Detailed Business Case Single Computer Aided Dispatch Project

Size: px
Start display at page:

Download "Detailed Business Case Single Computer Aided Dispatch Project"

Transcription

1 Detailed Business Case Single Computer Aided Dispatch Project Author: Angela Ashton, Bluestar Project Manager Date: 16 October 2008 Doc Ref: BSS_4707_CAD Business Case v0.5 Version: Draft v0.5 Final Decision: Date By Decision {Date Made} Decision {Director Meeting, Trust Board} {Approve/Reject}

2 Table of Contents 1. STRATEGIC INFORMATION Background Assumptions and Constraints Benefits Risks SERVICE PERSPECTIVE Options Preferred option FINANCIAL IMPACT Capital & Revenue Cost OPTIONS ANALYSIS MANAGEMENT ARRANGEMENTS Project Plan and Overview Project Roles and Responsibilities Risk Management Procedures CONCLUSION DOCUMENT CONTROL Change Record Who Has Reviewed This Document Approvals CAD Business Case Page 2 of 12

3 1. Strategic Information 1.1 Background The creation of SECAmb resulted from merging the three existing ambulance trusts; the new combined entity is required to provide comprehensive, seamless Emergency Services across the whole of its geographical area. To this end, as part of operational and clinical governance requirements, the Trust has embarked upon a review of technologies at its disposal, and the roles they fulfil, in support of these responsibilities. This business case has been prepared as a result of the review, and proposes and supports a move to rationalise the number of technology solutions deployed across the Trust s Emergency Despatch centres (EDCs), from three to one single-supply implementation. The principal aim to result from such rationalisation is to overcome interoperability issues across the three locations. Presently there are three different CAD systems; Visicad at Lewes, MIS (Alert 2000) at Banstead and MIS (C3) at Coxheath. As these systems do not interconnect, the Trust is presently faced with difficulties in managing activities at the boundary areas of the former merged trusts, from a command and control point of view. This has an impact on overall Trust efficiency, and the delivery and quality of patient care. The business case also recognises the need to meet ongoing, increasingly stringent performance targets and expectations and projected increases in demand for the use of its Emergency Services. The Trust has a duty to, and must be able to, provide a seamless approach to resource scheduling, improve the efficiency of each of the EDCs, maximise the utilisation of its fleet and have consistent management information from which to do this; all in support of the delivery of and quality of patient services. To achieve its quantitative and qualitative goals, present and future, the Trust executive management, therefore, proposes to implement a single CAD solution across the whole of SECAmb. This is seen as an operational imperative and as such will be consistent with the Trust s strategic aims and operational plans as contained in its : Vision, to be a clinically focused, high performing, team-based organisation that matches and exceeds international best practice Five Year Strategic Objectives for 2008/09 Business Plan Assumptions and Constraints The following assumptions are fundamental to this case being approved and progressed: That the three current CAD systems need to be replaced That the Board accepts the legitimacy of the Procurement Process to date That the preferred supplier is acceptable to the Board That Capital & Revenue Funding is available to support the procurement, implementation and ongoing operation That the Implementation Plan is approved That the established Project Board and Project Team, who have demonstrated their commitment to the delivery of this project continue in place That other Trust personnel are made available as required to support the Project Management Team in the implementation CAD Business Case Page 3 of 12

4 The following constraints are acknowledged as having a potentially adverse effect on satisfactory further progress : That the Board delays the approval of the Business Case That the pressure of delivering performance targets, particularly Call Connect response times, may have an impact on the availability of time and resources that the Trust can commit, particularly as regards staff availability That implementation cannot be allowed to have any negative impact on achievement of performance targets That the predominance of the need to maintain current operational capability during any transition period can hinder implementation That the level of change required within the EDCs may exceed that envisaged with implications on staff training requirements and consistency in the initial operational periods 1.3 Benefits The Project Team identified benefits associated with this acquisition, as listed below. These have been used in the Procurement Evaluation process, in the determination of the Preferred Supplier. The benefits form part of the comparison and relative scoring of the tenders submitted by suppliers in response to the Invitation to Tender. Benefits assessed fell into three categories: Quality those benefits that cannot be quantified in financial terms and are scored accordingly Financial, but non-cash releasing benefits such as staff efficiency savings, improved training delivery etc but where the gains will not be realised as cash savings Financial Cash releasing savings made on existing support contracts Quality benefits A single CAD will facilitate the development of : Operational Staff Time Efficiencies Improving standard working practices, and help focus on high performance, allowing more effective and efficient deployment of staff with improvement of performance against response targets and better clinical outcomes EDC Effectiveness removal of the current localised cross border restrictions, improving service coverage at the boundaries of the former legacy Trusts EDC Efficiency improved standard working practices of the support staff across the three EDCs, enabling greater flexibility in the use of EDC resources Data Quality Data quality will be improved due to the consistent approach to recording of information Reporting from the improved consistency in data collection, consequently improved management information reporting, generated with greater ease and accuracy, assisting in better informed strategic and operational decision making IT Support with the elimination of multiple applications, and only one system on a single platform, there will be more flexibility of resource usage CAD Business Case Page 4 of 12

5 Supplier Management Greater influence on supplier product development, and a stronger supplier relationship will emanate from a single, larger, if somewhat more complex, implementation Non-cash releasing benefits Improved Quality of Healthcare Better utilisation of resources by facilitating despatch of most appropriate available local response in cross-border areas, where current deployment is masked at border areas, with potentially better outcomes for patients Improved Deployment of Operational Resource As well as improving the effectiveness of clinical coverage in border areas, any resultant reduced resource overlap and duplication will allow more effective use of staff, as well as minimising undue fleet use, reducing mileages, maintenance and fuel costs Improved EDC Operational Efficiency Consistent working practices across all EDCs, staff being able to work in any location and cover other dispatch areas without incurring travelling costs, also enabling better balancing of peak and other period workloads Improved Target Achievement : Call Connect With the allied development of a best practice approach to its EDC operation, the Trust s improvements in operational efficiency will support the better sustained delivery of its targets, and the delivery of a High Performance operating regime Improved EDC Staff Training This can be streamlined, covering one single best practice, with more flexibility in the use of training resources Improved Technology : EDC Remote Operations The proposed solution offered by the preferred supplier of a thin client approach, using a standard CITRIX application will allow remote operations from almost any site, including potential wireless remote access via 3G, even with limited connectivity. This will mean that control centres could be flexibly deployed to allow the monitoring and dispatch of vehicles from major incident sites, stations, fall back centres, training facilities and at one-off/regular events etc. Improved Technology : EDC Disaster Recovery & Business Continuity The proposed solution offers increased flexibility, and its speed of deployment using existing links, rather than the installation of current communications lines, would allow for quick equipping of alternative nearby locations at which to re-site a control room, as opposed to relocating to another EDC or training location. If a server goes down, client connections are automatically and seamlessly put on to another server, with no impact on the user Improved Technology : Application and User benefits The advantages of the proposed solution of thin client approach include : o o Flexibility on core application location will eliminate ultimate dependency on specific single computers All system administration and control over user, network, resource and application management can be done centrally, providing more control over the environment and access control and improving user experience o All data is stored on a central server allowing for easier data protection, and backup for quicker and easier recovery using a mirrored application elsewhere o o In the event of the failure of an individual user client machine, replacement is simpler and can be done with a lower spec machine than at present As software updates are applied to the application servers only, they will be quicker and more consistently applied CAD Business Case Page 5 of 12

6 Improved Management Reporting Single format, consistent data collection, providing for simpler generation of more accurate information and reports to support better management decision making Improved Efficiency in Administration Better, consistent and complete information will allow for more co-ordinated planning across all Operational matters Cash releasing benefits Current CAD Support Costs Supplier Support costs will be reduced from the combined current annual total of 192k to 155k per annum (Note: The Finance Table includes costs and savings on a gross basis - the 155k is included in Software Support costs) Out of Hours Calls The new contract includes 24 hour service cover, which current arrangements do not (Note: The current annual costs shown above include an estimated of the present average charge of 2k per annum for those costs) 1.4 Risks The Project Team identified the main risks being as follows : Implementation disruption having an adverse impact on the delivery of performance targets There needs to be adequate senior management input and other resourcing throughout the implementation and transition Inadequate Training A robust Training Plan, appropriately resourced, will be a necessity, as will management support in ensuring the availability, and compliance of staff in its achievement Unrealistic Timescales/Project overrun The timescales are very tight. Senior management support will be essential to drive these. Adequate contingency planning will be essential to ensure that control is maintained in the event of unforeseen events disrupting the implementation timetable Availability of Trust resources The Project Board and Project Team should remain committed to delivery with as little disruption as possible Power Supplies Adequacy This must be safe at all EDC locations, so their status will require to be continually monitored and managed 2. Service perspective 2.1 Options The Trust has the following options, and these were considered prior to the commencement of the formal Procurement Process : Option 1 - Do Nothing Retain the three current CAD systems. Life expectancy of existing system at Banstead would be limited as this is an old system which is no longer included on the development path of the supplier and could potentially be at risk of discontinued support in the future. This would not deliver consistency of business processes, management information etc by continuing to use three different systems. Option 2 - link the existing three CAD systems This was regarded as untenable, for exactly the same reasons as the Do Nothing option CAD Business Case Page 6 of 12

7 Option 3 - Implement a single, Trust wide, CAD This would require a formal procurement and implementation, but provide foreseeable continuity and additional operational benefits. 2.2 Preferred option Option 3 was the preferred Option, supporting the Trust s vision, strategic and operational objectives, as stated above. A Formal procurement process has been undertaken. This assessed supplier organisational and technical and capabilities, and those deemed fit were invited to submit appropriate tenders. These were formally evaluated by the Project Team, including User Evaluations (5th 7th March 2008 and 28th April 2008), Site Visits, Technical Evaluation and Compliance with Terms & Conditions and a preferred supplier selected, this choice being ratified by the Project Board. The supplier whose product both meets the needs of the Trust and which has the technical ability to deliver the required solution is adjudged to be AssetCo, using its VisiCad solution. 3. Financial Impact 3.1 Capital & Revenue Cost For the sake of simplicity the financial projections are based as if the capital spend for 2008/09 and 2009/2010 is incurred under UKGAAP. From 2009/10 onwards, under IFRS, capital spend incurred on software intangibles may be treated as revenue spend. The amounts involved are not material ( 30k). It is anticipated that the implications of any IFRS changes that may be required, eg the writing out of the balance sheet of software intangible, when reporting standards change, will take place during the initial transition stage between 2008/09 and 2009/10, and impact on the balance sheet at that date, rather than as items affecting the bottom line in 2009/10. Timing would appear to be of essence. Any delay in the project timetable that defers any major parts of the proposed 2008/09 capital spend into 2009/10 may result in that spend instead becoming a direct charge to the Trust s revenue costs in that year and hence impact directly on the 2009/10 bottom line. This may make the project financing untenable. Otherwise the amounts shown cover the marginal costs associated with the CAD implementation. (The current costs identified specifically to the existing CAD are the 311K maintenance, that will not be payable in future. Additionally there is only one member of IT staff works on maintaining the CAD who will continue, but the amount is of zero impact and immaterial in this context). Cost Base All are shown at current pay and prices levels Capital The Initial Cost will be 1053k, 266k for hardware, 586k for software and 211k for implementation costs. There will be a further capital requirement of 262k every third year for a technology hardware refresh. These Capital Costs include irrecoverable VAT. Revenue The Estimated additional revenue cost in 2008/2009, including the initial implementation stage, is 316K. Of that, 312k relates to non recurrent charges. Of those, approximately 82K covers costs of implementation; 56K by the supplier, with 26K being incurred by the Trust directly, with the remainder being the anticipated Impairment Charge of 230k, relating to the write down of the existing CAD s NBV at 31 March CAD Business Case Page 7 of 12

8 Thereafter, the level of the estimated net increase in Revenue Costs, after offsetting current maintenance costs with a full year value of 311k that will no longer be incurred. This will be 342k in 2009/2010 and fluctuating from around 150k to revenue saving of 6k from 2010/2011 to 2015/16. The main recurring components of these costs are charges for Supplier support of software and hardware and costs incurred directly by the Trust in respect of depreciation and costs of capital. If the transition to IFRS occurs as anticipated, with the software asset being written down to a Nil value, the depreciation charge from 2009/10 will decrease by approximately 130k, up to and including 2014/15, with the bottom line adjusted accordingly. A summary of the Capital and Revenue costs is contained in Appendix A. 4. Options Analysis The evaluation process required formal analysis of the benefits that would be derived from the varying supplier proposals submitted. A number of suppliers were eliminated by formal decision making at different stages of the evaluation process. A summary of the Project Team s scoring of the main factors, for the two suppliers finally considered, is as follows : Supplier OBS Responses Supplier Total Score Weighted Score Ranking Weighting % Score AssetCo MIS User Evaluations 5 th 7 th March 2008 Supplier Total Score Weighted Score Ranking Weighting % Score AssetCo MIS User Evaluations 28 th April 2008 Supplier Score Ranking Weighting % Score AssetCo MIS Terms & Conditions Compliance Supplier Ranking Weighting % Score AssetCo MIS Site Visits Supplier Score Ranking Weighting % Score AssetCo MIS Overall Supplier Score Ranking Score AssetCo 1 95 MIS CAD Business Case Page 8 of 12

9 The preferred supplier selected in accordance with this process was therefore AssetCo. 5. Management Arrangements 5.1 Project Plan and Overview A High Level Project Plan has been prepared and this has been approved by the Project Board. The key milestones are set out below. A detailed Implementation Project Plan will be developed in conjunction with the supplier during finalisation of the contract. Below is an outline implementation plan for guidance purposes only and will be subject to change once implementation planning has commenced with supplier. Milestone Dates Preferred Supplier Identified August 2008 Full Business Case Development August / September 2008 Business Case Approval - FASC October 2008 Business Case Approval - Trust Board January 2009 Contract Negotiations September / January 2009 Site Role Out ~1 March 2009 Training April/ May 2009 Go Live May 2009 Post Implementation Support May 2009 / June 2009 Site Role Out ~2 June 2009 Training July / August 2009 Go Live September 2009 Post Implementation Support September / October 2009 Site Role Out ~3 October 2009 Training October / November 2009 Go Live November 2009 Post Implementation Support November / December 2009 Post Implementation Review December 2009 / January 2010 Project Sign Off January Project Roles and Responsibilities Project Management Structure and Methodology The project will be implemented in accordance with the standard NHS methodology, ie Projects in a Controlled Environment (PRINCE2) Project Governance Overall responsibility will rest with the IM&T Working Group CAD Business Case Page 9 of 12

10 The CAD Project Board will report directly to the IM&T Working Group. Its role will be to oversee all project delivery activities, including those related to the specification, business case, procurement and implementation. It will approve all major plans and authorises any major deviation from the agreed Stage Plan. It is responsible for signing off stage completion, authorising commencement of subsequent stages, ensuring that the required resources are being committed, arbitrating on any conflicts and negotiating solutions, either internally within the Trust or with external bodies. It approves the appointment and responsibilities of the Project Manager and any delegation of its Project Assurance responsibilities. A CAD Project Team has the role of supporting the procurement and implementation on a day to day basis. It reports periodically to the CAD Project Board. The project manager will provide a monthly highlight report to the Project Board. All formal project documentation will be prepared using PRINCE2 templates (adapted for NHS use). Documentation will be subject to at least one round of formal review. Lists of reviewers and approvers will be agreed with the Project Manager. Product Descriptions will accompany documents issued for review. Project Evaluation The project will be subject to a post project review, at an agreed time after go live, (this is normally 12 months) to address what lessons might be learned with regard to the delivery of project objectives against deliverables and problems encountered, to set out enhancements which may be made to best practice, and transfer of risk, to make recommendations for future developments, and to arrange for Project handover, including any still outstanding issues, and final sign off 5.3 Risk Management Procedures A risk management procedure has been developed to identify any potential risk to the project. A risk and issues register will be maintained for the duration of the project. All issues or risks identified will be logged, assigned an owner, given a risk and impact rating and any actions that will be taken to mitigate the issue/risk recorded. Once/if an issue or risk is resolved the actions will be documented and the risk or issue marked as closed. All risks shall be managed effectively; with all severe risks/issues being escalated to the project board via highlight reports. In the event that any risk is deemed so severe that it cannot wait for a routine Project Board meeting, an exception report will be immediately be prepared for, and a decision sought from, the Project Board. 6. Conclusion The reasons and evidence for moving to a single CAD are strong and the Board is recommended to give this appropriate approval CAD Business Case Page 10 of 12

11 6. Document Control 6.1 Change Record Date Author Version Reason for Change 16 Oct 08 Angela Ashton Draft V Oct 08 Angela Ashton Draft V0.2 Review by Alan Smith 27 Oct 08 Angela Ashton Draft V0.3 Minor Modifications 10 Nov 08 Angela Ashton Draft V0.4 Changes Incorporated with comments from NEDs 9 Jan 09 Angela Ashton Draft V0.5 Amendments as a result of November Trust Board 6.2 Who Has Reviewed This Document Name Position Date Ian Arbuthnot Steve Moss Alan Smith Greg Timmins Matt Gibbons Senior Responsible Owner Finance Finance Finance Finance Any other Department affected by Project 6.3 Approvals Functional Director {Signature & Date} Director Meeting Trust Board CAD Business Case Page 11 of 12

12 SOUTH EAST COAST AMBULANCE NHS TRUST COMPUTER AIDED DESPATCH PROGRAMME BUSINESS CASE SUMMARISED FINANCIAL INFORMATION APPENDIX A Yr 0 Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr /9 2009/ / / / / / / / /18 Total K K K K K K K K K K K Capital Expenditure Hardware ,042 Software Licences Implementation Costs Total Capital Expenditure REVENUE EXPENDITURE Additional Revenue Costs Recurrent Revenue Costs Software Support ,764 Hardware Support Depreciation ,606 Cost of 3.5% Total Recurrent Revenue Costs ,737 Add: Non Recurrent Revenue Costs Implementation Costs Impairment Charge - Writedown of former CADs Total Additional Revenue Costs ,437 Less: Reduction in current CAD costs ,716 Net Additional Revenue Costs ,721 BALANCE SHEET NBVs Balance brought forward 0 1, Additions 1, ,869 Depreciation ,606 Balance carried forward 1, CAD Business Case Page 12 of 12

Plymouth Hospitals NHS Trust Business Case for replacement Managed Equipment Service

Plymouth Hospitals NHS Trust Business Case for replacement Managed Equipment Service Plymouth Hospitals NHS Trust Business Case for replacement Managed Equipment Service Purpose The Business Case describes and seeks approval to award the contract for the replacement of the existing Pathology

More information

RTI Release. Project Management Plan. Brisbane Infrastructure Transport Planning & Strategy Strategic Transport Planning

RTI Release. Project Management Plan. Brisbane Infrastructure Transport Planning & Strategy Strategic Transport Planning 1 Project Management Plan Brisbane Infrastructure Transport Planning & Strategy Strategic Transport Planning SOUTH WEST CORRIDOR STUDY (OXLEY ROAD) PROJECT OWNER: GRAEME READ 2 Document Change History

More information

RISK MANAGEMENT STRATEGY

RISK MANAGEMENT STRATEGY Agenda Item No: 15 RISK MANAGEMENT STRATEGY PURPOSE: The Risk Management Strategy has been updated to reflect the revised approach to the Corporate Risk Register and Board Assurance Framework and to reflect

More information

UoD IT Job Description

UoD IT Job Description UoD IT Job Description Role: Service Delivery Manager (People HERA Grade: 8 Management Systems) Responsible to: Assistant Director (Business Services) Accountable for: Day to day leadership of team members

More information

Quality Impact Assessment Procedure. July 2012

Quality Impact Assessment Procedure. July 2012 Quality Impact Assessment Procedure July 2012 1 Document name Quality Impact Assessment Procedure Version 3.0 Document author (name/title) Karen Warner Compliance lead (name/title) Mark Turner, Assurance

More information

NHS Scotland. Job Description

NHS Scotland. Job Description NHS Scotland Job Description 1. Job Details Job Number Job Holder : Job Title: ICT Systems Support Manager Immediate Senior Officer: ICT Head of Service Delivery Board: Unit/HQ Division: Location: Scottish

More information

The Annual Audit Letter for Devon Partnership NHS Trust

The Annual Audit Letter for Devon Partnership NHS Trust The Annual Audit Letter for Devon Partnership NHS Trust. Year ended 31 March 2016 28 July 2016 Elizabeth Cave Director T 0117 305 7885 E liz.a.cave@uk.gt.com Mark Bartlett Manager T 0117 305 7896 E mark.bartlett@uk.gt.com

More information

UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DOCUMENTATION GUIDE: STAGE GATES

UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DOCUMENTATION GUIDE: STAGE GATES UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DOCUMENTATION GUIDE: STAGE GATES Document Status: Approving Body: Last Update: Author: Approved Information Services

More information

Trust to confirm. Second bullet sentence incomplete as states the Trust will work with.. Please update

Trust to confirm. Second bullet sentence incomplete as states the Trust will work with.. Please update Overall Appendices please can you review Updated the report and update the referencing for the appendices and as this appears to be mixed up within the report. i.e. refers to an appendix but this not included.

More information

Annual Audit Letter. The Whittington Hospital NHS Trust Audit

Annual Audit Letter. The Whittington Hospital NHS Trust Audit Annual Audit Letter The Whittington Hospital NHS Trust Audit 2008-2009 Contents Key messages Statement on internal control 5 Use of resources 6 Closing remarks 7 Appendix 1 ALE key findings and conclusions

More information

Asbestos Management. Final Internal Audit Report 2018/19. Powys Teaching Health Board. NHS Wales Shared Services Partnership

Asbestos Management. Final Internal Audit Report 2018/19. Powys Teaching Health Board. NHS Wales Shared Services Partnership Final Internal Audit Report 2018/19 NHS Wales Shared Services Partnership Audit and Assurance Services Reasonable Assurance - + Previous rating: 2012/13 Limited Assurance Report Contents CONTENTS Page

More information

GRIP for Programmes Release 1 (DRAFT) April Network Rail GRIP for Programmes Page 1 of 104

GRIP for Programmes Release 1 (DRAFT) April Network Rail GRIP for Programmes Page 1 of 104 GRIP for Programmes Release 1 (DRAFT) April 2015 Network Rail GRIP for Programmes Page 1 of 104 Network Rail GRIP for Programmes Page 2 of 104 Forward Purpose This document provides an overview and guidance

More information

IT Procurement Policy

IT Procurement Policy Policy Number: 240 Supersedes: Replaces all previous IT procurement policies Standards For Healthcare Services No/s 19 Version No: Date Of Review: Reviewer Name: 0.1 August 2011 Paul Solloway 1 September

More information

Internal Audit. Consultants Job Planning. February 2018

Internal Audit. Consultants Job Planning. February 2018 Internal Audit Consultants Job Planning February 2018 Internal Audit assessment: Objective Objective Objective Objective One Two Three Four Significant Objective Objective Objective Objective Five Six

More information

PROCUREMENT STRATEGY & ACTION PLAN. April 2012 March 2015

PROCUREMENT STRATEGY & ACTION PLAN. April 2012 March 2015 PROCUREMENT STRATEGY & ACTION PLAN CONTENTS Page 1 Executive Summary 2 2 Strategic Context 2 3 Scope 3 4 Values 3 5 Structure and Responsibilities 5 6 Aims, Objectives and Initiatives 6.1 Sustainability

More information

Internal Audit Report

Internal Audit Report Internal Audit Report Key Financial Controls Accounts Payable and Accounts Receivable December 2017 To: Deputy Chief Executive Director of Finance Head of Finance Finance Manager Copied to: Operations

More information

Public Private Partnerships: Airwave

Public Private Partnerships: Airwave Public Private Partnerships: Airwave REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 730 Session 2001-2002: 11 April 2002 LONDON: The Stationery Office 0.00 Ordered by the House of Commons to be printed

More information

NOT PROTECTIVELY MARKED

NOT PROTECTIVELY MARKED NOT PROTECTIVELY MARKED MEETING TITLE Audit Committee Public Session DATE 23 August 2017 PAPER TITLE IT Service Delivery ITEM NO 6.5 PREPARED BY Gary Devlin PURPOSE This paper presents our final report

More information

WHITE PAPER JUNE Running a Successful Global Payroll Implementation

WHITE PAPER JUNE Running a Successful Global Payroll Implementation WHITE PAPER JUNE 2017 Running a Successful Global Payroll Implementation CONTENTS Management Summary 3 Transition from procurement to implementation 5 Preparation 6 Project Management 8 Change Management

More information

Cancer Programme Manager. Full time (37.5 hours per week)

Cancer Programme Manager. Full time (37.5 hours per week) Job title Salary Hours Base Accountable to Cancer Programme Manager 33,222 to 59,964 (dependent on experience) Full time (37.5 hours per week) Cambridge Director of Transformation ABOUT EASTERN AHSN The

More information

Lexis PSL Commercial. Transition in outsourcing

Lexis PSL Commercial. Transition in outsourcing Transition in outsourcing 1 Please note that while this Practice Note is a comprehensive document, it does refer to some supplemental resources which are only available with a paid subscription to LexisPSL.

More information

United Lincolnshire Hospitals NHS Trust. Governance Statement 2015/16. Scope of responsibility. The governance framework of the organisation

United Lincolnshire Hospitals NHS Trust. Governance Statement 2015/16. Scope of responsibility. The governance framework of the organisation United Lincolnshire Hospitals NHS Trust Governance Statement 2015/16 Scope of responsibility As Accountable Officer, and Chief Executive of this Board, I have responsibility for maintaining a sound system

More information

AUDIT UNDP GLOBAL SHARED SERVICE CENTRE MALAYSIA. Report No Issue Date: 21 March 2014

AUDIT UNDP GLOBAL SHARED SERVICE CENTRE MALAYSIA. Report No Issue Date: 21 March 2014 UNITED NATIONS DEVELOPMENT PROGRAMME AUDIT OF UNDP GLOBAL SHARED SERVICE CENTRE IN MALAYSIA Report No. 1242 Issue Date: 21 March 2014 Table of Contents Executive Summary i I. About the Centre 1 II. Audit

More information

<Project Name> Business Case

<Project Name> Business Case Business Case Author(s) Contributors Department Campus DOCUMENT HISTORY Version Date Person Notes 1.0 ITS Portfolio Management Office Business Case Page 1 TABLE OF CONTENTS

More information

Scottish Ambulance Service. Job Description. Job Title: Programme Manager (Clinical Services Transformation)

Scottish Ambulance Service. Job Description. Job Title: Programme Manager (Clinical Services Transformation) Scottish Ambulance Service Job Description 1. JOB DETAILS Job Title: Programme Manager (Clinical Services Transformation) Department(s): Clinical Directorate Responsible to: General Manager ICT with Job

More information

Job Description and Person Specification

Job Description and Person Specification Job Description Directorate/Group: Corporate and Business Support (CBS) Location: Southampton Post Title: Grade: Project Delivery Lead NERC Band 4 Post responsible to: Chief Operating Officer Posts responsible

More information

Business Case and Proposal

Business Case and Proposal Business Case and Proposal Formation of an Internal Audit Service for Cambridge City Council, Huntingdonshire District Council and South Cambridgeshire District Council 1.0 Executive Summary 1.1 Cambridge

More information

AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS

AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS This document is available from the Economic Regulation Authority website www.era.wa.gov.au. For further

More information

GMS NETWORK PLUS PRODUCT SPECIFICATION 1. INTRODUCTION 2. SERVICE DEFINITION. 2.1 Service Overview. GMS Network Plus

GMS NETWORK PLUS PRODUCT SPECIFICATION 1. INTRODUCTION 2. SERVICE DEFINITION. 2.1 Service Overview. GMS Network Plus GMS NETWORK PLUS PRODUCT SPECIFICATION 1. INTRODUCTION This document contains product information for the GMS Network Plus Service. If you require more detailed technical information, please contact your

More information

Capital regime, investment and property business case approval guidance for NHS trusts and foundation trusts

Capital regime, investment and property business case approval guidance for NHS trusts and foundation trusts Capital regime, investment and property business case approval guidance for NHS trusts and foundation trusts Annex 4: Strategic outline case technical requirements November 2016 NHS Improvement publication

More information

NHSScotland Procurement Review

NHSScotland Procurement Review NHSScotland Procurement Review Project Initiation Document QuEST Portfolio Office Contents 1. Document Control 3 1.1 Programme Details 3 1.2 Version Control 3 2. Purpose of the Document 4 3. Context and

More information

INTERNAL AUDIT DIVISION

INTERNAL AUDIT DIVISION INTERNAL AUDIT DIVISION REPORT 2015/057 Audit of the Omgeo system in the Investment Management Division of the United Nations Joint Staff Pension Fund Overall results relating to the effective and efficient

More information

The Whittington Hospital NHS Trust. Modernising Clinical Services. Project Initiation Document

The Whittington Hospital NHS Trust. Modernising Clinical Services. Project Initiation Document The Whittington Hospital NHS Trust Modernising Clinical Services Project Initiation Document March 2008 Contents Contents...2 Appendices...2 1.0 Introduction...3 1.1 Overview...3 1.2 Background...3 1.3

More information

SERVICE PROCEDURE NOVEMBER 2011

SERVICE PROCEDURE NOVEMBER 2011 DERBYSHIRE FIRE & RESCUE SERVICE SERVICE PROCEDURE INCIDENT COMMAND TRAINING AND ASSESSMENT NOVEMBER 2011 VERSION 2.0 CONTENTS INTRODUCTION Introduction Procedure Training Courses Assessments Appeals Maintenance

More information

NHS ISLE OF WIGHT CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY POLICY

NHS ISLE OF WIGHT CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY POLICY NHS ISLE OF WIGHT CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY POLICY 1 AUTHOR/ APPROVAL DETAILS Document Author Written By: Phil Hartwell Authorised Signature Authorised By: Helen Shields Date: 06

More information

ANNEX THREE. Regime for Monitoring of Separation of Batelco and NBN Compliance

ANNEX THREE. Regime for Monitoring of Separation of Batelco and NBN Compliance ANNEX THREE Regime for Monitoring of Separation of Batelco and NBN Compliance Compliance Monitoring Regime Draft for Discussion Purpose: To establish a regime for monitoring Batelco s compliance with the

More information

ENVIRONMENTAL MANUAL. Page 1 of 26 Uncontrolled when printed NCH Env Manual Vers 11.0 date 01/02/18

ENVIRONMENTAL MANUAL. Page 1 of 26 Uncontrolled when printed NCH Env Manual Vers 11.0 date 01/02/18 ENVIRONMENTAL MANUAL Page 1 of 26 Uncontrolled when printed NCH Env Manual Vers 11.0 date 01/02/18 Document Control Identification and Approval Status Document Title: Environmental Manual Version Number:

More information

S3. Step 3 Develop Roadmap

S3. Step 3 Develop Roadmap S3. Step 3 Develop Roadmap PART OF IT STRATEGY TOOLIKIT VERSION 0.5 MAY 2007 1 TABLE OF CONTENTS S3-1. DETERMINE PRIORITIES... 3 S3-1.1 ASSESS DEPENDENCIES... 3 S3-1.2 PRIORITISE BUILDING BLOCKS... 3 S3-1.3

More information

Creating a Business Continuity Plan for your Health Center

Creating a Business Continuity Plan for your Health Center Creating a Business Continuity Plan for your Health Center 1 Page Left Intentionally Blank 2 About This Manual This tool is the result of collaboration between the Primary Care Development Corporation

More information

Supporting all NHS Trusts to achieve NHS Foundation Trust status by April 2014

Supporting all NHS Trusts to achieve NHS Foundation Trust status by April 2014 Supporting all NHS Trusts to achieve NHS Foundation Trust status by April 2014 Tripartite Formal Agreement between: Coventry and Warwickshire Partnership NHS Trust NHS West Midlands Department of Health

More information

Loch Lomond & The Trossachs National Park Authority. Annual internal audit report Year ended 31 March 2015

Loch Lomond & The Trossachs National Park Authority. Annual internal audit report Year ended 31 March 2015 Loch Lomond & The Trossachs National Park Authority Annual internal audit report Year ended 31 March 2015 Contents This report is for: Information Chief executive Audit committee Jaki Carnegie, director

More information

Manitoba Health, Seniors and Active Living Transformation Program Charter. February 16, 2018 Version 1.0

Manitoba Health, Seniors and Active Living Transformation Program Charter. February 16, 2018 Version 1.0 Manitoba Health, Seniors and Active Living Transformation Program Charter February 16, 2018 Version 1.0 Table of Contents 1 Purpose... 3 2 Background... 3 3 Scope of the Transformation Program... 5 3.1

More information

Financial Controller

Financial Controller Controller Grade: Department: Responsible To: Accountable To: Band 8c Finance Associate Director of Finance Director of Finance Job Summary To deputise for the Associate Director of Finance ( Services)

More information

The Integrated Support and Assurance Process (ISAP): detailed guidance on assuring novel and complex contracts

The Integrated Support and Assurance Process (ISAP): detailed guidance on assuring novel and complex contracts The Integrated Support and Assurance Process (ISAP): detailed guidance on assuring novel and complex contracts Part C: Guidance for NHS trusts and NHS foundation trusts Published by NHS England and NHS

More information

DATA QUALITY POLICY. Version: 1.2. Management and Caldicott Committee. Date approved: 02 February Governance Lead

DATA QUALITY POLICY. Version: 1.2. Management and Caldicott Committee. Date approved: 02 February Governance Lead DATA QUALITY POLICY Version: 1.2 Approved by: Date approved: 02 February 2016 Name of Originator/Author: Name of Responsible Committee/Individual: Information Governance, Records Management and Caldicott

More information

CCG CO12 Policy and Framework for Partnership Governance

CCG CO12 Policy and Framework for Partnership Governance Corporate CCG CO12 Policy and Framework for Partnership Governance Version Number Date Issued Review Date V2: 21/02/2015 29/04/2015 21/02/2018 Prepared By: Consultation Process: Formally Approved: 25/02/2015

More information

CGMA Competency Framework

CGMA Competency Framework CGMA Competency Framework Technical skills CGMA Competency Framework 1 Technical skills : This requires a basic understanding of the business structures, operations and financial performance, and includes

More information

PROCUREMENT AND TENDERING PROCEDURES POLICY 2018

PROCUREMENT AND TENDERING PROCEDURES POLICY 2018 PROCUREMENT AND TENDERING PROCEDURES POLICY 2018 1. Purpose of Document This document has been produced to help define and explain each individual s responsibilities in relation to Weymouth BID s procurement

More information

Gloucestershire Hospitals NHS Foundation Trust

Gloucestershire Hospitals NHS Foundation Trust Gloucestershire Hospitals NHS Foundation Trust 2009-10 Audit Planning Memorandum March 2009 Gloucestershire Hospitals NHSFT - 2009-10 Audit Plan Contents Page 1 Executive Summary 1 2 Principal accounts

More information

Action to date: Recommendation 2: Response: Action to date:

Action to date: Recommendation 2: Response: Action to date: ANNEX C 360 Assurance Report Urgent and Emergency Care Centre Project 3rd Project Governance Assurance Report Response to recommendations Background: 360 Assurance were appointed by the CCG to provide

More information

Business Case Guidelines for Investment in Information Technology

Business Case Guidelines for Investment in Information Technology Business Case Guidelines for Investment in Information Technology Citation: Ministry of Health. 2004. Business Case Guidelines for Investment in Information Technology. Wellington: Ministry of Health.

More information

Design Management Plan

Design Management Plan Lessons learned from one of New Zealand s most challenging civil engineering projects: rebuilding the earthquake damaged pipes, roads, bridges and retaining walls in the city of Christchurch 2011-2016.

More information

CGMA Competency Framework

CGMA Competency Framework CGMA Competency Framework Technical Skills CGMA Competency Framework 8 Technical Skills : This requires a basic understanding of the business structures, operations and financial performance, and includes

More information

MID ESSEX HOSPITAL SERVICES NHS TRUST ANNUAL AUDIT LETTER Audit for the year ended 31 March July 2016

MID ESSEX HOSPITAL SERVICES NHS TRUST ANNUAL AUDIT LETTER Audit for the year ended 31 March July 2016 MID ESSEX HOSPITAL SERVICES NHS TRUST ANNUAL AUDIT LETTER Audit for the year ended 31 March 2016 7 July 2016 LISA CLAMPIN Engagement Lead T: 01473 320 716 E: lisa.clampin@bdo.co.uk BARRY PRYKE Audit Manager

More information

National Ambulance Service 1 of 21 NAS Headquarters Version th September 2011 Authorised by NAS Leadership Team

National Ambulance Service 1 of 21 NAS Headquarters Version th September 2011 Authorised by NAS Leadership Team NATIONAL AMBULANCE SERVICE Severe Weather Response Plan National Ambulance Service 1 of 21 Document Control Plan Version Pages Issued to Date of Amendment Author Draft 1.0 All NAS Leadership Team 14 th

More information

1 For definition of a suitable project refer to the competency standards outlined in this document.

1 For definition of a suitable project refer to the competency standards outlined in this document. 3 1 For definition of a suitable project refer to the competency standards outlined in this document. . . . Getting started . In the table below read the evidence required for each unit of competence

More information

INFORMATION GOVERNANCE STRATEGY. Documentation control

INFORMATION GOVERNANCE STRATEGY. Documentation control INFORMATION GOVERNANCE STRATEGY Documentation control Reference Date Approved Approving Body Version Supersedes Consultation Undertaken Target Audience Supporting procedures GG/INF/01 TRUST BOARD Information

More information

DATIX CONSOLIDATION PROJECT INITIATION DOCUMENT

DATIX CONSOLIDATION PROJECT INITIATION DOCUMENT DATIX CONSOLIDATION PROJECT INITIATION DOCUMENT Reference Number: NHSCT/08/29 Responsible Directorate: Strategic Planning and Performance Management Replaces (if appropriate): N/A Policy Author/Team: Ron

More information

DEVELOPING A PERSUASIVE BUSINESS CASE FOR CRM. Glenda Parker

DEVELOPING A PERSUASIVE BUSINESS CASE FOR CRM. Glenda Parker DEVELOPING A PERSUASIVE BUSINESS CASE FOR CRM Glenda Parker CONTENTS INTRODUCTION 2 1. HAVE AN EXECUTIVE SUMMARY (BUT WRITE IT LAST) 3 2. CLEARLY OUTLINE THE PROJECT PURPOSE 3 3. IDENTIFY ALL KEY STAKEHOLDERS

More information

Risk Management Policy and Framework

Risk Management Policy and Framework Risk Management Policy and Framework Introductory Note to User: CompanyLongName There is no requirement in Australia for a non-publicly listed entity (other than a company regulated by APRA) to comply

More information

Annual Compliance Statement 2017 and Board of Directors / Governing Body and Corporate Governance Requirements

Annual Compliance Statement 2017 and Board of Directors / Governing Body and Corporate Governance Requirements Health Service Executive Annual Compliance Statement 2017 and Board of Directors / Governing Body and Corporate Governance Requirements Section 39 Providers Name of Provider: XXX March 2018 1 Contents

More information

NHS Milton Keynes Clinical Commissioning Group

NHS Milton Keynes Clinical Commissioning Group NHS Milton Keynes Clinical Commissioning Group Annual Audit Letter for the year ended 31 March 2016 July 2016 Ernst & Young LLP Contents Contents Executive Summary... 2 Purpose... 6 Responsibilities...

More information

HSCIC Audit of Data Sharing Activities:

HSCIC Audit of Data Sharing Activities: Directorate / Programme Data Dissemination Services Project Data Sharing Audits Status Approved Director Terry Hill Version 1.0 Owner Rob Shaw Version issue date 21/04/2016 HSCIC Audit of Data Sharing

More information

Appendix 1 Detailed Internal Audit Strategic Planning Process

Appendix 1 Detailed Internal Audit Strategic Planning Process AUDIT RISK ASSESSMENT AND PLANNING Introduction The objective of this paper is to explain the assessment criteria and methodology employed in formulating an Audit Risk Assessment and how this is used to

More information

AUDIT UNDP COUNTRY OFFICE INDONESIA. Report No Issue Date: 10 October 2014

AUDIT UNDP COUNTRY OFFICE INDONESIA. Report No Issue Date: 10 October 2014 UNITED NATIONS DEVELOPMENT PROGRAMME AUDIT OF UNDP COUNTRY OFFICE IN INDONESIA Report No. 1332 Issue Date: 10 October 2014 Table of Contents Executive Summary i I. About the Office 1 II. Good practices

More information

Transformation Programme. Sourcing Workstream PROCUREMENT PLAN. Inland Revenue. 28/06/2013 v1.0 FINAL Reference:

Transformation Programme. Sourcing Workstream PROCUREMENT PLAN. Inland Revenue. 28/06/2013 v1.0 FINAL Reference: Inland Revenue Transformation Programme Sourcing Workstream PROCUREMENT PLAN Project Sponsor: Greg James Prepared by: Sourcing Team Date: 28/06/2013 v1.0 FINAL Reference: 2013050 Document Control File

More information

ZSIC GROUP OF COMPANIES PROCUREMENT PLAN EXCEL VERSION

ZSIC GROUP OF COMPANIES PROCUREMENT PLAN EXCEL VERSION ZSIC GROUP OF COMPANIES PROCUREMENT PLAN 2015 EXCEL VERSION 1 P a g e 2 P a g e ZSIC Group Procurement Plan 2015 Contents Page 1. Background 3 2. Introduction 4 3. Executive Summary 5 4. Overall Expenditure

More information

This Policy supersedes the following Policy, which must now be destroyed:

This Policy supersedes the following Policy, which must now be destroyed: Document Title Reference Number Lead Officer Author(s) (name and designation) Ratified by Forensic Readiness Policy NTW(O)56 Lisa Quinn, Executive Director of Commissioning and Quality Assurance Angela

More information

Procurement Systems Report

Procurement Systems Report Procurement Systems Report Internal Audit Final Follow-up Report March 2017 1 Contents 1. Background page 3 2. Purpose of this report - page 3 3. Executive Summary page 4 4. Summary of Findings page 5

More information

CHILDREN'S SOCIAL CARE SERVICES ALTERNATIVE DELIVERY MODEL BUSINESS CASE APPROVAL

CHILDREN'S SOCIAL CARE SERVICES ALTERNATIVE DELIVERY MODEL BUSINESS CASE APPROVAL AGENDA ITEM 4 CABINET 29 MARCH CHILDREN'S SOCIAL CARE SERVICES ALTERNATIVE DELIVERY MODEL BUSINESS CASE APPROVAL Relevant Cabinet Member Mr A C Roberts Relevant Officer Director of Children, Families and

More information

Customer-focused review of the IT services formerly provided by Health Solutions Wales (now provided by NWIS) Velindre NHS Trust

Customer-focused review of the IT services formerly provided by Health Solutions Wales (now provided by NWIS) Velindre NHS Trust Customer-focused review of the IT services formerly provided by Health Solutions Wales (now provided by NWIS) Velindre NHS Trust Audit year: 2010-11 Issued: February 2012 Document reference: 161A2012 Status

More information

Invitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019

Invitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019 Invitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019 26th May 2016 1. Purpose of this Invitation to Tender (ITT) 1.1. This invitation to tender is for appointment to a three-year framework

More information

DS3 System Services Project Plan Detailed Design and Implementation Phase

DS3 System Services Project Plan Detailed Design and Implementation Phase DS3 System Services Project Plan Detailed Design and Implementation Phase Dated: 20/5/2015 Executive Summary The System Services work stream within the DS3 Programme relates to the procurement of services

More information

Annual Audit Letter. South Central Ambulance Service NHS Trust Audit 2008/09 September 2009

Annual Audit Letter. South Central Ambulance Service NHS Trust Audit 2008/09 September 2009 Annual Audit Letter South Central Ambulance Service NHS Trust Audit 2008/09 September 2009 Contents Key messages 3 Financial statements and statement on internal control 5 Use of resources 7 Closing remarks

More information

A CHECKLIST FOR PREPARING INITIAL AGREEMENT DOCUMENTS

A CHECKLIST FOR PREPARING INITIAL AGREEMENT DOCUMENTS Finance, ehealth & Pharmaceuticals Directorate Capital and Facilities Division Enquiries to: Steven Hanlon T: 0131-244 2139 E: steven.hanlon@scotland.gsi.gov.uk Chief Executives, NHS Boards and Special

More information

Discussion Paper: Shared Services

Discussion Paper: Shared Services Discussion Paper: Shared Services 23 November 2016 Overview This discussion paper presents an overview of the opportunities for the delivery of professional services for Western Sydney University (the

More information

PASA GUIDANCE. Trustees Administration Governance Checklist. July 2018

PASA GUIDANCE. Trustees Administration Governance Checklist. July 2018 PASA GUIDANCE Trustees Administration Governance Checklist July 2018 Administration Governance Occupational Pension Scheme Trustee Checklist The Pensions Administration Standards Association (PASA) has

More information

NRCS AUDIT AND RISK COMMITTEE TERMS OF REFERENCE

NRCS AUDIT AND RISK COMMITTEE TERMS OF REFERENCE NRCS AUDIT AND RISK COMMITTEE TERMS OF REFERENCE POLICY REGARDING THE ROLE AND RESPONSIBILITIES OF THE AUDIT AND RISK COMMITTEE 1. INTRODUCTION The Audit and Risk Committee ( The Committee ) is constituted

More information

GE/GN8640. Risk Evaluation and Assessment. Guidance on Planning an Application of the Common Safety Method on. Rail Industry Guidance Note

GE/GN8640. Risk Evaluation and Assessment. Guidance on Planning an Application of the Common Safety Method on. Rail Industry Guidance Note GN Published by: Block 2 Angel Square 1 Torrens Street London EC1V 1NY Copyright 2014 Rail Safety and Standards Board Limited GE/GN8640 Method on Risk Evaluation and Assessment Issue One; June 2014 Rail

More information

External Audit: Annual Audit Letter

External Audit: Annual Audit Letter INFRASTRUCTURE, GOVERNMENT AND HEALTHCARE External Audit: Annual Audit Letter 2005-06 Southport and Ormskirk Hospital NHS Trust September 2006 AUDIT Content The contacts at KPMG in connection with this

More information

POLICY DOCUMENT. Contracts Management Policy (Version 3.0) BM>SMC>Board

POLICY DOCUMENT. Contracts Management Policy (Version 3.0) BM>SMC>Board POLICY DOCUMENT Contracts Management Policy 2018 (Version 3.0) BM>SMC>Board Policy Review Schedule Date first Approved: Last Approved by the Board: January 2017 Date of Next Review: January 2018 Policy

More information

Operational Readiness Launching Capital Projects Successfully in Local Government

Operational Readiness Launching Capital Projects Successfully in Local Government Operational Readiness Launching Capital Projects Successfully in Local Government Mark Christison, Beca Limited Abstract We have all been involved in capital projects of importance to our communities,

More information

Job description and person specification

Job description and person specification Job description and person specification Position Job title Head of Genomics Unit Directorate Finance, Commercial and Specialised Commissioning Pay band AFC Band 9 Responsible to Director of Strategy and

More information

GP Out of Hours/111 Service Re-commissioning. Graham Clark, Lead Clinician, Out of Hospital Care Chris Coath, AD, Commissioning, Out of Hospital Care

GP Out of Hours/111 Service Re-commissioning. Graham Clark, Lead Clinician, Out of Hospital Care Chris Coath, AD, Commissioning, Out of Hospital Care Agenda item: 9.2 Subject: Presented by: Submitted to: GP Out of Hours/111 Service Re-commissioning Graham Clark, Lead Clinician, Out of Hospital Care Chris Coath, AD, Commissioning, Out of Hospital Care

More information

Guidance on portfolio, programme and project management

Guidance on portfolio, programme and project management Guidance on portfolio, programme and project management The Standard for Infrastructure Procurement and Delivery Management (SIPDM) defines the following two generic terms: Portfolio: collection of projects

More information

Project Initiation Document (PO003)

Project Initiation Document (PO003) Project Initiation Document (PO003) Document Control Project Title: INTO SITS to Exeter SITS Interface Project Manager: James Green Date: 4 March 2009 Version Date Author(s) Notes on Revisions 0.1 20/01/09

More information

Operational Readiness Launching Capital Projects Successfully in Local Government

Operational Readiness Launching Capital Projects Successfully in Local Government Operational Readiness Launching Capital Projects Successfully in Local Government Mark Christison, Beca Limited Abstract We have all been involved in capital projects of importance to our communities,

More information

Interim Audit Letter (Hywel Dda NHS Trust and Carmarthenshire, Pembrokeshire and Ceredigion Local Health Boards) Hywel Dda Local Health Board

Interim Audit Letter (Hywel Dda NHS Trust and Carmarthenshire, Pembrokeshire and Ceredigion Local Health Boards) Hywel Dda Local Health Board 2009-10 May 2010 Author: Ceri Stradling Ref: 250A2010 Interim Audit Letter 2009-10 (Hywel Dda NHS Trust and Carmarthenshire, Pembrokeshire and Ceredigion Local Health Boards) Hywel Dda Local Health Board

More information

Determine the project s level of complexity and agree with the owner the options and appropriate approach for delivery.

Determine the project s level of complexity and agree with the owner the options and appropriate approach for delivery. Job title Senior Project Manager - Migration Job family Project Management Grade 9 Job purpose The Senior Project Manager will deliver a project or multiple projects and expected outcomes, to stakeholder

More information

Invitation to Tender. Implementation of Microsoft Dynamics CRM for D2N2 Growth Hub

Invitation to Tender. Implementation of Microsoft Dynamics CRM for D2N2 Growth Hub Invitation to Tender Implementation of Microsoft Dynamics CRM for D2N2 Growth Hub 1. Purpose and Aims of the Contract East Midlands Chamber (EMC) is seeking proposals for a new implementation of Microsoft

More information

1 Management Responsibility 1 Management Responsibility 1.1 General 1.1 General

1 Management Responsibility 1 Management Responsibility 1.1 General 1.1 General 1 Management Responsibility 1 Management Responsibility 1.1 General 1.1 General The organization s management with executive The commitment and involvement of the responsibility shall define, document

More information

Project Plan City of Newport News; Department of Health and Human Services

Project Plan City of Newport News; Department of Health and Human Services Project Plan City of Newport News; Department of Health and Human Services 7/14/2010 Harmony Information Systems, Inc. 12120 Sunset Hills Road, Suite 500 Reston, VA 20190 MAIN: 703-674-5100 www.harmonyis.com

More information

QSS 0 Products and Services without Bespoke Contracts.

QSS 0 Products and Services without Bespoke Contracts. QSS 0 Products and Services without Bespoke Contracts. Use: Typically Sub 50k processes without a bespoke contract. Amendment History Version Date Status V3 June 2018 Updated for 2018 deployment Contents

More information

Business Case for Problem Management

Business Case for Problem Management PROBLEM MANAGEMENT ONLINE RESOURCES An implementation guide for the real world Michael G. Hall www.bcs.org/books/problem Business Case for Problem Management Date: Proposed by: Michael G Hall www.real-worldit.com

More information

Level 7 NVQ Diploma in Construction Senior Management. Qualification Specification

Level 7 NVQ Diploma in Construction Senior Management. Qualification Specification Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification Structure 4 Centre requirements 6 Support for candidates 6 Links to National Standards / NOS

More information

Level 7 NVQ Diploma in Construction Senior Management. Qualification Specification

Level 7 NVQ Diploma in Construction Senior Management. Qualification Specification Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification Structure 4 Centre requirements 6 Support for candidates 6 Links to National Standards / NOS

More information

Level 7 NVQ Diploma in Construction Site Management. Qualification Specification

Level 7 NVQ Diploma in Construction Site Management. Qualification Specification Level 7 NVQ Diploma in Construction Site Management Qualification Specification ProQual 2016 Contents Page Introduction 3 Qualification profile 3 Qualification Structure 4 Centre requirements 6 Support

More information

Key changes in new BCSH Transfusion I.T. Guidelines. Debbie Asher EPA Network Transfusion Manager Member, BCSH Guideline Writing Group

Key changes in new BCSH Transfusion I.T. Guidelines. Debbie Asher EPA Network Transfusion Manager Member, BCSH Guideline Writing Group Key changes in new BCSH Transfusion I.T. Guidelines Debbie Asher EPA Network Transfusion Manager Member, BCSH Guideline Writing Group Membership Joan Jones Head of Quality, Welsh Blood Service Paul Ashford

More information

The BBC s management of its Digital Media Initiative

The BBC s management of its Digital Media Initiative British Broadcasting Corporation The BBC s management of its Digital Media Initiative Report by the Comptroller and Auditor General This report has been prepared at the request of the BBC Trust under clause

More information

Business Continuity Framework

Business Continuity Framework Business Continuity Framework Author: Simon Featherstone, Business Continuity Specialist and Chris Orr, Business Planning Manager Date: 11 November 2016 Version: 1a Publication/ Distribution: Executive

More information