ADP-2 LINER PANEL ERECTION GUIDE

Size: px
Start display at page:

Download "ADP-2 LINER PANEL ERECTION GUIDE"

Transcription

1 ADP-2 LINER PANEL ERECTION GUIDE NOTE: See back side of cover for latest changes to this manual. BEHLEN MFG. CO. COLUMBUS, NE TECHNICAL INFORMATION Rev. 10/2/17 11/05/04

2 NOTE: If pink sheets are included in this manual, refer to them for latest revisions. LATEST CHANGES BY: SR DATE: 10/2/17 PAGE CHANGE 2 Revised the fastener schedule

3 FRAME BUILDING LINER TABLE OF CONTENTS TITLE OR DESCRIPTION PAGE NUMBER General Information Liner at Base...6 Liner at Girts...7 Liner at Eave Struts...8 Liner at Rake...9 At Columns By-Pass Girts...10 At Corners By-Pass Sidewall/Endwall Girts...11 & 12 At Columns 1 Projection Flush Girts...13 At Columns 0 Projection Flush Girts...14 At Corners Flush Girt...15, 16, & 17 Liner At Ceiling...18, 19 & 20 Liner At Self-Framing Window...21 Liner At Preassembled Window...22 Liner At Knocked-Down Door...23 Liner At Preassembled Door...24 Liner At Walk Door Rough Frame...25 Liner At Framed Opening...26 & 27 Liner At Framed Opening With Sill...28 & /21/05

4 GENERAL INFORMATION The erection information presented herein is provided as a supplement to the erection drawings prepared for your specific job. The information, illustrations and procedures in this guide are typical for most Behlen buildings. Variations may occur because of special building requirements. Always refer to the erection drawings supplied with each job which will govern specific part and assembly arrangements and applicable illustration details. Because Behlen products are constantly being improved, the information contained herein is subject to change without notice. The following fastener schedule is to be used with this erection guide and will correspond to the fastener schedule in the erection drawings supplied with each job. FASTENER SCHEDULE Loc. Part No. Description As Noted On Rigid-Frame Elevation b c Screw ¼ x 3/4 FL-TP SD WW d Screw 12 x 1 HWH SD NW e Screw 12 x 1-1/4 FL-TP SD WW f Screw ¼ x 1-1/4 LG-LF SD WW g Screw 8 x ½ HWH SD NW h i Bolt ½ x 2 HVHX A325 GALV and Nut ( ) j Bolt 5/8 x 2-1/4 HVHX A325T GALV and Nut ( ) 1) Bolt ¾ x 1-1/2 HVHX A325T GALV and Nut ( ) 1! Bolt ¾ x 2-1/2 HVHX A325T GALV and Nut ( ) 1@ Screw ¼ x 3/4 FL-TP SD WW for ADP-1 Roof Screw ¼ x 3/4 LG-LF SD WW for SSR 1# Screw 12 x 1-1/4 FL-TP SD WW for ADP-1 Roof Screw ¼ x 1-1/4 LG-LF SD WW for SSR 1$ Screw 12 x 1-1/4 HWH SD #5PT NW 1% Bolt ½ x 1-1/2 HVHX A325T GALV and Nut ( ) 1^ Bolt ½ x 1 FLT RD HD A307 PLTD and Nut ( ) 1& Screw 12 x 2 FL-TP SD WW Abbreviations HD = Head SD = Self-Drilling ST = Self-Tapping SS = Stainless Steel PT = Point RD = Round WW = With Washer NW = No Washer FLT = Flat HVHX = Heavy Hex GALV = Galvanized PLTD = Plated HWH = Hex Washer Head FL-TP = Flat Top LG-LF = Long Life ERECTION INFORMATION Liner panel sidelaps shall be stitched together with a c fastener at 24 centers. HANDLING LONG TRIM COMPONENTS When removing long trims from the shipping crate and during installation, care should be taken by construction workers to avoid damage caused by buckling

5 GENERAL INFORMATION STOP... PLEASE READ RECOMMENDED INSTALLATION FOR SELF-DRILLING TAPPING FASTENERS TO INSURE FASTENER PERFORMANCE. * Apply with 1800 RPM electric screw gun. * Drive socket size must fit appropriately to fastener head. Socket Types: 1. Super Star Socket - Used for long-life non-magnetic screw heads. Can be used with carbon screw to avoid drill chips collecting on magnetic sockets. Inland Part No. - 1/4 ( ) 5/16 ( ) 3/8 ( ) 2. Non-magnetic - Used by erectors on roofing applications, mainly to avoid drill chips collecting in sockets. Special Order - 1/4 5/16 3/8 Drilling/Driving fastener must be held perpendicular to the fastening surface. Self-Drilling fasteners should not be forced in. Allow the drill point to do the work. - CAUTION - Over-torquing may result in fastener separation/failure (head popping off). Care should be exercised during installation. Torque of in. lbs. Based on fastener size and application. FOR APPLICATION SUPPORT, CONTACT: ATLAS BOLT & SCREW TECHNICAL SERVICES (800) Inland Buildings (800) *1800 RPM screw guns and sockets are available at your local tool house or from: Dynamic Fasteners /21/05

6 GENERAL INFORMATION HANDLING LONG TRIM COMPONENTS When removing long trims from the shipping crate and during installation, care should be taken by construction workers to avoid damage caused by buckling. PROTECTIVE FILM REMOVAL The trim components received with this building have a protective film on the colored surface that must be removed prior to installation. Prolonged exposure (more than 3 weeks) to rain and/or sunlight will adversely effect the protective film making removal difficult. When film is being removed from trim having a hem along its edge, the film should be peeled off along the entire end. This includes the 3/8 hemmed area on the back side. Pull the entire film strip at a constant rate. Do NOT try to rip the film off as it will tend to tear at the hemmed edge and corners leaving a strip that will have to be removed separately. 4 9/21/05

7 GENERAL INFORMATION RELATIONSHIP OF LINER PANEL AND EXTERIOR PANEL RIBS Liner panels for a complete sidewall or endwall surface have been detailed with a process similar to the exterior wall panels. The location of the liner panels is based on the length of the exterior wall surface and whether there is a Start Dimension at each end of the wall surface. This detailing process will keep the liner panel ribs and the exterior panel ribs in line. During the erection process, the sidewall liner panel locations may start or stop at J-trims as desired but on the endwall surface, the liner panel length may be insufficient if moved to some other location

8 LINER AT BASE

9 LINER AT GIRT

10 LINER AT EAVE STRUT

11 LINER AT RAKE 9 9/21/05

12 LINER AT COLUMNS BY-PASS GIRTS

13 LINER AT CORNER BY-PASS SIDEWALL/ENDWALL GIRTS

14 LINER AT CORNER BY-PASS SIDEWALL/ENDWALL GIRTS

15 LINER AT COLUMN 1 PROJECTION FLUSH GIRTS

16 LINER AT COLUMNS 0 PROJECTION FLUSH GIRTS

17 1 INCH GIRT PROJECTION LINER AT CORNER FLUSH SIDEWALL/ENDWALL GIRTS

18 0 INCH GIRT PROJECTION LINER AT CORNER FLUSH SIDEWALL/ENDWALL GIRTS

19 LINER AT CORNER FLUSH SIDEWALL/ENDWALL GIRTS 0 INCH GIRT PROJECTION (1 INCH GIRT PROJECTION IS SIMILAR)

20 LINER AT CEILING 18 6/18/04

21 LINER AT CEILING 19 9/21/05

22 LINER AT CEILING 20 9/21/05

23 LINER AT SELF-FRAMING WINDOW

24 LINER AT PREASSEMBLED WINDOW

25 LINER AT KNOCK-DOWN DOOR 7/21/06 23

26 LINER AT PREASSEMBLED DOOR

27 LINER AT WALK DOOR ROUGH FRAME

28 LINER AT FRAMED OPENING HEADERS NEAR EAVE STRUTS HEADERS BELOW SIDEWALL / ENDWALL GIRTS AT STANDARD ELEVATIONS 11/8/10 26

29 LINER AT FRAMED OPENING

30 LINER AT FRAMED OPENING WITH SILL 28?

31 LINER AT FRAMED OPENING WITH SILL