C.P. data, CIPS & DCVG techniques: another way to predict Corrosion on Gas Pipeline.
|
|
- Emery Willis
- 6 years ago
- Views:
Transcription
1 23 rd World GAS Conference, Amsterdam 26 C.P. data, CIPS & DCVG techniques: another way to predict Corrosion on Gas Pipeline. A.Taberkokt ALGERIA 1
2 ABSTRACT One of the most important care of gas operators is how to prevent the presence of corrosion points on their metallic gas pipelines, and therefore repair them before they reach a critical threshold that could lead to an incident. This prevention can be assured by inspecting the pipe wall thickness with an intelligent pig tool. Indeed the evolution of the technology, allows the development of high resolution tools which locate corrosion points ( if they exist ) and restore them in three axial axis dimensions. The gas operators can then identify the critical corrosion points and undertake the appropriate actions to ensure a safe operation of its gas pipeline. Solely, this alternative of inspection, is on one hand costly and on another hand, depends on the technical characteristics of the pipe (diameter, thickness, bends...), without taking into account the time parameter from the call of tender to the data acquisition. In addition to that, the gas operator has to prepare the required conditions before and during the pipe inspection (gas equipments to be replaced, relive of ballast industrial customers in certain cases due to technical reasons, repeating the inspection if some troubles appear in the acquisition data recorder...). Therefore, the gas operators can undertake another alternative which consists of using electrical field survey methods: ON/OFF CIPS combined with DCVG measures over the buried gas pipeline. For which, he has to add historical data of cathodic protection parameters, such as soil resistivities, potential surveys, Off rectifiers time and any other parameters which favor the instability of the steel pipe wall thickness. The analysis of the obtained results leads in preventing the existence of the corrosion points. This alternative is undertaken whatever the gas pipeline characteristics are. The present work shows us an experience done on a part of section of the gas pipeline 2 diameter and 77 Km length gas pipeline (from Relizane town to Sig ) using the two techniques : Inspection by intelligent pig tool and electrical field survey methods. We focus our interest over the first ( 1 ) ten kilometers, cause it s first the section in which our previous study showed us to be the most probable affected part of the gas pipeline, and second because it s the section which supports the high pressure levels (existence of the compressor station ). The results of the both techniques were given; time and costs were evaluated showing the positive and negative sides of the two alternatives. Finally conclusion and recommendations were done for gas operators, who are interested to inspire with this experiment. 2
3 TABLE OF CONTENTS 1. Abstract 2. Introduction 3. Technical characteristics of the gas pipeline 4. Corrosion prediction using CP data and electrical fields surveys. 5. Inspection of the gas pipeline by intelligent tool. 6. Analysis and comparison of the MFL tool and On line surveys results 7. Conclusion. 8. References 9. Annexes 3
4 1. INTRODUCTION On 1977 the Algerian Gas & Electricity company SONELGAZ inherited the 2 Relizane Maghnia high pressure gas pipeline, called 2 Ouest. This pipe made off three sections coated with bitumen product, was strategic for the north west of Algeria, since it permitted the supply of natural gas to the towns situated in the neighboring of gas pipeline. Unfortunately, our company received the gas pipeline in very bad conditions, which required a rehabilitation programs just after putting gas into the pipeline. From these years a particular care was and is still given to the 2 Ouest, by establishing special programs such as inspections by intelligent pig and rehabilitation, to satisfy the required rules of supplying natural gas in a safety condition. From 1979 to 1995 our company has done: - The change of 3 % of the total gas pipelines length, - Reparation of all the severe corrosion points, - Reparation of thousands defects coating. On 1996, because of the possibility to feed a new customers, a power plant situated at 7 Km far the end of the network ( after the extension of the pipeline ), we prepared a rehabilitation study which undertook actions to short, medium and long term. Among these actions, we proposed to change the first 44 Km of the Relizane - Sig section, basing on cathodic protection parameters history, coating condition. In addition, it s the part of the gas pipeline which will support the highest pressures level. The technical committee of our company didn t accepted the proposal of the renovation, in fact, they agreed to undertake this action, only after inspecting the gas pipeline by the intelligent pig tool. So we took the opportunity to investigate, over the first 1 Km of the gas pipeline s first section* by using electrical field measurement methods ( DCVG & CIPS ),combined with the historical CP data parameters to predict where corrosion could take place and compare it with the results of the inspection by intelligent pig. This report throws investigation results, pictures of our undertaken actions, in which time and costs were evaluated showing the positive and negative sides of the two alternatives, a conclusion and recommendations are done in such case, someone could inspire with this experiment. * : the section is the one which support the high pressure levels 2 - TECHNICAL CHARACTERISTICS OF THE GAS PIPELINE: The main characteristics of the gas pipeline were as follow: - Diameter: Ø 2 - Total length: 273,524 Km ( 265 Km initially ) - Thickness: mm - Steel Grade: X 52 - Type of the coating: Km coal tar enamel (new parts) and the rest is petroleum bitumen. 4
5 3 - CORROSION PREDICTION USING CP DATA AND ELECTRICAL FIELD SURVEYS: 3 1 Choice of the area s pipe to investigate Starting from the acceptable basis that, containing external corrosion of buried metallic structures is possible only if two protection techniques are used. The first one is to assure the separation of the structure from the soil by applying an adequate coating. The second is applying cathodic protection ( CP ) to the structure, cause there in no coating which could insulate the structure from the soil at 1 % ( without taking into account that coating defects appear in time ). Our work was then, to delineate the coating defects on the buried pipeline. As we ve seen in the introduction, we focus our work over the Relizane Sig section. After analyzing the historical CP s data, three areas of the gas pipeline knew a level of potentials (to the copper copper sulfate half cell reference Cu/CuSO 4 ), below the criterion protection.(see Fig. 1 ). Three regions presented the same conditions to undertake investigations, we chose the first one cause as we said, it s the part of the gas pipeline which supports the high pressure levels. Potential [ - mv ] Threshold of protection On Potential 95 On Potential 97 On Potential 99 2'' Relizane-Sig On Potential Soil resistivity Resistivity [ Ω.m ] P.K. [ Km ] Area N 1 Area N 2 Area N 3 : New parts of the pipe GRD RELIZANE P.K., Line breaks GRA SIG Fig.1 Synoptic plan of Relizane Sig section and its potential plots P.K. : Kilometer Point. 5
6 3-2 Coating defects research: Principle of the survey methods: Tow survey methods were used simultaneously, the measurement of the lateral voltage drop using two copper copper sulfate half cell ( DCVG ) and the close order potential survey using only one half cell ( CIPS ) ( see Fig.2 ). The measurements were done in ON-OFF ( by connecting a time contactor to the rectifier ), of course, prior to undertake these measurements the pipe s location was done. The measurements were taken each 5 meters ( when necessary it s reduced to locate with accuracy the coating defect s epicenter). When an important defect is located it s marked on a map (experience showed that stakes could easily be stolen). At this time of these investigations we didn t get a GPS equipment, which could gave a big hand to our work. CIPS measurement Test point Half cell Cu/CuSO 4 mv Ω ρ soil resistivity measurement DCVG measurement Pipe detection Fig. 2 Illustration of the combined methods CIPS & DCVG techniques Interpretation of the results: Thousands of data were gathered, to interpret easily the results we plotted (versus the distance covered): - the On Off potential of the pipeline ( P On and P Off ) - the gradient voltage difference VOn VOff ( V ) or IR % (1x V/ P ). It s useful to remind that, when a direct current is applied to a pipeline, a voltage gradient is established on the ground, due to the passage of the current through the soil to the bare steel exposed at the defect. Generally, the larger defect is, the greater the current flow and hence larger voltage gradient. In the same manner we can use the % IR that represents the percentage of the applied potential ( P) which is lost on the fault position ( V), and generally the IR % value increases with the increasing defect size/current requirement. 6
7 Before giving the result of the coating survey it s useful to define the categories of the coating defects: - 1 st category means IR % greater or equal to 1 and less than rd category means IR % greater or equal to nd category is between 1 st and 3 rd ones. The following table synthesizes the surveys results by pipe s sections: Pipe sections Number of defects coating 3 rd category 2 nd category 1 st category P.K.2 TO P.K P.K 1.45 TO P.K P.K 4.4 TO P.K P.K 5.8 TO P.K P.K 6.9 TO P.K P.K 8. TO P.K The first attractive result is that the change of the sections during the 1 st programme of gas pipeline s rehabilitation presents a few number of defects. Once detecting the localisation coating defect, we start analysing them from the point of view of cathodic protection level ( see annexe I), and the soil aggressivity ( for the soil classification see table N 2 ), we can therefore predict the presence of the corrosion at the defect coating. The following table shows an example of how the gathered data are arranged to make easier the analysis: 3 rd category IR % greater or equal to 5 Pipe sections Defects Distance Cathodic Prot. Soil Resistivity Nbr distribution [ Km ] Level [ mv ] Ω.m to P.K 8. TO P.K to to to to to Of course, it s important to recall that we need the historical CP data. For this purpose, we took the last 8 years of the quarterly* ON potential surveys and the monthly* rectifier s measurement reports, in addition to the ON-OFF potential surveys done on and 99 ( see Fig.1 for the years 95,97 and 99 ). Here, it s important to mention that a BANK of PC data is vital for of any existing pipeline. As an example of that, the part of the pipeline situated between P.K 2 and 6 was found protected when we did the surveys, but it was the one which was the most affected: lack of protection for the years 1994 and 1995 (we have reinforced the protection system by a new rectifier at P.K. 6 ) and subjugated to an aggressive soil. * : measurements are done by our regional teams. 7
8 All the 3 rd and 2 nd categories coating defects were well analysed, and we have predicted the possibility of the corrosion presence (with the ration of one corrosion point per one coating defect in which the corrosion process is likely to occur: we don t have tools to predict more than one). The corrosion prediction is given by section of the pipe as shown in the following table: Pipe section Number of the Corrosion points predicted P.K.2 TO P.K 1.45 P.K 1.45 TO P.K 3.3 P.K 4.4 TO P.K P.K 5.8 TO P.K P.K 6.9 TO P.K P.K 8. TO P.K The results given in the above table were obtained, after analysing point per point of the second and third categories coating defects. As an example, the following table shows how the upper table is obtained. Pipe sections Corrosion prediction Distance Soil Resistivity Nbr distribution [ Km ] Ω.m 9 8 to to to P.K 8. to P.K to to to Cost of the survey operation: The DCVG and CIPS surveys were done by our own company team. 4 people (among them two experts), undertook the investigations which spent 8 days ( in site ). The total cost of the operation is 4 K$. 4 INSPECTION OF THE GAS PIPELINE BY THE INTELLIGENT TOOL. 4-1 Principle of the inspection The pipe inspection was done by the Magnetic flux leakage process, using a high resolution equipment with the range of accuracy for depth of defect up to ± 1%. The corrosion points were given in three axial axis dimensions. Many information were given concerning the corrosion point or the pipeline its self. ( see annexe). Fig. 2 shows how corrosion point is visualized in 3 D, by "zoom plot". The Red zones designate corrosion defects. Fig.2 Corrosion points 4-2 Time evaluation: from the call of tender to final results More than one year from the tender of call to the reception of the inspection results ( the time include the tender launching, analysing the technical offers, asking the tenderer for details and additional information, commercial offer, preparation of the conditions to permit the inspection of the gas pipeline.). 8
9 4-3 Inspection results The following table gives the corrosion number per sections of the pipeline. Pipe section Number of the Corrosion points P.K.2 TO P.K P.K 1.45 TO P.K P.K 3.3 TO P.K 4.4 TO P.K P.K 5.8 TO P.K P.K 6.9 TO P.K P.K 8. TO P.K The following graph gives the distribution of the corrosion points for the 1 first kilometres : thickness loss versus distance: 9 8 % T h ic k n e s s lo ss Corrosion Points Distance [ Km ] Fig.3. Corrosion distribution: % thickness loss versus distance 4-4 Cost of the inspection The total cost of the inspection was K$ 9
10 5 - ANALYSIS AND COMPARISON OF THE MFL TOOL AND ON LINE SURVEYS RESULTS : The following table synthesizes the corrosion points obtained by MFL tool inspection with the ones predicted by on line surveys methods: Pipe section Number of the Corrosion points Inspection s results Predicted by online surveys N 1 P.K.2 TO P.K N 2 P.K 1.45 TO P.K N 3 P.K. 3.3 TO N 4 P.K 4.4 TO P.K N 5 P.K 5.8 TO P.K N 6 P.K 6.9 TO P.K N 7 P.K 8. TO P.K At this step, if we had a GPS equipment the comparison of the two results would be very easy and accurate, because the measure of distance covered by the technician could never be equal to the one done by the intelligent pig. The P.K of the pipe s special points and the test points helped us in some cases to correct our results. As the work we ve done for the corrosion prediction, we compare point per point the results obtained and listed in the above table. As an example, the following table gives the way, of how we did the comparison for the pipe s section N 7 : Pipe sections Corrosion points Distance Nbr distribution Observations MFL Surveys MFL Surveys [ Km ] 9 8 to 8.13 Corros. at PK 7.8 and to P.K 8. to P.K to to to 8.98 Difference of 48 m to 9.5 Difference of 28m Difference of 19m If we neglect the number of the corrosion points, the first attractive result is, our prediction failed for the first sections N 1 and 2 (we predicted zero co rrosion point). In fact for the first sections, 15 corrosion points over the 17 (found), are located where we had found a coating defect of second category. We also missed to predict corrosion on these parts of the pipe: - P.K 3.3 to 4.4 : 48 corrosion points. 4 points with respectively metal loss of 25, 25, 22, 17 and 75 at the section P.K The rest are all less than 17 %. - P.K to 9.84: 24 corrosion points with metal loss, less or equal to 13% of the thickness and 2 of respectively 22 and 17 %. For the rest of our predictions, results showed that if we hadn t got approximately the same P.K. of the corrosion locations, we re at least far from of 5 to 7 meters. 1
11 Just after getting the MFL tool results, our company started the reparation of the most severe corrosion points located at P.K , this operation confirmed us that our result : coating defect location and the corrosion prediction. The graphs given in the annexe show the distribution of the corrosion and coating defect versus the distance of the pipe, and give an overview what we ve just explained. (they are better to evaluate rapidly the obtained results ) 6 CONCLUSION. There is no doubt that the best way to detect corrosion in pipeline is the inspection by intelligent tool, because the gas operator will know with accuracy the real condition of the pipe wall thickness and hence ensure a safe operation of its gas pipeline. On other hand if the gas operator has a non-piggable pipelines or he wants to save money the on line surveys ( GVDC CIPS techniques ) gives good results, providing, to get first of all, a large BANK of PC data, and an experiment technicians. 7 - REFERENCES 1. DR. J.M. Leeds A critical review of the techniques used to delineate pipeline coating defects as a precursor to refurbishment. 2. DR. J.M. Leeds The DC voltage gradient method for accurate delineation of coating defects on buried pipelines UK Corrosion W.G.Von Baeckmane (1973) Measurement and importance of the Off potential in applying cathodic protection to pipeline 12 th WGC NICE W.G.Von Baeckmane Taschenbuch fur den kathodischen korrsionsschutz. 5. C.Corradetti, E.Bini and D.Gentile Results of IN SITU coating integrity surveys as routine control on new gas lines impact on gas line quality, design aspects and organization of the work. 11
12 8 - ANNEXES 12
13 3 25 Potential On Off Sample N 1 Potential ON Potential Off Threshold protection Potential [ mv ] ,2,3,4,5,6,7,8,9 1 1,1 1,2 1,3 1,4 Distance [ Km ] IR % IR % IR % 2 1,2,3,4,5,6,7,8,9 1 1,1 1,2 1,3 1, Distance [ Km ] Corrosion points 3 % Corrosion depth Corrosion points,2,3,4,5,6,7,8,9 1 1,1 1,2 1,3 1,4 distance [ Km ] 13
14 Potential On-Off Sample N 2 Potential [ -mv ] Potential On Potential Off Threshold protection 4,425 4,525 4,625 4,725 4,825 4,925 5,25 5,125 5,225 distance [ Km ] 12 1 VOn-VOff VOn-VOff Voltage Gradient [ - mv ] , ,525 4,625 4,725 4,825 4,925 5,25 5,125 5, Distance [ Km ] % Corrosion depth Corrosion points Corrosion points 4,425 4,525 4,625 4,725 4,825 4,925 5,25 5,125 5,225 distance [ Km ] 14
15 Potentila On-Off Sample N Potential On Potentiel Off Threshold protection 1 Potential [ -mv ] ,2 8,4 8,6 8,8 9 9,2 Distance [ Km ] IR % 25 2 IR % 15 IR % ,2 8,4 8,6 8,8 9 9,2-5 Distance [ Km ] Corrosion point % Corrosion depth Corrosion point 8, 8,2 8,4 8,6 8,8 9, 9,2 Distance [ Km ] 15
16 Contrôle De Canalisation Algeria 2" VECTRA MFL Inspection ( 157 ) Sonelgaz_Relazine to Sig (76.883km) Informations D'Ellipsoïde: WGS84 Date of Inspection: 25 September 1999 Méridien Central : 3 E Nombre De Zone: 31 N BJ Process and Pipeline Services Ltd. BJ Chainag e (m) Position Horloge Épais. Paroi (mm) Long. (mm) Larg. (mm) Prof. Max (%) Loc. 4, : EXT. 4, : EXT. 4, : EXT. 4, : EXT. 4, : EXT. 4, : EXT. 4, : EXT. 4, : EXT. 8, : EXT. 8, : EXT. 8, : EXT. 8, : EXT. 8, : EXT. 8, : EXT. Longitude / Latitude (DMS) N: ' " E: 32 ' " N: ' " E: 32 ' " N: ' " E: 32 ' " N: ' " E: 32 ' " N: ' " E: 32 ' " N: ' " E: 32 ' " N: ' " E: 32 ' " N: ' " E: 32 ' " N: ' 6.74 " E: 29 ' " N: ' 6.74 " E: 29 ' " N: ' 6.74 " E: 29 ' 2.18 " N: ' 6.74 " E: 29 ' 2.18 " N: ' 6.74 " E: 29 ' " N: ' 6.74 " E: 29 ' " Sample of a part of the inspection s results 16
Auditing of Cathodic Protection Systems and Anticorrosion Coating Conservation Status in Oil and Gas Pipelines (CIPS DCVG Surveys)
Auditing of Cathodic Protection Systems and Anticorrosion Coating Conservation Status in Oil and Gas Pipelines (CIPS DCVG Surveys) Engineering Company in Duct Integrity We know what we do... 2007 Página
More informationManagement System. Updated Document Review
Pipeline Integrity Management System Updated Document Review 2Q 2011 POMA Subcommittee Meeting Introduction PIMS = A comprehensive, systematic and integrated management program Objectives: Provide information
More informationPipeline Integrity: Combining Coating Integrity and Cathodic Protection Surveys
Pipeline Integrity: Combining Coating Integrity and Cathodic Protection Surveys ABSTRACT Elizabeth Nicholson B. Eng, NACE CP-3 Cathodic Protection Technologist, Corrosion Technician General Manager Cathodic
More informationAN INNOVATIVE APPROACH TO MANAGING THE INTEGRITY OF OIL AND GAS PIPELINES: PIPELINE INTEGRITY MANAGEMENT SYSTEM
Petroleum & Coal ISSN 1337-7027 Available online at www.vurup.sk/petroleum-coal Petroleum & Coal 54 (1) 1-8, 2012 AN INNOVATIVE APPROACH TO MANAGING THE INTEGRITY OF OIL AND GAS PIPELINES: PIPELINE INTEGRITY
More informationPPTS OPERATOR ADVISORY: THE INS AND OUTS OF CORROSION RELEASES
PPTS OPERATOR ADVISORY: THE INS AND OUTS OF CORROSION RELEASES Executive Summary This Advisory reviews corrosion releases in hazardous liquids pipeline facilities and along the pipeline right-of-way (ROW).
More informationNEW TECHNOLOGIES OF SPETSNEFTEGAZ MAGNETIC IN-LINE INSPECTION
NEW TECHNOLOGIES OF SPETSNEFTEGAZ MAGNETIC IN-LINE INSPECTION By: Dr.V.A. Kanaykin, Dr.B.V.Patramanskiy, Dr.V.E.Loskutov Spetsneftegaz NPO JSC, Russia For the period from 1991 to 1995, Spetsneftegaz scientists
More informationDevelopment of Integrity Management Strategies for Pipelines. Presenter: Cheryl Argent
Development of Integrity Management Strategies for Pipelines Ivan Cvitanovic [1], Uwe Thuenemann [2], Cheryl Argent [3], Chris Lyons [3], Andrew Wilde [3], [1].JADRANSKI NAFTOVOD (JANAF) Plc, Croatia.
More informationRefining Corrosion Technologist NACE-RCT-001
Refining Corrosion Technologist NACE-RCT-001 NACE Cathodic Protection Specialist (CP 4) Essay Exam Exam Preparation Guide March 2018 Copyright 2016 by NACE International Institute. All rights reserved.
More informationRefining Corrosion Technologist NACE-RCT-001
Refining Corrosion Technologist NACE-RCT-001 NACE Cathodic Protection Technologist (CP3) Written Exam Exam Preparation Guide March 2018 Copyright 2016 by NACE International Institute. All rights reserved.
More informationIntroduction to Cathodic Protection
Introduction to Cathodic Protection Course No: T02-004 Credit: 2 PDH J. Paul Guyer, P.E., R.A., Fellow ASCE, Fellow AEI Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY
More informationDates of Innovation Development: January, 2014 to July 2015 Web site: Summary Description: Cathodic Protection
2017 Award Nomination Title of Innovation: Ultrasound Cathodic Protection Test Station Nominee(s) Eugene (Gene) B. Silverman PhD, Berkeley Springs Instruments LLC Category: Cathodic Protection Coatings
More informationPulsed Eddy Current Testing (PECT) Inspection Technique
Introduction Pulsed Eddy Current Testing (PECT) is an inspection technique used for corrosion under insulation (CUI) screening on carbon steel structures as pipes, vessels, tanks and spherical tank legs
More informationGas Transmission and Distribution Piping Systems
ASME B31.8-2007 (Revision of ASME B31.8-2003) Gas Transmission and Distribution Piping Systems ASME Code for Pressure Piping, B31 AN AMERICAN NATIONAL STANDARD Three Park Avenue New York, NY 10016 CONTENTS
More informationPart 192 Corrosion Enforcement Guidance
Part 192 Corrosion Enforcement Introduction The materials contained in this document consist of guidance, techniques, procedures and other information for internal use by the PHMSA pipeline safety enforcement
More informationPipeline Condition Assessment. The Essential Engineering Step in the Asset Management Process
Pipeline Condition Assessment. The Essential Engineering Step in the Asset Management Process Tom Sangster. Principal, Jason Consultants Group, Geneva, Switzerland Synopsis Condition assessment is a critical
More informationNational Academy of Sciences
National Academy of Sciences Transportation Research Board Study of Pipeline Transportation of Diluted Bitumen PHMSA Regulatory Authority and Keystone XL Pipeline October 23, 2012-1 - Topics for Briefing
More informationCapabilities of MFL Inspection in DUPLEX Steel Pipelines
Capabilities of MFL Inspection in DUPLEX Steel Pipelines Hendrik Aue and Werner Thale ROSEN Technology and Research Center Germany Am Seitenkanal 8, 49811 Lingen, Germany Age E. Pedersen and Samuel Moe
More informationDEUTSCHE NORM December 2000
DEUTSCHE NORM December 2000 Tape and shrinkable materials for the corrosion protection of buried or underwater pipelines without cathodic protection for use at operating temperatures up to 50 C { 30672
More informationInspection of water injection pipelines and future needs. By: Mikael Georgson and Roger Hunsbedt. Statoil ASA
Inspection of water injection pipelines and future needs By: Mikael Georgson and Roger Hunsbedt Statoil ASA Abstract Statoil ASA has recently inspected several water injection pipelines that have shown
More informationThe Importance of Pipeline Cleaning: Risks, Gains, Benefits, Peace of Mind
The Importance of Pipeline Cleaning: Risks, Gains, Benefits, Peace of Mind André van der Werff Brenntag Nederland B.V. Netherlands 1. Increased pipeline failures Time, deterioration and corrosion of the
More informationmaximize productivity in your operations
mids tream Pipeline maximize productivity in your operations bhge.com pipeline Maintaining top operational efficiency in your pipelines doesn t just protect the value of your assets it is directly linked
More informationNATIONAL ENERGY BOARD PIPELINE PERFORMANCE MEASURES REPORTING GUIDANCE
NATIONAL ENERGY BOARD PIPELINE PERFORMANCE MEASURES REPORTING GUIDANCE Amended November 2014 PIPELINE PERFORMANCE MEASURES - OVERVIEW Introduction The National Energy Board (Board) took action in March
More informationWHY OIL COMPANIES MUST GRASP THE CORROSION ISSUE Richard Pike
WHY OIL COMPANIES MUST GRASP THE CORROSION ISSUE Richard Pike Corrosion may seem an unexciting subject, but international and state oil companies now need to place much higher priority on both the technology
More informationNumerical simulation of the cathodic protection of pipeline networks under various stray current interferences
Numerical simulation of the cathodic protection of pipeline networks under various stray current interferences L. Bortels & J. Deconinck Department of Electrical Engineering (TW-ETEC), Vrije Universiteit
More informationA New Monitoring Method for Evaluation Cathodically Protected Large Diameterprestressed Concrete Cylinder Pipe Using Real Size Coupons
A New Monitoring Method for Evaluation Cathodically Protected Large Diameterprestressed Concrete Cylinder Pipe Using Real Size Coupons Dr.Abdulla Al Almughery 1, Dr. Sadek.S. RejeibI, 2 Dr. Ezzddin.R.
More informationFast Corrosion Screening Technique Saturation Low Frequency Eddy Current
Summary The inspection of ferromagnetic and non-ferromagnetic material components is an attractive and efficient method due to its fast screening of large areas with low surface preparations. Already qualified
More informationADVANCED POSSIBILITIES FOR CORROSION INSPECTION OF GAS PIPELINES USING EMAT TECHNOLOGY
ADVANCED POSSIBILITIES FOR CORROSION INSPECTION OF GAS PIPELINES USING EMAT TECHNOLOGY H. WILLEMS 1, B. JASKOLLA 1, T. SICKINGER 1, O.A. BARBIAN 1, F. NIESE 2 (1) NDT Systems & Services, Stutensee, Germany
More informationPermanent Buried Reference Electrodes: Technical Note on Significant Inaccuracies and Medium Term Trials
Permanent Buried Reference Electrodes: Technical Note on Significant Inaccuracies and Medium Term Trials Brian S Wyatt Eur Ing, BSc (Hons), CEng, MIMMM, FICorr, FCS Corrosion Control, 3 Ivy Court, Acton
More informationDetecting metal loss and pipeline wall thinning with a combination of Ultrasonic Testing (UT) and Magnetic Flux Leakage (MFL)
Detecting metal loss and pipeline wall thinning with a combination of Ultrasonic Testing (UT) and Magnetic Flux Leakage (MFL) Wolfgang Krieg ROSEN Swiss AG Abstract In-line inspections with Ultrasonic
More informationPipeline Condition Assessment Technology
Pipeline Condition Assessment Technology Presented by: Paul Schumi Collection Systems Fall Seminar December 1, 2016 water Asset Management Pipeline Assessment Hydrant Assessment Valve Assessment Leak Detection
More information195LiquidsCatalog.
195LiquidsCatalog www.energyu.org www.midwestenergy.org 195 Abnormal Operating Conditions... 3 195-0060 General Abnormal Operating Conditions (CT60)... 3 195-0000 Documentation & Reporting... 3 195-0403
More informationPIPELINE INTEGRITY MANAGEMENT SYSTEM: A COLOMBIAN MODEL FOR DEVELOPING COUNTRIES
PIPELINE INTEGRITY MANAGEMENT SYSTEM: A COLOMBIAN MODEL FOR DEVELOPING COUNTRIES Autors Hernando Gutiérrez de Piñeres Operations Vice President Promigas Marianella Ojeda Pipepline Integrity Coordinator
More informationWhat s Next Establishing Reassessment Intervals
What s Next Establishing Reassessment Intervals NACE ECDA Seminar Houston January 26- January 28 2009 Kevin C. Garrity, P.E. DNV Topics Covered Focus is ECDA - Reassessment Methodology, - Corrosion Growth
More informationUKOPA Recommendations for the Inspection and Maintenance of Buried Pipelines
UKOPA Recommendations for the Inspection and Maintenance of Buried Pipelines Reference: UKOPA/13/028 Disclaimer This document is protected by copyright and may not be reproduced in whole or in part by
More informationAn Introduction to Cathodic Protection
An Introduction to Cathodic Protection G u y e r P a r t n e r s 4 4 2 4 0 C l u b h o u s e D r i v e E l M a c e r o, C A 9 5 6 1 8 ( 5 3 0 ) 7 7 5 8-6 6 3 7 j p g u y e r @ p a c b e l l. n e t J. Paul
More informationINSULATED JOINTS. Monolithic Joints for Electrically Isolating Pipelines
INSULATED JOINTS Monolithic Joints for Electrically Isolating Pipelines INSULATED JOINTS TUBE TURNS INSULATED JOINTS are a pre-fabricated, non-separable, union used to isolate specific sections of pipelines
More informationCalScan TM EP Executive Summary. In-Line Inspection. Prepared for: SEICO Date issued: October 8, 2009 PII reference number:
CalScan TM EP Executive In-Line Inspection Prepared for: Date issued: October 8, 2009 PII reference number: 110357 CalScan TM EP - High Resolution Geometry Inspection In 2002, GE Oil & Gas began development
More informationIntroduction. Jeremy Hailey, P.E.
Introduction Jeremy Hailey, P.E. Engineer with 16 years experience Started NW 10 years ago Focus on corrosion control system designs, troubleshooting, and some installation work Conduct training seminars
More informationULTRASONIC IN-LINE INSPECTION: HIGH RESOLUTION CRACK DETECTION FOR PIPELINES USING A NEW GENERATION OF TOOLS
ULTRASONIC IN-LINE INSPECTION: HIGH RESOLUTION CRACK DETECTION FOR PIPELINES USING A NEW GENERATION OF TOOLS A. Barbian 1, M. Beller 1, K. Reber 1, N. Uzelac 2, H. Willems 1 1 NDT Systems & Services AG;
More informationIntegrity Management Software Solution Managing your daily activities.
Integrity Management Software Solution Managing your daily activities. S. Ruik Beyhaut Product Management ROSEN Integrity Solutions GmbH Lingen, Germany Contents Why does the industry need Asset Integrity
More informationBSR GPTC Z TR x GM Referenced Standards Page 1 of 12
Page 1 of 12 PURPOSE: Review existing GM and modify as appropriate in light of Amendment 192 119. Regulations Section 192.620 To address increased risk of a maximum allowable operating pressure based on
More informationPOLYGUARD RD-6 A FAIL SAFE PIPELINE COATING SYSTEM FOR REHABILITATION OR GIRTH WELDS ON CATHODICALLY PROTECTED PIPELINES
POLYGUARD RD-6 A FAIL SAFE PIPELINE COATING SYSTEM FOR REHABILITATION OR GIRTH WELDS ON CATHODICALLY PROTECTED PIPELINES A large percent of corrosion failures on cathodically protected structures are associated
More informationa: potential difference before direct current is applied b: potential difference after the application of current
CATHODIC PROTECTION Cathodic protection is a proven corrosion control method for protection of underground and undersea metallic structures, such as oil and gas pipelines, cables, utility lines and structural
More informationImplementing and Managing a Large Water Utility s Underground Corrosion-Control Program
Implementing and Managing a Large Water Utility s Underground Corrosion-Control Program Jeff Schramuk NACE CP Specialist #7695 630-235-1559 www.cpsolutionsinc.net Danny J. Klopfer, P.E. Infrastructure
More informationDynamic Stray Current Interference Testing And Mitigation Design For A 90-Inch Water Main
Dynamic Stray Current Interference Testing And Mitigation Design For A 90-Inch Water Main Authors: Rogelio de las Casas, Ron Turner, Kristi Roe; EN Engineering This paper discusses two sections of pipeline
More informationCondition Assessment of Pipeline Systems Within Power Generating Plants
Condition Assessment of Pipeline Systems Within Power Generating Plants Condition Assessment of Pipeline Systems within Power Generating Plants Many cities depend on safe, reliable power delivered from
More informationThere are many technologies available for
Engineering Technologies for Pipeline Asset Management Bryon L. Livingston, Ahmad Habibian, and Dan Kugler There are many technologies available for managing the condition of underground infrastructure,
More informationPipeline Oil & Gas Equipment, Inc.
Pipeline Oil & Gas Equipment, Inc. Web Page: www.pipe-equip.com - E-Mail: info@pipe-equip.com Tel: (936) 321 6963 - Fax: (936) 273 5150 WHERE Quality IS OUR, HIGHEST PRIORITY At Pipeline Oil & Gas Equipment,
More informationFLOW EFFICIENCY + CORROSION CONTROL AN ARGUMENT FOR INTERNAL PIPE COATINGS
FLOW EFFICIENCY + CORROSION CONTROL AN ARGUMENT FOR INTERNAL PIPE COATINGS The purpose of flow efficiency coatings How coatings affect pipeline pumping efficiency Flow efficiency coatings are meant to
More informationGrowth. Network grew steadily until early 1980s. Pipeline diameter increased. Increase in volume and amount of volume
Pipelines History Originally used to feed other modes of transportation 19 th Century Pennsylvania Railroad started the development of pipelines in oil fields. Sold out to Standard Oil Company Established
More informationPipelineCompass : Pipeline Corrosion Modeling, Prediction, Assessment & Solutions Version 9.17
Page 1 of 7 Advisory Consultancy Training Expert Witness FA Diagnosis Design Review Corrosion Test Inspection Coatings + More >>> PipelineCompass : Pipeline Corrosion Modeling, Prediction, Assessment &
More informationI. COMPARSION OF CORROSION MONITORING SYSTEMS IN THE OIL AND GAS INDUSTRY
Quality on the Move! Corporate Headquarters: 2449 West Park Avenue P.O. Box 1690 Gray, LA 70359 www.nvindt.com T: 1-877-638-6841 F: 985-876-9355 info@nvindt.com I. COMPARSION OF CORROSION MONITORING SYSTEMS
More informationL505 VISUAL LEVEL INDICATOR. Dip-Tape Visual Level Indicator INSTALLATION AND OPERATIONS MANUAL
L505 VISUAL LEVEL INDICATOR INSTALLATION AND OPERATIONS MANUAL Dip-Tape Visual Level Indicator READ THIS MANUAL PRIOR TO INSTALLATION This manual provides information on the L505 Dip-Tape Visual Level
More informationVALLEY LATERAL PROJECT. RESOURCE REPORT 11 Reliability and Safety. FERC Docket No. CP
VALLEY LATERAL PROJECT RESOURCE REPORT 11 Reliability and Safety FERC Docket No. CP16- -000 November 2015 Section TABLE OF CONTENTS Page 11.0 RELIABILITY AND SAFETY... 11-1 11.1 NATURAL GAS PIPELINE INDUSTRY
More informationPolymer Linings for Restoration & Corrosion Protection of Steel Surfaces: Crude Oil Storage Tank Repair and Reline in New Zealand
Polymer Linings for Restoration & Corrosion Protection of Steel Surfaces: Crude Oil Storage Tank Repair and Reline in New Zealand ~ 2009 SSPC Corrosion Conference ~ By: Greg Severyn, Sauereisen Inc., Greg
More informationCondensed Study Guide
192-0401 Corrosion Reactions This module will discuss a variety of corrosion types. Each type involves either a chemical reaction or an electrochemical reaction. Chemical Reaction Chemicals in the environment
More informationGas Transmission and Distribution Piping Systems
ASME B31.8-2014 (Revision of ASME B31.8-2012) Gas Transmission and Distribution Piping Systems ASME Code for Pressure Piping, B31 AN INTERNATIONAL PIPING CODE ASME B31.8-2014 (Revision of ASME B31.8-2012)
More informationMitigation of Internal Corrosion in Oil Effluent Pipeline Systems
BEST MANAGEMENT PRACTICES Mitigation of Internal Corrosion in Oil Effluent Pipeline Systems 2009-0012 The Canadian Association of Petroleum Producers (CAPP) represents 130 companies that explore for, develop
More informationRemoving the Barriers to Efficient Water Leakage Management
Removing the Barriers to Efficient Water Leakage Management by Ivan Nazzaretto Executive summary When water leakage is addressed as a business issue, many organizations make the mistake of limiting their
More informationQuality and Reliability Responsible Commitment to Customers
Quality and Reliability Responsible Commitment to Customers The fundamental principle of Monozukuri (manufacturing competitiveness) lies in Komatsu's commitment to quality and reliability in order to provide
More informationComparison of MEC and MFL Technique for Tank Floor Inspection
This document describes the difference between the MEC (Magnetic Eddy Current) technique and MFL (Magnetic Flux Leakage) technique, predominantly for the tank floor inspection application. Principle of
More informationIN-LINE INSPECTION OF PIPES USING CORROSION RESISTANT ALLOYS (CRA) M.Sc. Johannes Keuter PPSA Seminar Aberdeen 19-Nov-2014
IN-LINE INSPECTION OF PIPES USING CORROSION RESISTANT ALLOYS (CRA) M.Sc. Johannes Keuter PPSA Seminar Aberdeen 19-Nov-2014 CONTENT 1. Challenge 2. Technical Solution 3. Summary Slide 2 CHALLENGE Definition
More informationGIS-enabled ILI Repair Prioritization and Follow-Up. An integrated workflow from the submission of the Final Report to the Validation of Dig Results.
GIS-enabled ILI Repair Prioritization and Follow-Up An integrated workflow from the submission of the Final Report to the Validation of Dig Results. ROSEN Integrity Solutions GmbH Markus Brors 24-October-2011
More informationThe Pipelines Regulations, 2000
PIPELINES, 2000 P-12.1 REG 1 1 The Pipelines Regulations, 2000 being Chapter P-12.1 Reg 1 (effective April 1, 2000) as amended by the Statutes of Saskatchewan, 2014, c.21; and by Saskatchewan Regulations
More informationCCPS ASIA PACIFIC REGIONAL MEET ON PROCESS SAFETY
8 th CCPS ASIA PACIFIC REGIONAL MEET ON PROCESS SAFETY Chennai 22 th September 2014 Hirak Dutta ED-OISD Introduction Mode Of Transport Thru Pipeline Safe & Environment friendly and economic mode of transport
More informationCORROSION ENVIRONMENT PROBE INTERNAL CHECK F E B B C = MEASURE C D = REFERENCE D E = CHECK AC DRIVE CARBON STEEL DUCTILE IRON
Measuring Corrosion and Corrosion Control (CC) on Water Pipe Materials Graham E.C. Bell, Ph.D., P.E. Water/Wastewater Forum Corrosion: Why Should I Be Concerned? Corrosion 2010/San Antonio CC in the Water
More informationF Series Flow Meter F300. User Manual
F Series Flow Meter F300 User Manual Contents 1. F300 Series Flow Meter ------------------------------------- 2 1.1 F300 Series Flow Meter Structure Drawing ---------------------------- 2 1.2 Introduction
More informationProtective Coatings for Underground Utility Concrete Structures. By: John E. Davis Inside Sales & Marketing Specialist: Sauereisen, Inc.
Protective Coatings for Underground Utility Concrete Structures By: John E. Davis Inside Sales & Marketing Specialist: Sauereisen, Inc. As our cities and municipalities grow older, the utility and wastewater
More informationPIPE USERS GROUP (PUG) July 11, Michelle Beason, PE Regional Manager National Plant Services, Inc., a Carylon Company
PIPE USERS GROUP (PUG) July 11, 2017 Michelle Beason, PE Regional Manager National Plant Services, Inc., a Carylon Company NATIONAL PLANT SERVICES, INC. New Service yard in Hayward, CA. Headquarters in
More informationPerformance audit report. New Zealand Transport Agency: Information and planning for maintaining and renewing the state highway network
Performance audit report New Zealand Transport Agency: Information and planning for maintaining and renewing the state highway network Office of the Auditor-General PO Box 3928, Wellington 6140 Telephone:
More information192GasCatalog.
192GasCatalog www.energyu.org www.midwestenergy.org 192-Abnormal Operating Conditions... 4 192-0101 Characteristics and Hazards of Natural Gas... 4 192-0201 Gas Detection and Alarm System Maintenance...
More informationAssessment Methods For Large Diameter Water & Sewer Pressure Pipelines
Assessment Methods For Large Diameter Water & Sewer Pressure Pipelines Procrastinator s Workshop Thursday, December 12, 2013 Presented by: Michael J. Livermore Midwest Regional Manager Solutions for Sustainable
More informationJames M. Pleasants Success Story
James M. Pleasants Success Story CUSTOMER PROFILE James M. Pleasants Company (JMP) was founded in 1958 as a stocking sales representative for Bell & Gossett products. The company has grown as an employee-owned
More informationTransmission Pipeline Opportunities. Advancing Project Development in India through Public Private Partnerships
Transmission Pipeline Opportunities Advancing Project Development in India through Public Private Partnerships 22 23 February, 2007 Pipeline Maintenance and Repair: Agenda Methane Losses from Pipeline
More informationPipeline Integrity. QuestIntegrity.com CHALLENGE CONVENTION
Pipeline Integrity Solutions Pipeline Integrity Management Services (PIMS) InVista Ultrasonic In-Line Inspection Technology Engineering Assessment and Consulting QuestIntegrity.com CHALLENGE CONVENTION
More informationDetailed Requirements Document (DRD) Rail Engineering Advanced Technician Level 4 Electrification Knowledge & Skills Content
Detailed Requirements Document (DRD) Rail Engineering Advanced Technician Level 4 Electrification Knowledge & Skills Content Purpose The purpose of this Detailed Requirements Document (DRD) is to provide
More informationAvailable online at ScienceDirect. Procedia Engineering 86 (2014 )
Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 86 (2014 ) 539 545 1st International Conference on Structural Integrity, ICONS-2014 Optimization of Integrity Testing of Piping
More informationCATHODIC PROTECTION OF THE KRK BRIDGE
CATHODIC PROTECTION OF THE KRK BRIDGE D. Sekulic, J. Bleiziffer, J. Beslac, M. Ille Summary To extend service life of the Krk Bridge, as one of the most important infrastructure reinforced concrete objects
More informationINSTITUTE OF INTEGRATED ELECTRICAL ENGINEERS OF THE PHILIPPINES, INC. (IIEE-ERCSA) First IIEE Accredited Foreign Chapter (Charter
INSTITUTE OF INTEGRATED ELECTRICAL ENGINEERS OF THE PHILIPPINES, INC. () www.iiee-ercsa.org First IIEE Accredited Foreign Chapter (Charter No. 62) Most Outstanding Chapter Overseas for the year 1998, 1999,
More informationPipeline safety regulations apply to all pipelines that transport either flammable gas or hazardous liquids where the product affects interstate
1 Pipeline safety regulations apply to all pipelines that transport either flammable gas or hazardous liquids where the product affects interstate commerce. For example, the piping within a refinery or
More informationCEA Energy 101: The Association of Oil Pipe Lines (AOPL) An Overview of the liquids pipeline industry, policy, and how it impacts consumers
CEA Energy 101: The Association of Oil Pipe Lines (AOPL) An Overview of the liquids pipeline industry, policy, and how it impacts consumers Crude oil Liquid Pipeline Products Refined petroleum products
More informationRADIOGRAPHIC EVALUATION OF CORROSION AND DEPOSITS: IAEA CO-ORDINATED RESEARCH PROJECT ON LARGE DIAMETER STEEL PIPES
RADIOGRAPHIC EVALUATION OF CORROSION AND DEPOSITS: IAEA CO-ORDINATED RESEARCH PROJECT ON LARGE DIAMETER STEEL PIPES U. Zscherpel 1, I. Einav 2, S. Infanzon 3 and J. Zirnhelt 4 1 BAM, Berlin, Germany; 2
More informationPROCESSING COMBINED LASER, SONAR AND HD IMAGING FOR BETTER EVALUATION DECISIONS
North American Society for Trenchless Technology (NASTT) No-Dig Show 2011 Washington, D.C. March 27-31, 2011 Paper F-3-05 PROCESSING COMBINED LASER, SONAR AND HD IMAGING FOR BETTER EVALUATION DECISIONS
More information6 th Pipeline Technology Conference 2011
6 th Pipeline Technology Conference 2011 Rehabilitation of 32"Gas Pipeline in the most Cost Effective way- A Case study Mr. K. P. Sharma, PMP Presenter Mr. K. P. Sharma, PMP Kuwait Oil Company, Kuwait
More informationNOTE ON PERFORMANCE TESTING
NOTE ON PERFORMANCE TESTING Performance Profile Sheet(s) are included in a format that can be easily photo cop ied for each trainee. Performance tests are designed to mea sure competency in the tasks taught
More informationJemena Gas Networks (NSW) Ltd
Jemena Gas Networks (NSW) Ltd 2015-20 Access Arrangement Information Appendix 6.1 JGN 20 yr Asset Class Strategy Public 30 June 2014 JEMENA GAS NETWORKS 20 YEAR ASSET CLASS STRATEGIES APRIL 2014 Jemena
More informationDOUBLE WALLED PIPING SYSTEMS
DOUBLE WALLED PIPING SYSTEMS The design and construction of a double wall pipe is more complex than a single wall pipe because of the additional pipe, associated welds and tie in procedures. There are
More informationTABLE OF CONTENTS SELECTING AN ENCLOSURE COOLING SYSTEM MANUFACTURER. 3 7 QUALITIES TO LOOK FOR IN A MANUFACTURER Manufacturer Location..
TABLE OF CONTENTS SELECTING AN ENCLOSURE COOLING SYSTEM MANUFACTURER. 3 7 QUALITIES TO LOOK FOR IN A MANUFACTURER. 4 1. Manufacturer Location.. 4 2. Quality Standards 5 UL Ratings 5 NEMA Ratings 6 Performance
More information17/03/2017 CONTENTS. Real Cases Studies in the Region for Pipelines Inspection & Rehabilitation. Introduction CONTENTS. Introduction / Cont.
E M I R A T E S Real Cases Studies in the Region for Pipelines Inspection & Rehabilitation i) Introduction Dubia, UAE 14 March 2017 Trenchless Middle East Faiz Alelweet & Eng. Hamza Ali Maintenance Manager
More informationEuropean Standard En 1504
BS EN 1504 Products and Systems for the protection and repair of concrete structures Definitions, requirements, quality control and evaluation of conformity John Drewett Concrete Repairs Ltd 25% of the
More informationPART TWO. Pipeline Integrity Evaluation and Engineering Assessment
PART TWO Pipeline Integrity Evaluation and Engineering Assessment This page intentionally left blank CHAPTER ONE Introduction Contents Pipeline integrity management 136 High consequence area analysis 138
More informationRole of Corrosion & Field Joint Coating System Selection Criteria in Submarine Pipelines Integrity
Role of Corrosion & Field Joint Coating System Selection Criteria in Submarine Pipelines Integrity Nawin Singh McDermott International, Inc. 2014 McDermott International, Inc. All rights reserved. February
More informationCase Based Reasoning for Prestressed Concrete Cylinder Pipe Condition Assessment
Case Based Reasoning for Prestressed Concrete Cylinder Pipe Condition Assessment Nada M. Elbouri and Saleh M. Amaitik Operation and Maintenance Department, Building Maintenance Section, Man Made River
More informationStandard Recommended Practice. The Use of Coupons for Cathodic Protection Monitoring Applications
NACE Standard RP0104-2004 Item No. 21105 Standard Recommended Practice The Use of Coupons for Cathodic Protection Monitoring Applications This NACE International standard represents a consensus of those
More informationDesigned to reduce and eliminate pipeline damage associated with Water hammer Pressure spikes Line content velocity changes
NEW - JCM Surge Suppressor Simple to Install - Easy to Afford - Long Term Cost Savings Designed to reduce and eliminate pipeline damage associated with Water hammer Pressure spikes Line content velocity
More informationdeveloper.* The Independent Magazine for Software Professionals Automating Software Development Processes by Tim Kitchens
developer.* The Independent Magazine for Software Professionals Automating Software Development Processes by Tim Kitchens Automating repetitive procedures can provide real value to software development
More informationBitcoin Trader. ABN PO Box 455, Neutral Bay 2089
Bitcoin Trader ABN 92 610 960 051 1300 12 17 17 PO Box 455, Neutral Bay 2089 info@bitcointrader.org.au www.bitcointrader.org.au buy Cryptocurrency has created an entirely new asset class. There is no precedent
More informationCathodic Protection System in Oil & Gas Exploration Industry
An Intensive 5 Day Training Course Cathodic Protection System in Oil & Gas Exploration Industry 06-10 May 2018, Dubai 02-06 Dec 2018, Dubai 07-FEB-18 This course is Designed, Developed, and will be Delivered
More informationMulti-Zone Cathodic Protection Monitoring for Bridge Applications. Jamey Hilleary Elecsys Corporation 846 North Mart-Way Ct. Olathe, Kansas USA
Multi-Zone Cathodic Protection Monitoring for Bridge Applications Jamey Hilleary Elecsys Corporation 846 North Mart-Way Ct. Olathe, Kansas 66061 USA ABSTRACT The highway bridge infrastructure includes
More informationBend with wrinkles. Eliminate welding and X-RAY. Cigarette wrap isolated external corrosion pitting 68% wall loss.
Contact Gregg Crow Phone: 817-240-6434 Email: gcrow@myoilpatch.com Web: www.myoilpatch.com Elbow Repair Weld-O-Let Repair Eliminate welding and X-RAY Bend with wrinkles Cigarette wrap isolated external
More information