causally affects costs over a given time span Relevant range the band of normal

More information

2. Which of the following is true regarding the contribution margin ratio of a single-product company?

2. Which of the following is true regarding the contribution margin ratio of a single-product company? Student ID: 22099108 Exam: 061682RR - Costs and Decision Making When you have completed your exam and reviewed your answers, click Submit Exam. Answers will not be recorded until you hit Submit Exam. If

More information

DEFINITIONS AND CONCEPTS

DEFINITIONS AND CONCEPTS DEFINITIONS AND CONCEPTS ** CONCEPTS AND DEFINITIONS IN THIS MODULE APPEAR IN VARIOUS CHAPTERS ** Key Terms and Concepts to Know Major Management Activities Planning - formulating long and short-term plans

More information

Managerial Accounting: Making Decisions and Motivating Performance (Datar/Rajan) Chapter 2 An Introduction to Cost Terms and Purposes

Managerial Accounting: Making Decisions and Motivating Performance (Datar/Rajan) Chapter 2 An Introduction to Cost Terms and Purposes Managerial Accounting: Making Decisions and Motivating Performance (Datar/Rajan) Chapter 2 An Introduction to Cost Terms and Purposes Learning Objective 2-1 1) The cost incurred is: A) actual costs. B)

More information

Management Accounting and Control Spring 2007

Management Accounting and Control Spring 2007 MIT OpenCourseWare http://ocw.mit.edu 15.963 Management Accounting and Control Spring 2007 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. 15.963 Managerial

More information

Overheads/Job and Batch Costing. RST Ltd. has two production departments Machining and Finishing. There are three service

Overheads/Job and Batch Costing. RST Ltd. has two production departments Machining and Finishing. There are three service CA R. K. Mehta Overheads/Job and Batch Costing CA Past Years Exam Question Question : 1 Nov, 2006 RST Ltd. has two production departments Machining and Finishing. There are three service departments Human

More information

6. Refer to the Michael's Manufacturing, Inc. information above. Raw materials used for July is:

6. Refer to the Michael's Manufacturing, Inc. information above. Raw materials used for July is: Review II NUMBER 1. Which of the following is a characteristic of managerial accounting? a. It is used primarily by external users. b. It often lacks flexibility. c. It is often future-oriented. d. The

More information

PROCESS COSTING FIRST-IN FIRST-OUT METHOD

PROCESS COSTING FIRST-IN FIRST-OUT METHOD PROCESS COSTING FIRST-IN FIRST-OUT METHOD Key Terms and Concepts to Know Differences between Job-Order Costing and Processing Costing Process costing is used when a single product is made on a continuous

More information

CHAPTER 17 (FIN MAN); CHAPTER 2 (MAN) JOB ORDER COST SYSTEMS

CHAPTER 17 (FIN MAN); CHAPTER 2 (MAN) JOB ORDER COST SYSTEMS CHAPTER 17 (FIN MAN); CHAPTER 2 (MAN) JOB ORDER COST SYSTEMS Number Objective Description Difficulty Time AACSB IMA SS GL EO17(2)-1 17-1 Easy 5 min Analytic Cost Management EO17(2)-2 17-1 Easy 5 min Analytic

More information

70% of total manufacturing costs for the period

70% of total manufacturing costs for the period Midterm Review Class #1.1- COGM; Income Statement, Cost Behaviour On January 30, 2013, the manufacturing facility of Trucks R Us was severely damaged by a fire. As a result, the company s direct materials,

More information

ACCTG 221 / ABC Costing

ACCTG 221 / ABC Costing ACCTG 221 / ABC Costing ACTIVITY BASED COSTING SYSTEMS First identifies activities in an organization and then assigns the cost of each activity to products and services based on actual consumption The

More information

TUTORIAL -ABC. Ir. Haery Sihombing/IP Pensyarah Pelawat Fakulti Kejuruteraan Pembuatan Universiti Teknologi Malaysia Melaka

TUTORIAL -ABC. Ir. Haery Sihombing/IP Pensyarah Pelawat Fakulti Kejuruteraan Pembuatan Universiti Teknologi Malaysia Melaka TUTORIAL -ABC Ir. Haery Sihombing/IP Pensyarah Pelawat Fakulti Kejuruteraan Pembuatan Universiti Teknologi Malaysia Melaka TOTAL COST for a COST OBJECT EXAMPLE: 1 Direct Cost (Labor Material) Overhead

More information

Chapter 2--Cost Terminology and Cost Behaviors

Chapter 2--Cost Terminology and Cost Behaviors Chapter 2--Cost Terminology and Cost Behaviors TRUE/FALSE 1. A cost object is anything for which management wants to collect or accumulate costs. ANS: T PTS: 1 DIF: Easy OBJ: 2-1 2. A production plant

More information

JOB ORDER COSTING. LO 1: Cost Systems. Determine whether job order costing or process costing would be more appropriate for each industry.

JOB ORDER COSTING. LO 1: Cost Systems. Determine whether job order costing or process costing would be more appropriate for each industry. JOB ORDER COSTING Terms Cost Accounting Process Cost System Job Order Cost System LO 1: Cost Systems Job-Order Costing Used for custom or unique items Each job is accounted for separately Measures cost

More information

Part 3 : 11/11/10 07:42:55. MultiFrame Company has the following revenue and cost budgets for the two products it sells.

Part 3 : 11/11/10 07:42:55. MultiFrame Company has the following revenue and cost budgets for the two products it sells. Question 1 - CMA 1290 4-4 - Decision Making MultiFrame Company has the following revenue and cost budgets for the two products it sells. Plastic Frames Glass Frames Budgeted unit sales 100,000 300,000

More information

1. The cost of an item is the sacrifice of resources made to acquire it. 2. An expense is a cost charged against revenue in an accounting period.

1. The cost of an item is the sacrifice of resources made to acquire it. 2. An expense is a cost charged against revenue in an accounting period. Chapter 02 Cost Concepts and Behavior True / False Questions 1. The cost of an item is the sacrifice of resources made to acquire it. True False 2. An expense is a cost charged against revenue in an accounting

More information

Chapter 2 An Introduction to Cost Terms and Purposes

Chapter 2 An Introduction to Cost Terms and Purposes Chapter 2 An Introduction to Cost Terms and Purposes Copyright 2003 Pearson Education Canada Inc. Slide 2-15 Costs and Cost Objects Cost a resource sacrificed or foregone to achieve a specific objective

More information

Cost Accounting. Multiple Choice Questions:

Cost Accounting. Multiple Choice Questions: Multiple Choice Questions: 1- The Value Chain a- Involves external companies as well as internal activities. b- Is the sequence of business functions in which customer usefulness is added to products or

More information

CHAPTER 7: ITEM CHARGES

CHAPTER 7: ITEM CHARGES Chapter 7: Item Charges CHAPTER 7: ITEM CHARGES Objectives The objectives are: Provide an Overview of the Item Charges functionality Set up Item Charges Define Purchase Item Charges Handle Additional Costs

More information

Part 1 Study Unit 5. Cost Accumulations Systems Jim Clemons, CMA Ronald Schmidt, CMA, CFM

Part 1 Study Unit 5. Cost Accumulations Systems Jim Clemons, CMA Ronald Schmidt, CMA, CFM Part 1 Study Unit 5 Cost Accumulations Systems Jim Clemons, CMA Ronald Schmidt, CMA, CFM 1 Overview Cost accounting systems record manufacturing activities using a perpetual inventory system, which continuously

More information

Solutions Manual for Cost Accounting A Managerial Emphasis 14th edition by Horngren Datar and Rajan

Solutions Manual for Cost Accounting A Managerial Emphasis 14th edition by Horngren Datar and Rajan Solutions Manual for Cost Accounting A Managerial Emphasis 14th edition by Horngren Datar and Rajan Link download Solutions Manual for Cost Accounting A Managerial Emphasis 14th edition by Horngren Datar

More information

COST C O S T COST. Cost is not a simple concept. It is important to distinguish between four different types - fixed,, variable, average and marginal.

COST C O S T COST. Cost is not a simple concept. It is important to distinguish between four different types - fixed,, variable, average and marginal. Ir. Haery Sihombing/IP Pensyarah Fakulti Kejuruteraan Pembuatan Universiti Teknologi Malaysia Melaka Chapter 3 DIRECT COST Chapter 4 INDIRECT COSTS C O S T COST Cost is not a simple concept. It is important

More information

CHAPTER 5 ACTIVITY-BASED COSTING AND MANAGEMENT

CHAPTER 5 ACTIVITY-BASED COSTING AND MANAGEMENT CHAPTER 5 ACTIVITY-BASED COSTING AND MANAGEMENT SHORT-ANSWER QUESTIONS 5-1 Cost smoothing (or traditional costing, broad averaging, peanut-butter costing ) describes a costing approach that uses one average

More information

Chapter 3--Product Costing: Manufacturing Processes, Cost Terminology, and Cost Flows

Chapter 3--Product Costing: Manufacturing Processes, Cost Terminology, and Cost Flows Chapter 3--Product Costing: Manufacturing Processes, Cost Terminology, and Cost Flows Student: 1. Which of the following types of organizations is most likely to have a raw materials inventory account?

More information

KPI ENCYCLOPEDIA. A Comprehensive Collection of KPI Definitions for PROCUREMENT

KPI ENCYCLOPEDIA. A Comprehensive Collection of KPI Definitions for PROCUREMENT KPI ENCYCLOPEDIA A Comprehensive Collection of KPI Definitions for PROCUREMENT www.opsdog.com info@opsdog.com 844.650.2888 Table of Contents KPI Encyclopedia Metric Definitions.............................

More information

Test Bank For Cost Accounting A Managerial Emphasis Fifth Canadian 5th Edition By Horngren Foster Datar And Gowing

Test Bank For Cost Accounting A Managerial Emphasis Fifth Canadian 5th Edition By Horngren Foster Datar And Gowing Test Bank For Cost Accounting A Managerial Emphasis Fifth Canadian 5th Edition By Horngren Foster Datar And Gowing Link full download: https://digitalcontentmarket.org/download/test-bank-for-cost-accounting-amanagerial-emphasis-fifth-canadian-5th-edition-by-horngren-foster-datar-andgowing/

More information

Inventory Cost Accounting Tips and Tricks. Nick Bergamo, Senior Manager Linda Pei, Senior Manager

Inventory Cost Accounting Tips and Tricks. Nick Bergamo, Senior Manager Linda Pei, Senior Manager 1 Inventory Cost Accounting Tips and Tricks Nick Bergamo, Senior Manager Linda Pei, Senior Manager 2 Disclaimer The material appearing in this presentation is for informational purposes only and is not

More information

Chapter 2 Cost Terms, Concepts, and Classifications

Chapter 2 Cost Terms, Concepts, and Classifications Multiple Choice Questions 16. Indirect labor is a part of: A) Prime cost. B) Conversion cost. C) Period cost. D) Nonmanufacturing cost. Answer: B Level: Medium LO: 1,2 Source: CPA, adapted 17. The cost

More information

Cost Behavior. Material Cost: Direct material: 1. seen in the final product 2. economic/visible to trace Indirect Material:

Cost Behavior. Material Cost: Direct material: 1. seen in the final product 2. economic/visible to trace Indirect Material: 1 Chapter 2 Introduction to Cost Terms and Purposes Cost A cost is the value of economic resources (e.g., money) sacrificed or used up to achieve a particular objective (e.g., produce a product or perform

More information

2.1 Identify and distinguish between two manufacturing cost classification systems: direct and indirect, prime and conversion.

2.1 Identify and distinguish between two manufacturing cost classification systems: direct and indirect, prime and conversion. Chapter 2 An Introduction to Cost Terms and Purposes 2.1 Identify and distinguish between two manufacturing cost classification systems: direct and indirect, prime and conversion. 1) "Cost" is defined

More information

Introduction to Managerial Accounting 7th Edition Brewer Garrison Noreen Test Bank. Download:

Introduction to Managerial Accounting 7th Edition Brewer Garrison Noreen Test Bank. Download: Introduction to Managerial Accounting 7th Edition Brewer Garrison Noreen Test Bank. Download: https://testbankarea.com/download/introduction-managerial-accounting- 7th-edition-brewer-garrison-noreen-test-bank/

More information

Introduction to Managerial Accounting 7th Edition Brewer Garrison Noreen Test Bank. Download:

Introduction to Managerial Accounting 7th Edition Brewer Garrison Noreen Test Bank. Download: Introduction to Managerial Accounting 7th Edition Brewer Garrison Noreen Test Bank. Download: https://testbankarea.com/download/introduction-managerial-accounting- 7th-edition-brewer-garrison-noreen-test-bank/

More information

Financial Accounting and Auditing Paper-III Financial Accounting

Financial Accounting and Auditing Paper-III Financial Accounting Revised Syllabus of the Courses of B.Com. Programme at T.Y.B.Com. with Effect from the Academic Year 2015-2016 for IDOL Students Financial Accounting and Auditing Paper-III Financial Accounting SECTION

More information

Chapter 2--Product Costing: Manufacturing Processes, Cost Terminology, and Cost Flows

Chapter 2--Product Costing: Manufacturing Processes, Cost Terminology, and Cost Flows Chapter 2--Product Costing: Manufacturing Processes, Cost Terminology, and Cost Flows Student: 1. Which of the following types of organizations is most likely to have a raw materials inventory account?

More information

Can Innovation of Time Driven ABC System Replace Conventional ABC System?

Can Innovation of Time Driven ABC System Replace Conventional ABC System? Can Innovation of Time Driven ABC System Replace Conventional ABC System? Tan Ming Kuang Accounting Department, Maranatha Christian University Abstract: The purpose of this paper is to analyze the differences

More information

2.1 Identify and distinguish between two manufacturing cost classification systems: direct and indirect, prime and conversion.

2.1 Identify and distinguish between two manufacturing cost classification systems: direct and indirect, prime and conversion. Cost Accounting, Cdn. Ed., 7e (Horngren) Chapter 2 An Introduction to Cost Terms and Purposes 2.1 Identify and distinguish between two manufacturing cost classification systems: direct and indirect, prime

More information

Chapter 8 Inventories: Measurement

Chapter 8 Inventories: Measurement Chapter 8 Inventories: Measurement QUESTIONS FOR REVIEW OF KEY TOPICS Question 8 1 Inventory for a manufacturing company consists of (1) raw materials, (2) work in process, and (3) finished goods. Raw

More information

Multiple Choice Questions

Multiple Choice Questions Multiple Choice Questions 1. A cost not relevant to deciding whether to purchase a new machine is: a) The cost of the new machine b) Lower maintenance costs for the new machine c) The cost of the old machine

More information

AUDIT STATUS. Continuous Auditing Ideas and Priority Ranking Draft: 8/7/2012

AUDIT STATUS. Continuous Auditing Ideas and Priority Ranking Draft: 8/7/2012 Compliance Identify single day stays and subsequent re-admissions Identify inappropriate unbundling of lab tests Identify frequent use of high risk organizations Match OIG-excluded providers list with

More information

Akuntansi Biaya. Modul ke: 14FEB. Activity Based Costing. Fakultas. Diah Iskandar SE., M.Si dan Nurul Hidayah,SE,Ak,MSi. Program Studi Akuntansi

Akuntansi Biaya. Modul ke: 14FEB. Activity Based Costing. Fakultas. Diah Iskandar SE., M.Si dan Nurul Hidayah,SE,Ak,MSi. Program Studi Akuntansi Modul ke: Akuntansi Biaya Activity Based Costing Fakultas 14FEB Diah Iskandar SE., M.Si dan Nurul Hidayah,SE,Ak,MSi Program Studi Akuntansi Data biaya langsung produk Langkah 1 adalah menghitung biaya

More information

Variable Costing: A Tool for Management. M. En C. Eduardo Bustos Farías

Variable Costing: A Tool for Management. M. En C. Eduardo Bustos Farías Variable Costing: A Tool for Management M. En C. Eduardo Bustos Farías 1 Absorption Costing A system of accounting for costs in which both fixed and variable production costs are considered product costs.

More information

Management Accounting

Management Accounting Management Accounting Suggested Solutions to Practice Questions Professional, Practical, Proven www.accountingtechniciansireland.ie Table of Contents Part 1:... 2 Part 2:... 8 Part 3:... 14 Part 4:...

More information

APPENDIX 2 COMMUNITY DEVELOPMENT COMMISSION FINANCIAL CHECKLIST REQUIRED FOR ALL APPLICANTS (A SITE VISIT MAY BE CONDUCTED LATER)

APPENDIX 2 COMMUNITY DEVELOPMENT COMMISSION FINANCIAL CHECKLIST REQUIRED FOR ALL APPLICANTS (A SITE VISIT MAY BE CONDUCTED LATER) REQUIRED FOR ALL APPLICANTS (A SITE VISIT MAY BE CONDUCTED LATER) AGENCY NAME: AGENCY ADDRESS AGENCY PHONE: DATE PREPARED: PREPARED BY: TITLE: EMAIL: AGENCY GENERAL INFORMATION EXECUTIVE DIRECTOR /CITY

More information

CHAPTER 8. Valuation of Inventories: A Cost-Basis Approach 1, 2, 3, 4, 5, 6, 7, 8, 11, 12, 14, 15, 16

CHAPTER 8. Valuation of Inventories: A Cost-Basis Approach 1, 2, 3, 4, 5, 6, 7, 8, 11, 12, 14, 15, 16 CHAPTER 8 Valuation of Inventories: A Cost-Basis Approach ASSIGNMENT CLASSIFICATION TABLE (BY TOPIC) Topics Questions Brief Exercises Exercises Problems Concepts for Analysis 1. Inventory accounts; determining

More information

CEBU CPAR CENTER. M a n d a u e C I t y

CEBU CPAR CENTER. M a n d a u e C I t y Page 1 of 9 CEBU CPAR CENTER M a n d a u e C I t y AUDITING PROBLEMS AUDIT OF INVENTORIES PROBLEM NO. 1 The Pasay Company is a wholesale distributor of automobile replacement parts. Initial amounts taken

More information

Chapter 20: Job Order Costing

Chapter 20: Job Order Costing Chapter 20: Job Order Costing DO IT! 1 Accumulating Manufacturing Costs During the current month, Ringling Company incurs the following manufacturing costs: (a) Raw material purchases of $4,200 on account.

More information

Pricing Decisions & Profitability Analysis

Pricing Decisions & Profitability Analysis Pricing Decisions & Profitability Analysis Economic theory The optimum selling price is the price at which marginal revenue equals marginal cost. 1 Problems with applying economic theory 1. Difficult and

More information

CHAPTER 2 AN INTRODUCTION TO COST TERMS AND PURPOSES

CHAPTER 2 AN INTRODUCTION TO COST TERMS AND PURPOSES CHAPTER 2 AN INTRODUCTION TO COST TERMS AND PURPOSES 2-1 A cost object is anything for which a separate measurement of costs is desired. Examples include a product, a service, a project, a customer, a

More information

Master Document Audit Program. Version 4.28, dated March 2018 B-1 Planning Considerations

Master Document Audit Program. Version 4.28, dated March 2018 B-1 Planning Considerations Activity Code 17100 B-1 Planning Considerations Termination, Fixed Inventory Basis Type of Service - Attestation Examination Engagement Audit Specific Independence Determination Members of the audit team

More information

Differential Analysis and Product Pricing

Differential Analysis and Product Pricing chapter 24(9) Differential Analysis and Product Pricing OPENING COMMENTS This chapter covers (1) differential analysis, (2) methods of determining the selling price of a product using a cost-plus markup

More information

page: 1 - Controlling - CPUT University of Applied Sciences Prof Dr Carsten Berkau, 2010

page: 1 - Controlling - CPUT University of Applied Sciences Prof Dr Carsten Berkau, 2010 page: 1 ABC by Carsten Berkau 1.1 page: 2 Controlling FH Osnabrück 1.2 page: 3 1.3 page: 4 Osnabrück 1.4 page: 5 (1) FH Osnabrück (www.fh-osnabrueck.de) (2) Controlling Department (3) Teaching Controlling

More information

Eagle Business Management System - Manufacturing

Eagle Business Management System - Manufacturing Eagle Business Management System - Manufacturing Table of Contents INTRODUCTION...1 Technical Support...1 Overview...2 CREATING A BATCH...5 Creating a Simple Manufacturing Batch...5 Using Inventory Components

More information

Chapter 7 Activity-Based Costing and Management

Chapter 7 Activity-Based Costing and Management 34 Chapter 7 Activity-Based Costing and Management LEARNING OBJECTIVES Chapter 7 addresses the following questions: LO1 LO2 LO3 LO4 LO5 LO6 Differentiate activity-based costing (ABC) from traditional costing.

More information

Problem Exercise 3-12

Problem Exercise 3-12 Exercise 3-12 1. The overhead applied to Ms. Miyami s account would be computed as follows: 2002 2001 Estimated overhead cost (a)... $144,000 $144,000 Estimated professional staff hours (b)... 2,250 2,400

More information

ODE Child Nutrition Programs. Commodity Food Distribution Program Terminology

ODE Child Nutrition Programs. Commodity Food Distribution Program Terminology ODE Child Nutrition Programs Commodity Food Distribution Program Terminology Agencies State Agency (SA) The Oregon Department of Education enters into an agreement with USDA for the distribution of commodities

More information

1. Cost accounting involves the measuring, recording, and reporting of: A. product costs. B. future costs. C. manufacturing processes.

1. Cost accounting involves the measuring, recording, and reporting of: A. product costs. B. future costs. C. manufacturing processes. 1. Cost accounting involves the measuring, recording, and reporting of: A. product costs. B. future costs. C. manufacturing processes. D. managerial accounting decisions. 2. In accumulating raw materials

More information

Selling Price 60 Direct material 28 Direct Rs. 3 p. hr. 12 Variable overheads 6 Fixed cost (Total) 1,05,500

Selling Price 60 Direct material 28 Direct Rs. 3 p. hr. 12 Variable overheads 6 Fixed cost (Total) 1,05,500 Question 1 (a) PAPER 5 : ADVANCED MANAGEMENT ACCOUNTING Answer all questions. Working notes should form part of the answer. E Ltd. is engaged in the manufacturing of three products in its factory. The

More information

Fundamentals of Product and Service Costing:

Fundamentals of Product and Service Costing: Fundamentals of Product and Service Costing: Demonstration Problems 1 Demonstration Problem 1 In the first quarter of operation, the Blending Department of ChemUSA produced 50,000 barrels of Compound X

More information

Future revenues A$ A$6 500 Deduct future costs Operating income A$8 500 A$6 500

Future revenues A$ A$6 500 Deduct future costs Operating income A$8 500 A$6 500 Chapter 8 DECISION MAKING AND RELEVANT INFORMATION 8-16 (20 min.) Disposal of assets 1. This is an unfortunate situation, yet the A$78 000 costs are irrelevant regarding the decision to re-machine or sold

More information

CHAPTER 5: MERCHANDISING OPERATIONS

CHAPTER 5: MERCHANDISING OPERATIONS CHAPTER 5: MERCHANDISING OPERATIONS CHAPTER SYNOPSIS Chapter 5 first compares a service business with a merchandising business and then discusses the purchase and sale of merchandise inventory. The chapter

More information

2 Cost Concepts and Behavior

2 Cost Concepts and Behavior 2 Cost Concepts and Behavior Solutions to Review Questions 2-1. Cost is a more general term that refers to a sacrifice of resources and may be either an opportunity cost or an outlay cost. An expense is

More information

CHAPTER 6 PROCESS COST ACCOUNTING ADDITIONAL PROCEDURES

CHAPTER 6 PROCESS COST ACCOUNTING ADDITIONAL PROCEDURES CHAPTER 6 PROCESS COST ACCOUNTING ADDITIONAL PROCEDURES Review Summary 1. In many industries where a process cost system is used, the materials may be put into production in irregular quantities and at

More information

Inventories. Raw material 61,000 81,000 Work in process 80,000 30,000 Finished goods 90, ,000

Inventories. Raw material 61,000 81,000 Work in process 80,000 30,000 Finished goods 90, ,000 Beginning Inventories Ending Raw material 61,000 81,000 Work in process 80,000 30,000 Finished goods 90,000 110,000 Direct material used 318,000 Direct Labour 230,000 Manufecturing Overhead-60% of Direct

More information

Modul ke: Akuntansi Biaya. Activity Accounting. Fakultas Ekonomi dan Bisnis. Suryadharma Sim, SE, M. Ak. Program Studi S1 Manajemen

Modul ke: Akuntansi Biaya. Activity Accounting. Fakultas Ekonomi dan Bisnis. Suryadharma Sim, SE, M. Ak. Program Studi S1 Manajemen Modul ke: 14 Fakultas Ekonomi dan Bisnis Akuntansi Biaya Activity Accounting Suryadharma Sim, SE, M. Ak Program Studi S1 Manajemen Activity-Based Costing An accounting method that identifies the activities

More information

COST COST OBJECT. Cost centre. Profit centre. Investment centre

COST COST OBJECT. Cost centre. Profit centre. Investment centre COST The amount of money or property paid for a good or service. Cost is an expense for both personal and business assets. If a cost is for a business expense, it may be tax deductible. A cost may be paid

More information

Material available on web at

Material available on web at Material available on web at http://gtumcain.wordpress.com Major topics Modules of ERP Human Resources Management Financial Management Inventory Management Quality Management Sales and Distribution (Murlidhar

More information

Master Document Master Document. Version 4.28, dated December 2017 B-1 Planning Considerations

Master Document Master Document. Version 4.28, dated December 2017 B-1 Planning Considerations Activity Code 17100 B-1 Planning Considerations Termination, Total Cost Basis Type of Service - Attestation Examination Engagement Audit Specific Independence Determination Members of the audit team and

More information

SM-Ch02-5e.pdf Lanen_5e_IM_Ch_02.pdf Chapter 02 - Solutions.pdf Lanen_02_Instructor_Final.pdf Chapter 02.pdf

SM-Ch02-5e.pdf Lanen_5e_IM_Ch_02.pdf Chapter 02 - Solutions.pdf Lanen_02_Instructor_Final.pdf Chapter 02.pdf SM-Ch02-5e.pdf Lanen_5e_IM_Ch_02.pdf Chapter 02 - Solutions.pdf Lanen_02_Instructor_Final.pdf Chapter 02.pdf 2 Cost Concepts and Behavior Solutions to Review Questions 2-1. Cost is a more general term

More information

Chapter 5 Job Costing

Chapter 5 Job Costing Chapter 5: Job Costing 203 Chapter 5 Job Costing LEARNING OBJECTIVES Chapter 5 addresses the following questions: LO1 LO2 LO3 LO4 LO5 LO6 Explain product costs and cost flows through the manufacturing

More information