Stress Corrosion Cracking in a Dissimilar Metal Butt Weld in a 2 inch Nozzle. Master of Engineering in Mechanical Engineering

Size: px
Start display at page:

Download "Stress Corrosion Cracking in a Dissimilar Metal Butt Weld in a 2 inch Nozzle. Master of Engineering in Mechanical Engineering"

Transcription

1 Stress Corrosion Cracking in a Dissimilar Metal Butt Weld in a 2 inch Nozzle by Thomas E. Demers An Engineering Project Submitted to the Graduate Faculty of Rensselaer Polytechnic Institute in Fulfillment of the Requirements for the Degree of Master of Engineering in Mechanical Engineering Approved: Ernesto Gutierrez-Miravete, Project Adviser Rensselaer Polytechnic Institute Hartford, CT August, 2013

2 Table of Contents 1.0 Introduction/Background and Purpose Input and Methodology Stress Intensity Factor (K) Solution Stress Input Crack Growth Methodology and Growth Laws Limiting Flaw Depth Methodology Results and Discussion Calculation of Stress Intensity Factor K I Calculation of Stress Corrosion Cracking Growth Stainless Steel Growth Rate Alloy 82/182 Growth Rate at 617 F Alloy 82/182 Growth Rate at 650 F Summary and Conclusion References... 45

3 List of Tables

4 List of Figures

5 List of Symbols

6 Acronyms

7 Keywords

8 Acknowledgements I would like to thank Professor Ernesto Guiterrez-Miravete and my Current and Former Westinghouse colleagues David Ayres, Warren Bamford, and Reddy Ganta for their advice on this project and subject matter. I would like to thank Ya T. Wu for his work developing the residual stresses used as input to this report, and his assistance in providing additional information and clarification when necessary. I would also like to thank Westinghouse Electric Company for their financial support of my engineering masters degree.

9 Abstract

10 1.0 Introduction/Background and Purpose Alloy 82/182 dissimilar metal (DM) butt welds have been used in nuclear power plant reactor coolant systems (RCS) to join stainless steel piping to low alloy or carbon steel components (see Figure 1-1). These welds are typically between RCS nozzles and RCS piping. Alloy 82/182, a nickel-based alloy also referred to as Alloy 600, has been found to be susceptible to pressurized water stress corrosion cracking (PWSCC) as documented in several industry documents [3, 9, 11]. This is also mentioned in the input residual stress calculation [1]. PWSCC is also referred to as stress corrosion cracking (SCC). Per [3], PWSCC in Alloy 82 and 182 welds involves an intergranular cracking mechanism, which is referred to as intergranular stress corrosion cracking (IGSCC). Figure 1-1: Typical Dissimilar Metal Nozzle Butt Weld [1] IGSCC refers to stress corrosion cracking that occurs along the grain boundaries within a material. This is referred to as active path dissolution in [7], which involves accelerated corrosion along a path of higher than normal corrosion susceptibility. While IGSCC is the mechanism experienced in Alloy 82/182, it is important to realize that the cracking is not occurring due to sensitization, which is typically discussed for IGSCC in stainless steels [3]. According to [8], SCC is cracking due to conjoint corrosion and straining of a metal due to residual and applied stresses. Furthermore, as described in [7], SCC depends on the simultaneous achievement of three requirements: A susceptible material An environment that causes SCC for that material Sufficient tensile stress to induce SCC All three criteria are satisfied. Alloy 82/182 has been shown to be susceptible to SCC, and its susceptibility is documented in multiple industry documents, including [3]. The high pressure and corrosive environment of a pressurized water reactor causes SCC for the material, specifically on the inside diameter surface of the weld. Finally, the weld experiences sufficient tensile stress to induce SCC. In this case the high tensile stresses are due to a combination of highly tensile weld residual stresses on the inside surface with an applied stress. This matches the description from [8]. As mentioned in [8], the effect of the applied stress is mainly to open up the cracks, thereby allowing easier diffusion of corrosion products away from the crack tip, which in turn allows the crack tip to corrode faster.

11 Both the DM butt weld and the ID repair weld are modeled in [1] as Alloy 82/182 (see Figure 2-2). When using the term Alloy 82/182, 82 refers to a weld made with a wire and 182 refers to a weld made with a rod. Per [3], cracks in Alloy 182 are found to grow more rapidly due to SCC than those in Alloy 82, but both are susceptible. The evaluations performed herein assume the material is Alloy 182 and use the higher growth rates associated with Alloy 182. An inside diameter (ID) repair weld composed of Alloy 82/182 material, modeled in [1], would result in a high tensile residual stress on the inside surface of the weld. This high tensile stress results in the weld being more susceptible to SCC crack initiation and more rapid growth due to SCC at the surface, and is therefore undesirable. Weld overlays (WOL) made of Alloy 52/152 (also referred to as Alloy 690) are frequently applied preemptively to compress the entire DM weld, including the ID repair [11]. As indicated in [3] and [10], Alloy 52/152 material is very resistant to PWSCC, and no industry guidance on calculating SCC growth in 52/152 welds has yet been developed because the growth is expected to be much slower. Additionally, PWSCC requires that the crack be exposed to the coolant on the inside surface. The Alloy 52/152 WOL is applied to the outside surface of the DM weld and pipe, and is not exposed to the coolant unless there is a through-thickness flaw in the DM weld, which is not expected without first having part-through wall indications. The analysis performed herein uses linear elastic fracture mechanics to calculate stress intensity factors based on handbook solutions [2]. These values for stress intensity factors (K I ), are then used as input to K-dependent growth calculations using guidance from [3].

12 2.0 Input and Methodology 2.1 Stress Intensity Factor (K) Solution This project will study the growth of semi-elliptical, circumferentially oriented flaws in the butt weld of a 2-inch pipe. The growth laws used herein (discussed in Section 2.3) require a stress intensity factor as an input. Stress intensity factors for semi-elliptical surface flaws can be found in API-579 [2]. Specifically, for evaluating stress corrosion cracking (SCC), flaws are postulated on the inside diameter (ID) of the component. This is because flaws on the ID will grow due to SCC, while flaws on the outside diameter and embedded flaws would not grow due to SCC because they would not be exposed to the coolant in the pipe. Section C.5.14 of [2] provides the solution for a Cylinder Surface Crack, Circumferential Direction Semi-Elliptical Shape, Through-Wall Fourth Order Polynomial Stress Distribution with a Net Section Bending Stress. This is applicable to the scenario evaluated herein. Equation 2-1: Mode I Stress Intensity Factor Solution In Equation 2-1: a = the flaw depth t = the wall thickness σ 0 through σ 4 are the coefficients of the fourth order polynomial of stress distribution through the wall thickness. σ 5 and σ 6 are the net section bending stresses about the x-axis and y-axis. For the depth point, only σ 5 is necessary for the calculation. Additionally, only one bending stress is used herein, so the σ 6 term is discarded. The influence coefficients G 0, G 1, G 5 and G 6 for inside and outside surface cracks can be determined using the following equations:

13 where the parameters A ij are provided in Table C.14 of [2] for an inside diameter crack and β = 2φ/π φ is the angle between the surface and the point being evaluated. In this case, φ = π/2 to obtain the stress intensity factor solution at the deepest point. G 2, G 3, and G 4 are calculated using the following equations for the deepest point (φ= π/2): where M 1 through M 3 are calculated as: and Q is calculated as:

14 The ratio a/c is always less than zero for the aspect ratios evaluated herein. p c = crack face pressure (2500 psi in this calculation) Figure 2-1: Component and Crack Geometry

15 2.2 Stress Input Stress input is available in [1] that contains the weld residual stresses. Two sets of stresses are available; one that is applicable after an inside diameter (ID) repair weld prior to application of a weld overlay, and one that is applicable after an ID repair weld with a weld overlay. The stresses are developed using a 2-D axisymmetric model of a 2-inch nozzle (see geometry summarized in Table 2-2). Figure 2-2 depicts the model. Figure 2-2: 2-D Axisymmetric Nozzle Model [1] Stresses are provided in [1] along the centerline of the ID repair weld. The stress path can be seen in Figure 2-3. The inside surface path is not used in this evaluation, since the stresses along this path are not useful in evaluating a circumferentially oriented flaw (a stress profile through the thickness is needed for this evaluation). Figure 2-3: Stress Paths at the DM Weld [1]

16 Figure 2-4 is used to justify use of results taken along the stress path through the center of the ID repair weld. It can be observed that there is not a significant difference in the stress profile across the repair weld width, and that the center of the ID repair weld is where the most severe tensile and residual stresses are experienced. While cracks may grow slightly away from the center of the weld (adjacent to the edge of the weld or in the heat affected zones) using stresses from the center of the weld is appropriate and conservative for evaluating flaws in this region based on this being the location of the most severe tensile stresses. Additionally, a flaw growing along the edge of the DM or ID repair weld may not be oriented perfectly circumferentially (perpendicular to the surface of the pipe), however the ASME code [4] indicates that flaws should be projected into the plane perpendicular to the stresses being evaluated. Here, the concern is a circumferential flaw being driven by axial stresses, thus flaws growing along the edge of the weld or in the heat affected zone can be projected into the circumferential plane, and considered bounded by the evaluation performed herein. This concept is shown in Figure 2-6. Figure 2-5 is provided for additional information. The entire cross section of the original pipe and DM weld is put into compression after a WOL; therefore the location of the stress cut is inconsequential for this condition. Figure 2-4: Axial Residual Stress Contour Plot (psi) at 650 F after ID Repair [1] Figure 2-5: Axial Residual Stress Contour Plot (psi) at 650 F after WOL Repair [1]

17 Figure 2-6: Illustration of Flaw Projection into Circumferential Plane Stress distributions along paths through the center of the ID repair weld are provided at 70 F and 650 F in [1]. This calculation will determine stress corrosion cracking during plant operation; therefore the stress distribution experienced during normal operation is most applicable for studying the growth of a flaw. Normal operating conditions correspond to 650 F and 2,250 psi [1]. These stress distributions can be seen in Figure 2-7 and Figure 2-8 as a function of % through the wall thickness. The flaws evaluated in this analysis are oriented circumferentially, which will be driven by the axial stress. It can be observed in Figure 2-7 that, for an ID Repair, the stress on the inside surface is tensile, and the stress on the outside surface is compressive. This is intuitive, because the repair weld is on the inside surface. As this repair weld cools it will experience tension, and will put the rest of the pipe wall in compression. Figure 2-7 provides stresses from 0% to 100% through the wall thickness. In Figure 2-8, for the WOL, the stress in the DM weld is compressive and the stress in the WOL is tensile. This is intuitive, because the WOL is on the outside surface of the pipe. As the WOL cools it will experience tension, and will put the entire pipe (and DM weld) cross section into compression. Compressive stress will serve to stunt crack growth. Figure 2-8 provides stresses from 0% to 216% of the original wall thickness (percentages above 100% would indicate locations within the weld overlay, which is not susceptible to cracking and not evaluated herein).

18 Figure 2-7: Axial and Hoop Residual Stresses through the Wall Thickness at 650 F after ID Repair Figure 2-8: Axial and Hoop Residual Stresses through the Wall Thickness at 650 F after WOL

19 The stresses that will drive a circumferentially oriented weld are the tensile axial stresses, because they act normal to the surface of the flaw and will cause crack opening. As explained in [1], the stresses already contain the axial stress due to the 2,250 psi internal pressure experienced by the pipe at normal operation. Steady-state thermal stresses due to the temperature gradient are also included, because only the ID of the pipe sees the 650 F normal operating temperature. In addition to the pressure, residual, and thermal stresses contained in the stress distributions from [1], representative stresses due to mechanical loads must be considered. For this analysis, the mechanical loads are summarized in Table 2-1. The loads provided are applicable to normal operating conditions. These stresses are arbitrary and based only on experience. Table 2-1: Mechanical Loading Axial (lb) Bend (in lb) Normal Operation 0 10,000 To determine the stresses, the geometry of the butt weld is needed. This geometry is summarized in Table 2-2. Table 2-2: Butt Weld Geometry Dimensions Butt Weld Inside Radius (R i ) in Outside Radius (R o ) in Thickness (t) in Area (A) In 2 Moment of Inertia (I) In 4 The axial stress is calculated using Equation 2-2. Where: F/A + M c/i Equation 2-2: Combined Mechanical Stress Equation F = axial force for a given loading condition A = cross sectional area M = moment for a given loading condition c = radius where the stress result is desired I = moment of ineria The mechanical stresses calculated for normal operating conditions are provided in Table 2-3. Table 2-3: Normal Operating Condition Mechanical Stresses Stress Units Axial 0 psi Bend (OD) psi Bend (ID) psi

20 The stress distributions from [1] used to make Figure 2-7 and Figure 2-8 are provided in Table 2-4, along with the mechanical stress distribution for normal operation. Table 2-4: Stress Distributions from [1] and Mechanical Stress Distributions (psi) % x coordinate (in) Radius (in) Residual Before WOL Residual After WOL Mechanical 0% % % % % % % % % % % % % % % % % % % % % % % % As indicated in Section 2.1; the input should be applied as a fourth order polynomial of the stress distribution from [1] and the net section bending should be provided individually. The polynomial representation of the axial stress distribution from Figure 2-4 (which includes the axial stress due to pressure, steady-state thermal, and residual stress due to the inside surface weld repair) is provided in Figure 2-9. The stress distribution after the WOL is provided in Figure It can be observed in Figure 2-10 that after the WOL is applied, the entire butt weld is put into compression. Compressive stress will stop the growth of a crack due to PWSCC. For the calculations contained herein, the benefit of the compressive stress was ignored to provide a worst case conservative scenario following the WOL. If the compressive stresses were used, no crack growth could be predicted using K-dependent growth equations.

21 Figure 2-9: Stress Distribution for Normal Operating Conditions (650 F) (Before WOL) Figure 2-10: Stress Distribution for Normal Operating Conditions (650 F) (After WOL)

22 2.3 Crack Growth Methodology and Growth Laws Crack growth in Alloy 82/182 welds is described in MRP-115 [3], which is a public document available through EPRI. The Alloy 82/182 growth rates from [3] also match those available for Alloy 82/182 in Section C-8511 of Section XI of the ASME Code [4]. Specifically, it provides the following equations: Equation 2-3: Alloy 182 Growth Rate at 617 F More generically: Equation 2-4: Generic Alloy 182 Growth Rate where: a dot = crack growth rate at temperature T in in/h Q g = thermal activation energy for crack growth (31.0 kcal/mole) R = universal gas constant (1.103x10-3 kcal/mole- R) T = absolute operating temperature at location of crack ( R) T ref = absolute reference temperature used to normalize data ( R) α = power-law constant (2.47x10-7 ) f alloy = 1.0 for Alloy 182 and 1/2.6 for Alloy 82 f orient = 1.0 K = crack tip stress intensity factor (ksi in) β = exponent = 1.6 Additionally, for the purpose of comparison, the growth rate for stainless steel available in Section C-8520 of [4] was also used to predict growth. This allows observation of the increased predicted crack growth in Alloy 82/182 welds versus typical stainless steel components. The crack growth is performed in 1 month intervals or 0.1 month intervals, depending on the set of calculations. 1 month intervals were adequate for the calculations using the stainless steel growth rate due to the long periods of growth, however the allowable operating period is significantly reduced when using the Alloy 82/182 growth rate, and a shorter interval was used to provide more data points over the shortened operating period. All crack calculations start with a flaw that is 10% through the wall of the component.

23 2.4 Limiting Flaw Depth Methodology The flaw depth can be limited by two things: 1. The stress intensity factor when compared to fracture toughness. 2. A limit load evaluation, which ensures that the remaining cross section of the component does not experience plastic collapse. Therefore, in this set of calculations, the stress intensity factor is compared to the material fracture toughness. The fracture toughness of Alloy 82/182 is not readily available, but based on literature [3] it is expected to be high compared to other materials. In order to come up with a conservative value for use in these calculations, a fracture toughness of 150 ksi in is obtained from [5]. This corresponds to stainless steel. For these calculations, a safety factor of 3 will be applied to this fracture toughness and a value of 50 ksi in will be used going forward. As can be observed in Figure 3-1 and Figure 3-2, the calculated stress intensity factor does not exceed the fracture toughness in these calculations. Allowable flaw depths are therefore established based on limit load per Article C-5000 of [4]. Limit load evaluations are meant to ensure there is not net section failure. For these evaluations, Table C from [4] is used, which applies to Level B, or upset, conditions. As can be observed in Figure 2-11, the maximum allowable depth is 75% of the total wall thickness. However as the ratio of the applied stress to the flow stress increases, and the flaw length increases, the allowable depth will reduce. In Table C of [4]: l f = flaw length Figure 2-11: Table C of [4] Stress Ratio = (Primary Membrane Stress + Primary Bending Stress)/Flow Stress Flow Stress = (σ u + σ y )/2 Since the Alloy 82/182 weld is between 105 Gr. 2 carbon steel nozzle and a 316 stainless steel safe end, the minimum flow stress of the three materials will be used. The material properties in Table 2-5 are applicable at a temperature of 650 F, and are interpolated from data available in [1].

24 Table 2-5: Yield Strength, Ultimate Strength, and Flow Stress at 650 F Alloy 82/ Gr. 2 Carbon Steel 316 Stainless σ y (psi) 46,975 26,675 29,775 σ u (psi) 125,750 90, ,500 σ f (psi) 86,363 58,338 69,638 The secondary stress is not included in the calculation of the stress ratio for limit load evaluations. This means that the stress ratio is based purely on the applied external loads, and will remain constant. The only primary stress to consider for the stress ratio is the bending stress of ksi, which is provided in Table 2-3. The ASME code [4] prescribes a safety factor of 2.3 to these loads, which increases the stress to ksi. This results in a stress ratio of ksi/ ksi, or The data from Table C of [4], interpolated for a stress ratio of 0.402, is used directly in the calculations and included in plots in Section 3.2.1, 3.2.2, and The most limiting allowable flaw depth, as determined by stress intensity factor or limit load calculation per Article C-5000 of [4], is used to establish the final allowable flaw depth for a given flaw and loading.

25 3.0 Results and Discussion 3.1 Calculation of Stress Intensity Factor K I For this calculation, all flaws are assumed to have a starting depth of 10% of the wall thickness. This means the initial flaw depth is in. The selection of 10% is arbitrary, but this is a common starting point for flaw evaluations, and a conservatively large estimate of the minimum detectable flaw during an inspection. The K-solution equations have an upper-bound of 80% of the wall thickness. Therefore, K I is provided in units of ksi in for a range of flaw depths from 10% to 80% of the wall thickness ( in to in) in Figure 3-1 and Figure 3-2. Figure 3-1 provides K I due to only mechanical loads. Figure 3-2 provides K I due to the combined mechanical, thermal, and residual stresses. It can be observed that, for both loading conditions, the stress intensity factor remains below the conservative value of 50 ksi in being used as the fracture toughness, and therefore brittle fracture is not a concern. The K-solution for the mechanical loads increases as the flaw grows (see Figure 3-1). This is intuitive because the solution orients the flaw on the side of the pipe loaded in tension due to the mechanical bending moment. The tensile stresses due to the bending moment serve to open up the flaw. As the crack grows, the stress remains positive and the flaw opens up more, increasing the value of K I. This can be understood by using the most rudimentary solution for K I of a flaw in an infinite plate (Equation 3-1), which is taken from [6]. If the stress value (σ) remains constant and the value for the flaw depth (a) increases, the value for K I will continue to increase. K I = σ (πa) Equation 3-1: K I Solution for a Flaw in an Infinite Plate The K-solution for the combined mechanical, thermal, and residual stresses increases as the flaw grows until a depth of around 0.18 inches (just over 50%) (see Figure 3-2). This is intuitive because the flaw starts in the tensile portion of the residual stress at a depth of 10% (see Figure 2-4 for the stress distribution). As the flaw grows, the stress becomes less tensile, which results in the downward turning K I curve. Once the flaw tip enters the compressive portion of the stress distribution, the K I solution starts to decrease. While the K I solution begins to decrease, it remains a positive value for the flaw sizes evaluated herein, because a majority of the stress distribution over the flaw depth remains tensile, even as portions of the flaw (near the crack tip) are penetrating the compressive region.

26 Figure 3-1: Stress Intensity Factor vs. Flaw Depth for Mechanical Loads Only Figure 3-2: Stress Intensity Factor vs. Flaw Depth for Combined Mechanical, Thermal, and Residual Loads

27 3.2 Calculation of Stress Corrosion Cracking Growth For this calculation, all flaws are assumed to have a starting depth of 10% of the wall thickness. This means the initial flaw depth is in. The selection of 10% is arbitrary, but this is a common starting point for flaw evaluations, and a conservatively large estimate of the minimum detectable flaw during an inspection. As mentioned in Section 3.1, K I does not exceed the fracture toughness, and brittle fracture is not expected. Therefore, the allowable depth is set by the ASME code as described in Section 2.4. As shown in Figure 2-11, the allowable end-of-evaluation period flaw depth-to-thickness ratios for circumferential flaws are provided as a function of the stress ratio and the ratio of the flaw length to pipe circumference. The stress ratio is based purely on the mechanical stresses and remains constant as the crack grows. However, as the flaw grows the flaw length to pipe circumference ratio increases, and the allowable flaw depth-to-thickness ratio decreases. To simplify the calculations, an acceptable flaw depth-to-thickness ratio is calculated for each step in the growth calculations, and the corresponding flaw depth is calculated. This can be seen in the individual plots provided for each aspect ratio as a dashed line. The final acceptable flaw depth is where the dashed line intersects the plot of the flaw growth. For aspect ratios of 2 and 4, this is always 75% of the wall thickness (0.258 inches). However for aspect ratios of 10, the allowable flaw depth was 66.3% of the wall thickness (0.228 inches). For all growth rates, the same trends can be observed, however they occur over different periods of time. For the case considering only mechanical loads, the growth has an upwardbending curve. This is because K I is always increasing with larger flaw depth, and the growth laws raise K I to a power greater than 1. For the combined mechanical, thermal, and residual stresses, the growth curves tend to accelerate early on (due to an increased K I for flaws in the tensile region of the residual stress profile), then level off as the flaw enters the compressive region of the residual stress field. This is intuitive, and serves as a sanity check of the results.

28 3.2.1 Stainless Steel Growth Rate Section provides the expected growth of flaws with aspect ratios of 2, 4, and 8 using the stainless steel growth rate from Section C-8520 of [4]. These results are provided simply for comparative purposes to show the accelerated growth in Alloy 82/182 material versus the growth expected in stainless steels. Figure 3-3: Stainless Steel Growth Calculations - Mechanical Only

29 Figure 3-4: Stainless Steel Growth Calculations (AR = 2) - Mechanical Only Figure 3-5: Stainless Steel Growth Calculations (AR = 4) - Mechanical Only

30 Figure 3-6: Stainless Steel Growth Calculations (AR = 8) - Mechanical Only Figure 3-7: Stainless Steel Growth Calculations - Mechanical + Thermal + Residual

31 Figure 3-8: Stainless Steel Growth Calculations (AR = 2) - Mechanical + Thermal + Residual Figure 3-9: Stainless Steel Growth Calculations (AR = 4) - Mechanical + Thermal + Residual

32 Figure 3-10: Stainless Steel Growth Calculations (AR = 8) - Mechanical + Thermal + Residual

33 3.2.2 Alloy 82/182 Growth Rate at 617 F Section provides the expected growth of flaws with aspect ratios of 2, 4, and 8 using the Alloy 82/182 growth rate from [3]. The growth rate calculation, summarized in Section 2.3, is evaluated at 617 F (as originally presented in MRP-115 [3]). While the residual stress reference [1] indicates that 650 F is the normal operating temperature, the actual fluid temperature experienced by the welds is typically much lower. The temperature presented in MRP-115 [3] is considered a best-estimate of the actual fluid temperature that may be seen by the weld during normal operation. Figure 3-11: Alloy 82/182 Growth Calculations at 617 F - Mechanical Only

34 Figure 3-12: Alloy 82/182 Growth Calculations (AR = 2) at 617 F - Mechanical Only Figure 3-13: Alloy 82/182 Growth Calculations (AR = 4) at 617 F - Mechanical Only

35 Figure 3-14: Alloy 82/182 Growth Calculations (AR = 8) at 617 F - Mechanical Only Figure 3-15: Alloy 82/182 Growth Calculations at 617 F - Mechanical + Thermal + Residual

36 Figure 3-16: Alloy 82/182 Growth Calculations (AR = 2) at 617 F - Mechanical + Thermal + Residual Figure 3-17: Alloy 82/182 Growth Calculations (AR = 4) at 617 F - Mechanical + Thermal + Residual

37 Figure 3-18: Alloy 82/182 Growth Calculations (AR = 8) at 617 F - Mechanical + Thermal + Residual

38 3.2.3 Alloy 82/182 Growth Rate at 650 F Section provides the expected growth of flaws with aspect ratios of 2, 4, and 8 using the Alloy 82/182 growth rate from [3]. The growth rate calculation, summarized in Section 2.3, is evaluated at 650 F, which is the normal operating temperature described in the weld residual stress calculation [1]. This is meant to be a conservative upper bound for growth during normal operation. In practice, if these results were unacceptable and shown to be overly conservative, the results of the evaluation in Section (for a more realistic temperature) could be used. Figure 3-19: Alloy 82/182 Growth Calculations at 617 F - Mechanical Only

39 Figure 3-20: Alloy 82/182 Growth Calculations (AR = 2) at 617 F - Mechanical Only Figure 3-21: Alloy 82/182 Growth Calculations (AR = 4) at 617 F - Mechanical Only

40 Figure 3-22: Alloy 82/182 Growth Calculations (AR = 8) at 617 F - Mechanical Only Figure 3-23: Alloy 82/182 Growth Calculations at 617 F - Mechanical + Thermal + Residual

41 Figure 3-24: Alloy 82/182 Growth Calculations (AR = 2) at 617 F - Mechanical + Thermal + Residual Figure 3-25: Alloy 82/182 Growth Calculations (AR = 4) at 617 F - Mechanical + Thermal + Residual

42 Figure 3-26: Alloy 82/182 Growth Calculations (AR = 8) at 617 F - Mechanical + Thermal + Residual

43 4.0 Summary and Conclusion Table 4-1 and Table 4-2 provide the time (in months) required for a 10% through-wall semielliptical flaw to grow to the allowable depth. Additionally, the same information is provided in years in Table 4-3 and Table 4-4. A general trend that can be observed is that the time needed for the flaw to grow to the maximum allowable depth decreases as the aspect ratio increases, and that the Alloy 82/182 material grows to the maximum allowable depth much more quickly than a crack would in stainless steel. Table 4-1: Time (in months) to Reach Allowable Flaw Depth after Application of a Weld Overlay Mechanical + Residual (After WOL) Time to Reach Allowable Depth (months) Growth Rate Aspect Ratio Stainless Steel Rate 2, , Alloy 82/182 Rate (617F) Alloy 82/182 Rate (650F) Table 4-2: Time (in months) to Reach Allowable Flaw Depth before Application of a Weld Overlay Mechanical + Residual (Before WOL) Time to Reach Allowable Depth (months) Growth Rate Aspect Ratio Stainless Steel Rate Alloy 82/182 Rate (617F) Alloy 82/182 Rate (650F) Table 4-3: Time (in years) to Reach Allowable Flaw Depth after Application of a Weld Overlay Mechanical + Residual (After WOL) Time to Reach Allowable Depth (years) Growth Rate Aspect Ratio Stainless Steel Rate Alloy 82/182 Rate (617F) Alloy 82/182 Rate (650F) Table 4-4: Time (in years) to Reach Allowable Flaw Depth before Application of a Weld Overlay Mechanical + Residual (Before WOL) Time to Reach Allowable Depth (years) Growth Rate Aspect Ratio Stainless Steel Rate Alloy 82/182 Rate (617F) Alloy 82/182 Rate (650F)

44 Alloy 82/182 versus Stainless Steel A comparison can be made between the time it takes a crack to grow to the maximum allowable depth in stainless steel versus Alloy 82/182. It can be observed in Table 4-1 and Table 4-2 that, for a given aspect ratio, the number of months it takes a 10% through-wall semi-elliptical flaw to grow to the maximum allowable depth in stainless steel is an order of magnitude larger than in Alloy 82/182. This serves to show, and confirm, that crack growth occurs much more rapidly in Alloy 82/182 welds than typical stainless steels used in PWR applications. This is true both before and after the application of a WOL. Using the stainless steel growth rate, the amount of time for a 10% through-thickness flaw to grow to the maximum allowable depth after a WOL is applied is longer than the typical year life [12] of a plant. Crack growth in Alloy 82/182 is on the scale of months, which is closer to the amount of time covered between outages, which occur every 18 to 24 months [13]. This helps to explain why crack growth in Alloy 82/182 is such a concern in the nuclear industry. Crack Growth Before and After WOL Application Even for the worst case scenario evaluated ignoring the beneficial residual stress introduced by a WOL, the time before reaching the maximum allowable flaw depth with the WOL is greater than ten times the amount of time it would take without the WOL. Additionally, it should be noted that the compressive residual stresses introduced by the WOL would serve to prevent SCC from initiating on the inside surface and halt (or significantly slow) the growth of any preexisting flaws. This clearly shows the benefit of applying a WOL. According to [13], outages at nuclear plants occur every 18 to 24 months. According to Table 4-2, the time that it would take a crack in Alloy 82/182 to reach the allowable crack depth ranges from 1.6 months to 9.2 months if a WOL were not applied. This means that if a flaw of 10% is not detected during a particular outage, it could grow to be larger than the allowable depth prior to the next outage. In other words, a crack that could grow from initiation to a size that violates code allowable depths in such a short time that it could not be detected using the typical outage/inspection schedule of a nuclear plant. This implies that failure could occur before a crack is detected. As mentioned in [11], WOL are applied preemptively in the nuclear industry. This means they may be applied even if there is no current indication of cracking due to PWSCC. The results in Table 2-1 help to show why preemptive WOL are used, and how they can help a plant ensure they will detect flaws before they can grow to unacceptable depths. According to Table 2-1, it would take a crack in Alloy 82/182 between 25.8 months to months even when the beneficial compressive residual stress due to WOL is ignored. This means that a 10% flaw may go undiscovered in a given outage, and will still not grow to unacceptable depths before the next outage. This ensures the plant will detect a flaw before pipe failure, and can repair any indications that are found. Considering the actual stress distribution after WOL (shown in Figure 2-10), cracks should not initiate due to PWSCC after a WOL due to the highly compressive stress on the inside surface. Furthermore, pre-existing cracks should not grow when in a compressive stress field. These observations, along with the results in Table 4-1 and Table 4-2, show the benefits of applying a preemptive WOL after performing an ID repair weld.

45 5.0 References 1. Wu, Ya T, Residual Stress Study at the Dissimilar Metal Butt Weld due to the Weld Overlay Repair on 2 inch Nozzle Using ANSYS, Rensselear Polytechnic institute, Hartford, CT, April API 579-1/ASME FFS-1, Fitness-for-Service, Annex C, Compendium of Stress Intensity Factor Solutions, June 5, Materials Reliability Program Crack Growth Rates for Evaluating Primary Water Stress Corrosion Cracking (PWSCC) of Alloy 82, 182, and 132 Welds (MRP-115), EPRI, Palo Alto, CA: ASME Boiler & Pressure Vessel Code, Section XI, BWR-VIP-76NP, Revision 1: BWR Vessel and Internals Project, BWR Core Shroud Inspection and Flaw Evaluation Guidelines. EPRI, Palo Alto, CA: NP. 6. Tada, Hiroshi, Paul C. Paris, and George R. Irwin, The Stress Analysis of Cracks Handbook, Third Edition, The American Society of Mechanical Engineers, New York, NY, Cottis, R. A., Stress Corrosion Cracking, National Physical Laboratory, Guides to Good Practice in Corrosion Control, Wollman, M., Stress Corrosion Cracking (SCC), Clausthal University of Technology, May Materials Reliability Program (MRP) Crack Growth Rates for Evaluating Primary Water Stress Corrosion Cracking (PWSCC) of Thick-Wall Alloy 600 Materials (MRP-55) Revision 1. EPRI. Palo Alto, CA: Materials Reliability Program (MRP), Resistance to Primary Water Stress Corrosion Cracking of Alloys 690, 52, and 152 in Pressurized Water Reactors (MRP-111. EPRI, Palo Alto, CA: Materials Reliability Program (MRP), Technical Basis for Preemptive Weld Overlays for Alloy 82/182 Butt Welds in Pressurized Water Reactors (PWRs) (MRP-169) Revision 1-A. EPRI, Palo Alto, CA: Extending the Operational Life Span of Nuclear Plants, Division of Public Information, International Atomic Energy Agency, February 18, Accessed June 20, < What is an Outage?, Clean Energy Insight: Moving Energy Forward, May, 10, Accessed June 20, <

PVP PVP EFFECTS OF WELD OVERLAYS ON LEAK-BEFORE BREAK MARGINS

PVP PVP EFFECTS OF WELD OVERLAYS ON LEAK-BEFORE BREAK MARGINS Proceedings of the ASME 2011 Pressure Vessels & Piping Division Conference PVP2011 July 17-21, 2011, Baltimore, Maryland, USA Proceedings of PVP2011 2011 ASME Pressure Vessels and Piping Division Conference

More information

PRESSURE-TEMPERATURE LIMIT CURVES

PRESSURE-TEMPERATURE LIMIT CURVES Training School, 3-7 September 2018 Polytechnic University of Valencia (Spain) PRESSURE-TEMPERATURE LIMIT CURVES Carlos Cueto-Felgueroso This project received funding under the Euratom research and training

More information

18 Excavate & Weld Repair (EWR) for SCC Mitigation

18 Excavate & Weld Repair (EWR) for SCC Mitigation 18 Excavate & Weld Repair (EWR) for SCC Mitigation Annual NRC/Industry Technical Exchange Meeting NRC Three White Flint North, Rockville MD Wednesday June 3, 2015 Steve McCracken & Jon Tatman EPRI Welding

More information

TECHNICAL JUSTIFICATION FOR ASME CODE SECTION XI CRACK DETECTION BY VISUAL EXAMINATION

TECHNICAL JUSTIFICATION FOR ASME CODE SECTION XI CRACK DETECTION BY VISUAL EXAMINATION FR0108123 TECHNICAL JUSTIFICATION FOR ASME CODE SECTION XI CRACK DETECTION BY VISUAL EXAMINATION R. E. NICKELL Applied Science and Technology, 16630 Sagewood Lane, Poway, CA 92064, U. S. A. E-mail: mickell(

More information

Ductile Tearing Instability Assessment of a Cracked Reactor Pressure Vessel Nozzle for Larger Critical Crack Size Compared to the FAD Method

Ductile Tearing Instability Assessment of a Cracked Reactor Pressure Vessel Nozzle for Larger Critical Crack Size Compared to the FAD Method Ductile Tearing Instability Assessment of a Cracked Reactor Pressure Vessel Nozzle for Larger Critical Crack Size Compared to the FAD Method G. Thorwald and J. Wright Quest Integrity Group, 1965 57 th

More information

BACKGROUND TO PROCEDURES IN SECTION XI OF THE ASME CODE FOR EVALUATION OF FLAWS IN NUCLEAR PIPING

BACKGROUND TO PROCEDURES IN SECTION XI OF THE ASME CODE FOR EVALUATION OF FLAWS IN NUCLEAR PIPING BACKGROUND TO PROCEDURES IN SECTION XI OF THE ASME CODE FOR EVALUATION OF FLAWS IN NUCLEAR PIPING Douglas A. Scarth Kinectrics, Inc. Toronto, Ontario, Canada Keywords: ASME, Section XI, nuclear, pipe,

More information

PROPOSED ASME SECTION III CODE CASE REDUCTION OF NDE WELD REPAIRS

PROPOSED ASME SECTION III CODE CASE REDUCTION OF NDE WELD REPAIRS Proceedings of the ASME 2011 Pressure Vessels & Piping Division Conference PVP2011 July 17-21, 2011, Baltimore, Maryland, USA PVP2011-57675 PVP2011- PROPOSED ASME SECTION III CODE CASE REDUCTION OF NDE

More information

Evaluation of Pipe Weld NDE Indications

Evaluation of Pipe Weld NDE Indications Evaluation of Pipe Weld NDE Indications Brasse, Markus Westinghouse Electric Germany Dudenstrasse 44, D-68167 Mannheim, Germany Markus.Brasse@de.westinghouse.com ABSTRACT This paper discusses the evaluation

More information

XRD RESIDUAL STRESS MEASUREMENTS ON ALLOY 600 PRESSURIZER HEATER SLEEVE MOCKUPS

XRD RESIDUAL STRESS MEASUREMENTS ON ALLOY 600 PRESSURIZER HEATER SLEEVE MOCKUPS XRD RESIDUAL STRESS MEASUREMENTS ON ALLOY 6 PRESSURIZER HEATER SLEEVE MOCKUPS J. F. Hall, J. P. Molkenthin - ABB-Combustion Engineering Nuclear Power Paul S. Prevéy Lambda Research ABSTRACT Alloy 6 penetrations

More information

NDT WITH THE STRUCTURAL WELD OVERLAY PROGRAM: RECENT FIELD EXPERIENCE AND LESSONS LEARNED

NDT WITH THE STRUCTURAL WELD OVERLAY PROGRAM: RECENT FIELD EXPERIENCE AND LESSONS LEARNED NDT WITH THE STRUCTURAL WELD OVERLAY PROGRAM: RECENT FIELD EXPERIENCE AND LESSONS LEARNED Rick Rishel WesDyne International LLC I-70 Madison Exit Gate D P.O. Box 409 Madison, PA 15663 USA rishelrd@westinghouse.com

More information

Structural design criteria

Structural design criteria chapter three Structural design criteria Contents 3.1 Modes of failure... 3.2 Theories of failure... 3.3 Theories of failure used in ASME Boiler and Pressure Vessel Code... 3.4 Allowable stress limits

More information

4.4 Single Load Path Structure

4.4 Single Load Path Structure 4.4 Single Load Path Structure For a single load path structure, the only means to protect the safety is to prevent the damage growth from degrading the strength of the structure to less than the design

More information

Overview of NRC-EPRI PWSCC Initiation Testing - Status Update

Overview of NRC-EPRI PWSCC Initiation Testing - Status Update Overview of NRC-EPRI PWSCC Initiation Testing - Status Update Materials Reliability Program Industry-NRC Materials R&D Meeting June 2-4, 2015 Rockville, MD Presentation Outline Background on PWSCC Initiation

More information

Advances In ILI Allow Assessing Unpiggable Pipelines. By Lisa Barkdull and Ian Smith, Quest Integrity Group, Houston

Advances In ILI Allow Assessing Unpiggable Pipelines. By Lisa Barkdull and Ian Smith, Quest Integrity Group, Houston As seen in Pipeline & Gas Journal, August 2011 edition Advances In ILI Allow Assessing Unpiggable Pipelines By Lisa Barkdull and Ian Smith, Quest Integrity Group, Houston Advances in in-line inspection

More information

Thomas D. Gatlin. February 24, 2014 RC Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC

Thomas D. Gatlin. February 24, 2014 RC Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC Thomas D. Gatlin Vice President, Nuclear Operations 803.345.4342 A SCANA COMPANY February 24, 2014 Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555 Dear Sir / Madam: Subject:

More information

by NISHIKAWA Hiroyuki, KATSUYAMA Jinya and ONIZAWA Kunio

by NISHIKAWA Hiroyuki, KATSUYAMA Jinya and ONIZAWA Kunio [ 27 p. 245s-250s (2009)] by NISHIKAWA Hiroyuki, KATSUYAMA Jinya and ONIZAWA Kunio Numerical simulations by thermal-elastic-plastic-creep analysis using finite element method (FEM) have been performed

More information

Pressurized Water Reactor Materials Reliability Program (QA)

Pressurized Water Reactor Materials Reliability Program (QA) Pressurized Water Reactor Materials Reliability Program (QA) Program Description Program Overview Stress corrosion cracking and general environmental corrosion of reactor coolant system components have

More information

PVP ALTERNATIVE ACCEPTANCE CRITERIA FOR FLAWS IN FERRITIC STEEL COMPONENTS OPERATING IN THE UPPER SHELF TEMPERATURE RANGE

PVP ALTERNATIVE ACCEPTANCE CRITERIA FOR FLAWS IN FERRITIC STEEL COMPONENTS OPERATING IN THE UPPER SHELF TEMPERATURE RANGE Proceedings of the ASME 2012 Pressure Vessels & Piping Conference PVP2012 July 15-19, 2012, Toronto, Ontario, CANADA PVP2012-78190 ALTERNATIVE ACCEPTANCE CRITERIA FOR FLAWS IN FERRITIC STEEL COMPONENTS

More information

Material Orientation Toughness Assessment (MOTA) for the Purpose of Mitigating Branch Technical Position (BTP) 5-3 Uncertainties

Material Orientation Toughness Assessment (MOTA) for the Purpose of Mitigating Branch Technical Position (BTP) 5-3 Uncertainties Westinghouse Non-Proprietary Class 3 2015 Westinghouse Electric Company LLC All Rights Reserved Global Expertise One Voice Material Orientation Toughness Assessment (MOTA) for the Purpose of Mitigating

More information

Fracture. Brittle vs. Ductile Fracture Ductile materials more plastic deformation and energy absorption (toughness) before fracture.

Fracture. Brittle vs. Ductile Fracture Ductile materials more plastic deformation and energy absorption (toughness) before fracture. 1- Fracture Fracture: Separation of a body into pieces due to stress, at temperatures below the melting point. Steps in fracture: 1-Crack formation 2-Crack propagation There are two modes of fracture depending

More information

ALLOY 600 REACTOR VESSEL HEAD PENETRATION ISSUES. Dudenstrasse 44, Mannheim, Germany. Post Office Box 355 Pittsburgh, PA ABSTRACT

ALLOY 600 REACTOR VESSEL HEAD PENETRATION ISSUES. Dudenstrasse 44, Mannheim, Germany. Post Office Box 355 Pittsburgh, PA ABSTRACT ALLOY 600 REACTOR VESSEL HEAD PENETRATION ISSUES Herbert Lenz 1, Edward Siegel 2 and Donald Seeger 2 1 Westinghouse Reaktor GmbH, Dudenstrasse 44, 68167 Mannheim, Germany 2 Westinghouse Electric Company

More information

3.3 Proof Test Determinations

3.3 Proof Test Determinations 3.3 Proof Test Determinations Tiffany and Masters [1965] first suggested that the conventional structural proof test could be used to inspect for crack mage that would eventually lead to catastrophic failure.

More information

Analysis of the Effects of Surface Preparation on Fracture Crack Propagation

Analysis of the Effects of Surface Preparation on Fracture Crack Propagation Analysis of the Effects of Surface Preparation on Fracture Crack Propagation by Timothy George Andrews A Project Submitted to the Graduate Faculty of Rensselaer Polytechnic Institute in Partial Fulfillment

More information

Tensile/Tension Test Advanced Topics

Tensile/Tension Test Advanced Topics CIVE.3110 Engineering Materials Laboratory Fall 2017 Tensile/Tension Test Advanced Topics Tzuyang Yu Associate Professor, Ph.D. Structural Engineering Research Group (SERG) Department of Civil and Environmental

More information

INVESTIGATIVE STUDY OF 2-D VS. 3-D WELD RESIDUAL STRESS ANALYSES OF THE NRC PHASE II MOCKUP

INVESTIGATIVE STUDY OF 2-D VS. 3-D WELD RESIDUAL STRESS ANALYSES OF THE NRC PHASE II MOCKUP Proceedings of the ASME 212 Pressure Vessels & Piping Conference PVP212 July 15-19, 212, Toronto, Ontario, CANADA PVP212-7876 INVESTIGATIVE STUDY OF 2-D VS. 3-D WELD RESIDUAL STRESS ANALYSES OF THE NRC

More information

COMPARISON BETWEEN DUCTILE TEARING ANALYSIS AND LINEAR ELASTIC FRACTURE MECHANICS ANALYSIS

COMPARISON BETWEEN DUCTILE TEARING ANALYSIS AND LINEAR ELASTIC FRACTURE MECHANICS ANALYSIS COMPARISON BETWEEN DUCTILE TEARING ANALYSIS AND LINEAR ELASTIC FRACTURE MECHANICS ANALYSIS Mr. Quinton Rowson Consultant Structural Integrity, Quest Integrity NZL Ltd., New Zealand Mr. Michael Rock Engineering

More information

1-6.4 THE CRACK TIP: THE INGLIS EQUATION

1-6.4 THE CRACK TIP: THE INGLIS EQUATION 1-6.4 THE CRACK TIP: THE INGLIS EQUATION In our discussions of fracture so far we have assumed that the crack looks much like that shown in Figure 1.26a. The crack separates planes of atoms, is atomically

More information

Abstract. 1. Introduction. 2. Literature Review

Abstract. 1. Introduction. 2. Literature Review Experimental And Numerical Analysis Of Critical Stress Intensity Factor Of Pressure Vessel Material Used In Disc Shaped Compact Specimen B. C. Patel 1, Bharat Gupta 2 and Abhishek Choubey 2 1 M.Tech Student,

More information

THE EFFECTS OF FLAW SIZE AND IN-SERVICE INSPECTION ON CASS PIPING RELIABILITY

THE EFFECTS OF FLAW SIZE AND IN-SERVICE INSPECTION ON CASS PIPING RELIABILITY THE EFFECTS OF FLAW SIZE AND IN-SERVICE INSPECTION ON CASS PIPING RELIABILITY T. J. Griesbach, D. O. Harris, H. Qian, D. Dedhia, J. Hayden, Structural Integrity Associates, Inc. A. Chockie, Chockie Group

More information

Welding simulations: assessment of welding residual stresses and post weld heat treatment

Welding simulations: assessment of welding residual stresses and post weld heat treatment Welding simulations: assessment of welding residual stresses and post weld heat treatment Etienne Bonnaud and Jens Gunnars, Inspecta Technology AB Third Nordic Conference on Design and Fabrication of Welded

More information

4.3 Residual Strength Capability

4.3 Residual Strength Capability 4.3 Residual Strength Capability To establish the residual strength capability of a given structure under certain loading conditions, prediction techniques must be developed with a thorough understanding

More information

HYBRID COMPOSITE REPAIR for OFFSHORE RISERS

HYBRID COMPOSITE REPAIR for OFFSHORE RISERS HYBRID COMPOSITE REPAIR for OFFSHORE RISERS O. O. Ochoa and C. Alexander Mechanical Engineering Texas A&M University College Station, TX 77840 oochoa@tamu.edu SUMMARY An innovative design based on integrated

More information

9.7 Residual Strength Parametric Analysis

9.7 Residual Strength Parametric Analysis 9.7 Residual Strength Parametric Analysis This section illustrates parametric analyses available to an engineer for evaluating the sensitivity of residual strength to geometric and material parameters.

More information

CH 6: Fatigue Failure Resulting from Variable Loading

CH 6: Fatigue Failure Resulting from Variable Loading CH 6: Fatigue Failure Resulting from Variable Loading Some machine elements are subjected to statics loads and for such elements, statics failure theories are used to predict failure (yielding or fracture).

More information

REVISED PAGES IMPORTANT TERMS AND CONCEPTS REFERENCES QUESTIONS AND PROBLEMS. 166 Chapter 6 / Mechanical Properties of Metals

REVISED PAGES IMPORTANT TERMS AND CONCEPTS REFERENCES QUESTIONS AND PROBLEMS. 166 Chapter 6 / Mechanical Properties of Metals 1496T_c06_131-173 11/16/05 17:06 Page 166 166 Chapter 6 / Mechanical Properties of Metals IMPORTANT TERMS AND CONCEPTS Anelasticity Design stress Ductility Elastic deformation Elastic recovery Engineering

More information

TENSILE RESIDUAL STRESS FIELDS PRODUCED IN AUSTENITIC ALLOY WELDMENTS

TENSILE RESIDUAL STRESS FIELDS PRODUCED IN AUSTENITIC ALLOY WELDMENTS TENSILE RESIDUAL STRESS FIELDS PRODUCED IN AUSTENITIC ALLOY WELDMENTS Douglas J. Hornbach and Paul S. Prevéy Lambda Research ABSTRACT Residual stresses developed by prior machining and welding may either

More information

PRESTRESSED CONCRETE STRUCTURES. Amlan K. Sengupta, PhD PE Department of Civil Engineering Indian Institute of Technology Madras

PRESTRESSED CONCRETE STRUCTURES. Amlan K. Sengupta, PhD PE Department of Civil Engineering Indian Institute of Technology Madras PRESTRESSED CONCRETE STRUCTURES Amlan K. Sengupta, PhD PE Department of Civil Engineering Indian Institute of Technology Madras Module 5: Analysis and Design for Shear and Torsion Lecture-23: Analysis

More information

COMPARISON OF LIMIT LOAD, LINEAR AND NONLINEAR FE ANALYSES OF STRESSES IN A LARGE NOZZLE-TO-SHELL DIAMETER RATIO APPLICATION

COMPARISON OF LIMIT LOAD, LINEAR AND NONLINEAR FE ANALYSES OF STRESSES IN A LARGE NOZZLE-TO-SHELL DIAMETER RATIO APPLICATION COMPARISON OF LIMIT LOAD, LINEAR AND NONLINEAR FE ANALYSES OF STRESSES IN A LARGE NOZZLE-TO-SHELL DIAMETER RATIO APPLICATION Michael A. Porter Dynamic Analysis 2815 Stratford Road Lawrence, Kansas 6649

More information

A Review of Suitability for PWHT Exemption Requirements in the Aspect of Residual Stresses and Microstructures

A Review of Suitability for PWHT Exemption Requirements in the Aspect of Residual Stresses and Microstructures Transactions, SMiRT-23 Division IX, Paper ID 612 (inc. assigned division number from I to X) A Review of Suitability for PWHT Exemption Requirements in the Aspect of Residual Stresses and Microstructures

More information

GLOBAL RATCHETING BY ELASTIC-PLASTIC FEA ACCORDING TO ASME SECTION VIII RULES

GLOBAL RATCHETING BY ELASTIC-PLASTIC FEA ACCORDING TO ASME SECTION VIII RULES Proceedings of the ASME 2011 Pressure Vessels & Piping Division Conference Proceedings of PVP2011 2011 ASME Pressure July Vessels 17-21, and 2011, Piping Baltimore, Division Maryland, Conference USA July

More information

Subject Index. STP 1207-EB/Dec. 1994

Subject Index. STP 1207-EB/Dec. 1994 STP 1207-EB/Dec. 1994 Subject Index A Aircraft transparency, crack propagation prediction, 766 AlzO3 ceramics, impact testing, 793 Aluminum alloys stable growing crack, 48 tungsten inert gas welded, 339

More information

Reactor Internals Overview

Reactor Internals Overview 1 Reactor Internals Overview Mechanisms: Cracking due to Irradiation Assisted Stress Corrosion (IASCC) and Stress Corrosion (SCC) Reduction of Fracture Toughness due to Irradiation Embrittlement (IE) and

More information

STRESS ANALYSIS OF A 46-INCH REACTOR FEED/EFFLUENT EXCHANGER

STRESS ANALYSIS OF A 46-INCH REACTOR FEED/EFFLUENT EXCHANGER STRESS ANALYSIS OF A 46-INCH REACTOR FEED/EFFLUENT EXCHANGER Chris Alexander Stress Engineering Services, Inc. Houston, Texas John Jagodzinski Brown Fintube Houston, Texas Richard Biel, P.E. Stress Engineering

More information

Regulatory Perspective on CANDU Feeder Pipe Degradation due to FAC and IGSCC

Regulatory Perspective on CANDU Feeder Pipe Degradation due to FAC and IGSCC Regulatory Perspective on CANDU Feeder Pipe Degradation due to FAC and IGSCC John C. Jin, Specialist Raoul Awad, Director, Canadian Nuclear Safety Commission Commission canadienne de surete nucleaire IAEA

More information

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS - June 2013 Addendum GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS SUBSECTION "A" : GENERAL RULES SUBSECTION "B" : CLASS 1 COMPONENTS SUBSECTION "C" : CLASS 2 COMPONENTS SUBSECTION "D" : CLASS

More information

LOS ALAMOS NATIONAL LABORATORY

LOS ALAMOS NATIONAL LABORATORY TOMSK-7 RADIOCHEMICAL FACILITY EXPLOSION: CHEMICAL VESSEL BURST FAILURE ANALYSIS Work Performed for the US Department of Energy by Los Alamos National Laboratory Los Alamos, NM 87545 by E. A. Rodriguez

More information

Assume that the growth of fatigue cracks in the plate is governed by a Paris type of law, i.e. da

Assume that the growth of fatigue cracks in the plate is governed by a Paris type of law, i.e. da 3. Mechanical Properties of Materials Exam #3 May 16, 00 This examination contains 9 single-sided pages. Please give your answers only in this examination booklet. Do not use any other sheets of paper.

More information

Modelling thickness limits transition joints between pipes of different thickness

Modelling thickness limits transition joints between pipes of different thickness Institute of Materials Engineering TITLE: Modelling thickness limits transition joints between pipes of different thickness AUTHOR: Michael Law DATE OF REPORT: November 2008 APPROVED BY: W Payten ISSUED

More information

Finite Element Simulation of Residual Stresses in Butt Welding of Two AISI 304 Stainless Steel Plates

Finite Element Simulation of Residual Stresses in Butt Welding of Two AISI 304 Stainless Steel Plates Finite Element Simulation of Residual Stresses in Butt Welding of Two AISI 304 Stainless Steel Plates Gurinder Singh Brar Department of Mechanical Engineering, Guru Nanak Dev Engineering College, Gill

More information

GA A22436 CREEP-FATIGUE DAMAGE IN OFHC COOLANT TUBES FOR PLASMA FACING COMPONENTS

GA A22436 CREEP-FATIGUE DAMAGE IN OFHC COOLANT TUBES FOR PLASMA FACING COMPONENTS GA A22436 CREEP-FATIGUE DAMAGE IN OFHC COOLANT TUBES FOR PLASMA FACING COMPONENTS by E.E. REIS and R.H. RYDER OCTOBER 1996 GA A22436 CREEP-FATIGUE DAMAGE IN OFHC COOLANT TUBES FOR PLASMA FACING COMPONENTS

More information

Steam Turbine Critical Crack Evaluation and Ranking Cracks to Prioritize Inspection

Steam Turbine Critical Crack Evaluation and Ranking Cracks to Prioritize Inspection Steam Turbine Critical Crack Evaluation and Ranking Cracks to Prioritize Inspection G. Thorwald, V. Garcia, R. Bentley, and O. Kwon Quest Integrity Abstract: The objective of this paper is to evaluate

More information

FINITE ELEMENT ANALYSIS OF COMPOSITE REPAIRS WITH FULL-SCALE VALIDATION TESTING

FINITE ELEMENT ANALYSIS OF COMPOSITE REPAIRS WITH FULL-SCALE VALIDATION TESTING Proceedings of the 2016 11th International Pipeline Conference IPC2016 September 26-30, 2016, Calgary, Alberta, Canada IPC2016-64214 FINITE ELEMENT ANALYSIS OF COMPOSITE REPAIRS WITH FULL-SCALE VALIDATION

More information

Maintenance Technologies for SCC which Support Stable Operations of Pressurized Water Reactor Power Plants

Maintenance Technologies for SCC which Support Stable Operations of Pressurized Water Reactor Power Plants Maintenance Technologies for which Support Stable Operations of Pressurized Water Reactor Power Plants KOJI OKIMURA* 1 MASAYUKI MUKAI* 1 KAZUHIKO KAMO* 2 NOBUYUKI HORI* 1 KOICHIRO MASUMOTO* 1 MASAAKI KUROKAWA*

More information

Phenomenon of (irradiation assisted) stress corrosion cracking for internals of PWR & BWR systems

Phenomenon of (irradiation assisted) stress corrosion cracking for internals of PWR & BWR systems Phenomenon of (irradiation assisted) stress corrosion cracking for internals of PWR & BWR systems Rdk Radek Novotny & Luigi Lii Db Debarberisb Institute for Energy (IE) Petten, The Netherlands http://www.jrc.ec.europa.eu

More information

Welding & Repair Technology Center

Welding & Repair Technology Center Welding & Repair Technology Center Program Description Program Overview High-quality, reliable welds, repair methodologies, and mitigation processes are critical to safe nuclear plant operation. The safety

More information

Stress Analysis of Fixed Site Series 6000 Antennas

Stress Analysis of Fixed Site Series 6000 Antennas Stress Analysis of Fixed Site Series 6000 Antennas 1.0 Introduction A Technical Application Note from Doppler Systems April 12, 2002 This stress analysis considers five different antenna configurations,

More information

Page 1 of 46 Exam 1. Exam 1 Past Exam Problems without Solutions NAME: Given Formulae: Law of Cosines: C. Law of Sines:

Page 1 of 46 Exam 1. Exam 1 Past Exam Problems without Solutions NAME: Given Formulae: Law of Cosines: C. Law of Sines: NAME: EXAM 1 PAST PROBLEMS WITHOUT SOLUTIONS 100 points Tuesday, September 26, 2017, 7pm to 9:30 You are allowed to use a calculator and drawing equipment, only. Formulae provided 2.5 hour time limit This

More information

Fatigue Crack Paths in Shafts Subjected to Bending and Torsion

Fatigue Crack Paths in Shafts Subjected to Bending and Torsion Fatigue Crack Paths in Shafts Subjected to Bending and Torsion T. Lassen 1 and A. Spagnoli 2 1 University of Stavanger, Norway tom.lassen@uis.no 2 University of Parma, Italy spagnoli@unipr.it ABSTRACT.

More information

THE USE OF FIELD INDENTATION MICROPROBE IN MEASURING MECHANICAL PROPERTIES OF WELDS

THE USE OF FIELD INDENTATION MICROPROBE IN MEASURING MECHANICAL PROPERTIES OF WELDS Recent Trends in Welding Science and Technology - TWR 89 Proceedings of the 2 nd International Conference on Trends in Welding Research Gatlinburg, Tennessee USA 14-18 May 1989 THE USE OF FIELD INDENTATION

More information

Stress Evaluation of a Typical Vessel Nozzle Using PVRC 3D Stress Criteria: Guidelines for Application

Stress Evaluation of a Typical Vessel Nozzle Using PVRC 3D Stress Criteria: Guidelines for Application Stress Evaluation of a Typical Vessel Nozzle Using PVRC 3D Stress Criteria: Guidelines for Application Michael A. Porter Dynamic Analysis Leawood, Kansas 66206 Dennis H. Martens Black & Veatch Pritchard

More information

Chapter 14 Fracture Mechanics

Chapter 14 Fracture Mechanics Chapter 14 Fracture Mechanics Stress Concentrations - discontinuities typically exist in structures (holes, cross-section changes, keyways, etc) - discontinuities locally increase stress (stress raisers)

More information

Bulging Assessment and Long- Term Repair of Coke Drums

Bulging Assessment and Long- Term Repair of Coke Drums Bulging Assessment and Long- Term Repair of Coke Drums Mahmod Samman, Ph.D., P.E. Houston Engineering Solutions (832) 512-0109 mms@hes.us.com Ediberto B. Tinoco Fábio C. Marangone Petrobras, Brazil RIO

More information

INTRODUCTION TO THE USE OF LINEAR ELASTIC FRACTURE MECHANICS IN ESTIMATING FATIGUE CRACK GROWTH RATES AND RESIDUAL STRENGTH OF COMPONENTS

INTRODUCTION TO THE USE OF LINEAR ELASTIC FRACTURE MECHANICS IN ESTIMATING FATIGUE CRACK GROWTH RATES AND RESIDUAL STRENGTH OF COMPONENTS INTRODUCTION TO THE USE OF LINEAR ELASTIC FRACTURE MECHANICS IN ESTIMATING FATIGUE CRACK GROWTH RATES AND RESIDUAL STRENGTH OF COMPONENTS 1. INTRODUCTION This Item introduces the concepts of linear elastic

More information

Monitoring of Lack of Bond in a Cladded (Alloy 825) Carbon Steel Vessel by Ultrasonic Phased Array Longitudinal Waves.

Monitoring of Lack of Bond in a Cladded (Alloy 825) Carbon Steel Vessel by Ultrasonic Phased Array Longitudinal Waves. More Info at Open Access Database www.ndt.net/?id=15153 Monitoring of Lack of Bond in a Cladded (Alloy 825) Carbon Steel Vessel by Ultrasonic Phased Array Longitudinal Waves. Santanu Saha 1, Amaresh Majumder,2

More information

REINFORCING FIELD FABRICATED BRANCH CONNECTIONS USING COMPOSITE MATERIALS

REINFORCING FIELD FABRICATED BRANCH CONNECTIONS USING COMPOSITE MATERIALS Proceedings of IPC2006 6th International Pipeline Conference September 25-29, 2006, Calgary, Alberta, Canada IPC2006-10483 REINFORCING FIELD FABRICATED BRANCH CONNECTIONS USING COMPOSITE MATERIALS Chris

More information

Structural Integrity Evaluation of Cast Austenitic Stainless Steel Reactor Coolant Piping for Continued Operation of Nuclear Power Plants GNEC

Structural Integrity Evaluation of Cast Austenitic Stainless Steel Reactor Coolant Piping for Continued Operation of Nuclear Power Plants GNEC PLiM Symposium in Shanghai Structural Integrity Evaluation of Cast Austenitic Stainless Steel Reactor Coolant Piping for Continued Operation of Nuclear Power Plants 2007 년 10 월 18 일 YOUNG JONG KIM GNEC

More information

Convection Section Failure Analysis and Fitness-for-Service Assessment*

Convection Section Failure Analysis and Fitness-for-Service Assessment* Convection Section Failure Analysis and Fitness-for-Service Assessment* We had a failure of convection tubes in our furnace. Can we restart and continue to operate until our next planned shutdown? A brittle

More information

4.2 Failure Criteria 4.2.1

4.2 Failure Criteria 4.2.1 4.2 Failure Criteria The determination of residual strength for uncracked structures is straightforward because the ultimate strength of the material is the residual strength. A crack in a structure causes

More information

Fitness-for-Service Evaluation of a Pipe with an Incomplete Penetration Flaw

Fitness-for-Service Evaluation of a Pipe with an Incomplete Penetration Flaw Materials Transactions, Vol. 51, No. 2 (2010) pp. 389 to 393 #2010 The Japan Institute of Metals Fitness-for-Service Evaluation of a Pipe with an Incomplete Penetration Flaw Soo-Keun Park 1 and Tae-Woon

More information

Proceedings of the ASME nd International Conference on Ocean, Offshore and Arctic Engineering OMAE2013 June 9-14, 2013, Nantes, France

Proceedings of the ASME nd International Conference on Ocean, Offshore and Arctic Engineering OMAE2013 June 9-14, 2013, Nantes, France Proceedings of the ASME 2013 32nd International Conference on Ocean, Offshore and Arctic Engineering OMAE2013 June 9-14, 2013, Nantes, France OMAE2013-10684 A COMPARISON STUDY OF PRESSURE VESSEL DESIGN

More information

Irradiated Material Welding Solutions: Potential Applications of Welding to Repair Irradiated Reactor Internals

Irradiated Material Welding Solutions: Potential Applications of Welding to Repair Irradiated Reactor Internals Irradiated Material Welding Solutions: Potential Applications of Welding to Repair Irradiated Reactor Internals Jon Tatman EPRI WRTC Wayne Lunceford EPRI BWRVIP Greg Frederick EPRI WRTC Background - Helium-Induced

More information

Burst Pressure Prediction of Cylindrical Shell Intersection

Burst Pressure Prediction of Cylindrical Shell Intersection Burst Pressure Prediction of Cylindrical Shell Intersection Liping Xue, G. E. O. Widera Marquette University Center for Joining and Manufacturing Assembly Milwaukee, Wisconsin 53201 Zhifu Sang Nanjing

More information

IGSCC OF INCONEL 718 HOLD DOWN SPRING IN 400 O C STEAM ENVIRONMENT

IGSCC OF INCONEL 718 HOLD DOWN SPRING IN 400 O C STEAM ENVIRONMENT IGSCC OF INCONEL 718 HOLD DOWN SPRING IN 400 O C STEAM ENVIRONMENT H. Jang 1, J.D. Hong 1, S.S. Kim 2, K.B. Eom 2, O.H. Kwon 2, C. Jang 1 1 Department of Nuclear and Quantum Engineering, KAIST, Daejeon,

More information

FITNESS FOR SERVICE ASSESSENENT FOR CRYSTALLIZERS WITH CRACK LIKE FLAWS

FITNESS FOR SERVICE ASSESSENENT FOR CRYSTALLIZERS WITH CRACK LIKE FLAWS FITNESS FOR SERVICE ASSESSENENT FOR CRYSTALLIZERS WITH CRACK LIKE FLAWS Morteza K. Jafari 1, PE, Steve Wickerson 1, PE 1 MISTRAS Group, Inc., 4000 Underwood Rd., La Porte, Texas 77571 Abstract Since 2001,

More information

Boiling Water Reactor Vessel and Internals Project (QA)

Boiling Water Reactor Vessel and Internals Project (QA) Boiling Water Reactor Vessel and Internals Project (QA) Program Description Program Overview As boiling water reactors have aged, various forms of operation-limiting stress corrosion cracking have appeared,

More information

ATI 2205 ATI Technical Data Sheet. Duplex Stainless Steel GENERAL PROPERTIES. (UNS S31803 and S32205)

ATI 2205 ATI Technical Data Sheet. Duplex Stainless Steel GENERAL PROPERTIES. (UNS S31803 and S32205) ATI 2205 Duplex Stainless Steel (UNS S31803 and S32205) GENERAL PROPERTIES ATI 2205 alloy (UNS S31803 and/or S32205) is a nitrogen-enhanced duplex stainless steel alloy. The nitrogen serves to significantly

More information

Fatigue Damage Management Based on Postulated Crack Growth Curve

Fatigue Damage Management Based on Postulated Crack Growth Curve E-Journal of Advanced Maintenance Vol.7- (25) 43-49 Japan Society of Maintenology Fatigue Damage Management Masayuki KAMAYA,* and Takao NAKAMURA 2 Institute of Nuclear Safety System, Inc., 64 Sata, Mihama-cho,

More information

42 MPA-SEMINAR 2016, October 4 and

42 MPA-SEMINAR 2016, October 4 and Plastic buckling of thin-walled pipes with D/t > 50 and conclusions for the nuclear design codes Henry Schau, Angelika Huber TÜV SÜD Energietechnik GmbH, Mannheim, Germany 42 nd MPA-Seminar October 4 th

More information

Cold Spray Coatings for Prevention and Mitigation of Stress Corrosion Cracking

Cold Spray Coatings for Prevention and Mitigation of Stress Corrosion Cracking Cold Spray Coatings for Prevention and Mitigation of Stress Corrosion Cracking Arash Parsi 1, Jack Lareau 1 Brian Gabriel 2, Victor Champagne 2 1 Westinghouse Electric Co LLC, 1340 Beulah Road, Pittsburgh,

More information

by MAEKAWA Akira, NODA Michiyasu, TAKAHASHI Shigeru, OUMAYA Toru, SERIZAWA Hisashi and MURAKAWA Hidekazu

by MAEKAWA Akira, NODA Michiyasu, TAKAHASHI Shigeru, OUMAYA Toru, SERIZAWA Hisashi and MURAKAWA Hidekazu [ 27 p. 240s-244s (2009)] by MAEKAWA Akira, NODA Michiyasu, TAKAHASHI Shigeru, OUMAYA Toru, SERIZAWA Hisashi and MURAKAWA Hidekazu This paper reports measured and estimated results of residual stress distributions

More information

TARGET FLAW SIZE IN CANDU FERRIT PIPES THE CONSIDERATION OF TILTED AND SKEWED FLAW ANGLES

TARGET FLAW SIZE IN CANDU FERRIT PIPES THE CONSIDERATION OF TILTED AND SKEWED FLAW ANGLES TARGET FLAW SIZE IN CANDU FERRIT PIPES THE CONSIDERATION OF TILTED AND SKEWED FLAW ANGLES Songyan Yang, OPG Richard Yee, AMEC-NSS KiSang Jang, COG 1 June 15-17 2010 3rd. International

More information

CONTENTS. Foreword... xiii Statements of Policy... xv Personnel... xvii Organization of Section III... xxvii Summary of Changes...

CONTENTS. Foreword... xiii Statements of Policy... xv Personnel... xvii Organization of Section III... xxvii Summary of Changes... CONTENTS Foreword... xiii Statements of Policy... xv Personnel... xvii Organization of Section III... xxvii Summary of Changes... xxxi Article NB-1000 Introduction... 1 NB-1100 Scope... 1 NB-1110 Aspects

More information

Introduction to Joining Processes

Introduction to Joining Processes 4. TEST METHODS Joints are generally designed to support a load, and must be tested to evaluate their load-supporting capabilities. However, it is also important to evaluate, not the joint, but rather

More information

A REVIEW ON DESIGN AND ANALYSIS OF PRESSURE VESSEL

A REVIEW ON DESIGN AND ANALYSIS OF PRESSURE VESSEL A REVIEW ON DESIGN AND ANALYSIS OF PRESSURE VESSEL 1 Umbarkar Bhagyashri B. 2. Prof. Hredeya Mishra 1 Student, Dept. of Mechanical Engg.,Jaihind college of Engg. & Technology, Maharashtra, India. Um.bhagyashri@gmail.com

More information

EFFECT OF PRIOR MACHINING DEFORMATION ON THE DEVELOPMENT OF TENSILE RESIDUAL STRESSES IN WELD FABRICATED NUCLEAR COMPONENTS

EFFECT OF PRIOR MACHINING DEFORMATION ON THE DEVELOPMENT OF TENSILE RESIDUAL STRESSES IN WELD FABRICATED NUCLEAR COMPONENTS EFFECT OF PRIOR MACHINING DEFORMATION ON THE DEVELOPMENT OF TENSILE RESIDUAL STRESSES IN WELD FABRICATED NUCLEAR COMPONENTS P. S. Prevéy, P. W. Mason, D. J. Hornbach, and J. P. Molkenthin ABSTRACT Austenitic

More information

Metal-plate connections loaded in combined bending and tension

Metal-plate connections loaded in combined bending and tension Metal-plate connections loaded in combined bending and tension Ronald W. Wolfe Abstract This study evaluates the load capacity of metal-plate connections under combined bending and axial loads and shows

More information

Reeling-induced residual stress and its effect on the fracture behavior of pipes with through thickness cracks

Reeling-induced residual stress and its effect on the fracture behavior of pipes with through thickness cracks To be presented at the 4th International Conference on Pipeline Technology, Ostend, Belgium, 9-13 May 24 Reeling-induced residual stress and its effect on the fracture behavior of pipes with through thickness

More information

High Energy Piping Inspection Program for Power Generation and Process Industries. For Regulatory Compliance, Safety, and System Longevity

High Energy Piping Inspection Program for Power Generation and Process Industries. For Regulatory Compliance, Safety, and System Longevity High Energy Piping Inspection Program for Power Generation and Process Industries For Regulatory Compliance, Safety, and System Longevity EAPC Industrial Services offers an inspection plan for assessment

More information

Boiling Water Reactor Vessel and Internals

Boiling Water Reactor Vessel and Internals Boiling Water Reactor Vessel and Internals Program Description Program Overview As boiling water reactors have aged, various forms of operation-limiting stress corrosion cracking have appeared, first in

More information

VIBRATION FATIGUE TESTING OF SOCKET WELDS, PHASE II

VIBRATION FATIGUE TESTING OF SOCKET WELDS, PHASE II VIBRATION FATIGUE TESTING OF SOCKET WELDS, PHASE II Paul Hirschberg Michael Sullivan Robert Carter Peter C. Riccardella Jon Schletz EPRI Project Manager Structural Integrity Associates Pacific Gas & Electric

More information

Draft Fracture Mechanics Code Case for American Society of Mechanical Engineers NUPACK Rules

Draft Fracture Mechanics Code Case for American Society of Mechanical Engineers NUPACK Rules 14th International Symposium on the Packaging and Paper # 085 Transportation of Radioactive Materials (PATRAM 2004), Berlin, Germany, September 20-24, 2004 Draft Fracture Mechanics Code Case for American

More information

Effective PA UT Inspection Techniques for Austenitic Welds

Effective PA UT Inspection Techniques for Austenitic Welds Effective PA UT Inspection Techniques for Austenitic Welds Guy MAES, Johan BERLANGER, Frédéric LAPRISE (Zetec, Quebec, Canada) NDTMA 2017 Las Vegas, February 15, 2017 Zetec Inc. All right reserved 1 Introduction

More information

EFFECT OF PRIOR MACHINING DEFORMATION ON THE DEVELOPMENT OF TENSILE RESIDUAL STRESSES IN WELD FABRICATED NUCLEAR COMPONENTS

EFFECT OF PRIOR MACHINING DEFORMATION ON THE DEVELOPMENT OF TENSILE RESIDUAL STRESSES IN WELD FABRICATED NUCLEAR COMPONENTS EFFECT OF PRIOR MACHINING DEFORMATION ON THE DEVELOPMENT OF TENSILE RESIDUAL STRESSES IN WELD FABRICATED NUCLEAR COMPONENTS P. S. Prevéy, P. W. Mason, D. J. Hornbach, and J. P. Molkenthin ABSTRACT Austenitic

More information

C. PROCEDURE APPLICATION (FITNET)

C. PROCEDURE APPLICATION (FITNET) C. PROCEDURE APPLICATION () 63 INTRODUCTION INPUTS ANALYSIS FAD AND CDF ROUTES GUIDANCE ON OPTION SELECTION SPECIAL OPTIONS 64 INTRODUCTION INTRODUCTION: The Fracture Module is based on fracture mechanics

More information

Structural Vessel Repairs Using Automated Weld Overlays

Structural Vessel Repairs Using Automated Weld Overlays Structural Vessel Repairs Using Automated Weld Overlays Mahmod Samman, Ph.D., P.E. mms@hes.us.com Houston Engineering Solutions, LLC Eric Williams George Gemmel ewilliams@cimsltd.com ggemmell@cimsltd.com

More information

MSE 3143 Ceramic Materials

MSE 3143 Ceramic Materials MSE 3143 Ceramic Materials Mechanical Properties of Ceramics Assoc.Prof. Dr. Emre YALAMAÇ Res.Asst. B.Şölen AKDEMİR 2017-2018 Fall 1 OUTLINE Elasticity & Strength Stress & Strain Behaviour Of Materials

More information

CHAPTER 8 DEFORMATION AND STRENGTHENING MECHANISMS PROBLEM SOLUTIONS

CHAPTER 8 DEFORMATION AND STRENGTHENING MECHANISMS PROBLEM SOLUTIONS CHAPTER 8 DEFORMATION AND STRENGTHENING MECHANISMS PROBLEM SOLUTIONS Slip Systems 8.3 (a) Compare planar densities (Section 3.15 and Problem W3.46 [which appears on the book s Web site]) for the (100),

More information

RPV and Primary Circuit Inspection. Nondestructive Examination Standard for PWR Vessel Internals J. Spanner, EPRI, USA

RPV and Primary Circuit Inspection. Nondestructive Examination Standard for PWR Vessel Internals J. Spanner, EPRI, USA RPV and Primary Circuit Inspection Nondestructive Examination Standard for PWR Vessel Internals J. Spanner, EPRI, USA INTRODUCTION The Electric Power Research Institute s Materials Reliability Program

More information

Effective Aging Management of Baffle-to-Former Bolts to Assure Long-Term Reliability of Reactor Vessel Internals

Effective Aging Management of Baffle-to-Former Bolts to Assure Long-Term Reliability of Reactor Vessel Internals Effective Aging Management of Baffle-to-Former Bolts to Assure Long-Term Reliability of Reactor Vessel Internals Tiangan Lian Kyle Amberge Electric Power Research Institute Fourth Nuclear Power Plant Life

More information

Structural Integrity and NDE Reliability I

Structural Integrity and NDE Reliability I Structural Integrity and NDE Reliability I Influence of Uncertainties in NDT on the Assessment of the Integrity of Components S. Dugan, X. Schuler, G. Wackenhut, S. Zickler Materials Testing Institute

More information