EXHIBIT "A" County Road 54 (Wesley Chapel Boulevard) (from North of Magnolia Boulevard to Oakley Boulevard) Work Order No. C-1640.

Size: px
Start display at page:

Download "EXHIBIT "A" County Road 54 (Wesley Chapel Boulevard) (from North of Magnolia Boulevard to Oakley Boulevard) Work Order No. C-1640."

Transcription

1

2 EXHIBIT "A" County Road 54 (Wesley Chapel Boulevard) (from North of Magnolia Boulevard to Oakley Boulevard) Work Order No. C SECTION I PURPOSE This document describes the scope of work and the responsibilities of the PROFESSIONAL and the COUNTY in connection with the design and preparation of a complete set of roadway construction plans, and permitting for proposed improvements to these transportation facilities. The COUNTY desires plans to: Widen County Road 54 in the median from north of Magnolia Boulevard to Oakley Boulevard from a four (4) lane divided urban section to a six (6) lane divided urban section. The PROFESSIONAL shall design based on "As-Built" information provided for the recently completed construction of the four (4) lane divided section in the project area. The PROFESSIONAL shall also consider any other applicable documents and reports generated for the four (4) lane design. Plans shall consist of roadway plans with any necessary adjustments for drainage purposes, signing and pavement marking plans, and any necessary adjustment to existing signals. The PROFESSIONAL shall also provide any necessary permits or modifications to existing permits. The project duration shall be two hundred and seventy (270) calendar days from the Notice to Proceed including 28 calendar days for COUNTY review. DESIGN CRITERIA: Design speed is 45 mph. Design Vehicle is Single Unit Bus (fire truck, garbage truck and school bus). Lane widths = 12' standard. Outside curbs are Type F. Curb inlets = Inlet Types 1-6 allowable, with maximum spacing 300'. Max. spread = six feet from lip of outside gutter. No inlets in returns. Left-turn control radius = 75' standard; 60' minimum. Right-turn control radius = 50' standard; 35' minimum. Stopping sight distance = 400'. Passing sight distance= 1800'. Minimum K factor (crest) = 120. Min. Crest VC = 300', Sag VC=2001. Vertical curves for algebraic differences >0.60%. Minimum gutter = 0.3% grade. Sodded utility strip between curb and sidewalk = 6'-10' standard; 4' minimum. Sidewalk minimum width = 5'-0"; TrailISidewalk minimum - 8'-0" Pedestrian ramps at all corners of all intersections. Minimum clear zone = 9' behind face of curb. Design criteria may change if compelling reason demands but shall not be made prior to written justification from the PROFESSIONAL including written concurrence by the COUNTY.

3 Project Deliverables to include: 1. Original 1 1 "x17" Mylar Construction Plans I"= 40' (includes Signing & Marking). 2. Original 8.5"x14" Computation Book. 3. Original 8.5"xI 1" Drainage Design Report. 4. Complete file of all permits issued to COUNTY with their conditions. 5. Other supporting documentation. 6. A computer CD-R disc for IBM format with all CADD files in AutoCAD (preferable) or generic graphic (.dxf) format, documentation of colors and line definitions utilized within the plans, and the data and text files from the electronic fieldbook. The CD disc shall also contain a complete set of final Il"x17" plans in Adobe PDF format, and electronic copies of the final reports and technical specifications. PDF copies should be made from 1 1 "XI 7" originals compressed to produce the smallest web compatible files. SECTION II DESIGN REQUIREMENTS AND PROVISIONS FOR WORK Il-A. Governing Format and Guidelines: The services performed by the PROFESSIONAL shall be in general compliance with applicable Florida Department of Transportation (FDOT) manuals and guideline publications, to accomplish a COUNTY project. FDOT materials incorporate by requirement or reference, applicable State and Federal regulations. Current editions, including updates, of the following Manuals and Guidelines shall be used in the performance of this work and identified in the plans as needed. AASHTO English criteria shall apply; and plans will use English units. This list is not arranged by priority. FDOT Project Development and Environment Guidelines Manual. FDOT Roadway Plans Preparation Manual (2005). FDOT Manual of Uniform Minimum Standards for Design, Construction and Maintenance for Streets and Highways, May FDOT Bicycle Facilities Planning and Design Handbook, Rev FDOT Access Management Standards FDOT Drainage Manual. FDOT Soils & Foundations Procedure Manual. Soil Survey of Pasco County, Florida (1982); USDA Soil Conservation Service. Pasco County Stormwater Management Practices Manual. Pasco County Comprehensive Plan. Pasco County Surveying and Mapping Specifications (1 996). Pasco County Standards for Design & Construction of Water, Wastewater and Reclaimed Water Facilities, June, FDOT Standard Specifications for Road and Bridge Construction (2004) amended for Pasco County modifications. C.R. 54 (SIX) EXHIBIT " A Page 2 of 8

4 Manual on Uniform Traffic Control Devices, (M UTCD), AAS HTO, Manual of Traffic Signal Design (1990), Institute of Transportation Engineers. Il-B. Project Schedule and Progress Reports: Within ten (10) days after the Notice to Proceed, the PROFESSIONAL shall update their proposed schedule, including establishing milepost event dates, and provide a projected payout curve based on that schedule. The schedule may be as detailed as the PROFESSIONAL chooses, but MUST reflect deadlines for mileposts including: Data Gathering, 60% Phase Submittal, 60% Phase Review, Utility Contact, Utility Pre-Design, 100% Phase Review, Receipt of SWFWMD permit, COUNTY reviews and any other events the PROFESSIONAL considers significant. The schedule may be kept in units of calendar days or weeks, but will be presented in a form tracking weeks using Monday dates. The schedule, together with identified mileposts shall be produced and maintained in a format comparable to the Microsoft Project. Single page status/progress reports shall be delivered to the COUNTY in a format approved by the COUNTY, within 5 days of and prior to, submission of the corresponding invoice. These will describe any work behind schedule along with activities underway for the coming month. The approval of each invoice for payment shall be based on confirmation that work of sufficient quality and quantity has been accomplished, and will be made by comparing the reported percent complete against actual work accomplished. Il-C. Key Personnel: The PROFESSIONAL'S work shall be performed and directed by the key personnel identified in the proposal negotiations and/or presentations by the PROFESSIONAL. Any changes in the identified personnel shall be subject to review and approval by the COUNTY. Il-D. Meetings and Presentations: The PROFESSIONAL and his staff shall also be available with no more than a five (5) workday notice to attend meetings or make presentations at the request of the COUNTY. Such meetings and presentations may be held at any hour between 9:00 A.M. and 9:00 P.M., Monday through Friday, with as little as forty-eight (48) hours notice. The PROFESSIONAL may be called upon to provide maps, visual displays and similar material for such meetings. No more than one (1) such meeting is anticipated. Computer simulations will not be required. The PROFESSIONAL and his staff will participate in at least one (1) Public Workshop. The PROFESSIONAL will produce the graphics to be utilized, but will NOT be the presenter. Il-E. Quality Control: The PROFESSIONAL shall be responsible for insuring that work products conform to COUNTY standards and criteria, and represent the same or higher professional quality than available from C.R. 54 (SIX) EXHIBIT "A Page 3 of 8

5 other qualified vendors. This may be accomplished via whatever internal Quality Control (QC) process is customarily performed by the PROFESSIONAL. A QC process that ensures quality is routinely achieved through review by objective, and qualified individuals not directly responsible for performing the initial work may be the most suitable. Prior to submittal of the first invoice, the PROFESSIONAL shall submit to the COUNTY the proposed method or process of providing Quality Control for all work products. The Quality Control Plan shall identify the products to be reviewed, the personnel who perform the reviews and the method of documentation. Il-F. Correspondence: Copies of all written correspondence between the PROFESSIONAL and any other party pertaining specifically to this work shall be provided to the COUNTY for their review and records within one (1) week of the receipt of said correspondence. No changes should occur from unwritten comments. Il-G. Project Manager: The COUNTY will designate a Project Manager who shall be the representative of the COUNTY for the Project. While it is expected the PROFESSIONAL shall seek and receive advice from various state, regional, and local agencies, the final direction on all matters of the Project remain with the Project Manager. SECTION Ill ROADWAY PLANS PACKAGE Ill-A. Roadway Plans Package: The Roadway Plans Package shall be prepared by the PROFESSIONAL. This work effort includes the design and drainage analysis needed to prepare a complete set of roadway plans, drainage plans, signing and pavement marking plans, signalization plans, utility relocation, cost estimates, environmental permits, and other necessary documents, as required. The PROFESSIONAL shall design geometrics for the Project using design standards appropriate with proper consideration given to the design traffic volumes, design speed, capacity and levels of service, functional classification, adjacent land use, design consistency and driver expectancy, aesthetics, pedestrian and bicycle concerns, ADA requirements, elder road user policy, access management, and scope of work. Design elements shall include but not be limited to, the horizontal and vertical alignment, lane width(s), shoulder width, cross slope(s), border width, sight distance, side slopes and ditches, lane transitions, superelevation, features of intersections, interchanges, and limited access points. The geometric design developed by the PROFESSIONAL shall be a desirable engineering solution rather than a simple adherence to the minimum AASHTO andlor FDOT standards. Roadway PlanIProfile Sheets shall be developed to 1 " = 40' on 1 1" x 17" sheets; cross-sections should be at H: 1" = 20'; V: 1" = 5' and will include tabulations of unsuitable materials on the left and suitable material on the right of each sheet. Half-sections shall be shown at driveways and Fullsections at all intersecting roadways. A single Summary of Earthwork shall tabulate volumes for the entire Project, and shall include identification of the contributions of pond and mitigation areas. Plans will be produced as described in Volume II (at ) of the FDOT Plans Preparation Manual. C.R. 54 (SIX) EXHIBIT "A Page 4 of 8

6 Pavement Design: Generally, the pavement design should match the existing pavement. The PROFESSIONAL shall review this Pavement Design for adequacy and recommend another design, if warranted. Ill-C. Drainage Analysis: The PROFESSIONAL shall be responsible for designing a drainage and stormwater management system. All design work shall be in compliance with FDOT'S Drainage Manual, the Southwest Florida Water Management District (SWFWMD), the COUNTY Stormwater Management Practices Manual and the requirements of regulatory agencies. This work will include the engineering analysis necessary to design any or all of the following: cross drains, French drains, roadway ditches, outfall ditches, storm sewers, retention or detention facilities, interchange drainage and stormwater management, 100- year floodplain mitigation, other drainage systems and elements of such systems as may be required for a complete analysis. Full coordination with all permitting agencies and COUNTY will be required. Documentation of all meetings and decisions shall be afforded to the COUNTY. These activities and submittals shall be coordinated with, NOT through, the COUNTY'S Project Manager. 2. The objective is to obtain approved stormwater treatment andlor attenuation design. This work is expected to include, but is not limited to the following: a) Coordinate with local government offices regarding local regulation, restrictions, and investigate possible joint use with the COUNTY. Obtain information concerning present or future development, which could impact the design. b) Discuss preliminary design concepts with permitting agencies. c) Provide preliminary plans during phase submittals for review by the COUNTY and revise as necessary. d) Review modifications to design concept with permitting agencies and finalize plans. 3. The PROFESSIONAL shall design all cross drains to preserve existing flow patterns. Flood data requirements will be determined in accordance with FDOT procedures, except that spread limits apply only to primary through lanes. 4. The PROFESSIONAL shall provide the COUNTY a signed and sealed drainage design report, at the time the Engineering Services Director is asked to sign the Environmental Resource Permit as applicant. This report shall be a record set of all drainage computations, both hydrologic and hydraulic. The PROFESSIONAL shall include all supporting data such as soil borings and permeability tests. A complete set of each response to each Request for Additional Information shall be promptly forwarded to the COUNTY Project Manager. Ill-D. Design Support Components: Plans components for Signing and Pavement Marking and Signalization Design shall each be maintained separately by the Engineer having that expertise, and added to the contract plans set by the 60% roadway submittal. Each element will have a cover sheet similar to the roadway key C.R. 54 (SIX) EXHIBIT "A" Page 5 of 8

7 sheet, without the location map, but listing contents, plus a tabulation of quantities (often with subtotals by plan sheet), and plan sheets or details as needed. Ill-E. Utilities: Initial Contacts - The PROFESSIONAL shall furnish two (2) copies of the 60% review plans (1 l"x17" sheets) to the utility owners for each utility located or known to be proposed within the project limits. The plans shall depict all utilities in accordance with FDOT procedure manuals, design memos, and guidelines. Coordination with Utility Companies - The PROFESSIONAL will be responsible for providing technical data at a Utility Pre-Design Conference arranged by the PROFESSIONAL. The purpose will be to determine the effects the Project has on existing and proposed utility facilities. This allows utility representatives input into the development of the roadway plans. Normally this meeting will be held shortly before 60% Plan completion. The existing utilities shall be shown on the plans and cross section sheets. The PROFESSIONAL shall furnish two (2) copies of the approximately 60% plans to the utility owners for each utility located or proposed within the Project limits. Utility Relocation Agreements shall be requested; using COUNTY forms, along with the adjustment details to be marked on one set the 60% plan prints. Existing and proposed facilities shall be included on the Plan and Profile sheets or separate Utility Adjustment sheet@) in the 100% plans, depicting information on planned adjustments supplied by the utility owners. Ill-F. Environmental Services/Permits: Preliminary Field Review - The PROFESSIONAL shall perform a preliminary field review and shall be responsible for early identification of and coordination with, the appropriate regulatory agencies to assure that design efforts are properly directed toward permit requirements. Agency Coordination - The PROFESSIONAL shall notify the COUNTY of all scheduled meetings with the regulatory agencies and shall copy the COUNTY on all permit-related correspondence and meetings. Agency Field Review - The PROFESSIONAL shall be responsible for coordinating regulatory agency field reviews. Permit Preparation - The PROFESSIONAL shall prepare Permit Packages to include, as required: Wetland ResourceIDredge and Fill permit, Environmental Resource Permit and/or Threatened Species relocation permit. The permits shall be obtained in the name of the COUNTY and signed by the of Engineering Services Director (or Assistant Director), authorized agents for the COUNTY. The PROFESSIONAL shall produce the required number of applications, with all supporting material, for signature by the COUNTY, identify the PROFESSIONAL'S contact person for resolving questions, document the permit fee, and submit the entire package to the COUNTY Project Manager. The COUNTY will sign the permit as the owner, produce the payment check, and deliver the package to SWFWMD for processing. Ill-G FDOT Permits The PROFESSIONAL shall secure any required FDOT Special Use and/or Right-of-way Use Permits for any work in FDOT right-of-way, including driveway and/or drainage connections. C.R. 54 (SIX) EXHIBIT "A" Page 6 of 8

8 SECTION IV SIGNING AND PAVEMENT MARKING PLANS The PROFESSIONAL shall prepare plan sheets, notes, and details to include the following: Key Sheet, Tabulation of Quantities sheet(s) with the quantities tabulated by sheet, General Note sheet(s) including the COUNTY Standard Traffic Control Devices Notes, Plan Sheet(s), Sign Cross Section and Layout sheet(s), Special Marking Detail sheet(s), and Metallconcrete Pole detail(s). Signs and pavement marking shall be designed in accordance with the elder road user policy. All truss or cantilever mounted signs shall include a complete foundation design. Overhead signing (truss or cantilever) shall be lighted; lighted span wire signing will NOT be accepted. If signing requiring lighting is utilized, the PROFESSIONAL shall include electrical details from the service point. SECTION V SIGNALIZATION The purpose for the inclusion of signalization on this project is to adjust existing signals on the project to the six (6) lane configuration. The PROFESSIONAL shall prepare plan sheets, notes and details to include, if required, the following: Key Sheet, Tabulation of Quantities sheet(s) with the quantities tabulated by sheet, General Note sheet(s), Plan Sheet(s), Signalization Plan sheet(s), Special Sign Detail sheet(s) for signs mounted on Signal arms or wires, and Metallconcrete Pole detail(s). Electrical details shall be included from the service point. The signal timings and signal operating plans are included in this work. All signal designs shall use Mast Arms in accordance with the FDOT Mast Arm policy. If span wires must be used, steel strain poles shall be used; concrete strain poles are unacceptable. Appropriate COUNTY standard signal notes shall be included in the signal plans. Notes to be included will depend on pole design and other items. All signal designs shall include overhead street name signs in accordance with FDOT standards. The PROFESSIONAL shall coordinate with the Traffic Operations Division. The PROFESSIONAL shall coordinate with the COUNTY'S Traffic Operations Engineer to ensure equipment inventories remain manageable. The COUNTY will retain final authority on selected equipment. SECTION Vl SUBMITTALS The PROFESSIONAL shall provide copies of the required documents as listed below. These are the anticipated printing requirements for the Project. This tabulation will be used for estimating purposes and the COUNTY will determine the actual number of copies required prior to each submittal. Reproduction for Phase Reviews All CADD-produced drawings for construction (roadway, bridge and component plans) shall be 1l"x 17" at a true scale. Phase submittals of preliminary plans shall be made at the following phases of plans completion with the indicated number of plan sets. Review Phase Copies County Review (Weeks) a. Roadway Plans* (60%) 5 2 weeks (I 00%) 3 2 weeks C.R. 54 (SIX) EXHIBIT " A Page 7 of 8

9 nnn oh)- VVV

EXHIBIT A SCOPE OF SERVICES INTERCHANGE JUSTIFICATION REPORT (IJR) FOR INTERSTATE 75 AT OVERPASS ROAD

EXHIBIT A SCOPE OF SERVICES INTERCHANGE JUSTIFICATION REPORT (IJR) FOR INTERSTATE 75 AT OVERPASS ROAD Scope of Services 12/08/2008 EXHIBIT A SCOPE OF SERVICES INTERCHANGE JUSTIFICATION REPORT (IJR) FOR INTERSTATE 75 AT OVERPASS ROAD TABLE OF CONTENTS Section Pace I. 0 PROJECT DESCRIPTION........................,............................................................

More information

TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP &

TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP & TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP 4910-29 & 0504-14 Contract No. 1002252 Project Overview is in need of professional and technical assistance to provide detail design for State

More information

EXHIBIT A SCOPE OF SERVICES FOR DISTRICTWIDE CONSULTING ENGINEERNG SERVICES STRUCTURES DESIGN

EXHIBIT A SCOPE OF SERVICES FOR DISTRICTWIDE CONSULTING ENGINEERNG SERVICES STRUCTURES DESIGN EXHIBIT A SCOPE OF SERVICES FOR DISTRICTWIDE CONSULTING ENGINEERNG SERVICES STRUCTURES DESIGN Financial Project ID: 417069-1-32-04 Work Program Item No.: N/A Federal Aid Project ID: County/Section No.:

More information

CHAPTER 3 SCOPE SUMMARY

CHAPTER 3 SCOPE SUMMARY CHAPTER 3 SCOPE SUMMARY GENERAL The SDDOT is an active member of AASHTO to share common national design standards for the state highway system. The AASHTO Task Force on Geometric Design has completed the

More information

ATTACHMENT "A" SCOPE OF SERVICES FOR TRAFFIC ENGINEERING STUDIES AND ENGINEERING REVIEWS CONSULTANT

ATTACHMENT A SCOPE OF SERVICES FOR TRAFFIC ENGINEERING STUDIES AND ENGINEERING REVIEWS CONSULTANT ATTACHMENT "A" SCOPE OF SERVICES FOR TRAFFIC ENGINEERING STUDIES AND ENGINEERING REVIEWS CONSULTANT I. OBJECTIVE The objective of this contract is to provide professional and technical services to develop

More information

Exhibit A Scope of Work. 0.0 Separation of work Types and Cost Estimate

Exhibit A Scope of Work. 0.0 Separation of work Types and Cost Estimate 0.0 Separation of work Types and Cost Estimate Exhibit A Scope of Work 0.1 Prepare scope of work and cost estimate for MnDOT efforts relating to all items numbered less than 20.0. 0.2 Prepare scope of

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design Exceptions / Waivers SPECIFIC SUBJECT: Design Exception Request Form

More information

CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS CUYAHOGA COUNTY ENGINEER TOWNSHIP SUBDIVISION STREET DESIGN STANDARDS AND IMPROVEMENT PLAN REQUIREMENTS

CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS CUYAHOGA COUNTY ENGINEER TOWNSHIP SUBDIVISION STREET DESIGN STANDARDS AND IMPROVEMENT PLAN REQUIREMENTS CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS CUYAHOGA COUNTY ENGINEER TOWNSHIP SUBDIVISION STREET DESIGN STANDARDS AND IMPROVEMENT PLAN REQUIREMENTS November 25, 2013 Table of Contents Cuyahoga County Engineer's

More information

Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida

Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida November 7, 2014 SUBMITTED BY: Dewberry Bowyer-Singleton 520 South

More information

GENERAL NOTES ROADWAY CONSTRUCTION RD0001-1A ISSUED:2017 REVISED: --

GENERAL NOTES ROADWAY CONSTRUCTION RD0001-1A ISSUED:2017 REVISED: -- ROADWAY CONSTRUCTION NOTES 1. ALL RIGHT-OF-WAY OTHER THAN ROADWAY AREAS SHALL BE SODDED. ALL SLOPE STEEPER THAN 6:1 SHALL REQUIRE SODDING. THE CITY RESERVES THE RIGHT TO REQUIRE SODDING IN SPECIAL AREAS

More information

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction Chapter 1 Bridge Design Manual General Design Information Section 1.02 Selection and Geometry Introduction Selection or Rehabilitation Report This section of the design manual provides guidance on the

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

Plan Preparation Guide. Chapter 2. Typical Sections - Pavement Design

Plan Preparation Guide. Chapter 2. Typical Sections - Pavement Design Plan Preparation Guide Chapter 2 Typical Sections - Pavement Design Section Description Page 1 Typical Sections 2-1 2 Secondary ( C projects) Typical Sections 2-3 3 Base Course 2-4 4 Full Depth Asphalt

More information

SCOPE 1.0 General Requirements

SCOPE 1.0 General Requirements SCOPE 1.0 General Requirements This section outlines a general list of the responsibilities and requirements for the GEC. It is anticipated that the GEC will be used to support and supplement MnDOT staff

More information

ROADWAY DESIGN AND CONSTRUCTION STANDARDS

ROADWAY DESIGN AND CONSTRUCTION STANDARDS ROADWAY DESIGN AND CONSTRUCTION STANDARDS Adopted: 1990 Amended: 1994 2003 2011 2013 ROADWAY DESIGN AND CONSTRUCTION STANDARDS ORIGINALLY ADOPTED IN 1990 Resolution No. R-990-046 OFFICIALLY AMENDED IN

More information

Table Related Arlington County Standards, Specification and Policies

Table Related Arlington County Standards, Specification and Policies 2.1 GENERAL 2.1.1 DESCRIPTION SITE WORK V02000 2.1 GENERAL 2.1.1 Description This standard identifies minimum requirements that shall be met for all site work in the design and construction of elements

More information

TABLE OF CONTENTS SECTION

TABLE OF CONTENTS SECTION PREFACE This manual contains current information for designing and submitting transportation plans for proposed projects to be constructed in unincorporated Hillsborough County. This manual is a readily

More information

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects SEPTEMBER 1989 Arkansas State Highway and Transportation Department GEOMETRIC DESIGN CRITERIA for Non-freeway

More information

DRAFT SCOPE 1.0 General Requirements

DRAFT SCOPE 1.0 General Requirements DRAFT SCOPE 1.0 General Requirements This section outlines a general list of the responsibilities and requirements for the GEC. It is anticipated that the GEC will be used to support and supplement MnDOT

More information

CONSTRUCTION PLAN CHECKLIST

CONSTRUCTION PLAN CHECKLIST CONSTRUCTION PLAN CHECKLIST The design engineer is responsible for ensuring that plans submitted for city review are in accordance with this checklist. It is requested that the executed checklist be submitted

More information

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision Plat Name: Location Description/ Nearest Intersection: Acreage:

More information

TxDOT Houston District Permit Requirements (Information contained herein is subject to change)

TxDOT Houston District Permit Requirements (Information contained herein is subject to change) Houston District Permit Requirements (Information contained herein is subject to change) Access Driveway for Commercial / Industrial Developments; or Street Tie-In / Drainage-Only 1) Complete the three

More information

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES 1 PURPOSE... 3 2 PROJECT DESCRIPTION... 5 3 PROJECT COMMON AND PROJECT GENERAL TASKS... 6 4 ROADWAY

More information

INDIVIDUAL PROJECT ORDER NUMBER 2 January 5, 2010

INDIVIDUAL PROJECT ORDER NUMBER 2 January 5, 2010 INDIVIDUAL PROJECT ORDER NUMBER 2 January 5, 2010 Describing a specific agreement between Kimley-Horn and Associates, Inc. ( KHA or the Consultant ), and The Village Center Community Development District

More information

EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID: DISTRICT TWO

EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID: DISTRICT TWO EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID: 430959-1-22-01 DISTRICT TWO Stage I Scope A-1 August 2, 2017 SCOPE OF SERVICES DISTRICTWIDE ENVIRONMENTAL SERVICES FLORIDA DEPARTMENT OF TRANSPORTATION

More information

APPENDIX B. Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies

APPENDIX B. Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies APPENDIX B Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies Revised December 7, 2010 via Resolution # 100991 Reformatted March 18, 2011 TABLE OF CONTENTS

More information

12 DRAINAGE General Administrative Requirements Standards

12 DRAINAGE General Administrative Requirements Standards 12 DRAINAGE 12.1 General The Design-Builder shall conduct all Work necessary to meet the requirements associated with drainage, including culverts, bridge hydraulics, roadway ditches, and closed storm

More information

Transportation Technical Manual for Subdivision and Site Development Projects

Transportation Technical Manual for Subdivision and Site Development Projects Public Works Department Transportation Technical Manual for Subdivision and Site Development Projects October 2015 HillsboroughCounty.org PREFACE This manual contains current information for designing

More information

Exhibit A Mn/DOT Contract No

Exhibit A Mn/DOT Contract No Exhibit A Mn/DOT Contract No. 98142 SCOPE OF WORK AND DELIVERABLES Preliminary Design Red Wing US 63 Bridge and Approach Roadways State Project (SP) 2515-21 SCOPE OVERVIEW... 2 SCHEDULE... 2 PROJECT TASK

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

CHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS

CHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS CHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS Section Title Page 12.1 General... 12-1 12.2 Design Standards... 12-1 12.2.1 General Requirements...12-1 12.2.2 Minimum Depth...12-1

More information

Texas Department of Transportation Book 2 Technical Provisions. Grand Parkway Project. Attachment 2-2. Work Breakdown Structure Requirements

Texas Department of Transportation Book 2 Technical Provisions. Grand Parkway Project. Attachment 2-2. Work Breakdown Structure Requirements Texas Department of Transportation Book 2 Technical Provisions Grand Parkway Project Work Breakdown Structure Requirements Table 1 represents the minimum levels of the WBS that all schedule information

More information

Exit 73 I-29 Interchange Modification Justification Study

Exit 73 I-29 Interchange Modification Justification Study xit 73 I-29 Interchange Modification Justification tudy Introduction Figure 1 shows the location of xit 73. This interchange is proposed to be the connecting point of the ast and West Corridors to I-29.

More information

EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE

EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE The Existing Roadway Condition Assessment Report (ERCAR) should include the evaluation of all elements against new construction criteria.

More information

Final Estimates Level 2

Final Estimates Level 2 Florida Department of TRANSPORTATION Final Estimates Level 2 Module 8 Final As Built Plans 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 8 1 Final As-Built Plans are important to construction,

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW7 September 2017 SW7.01 Purpose The purpose of this Chapter is to establish a basis for inlet design utilizing City of Fort Wayne standard inlets and

More information

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification 7. Introduction This chapter summarizes methods to evaluate runoff conveyance in various street cross sections and curb types in the Town of Castle Rock and identifies acceptable upper limits of street

More information

The TIS is to be signed and sealed by a Florida Registered Professional Engineer.

The TIS is to be signed and sealed by a Florida Registered Professional Engineer. CHAPTER 900. SECTION 901. DEVELOPMENT STANDARDS INFRASTRUCTURE STANDARDS 901.5. Transportation Impact Study A. Intent and Purpose The intent and purpose of the Traffic Impact Study (TIS) is to identify

More information

HILLSBOROUGH COUNTY TRANSPORTATION TECHNICAL MANUAL FOR SUBDIVISION AND SITE DEVELOPMENT PROJECTS APPROVED

HILLSBOROUGH COUNTY TRANSPORTATION TECHNICAL MANUAL FOR SUBDIVISION AND SITE DEVELOPMENT PROJECTS APPROVED Potential Changes/Edits to be Incorporated and Effective October 2017 HILLSBOROUGH COUNTY TRANSPORTATION TECHNICAL MANUAL FOR SUBDIVISION AND SITE DEVELOPMENT PROJECTS APPROVED APPROVED: Michael Williams,

More information

Location Drainage Study

Location Drainage Study Location Drainage Study PROJECT ROUTE: LIMITS: MUNICIPALITY/COUNTY: JOB NUMBER: IL 47 at Burlington Road 750ft NW to 750ft SE of IL 47(Burlington), & 1000ft S to 1000ft N of Burlington (IL47) Kane County

More information

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES 4.0 INTRODUCTION The ability to accommodate high volumes of intersecting traffic safely and efficiently through the arrangement of one or more interconnecting

More information

District No.: Applicant: Type of Work:

District No.: Applicant: Type of Work: Fee: Permit No.: District No.: Applicant: Type of Work: FOR DEPARTMENT USE ONLY APPLICATION AND ANNUAL PERMIT FOR TELECOMMUNICATION OCCUPANCY OF NEVADA DEPARTMENT OF TRANSPORTATION RIGHT-OF-WAY (Under

More information

TRAFFIC SAFETY STUDIES & HIGHWAY DESIGN GUIDE SCOPE OF WORK EXHIBIT A SCOPE OF SERVICES. For / 16

TRAFFIC SAFETY STUDIES & HIGHWAY DESIGN GUIDE SCOPE OF WORK EXHIBIT A SCOPE OF SERVICES. For / 16 TRAFFIC SAFETY STUDIES & HIGHWAY DESIGN GUIDE SCOPE OF WORK EXHIBIT A SCOPE OF SERVICES For 237995-1-32 15 / 16 DISTRICTWIDE SAFETY STUDIES AND DESIGN SCOPE OF SERVICES FOR CONSULTING ENGINEERING SERVICES

More information

CITY OF VALLEJO PUBLIC WORKS DEPARTMENT TRAFFIC IMPACT Analysis/Study GUIDELINES

CITY OF VALLEJO PUBLIC WORKS DEPARTMENT TRAFFIC IMPACT Analysis/Study GUIDELINES The City Engineer, under the authority of the Public Works Director and recommendations from the Traffic Engineer, will make the final decision on the need for a traffic study. The purpose of the traffic

More information

Chapter 8. Inlets. 8.0 Introduction. 8.1 General

Chapter 8. Inlets. 8.0 Introduction. 8.1 General . Introduction This chapter provides criteria and design guides for evaluating and designing storm sewer inlets in the City of Centennial. The review of all planning submittals will be based on the criteria

More information

CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION

CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION SECTION 2B 1 - GROUND SURVEYS Survey Authorization... 2B-1 Interstate... 2B-1 Principal / Minor Arterial... 2B-1 Urban...

More information

PERMITTED USES: Within the MX Mixed Use District the following uses are permitted:

PERMITTED USES: Within the MX Mixed Use District the following uses are permitted: 6.24 - MX - MIXED USE DISTRICT 6.24.1 INTENT: The purpose of the MX Mixed Use District is to accommodate the development of a wide-range of residential and compatible non-residential uses (including major

More information

TRANSPORTATION TECHNICAL MANUAL

TRANSPORTATION TECHNICAL MANUAL HILLSBOROUGH COUNTY TRANSPORTATION TECHNICAL MANUAL FOR SUBDIVISIONS AND SITE DEVELOPMENT PROJECTS PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION September 1, 2009 REVISIONS The Transportation Technical

More information

SUBDIVISION SECTION STREET DESIGN MANUAL

SUBDIVISION SECTION STREET DESIGN MANUAL CITY OF ANAHEIM SUBDIVISION SECTION STREET DESIGN MANUAL A. INTRODUCTION : POLICY STATEMENT B. STREET CLASSIFICATION C. STREET STANDARDS REQUIREMENTS Requirements Approval of Street Improvement Plans Widening

More information

I535 NB off ramp to I35 SB over I35 and the Burlington Northern Santa Fe (BNSF) Railroad I535 NB off ramp to I35 NB over I35 and the BNSF

I535 NB off ramp to I35 SB over I35 and the Burlington Northern Santa Fe (BNSF) Railroad I535 NB off ramp to I35 NB over I35 and the BNSF Final Bridge Design Twin Ports Interchange Bridges State Project Nos. (SP) 6980-60, 6915-136, 6982-322 Exhibit A Scope of Services PROJECT OVERVIEW State has programmed the construction of the Twin Ports

More information

I. Project Overview and Limits. Project Goal

I. Project Overview and Limits. Project Goal Scope of Work and Deliverables for Subsurface Utility Engineering (SUE) for both Underground and Overhead Utilities on T.H. 10, and its Connecting Roads under S.P. 8001-40 I. Project Overview and Limits

More information

TABLE OF CONTENTS CHAPTER 2D - PLAN DESIGN. SECTION 2D-1 PROJECT REVIEW General... 2D-1

TABLE OF CONTENTS CHAPTER 2D - PLAN DESIGN. SECTION 2D-1 PROJECT REVIEW General... 2D-1 TABLE OF CONTENTS CHAPTER 2D - PLAN DESIGN SECTION 2D-1 PROJECT REVIEW General... 2D-1 SECTION 2D-2 PREPARATION OF INFORMATIONAL BROCHURES Responsibility... 2D-2 Purpose of Brochure... 2D-2 Review of Draft

More information

Request for Proposals. Hillsdale Pedestrian/Bicyclist Bridge Design

Request for Proposals. Hillsdale Pedestrian/Bicyclist Bridge Design Request for Proposals Hillsdale Pedestrian/Bicyclist Bridge Design Public Works Department City of San Mateo 330 West 20th Avenue San Mateo, CA 94403 JUNE 13, 2013 The City of San Mateo (CITY) is accepting

More information

EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID FEDERAL AID NO. D B

EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID FEDERAL AID NO. D B EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID 440225-1-32-01 FEDERAL AID NO. D118 091 B ADAPTIVE SYSTEM ON US 27 FROM HIGHLANDS AVE TO SEBRING PKWY HIGHLANDS COUNTY DISTRICT ONE June 7, 2018 TABLE

More information

Article 16 Traffic Impact Analysis

Article 16 Traffic Impact Analysis Article 16 Traffic Impact Analysis Table of Contents... 16-1 Chapter 16.1 Purpose and Intent... 16-2 Chapter 16.2 Applicability... 16-2 Chapter 16.3 Exemptions... 16-2 Chapter 16.4 Trip Generation Data...

More information

EXHIBIT "A" SCOPE OF SERVICES FOR DISTRICT 7 AREAWIDE LIGHTING DATABASE & ASSESSMENT CONTINUING SERVICES FINANCIAL PROJECT NO.

EXHIBIT A SCOPE OF SERVICES FOR DISTRICT 7 AREAWIDE LIGHTING DATABASE & ASSESSMENT CONTINUING SERVICES FINANCIAL PROJECT NO. EXHIBIT "A" SCOPE OF SERVICES FOR DISTRICT 7 AREAWIDE LIGHTING DATABASE & ASSESSMENT CONTINUING SERVICES FINANCIAL PROJECT NO. 443787 1 72 01 Revised: 07/05/18 06/29/18 TABLE OF CONTENTS PAGE NO. I. PURPOSE...

More information

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements This checklist is to be completed and submitted with all Subdivision Applications. The Town reserves

More information

Agenda Item B.9 CONSENT CALENDAR Meeting Date: May 19, 2015

Agenda Item B.9 CONSENT CALENDAR Meeting Date: May 19, 2015 CPMS Agenda Item B.9 CONSENT CALENDAR Meeting Date: May 19, 2015 TO: FROM: Mayor and Councilmembers Rosemarie Gaglione, Public Works Director CONTACT: James Winslow, Sr. Project Manager SUBJECT: Amendment

More information

175 th Street Quivira to Antioch (TH-1343) Preliminary Engineering Study Overland Park, KS

175 th Street Quivira to Antioch (TH-1343) Preliminary Engineering Study Overland Park, KS 175 th Street Quivira to Antioch (TH-1343) Preliminary Engineering Study Overland Park, KS June 2012 Prepared by: Public Works Department City of Overland Park, KS EXECUTIVE SUMMARY... 2 INTRODUCTION...

More information

St. Francis Drive through the City of Santa Fe Corridor Study

St. Francis Drive through the City of Santa Fe Corridor Study VIII. ENGINEERING AND ENVIRONMENTAL EVALUATION INTERSECTION IMPROVEMENTS SOUTHERN For the southern end of the corridor, traffic volumes are expected to increase over existing levels. The Phase A Report

More information

Highway Engineering. 3 _ 2/2 Lecture/Laboratory Hours

Highway Engineering. 3 _ 2/2 Lecture/Laboratory Hours COURSE OUTLINE CIV216 Course Number Highway Engineering Course Title 3 _ 2/2 Credits Lecture/Laboratory Hours COURSE DESCRIPTION Explores the planning, design, construction, and characteristics of highways

More information

Final Air Quality Report

Final Air Quality Report Florida Department of TRANSPORTATION Final Air Quality Report PD&E Study From East of Babcock Street (SR 507) to US 1 Brevard County, Florida Financial Project ID: 430136-1-22-01 ETDM Project Number: 13026

More information

Review of Plans and Specs from a Constructability Perspective

Review of Plans and Specs from a Constructability Perspective Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability

More information

LOCATION HYDRAULIC REPORT

LOCATION HYDRAULIC REPORT Draft LOCATION HYDRAULIC REPORT Florida Department of Transportation District One US 41 at Fruitville Road (CR 780) Intersection Improvements - PD&E STUDY Sarasota County, Florida Financial Project ID

More information

Chapter 5. Utilities

Chapter 5. Utilities Chapter 5 Utilities 5.1 General...5-1 5.2 Utility Accommodation Manual...5-2 5.3 Location of Existing Utilities...5-3 5.3.1 Quality Levels of Utility Locates...5-3 5.4 Subsurface Utility Engineering...5-5

More information

CITY OF HILSHIRE VILLAGE SWIMMING POOL PLAN SUBMITTAL CHECK LIST ADDRESS: DATE:

CITY OF HILSHIRE VILLAGE SWIMMING POOL PLAN SUBMITTAL CHECK LIST ADDRESS: DATE: CITY OF HILSHIRE VILLAGE SWIMMING POOL PLAN SUBMITTAL CHECK LIST "THE FOLLOWING CHECKLIST IS ONLY A SUMMARY THAT IS PROVIDED FOR THE APPLICANT'S BENEFIT; HOWEVER, FULFILLING THE REQUIREMENTS OF THIS SUMMARY

More information

Tarbutton Road Interchange and I-20 Frontage Roads. Estimating and Planning Group

Tarbutton Road Interchange and I-20 Frontage Roads. Estimating and Planning Group Tarbutton Road Interchange and I-20 Frontage Roads Dr. N. Wasiuddin Braden Smith Jared Taylor John Harrison Sarah Wells Samantha Tatro Ryan Ross Instructor Project Manager Transportation Group Geotechnical

More information

PLANNED UNIT DEVELOPMENT, PLANNING APPROVAL & SUBDIVISION STAFF REPORT Date: June 4, 2015

PLANNED UNIT DEVELOPMENT, PLANNING APPROVAL & SUBDIVISION STAFF REPORT Date: June 4, 2015 PLANNED UNIT DEVELOPMENT, PLANNING APPROVAL & SUBDIVISION STAFF REPORT Date: June 4, 2015 NAME SUBDIVISION NAME CC Williams Plant Subdivision CC Williams Plant Subdivision LOCATION CITY COUNCIL DISTRICT

More information

MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK

MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK The professional services to be provided by the Consultant under this Agreement shall be as necessary to complete the required analyses, layouts,

More information

Stormwater Management Manual Revision History

Stormwater Management Manual Revision History Stormwater Management Manual Revision History Manual Creation Date: January 30, 2007 12/12/2006 Water Quality for Post-Construction Standards and Criteria are established as part of the National Pollution

More information

LOT GRADING. LOT GRADING REQUIREMENTS The following lot grading requirements came into effect on May 1, 2007:

LOT GRADING. LOT GRADING REQUIREMENTS The following lot grading requirements came into effect on May 1, 2007: LOT GRADING DEFINITION Lot grading is the reshaping or sloping of the land in such a way that surface drainage from rain runoff is directed away from the buildings and is controlled in a manner that eliminates

More information

STREET IMPROVEMENTS (Refer to Title 18, chapter entitled "STREETS" of the Layton Municipal Code.)

STREET IMPROVEMENTS (Refer to Title 18, chapter entitled STREETS of the Layton Municipal Code.) STREET IMPROVEMENTS (Refer to Title 18, chapter 18.24 entitled "STREETS" of the Layton Municipal Code.) I. Street widths STREET TYPE (ALL MEASUREMENTS IN FEET) ROW WIDTH LAYTON CITY STANDARD STREET SECTIONS

More information

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials.

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials. I. Drainage Report A. Executive Summary - Brief Overview of Project Drainage Design B. Project Description 1. Existing Conditions 2. Proposed Project Conditions 3. Project Justification Narrative - Basin

More information

DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA

DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA This report was prepared to present development information (Utility availability, Development Regulations, Flood Plain information,

More information

Conceptual Design Report

Conceptual Design Report Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE

More information

SECTION 6. ROAD CONSTRUCTION STANDARDS

SECTION 6. ROAD CONSTRUCTION STANDARDS SECTION 6. ROAD CONSTRUCTION STANDARDS Construction of new roads or reconstruction of existing roads proposed for dedication to the County shall conform to the standards set forth in this section. Roads

More information

SECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS

SECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS SECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS 12.1 The subdivider shall construct and install the improvements in accordance with the County's Standards for Construction Plans and Specifications

More information

2003 PRELIMINARY ENGINEERING STUDY JUNE 2006

2003 PRELIMINARY ENGINEERING STUDY JUNE 2006 167 TH STREET PFLUMM ROAD TO METCALF AVENUE 159 th STREET & PFLUMM ROAD INTERSECTION PFLUMM ROAD 159 TH STREET TO 175 TH STREET QUIVIRA ROAD 159 TH STREET TO 167 TH STREET SWITZER ROAD 159 TH STREET TO

More information

SUBDIVISION CHECKLIST. Subdivision Name. Prior To Review. Preliminary plan approved by Planning Commission / Council as required.

SUBDIVISION CHECKLIST. Subdivision Name. Prior To Review. Preliminary plan approved by Planning Commission / Council as required. SUBDIVISION CHECKLIST Subdivision Name Account Number Review Engineer Prior To Review Preliminary plan approved by Planning Commission / Council as required. Review fee paid. Statement of Responsibility

More information

SR 50 PD&E Study

SR 50 PD&E Study SR50 Project Development & Environment Study Public Hearing November 1, 2011 SR 50 PD&E Study 427056-1-22-01 1 Purpose of the Public Hearing Afford persons the opportunity to express their views about

More information

PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56

PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56 PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56 Additional Fees Additional fees may be charged by PennDOT consistent with Sections 411 and 420 of the State Highway Law and Regulations 441.4(d)

More information

Traffic Impact Analysis (TIA) POLICY

Traffic Impact Analysis (TIA) POLICY Ascension Parish Planning Commission Traffic Impact Analysis (TIA) POLICY This policy establishes requirements for studies that provide information on traffic projected to be generated by all proposed

More information

ARTICLE 700 LARGE SCALE DEVELOPMENTS

ARTICLE 700 LARGE SCALE DEVELOPMENTS ARTICLE 700 LARGE SCALE DEVELOPMENTS SEC. 700.1 APPLICABILITY A development plan shall be submitted to the Bentonville Planning Commission for all developments or building construction regardless of zone

More information

Construction Cost Estimation Preparation Manual for Preliminary Design (English Units)

Construction Cost Estimation Preparation Manual for Preliminary Design (English Units) 10/16/2014 Construction Cost Estimation Preparation Manual for Preliminary Design (English Units) July 2002 Prepared by Construction Cost Estimating Unit Program Support Services 10/16/2014 Table of Contents

More information

Chapter 9 - Storm Drains

Chapter 9 - Storm Drains Chapter 9 - Storm Drains TABLE OF CONTENTS CHAPTER 9 - STORM DRAINS... 9-1 9.1 Introduction... 9-1 9.1.1 Objective 9-1 9.2 Design Policy... 9-2 9.2.1 Definition 9-2 9.2.2 General Policies... 9-2 9.3 Design

More information

CUYAHOGA COUNTY ENGINEER

CUYAHOGA COUNTY ENGINEER CUYAHOGA COUNTY ENGINEER DRAINAGE MANUAL Supplement to O.D.O.T. LOCATION and DESIGN MANUAL, Volume 2, Drainage Design, Section 1000 and 1100 May 28, 2010 Revisions to the July 29, 2009 edition are noted

More information

EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID TRANSPORTATION SYSTEM MANAGEMENT & OPERATIONS (TSM&O) GENERAL CONSULTANT SERVICES

EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID TRANSPORTATION SYSTEM MANAGEMENT & OPERATIONS (TSM&O) GENERAL CONSULTANT SERVICES EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID 432430-1-32-13 TRANSPORTATION SYSTEM MANAGEMENT & OPERATIONS (TSM&O) GENERAL CONSULTANT SERVICES DISTRICT TWO November 27, 2017 Page 1 EXHIBIT A SCOPE

More information

AMENDMENT D TO THE CONTRACT FOR INDEPENDENT CONTRACTOR SERVICES BETWEEN THE CITY OF FERNLEY AND NCE

AMENDMENT D TO THE CONTRACT FOR INDEPENDENT CONTRACTOR SERVICES BETWEEN THE CITY OF FERNLEY AND NCE AMENDMENT D TO THE CONTRACT FOR INDEPENDENT CONTRACTOR SERVICES BETWEEN THE CITY OF FERNLEY AND NCE This Amendment D to the Contract for Independent Contractor between the City of Fernley and NCE is entered

More information

New Jersey Turnpike Authority

New Jersey Turnpike Authority New Jersey Turnpike Authority DOCUMENT UPDATE REQUEST Forward to Assistant Chief Engineer, Design Initiator Russell Saputo, PE Submittal Date 6/21/16 Firm Stantec Consulting Services Inc. Telephone 201-587-9040

More information

Community Advisory Committee Meeting No. 2. June 22, 2006

Community Advisory Committee Meeting No. 2. June 22, 2006 Community Advisory Committee Meeting No. 2 June 22, 2006 Introductions The Study Team KDOT Wichita Partners Consultants CAC members Overview Today s Agenda Opinion Survey Study Status Starting Concept

More information

TSM&O STUDIES & DESIGN SCOPE OF SERVICES TRANSPORTATION SYSTEMS MANAGEMENT AND OPERATIONS SCOPE OF SERVICES FOR CONSULTING ENGINEERING SERVICES

TSM&O STUDIES & DESIGN SCOPE OF SERVICES TRANSPORTATION SYSTEMS MANAGEMENT AND OPERATIONS SCOPE OF SERVICES FOR CONSULTING ENGINEERING SERVICES TSM&O STUDIES & DESIGN SCOPE OF WORK EXHIBIT A SCOPE OF SERVICES For 439045-1-32-02 439045-1-32-03 DISTRICT WIDE TRANSPORTATION SYSTEMS MANAGEMENT AND OPERATIONS SCOPE OF SERVICES FOR CONSULTING ENGINEERING

More information

Scope of Services Experience Requirements Vendor Responsibilities

Scope of Services Experience Requirements Vendor Responsibilities Scope of Services The Ocala/Marion County Transportation Planning Organization (TPO) requires the professional services of one or more consultant(s) to provide production support to the TPO Staff in accomplishing

More information

Gloucester Parkway Extension RFQ Information Meeting

Gloucester Parkway Extension RFQ Information Meeting Gloucester Parkway Extension RFQ Information Meeting May 24, 2013 Tim Hartzell, PE District Project Manager Kevin Reichert, PE APD Project Manager and POC Topics Project Location & Overview RFQ Information

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS Village of La Grange Phase II Design Engineering Services for Submission Deadline: No later than 10:00 am on October 19, 2018 Published on: October 5, 2018 on the Village of

More information

Project: Developer/Designer: Reviewer:

Project: Developer/Designer: Reviewer: City of Charlottesville, Virginia Engineering Plan Review Checklist (Site Plans, Site Plan Amendments, and Major Subdivisions) 610 East Market Street, Charlottesville, VA 22902 Telephone 434-970-3182;

More information

2017 Highway Safety Improvement Program Call

2017 Highway Safety Improvement Program Call 2017 Highway Safety Improvement Program Call The Highway Safety Improvement Program (HSIP) is for highway safety projects that eliminate or reduce the number of fatalities and serious injuries on all public

More information

Section 13. Guidelines for the Design of Ground Mounted Sign Supports

Section 13. Guidelines for the Design of Ground Mounted Sign Supports Section 13 BDC11MR-04 13.1 Introduction Highway signs fall into two main categories, which are subdivided as follows: 1. Overhead Signs a. Sign Bridge Structures (GO) b. Sign Cantilever Structures (GO)

More information

Construction Cost Estimation Preparation Manual (Metric Units)

Construction Cost Estimation Preparation Manual (Metric Units) 07/25/2001 Construction Cost Estimation Preparation Manual (Metric Units) July 2001 Prepared by Cost Estimating Unit Program Support Services 07/25/2001 Table of Contents Section Page 1.0 Introduction

More information

Page 1D-1 Revised language to link from Project Management Manual to Project Management Online Guide.

Page 1D-1 Revised language to link from Project Management Manual to Project Management Online Guide. IMPERIAL ROAD DESIGN MANUAL REVISIONS July 2008 CHAPTER 1D Page 1D-1 Revised language to link from Project Management Manual to Project Management Online Guide. CHAPTER 2A Page 2A-3 Revised language to

More information