Contractor Purchasing Systems Reviews (CPSR) The Current CPSR Environment. Bryan Felber, Director of Purchasing & Compliance
|
|
- Alfred Baldwin
- 5 years ago
- Views:
Transcription
1 Contractor Purchasing Systems Reviews (CPSR) The Current CPSR Environment Bryan Felber, Director of Purchasing & Compliance
2 Cautions This will not be a complete CPSR primer If you are new to CPSRs, get fully immersed and trained in all aspects of CPSR 98% of companies fail their first CPSR There are lots of companies and consultants that offer training and CPSR prep assistance 2
3 Cautions (continued) Expectations and requirements change over time New guidance from DCMA HQ Different auditors and interpretations Changes in regs Different people have different opinions as to requirements/expectations Contractors Auditors Consultants Imperative to keep current and monitor 3
4 Resources LinkedIn Contractor Purchasing System Review (CPSR) Forum CPSR Helps and Hints FAR & DFARS Discussions Various training opportunities Webinars Seminars 4
5 CPSR Who is Impacted Even if not on the CPSR radar all are subject to the regs in their contracts. READ YOUR CONTRACT!! If , Subcontracts, is in your contract, consent, notification, etc., apply If , Business Contractor Business Systems, You must establish and maintain acceptable business systems in accordance with the terms and conditions of the contract. If , Contractor Purchasing System Administration, your system must be CPSR compliant DCMA usually goes by the $25M threshold, but can mandate a CPSR ANYTIME!!! 5
6 CPSR It s a brave new world! Expectations in the past very different than Review is much more formal and rigorous Companies doing the same thing under successful CPSRs 3 or 4 years ago are failing Questionable Review Team interpretations/application of regs 6
7 What to Expect Generally 2 weeks duration, with 2 or more analysts Data call comes about two months prior to the review Important to be able to segregate POs properly to exclude those not subject to review Template Selected POs provided ~1 week in advance of arrival Electronic files 7
8 What to Expect (Cont) Entrance conference Questionnaires provided before or upon arrival: Training Procurement Authority Purchase requisition through purchase order Internal Audit Parts Management Receiving Vendor Rating System Close out process Written questions/observations on purchase files, response required within 24 hrs 8
9 What to Expect (Cont) Interviews of Buyers Daily debriefs of observations, concerns Exit conference Report promised to ACO about a month after conclusion of CPSR Please don t hold your breath 9
10 What They Look For Policies: Cover all the bases Emerging expectation: split awards Public law compliance TINA certs must be in the form at FAR , including FAR references CAS notification within 30 days of award DPAS: written acceptance in required time Price/cost analysis Reps and certs SAM 10
11 What They Look For (Cont) Debarment SAM? Day of award cert Actual cert In forms, agreements, POs To be valid, agreements/orders must be signed or accepted in writing Evidence of written acceptance of small bus plans 11
12 What They Look For (Cont) Source Justifications Adequate support Customer directed: attach evidence Teammate: Attach teaming agmt and/or contract proposal identifying teammates Economically justified: Have analysis Only known source: explain, document market research 12
13 What They Look For (Cont) Commerciality Com l Item Determination form not enough Need support to prove commerciality Your own market research Proof vendor has sold or offered for sale commercially If not adequately supported, vendor to be treated non-commercially If $750K, TINA cert required 13
14 What They Look For (Cont) Misc. DCMA does not accept the use of GSA schedules for price analysis (based on MAR 2014 DoD directive). Subcontractor Financing - especially progress payments and financing on FFP awards Policy on Split Awards Negotiation of all noncompetitive awards. You might diplomatically push back, but be SURE to have clean and effective price analyses 14
15 Buyer Interviews How long have you been a buyer with company? Who does your cost/price analysis? Who does your source justifications? Who s responsible for reps/certs (review, location)? Who does expediting reports and how often? How do you do best value? How do you validate commercial item determinations? During RFP, do you check Ts & Cs, reps/certs before sending? Do you have adequate time to process PRs? Does management support me? 15
16 Buyer Interviews (cont) What is the extent of competition? How well does Purchasing work with other depts? How often have I been told to go to a specific vendor? Policies & procedures. Do you have a policy on counterfeit avoidance? How do you avoid counterfeits? How often do we do training? Do we have waste, fraud, abuse signs in our building? Do I get what I need from management? If I was a manager, what type of training would I see the need for? 16
17 Questionable Application Intercompany orders DCMA expected: TINA and CAS applicability Small bus plans Anti-lobbying and Exec Comp Make/buy analysis Explanation why intercompany transaction is in the best interest of the government Price/cost analysis 17
18 Questionable Application (Cont) Intercompany orders useful definitions: Contractor means the total contractor organization or a separate entity of it, such as an affiliate, division, or plant, that performs its own purchasing Subcontractor means any supplier, distributor, vendor, or firm that furnishes supplies or services to or for a prime contractor or another subcontractor Make item,... means an item or work effort to be produced or performed by the prime contractor or its affiliates, subsidiaries, or divisions (b) Affiliates means associated business concerns or individuals if, directly or indirectly-(1) Either one controls or can control the other; or (2) A third party controls or can control both Subcontract (except as used in ) also includes a transfer of commercial items between divisions, subsidiaries, or affiliates of a contractor or a subcontractor (10 U.S.C. 2306a(h)(2) and 41 U.S.C. 3501(a)(3))
19 Questionable Application (Cont) Intercompany TINA and Small Business Plans: DCAA Memorandum PSP / , March 2, 2010, excludes TINA applicability to interorganizational transfers. DCMA Small Business analyst confirmed in 2014:, The affiliate/other division, does NOT do a plan for you as the prime 19
20 Questionable Application (Cont) Intercompany make/buy and price/cost analysis: Make/Buy analysis only done if doing out of the ordinary, e.g., buying something we usually make, vice versa only applies Part 15 requirements to transfers of commercial items Just as purchasing does not do a make/buy analysis on items normally proposed as make items by the awarded entity, we would not do a make/buy analysis for items made by an affiliate Just as purchasing doesn t perform price/cost analysis on the make portions of the contract awarded to the contractor, it also does not perform price/cost analysis of an affiliate 20
21 Questionable Application (Cont) Orders below micro-purchase threshold Selected a good number (28%) Recommend procurement files include documentation supporting the vendor selected and a fair and reasonable price. DFARS (c)(4) 21
22 Questionable Application (Cont) Orders below micro-purchase threshold FAR (a) Solicitation, evaluation of quotations, and award. (1) To the extent practicable, micro-purchases shall be distributed equitably among qualified suppliers. (2) Micro-purchases may be awarded without soliciting competitive quotations if the contracting officer or individual appointed... considers the price to be reasonable. (3) The administrative cost of verifying the reasonableness of the price for purchases may more than offset potential savings from detecting instances of overpricing. Therefore, action to verify price reasonableness need only be taken if -(i) The contracting officer... suspects that the price may not be reasonable, or (ii) Purchasing a supply or service for which no comparable pricing information is readily available (b) Documentation. If competitive quotations were solicited and award was made to other than the low quoter, documentation to support the purchase may be limited to identification of the solicited concerns and an explanation for the award decision. 22
23 Questionable Application (Cont) Ts & Cs They faulted us for having terms that restrict subcontractor/vendor contact with our customer Privity of contract Prime contractor is the one responsible for performance Unrestricted contact can create problems the subcontractor saying or providing something with which we disagree and on which the government relies duplication of effort where the sub provided something that the prime also supplied constructive changes adopted by the subcontractor without our knowledge and which we might have prevented Order of precedence: Some teams say FAR should be 1st, though says otherwise AND orders with subs are commercial transactions, even if not com l items. 23
24 Questionable Application (Cont) Consultants Analyst said anything charged directly to a govt contract One consultant has seen the following in data calls in several CPSRs this year: "Purchases excluded from the universe:... Consulting Agreements (where the consultant is a contract hire, acting as an employee of the company, under the direct supervision of company personnel)" Past Team Lead and Jeff White have same application Subcontract means any agreement (other than one involving an employer-employee relationship) entered into by a Government prime contractor or subcontractor calling for supplies and/or services required for performance of the contract, contract modification, or subcontract. (FAR ) 24
25 Hints Ensure s have clear references to attachments, approval requests, etc. Interviewees should not guess at answers, but if they don t know, say they know where to go to find answers (policies, procedures, regulations, management). Be sure POs are carefully reviewed before they go out Especially for things not manually entered in PO, but which come from other inputs that appear on the PO 25
26 Additional Expectations When a file review is requested, any and all underlying agreements must also be provided, e.g.,: SubK, ICA, BOA, IDIQ, TO/DO, Mod The final award documents of any award with a total anticipated award value $750K should be reviewed by management before it is issued and follow up review within 30 days. Keep up with closeouts 26
27 Penalties for Failure 5% to 10% payment withholds for one or more business system failures Inability to bid on contracts that require approved system Competitive disadvantage in bidding on contracts which consider system approval in evaluation Requirement for prior consent to subcontract Additional oversight by other agencies Corrective action plan Impact to reputation 27
28 Questions? 28
29 Bryan Felber, CPCM, CFCM 29
Purchasing System (Including Counterfeit Parts)
Purchasing System (Including Counterfeit Parts) Steven M. Masiello Joseph G. Martinez April 26, 2016 McKenna Government Contracts, continuing excellence at Dentons Agenda Purchasing system overview Contractor
More informationSubcontract Management Regulatory Compliance - The Most Current Trends and Issues
Subcontract Management Regulatory Compliance - The Most Current Trends and Issues Breakout Session #: B16 Presented by: Jeffery A. White, C.P.M. Date: July 22, 2013 Time: 2:30 3:45 Subcontract Compliance
More informationThe New Purchasing System Review
The New Purchasing System Review Presented by J.A. White & Associates, Inc. Date 17 October 2012 We re drowning in information and starving for knowledge. -Rutherford D. Rodgers 2 Goal of This Session
More informationGC-153. Preparing for the CPSR A Practical Guide. Presented By: Susan Longo, Supervisor, Watkins Meegan Rich Wilkinson, Director, Watkins Meegan
GC-153 Preparing for the CPSR A Practical Guide Presented By: Susan Longo, Supervisor, Watkins Meegan Rich Wilkinson, Director, Watkins Meegan Session Content Background Where to Start (And, It s Not Where
More informationAdvantages of Having an Approved Purchasing System
Advantages of Having an Approved Purchasing System Presented by CohnReznick s Government Contracting Industry Practice Rebecca Kehoe, Esq., Manager & Roy Conley, Senior Manager PLEASE READ This presentation
More informationCPSR Expectations Before, During and After Review
CPSR Expectations Before, During and After Review Breakout Session #: C04 Andrew C. Obermeyer, Director, Business Operations Center, Defense Contract Management Agency Karen M. Ouellette, Procurement Analyst,
More informationPreparing for a CPSR Audit
Preparing for a CPSR Audit Presented by Phil Bail Phil Bail & Associates 3/18/2015 1 What is your experience with CPSR s? I have no real idea what a CPSR audit is. My company has a government approved
More informationTimes Are Changing: Contractor Purchasing System Review Expectations and Realities for 2017
Times Are Changing: Contractor Purchasing System Review Breakout Session #: E06 Presented by: E Jean Labadini Michael Carter Date: 7/25/17 Time: 2:30 3:45 1 Take Aways The most recent changes to the CPSR
More informationContractor Estimating Systems: System Adequacy Standards and Key Compliance Issues
McKenna Government Contracts, continuing excellence in Dentons Contractor Estimating Systems: System Adequacy Standards and Key Compliance Issues Joe Martinez, Esq. Dentons US LLP Michael Steen, CPA Redstone
More informationContractor Purchasing System Review, an Alternative Perspective
Contractor Purchasing System Review, an Alternative Perspective Breakout Session # D01 Jack Hott, CPCM, CFCM, Fellow Michael Thacker, Senior Contract Specialist, RSI Date: March 18, 2016 Time: 9:00 am
More informationContractors Purchasing System Review
Contractors Purchasing System Review Jeffery A. White, C.P.M. February 2016 Our Mission Statement With constant and ever changing challenges in a procurement environment, J.A. White & Associates, Inc.
More informationDefective Pricing- Material Pricing Deficiencies. Next Slide
Defective Pricing- Material Pricing Deficiencies Table of Contents Risk Assessment Research and Planning Risk Assessment - Initial Data Obtained from Contractor Risk Assessment Overrun or Underrun Analysis
More information2018 National Contract Management Association Boston Workshop
2018 National Contract Management Association Boston Workshop Hot topics March 7, 2018 Agenda DCAA/DCMA update DCAA accounting system pilot Purchasing system 2018 National Defense Authorization Acts DCAA
More informationDFARS Business Systems Compliance. March 11, 2015
DFARS Business Systems Compliance March 11, 2015 Speakers Steven Tremblay Ernst & Young Executive Director Government Contract Services Jack Gay Ernst & Young Senior Manager Government Contract Services
More informationA cost analysis is required for any negotiated (non competitive) contract procurement on behalf of any University program, if:
SECTION 7: ACQUISITION PROCEDURES SUBJECT: COST ANALYSIS PROCEDURE 7.4.2 POLICY: A cost analysis is required for any negotiated (non competitive) contract procurement on behalf of any University program,
More informationMake or Buy Decisions in a Proposal Audit. Next Slide
Make or Buy Decisions in a Proposal Audit Table of Contents Risk Assessment Research and Planning Risk Assessment Initial Review of Proposal Risk Assessment Coordination with the PCO and ACO Preliminary
More informationUnderstanding the DCAA Audit Process and How to Prepare for Success
Understanding the DCAA Audit Process and How to Prepare for Success Breakout Session #: C11 Presented by: Beverly Arviso, CPA, Fellow, CPCM, CFCM Date: July 22, 2013 Time: 4:00-5:15 DCAA s Mission Compliance
More informationUnderstanding Contractor Purchasing System Reviews
Understanding Contractor Purchasing System Reviews Breakout Session #A01 Andrew C. Obermeyer, Director, DCMA Business Operations Center March 12, 2015 10:45am - 12:00pm Centralized Lines of Service Business
More informationAs any contractor knows that
16 Contract Management August 2011 Contract Management August 2011 17 contractor purchasing system reviews a tale of two companies As any contractor knows that has undergone a contractor purchasing system
More informationHow to Prepare a DCAA Compliant Cost or Price Proposal. Bag Lunch Webinar November 17, 2016
How to Prepare a DCAA Compliant Cost or Price Proposal Bag Lunch Webinar November 17, 2016 Presenter: Paul H. Calabrese Rubino & Company, CPAs & Consultants Senior Manager Tel: 301 214 4137 pcalabrese@rubino.com
More informationDeveloping a Compliant Procurement Policy. Bag Lunch Webinar August 29, 2017
Developing a Compliant Procurement Policy Bag Lunch Webinar August 29, 2017 Co-Presenter: Presenter: Jenny E. Herrera, CPA CGMA Rubino & Company, CPAs & Consultants Shareholder Tel: 301-214-4179 jherrera@rubino.com
More informationPOLICY AND PROCEDURES FOR THE DOD PILOT MENTOR-PROTEGE PROGRAM (Revised August 12, 2008)
POLICY AND PROCEDURES FOR THE DOD PILOT MENTOR-PROTEGE PROGRAM (Revised August 12, 2008) I-100 Purpose. (a) This Appendix I to 48 CFR Chapter 2 implements the Pilot Mentor-Protege Program (hereafter referred
More informationDFARS Appendix I. Appendix I Policy and Procedures for the DoD Pilot Mentor- Protégé Program TABLE OF CONTENTS. I-100 Purpose. I-101 Definitions.
DFARS Appendix I Appendix I Policy and Procedures for the DoD Pilot Mentor- Protégé Program I-100 Purpose. I-101 Definitions. I-102 Participant eligibility. I-103 Program duration. I-104 Selection of protege
More informationGovernment contracting hot topics
Government contracting hot topics NCMA Boston workshop 13 March 2019 Written by Agenda Other Transaction Authority current trends Section 809 Panel Business system updates Cybersecurity Audit guidance
More informationMETHODS OF CONTRACTING
METHODS OF CONTRACTING Your CON 120 pre-class assignment is to read and be prepared to use the following material in classroom exercises and case studies. Please note that this chart includes only the
More informationCommercial Item Subcontracting
Commercial Item Subcontracting Jeffery A. White, C.P.M. January 2018 Our Mission Statement With constant and ever changing challenges in a procurement environment, our mission is to be the most Trusted
More informationBest Practices in Dealing with the DCAA
Best Practices in Dealing with the DCAA Bag Lunch Webinar December 7, 2016 1 Presenter: Paul H. Calabrese Rubino & Company, CPAs & Consultants Senior Manager Tel: 301-214-4137 pcalabrese@rubino.com www.linkedin.com/pub/paul-calabrese/20/293/645/
More informationGeneral Procurement Guidelines
Procurement Department 2 Space Drive Taylors, SC 29687-6072 (864) 355-1279 Fax (864) 355-1283 The School District of Greenville County General Procurement Guidelines 2016-2017 The Board of Trustees of
More informationImproper Billing of Costs on Progress Payments 1
Improper Billing of Costs on Progress Payments 1 1 Progress payments are not interim vouchers or invoices that the government pays based on the allowable costs incurred and charged to the contract. Instead,
More informationSTUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 4, Lesson 1 Differences between Cost & Price Analysis
STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 4, Lesson 1 Differences between Cost & Price Analysis April 2018 STUDENT PREPARATION Required Student Preparation Read FAR subpart 15.4,
More informationSTUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 4, Lesson 1 Differences between Cost & Price Analysis
STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 4, Lesson 1 Differences between Cost & Price Analysis July 2018 STUDENT PREPARATION Required Student Preparation Read FAR subpart 15.4,
More informationProcurement Under the New Requirements 1
Requirements 1 Procurement under the New Requirements 1 Why This Session Is Needed New provisions in Uniform Guidance Changes to conflict of interest requirements in Uniform Guidance Distinctions between
More informationSTUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems
STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems January 2017 CON170, Unit 5 Lesson 1 Cost Analysis Process and Players
More informationSubcontract Management &
Subcontract Management & What if you were to discover that your subcontract management department has been accused of misappropriating funds, violating laws, and operating under poor business practices?
More information"The Price is Right!" Commercial Item/GSA Schedule Contracting Jack G. Horan Phillip R. Seckman
"The Price is Right!" Commercial Item/GSA Schedule Contracting Jack G. Horan Phillip R. Seckman 2 3 Commercial Item Acquisition FAR Part 12: Prescribes policies and procedures unique to the acquisition
More informationSubcontractor and Vendor Kickbacks. Next Slide
Subcontractor and Vendor Kickbacks Table of Contents Risk Assessment Research and Planning Preliminary Analytical Procedures Entrance Conference Audit Team Brainstorming for Fraud Risk Assessment Results
More informationHUD-US DEPT OF HOUSING & URBAN DEVELOPMENT: Overview of Procurement Policies and Procedures
Final Transcript HUD-US DEPT OF HOUSING & URBAN DEVELOPMENT: Overview of Procurement Policies and Procedures SPEAKERS Petergay Bryan Booth Management Consulting Virginia (Ginger) Holman PRESENTATION Moderator
More informationADDENDUM NO. 1 Kansas City Area Transportation Authority 1350 E. 17 th Street Kansas City, Missouri 64108
ADDENDUM NO. 1 Kansas City Area Transportation Authority 1350 E. 17 th Street Kansas City, Missouri 64108 REQUEST FOR PROPOSAL (RFP) 18-4016-28A TEMPORARY STAFFING AGENCY SERVICES Issue Date: December
More informationContract and Procurement Fraud
Contract and Procurement Fraud Performance Schemes 2018 Association of Certified Fraud Examiners, Inc. Invoicing Schemes Vendor submits fraudulent invoices to generate false payments. False invoices Inflated
More informationEdmore School District Policies
Recommended FOOD SERVICE PROCUREMENT POLICY Descriptor Code: HCAF The District shall adhere to the most restrictive of federal, state, and school district standards (see HCAA-E) for the procurement of
More informationThe Contracts Crunch. Jennifer Eastman Senior Product Marketing Specialist, Deltek. Melissa Amdahl Product Manager, Compusearch.
The Contracts Crunch Jennifer Eastman Senior Product Marketing Specialist, Deltek Melissa Amdahl Product Manager, Compusearch February 26, 2015 12:00 p.m. 1:00 p.m. (Eastern) About the Presenters Jennifer
More information12 Essentials to a Successful DCMA Contractor Purchasing System Review
12 Essentials to a Successful DCMA Contractor Purchasing System Review By Stephen Chase Kunk, J.D. Vice President, Contracts & Procurement/Senior Manager 2 12 Essentials to a Successful DCMA Contractor
More informationProcurement Under Uniform Guidance
Procurement Under Uniform Guidance September 21, 2018 Presenters Manju Patnaik, CPA Professional Standards Technical Manager Manju is a technical audit manager with 13 years of experience serving our public
More informationSUBRECIPIENT MONITORING GUIDE
SUBRECIPIENT MONITORING GUIDE Introduction The following Roles and Responsibilities Chart serves as a reference for University of Arizona Principal Investigators and designated department personnel (Business/Finance
More informationSECTION 6.2: CONTRACT MANAGER
: Section 287.057(15), Florida Statutes, requires the department, for each contractual service contract, to designate an employee to be responsible for enforcing the performance of the contract terms and
More informationProcurement Requirements under the Uniform Administrative Guidance
Procurement Requirements under the Uniform Administrative Guidance Purpose: This Technical Assistance Guide has been developed to assist Local Workforce Development Areas (LWDAs) in making informed decisions
More informationProcurement Standards Expectations Document
Procurement Standards Expectations Document Certain of the procurement requirements of 2 CFR 200 are explicit statements of what the University would consider as general expectations of any University
More informationOCEAN COUNTY COLLEGE PURCHASING MANUAL
OCEAN COUNTY COLLEGE PURCHASING MANUAL 1 OCEAN COUNTY COLLEGE PURCHASING MANUAL Issued by the Office of the Vice President of Finance & Administration January 1, 2014 The purpose of this manual is to assist
More informationSalt Lake Community College Policies and Procedures
COLLEGE PROCUREMENT POLICY Board of Trustees Approval: 04/12/2017 POLICY 10.01 Page 1 of 1 I. POLICY All products and services purchased by the College shall be procured in compliance with applicable statutes,
More informationFISCAL: PROFICIENCY IN PROCUREMENT
FISCAL: PROFICIENCY IN PROCUREMENT CAPLAW 2009 National Training Conference June 25, 2009 9:00 a.m. 11:00 a.m. Seattle, WA Kay Sohl 3343 NE 18th Ave Portland, OR 97212 P: (503) 314-8265 kay@kaysohlconsulting.net
More informationRecent Changes in Definitions and Determinations of Commerciality: How They Can Affect Your Products and Services Sold to the Federal Government
Recent Changes in Definitions and Determinations of Commerciality: How They Can Affect Your Products and Services Sold to the Federal Government Presented by Darrell Hineman, CPA, CFE, Director Donald
More informationForward Pricing Proposal- Labor Categories. Next Slide
Forward Pricing Proposal- Labor Categories Table of Contents Risk Assessment Research and Planning Initial Discussion with Contractor s Representative and Request for Information Preliminary Analytical
More informationDAU Hot Topics Forum on: Using commercial items to increase innovation, increase competition and lower costs
DAU Hot Topics Forum on: Using commercial items to increase innovation, increase competition and lower costs John Tenaglia Deputy Director, DPAP/CPIC 19 July 17 1 Briefing Overview Status of Current Guidance
More informationNETWORX PROGRAM INDIVIDUAL SMALL BUSINESS SUBCONTRACTING PLAN IDIQ TASK ORDER BASED
NETWORX PROGRAM INDIVIDUAL SMALL BUSINESS SUBCONTRACTING PLAN IDIQ TASK ORDER BASED Company Name: Qwest Government Services, Inc. (QGSI) Address: 4250 N. Fairfax Drive Arlington, VA 22203 Date Submitted:
More informationGeneral Policy - Purchasing
General Policy - Purchasing Policy: All purchases of commodities (supplies, materials, equipment, printing, insurance, and leases of equipment) and services (furnishing of labor and time and effort by
More informationPSP A/ March 28, PSP-003(R)
DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 IN REPLY REFER TO PSP 730.5.1.A/2012-004 March 28, 2013 13-PSP-003(R) MEMORANDUM FOR
More informationContractor Business Systems Earned Value Management, Material Management and Accounting, and Property Management
McKenna Government Contracts, continuing excellence in Dentons Contractor Business Systems Earned Value Management, Material Management and Accounting, and Property Management Michael McGuinn, Dentons
More informationSponsored Funds (FAO=GR) Supplier Price Justification Conflict Information (SSPJCI) Form
Sponsored Funds (FAO=GR) Supplier Price Justification Conflict Information (SSPJCI) Form SPJCI Form What is it? A Sponsored Funds Supplier Price Justification Conflict Information Form is a 5-page form
More informationTitle: PROCUREMENT Last Update: March 24, Responsible Officer: Mark Savoff I. POLICY SUMMARY
Page 1 of 21 Subject Matter Expert: Mark Chapman Responsible Officer: Mark Savoff Approved By: Corporate Compliance Committee Approval Date: May 31, 2001 I. POLICY SUMMARY This policy outlines the guidelines
More informationCONSTRUCTION MANAGEMENT SERVICES
DrAFTDRAFTdd EXHIBIT 1 CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR QUALIFICATIONS (RFQ) SELECTION PROCESS School District of Lee County, Florida TABLE OF CONTENTS 1. INTRODUCTION 1 Lobbying 2 2. 3 A.
More informationTop 10 Cost/Price Proposal Missteps
Baker Tilly Government Contractor Advisory Services Top 10 Cost/Price Proposal Missteps NCMA San Diego Chapter April 18, 2018 Faux Pas Preview > Cost/Price Proposal as a Sales Document 1. Poor alignment
More informationGROUND RULES AND PRICING INSTRUCTIONS:
GROUND RULES AND PRICING INSTRUCTIONS: F-22 REPLENISHMENT SPARES PRICING CY2013 CY2017 REQUIREMENTS CONTRACT (MRC) WITH VARIABLE QUANTITIES I. GENERAL INSTRUCTIONS: The objective of this Spares Requirements
More informationARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES
ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES Section I Application (These procedures do not apply to Design-Build Contracts.)
More informationPrice to Perform: Winning the Battle of Business in an Austere Environment
Title Price to Perform: Winning the Battle of Business in an Austere Environment Breakout Session B04 Jacob George Director of Finance Red Team Consulting November 18, 2013 2:15pm 3:30pm 1 Agenda Introductions
More informationManager, Sourcing Supply and Contracts, Grid Projects Approved By:
Procurement Policy ISSUE DETAILS Effective Date: 1 Policy Owner: Chief Executive Officer Written By: Manager, Sourcing Supply and Contracts, Grid Projects Approved By: Transpower Board of Directors Minute
More informationComprehensive List of Fraud Indicators
Comprehensive List of Fraud Indicators This document provides links to our contract audit resources. The scenarios are grouped by audit type, but the issues presented could be applicable to other audits
More informationUniform Guidance Purchasing Updates. What University Administrators and PIs Need to Know
Uniform Guidance Purchasing Updates What University Administrators and PIs Need to Know Executive Summary The Uniform Guidance (UG) governs the management of federally funded sponsored projects across
More informationMicro Purchase & Small Purchase Procurement
Micro Purchase & Small Purchase Procurement Informal Procurement Methods Regulations Micro Purchases 200. 320(a) 200.67 Small Purchase Procedures 200.320(b) 200.88 Procedures in a nutshell State Agency
More informationTEAMING, SUBCONTRACTING, AND JOINT VENTURES
888 17 th Street, NW, 11 th Floor Washington, DC 20006 Tel: (202) 857-1000 Fax: (202) 857-0200 TEAMING, SUBCONTRACTING, AND JOINT VENTURES 2013 NATIONAL HUBZONE CONFERENCE SEPTEMBER 10, 2013 Presented
More informationContract and Procurement Fraud
Contract and Procurement Fraud Fraud in Procurement Without Competition 2018 Association of Certified Fraud Examiners, Inc. Sole-Source Awards The procurement process is noncompetitive through the solicitation
More informationINTERNAL AUDIT OF PROCUREMENT AND CONTRACTING
OFFICE OF THE COMMISSIONNER OF LOBBYING OF CANADA INTERNAL AUDIT OF PROCUREMENT AND CONTRACTING AUDIT REPORT Presented by: Samson & Associates February 20, 2015 TABLE OF CONTENT EXECUTIVE SUMMARY... I
More informationUnderstanding Contractor Team Arrangements in the GSA FSS Environment
1 Understanding Contractor Team Arrangements in the GSA FSS Environment Breakout Session #: B17 Tommy Benton, Senior Procurement Analyst Date: Monday, July 25 Time: 2:30pm 3:45pm 2 Learning Objectives
More informationPHASE 4 - Post-Award. Type of Feedback Type of Contract Feedback Category Feedback
PHASE 4 - Post-Award Type of Feedback Type of Feedback Category Feedback Commodity (Competitive) Use of the Bid Evaluation Model (BEM), when validated, is a best practice approach to evaluating competitive,
More informationRoger D. Duke Vice President -Contracts & Procurement. September 21, 2016
MINDING THE GAPS BETWEEN THE PRIME CONTRACT AND SUBCONTRACT(S) Roger D. Duke Vice President -Contracts & Procurement September 21, 2016 The 1 concepts expressed herein are solely my own and do not necessarily
More informationPurchasing Policy Update: Implementation of the Uniform Guidance Procurement Standard. Katie Cattrell, Training Specialist
Purchasing Policy Update: Implementation of the Uniform Guidance Procurement Standard Katie Cattrell, Training Specialist 1 Agenda 1. Background and Timeline 2. Procurement Thresholds 3. Procurement Standards
More informationKeeping your Business Systems Current in Response to DCAA Initiatives and Emerging Regulations
Keeping your Business Systems Current in Response to DCAA Initiatives and Emerging Regulations James W. Thomas PricewaterhouseCoopers LLP Brian D. Taylor Accenture Federal Services Business Systems and
More informationProcurement. Pete McLoughlin Financial Management Section Head Office for Food and Nutrition Programs
Procurement Pete McLoughlin Financial Management Section Head Office for Food and Nutrition Programs USDA Non-Discrimination Statement In accordance with Federal civil rights law and U.S. Department of
More informationContractor Business System MMAS
Contractor Business System MMAS Material Management and Accounting System Presented By: Dan Jackson January 15, 2013 Administrative Remarks Mute Button Questions Will attempt to capture any questions submitted
More informationPURCHASING CHAPTER 3 POLICY 3-11
A. GENERAL The function of the Purchasing Office is to be of service to all City Divisions in the procurement of goods, materials, supplies, equipment, and services at the lowest possible cost consistent
More informationDCMA INSTRUCTION 2501 CONTRACT MAINTENANCE
DCMA INSTRUCTION 2501 CONTRACT MAINTENANCE Office of Primary Responsibility: Contract Maintenance Capability Effective: August 14, 2017 Releasability: Cleared for public release New Issuance Incorporates:
More information6/15/2017. In SY 17-18, foodservice procurement records will be reviewed from SY How do I prepare? CSNA June 2017
How do I prepare? CDE OSN: Colorado Department of Education Office of School Nutrition. LEA (local education agency): your district or charter school. Procurement: multi-step competitive process to obtain
More informationConstruction Contracts
Construction Contracts By Dr. Ibrahim Assakkaf Construction Contracts By Dr. Ibrahim Assakkaf 1 The Need Web-based Contracts Supporting scheduling Controlling Regulating Analyzing Auditing the procurement
More informationDFARS Accounting System Reviews
DFARS Accounting System Reviews Presented by CohnReznick s Government Contracting Industry Practice Kristen Soles, Partner PLEASE READ This presentation has been prepared for information purposes and general
More informationPublic Disclosure Requirements for Buyers. BY William A. Cox. and Sellers:
Public Disclosure Requirements for Buyers BY William A. Cox and Sellers: 44 Contract Management February 2010 Justifications for Other than Full and A review of the documentation requirements for justifications,
More informationSeattle Public Schools The Office of Internal Audit
Seattle Public Schools The Office of Internal Audit Internal Audit Report September 1, 2014 through Current Issue Date: June 21, 2016 Executive Summary Background Information The function is centralized
More informationSEMINOLE COUNTY OFFICE OF MANAGEMENT AND BUDGET PURCHASING DIVISION BLANKET PURCHASE ORDER PROCESS AUDIT. March 31, 1998
SEMINOLE COUNTY OFFICE OF MANAGEMENT AND BUDGET PURCHASING DIVISION BLANKET PURCHASE ORDER PROCESS AUDIT March 31, 1998 March 31, 1998 The Honorable Randall C. Morris Chairman The Board of County Commissioners
More informationCost Accounting Standards (CAS) Lee Canada. Cost Accounting Standards Act (CAS) PL
Click to view this email in a browser J.A. White & Associates, Inc, 1341 Garner Lane, Suite 104 Columbia, SC 29210 Tel: (803) 407-1399 Fax: (803) 407-0256 info@jawhite.com www.jawhite.com Cost Accounting
More informationOBSERVATIONS, RECOMMENDATIONS AND RESPONSES CONTRACTOR SELECTION - QUOTE SOLICITATION In thirteen of the projects reviewed, the files lacked documentation to support that PPD solicited at least three quotes.
More informationJUL 14 Rev B All Paragraphs Revised
Quality Specification 102-32039 22 JUL 14 Rev B All Paragraphs Revised Counterfeit Electronic Parts Detection and Avoidance System 1. PURPOSE 1.1. Content The purpose of this document is to describe the
More informationThis policy will outline the requirements for competitive bids on goods and services purchased by the College.
Policy Name: Procurement Sole Source/Competitive Bid Policy Updated/Reviewed: August 10, 2017 Effective Date: November 15, 2010 Office with Primary Responsibility: Procurement Services Offices with Secondary
More informationResults in Brief. OIG September 27, Audit of WMATA s Blanket Purchase Agreements (BPAs)
IG re Results in Brief OIG 19-03 September 27, 2018 Why We Did This Review According to WMATA s procurement manual, a Blanket Purchase Agreement (BPA) may be used as a simplified method of filling anticipated
More informationCentral Consolidated School District Purchasing Procurement Guidelines
Central Consolidated School District Purchasing Procurement Guidelines Procurement Purchasing Procedures: The following procedures have been implemented to comply with the State of New Mexico regulations
More informationPROCEDURE CITY OF GRANDE PRAIRIE PURPOSE SCOPE PROHIBITIONS:
CITY OF GRANDE PRAIRIE PROCEDURE PROCEDURE NO: 310-2 PAGE: 1 OF 6 TITLE: Request for Quotation POLICY: 310 Purchasing Policy SECTION: APPROVAL DATE: APPROVED BY: City Manager REVISION DATE: DEPARTMENT:
More informationJuly 30, (1) CHAPTER 5. Table of Contents
July 30, 2013 5(1) CHAPTER 5 Table of Contents Paragraph Page 5-000 Audit of Policies, Procedures, and Internal Controls Relative to Accounting and Management Systems 5-001 Scope of Chapter... 501 5-100
More informationMaster Document Audit Program. Version 4.28, dated March 2018 B-1 Planning Considerations
Activity Code 17100 B-1 Planning Considerations Termination, Fixed Inventory Basis Type of Service - Attestation Examination Engagement Audit Specific Independence Determination Members of the audit team
More informationContract and Procurement Fraud. Fraud in Procurement without Competition
Contract and Procurement Fraud Fraud in Procurement without Competition Sole-Source Awards Noncompetitive procurement process through the solicitation of only one source Procurement through sole-source
More informationATSP4 RFP Questions and Answers Last edited 10 March 2015 Questions have been modified only to provide anonymity
ATSP4 RFP Questions and Answers Last edited 10 March 2015 Questions have been modified only to provide anonymity This Q&A document provides responses to questions submitted to DMEA in response to both
More informationACADEMY OF NATURAL SCIENCES PURCHASING AND PROCUREMENT POLICY
ACADEMY OF NATURAL SCIENCES PURCHASING AND PROCUREMENT POLICY Academy of Natural Sciences Purchasing Policy Overview This policy framework is intended to provide for the procurement of goods and services
More informationUTSA HUB Program. Locate bids at: Agency #743
UTSA HUB Program Historically Underutilized Business Subcontracting Plans (HSP) Tip Sheet The Historically Underutilized Business (HUB) Program of UT at San Antonio was established to identify Historically
More information