Pre-Feasibility Report

Size: px
Start display at page:

Download "Pre-Feasibility Report"

Transcription

1 Pre-Feasibility Report OF PILIDHAR BAUXITE MINE (Mining Lease Area: ha) FOR Enhancement in Production capacity of Bauxite from 80,000 TPA to 3,00,755 TPA in addition of removal of Topsoil 8,800 TPA & OB/waste 2,22,080 TPA with Total Excavation 5,31,635 TPA At Survey No. 136/P(New)- 110/P (Old), Village Virpur, Taluka Kalyanpur, District Devbhumi Dwarka, Gujarat APPLICANT Dalmia Refractories Limited (Earlier M/s Shri Nataraj Ceramic & Chemical Industries Limited) Post Box No. 10, At & Po: Jam Khambhaliya, Dist: Devbhumi Dwarka, State: Gujarat 1

2 TABLE OF CONTENTS 1 EXECUTIVE SUMMARY The Project Proponent Project Background Brief Description of the Nature of the Project Size or Magnitude of Operation Project Description with Process Details Mineral Beneficiation Stacking of Mineral Rejects and disposal of Waste Landuse pattern Plantation in proposed year Availability of Water its Source and Energy/Power Requirement Fuel/Power Requirement Employment Generation (Direct and Indirect) due to the Project INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION The Project Proponent The Project Background Brief Description of the Nature of the Project Need for the project and its importance to the country and region Demand-Supply Gap Imports v/s Indigenous Production Export Possibility Domestic / Export Markets Employment Generation (Direct and Indirect) due to the Project Direct Indirect Project Description Type of Project including Interlinked and Interdependent Projects LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION, AND PROJECT BOUNDARY AND PROJECT SITE LAYOUT) WITH COORDINATES Alternate Sites Considered Size or Magnitude of Operation Project Description with Process Details Salient Features of Mode of Working

3 3.5.2 Drilling and Blasting Transport Mineral Processing Operations (if any) Production for the planned period Life of Mine Conceptual Mining Plan Mineral Exploration Ultimate Pit Limit Ultimate Pit extent Stacking of Mineral Rejects and disposal of Waste Plantation Extent of Mechanization Raw Materials Required along with Quantity likely Source, Marketing area of Final Product Mode of Transport of Raw Material & Finished Products Raw Materials Marketing Mode of Transport RESOURCE OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN THE PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED Availability of Water its Source and Energy/Power Requirement Water Fuel/Power Requirement Quantity of Wastes to Be Generated (Liquid and Solid) And Scheme For Their Management/ Disposal Nature of Waste & Rate of yearly generation Quantity of Waste Selection of Dumping Site and Disposal Liquid Waste Management Site Analysis Connectivity Land Form, Land Use and Land Ownership Topography Geology Geology of Area Geology of lease area

4 4.5 EXISTING LAND USE PATTERN (AGRICULTURE, NON-AGRICULTURE, FOREST, WATER BODIES (INCLUDING AREA UNDER CRZ)), SHORTEST DISTANCES FROM THE PERIPHERY OF THE PROJECT TO PERIPHERY OF THE FORESTS, NATIONAL PARK, WILD LIFE SANCTUARY, ECO SENSITIVE AREAS, WATER BODIES (DISTANCE FROM THE HFL OF THE RIVER), CRZ. IN CASE OF NOTIFIED INDUSTRIAL AREA, A COPY OF THE GAZETTE NOTIFICATION SHOULD BE GIVEN Existing Infrastructure Soil Classification Climatic Data from secondary sources Temperature Wind Rainfall Cloud Cover Humidity Social Infrastructure Planning Brief Planning Concept (Type of industries, facilities, and transportation etc.) Town and Country Planning/ Development Authority Classification Population Projection Landuse Planning (BREAKUP ALONG WITH GREEN BELT ETC.) Assessment of Infrastructure Demand Amenities / Facilities Proposed infrastructure Industrial Area (Processing Area) Residential Area (Non-Processing Area) Social Infrastructure Connectivity (Traffic and Transportation Road / Rail / Metro / Waterways) Drinking Water Management (source & supply of water) Sewerage System Power Requirement and Supply / Source Industrial Waste Management Solid Waste Management Rehabilitation and Resettlement (R& R) Plan Project Schedule and Cost Estimates LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF COMPLETION (TIME SCHEDULE FOR THE PROJECT WILL BE GIVEN)

5 Estimated Project Cost ALONG WITH ANALYSIS IN TERMS OF ECONOMIC VIABILITY OF THE PROJECT Analysis of proposal

6 LIST OF ANNEXURES Annexure 1: Name Change Certificate Annexure 2: Transfer order & ML deed Annexure 3: Recommendation of District Geologist, DGM, Devbhumi Dwarka for Extension of Lease validity under MMDR Amendment Act Annexure 4: Copy of Previous Environmental Clearance Annexure 5: NOC and previous & current CTOs obtained from GPCB Annexure 6: Copy of approval of Mining plan Annexure 7: Copy of letter issued by CCF regarding Eco sensitive zone Annexure 8: Certified Map Showing ESZ & ML Boundary Annexure 9: Certified CRZ Map & Report Annexure 10: Authenticated Production data since

7 LIST OF TABLES Table 2-1: Existing employment available Table 2-2: Proposed additional employment in accordance with the govt. provisions Table 3-1: Geographical Position of the Mine lease Boundary: Table 3-2: Broad Blasting Parameters Table 3-3: Type and Class of explosive to be used as per approved explosive licence Table 3-4: In situ Tentative Excavation Table 3-5: Production planned period Table 3-6: Land Use Pattern Table 3-7: Area to be back filled by Table 3-8: Details of sub-grade stacks present as on Table 3-9: Summery of Equipment Required Table 4-1: Reserve as on Table 4-2: Existing Land Use Pattern Table 4-3: Important Features and Sensitive Ecological locations Table 4-4: Month wise Predominant Wind Direction-Dwarka Table 4-5: Long Term Cloud Cover Information-Dwarka Table 4-6: Average Meteorological Conditions at IMD Dwarka Table 5-1: Land Use Pattern at site (in Ha)

8 1 EXECUTIVE SUMMARY 1.1 The Project Proponent M/s Dalmia Refractories Ltd. (earlier M/s Shri Nataraj Ceramic & Chemical Industries Limited) was originally incorporated as Dalmia Ceramic Industries Limited on June 21, 1973, under the Companies act, 1956, with the Registrar of Companies, Tamil Nadu. The name of the Company was changed to Shri Nataraj Ceramic and Chemical Industries Limited w.e.f. November 01, Once again the name of the company has changed to M/s Dalmia Refractories Ltd. (DRL), w.e.f from M/s Shri Nataraj Ceramic and Chemical Industries Limited. In this regard, Fresh Certificate of Incorporation consequent upon Change of Name issued by Govt. of India Ministry of Corporate Affairs, Registrar of Companies, Tamil Nadu, Chennai, Andaman & Nicobar Island. All other details of company are kept same as that of M/s Shri Nataraj Ceramic & Chemical Industries Limited. 1.2 Project Background The mining lease was sanctioned vide Gujarat Govt. Order No. MCR-1578(B-15)1999/CHH dated Application for renewal of lease has been filed on 5 th Oct., 1998 and mine is operating under deemed renewal of the lease. Application for Extension of lease validity as per MMDR Amendment Act 2015 is recommended by District Geologist, Department of Geology & Mining, Devbhumi Dwarka and is under consideration by the State Govt. It is to be noted that the said lease is now valid upto 31 st March, 2030 as per the provisions of The Mines and Minerals (Development and Regulation) Amendment Act, 2015 which came into force on 12 th Jan The mine lease is Government waste land and does not involve any type of forest area. The land of the Mine lease is under possession of the DRL. Mining Scheme for period to with Progressive Mine Closure Plan was approved by IBM vide Letter No. 682(23) MS-499/2009-MCCM (N) UDP dated for ROM production TPA. Modified Mining Plan with Progressive Mine Closure Plan was approved by IBM vide Letter No. 682(4)(1)MS-134/2018 dated for the period of one year for ROM production 3,00,755 TPA in addition of removal of Topsoil 8,800 TPA & OB \ Waste material 2,22,080 TPA with Total Excavation 5,31,635 TPA. CRZ III Category - A survey was carried out by Institute of Remote Sensing, Anna University, Chennai towards demarcation of High Tide, Low Tide Line for CRZ mapping in or around Mining Lease area. The Mining Lease area Sq.m. (0.3887Ha.) is overlapped under CRZ III Category and this area is under Non Mining Zone. No mining activity has been carried out neither proposed in that area. Eco Sensitive Zone - The mining lease area is not falling in the Eco Sensitive Zone of Marine National Park. The Clearance has been given by Chief Conservator of Forest, Marine National Park, Jamnagar in favour of Pillidhar Bauxite Mine vide its office letter No.: K/24/JMN/Survey/05/ , Dated: Environmental Clearance (EC): An environment clearance for enhancement of production capacity from 65,463 tonnes per annum to 80,000 tonnes per annum of Bauxite was granted by MoEF & CC vide letter J IA. II (M) dated 27/8/2007 under EIA Notification, Details of earlier applications and Environmental Clearance are tabulated below: S. No. Proposal No. MOEFCC File No. Capacity Proposal Status Remarks 1 IA/GJ/MIN/11151/ 2006 No.J /168/2006- IA.II(M) Expansion from TPA to 80,000 TPA EC GRANTED 8

9 S. No. Proposal No. MOEFCC File No. Capacity Proposal Status Remarks 2 IA/GJ/MIN/8534/ 2009 Consent to Operate J /324/2009- IA-II(M) Expansion from 80,000TPA to 3,00,000 TPA TOR GRANTED on PH conducted EC not obtained & project was delisted EC process was not completed as accreditation of engaged consultant was withheld by MOEF&CC Renewal of Consent to operate has been obtained from Gujarat Pollution Control Board (GPCB) vide Consent no AWH dated valid upto Other Recognition: Our efforts have been appreciated at various level, some of them are given below: 9

10 25 th Mines Environment & Mineral Conservation Week under the ages of Regional office, Indian Bureau of Mines, Gandhinagar, Gujarat : Six Prizes in following Heads including Overall Second Prize in B1 (Bauxite) Mechanized Category in the 24 th Mines Environment & Mineral Conservation Week : Two Nos. of Prizes for Afforestation and Reclamation & Rehabilitation 10

11 1.3 Brief Description of the Nature of the Project The The proposal is for enhancement of production capacity of the existing mine Pillidhar Bauxite Mine ( hectares) from 80,000 TPA Bauxite to 3,00,755 TPA with Total Excavation 5,31,635 TPA by semi-mechanised opencast mining. 1.4 Size or Magnitude of Operation Name : Pillidhar Bauxite Mine Area (Hectares) : (Govt. waste land under possession of the DRL) Survey No.: : 136/P (New)- 110/P (Old) Existing Raw Bauxite Production Capacity : 80,000 TPA Proposed Raw Bauxite Production Capacity : 3,00,755 TPA Total proposed excavation: : 5,31,635 TPA (Bauxite 3,00,755 TPA, Topsoil 8,800 TPA & OB/waste 2,22,080 TPA). 1.5 Project Description with Process Details The present proposal is for enhancement of production capacity from 80,000 TPA Bauxite to 3,00,755 TPA Bauxite in addition of removal of Topsoil 8,800 TPA & OB/waste 2,22,080 TPA with Total Excavation 5,31,635 TPA in Pillidhar Bauxite mine with lease admeasuring Ha at survey no. 136/P (New)- 110/P (Old) in village Virpur, Taluka Kalyanpur, District Devbhoomi Dwarka of Gujarat state in order to provide Refractory Grade Bauxite to manufacturing high alumina refractories and related products from all plants of DRL located at Khambhaliya (Guj), Katni (MP) & Dalmiapuram (TN). Semi-mechanised Opencast mining shall be adopted. However, Non Refractory Grade Bauxite generated during mining is disposed off by way of sale in accordance with the lease terms imposed by the State Govt. of Gujarat. Scientific blending is already in practice for achieving better rate of economic production and optimum utilization of marginal grade bauxite inferior to the specification Mineral Beneficiation Mineral Beneficiation is currently not practiced. However, trial beneficiation involving magnetic separation after calcination of Bauxite has been conducted at laboratory scale and have shown encouraging result. The study was conducted by Jawaharlal Nehru Aluminium Research Development and Design Centre, Nagpur (An autonomous Body of Ministry of Mines, Govt. of India) in The study suggested that a detailed study involving various characterization and beneficiation techniques should be conducted. Subsequently, detail methodology and feasibility is under process and being studied at Dalmia Institute of Scientific and Industrial Research, Rajgangpur, Odisha Stacking of Mineral Rejects and disposal of Waste It has been estimated that during the year phase of mine working, the overburden will have to be removed from the area covered by alluvium soil and weathered calcareous material. The alluvium area shall be removed in advance prior to the commencement of the ROM production. The waste generated during last five years has been disposed off by means of backfilling. Present back filled area is about Hect. The backfilling program in fully exploited portion of the worked out pit is a part of the reclamation program and is already in operational practice. No surface dump will be generated and all OB material will be used for simultaneous reclamation by back filling method. An area of about 1.31 Ha is proposed to be backfilled during the Modified Mining plan period Area will be converted into water reservoir. The area program in the year for estimated in situ quantity of overburden is as follows: 11

12 Area to be back filled Year Top Soil (Mt.) Over Burden (Mt.) Mineral Rejects (Cum) Reuse / Spreading Storage Backfilling Storage Storage Beneficiation 8800 on top of Backfilled Area for plantation Nil NA NA Under Trial The sub-grade mineral bauxite (non Plant (Refractory) Grade) is being stacked on temporary basis and disposed off only after obtaining specific permission of State Govt. 1.6 Landuse pattern At the end of life of mine, out of the total excavated area ( Ha.), about Ha. area shall be backfilled & reclaimed and Ha. Will be converted into water reservoir Heads Existing After Plan period Conceptual stage a) Pits & Quarries b) Dumps of Waste & O.B c) Mineral Stack c) Infrastructure including of office, urinal, magazine& Mine Road etc. d) Township (Colony & School) e) Others Barren land Crop land f) Undisturbed area affected under CRZ III Category/ Non Mining Zone Total ML area Plantation in proposed year At present about 8 ha area is under plantation. About 1500 No. of saplings per hectare is proposed to be planted within the existing plantation area to improve aesthetic beauty. Measures will be adopted to ensure survival & protection of plantation. At the end of the life of mine, about ha area shall be under plantation. 1.8 Availability of Water its Source and Energy/Power Requirement The Proposed Daily Requirement of Water at Mine Site: - 1. Water sprinkling : KLD 2. Plantation : KLD 3. Domestic & Drinking : KLD Total : KLD Source: Drinking water is purchased and transported by authorised water tankers on hired basis whereas rain water collected in mined out pits is used for plantation and dust suppression. In addition to this, if more water require for dust suppression other than accumulated rain water, will be sourced from authorised tankers. 12

13 1.9 Fuel/Power Requirement The mine is being/will be worked by semi-mechanized method. Electric connection has already been taken for office and other facilities. For HEMM operation during mining, it is envisaged that about 1 KLD of diesel will be required. About 3 lit/hr diesel will be used as fuel for running pump for dewatering in rainy season Employment Generation (Direct and Indirect) due to the Project At present 144 employees are working in the mine and additional 137 employment shall be generated for the expansion of the subject mine. 13

14 2 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION 2.1 The Project Proponent M/s Dalmia Refractories Ltd. (earlier M/s Shri Nataraj Ceramic & Chemical Industries Limited) was originally incorporated as Dalmia Ceramic Industries Limited on June 21, 1973, under the Companies act, 1956, with the Registrar of Companies, Tamil Nadu. The name of the Company was changed to Shri Nataraj Ceramic and Chemical Industries Limited w.e.f. November 01, Once again the name of the company has changed to M/s Dalmia Refractories Ltd. (DRL), w.e.f from M/s Shri Nataraj Ceramic and Chemical Industries Limited. In this regard, Fresh Certificate of Incorporation consequent upon Change of Name issued by Govt. of India Ministry of Corporate Affairs, Registrar of Companies, Tamil Nadu, Chennai, Andaman & Nicobar Island (attached as Annexure 1:). All other details of company are kept same as that of M/s Shri Nataraj Ceramic & Chemical Industries Limited. 2.2 The Project Background The Mine is located at survey no. 136/P (New) - 110/P (Old) in village - Virpur, Taluka Kalyanpur, District Dev Bhumi Dwarka, State Gujarat. The mining lease was sanctioned vide Gujarat Govt. Order No. MCR-1578(B-15)1999/CHH dated in favour of M/S Bharat Abrasives & Chemical Industries, Proprietor Shri B.K. Makecha, for 20 years commencing , being the date of execution of mining lease. This mining lease was later transferred in the name of M/S B P Abrasives & Chemical Industries Pvt Limited, Porbandar, Gujarat, vide Gujarat Govt. order No MCR-1582(B-122)6434/CHH dated for the remaining period and the transfer deed of mining lease was executed on M/s Dalmia Refractories Ltd. (DRL) (Earlier known as Shri Nataraj Ceramic And Chemical Industries Limited), a public Limited Company in private sector. The company negotiated the transfer of the said mining lease in its favour vide deed dated against Gujarat Govt. order No. MCR-1589(N-17) 695/CHH dated for the remaining period ending to cater to its captive requirements (attached as Annexure 2) Application for renewal of mine lease has been filed on 5 th Oct., 1998 and mine is operating under deemed renewal of the lease. Application for Extension of lease validity as per MMDR Amendment Act 2015 is recommended by District Geologist, Department of Geology & Mining, Devbhumi Dwarka (attached as Annexure 2) and is under consideration by the State Govt. It is to be noted that the said lease is now valid up to 31 st March, 2030 as per the provisions of The Mines and Minerals (Development and Regulation) Amendment Act, 2015 which came into force on 12 th Jan 2015 The mine lease is Government waste land and does not involve any type of forest area. The land of the Mine lease is under possession of the DRL. Mining Scheme for period to with Progressive Mine Closure Plan was approved by IBM vide Letter No. 682(23) MS-499/2009-MCCM (N) UDP dated Modified Mining Plan with Progressive Mine Closure Plan was approved by IBM vide Letter No. 682(4)(1)MS-134/2018 dated for the period of one year for ROM production 3,00,755 TPA in addition of removal of Topsoil 8,800 TPA & OB \ Waste material 2,22,080 TPA with Total Excavation 5,31,635 TPA. CRZ III Category - A survey was carried out by Institute of Remote Sensing, Anna University, Chennai towards demarcation of High Tide, Low Tide Line for CRZ mapping in or around Mining Lease area. The Mining Lease area Sq.m. (0.3887Ha) is overlapped under CRZ III Category and this area is under Non Mining Zone. No mining activity has been carried out neither proposed in that area. The area falls under non-mineralised zone of the lease area. ML boundary superimposed on the CRZ map on 1:4000 scale is attached as Annexure 9 14

15 Eco Sensitive Zone - The mining lease area is not falling in the Eco Sensitive Zone of Marine National Park. The Clearance has been given by Chief Conservator of Forest, Marine National Park, Jamnagar in favour of Pillidhar Bauxite Mine vide its office letter No.: K/24/JMN/Survey/05/ , Dated: (Attached as Annexure 8). Environmental Clearance (EC): An environment clearance for enhancement of production capacity from 65,463 tonnes per annum to 80,000 tonnes per annum of Bauxite was granted by MoEF & CC vide letter J IA. II (M) dated 27/8/2007 under EIA Notification, Details of earlier applications and Environmental Clearance are tabulated below: S. No. Proposal No. MOEFCC File No. Capacity Proposal Status Remarks 1 IA/GJ/MIN/11151/ IA/GJ/MIN/8534/2009 No.J /168/2006- IA.II(M) J-11015/324/2009-IA- II(M) Expansion from TPA to 80,000 TPA Expansion from 80,000TPA to 3,00,000 TPA EC GRANTED TOR GRANTED on PH conducted EC not obtained and project was delisted Attached as Annexure 4) EC process was not completed as accreditation of engaged consultant was withheld by MOEF&CC Consent to Operate Renewal of Consent to operate has been obtained from Gujarat Pollution Control Board (GPCB) vide Consent no AWH dated valid up to The details of all NOC and previous CTO granted by GPCB are attached as Annexure 5. Proposed Project Looking into the market conditions, now DRL proposes to pursue its application for enhancement in production capacity from 80,000 TPA Bauxite to 3, 00,755 TPA (Total excavation- 5, 31,635 TPA) as proposed in the present proposal. 2.3 Brief Description of the Nature of the Project The mine is located at survey no. 136/P (New)- 110/P (Old) in Village - Virpur, Taluka Kalyanpur, District Devbhumi Dwarka, State Gujarat. The mine lease is Government waste land and does not involve any type of forest area. The land of the Mine lease is under possession of the DRL. The proposal is for enhancement of production capacity of the existing Pillidhar Bauxite Mine ( hectares) from 80,000 TPA Bauxite to 3,00,755 TPA Bauxite with Total Excavation 5,31,635 TPA. Scientific blending is already in practice. Mining is being carried out by semi mechanized open cast method with the use of drilling and blasting and the same method shall be continued. During this plan of mining period, Mining will be carried out in five blocks named A1, B1, C1, D1, & E Need for the project and its importance to the country and region The enhancement of the production capacity of the mine is proposed to cater the bauxite requirement of all the Refractory plants located at Khambhaliya (Guj), Katni (MP) & Dalmiapuram (TN) of M/s Dalmia Refractories Ltd. The manufactured products of high alumina refractories and other related products etc. are mainly used in Cement, Steel, and Chemical plants. Mining industry plays an important role in economic sector in India. Bauxite mine plays an important role for major production of aluminum. The bauxite is also use in different sector according to their use in commercial application, like abrasive, cement, chemical, metallurgical, refractory, etc. 15

16 India is ranked 6 th in the world in terms of Bauxite Reserves. With the development of aluminium factories the domestic demand for bauxite has been increased in the country. Gujarat is rich in mineral like bauxite. Next to Orissa, Gujarat ranks second and Jharkhand third in Bauxite production in India. Gujarat produces about 15% of India s bauxite and occupies third position. Jamnagar, Kaina, Sabarkantha, Kachchh and Surat are the main bauxite-producing districts. The state is endowed with major and minor mineral resources. The region, where the project is situated, people are mostly dependent on agriculture and mineral resources. The developments of mining in the area provide direct and indirect employment opportunities, infrastructure development, communication and socio-economic infrastructure. DRL is also implementing various programs for betterment of the surrounding area. 2.5 Demand-Supply Gap The demand for bauxite is mainly requirement of aluminum, cement, chemical, metallurgical, refractory industries. Gujarat was the main supplier of abrasive and refractory grade bauxite. Alumina plants draw supplies mostly from their captive mines In , the consumption of bauxite was estimated as million tonnes as compared to million tonnes in the previous year. Alumina / Aluminium Industry was the principal consumer of bauxite and accounted for 91% consumption in followed by Cement (7%) and Calcination (1%). The production of bauxite in the country for was at 24,665 thousand tonnes which decreased by 12% as compared to the previous year. There were 157 reporting mines in as against 190 in the previous year. Besides, 7 mines have reported production of bauxite as associated mineral during the year. Odisha emerged as the leading producing State accounting for about 49% of the total production followed by Gujarat (24%), Jharkhand (9%), Chhattisgarh and Maharashtra (8% each). The remaining was produced by Madhya Pradesh, Goa, Karnataka and Tamil Nadu. (Source: Indian Minerals Year book 2017 (Part- III : Mineral Reviews) 56 th Edition BAUXITE) There is a gap between the demand and the supply of bauxite. The enhanced capacity of the project aims to fill the demand supply gap through optimum allocation and excavation of natural resources required to meet the demand effectively. 16

17 2.6 Imports v/s Indigenous Production This is an existing operational mine for supply of Refractory Grade material for captive consumption for manufacturing of High Alumina Refractories & other related products in the DRL s plants located at Khambhaliya (Guj), Katni (MP) & Dalmiapuram (TN). However, Non Refractory Grade Bauxite generated during mining is disposed off by way of sale in accordance with the lease terms imposed by the State Govt. of Gujarat. 2.7 Export Possibility No proposal for direct exports of the Bauxite. 2.8 Domestic / Export Markets Refractory Grade Bauxite from the mine will be used for captive consumption in all DRL s manufacturing plants while the balance Non Refractory grade bauxite is periodically disposed off by sale against specific clearance from the State Govt. Scientific blending is already in practice as per approved mining scheme for achieving better rate of economic production and for optimum utilization of marginal grade bauxite inferior to the specification. 2.9 Employment Generation (Direct and Indirect) due to the Project Direct At present 144 employees are working in the mine and additional 137 employment shall be generated after the expansion of the subject mine. The following employment is under provisions of the MMR 1961 & MCDR, 2017 including Mining engineer & Mining Geologist : Table 2-1: Existing employment available Title Qualification Existing Numbers Mine Manager & Mining Engineer B.E. (Mining) & Second Class Mine Manager s Certificate of Competency Asst. Mine Manager & V.T.O Second Class Mine Manager s Certificate 01 Vocational Training Instructor Foreman s Certificate of Competency 01 Mining Geologist M.Sc. (Geology) 01 Mine Surveyor Mine Surveyor s Certificate of Competency 01 Mine Foreman Foreman s Certificate of Competency 01 Mining Mate & Blaster Mining Mate s & Blaster Certificate 05 Register keeper Contractual 01 Weighbridge Operator Contractual 01 Supervisor (Skilled) Contractual 06 Security Guards Contractual 05 Contractors Contractual (Manual & Machine) 10 Labour (Skilled) Contractual 108 Driver Contractual 02 Table 2-2: Proposed additional employment in accordance with the govt. provisions Title Qualification Required Numbers Mine Manager & Mining Engineer BE or Diploma in Mining. First Class / Second Class Mine Manager s Certificate of Competency Environment Section B.E. / M.Sc. (Environment) 01 Horticulturist Graduate/Post Graduate (Ag.) 01 (Hired)

18 Title Qualification Required Numbers Mining Foreman Foreman s Certificate of Competency 02 Mining Mate cum Blaster Mining Mate s Certificate 02 Weighbridge Operator Contractual 01 Supervisor Skilled 02 Security guards Contractual 02 Contractors Contractual (Manual & Machine) 05 Labour (Skilled) Contractual 120 Preference for employment has been given to the suitable locals and the same practice shall be continued Indirect Apart from direct employment, many indirect opportunities shall be occurred after the proposed expansion. Few people would be engaged in providing support services to the mining operation including transportation of ROM. The exact number of such persons is likely to be in the order of ~ Bauxite produced from mine is being processed in all DRL s Refractory Plant and final product is being sold to customers for use or further processing. The proposed expansion will generate additional economic demand that could translate into additional employment. 18

19 3 PROJECT DESCRIPTION 3.1 Type of Project including Interlinked and Interdependent Projects The mine is a captive mine and cater the requirement of Refractory Grade Bauxite as main raw material to all DRL s manufacturing plants located at Khambhaliya (Guj), Katni (MP) & Dalmiapuram (TN) while the balance Non Refractory grade bauxite is periodically disposed off by sale against specific clearance from the State Govt. Scientific blending is already in practice as per approved mining scheme for achieving better rate of economic production and for optimum utilization of marginal grade bauxite inferior to the specification. 3.2 LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION, AND PROJECT BOUNDARY AND PROJECT SITE LAYOUT) WITH COORDINATES The mining lease over an area of hectares is located in survey no. 136/P (New)- 110/P (Old), village - Virpur, Taluka Kalyanpur, Dist : Devbhumi Dwarka, State Gujarat. The Mine is about 0.81 km by crow flight distance towards NNE of Village Virpur, while by Village road, which could best be described as cart track, the approach is 2 km. Virpur is approachable only by a semi metallic road with combination of Kaccha road & passing through village Ran which is located about 11 km north of the tar road connecting village Limbdi with Dwarka. State highway no. 29 linking Limli to Dwarka via Gorgadh through Village Ran and Mewasa at a distance of about 12 km. Coastal Highway CH-6 is at distance of ~10 Km in south direction of lease. The nearest railway station is Bhatia, which is located on Okha- Devbhumi Dwarka- Rajkot-Viramgam broad gauge section of western railway and about 20 km from the site. The nearest sea port is Okha which is about 105 km from Village Virpur. The project site falls in Survey of India Toposheet No. 41F/7. The project area falls between following geographical co-ordinates: Table 3-1: Geographical Position of the Mine lease Boundary: Bounding Box Maximum (Degrees Minutes Seconds) 22 16' ", ' " Bounding Box Minimum (Degrees Minutes Seconds) 22 15' ", ' " 19

20 Map 3-1: Map showing location of site Mining lease area Non mining zone Not In ML 3.3 Alternate Sites Considered No alternative sites have been considered since it is a site specific existing mining project and all necessary statutory clearances and permissions under various acts and rules of Govt. of India & State Govt. have been obtained and are being periodically renewed during all these years of mining operation. 20

21 3.4 Size or Magnitude of Operation Name: Pillidhar Bauxite Mine Area (Hectares): Survey No.: Existing Raw Bauxite Production Capacity: Proposed Raw Bauxite Production Capacity: Total proposed excavation: 110/P (Old) 136/P (New) 80,000 TPA 3,00,755 TPA 5,31,635 TPA including (Bauxite 3,00,755 TPA, Topsoil 8,800 TPA & OB/waste 2,22,080 TPA). 3.5 Project Description with Process Details The present proposal is for enhancement of production capacity of bauxite from 80,000 TPA to 3,00,755 TPA with Total Excavation 5,31,635 in order to provide Refractory Grade Bauxite to manufacturing high alumina refractories and related products from all plants of DRL located at Khambhaliya (Guj), Katni (MP) & Dalmiapuram (TN). However, Non Refractory Grade Bauxite generated during mining is disposed off by way of sale in accordance with the lease terms imposed by the State Govt. of Gujarat. Scientific blending is already in practice for achieving better rate of economic production and optimum utilization of marginal grade bauxite inferior to the specification Salient Features of Mode of Working The Mine development and subsequent exploitation is undertaken as proposed in the modified approved Mine plan and PMCP. There are five working pits at present i.e. Block A1, B1, C1, D1 and E1. Method of mining will be semimechanized opencast mining method forming benches up to 1.5m (avg.) height in O.B and 3.0m (avg.) height in ore. The sides of the benches have slopes at a safe angle not more than 45 degree from horizontal.. The overburden removal is by both means i.e. manual and mechanical method. In case the overburden thickness is more resulting in large volume of overburden handling, the excavation is carried out with the help of JCB excavators. Otherwise manual overburden excavation is carried out. In addition to the manual drilling, shallow blast hole drilling is also carried out with jack hammer / hand drills operated by air compressors. Mining in hard and compact bauxite horizon is carried out manually with benches not exceeding 3 m in height and width of the bench being maintained correspondingly. The slope of the faces in hard and compact bauxite is not allowed to be more than 60 degree from horizontal. Number of benches is varying as per the topography of the area. The cleaning of broken muck pile of the bauxite from mining face graded manually based on physical appearance by chipping, sizing, sorting & stacked in mining face for movement in assigned place for further assessment. The scientific blending is already in practice as stated in the approved mining plan / scheme in details for achieving better Refractory Grade Production or improvement for economic aspect and optimum utilization of marginal grade bauxite inferior to the specification with a view to achieve conservation of mineral. The Over burden is generated concurrently and simultaneously backfilling is done in mined out area. Top soil is being used for plantation purpose and also spread on backfilled area for Reclamation and Rehabilitation of mined out areas. The backfilled area is properly levelled and reclaimed by plantation. There were three dumps out of which two dumps have been completely utilized for backfilling and remaining one dump shall be liquidated in due course time Drilling and Blasting The manual activities of mining are predominantly based on manual drilling. But, at the time of hard and compact formations the shallow blast hole is carried out by machine drilling with the help of Jack Hammer & operated by Air compressors. The mine is worked with shallow hole blasting with holes of average depth of around 0.75 meters but 21

22 never more than 1.5 meters. Generally ten blast holes in single row are placed 0.75 m apart, in both parallel and vertical axis to the mine face.. Various types of explosives such as ANFO, slurry, emulsion etc. will be used for blasting. Table 3-2: Broad Blasting Parameters Item Bench height (m) 1.5 Hole inclination Hole depth (m) (including 10 % sub-grade drilling) 1.73 Burden (m) 1.0 Spacing (m) 1.3 Parameters 150 to vertical Volume (m3) 1.3x1.0x1.5= 1.95 Tonnage yield (t) ROM per day (3,00,000/300 = 1000 tpd) Powder Factor Explosive per hole (4.49/4=1.12kg) Volume of rock to broken /day (1000/2.3=435cum) 1.95x2.3= t No. of holes required/day (435/1.95=223) 223 Explosive per day 4 t/kg of explosive 1.12 kg 435 cu.m. 250 kg. Secondary blasting is rarely resorted for breaking of large boulders generated during primary blasting. Overburden does not require any use of explosive since it is primarily soft soil only. The Magazine for storage of explosives is existing at mine site with following capacity as approved by competent authority under the Chief Inspector of Explosives. Table 3-3: Type and Class of explosive to be used as per approved explosive licence. S. No. EXPLOSIVES CLASS &DIV. CAPACITY 1 Nitrate Mixture/ Nitrate Compound 2 & Nil 150 Kgs. 2 Ammonium Nitrate Nil Kgs 3 Safety Fuse 6 & mtrs. 4 Detonating Fuse 6 & mtrs. 5 Ordinary Detonator 6 & Nos. 6 Electrical Detonator 6 & Nos. Mine development on year-to-year basis is described as under: a. Tentative Excavation Table 3-4: In situ Tentative Excavation No. of Pit Total Tentative Excavation (Mt) Top Soil OB ROM (Cum Mineral Ore Mineral Reject Reject 5 (A1,B1,C1,D1,E1) :1 ROM / Waste Ratio Dump Re-handling All OB material will be used for simultaneous reclamation by back filling method. There will be no dump Transport There are separate roads for incoming and outgoing traffic from the pit to provide one-way traffic at a gradient of not more than 1:16. Four Wheeled Trolley attached to tractor is generally used for movement of minerals and overburden within the lease area. The mineral transported out of the lease hold is with the help of dumpers and 22

23 trucks on hired basis. The Refractory Grade bauxite is transported to company s manufacturing unit located at Khambhaliya (Guj), Katni (MP) & Dalmiapuram (TN) using hired trucks / dumpers on road, rail and sea Mineral Processing Operations (if any) No mineral processing operation is carried out. Scientific blending is already in practice as stated in the approved mining scheme / plans for achieving better rate of economic production and optimum utilization of marginal grade Bauxite inferior to the specification with a view to achieve conservation of mineral by Manual sizing, sorting & grading during the operation Production for the planned period The bauxite production for planned period is 3,00,755 TPA which is detailed below. Table 3-5: Production planned period Year Block Bauxite Plant (Refractory) Grade (tones) Non-Plant (Refractory) Grade (tones) Total (tones) A B C D E Total Along with the bauxite, about 8,800 TPA Topsoil & 2,22,080 TPA OB/waste will also be generated at peak production Life of Mine Left out mineable reserves is 6.41 million tonnes and proposed rate of production is 3,00,755 TPA (0.3 MTPA) hence life of mine is envisaged around 21 years. 3.6 Conceptual Mining Plan Mineral Exploration No Proposal, because complete exploration work was carried out Ultimate Pit Limit The conceptual mining limit has been derived on the basis of geological plan, geological sections slope of working faces & sequence of mine development. The ultimate pit limit shows the extent of the extraction from the mines Geological Sections showing in approved mining plan. To delineate mining limits covering all Mineable blocks a number of geological sections have been examined and the pit limit boundary have been drawn considering slope of working faces and sequence of mine development in all the blocks. The conceptual mining plan has been considered based on available Mineable reserves in all blocks. A conceptual mining limit (in section) has been drawn showing the ultimate pit limit. The Ultimate pit limit shall be over an area of Ha Ultimate Pit extent As per approved mining plan, during this mining period, Mining will be carried out in five blocks named A1, B1, C1, D1 & E1. The rate of ROM production will be 3,00,755 TPA. During this mining period the depth of excavation will be up to 7.0 m in A1 block, 13.0 m in B1 block, 9.0 m in C1 block, 9.0 m in D1 block & 14.0 m in E1 block by making systematic benches of 5.0 m maximum height in mineral. 23

24 Table 3-6: Land Use Pattern Heads Existing After Plan period Conceptual stage a) Pits & Quarries b) Dumps of Waste & O.B c) Mineral Stack c) Infrastructure including of office, urinal, magazine& Mine Road etc d) Township (Colony & School) e) Others Barren land Crop land f) Undisturbed area affected under CRZ III Category/ Non Mining Zone Total ML area Reclamation & Rehabilitation: Present back filled area is about Ha Simultaneous backfilling and reclamation of the excavated pit shall be carried out. At the end of life of mine, out of the total excavated area about Ha area shall be backfilled & reclaimed by plantation and remaining Ha area shall be converted into water reservoirs. The depth of water reservoir shall be from 7 m to 12 m Stacking of Mineral Rejects and disposal of Waste The modified plan envisages soil & overburden removal in the year as seen from the Table 3-7 below. It has been estimated that during the year phase of mine working, the overburden will have to be removed from the area covered by alluvium soil and weathered calcareous material. The alluvium area shall be removed in advance, prior to the commencement of the ROM production. The waste generated in past has been disposed off by means of backfilling and rehabilitated by plantation. Present back filled area is about Ha. OB material will be used for simultaneous backfilling and will be rehabilitated by plantation, hence there will be no dump at the site. An area of about 1.31 Ha is proposed to be backfilled during the Modified Mining plan period At the end of life of mine about Ha area shall be backfilled & reclaimed. The area program in the year for estimated in situ quantity of overburden is as follows: Table 3-7: Area to be back filled by Year Top Soil (Mt.) Over Burden (Mt.) Mineral Rejects (Cum) Reuse / Spreading Storage Backfilling Storage Storage Beneficiation 8800 on top of Backfilled Area for plantation Nil NA NA NA The sub-grade mineral bauxite (non Plant (Refractory) Grade) is being stacked on temporary basis and disposed off only after obtaining specific permission of State Govt. There are total seven non Plant (Refractory) Grade piles can be seen at mine site. The height of sub-grade bauxite mineral is varying from 4.0 m to 8.5 m whereas area covered is varying from 505 sq mts to sq. mts. The Piles are made in single bench with average height not exceeding 7.5 meters and slopes ranging around 35 degrees from horizontal on rocky base. Since these piles are temporary in nature the existing arrangement is considered adequate. The details of sub-grade stacks present as on at the mine are as follows: Table 3-8: Details of sub-grade stacks present as on PB. No Area (sq.m.) Height (m)

25 PB. No Area (sq.m.) Height (m) Total Plantation At present about 8 ha area is under plantation (including backfilled area). About 1500 No. of saplings per hectare is proposed to be planted within the existing plantation area (1.41 ha) to improve aesthetic beauty. Measures will be adopted to ensure survival & protection of plantation. At the end of the life of mine, about ha area shall be under plantation Extent of Mechanization As per Approved Mining Plan, the mining will be done by semi mechanized open cast mining method with the use of manual, following type of machinery. Table 3-9: Summery of Equipment Required S. No. Type of Machinery Unit Capacity Motive Power H P 1 Compressor on hired basis cfm Diesel HEMM on hired basis Haulage on hired basis Excavator JCB 1 1 Bucket capacity 1.0 cum Bucket capacity 0.2 cu.m Diesel Dumper cu.m 180 Tractor with Diesel cu.m 35 Trolley 4 Drilling on hired basis - - Comp. Air - 5 Water Sprinkler on hired basis 1 10 KL Diesel Jeep 2 - Diesel Raw Materials Required along with Quantity likely Source, Marketing area of Final Product Mode of Transport of Raw Material & Finished Products Raw Materials Being mining project, no further raw material is required for mining except explosives material requires for blasting and fuel / diesel for HEMM. Proposed mining project is a Captive requirement for producing of Refractory Grade Bauxite from ROM production for all DRL s plant as stated earlier Marketing Company has got lease for its captive consumption. Plant Grade Bauxite is completely used for company s own plant. The inferior grade of (non-plant grade) bauxite material failed on chemical analysis pilled within the ML area, are sold after getting prior permission from the State Govt Mode of Transport Four Wheeled Trolley attached to tractor is generally used for movement of minerals and overburden within the lease area. The chemically accepted Refractory Grade Bauxite is transported by hired /owned truck to company s manufacturing unit of DRL. Non Refractory grade bauxite is stacked separately & lessee sale it upon obtaining prior permission from State Govt. 25

26 3.8 RESOURCE OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN THE PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED Top soil is being/will be used for plantation purpose and also spread on backfilled area for Reclamation and Rehabilitation of mined out areas. No mineral processing operation is carried out. The Over burden is generated concurrently and simultaneously backfilling is done in mined out area and the same practice shall be continued. Scientific blending is already in practice as stated in the approved mining scheme / plants for achieving better rate of economic production and optimum utilization of marginal grade Bauxite inferior to the specification with a view to achieve conservation of mineral by Manual sizing, sorting & grading during the operation. The on and average blending ratio of bauxite production from blocks A1, B1, C1, D1 & E1 will be 10%, 20%, 21%, 25% & 24% respectively. The sub-grade mineral called the non-plant (Refractory) Grade bauxite has a ready market for disposal. But due to the insistence of the State Government to incorporate extraneous clause in the lease deed restricting the disposal only after obtaining their specific permission each time results in accumulation of stocks at the pit head results in accumulation of stocks at the pit head of such material since the State Govt. takes considerable time in granting the permission. The sub-grade mineral bauxite (non Plant (Refractory) Grade) is being stacked on temporary basis and disposed off only after obtaining specific permission of State Govt. There are total seven non Plant (Refractory) Grade piles can be seen at mine site. The height of sub-grade bauxite mineral is varying from 4.0 m to 8.5 m whereas area covered is varying from 505 sq mts to sq. mts. The Piles are made in single bench with average height not exceeding 7.5 meters and slopes ranging around 35 degrees from horizontal on rocky base. Since these piles are temporary in nature the existing arrangement is considered adequate. 3.9 Availability of Water its Source and Energy/Power Requirement Water The Proposed Daily Requirement of Water at Mine Site: - 1. Water sprinkling : KLD 2. Plantation : KLD 3. Domestic & Drinking : KLD Total : KLD Source: Drinking water is purchased and transported by authorised water tankers on hired basis whereas rain water collected in mined out pits is used for plantation and dust suppression. In addition to this, if more water require for dust suppression other than accumulated rain water, will be sourced from authorised tankers Fuel/Power Requirement The mine is being/will be worked by semi-mechanized method. Electric connection has already been taken for office and other facilities. For HEMM operation during mining, it is envisaged that about 1 KLD of diesel will be required. About 3 lit/hr diesel will be used as fuel for running pump for dewatering in rainy season. 26

27 3.10 Quantity of Wastes to Be Generated (Liquid and Solid) And Scheme For Their Management/ Disposal Nature of Waste & Rate of yearly generation In the proposed mining plan period, soil and OB is likely to be generated. Soil will be used for plantation while OB will be used for backfilling. Quantity of Waste Quantity of Waste During the proposed plan period about 8800 MT of topsoil and MT of OB shall be generated at peak production Selection of Dumping Site and Disposal The subjected mine is an existing operational mine. The backfilling program, in fully exploited portion of the worked out pit, is a part of the reclamation program which is already in operational practice. The waste generated in past has been disposed off by means of backfilling and reclaimed by plantation. Present back filled area is about Ha. The OB generated during mining period will be backfilled in the mined out area in north part of the lease area. An area of about 1.31 Ha is proposed to be backfilled during the Modified Mining plan period There will be no fresh OB surface dumping within ML. As volume of voids is much more than material available for backfilling of entire mined out area up to original ground level will not possible. Therefore, at the end of the life of mine, Ha area will be backfilled and will be reclaimed by plantation. Remaining Ha of the excavated area will be used as water reservoir. There is no surface dump proposed at outside the ML area Liquid Waste Management Sewage: Domestic waste water will be disposed off in septic tank followed by soak pit at site. a) Regular monitoring of ground water level and quality shall be carried out in and around the mine lease by establishing a network of existing wells and constructing new piezometers during mining operations. The monitoring is being/shall be carried out four times in a year and data thus collected is sent to concerned authorities. b) Surface run off: - Garland Drains, if required shall be constructed for pit and dumps and, sump capacity shall be designed, keeping 50% safety margin over and above peak sudden rainfall and maximum discharge in the area and adjoining mine site. Sump capacity shall also provide for adequate retention period to allow proper settling of silt material. Sedimentation pits shall be constructed at the corner of the garland drain and desilted at regular interval. A water pump will be installed for dewatering the accumulated rain or surficial water from the excavated area of the mine during monsoon season. During monsoon season; the mine will be closed/sealed during the rains. Accumulated rainwater will be filtered during pumping process to pendent or suspend solids materials. Part of filtered water will be used for plantation & rest will be diverted into natural drainage. Mineral bauxite being non-toxic in nature, no harm is envisaged on surface water. There is no discharge of water or any other effluent from this mine and also no generation of any toxic or hazardous substance which may affect the quality of water in buffer zone of lease area. 27

28 4 SITE ANALYSIS 4.1 Connectivity Mine can be easily approachable by the local road/village road. The Mine is about 0.81 km by crow flight distance towards NNE of Village Virpur, while by Village road, which could best be described as cart track, the approach is two km long. Virpur is approachable by a combination of ill maintained paved road, gravel road and cart track through village Ran which is located about 1km north of the tar road connecting village limbdi with Dwarka. Limdi is located on the Devbhumi Dwarka- Okha state highway no. 29 and is about 35km from Khambhaliya. State Highway 29 is located ~12 km South direction of the lease area. Coastal Highway CH-6 is at distance of ~10 Km in south direction of lease. The nearest railway station is Bhatia which is located Okha-Devbhumi Dwarka-Rajkot-Virgaon broad gauge section of western railways and about 20 km from the site. The nearest sea port is Okha which is about 105km from Mewasa. 4.2 Land Form, Land Use and Land Ownership Entire lease area is designated as Government Waste land free from any type of Forest Land, habitation, Eco Sensitive Zone. As per the Survey carried out by Institute of Remote Sensing,Anna University,Chennai, Sq.m (about Ha) area at Northern boundary of ML is falling uin CRZ III Category which is already demarcated as non-mining zone. There is no habitation within the ML. The highest contour value in the lease area is m and lowest contour is of 6 m. The general slope of the area is towards northeast direction. There is no seasonal Nalla flowing through the lease area. There is no firm drainage pattern. 4.3 Topography Rugged topography was seen in the mine. The temporary benchmark has been shown on surface plan i.e m. Maximum elevation recorded in the mine is 29.52m, whereas the minimum elevation is observed 6.00m. (these m levels are based on the total station survey data with the reference of assumed base level i.e m). Trees are found in very less numbers in and near the mine. Dispersed some type of thorny bushes can be seen in accepting numbers. Human settlement are not present near the vicinity of the mine. 4.4 Geology Geology of Area The shallow bauxite deposit of Kalyanpur occurs in north-south trending laterite belt from Mota Asota to Lamba Village. The laterite forms almost a continuous horizon underlying Gaj beds and overlying Deccan Traps. The scattered bauxite pockets are encountered in the exposed as well as concealed laterite horizon. Deccan Trap covers almost entire eastern portion of the district over lain by a mantle of soil. Quartz / Calcite fill the geodes in Trap which is traversed by Dolerite dykes. Laterite belt occupies the periphery of the Trap. Tertiary formations commence with the Gaj Beds over lying the traps as well as laterite. Fossiliferous limestone of Gaj Beds spread out extensively in Kalyanpur Taluka whereas at other places it occurs in isolated patches. Fossils are conspicuously absent from Dwarka Beds developed near Dwarka and Bayt island. Milliolite limestone occurs all along the coast as well as in small island pockets. 28

29 Items Age Period Soil, Alluvium, Sand Complex & Fluvio Marine deposits Milliolite Lime Stone Dwarka Beds Gaj Beds Lateritic Rock Deccan Trap Holocene Pleistocene Pliocene Miocene Eocene Lower Eocene to Upper Cretaceous. Quaternary Tertiary Geology of lease area The surface geology indicates presence of alluvial and soil mostly in the peripheral low lying plan part of the leasehold. The undulating terrain within the leasehold predominantly contains lateritic / bauxitic exposures over lain with small pockets of the highly weathered calcareous material. Two pockets of the highly weathered calcareous material, one in the central part of the southern boundary of the major northern part of the leasehold and the other near the eastern boundary of the small south eastern part of the leasehold, are however noticeably larger in size. The highly weathered friable calcareous material consists of clay which is predominantly yellow in colour and frequently concretionary in nature. The lateritic and bauxite horizon red in colour when consisting chiefly of ferruginous material associated with bauxite and mottled red, pink and gray coloured clay. The mine section has been generalized as Soil, alluvium and clay: 8 10 meter Weathered calcareous rock: 3 4 meter Bauxite and Lateritic Zone: meter Laterite grading to lithomarge: Below Bauxite Material. Reserves/Resources Table 4-1: Reserve as on Classification Code Quantity Grade (million tons) Total Mineral Resources (A+B) A. Mineral Reserve: - 1. Proved Mineral Reserves 2. Probable Mineral Reserves B. Remaining Resources: - 1. Feasibility Mineral Resources 2. Prefeasibility Mineral Resources 3. Measured Mineral Resources 4. Indicated Mineral Resources 5. Inferred Mineral Resources 6. Reconnaissance Mineral Resources & & Plant (Refractory) Grade & Non Plant (Refractory) Grade Total Reserve + Resources 6.41 Balance of probable reserves, as these reserves has been upgraded to 111 categories and re-casted fewer than 211, 221 & 333 categories. 29

30 4.5 EXISTING LAND USE PATTERN (AGRICULTURE, NON-AGRICULTURE, FOREST, WATER BODIES (INCLUDING AREA UNDER CRZ)), SHORTEST DISTANCES FROM THE PERIPHERY OF THE PROJECT TO PERIPHERY OF THE FORESTS, NATIONAL PARK, WILD LIFE SANCTUARY, ECO SENSITIVE AREAS, WATER BODIES (DISTANCE FROM THE HFL OF THE RIVER), CRZ. IN CASE OF NOTIFIED INDUSTRIAL AREA, A COPY OF THE GAZETTE NOTIFICATION SHOULD BE GIVEN Table 4-2: Existing Land Use Pattern Heads Forest Land Crop Land Waste Land Others Total Indicate land req. Outside lease area a) Pits & Quarries b) Dumps of Waste & O.B c) Mineral Stack c) Infrastructure including of office, urinal, magazine& Mine Road etc. d) Township (Colony & School) e) Others i. Barren land ii. Crop land Total occupied area Area backfilled by company Ha Area afforested by company 8.0 Ha (Including backfilled area) Details regarding to the other ecological and important areas are provided in Table 4-3 Table 4-3: Important Features and Sensitive Ecological locations S. No. Feature Name 1 Forest Land From Project Site Distance (km) Reserve Forest ~ 0.60 (source Toposheet) NE Reserve Forest ~ 1.1 (source Toposheet) E Reserve Forest ~ 9.49 (source Toposheet) SE Mangrove Swamp ~ 0.8 km (source Toposheet) NW 2 National Park Marine National Park ~ 5.20 (Source authenticated ESZ Map) North 3 Wild Life Sanctuary 4 Eco Sensitive Zone Marine Sanctuary ~ 1.8 (Source authenticated ESZ Map) NW GAGA Bird Sanctuary (Source authenticated ESZ Map) SW ESZ of Marine national park and marine Sanctuary Eco Sensitive Zone Area is not overlapping with existing Mining Lease Area, the Clearance has been given by Chief Conservator of Forest, Marine National Park, Jamnagar 5 Water Body Sea ~ 1.4 km (source ESZ letter by forest Department) North 6 CRZ Zone Sea Survey was carried out by Institute of Remote Sensing, Anna University, Chennai towards demarcation of High Direction - 30

31 S. No. Feature Name 7 River 8 Nearest station Railway From Project Site Distance (km) Tide, Low Tide Line for CRZ Mapping in or around Mining Lease Area. The Mining Lease Area affected under CRZ III Category is Sq.m. (0.3887Ha) in non-mining zone and non-mineralized. No mining activity has been/will be carried out. (source Map by Anna University) Seasonal Valotri river Passing through NE corner of ML (source Toposheet) East Rani river 3.60 km (source Toposheet) West Vedmati River 6.5 km (source Toposheet) East Bhatia 20 km (Source distance from Google Earth) SSW 9 Airport Jamnagar 80 km (Source distance from Google Earth) East 10 Highway State Highway no km (Source distance from Google Earth) Direction South Coastal Highway 6 10 km (Source distance from Google Earth) South 4.6 Existing Infrastructure Mine office, rest shelter, Drinking water facility, store room, canteen, Weigh Bridge, toilet and lavatory at the mine site. The other infrastructure is available in nearby villages. 4.7 Soil Classification The project area falls under North Saurashtra Agro-climatic Zone (GJ-6) and Agro-ecological region-10. The soils are medium black to shallow black, mixed red & black and coastal alluvial soils. Period ending March 2019, it was estimated qty. that only 8800 Mt. of Top Soil shall be generated and it shall be used for spreading on the backfilled area for plantation. 4.8 Climatic Data from secondary sources The climate in the region is characterized by a hot summer and general dryness except in the southwest monsoon season. The year may be divided into four seasons. The cold season from December to February is followed by the hot season from March to May. The period from June to September is the Southwest monsoon season. October and December constitute the post-monsoon or retreating monsoon season Temperature1 The period from March to May is one of continuous increase in temperatures. May is generally the hottest month with a mean daily maximum temperature of 32.1 C and mean daily minimum of about 21.2 C. The weather is intensely hot in summer and on some days the day temperature may reach up to 35.4 C. From November, both day and night temperatures begin to decrease rapidly. January is generally the coldest month with the mean daily maximum temperature at about 26.0 C and mean daily minimum at about 15.7 C. 31

32 4.8.2 Wind 1 Long term wind direction is presented in Table 4-4. During June to September, that is during the monsoon season wind blows mostly from south-west. During the period from October to February, wind mostly blows from north-east. During March to May wind mostly blows from west direction. Table 4-4: Month wise Predominant Wind Direction-Dwarka Month Predominant Wind First Second Evening Morning Evening Morning Evening Morning Evening January N N NE NW E W/NE February N NW NE W E N March N W W NW NW N April W W NW NW N SW May W W SW SW NW NW June SW SW W W S S July SW SW W W S S August W W SW SW S S/NW September W W SW SW NW NW October N W W/NW NW Calm N November N N NE NW E NE December NE N N NE E NW Rainfall1 The total annual rainfall in Dwarka region is mm out of which 357 mm i.e. ~95% was received during the months of monsoon which is from June to September with July as the rainiest month. Maximum rainfall in any one month was recorded in the month of July in year 1967 which was about mm Cloud Cover1 Long term cloud cover information is presented in Table 4-5. Table 4-5: Long Term Cloud Cover Information-Dwarka Month January February March April May June July August Cloud Amount No. of Days with Cloud Amount No. of Days with Cloud Amount (All Clouds) OKTAS (Low Clouds) OKTAS All Clouds Low Clouds 0 T T Indian Meteorological Department (IMD), Long Term Climatological Tables ( ), Dwarka 32

33 Month September October November December Cloud Amount No. of Days with Cloud Amount No. of Days with Cloud Amount (All Clouds) OKTAS (Low Clouds) OKTAS All Clouds Low Clouds 0 T T The area remains cloudy between June - September, which is the active period of the monsoon season Humidity1 Most humid conditions are found in the monsoons. Mornings are more humid than evenings and humidity ranges from a high of 85-88% in monsoon mornings to a low of 48-56% in winter evenings. During post-monsoon season, in morning humidity remains between % and in the evening it remains between 59-74%. Table 4-6: Average Meteorological Conditions at IMD Dwarka Month Mean Daily Temperature Max Min Rainfall (mm) Monthly Total No. of Rainy days Relative Humidity (%), Morning Relative Humidity (%), Evening January February March April May June July August September October November December Total / Mean Social Infrastructure The entire lease area is designated as Government Waste land. Mine site have all kind of facilities available including of office, urinal, mine Road, storage of drinking water and rest shelter. Site is about 0.81 km from the virpur village. Virpur is approachable only by a semi metallic road with combination of Kaccha road & passing through village Ran which is located about 11 km north of the tar road connecting village Limdi with Dwarka. Limdi is located on the Devbhumi Dwarka- Okha state highway no. 29 and is about 35km from Khambhalia. The nearest railway station is Bhatia, which is located on Okha- Devbhumi Dwarka- Rajkot-Viramgam broad gauge section of western railway and about 20 km from the site. The nearest sea port is Okha which is about 105 km from Village Virpur. State Highway 29 is located ~12 km South direction of the lease area. Coastal Highway CH-6 is at distance of ~10 Km in south direction of lease.bhatia which is about 35km from mine site have all kind of educational and medical facilities available. 33

34 5 PLANNING BRIEF 5.1 Planning Concept (Type of industries, facilities, and transportation etc.) Town and Country Planning/ Development Authority Classification Type of Industry: Mining of Bauxite Present Proposal: For enhancement of bauxite production from 80,000 TPA to TPA in addition of removal of Topsoil 8,800 TPA & OB/waste 2,22,080 TPA with Total Excavation 5,31,635 TPA. Facilities: Mine office, rest shelter, Drinking water facility, store room, Weigh Bridge, canteen, toilet and lavatory. Transportation: Bauxite will be transported through trucks to the plants of DRL. 5.2 Population Projection This is an existing mine. Temporary influx of people will be there as the managerial and supervisory staff will generally be from outside the area. Suitable local people has been /will be appointed preferably in the mine. Hence project will not contribute significantly in the decadal population. 5.3 Landuse Planning (BREAKUP ALONG WITH GREEN BELT ETC.) Table 5-1: Land Use Pattern at site (in Ha) Heads Existing After Plan period Conceptual stage a) Pits & Quarries (Within) (Backfilling : Ha & water reservoir :60.65 Ha) b) Dumps of Waste & O.B c) Mineral Stack c) Infrastructure including of office, urinal, magazine& Mine Road etc d) Township (Colony & School) e) Others Barren land Crop land f) Undisturbed area affected under CRZ III Category/ Non Mining Zone Total occupied area At present about 8 ha area is under plantation. About 1500 No. of saplings per hectare is proposed to be planted within the existing plantation area to improve aesthetic beauty. Measures will be adopted to ensure survival & protection of plantation. At the end of the life of mine, about ha area shall be under plantation including backfilled area. 5.4 Assessment of Infrastructure Demand This is an existing Mine. There will be negligible additional impact as the existing infrastructure will be sufficient for the expansion project. Existing social and physical infrastructure are sufficient to cater to the requirement. The mine site is well connected to the nearest state highway. 34

35 5.5 Amenities / Facilities The mine is working mine and following infrastructure is available at site Mine office Rest shelter Drinking water facility Store room Weigh bridge canteen Toilet & Lavatory etc. 35

36 6 PROPOSED INFRASTRUCTURE 6.1 Industrial Area (Processing Area) Not applicable. 6.2 Residential Area (Non-Processing Area) Not applicable. This is an existing mine. Suitable local people has been /will be appointed in the mine. Temporary influx of people will be there as the managerial and supervisory staff will generally be from outside the area. 6.3 Social Infrastructure Detailed in Section Connectivity (Traffic and Transportation Road / Rail / Metro / Waterways) As per Section Drinking Water Management (source & supply of water) Detailed in Section and Section Sewerage System Toilet facility has been provided at site. The generated sewage is channelized to septic tank followed by soak pit. 6.7 Power Requirement and Supply / Source Discussed in Section Industrial Waste Management Discussed in Section Solid Waste Management Discussed in Section Rehabilitation and Resettlement (R& R) Plan Not applicable as this is an existing mine and no additional land purchase is involved. 36

37 6.11 Project Schedule and Cost Estimates LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF COMPLETION (TIME SCHEDULE FOR THE PROJECT WILL BE GIVEN) The mine lease is working site of DRL however; DRL will start production at proposed rate only after obtaining necessary clearance from Central and State Government Estimated Project Cost ALONG WITH ANALYSIS IN TERMS OF ECONOMIC VIABILITY OF THE PROJECT Estimated cost of the proposed expansion would be around Rs lacs only. This cost includes the project expenditure towards the Bauxite mine. The mine has been sanctioned by the Government for captive consumption; hence the profitability factor does not arise at this stage. 37

38 7 ANALYSIS OF PROPOSAL Local labourers will be employed from the nearby villages as per this mine operation. Financial and Social Benefits with Special Emphasis on the Benefit to the Local People including Tribal Population, if any, in the Area Critical analysis of the existing socio-economic profile of the area vis-à-vis its scenario with proposed project activities identifies the following: Collectively mining (present in the Region since more than 5 decades) can however be considered a significant economic activity in the Region. Supporting infrastructure (essentially roads & power supply) is already in place. Consequently, the possibility of this project triggering significant ancillary developments seems unlikely. However, the proposed activities shall generate direct and indirect employment in the region due to the requirement of workers in supply auxiliary such as higher machinery service and Ore Transport service afford from the ancillary works, which would marginally improve the economic status of the people. About 137 employees shall be appointed in the mine after proposed expansion. Preference shall be given suitable local people. This will upgrade the economic status of the region and people living therein. Further the additional benefits from the downstream units such as iron industry, steel industry, cement plant, and metallurgical industry also add value to the society. The PP proposes for sustainable development as per the Companies Act 2013 and its subsequent notifications. As per the MoEF&CC office memorandum dated 1 st May 2018, an amount of 1% (about Rs. 85,000/-) of the total project cost shall be spent as Corporate Environmental Responsibility (CER) for betterment of surroundings. Based on the Need based Assessment, community development program shall be taken up for the betterment of the locals. 38

39 Annexure 1: Name Change Certificate 39

40 Annexure 2: Transfer order & ML deed 40

41 41

42 42

43 43

44 44

45 45

46 46

47 47

48 48

49 49

50 50

51 51

52 52

53 53

54 Annexure 3: Recommendation of District Geologist, DGM, Devbhumi Dwarka for Extension of Lease validity under MMDR Amendment Act

55 Translated copy of Recommendation of District Geologist, DGM, Devbhumi Dwarka for Extension of Lease validity under MMDR Amendment Act

56 Annexure 4: Copy of Previous Environmental Clearance 56

57 57

58 58

59 59

60 60

61 61

62 62

63 Annexure 5: NOC and previous & current CTOs obtained from GPCB 63

64 64

65 65

66 66

67 67

68 68

69 69

70 70

71 71

72 72

73 73

74 74

75 75

76 Annexure 6: Copy of approval of Mining plan 76

77 77

78 78

79 Annexure 7: Copy of letter issued by CCF regarding Eco sensitive zone 79

80 Translated Copy of letter issued by CCF regarding Eco sensitive zone 80

81 Annexure 8: Certified Map Showing ESZ & ML Boundary by Chief Conservator of Forest (CCF), Marine National Park 81

82 Annexure 9: CRZ Map prepared by Institute of Remote Sensing, Anna University, Chennai 82

83 CRZ Report by Institute of Remote Sensing, Anna University, Chennai 83

84 84

85 85

86 86

87 87