1 Breakout Session: CPM Scheduling The Full Potential of the CPM Scheduling Process Brandon Howell January 29, 2019 LAYTONCONSTRUCTION.COM 2 nd most common cause of disputes in 2016 was poorly drafted or 1/3 of all construction contracts end in dispute incomplete / unsubstantiated claims - Arcadis: 2017 Global Construction Disputes Report

2 What We Will Cover Scheduling 101 How to organize and manage your schedule as a defense tool Key data to monitor in the schedule to avoid liability in the case of claims Steps needed to maintain documentation during the scheduling process

3 Schedule in a Nutshell

4 Organizing your Schedule as a Defense Tool How to document delays Backup documentation

5 Question When should you As soon as you realize document a delay in the there s an impact schedule?

6 Delay Fragnet Example

7 Weather Delay Example

8 Use the Notebook

9 How do you Mitigate Delays? Watch for trends with trouble subs Always document the delay first Understand the impacts and who s responsible Make a copy of the schedule Prepare acceleration options

10 Backup Documentation Delay Binder Delay Binder Delay Binder Delay Binder

11 Table of Contents Tab 1 PCO #48 Building 21 Structural Steel Changes Tab 2 PCO #58 Bulletin L-008 Revisions to Door Hardware Tab 3 RFI #13 Unit Height Conflicts Tab 4 RFI #29 Structural Steel Clarifications Tab 5 RFI #127 Building 21 Canopy Attachment

12 1 PCO #48 Building 21 Structural Steel Changes Tab 1 Delay Fragnet

13 1 PCO #48 Building 21 Structural Steel Changes Tab 1 PCO #48 Time Impact Analysis

14 1 PCO #48 Building 21 Structural Steel Changes Tab

15 1 2 PCO #58 Bulletin L-008 Revisions to Door Hardware Delay Fragnet Tab

16 1 PCO #58 Bulletin L-008 Revisions to Door Hardware Tab

17 What to Monitor in the Schedule Milestone Management Determine responsibility Concurrency analysis Watch trouble subs closely

18 Milestone Management 14 Milestone Trending Chart Baseline Projected Late Finish Projected Acceleration Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 9 Month 10

19 Determine Responsibility

20 Concurrency Analysis Concurrent Delays Storefront / Canopy Re-Design Joint Trench Delays RFI #204 - Bored Holes in Walls Permanent Power Delays Lift Station Procurement Drywall Manpower Countertop Procurement RFI #307 - Elevator Counterweight Expansion Joint Procurement Framing Manpower Owner GC

21 Steps to Maintain Documentation Open communication between Scheduler and Project Team Information that the Scheduler needs Death by 1,000 cuts / Measles

22 Open Communication The project team needs to let the Scheduler know of all major changes if there is a potential for schedule impact

23 Information the Scheduler Needs What s the trigger? Date any documentation was issued (RFI, ASI, etc.) Copy of the actual document If added scope, develop delay Fragnet What activities are being impacted?

24 Death by 1,000 Cuts Numerous or constant changes to the project

25 PCO s vs. Substantial Completion PCO's vs. Substantial Completion Contract Completion Jul-15 6-Apr Dec Time Extension Sep Jun Mar Nov-13 PCO Start PCO Approvals Contract Completion Substantial Completion

26 Measles Demonstration

27 GRANITE MOUNTAIN IMPACT ANALYSIS

28 GRANITE MOUNTAIN Impacts Successfully Overcome Throughout the Project Power Pole The power pole supplying the main power to the existing building was replaced with a below-grade power feed. Rock Slide Boulders sheared off the face of the mountain landing where the new building needed to be built. Asbestos The asbestos survey was found to be inaccurate causing a large amount of additional asbestos to require abatement Lead Paint The hazardous material survey was found to be inaccurate requiring additional lead paint to require abatement Existing Operations Employees were much more sensitive to dust, noise, and odors than expected. Ground Rock The soils report indicated that below-grade rock should not have been as large an impact as it was. Avalanches Snow and ice slide threats were not expected to impact the project as much as they did. Rock Pinning and Analysis The need to pin rock and analyze the threats to safety were not expected. Winter The project was originally expected to span one winter, but was required to span two.

29

30

31 PERMANENT POWER MOVED UNDERGROUND

32

33

34

35

36 LAYTON RELEASED TO START CONSTRUCTION

37

38 CONCRETE IMPACT #10 - Potential Water Tank Rock Slide / Tank Re-Design CONCRETE IMPACT #3 - RFI #195 & 196 Grade Beam Delay

39

40 CONCRETE IMPACT #7- Snow & Ice Slides

41

42 CONCRETE IMPACT #8A - Design flaws between architectural & structural CONCRETE IMPACT #8B - 2ea Missing CC3 columns on structural S302, C2 & C7

43

44 CONCRETE IMPACT #14 - Hydration of leveling slabs in the vaults Added cost of de-humid CONCRETE IMPACT #1 - Column size discrepancies (A line S302 vs A line A302)

45

46 CONCRETE IMPACT #12-2 nd Floor Matt Slab Change Re-Sequencing from Delays

47

48 FINAL COMPLETION DATE DECEMBER 2, 2015

49 PCO #001 PCO #002 PCO #003 PCO #004 PCO #005 PCO #006 PCO #007 PCO #008 PCO #009 PCO #010 PCO #011 PCO #012 PCO #013 PCO #014 PCO #015 PCO #016 PCO #017 PCO #018 PCO #019 PCO #020 PCO #021 PCO #022 PCO #023 PCO #024 PCO #025 PCO #026 PCO #027 PCO #028 PCO #029 PCO #030 PCO #031 PCO #032 PCO #033 PCO #034 PCO #035 PCO #036 PCO #037 PCO #038 PCO #039 PCO #040 PCO #041 PCO #042 PCO #043 PCO #044 PCO #045 PCO #046 PCO #047 PCO #048 PCO #049 PCO #050 PCO #051 PCO #052 PCO #053 PCO #054 PCO #055 PCO #056 PCO #057 PCO #058 PCO #059 PCO #060 PCO #061 PCO #062 PCO #063 PCO #064 PCO #065 PCO #066 PCO #067 PCO #068 PCO #069 PCO #070 PCO #071 PCO #072 PCO #073 PCO #074 PCO #075 PCO #076 PCO #077 PCO #078 PCO #079 PCO #080 PCO #081 PCO #082 PCO #083 PCO #084 PCO #085 PCO #086 PCO #087 PCO #088 PCO #089 PCO #090 PCO #091 PCO #092 PCO #093 PCO #094 PCO #095 PCO #096 PCO #097 PCO #098 PCO #099 PCO #100 PCO #101 PCO #102 PCO #103 PCO #104 PCO #105 PCO #106 PCO #107 PCO #108 PCO #109 PCO #110 PCO #111 PCO #112 PCO #113 PCO #114 PCO #115 PCO #116 PCO #117 PCO #118 PCO #119 PCO #120 PCO #121 PCO #122 PCO #123 PCO #124 PCO #125 PCO #126 PCO #127 PCO #128 PCO #129 PCO #130 PCO #131 PCO #132 PCO #133 PCO #134 PCO #135 PCO #136 PCO #137 PCO #138 PCO #139 PCO #140 PCO #141 PCO #142 PCO #143 PCO #144 PCO #145 PCO #146 PCO #147 PCO #148 PCO #149 PCO #150 PCO #151 PCO #152 PCO #153 PCO #154 PCO #155 PCO #156 PCO #157 PCO #158 PCO #159 PCO #160 PCO #161 PCO #162 PCO #163 PCO #164 PCO #165 PCO #166 PCO #167 PCO #168 PCO #169 PCO #170 PCO #171 PCO #172 PCO #173 PCO #174 PCO #175 PCO #176 PCO #177 PCO #178 PCO #179 PCO #180 PCO #181 PCO #182 PCO #183 PCO #184 PCO #185 PCO #186 PCO #187 PCO #188 PCO #189 PCO #190 PCO #191 PCO #192 PCO #193 PCO #194 PCO #195 PCO #196 PCO #197 PCO #198 PCO #199 PCO #200 PCO #201 PCO #202 PCO #203 PCO #204 PCO #205 PCO #206 PCO #207 PCO #208 PCO #209 PCO #210 PCO #211 PCO #212 PCO #213 PCO #214 PCO #215 PCO #216 PCO #217 PCO #218 PCO #219 PCO #220 PCO #221 PCO #222 PCO #223 PCO #224 PCO #225

50 THANK YOU! Brandon Howell Manager of Corporate Scheduling Layton Construction Company