Constructing Networks
|
|
- Damon Henderson
- 5 years ago
- Views:
Transcription
1 Constructing Networks 1
2 Network Terms Project: Obtain a college degree (B.S.) Register 1 Attend class, study etc. 4 Years Receive diploma Event (Node) Activity (Arrow) Event (Node)
3 Activity Relationships
4 Activity Relationships 1 4
5 Activity Relationships A 1 B A & B can occur concurrently 5
6 Activity Relationships A must be done before C & D can begin A 1 4 C D B 6
7 Activity Relationships D A 1 4 C 7 B E B & C must be done before E can begin
8 Activity Relationships A must be done before C & D can begin A 1 4 C D B A & B can occur concurrently 8 E B & C must be done before E can begin
9 Dummy Activities Activities are defined often by beginning & ending events Example: Activity - Every activity must have unique pair of beginning & ending events Computer programs get confused Dummy activities maintain precedence Consume no time or resources 9
10 Dummy Activities Example 10
11 Incorrect 1- Dummy Activities - Example
12 Incorrect 1- Dummy Activities - Example Different activities; same designation 1
13 Dummy Activities Example Incorrect Correct : Dummy activity
14 Network Example You re a project manager for Bechtel. Construct the network. Activity Predecessors A -- B A C A D B E B F C G D 14 H E, F 1995 Corel Corp.
15 Network Solution 1 15
16 Network Solution 1 All networks start with 1 event. 16
17 Network Solution A 1 17
18 Network Solution A 1 Event 1 starts the project; Activity A, with no predecessors, comes from it. 18
19 Network Solution A 1 B 19
20 Network Solution A 1 B Activity B requires completion of A; arrow leaves Event. 0
21 Network Solution A 1 B C 4 1
22 Network Solution B A 1 C 4 Activity C requires completion of A; arrow leaves Event.
23 Network Solution B D 5 A 1 C 4
24 Network Solution B D 5 A 1 C 4 Activity D requires completion of B; arrow leaves Event. 4
25 Network Solution B D 5 1 A E C 4 6 5
26 Network Solution B D 5 1 A E C Activity E requires completion of B; arrow leaves Event.
27 Network Solution B D 5 1 A E C 4 F 6 7
28 Network Solution Activity F requires completion of C; B arrow leaves Event 4. A 1 D E 5 C 4 F 6 8
29 Network Solution In problem statement, Activity H requires B completion of E & F. A Therefore, E & F have 1 same ending event (Event 6). C 4 D F E 5 6 9
30 Network Solution B D 5 G 1 A E 7 C 4 F 6 0
31 Network Solution B D 5 G 1 A E 7 Activity G requires C completion of D; arrow leaves Event 5. 4 F 6 1
32 Network Solution B D 5 G 1 A E 7 C 4 F 6 H
33 Network Solution B D 5 G 1 A E 7 C Activity H requires completion of E & F; arrow leaves Event 6. 4 F 6 H
34 Network Solution B D 5 G 1 A E 7 Activity H ends C at Event 7 since a network has 1 ENDING event. 4 F 6 H 4
35 5 Critical Path Analysis
36 Critical Path Analysis Provides activity information Earliest (ES) & latest (LS) start Earliest (EF) & latest (LF) finish Slack (S): Allowable delay Identifies critical path Longest path in network Shortest time project can be completed Any delay on activities delays project Activities have 0 slack 6
37 Critical Path Analysis Example You re project manager for Cooper Homes. Draw the network. Find the ES, EF, LS, LF & critical path. Begin Event 7 Ending Event Description Activity Time (Wks) 1 Pour fdn. & frame Buy shrubs etc. 1- Roof - 4 Do interior work -4 4 Landscape -4 4
38 Network Solution 1 8
39 Network Solution Pour foundation & frame 1 6 wk. 9
40 Network Solution Pour foundation & frame 1 6 wk. wk. Buy shrubs etc. 40
41 Network Solution Pour foundation & frame 1 6 wk. Roof wk. wk. Buy shrubs etc. 41
42 Network Solution Pour foundation & frame 6 wk. 1 4 wk. Buy shrubs etc. Roof wk. Do interior work wk. 4
43 Network Solution Pour foundation & frame 6 wk. 1 4 wk. Buy shrubs etc. Roof wk. Do interior work wk. Landscape 4 wk. 4
44 Earliest Start & Finish Steps Begin at starting event & work forward ES = 0 for starting activities ES is earliest start EF = ES + Activity time EF is earliest finish ES = Maximum EF of all predecessors for non-starting activities 44
45 Activity 1- Earliest Start Solution 45
46 Activity 1- Earliest Start Solution Activity ES EF LS LF Slack
47 Activity 1- Earliest Start Solution Activity ES EF LS LF Slack For starting activities, ES =
48 Activity 1- Earliest Finish Solution Activity ES EF LS LF Slack EF = ES + Activity time
49 Activity 1- Earliest Start Solution Activity ES EF LS LF Slack For starting activities, ES =
50 Activity 1- Earliest Finish Solution Activity ES EF LS LF Slack EF = ES + Activity time
51 Activity - Earliest Start Solution Activity ES EF LS LF Slack For non-starting activities, ES = Max EF of all predecessors. 4
52 Activity - Earliest Finish Solution Activity ES EF LS LF Slack EF = ES + Activity time
53 Activity -4 Earliest Start Solution Activity ES EF LS LF Slack For non-starting activities, ES = Max EF of all predecessors. 4
54 Activity -4 Earliest Finish Solution Activity ES EF LS LF Slack EF = ES + Activity time
55 Activity -4 Earliest Start Solution Activity ES EF LS LF Slack For non-starting activities, ES = Max EF of all predecessors
56 Activity -4 Earliest Finish Solution Activity ES EF LS LF Slack EF = ES + Activity time
57 Latest Start & Finish Steps Begin at ending event & work backward LF = Maximum EF for ending activities LF is latest finish; EF is earliest finish LS = LF - Activity time LS is latest start LF = Minimum LS of all successors for non-ending activities 57
58 Activity -4 Latest Finish Solution 58
59 Activity -4 Latest Finish Solution Activity ES EF LS LF Slack For ending activities, LF = Maximum EF. 59
60 Activity -4 Latest Start Solution Activity ES EF LS LF Slack LS = LF- Activity time. 60
61 Activity -4 Latest Finish Solution Activity ES EF LS LF Slack For ending activities, LF = Maximum EF
62 Activity -4 Latest Start Solution Activity ES EF LS LF Slack LS = LF- Activity time
63 Activity - Latest Finish Solution Activity ES EF LS LF Slack For non-ending activities, LF = Min LS of all successors. 6
64 Activity - Latest Start Solution Activity ES EF LS LF Slack LS = LF- Activity time.
65 Activity 1- Latest Finish Solution Activity ES EF LS LF Slack For non-ending activities, LF = Min LS of all successors. 65
66 Activity 1- Latest Start Solution Activity ES EF LS LF Slack LS = LF- Activity time.
67 Activity 1- Latest Finish Solution Activity ES EF LS LF Slack For non-ending activities, LF = Min LS of all successors. 67
68 Activity 1- Latest Start Solution Activity ES EF LS LF Slack LS = LF- Activity time.
69 Slack Solution Activity ES EF LS LF Slack Slack = LF - EF = LS - ES.
70 Critical Path Solution Activity ES EF LS LF Slack Critical path has 0 slack: 1-, -, -4.
Developing a Project Plan
Chapter 6 Developing a Project Plan I had six honest serving men who taught men all I know : their names were what and how and why, and when and where and who. Rudyard Kipling Project Management 105 Figure
More informationProject Scope Management
Project Scope Management Work Breakdown Structure (WBS) Created in Planning Process -> Scope Area Benefits of Work Breakdown Structure Organizes and defines the total scope of the project Helps prevent
More informationIST 302 : Project Time Management
IST 302 : Project Time Management Developing quality schedules is important. 1 Schedule issues are the main reason for conflicts on projects There are five core project time management process groups.
More informationCambridge International AS & A Level Computer Science
Topic Support Guide Cambridge International AS & A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
More informationPlanning & Scheduling
Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1 Planning Successful Project Management depends on continues planning. The activities of Designers,
More informationArtificial Intelligence
Artificial Intelligence Combinatorial Optimization G. Guérard Department of Nouvelles Energies Ecole Supérieur d Ingénieurs Léonard de Vinci Lecture 4 Outline 1 2 Decisions about Resource Allocation Which
More informationCIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8
CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8 Project Scope -Definition A documented description of the project in terms of
More informationProject Management in Practice Fifth Edition
Project Management in Practice Fifth Edition Chapter 5 Scheduling the Project Copyright 2014 John Wiley & Sons, Inc. Introduction Project schedule is the project plan in an altered format It is a convenient
More informationProject Time Management
Project Time Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Adapted from Managing Information Technology Projects, Schwalbe Learning Objectives Define activities as the basis
More informationNetwork Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)
/11/16 Network Diagram 11//16 1 WORK BREAKDOWN STRUCTURE (WBS) A work breakdown structure is a key project deliverable that organizes the team's work into manageable sections. The Project Management Body
More informationEFFICIENCY OF CRITICAL PATH METHOD (CPM) AND PERT TECHNIQUE FOR YACHT CONSTRUCTION
International Journal of Mechanical Engineering and Technology (IJMET) Volume 9, Issue 11, November 2018, pp. 48 54, Article ID: IJMET_09_11_006 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=9&itype=11
More informationLuis R. Garcilaso March 13, Lecture #22. Service Processes & Systems Dept. of Mechanical Engineering - Engineering Mechanics
Lecture #22 Luis R. Garcilaso March 13, 2006 Graphs & Networks Subgraphs Graph coloring Activity networks Route problems Network flow Visibility graph problems Covering problems Project Management Service
More informationPMP Exam Preparation Course Project Time Management
Project Time Management 1 Project Time Management Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity duration Develop Schedule Control Schedule In some projects,
More informationConstruction Scheduling and Estimating
P.E. Civil Exam Review: Construction Scheduling and Estimating J.P. Mohsen Email: jpm@louisville.edu 2 Project Management What is a Project? Project unique, one-time operational activity or effort Examples
More informationScheduling. Adapted from John Musser
Scheduling Adapted from John Musser Today Network Fundamentals Gantt Charts PERT/CPM Techniques WBS Review Types: Process, product, hybrid Formats: Outline or graphical organization chart High-level WBS
More informationGlobal Project Management, LLC
Global Project Management, LLC 2250 Gause Boulevard, Suite 310 Slidell, Louisiana 70461 Tel: 985-781-9190 A Projectis a temporary endeavor undertaken to create a unique product, service, or result. Initiation
More informationProject Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:
Project Management Dr. Richard Jerz 1 Learning Objectives Describe or Explain: What are projects The role of the project manager Work breakdown structure Project management tools (Gantt, PERT, & CPM) The
More informationProject Management. Dr. Richard Jerz rjerz.com
Project Management Dr. Richard Jerz 1 2010 rjerz.com Learning Objectives Describe or Explain: What are projects The role of the project manager Work breakdown structure Project management tools (Gantt,
More information6 PROJECT TIME MANAGEMENT
CHAPTER 6 PROJECT TIME MANAGEMENT LEARNING OBJECTIVES After reading this chapter, you will be able to: Understand the importance of project schedules and good project time management Define activities
More informationEstimating and Scheduling
Estimating and Scheduling Practical Tips and Techniques for Construction Scott Feeney, CPE, LEED AP Q1stCM Ram Ramdass, PMP, PSP Turner Construction April 2018 Today s Discussion: Scheduling techniques
More informationIntroduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.
Project Scheduling ARCH 738: REAL ESTATE PROJECT MANAGEMENT Morgan State University Jason E. Charalambides, PhD, M.ASCE, AIA, ENV_SP (This material has been prepared for educational purposes) Introduction
More informationTime has the least. amount of flexibility; Schedule issues are the main reason for
PMBOK 5 Ed. DEI- Time has the least amount of flexibility; Schedule issues are the main reason for conflicts on projects, especially during the second half of projects The process required to manage timely
More informationWeek 5 Project Work Plan
Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304
More informationPDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05
PDM Precedence Diagramming Method (PDM) Part 1 Con E 441 P05 A. Four (4) possible relationships 1. Finish to Start (FS). Start to Start (SS) 3. 4. Start to Finish (SF) B. Plus combined relationships SS
More informationLecture- 10. Project Scheduling. Dronacharya College of Engineering
Lecture- 10 Project Scheduling Dronacharya College of Engineering Scheduling and Planning The majority of projects are 'completed' late, if at all. A project schedule is required to ensure that required
More informationFor the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.
For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com
More informationResearch Article Scheduling Methods for Food Resource Management under the Environment of Cloud
Advance Journal of Food Science and Technology 11(4): 281-285, 2016 DOI:10.19026/ajfst.11.2411 ISSN: 2042-4868; e-issn: 2042-4876 2016 Maxwell Scientific Publication Corp. Submitted: May 5, 2015 Accepted:
More informationPOLYTECHNIC OF NAMIBIA
... POLYTECHNIC OF NMII SCHOOL OF MNGEMENT SCIENCES DEPRTMENT OF MNGEMENT CHELOR OF USINESS DMINISTRTION PROJECT MNGEMENT 21D SUJECT CODE: PRM422S (UNDERGRDUTE) DTE: NOVEMER 2014 DURTION: 3 Hours MRKS:
More information1. are generally independent of the volume of units produced and sold. a. Fixed costs b. Variable costs c. Profits d.
Final Exam 61.252 Introduction to Management Sciences Instructor: G. V. Johnson December 17, 2002 1:30 p.m. to 3:30 p.m. Room 210-224 University Centre Seats 307-328 Paper No. 492 Model Building: Break-Even
More information12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish
International Campus Kish Sharif University of Technology Session#11 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,
More informationMBP1133 Project Management Framework Prepared by Dr Khairul Anuar
MBP1133 Project Management Framework Prepared by Dr Khairul Anuar L4 Project Time Management www.notes638.wordpress.com Content 1. Scheduling 2. Common Scheduling Techniques 3. PERT 4. Network Fundamentals
More informationOperations Management
17-1 Project Management Operations Management William J. Stevenson 8 th edition 17-2 Project Management CHAPTER 17 Project Management McGraw-Hill/Irwin Operations Management, Eighth Edition, by William
More informationExaminations for Semester I / 2014 Semester II
Programme BSc (Hons) Management BSc (Hons) Economics and Management Cohort BMANM/09/PT BMANM/L/12B/FT BMANG/12A/12B/FT BMANG/F/12B/FT BMANG/L/12A/FT BEM/12B/FT Examinations for 2014 2015 Semester I / 2014
More informationWeek 5 Project Work Plan
Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304
More informationSoftware Project Management
Software Project Management Dr. M.E. Fayad, Professor Computer Engineering Department College of Engineering, San José State University One Washington Square, San José, CA 95192-0180 E-mail: m.fayad@sjsu.edu
More informationWeek 5 Project Work Plan
Week 5 Project Work Plan 457.307 Construction Planning and Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304 호 Project
More informationScheduling Resources and Costs
Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used
More informationProject Management THE MANAGERIAL PROCESS
Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Lecture 4 Developing a Project Plan Activity on Node (AON) Copyright 2006 The McGraw-Hill Companies. All rights reserved.
More informationProject Time Management
Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use
More informationWeek 5 Project Work Plan
Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304
More informationHow to Strengthen Workers Management Relationship Using Network Techniques - A Case Study
ISSN: 2278 0211 (Online) How to Strengthen Workers Management Relationship Using Network Techniques - A Case Study Paramveer Singh Research Scholar, NIMS University, Shobha Nagar, Jaipur, Rajasthan, India
More informationTime Management PLANNING
Time Management 6.1 Plan Schedule Management: The process of establishing policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule # Schedule
More informationLecture- 11. Project Scheduling. Dronacharya College of Engineering
Lecture- 11 Project Scheduling Dronacharya College of Engineering Project Scheduling Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) Project Scheduling Both techniques (PERT and
More informationImagine this: If you create a hundred tasks and leave their default constraints
Chapter 6 Timing Is Everything In This Chapter Discovering how dependency links affect timing Reviewing the different kinds of dependency relationships Allowing for lag and lead time Creating dependency
More informationMnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Risk Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions
More informationThe Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
More informationChapter 3 Managing the Information Systems Project
Princess Noura University Computer Science and Information Faculty Information Systems Department IS321 Chapter 3 Managing the Information Systems Project Learning Objectives Discuss skills required to
More informationTeam Member Application
MnDOT Project Management Office Presents: Team Member Application Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
More informationProject Scheduling: Lagging, Crashing and Activity Networks
Project Scheduling: Lagging, Crashing and Activity Networks Chapter 10 Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-1 Lags in Precedence Relationships The logical relationship
More informationWork Analysis and Design
END 202 Work Analysis and Design Problem Solving Tools 1 Sibel ALUMUR ALEV January 2011 Methods engineering A technique for increasing the production per unit time or decreasing the cost per unit output
More informationPERT and CPM S K Mondal Chapter 5. Time (4) To Calculate ES. To Calculate LS 34, 32 = 34. ES = max ES + t ; ES + t = max 15, 21 = 21
PERT and CPM S K Mondal Chapter 5 A B C 2 3 4 D E 5 G 7 F 6 H Fulkerson's Rule Time (4) ES = The earliest start time for an activity. The assumption is that all predecessor activities are started at their
More informationENGINEERING MANAGEMENT (GE
بسم هللا الرحمن الرحيم ENGINEERING MANAGEMENT (GE 404) 1 L E C T U R E # 4 Scheduling and Bar Chart Contents Objectives of the present lecture Planning and Scheduling Activity and Event Scheduling Techniques
More informationModern Systems Analysis and Design Seventh Edition
Modern Systems Analysis and Design Seventh Edition Jeffrey A. Hoffer Joey F. George Joseph S. Valacich Managing the Information Systems Project Learning Objectives ü Explain the process of managing an
More informationMnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Impact Schedules Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
More informationProject Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management
Project Management Professional (PMP) Exam Prep Course 6 - Project Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com
More informationViews and Layouts for Program Management
MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted
More informationInformation Technology Project Management, Seventh Edition
Information Technology Project Management, Note: See the text itself for full citations. Understand the importance of project schedules and good project time management Discuss the process of planning
More informationTopic # 12. CIS Project Management: an overview
Topic # 12 CIS Project Management: an overview Project Planning Major Activities during Project Planning: 1) describing project scope, alternatives, and feasibility; 2) dividing the project into manageable
More informationMBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar. Lecture 6b Project Time Management - II
MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar Lecture 6b Project Time Management - II MBP1123 Scope, Time & Cost Management Prepared by Dr. Zohreh Content 1. Introduction
More informationPrinciples of Planning for IT Projects
Principles of Planning for IT Projects Introduction Building Timings Exercises Meals & refreshments Mobile Phones Part 1 Setting the Scene 1. Course Objectives 2. Where projects come from 3. What is a
More informationCHAPTER 1. Basic Concepts on Planning and Scheduling
CHAPTER 1 Basic Concepts on Planning and Scheduling Eugénio Oliveira Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the and ordering of activities as well
More informationManaging Complexity in the Face of Uncertainty
Effective Project Management: Traditional, Agile, Extreme Managing Complexity in the Face of Uncertainty After successful studying this chapter You should be able to: Use tools, templates, and processes
More informationTEXTS IN OPERATIONAL RESEARCH
TEXTS IN OPERATIONAL RESEARCH Aimed at final year undergraduates and masters students, this is a new series of texts covering core subjects in Operational Research in an accessible student-friendly format.
More informationSCHEDULING AND CONTROLLING PRODUCTION ACTIVITIES
SCHEDULING AND CONTROLLING PRODUCTION ACTIVITIES Al-Naimi Assistant Professor Industrial Engineering Branch Department of Production Engineering and Metallurgy University of Technology Baghdad - Iraq dr.mahmoudalnaimi@uotechnology.edu.iq
More informationEmbarking new Project
Embarking new Project Go to file, select new. This will open a screen for blank project click ok. You can now enter your project information viz. start date, finish date and also how would you like to
More informationUNCLASSIFIED AH R&pAaduced. by Ute ARMED SERVICES TECHNICAL INFORMATION AGENCY ARLINGTON HALL STATION ARLINGTON 12, VIRGINIA UNCLASSIFIED
UNCLASSIFIED AH 282 450 R&pAaduced by Ute ARMED SERVICES TECHNICAL INFORMATION AGENCY ARLINGTON HALL STATION ARLINGTON 12, VIRGINIA UNCLASSIFIED i NOTICE: When government or other drawings, sped - fications
More informationEstimating Project Schedule-Time and Cost
Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities
More informationGLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155
GLOSSARY AND INDEX Glossary Index iv 1996 Project Management Institute, 130 South State Road, Upper Darby, PA 19082 USA 155 156 NOTES GLOSSARY 1. Inclusions and Exclusions This glossary includes terms
More informationEast Central College
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationMGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1
MGT/437 Project Management Session #2 University of Phoenix 02/12/2004 Brian Smithson 02/12/2004 MGT/437 #2 -- Brian Smithson 1 Agenda Review/Questions Session content PMI project framework Project Knowledge
More informationCalculating and Using Float
Core Scheduling Papers: #5 Calculating and Using Float Origin of Float The concept of schedule float is the creation of the Critical Path Method (CPM) of scheduling. Before 1957 float only had one meaning
More informationPMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep
PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT PMP Exam Prep PROJECT SCHEDULE MANAGEMENT Page 223 Schedule Management Process : Contains 6 of the 49 total processes Plan Schedule Management Define
More informationCE2353-CONSTRUCTION PLANNING & SCHEDULING
CE2353-CONSTRUCTION PLANNING & SCHEDULING UNIT-1 CONSTRUCTION PLANNING 1. What is planning? 2. What is construction planning? 3. What are the objectives of planning? 4. What are the types of project plans?
More informationCalculating and Using Float
Core Scheduling Papers: #5 Calculating and Using Float Origin of Float The concept of schedule float is the creation of the Critical Path Method (CPM) of scheduling. Before 1957 float only had one meaning
More informationOrganization of Software Projects
Organization of Software Projects Why care about software project organization? A study shows that only 10% of projects were successful between 1998 and 2004 Delays in final product delivery Cost over-runs
More informationPROJECT TIME MANAGEMENT
PROJECT TIME MANAGEMENT 2020 Powered by POeT Solvers Limited SEQUENCE ACTIVITIES PLANNING MONITORING & CONTROLLING 6.1 Plan Schedule Mgt 6.7 Control Schedule 6.2 Define Activities 6.3 Sequence Activities
More informationProject Planning and Estimating DJ
Project Planning and Estimating DJ201 0807 Copyright ESI International August 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any
More informationKristin Fitzgerald Director, Global Project and Alliance Management, Merck & Co, Inc.
Kristin Fitzgerald Director, Global Project and Alliance Management, Merck & Co, Inc. Kris%n s Background BS Behavioral Neuroscience - Lehigh University MBA Monmouth University Merck Career PMP Certification
More informationTHE PMP EXAM PREP COURSE
THE PMP EXAM PREP COURSE Session 2 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falconppm.com Agenda 9:00 10:15 Practice the PMP Questions 10:15 10:30 Break 10:30
More informationThe recommended guided learning hours for this unit are 30 hours.
Unit 281 Project Management 2 Credit 4 Level 2 QCA accreditation number Rationale The aim of this unit is to enable candidates to understand the business environment within which new Projects are initiated.
More informationPrimavera P6 Exercise Worksheet
Primavera P6 Exercise Worksheet Revision 1.04 P6 Exercise Worksheet Introduction These exercises are for use in support of the Ten Six Consulting Primavera P6 Professional video training course. At the
More informationSuccessful Project Management
Successful Project Management Successful Project Management Thomas C. Belanger Contents About This Course How to Take This Course 1 The Project Management Process Project Selection and Evaluation Cost
More informationProject Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference
Project Planning & CPM Scheduling using MS Project APWA NorCal 2018 Annual Conference What is Planning? Planning: A determination of the what, how, where and by whom ; the tasks that need to be completed
More information: INDUSTRIAL MANAGEMENT & SAFETY COURSE CODE : 5001 COURSE CATEGORY : C PERIODS/WEEK : 4 PERIODS/SEMESTER : 52 CREDITS : 4
COURSE TITLE : INDUSTRIAL MANAGEMENT & SAFETY COURSE CODE : 5001 COURSE CATEGORY : C PERIODS/WEEK : 4 PERIODS/SEMESTER : 52 CREDITS : 4 TIME SCHEDULE MODULE TOPIC PERIODS 1 Principles of management Human
More informationOperations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management
Instant download and all chapters Test Bank Operations Management 11th Edition Jay Heizer, Barry Render https://testbankdata.com/download/test-bank-operations-management-11thedition-jay-heizer-barry-render/
More informationA New Networking Technique The Beeline Diagramming Method Seon-Gyoo Kim
2018 International Conference on Mechanical, Electronic and Information Technology (ICMEIT 2018) ISBN: 978-1-60595-548-3 A New Networking Technique The Beeline Diagramming Method Seon-Gyoo Kim Department
More informationProject Management Glossary of Terms
Project Management Glossary of Terms activity An element of project work that has an expected duration, and usually consumes cost and resources. Activities generally cover one or more tasks from a work
More informationThe E- project manager
The E- project manager Jayashree A. Mahajan 1, A.N.Paithane 2 1 (Department of Electronics and Telecommunication,Rajrshi Shahu College of Engineering, Pune, India) 2(Faculty, Dept of Electronics and Telecommunication,Rajrshi
More informationLinks, Lags and Ladders - the subtleties of overlapping tasks -
Core Scheduling Papers: #4 Links, Lags and Ladders Logic in a Precedence Network Precedence diagrams use boxes to represent the basic network elements - the task (or activity). Tasks have durations giving
More informationProject Time Management
Project Time Management Project Time Management Project Time Management includes the processes required to manage timely completion of the project. Plan schedule management The process of establishing
More informationGame Production: planning and risk
Game Production: planning and risk Fabiano Dalpiaz f.dalpiaz@uu.nl 1 Acknowledgment These slides are based on Chapter 11 of Chandler s book Chapter 7 of Project management: the managerial process, fifth
More informationA D-A1I CRITICAL PATH METHOD NETNORKS AND THEIR USE IN CLAIMS 1/2 ANALYSIS(U) FLORIDA UNIV GAINESVILLE M J PATTERSON usi FE 1984
A D-A1I59 234 CRITICAL PATH METHOD NETNORKS AND THEIR USE IN CLAIMS 1/2 ANALYSIS(U) FLORIDA UNIV GAINESVILLE M J PATTERSON usi FE 1984 N663i4-72-A-3029 FO51 N 134. J 11111120.4 12 11_L ICRCP ESLTO TS HR
More informationScheduling Concepts and MS. Project AZURITE PROJECT TRAINING AND CONSULTING PVT LTD (OPC) 2014
Scheduling Concepts and MS Project 1 About the Faculty- Venkat Annapragada Chem Engg from IIT KGP in 1993 Graduation Process Engineer Cement Industry from 1993 to 1997 IT Industry from 1997 to 2010 Corporate
More informationRetained Logic and Progress Override in Primavera P6
By Pat Hendricks TEPCO, LLC www.tepco.us Retained Logic and Progress Override The retained logic and progress override setting can drastically affect a schedule depending on which is used, so understanding
More informationResource-Constrained Multi-Project Scheduling with Resource Moving Time for Construction Projects in Vietnam
First International Conference on Construction In Developing Countries (ICCIDC I) Advancing and Integrating Construction Education, Research & Practice August 4-5, 2008, Karachi,, Pakistan Resource-Constrained
More informationProject Management PSGLE 122. Time and Resources
Project Management PSGLE 122 Time and Resources Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation
More informationChapter-7# Project Controlling and Scheduling
Chapter-7# Project Controlling and Scheduling 7.1 Meaning of Project Controlling (PC) PC is concerned with the optimum use of the total resources of an organization to meet the technical, cost and time
More informationTime Management: The Engineering Student Dilemma. Saylisse Dávila, Ph.D. Department of Industrial Engineering University of Puerto Rico at Mayagüez
Time Management: The Engineering Student Dilemma Saylisse Dávila, Ph.D. Department of Industrial Engineering University of Puerto Rico at Mayagüez Outline 1. Time Management Overview What? Why? How? 2.
More informationInformation Technology Audit & Cyber Security
Information Technology Audit & Cyber Security Managing Information System Projects Systems & Infrastructure Lifecycle Management Introduction Definitions INTRODUCTION Governance Roles and Responsibilities
More informationMICROSOFT PROJECT 2007 Level 1
Microsoft Project 2007 Level 1 Contents MICROSOFT PROJECT 2007 Level 1 WWP Learning and Development Page 1 Microsoft Project 2007 Level 1 Contents CONTENTS PREFACE - PROJECT MANAGEMENT BASICS... 5 Project
More information