MINING AND UPSTREAM PETROLEUM PRODUCTION. CONTAMINATED SITES ASSESSMENT AND REMEDIATION THE REGULATORY REGIMES AND THE POTENTIAL FOR LIABILITY
|
|
- Pearl Quinn
- 5 years ago
- Views:
Transcription
1 MINING AND UPSTREAM PETROLEUM PRODUCTION. CONTAMINATED SITES ASSESSMENT AND REMEDIATION THE REGULATORY REGIMES AND THE POTENTIAL FOR LIABILITY Ecoforum Conference, Sydney. May, 2009 Abstract Increasing awareness of the need to effectively address the assessment and remediation of contaminated sites inherited from historical industrial land uses is reflected in the range of specific contaminated sites legislation adopted by all of the Australian states and the ACT. The drivers of the process of identifying, assessing and remediating contaminated sites in urban areas differ from those applicable to industrial activities that have taken place in more remote geographical locations. However, the issue in such areas remains significant. Historically and culturally, the contaminated sites issue for miners and petroleum producers has been addressed through regulatory regimes based principally on petroleum and mining legislation. However, there is generally no legal constraint on the application of specific contaminated sites legislation to land and water resources contaminated by minerals processing and petroleum production activities. It would be prudent to factor into mine and petroleum production planning, particularly for decommissioning stages, the potential application of specific contaminated sites legislation. The Rise and Rise of the Contaminated Sites Issue The social and environmental issue of the identification, assessment and remediation of historically contaminated sites 1 (hereinafter referred to as IAR ) has assumed considerable prominence in the last two decades or so in Australia. This prominence is due as much to economics as environmental concerns. Former industrial land, waste disposal facilities and sites contaminated by past activities have gained in potential value as urban areas have expanded and inner city land, where most industries in Australia were initially located, has increased in value. Where the cost of remediation can be absorbed into re-development projects and their commercial viability maintained there is incentive for the remediation and development of contaminated sites. 1 The term historical contamination refers to soil and groundwater contamination that has occurred as a consequence of industrial and agricultural land uses that have been undertaken over time and resulted in the accumulation of chemical and other contaminants at levels deemed unacceptable. However, land and water contamination can occur as a result of single or isolated incidents with long-term impacts. 1
2 The mining sector and the upstream petroleum industry potentially face the challenge of dealing with contaminated sites, but the drivers behind the remediation of such sites may differ considerably from those in the urban context. Additionally, the regulatory regimes applying to operators in those sectors may differ and in some respects be more complex. Nevertheless, assumptions that miners and petroleum producers are somehow insulated from relatively recent contaminated sites laws in Australian jurisdictions are mistaken. In some circumstances, failure of mining and petroleum regulatory regimes to address effectively contaminated sites issues, particularly where impacts on groundwater are involved, may attract the attention of the regulatory authority administering dedicated contaminated sites legislation in the particular jurisdiction. The Issues Some of the more significant issues confronting miners and upstream petroleum producers may be identified as follows: i. Effective forward planning and costing with respect to the decommissioning of facilities and the assessment and remediation of associated contaminated sites (whether within or outside a tenement area). ii. iii. iv. Identification of the factors in any particular circumstance that may determine likely regulatory responses for example, operations that may have impacted on a significant water resource. Realistic identification of the regulatory regimes likely to be applied to contaminated mining and upstream petroleum sites. Identification of potentially liable parties under relevant legislation, particularly where joint ventures are involved. The Regulatory Regimes In broad terms, the application of IAR to historically contaminated land in urban areas will be addressed, where necessary, by pollution management legislation, much of it specific contaminated sites legislation such as the contaminated sites provisions of the Queensland Environmental Protection Act 1994, the more recent West Australian Contaminated Sites Act 2003 and the contaminated sites provisions of the South Australian Environment Protection Act 1993 that are due to come into effect on July 1 st As will be seen later, such legislation can apply to mining and petroleum operations. It is generally assumed, however, that within existing tenement areas the relevant mining or petroleum legislation and associated administrative regimes will be the principal framework for addressing the issue of sites contaminated by such activities over time. For historical 2
3 and cultural reasons, there can be a tendency to assume that legal obligations will follow largely from these regimes rather than from dedicated contaminated sites legislation. However, as mentioned above and illustrated below, it does not follow that the specific contaminated sites legislation in each jurisdiction is necessarily excluded from application to contaminated land located within a mining or petroleum tenement area. The historical role of mining and petroleum regulators has been significantly diminished in some jurisdictions in relation to environmental management where environment and pollution control agencies have assumed greater prominence through pollution licensing and more recently the administration of contaminated sites legislation. When contemplating the decommissioning of a facility or the relinquishment of a tenement area where contamination of land may have arisen through operations, it would be prudent to factor into planning processes the potential application of a range of environmental legislation, particularly the prospective application of dedicated contaminated sites legislation. Off-site minerals or hydrocarbon processing (that is, outside a tenement area) presents less regulatory complexities. Where the ore or other unprocessed product is transported to non-tenement sites, the issue of site contamination and its resolution will fall more directly under the dedicated contaminated sites regime, if any, applicable within that jurisdiction. The application of IAR to orphan 2 mining or petroleum sites raises special problems, the resolution of which argues for meaningful government intervention Influencing Factors IAR of Contaminated Mining and Petroleum Production Sites The relative geographical remoteness of most, although by no means all, mining and petroleum operations from large urban settlement does tend to shield those industries from the dynamic of urban growth that is encouraging the remediation of contaminated sites within Australian cities, particularly in what are now inner-urban areas. There are, however, other factors that are likely to influence mining and petroleum operators to address the issue within their tenements. These include: 1) Actual or threatened contamination of surface or groundwater in a socio-political climate focusing increasingly on the issue or water resources. 2) Agricultural use of surface and groundwater. 3) Residential expansion in regional centres where contamination of land and groundwater may limit subdivision potential and discourage expansion in areas where there are legitimate fears of groundwater contamination. 2 Orphan sites are those sites for which the original polluter cannot be found and held responsible for remediating the site or where, for whatever reason, it is not practicable or reasonable to hold the person with current title to the land or otherwise in occupation of it responsible for the cleanup. 3
4 4) The concerns of indigenous Australians about their lands and the continuation of traditional land uses. Remediation of Contaminated Mine and Petroleum Sites Nature and Origins Broadly speaking the following regulatory and financial sources exist to address remediation of sites contaminated by mining or petroleum activities. They can be inter-related: i. Specific statutory rehabilitation/restoration requirements imposed on tenement holders; ii. iii. iv. Conditions of tenements requiring rehabilitation or restoration prior to decommissioning; Statutory bonds or securities; Statutory rehabilitation funds; v. Government (publicly funded) mine rehabilitation programs; vi. vii. Conditions imposed on operators holding relevant pollution control authorisations under general pollution control legislation such as Environment Protection Acts; Specific contaminated sites legislation. Specific Statutory Requirements Some legislation contains specific provisions requiring rehabilitation of land within a tenement area prior to surrender or relinquishment of the tenement. For example, the Queensland Petroleum Act 1923 specifies that in no case shall such surrender be effective until the lessee has made full provision for conservation and protection of the property. 3 Whilst it may be inferred from such a provision that remediation of contaminated sites, including evaporation ponds, is contemplated, it would appear that in all practicality surrender or relinquishment would depend upon a determination by the Minister or relevant authority as to whether such remediation was necessary. No equivalent provision is incorporated into the more recent Petroleum and Gas (Production and Safety) Act This reflects the relatively recent transfer of responsibility for environmental management of petroleum and mining activities to the EPA under the Environmental Protection Act The Victorian Petroleum Act imposes on the holder of an authority an obligation to rehabilitate any land that is used in carrying out any operation under the authority and [to], as far as is practicable, complete the rehabilitation of the land before the authority... ceases to apply to the land. 3 Petroleum Act 1923, section 52(1). 4 Transitional provisions of this Act maintain the currency of the Petroleum Act where necessary. 5 Petroleum Act 1998, section
5 Tenement Conditions and Operational Approvals It has commonly been the practice to include in mining and petroleum production tenements in some jurisdictions specific environmental conditions. These conditions are frequently broad, although they arguably encompass the issue of remediation of contaminated sites. For example, production licences issued under the former West Australian Petroleum Act 1967 contained the following standard clause: In carrying out its operation in the licence area the licensee shall take adequate measures for the protection of the environment and shall comply with all reasonable requests of the Minister for Mines in relation thereto. 6 More likely, however, such remediation requirements will be included as conditions of the various operational approvals required from the relevant mining or petroleum agency before specific production operations may commence. In South Australia, the Petroleum Act 2000 requires the preparation of a Statement of Environmental Objectives (SOE) that will require approval by the Minister before operations may commence. This SOE will normally refer to the issue of rehabilitation. For example, the Stuart Petroleum SOE for petroleum production at Acrasia Field 7 contains the following environmental objective: Develop a long term closure and remediation plan in advance of any closure (Objective 21). This is elaborated upon in Appendix 1 of the SEO stipulating that detail of closure and remediation should be developed before closure commences, but attempting detailed planning at the start of production is not an effective course. A further commitment is given to "develop a rehabilitation SEO prior to first well abandonment. It is clear that such conditions and commitments do not normally specify the nature of the restoration or rehabilitation. In relation to contaminated sites, that will lie with the nature of rehabilitation plans developed over time and any subsequent regulatory approvals required. Statutory Bonds and Securities The requirement for the holder of a mining or petroleum tenement to enter into a bond and to provide related security to address on-going and future liabilities, including site rehabilitation, is one means of ensuring that a legacy of unremediated contaminated sites is 6 Now the Petroleum Production and Geothermal Energy Act Stuart Petroleum Pty Ltd. November Statement of Environmental Objectives. Petroleum Production at Acrasia Basin, Cooper Basin SA. 5
6 not bequeathed to future generations and the environment at large. 8 However, whether the financial assurance will adequately address the costly process of assessing and remediating contaminated land will depend on the extent of the security required. The application of a bond to such remediation works may also be determined by the specificity or otherwise of the matters to which it must or can be applied. For example, will it be applied to rehabilitation broadly to the satisfaction of the Minister, or will it be specifically tied to addressing conditions of the relevant mining or petroleum tenement as is the case under the Western Australian Mining Act 1978? 9 It follows that if the conditions can be interpreted narrowly to exclude remediation of contaminated areas of a mine site, the application of the security may not extend to that issue. In Western Australia the requirement for securities under section 126 of the Mining Act 1978 increased from $10,000 per hectare to $20,000 per hectare in 2008 with the Department of Industry and Resources utilising a risk-based approach to calculating performance bonds. 10 In the case of mines of relatively small areas (compared with, say, mineral sands mining) where processing is occurring on site, a risk-based approach would appear much more appropriate than an approach to determining the quantum of security required based on aerial calculation. The Queensland Department of Natural Resources, Mines and Energy reports that the introduction of the Mineral Resources Act 1989 has caused a massive increase in the amount of security required. 11 The Department s report states that since then the amount of security held by the Department increased from about $5 million in 1991 to $45 million in 1993, $62 million in 1994 and more than $370 million in The Victorian Petroleum Act 1998 specifies that the holder of a petroleum authority cannot undertake a petroleum operation unless it has obtained a rehabilitation bond that is acceptable to the Minister. 13 Not all States have adopted the machinery of performance bonds in relation to petroleum activities. The South Australian Petroleum Act 2000 specifies that: It is a mandatory condition of every licence that the licensee must have adequate technical and financial resources to ensure compliance with the licensee s environmental obligations (including the rehabilitation of land adversely affected by regulated activities carried out under the licence) See, for example, section 62 of the South Australian Mining Act See Mining Act 1978, section 84A(1). 10 Audeyev, S., Whinnen, C. and Gishubi, B. Does it Ever End? "Legal Aspects of Mine Closure in Western Australia", in Environment Matters. Blake Dawson. 5 June Department of Mines and Energy Queensland. ww.dme.qld.gov.au/mines/regulation.cfm. 12 Ibid. 13 Petroleum Act 1998, section Petroleum Act 2000, section 75. 6
7 Additionally, the Minister has the power to direct the rehabilitation of land and to undertake necessary work and to recover the cost of so doing from the licensee or former licensee. 15 Presumably, these powers can be applied to a situation where there is substantial hydrocarbon contamination of a site. However, this approach tends to assume that the licensee will be in a position financially to comply with any relevant direction or to recompense the State for the cost of so doing. Statutory Rehabilitation Funds and Government Restoration Programs Some mining and petroleum legislation establishes rehabilitation funds based on a levy imposed on the miner or petroleum producer. The South Australian Mining Act 1971 retains the Extractive Areas Rehabilitation Fund (to address rehabilitation of areas disturbed by extractive industries) which presumably can be applied to contaminated land, although the potential for process-induced contamination from the milling of quarry materials would appear limited. In Queensland, the State Government conducts a state-wide, publicly funded abandoned mine land program directed to the rehabilitation of mine sites abandoned before the more stringent security requirements came into place and where the company that caused the problem no longer exists or does not have the financial resources to meet the rehabilitation costs. Work under this program has reached approximately $12 million (to the end of 2007) and clearly encompasses contaminated sites assessment and remediation. Environmental Assessment and Pollution Licensing In the last fifteen years or so in Australia, most jurisdictions have moved to transfer responsibility for regulating pollution (both short and long-term) associated with mining and petroleum activities from the relevant mining or petroleum agency to the State s Environment Protection Agency or equivalent. Effective a priori assessment of the potential of pollution (including land and water contamination) will occur through the environmental impact assessment (EIA) and associated licensing processes. Two examples of approaches taken by different jurisdictions are outlined below. In Queensland there has been a conscious and concerted effort to integrate environmental regulation of mining and petroleum activities into the Environmental Protection Act Consequently, proposed mining production activities in Queensland may be subject to a requirement for environmental impact assessment, the preparation of an environmental management plan (EMP) and the issuing of an environmental authority based on that plan. To this extent there is ample opportunity under the Environmental Protection Act to manage activities that may have the potential to cause long-term contamination of land and water associated with mining activities. 15 See Petroleum Act 2000, section
8 Petroleum production activities are subject to a similar EIA regime and an environmental authority is required for such activities under the Environmental Protection Act. An applicant for a "Level 1" environmental authority (petroleum activities) is required to submit a plan that is used as a basis for the application of appropriate conditions in the environmental authority. Again, in the context of the petroleum industry, effective regulation of activities that might lead to contamination of land or water is contemplated. In South Australia the processes of EIA and pollution management are not integrated into a single piece of legislation. In the case of the petroleum activities, EIA is managed through the Petroleum Act 2000 and the Development Act 1993 with proposed petroleum production activities (and pipelines) that may have major social, environmental or economic impacts falling under the Development Act. The Environment Protection Act requires that an authorisation be acquired for petroleum producing activities above a certain production or storage threshold. If the proposed production activity has been subject to formal EIA processes under the major project provisions of the Development Act, the EPA will have been consulted under that process and would have had the opportunity to stipulate the appropriate pollution control conditions to be included in any subsequent project approval. These will be reflected in the authorisation that the EPA is then obliged to issue under the Environment Protection Act. 16 Presumably, satisfactory remediation of any contaminated site would be a condition. Mineral processing activities are subject to environmental assessment regimes under the Mining Act 1971 and Development Act respectively, with an authorisation under the Environment Protection Act required for mineral processing activities. Broadly speaking, the processes in relation to major project EIA for mine proposals are the same as those described for petroleum production proposals of similar significance. Again, this facilitates the regulation of activities in both sectors that have the potential to contaminate land or water and to require appropriate assessment and remediation prior to relinquishment or expiry of any authorisation issued under the Environment Protection Act. Specific Contaminated Sites Legislation It is apparent from the above that within the mining and petroleum production regulatory regimes there is substantial scope to implement preventative mechanisms in relation to activities with the potential to contaminate soil and groundwater. There also exist in some jurisdictions requirements for securities and performance bonds that appear adequate to cover residual contamination that must be addressed prior to relinquishment of tenements and decommissioning of production and processing facilities. Furthermore, in some jurisdictions programs have been established to rehabilitate abandoned mine sites. Presumably, such programs extend to assessment and remediation of contaminated land. 16 Environment Protection Act 1993, section 47(2). 8
9 Despite this, situations will inevitably arise where contaminated sites, for whatever reason, remain after the cessation of petroleum or mining activities and pressures to address the problem may occur. For example, whilst the upstream petroleum industry is relatively young, production activities have been occurring in the Cooper Basin for nearly 30 years. There will almost inevitably exist evaporation ponds and hydrocarbon waste pits established in the 1980s that, whilst remote, may not be acceptable in the longer term in an unremediated state. Decommissioned mines and associated minerals processing facilities in peri-urban areas may attract attention sooner than expected under normal mine rehabilitation regimes, whether privately or publicly resourced. The growing demand for residential and ruralresidential land may accelerate the need for effective remediation. If the mining and petroleum regulatory regimes are inadequate in these circumstances, what is the role of the relatively new dedicated land contamination legislation? In short, contaminated sites legislation can apply. Essentially, Australian contaminated sites legislation adopts the following framework: 1) Definition of parties liable for assessment and remediation essentially, the polluter first and the owner second where the polluter cannot be found or is unable to pay for the processes. 2) In some jurisdictions, the creation of registers of potentially and actually contaminated sites. 3) Creation of powers in the relevant authority (for example, the relevant state EPA) to issue assessment and remediation orders to the polluter or, in specified circumstances, the owner. 4) The recognition of environmental auditors who exercise a form of delegated authority under the relevant legislation to ensure that assessment and remediation adheres to statutory criteria and adopted guidelines; 5) Specification of the obligation on contaminated sites professionals (consultants and auditors) to adhere to the range of guidelines created or adopted by the relevant authority; 6) Some connection of the contaminated sites regime, formally or informally, with the relevant local land-use planning and development application process in order that assessment and remediation of contaminated land is integrated into development proposed on such land. Land contaminated by mining or upstream petroleum processes is generally not excluded from the application of specific contaminated sites assessment and remediation legislation. 9
10 As amendments to the Environment Protection Act 1993, the South Australian legislation will apply within tenement areas despite exclusions created by section 7 whereby the Act does not apply to wastes produced in the course of an activity (being one requiring an authorisation under the Act) undertaken within the boundaries of a mining or petroleum tenement provided the waste is produced and disposed of within the tenement boundary. Most mineral processing and petroleum production and processing activities (which are those most likely to produce land and water contaminants) do require a licence under the Act. It follows that any person responsible for contaminating land as a consequence of their activities within a petroleum or mining tenement in South Australia (or in some cases, if applicable, the subsequent owner of the contaminated land) could be issued with site contamination assessment orders and site remediation orders. The site contamination provisions of the Queensland Environmental Protection Act 1994 similarly have the potential to apply to mine sites and petroleum production sites. As indicated above, the decommissioning of mining and petroleum operations will fall substantially to the Department of Natural Resources, Mines and Water although the EPA would also have a role through the conditions of any environmental authorities issued to the operator under the Environmental Protection Act. 17 In the event of a petroleum or mining site being contaminated but not addressed through either of those mechanisms, the Environmental Protection Agency could apply the contaminated sites provisions. The WA Contaminated Sites Act 2003 similarly has no provision excluding its application from mining or petroleum sites. Liable Parties The general position under contaminated sites legislation in Australia is that the polluter is the party principally exposed to the issuing of contaminated sites assessment and remediation orders. Where the polluter cannot be found, no longer exists, or is not in a financial position to respond to such orders, the owner of the land may be subject to such orders. In South Australia, for example, the appropriate person to be issued with a site contamination assessment order (SCAO) or a site remediation order (SRO) will be the person who caused the site contamination at the site or, if it is not practicable to issue the order to that person, the owner in specified circumstances It should be noted that the Queensland Environmental Protection Act requires that the owner or occupier of land who becomes aware of a notifiable activity being carried out on land or that land is being contaminated must notify the EPA within 22 days of becoming so aware (sections 371(1) & 371(2)). 18 Environment Protection Act 1993, section 103C. 10
11 Potential liability for the assessment and remediation of contaminated sites under the West Australian Contaminated Sites Act follows the polluter pays principle, but for contamination caused before the Act came into effect (2006) the contamination must have been caused by an unlawful Act. 19 Otherwise, it is the owner of the site who is liable for assessment and remediation under the Act. In Queensland the person who released the contaminant (the polluter), the relevant local government in certain circumstances, or the owner of the relevant land may be liable for site assessment and/or remediation. 20 In cases of site contamination caused by mining or petroleum operations, identifying the party (or parties) liable for assessment or remediation can be complicated by the now relatively common concept of the joint venture (JV). Legally, these relationships are difficult to define and have the potential to give rise to issues of agency and vicarious liability as between operators and members of the joint venture. Complex issues of law and fact may be involved in determining the extent to which, if at all, a joint venture member may be liable for the assessment and remediation of a site contaminated as a consequence of operations conducted on behalf of the JV. Whilst it is not practicable to address this issue in detail here, it is one that might well attract the attention of members of mining and petroleum joint ventures, particularly if a project or programme is nearing completion. Conclusions Historically, remediation of contaminated land within mining and petroleum production tenements has fallen to a range of regulatory frameworks and government programs located within or associated with the relevant State or Territory mining and petroleum agencies. This situation has changed in the last fifteen years or so in Australia with the application of specific pollution management legislation to a range of mining and petroleum production activities. Nevertheless, parallel regulatory regimes remain with the potential to address the issue of the assessment and remediation of sites contaminated by petroleum production and mining activities. Assessment and remediation of contaminated sites, particularly if water resources are affected, can be an extremely costly exercise to be integrated into the total cost of decommissioning. Arguably flexible approaches to remediation of contaminated sites hitherto available to companies under mining and petroleum regulatory regimes may be constrained by the relatively recent introduction and application of dedicated contaminated sites legislation. 19 Contaminated Sites Act 2003, section Environmental Protection Act, sections 376 and
12 It would be prudent for operators to factor in to the decommissioning and rehabilitation phase of a mine or upstream petroleum operation the potential application of contaminated sites legislation within the relevant jurisdiction. David Cole Special Counsel (Environmental Law) DLA Phillips Fox and Project Leader, Program 4 CRC for Contamination Assessment and Remediation of the Environment 15 April
Attachment 4. Brimbank City Council Submission to EPA Ministerial Advisory Committee 2015
Attachment 4 Brimbank City Council Submission to EPA Ministerial Advisory Committee 2015 About Brimbank Brimbank City is located in Melbourne s west, one of the fastest growing regions in Australia. The
More informationUranium mining legal and regulatory framework
South Australia s Environment Protection Authority Uranium mining legal and regulatory framework An Australian perspective Keith Baldry Director Mining Radiation and Regulatory Support IAEA Seminar on
More informationElectricity Distribution Network Code. made under the Electricity Act 1994
Electricity Distribution Network Code made under the Electricity Act 1994 CHAPTER 1: THIS CODE 4 1.1 Introduction 4 1.1.1 Code objective 4 1.1.2 Scope of the Code 4 1.1.3 Authority 4 1.1.4 Date of effect
More informationSection 3. Legislative Framework and Impact Assessment Process
Section 3 Legislative Framework and Impact Assessment Process 22 Cameco Australia Pty Ltd 3. Legislative Framework and Impact Assessment Process 3.1 Key Legislative Requirements The Project requires environmental
More informationSantos Gas Field Development Project (GFD Project)
Santos Gas Field Development Project (GFD Project) EPBC Approval No. 2012 / 6615 Annual Environmental Return 2017 Santos Ltd l 2017 GFD Project AER (2012/6615) l February 2018 Page 1 of 17 Introduction
More information12. A Sustainable Murray Darling Basin: The legal challenges
12. A Sustainable Murray Darling Basin: The legal challenges Douglas Fisher Introduction The range of legal instruments informing how the Murray Darling Basin (MDB) is managed is extensive. Some provide
More informationFACTS. Highlights of Legislation and Regulations ON CONTAMINATED SITES
3 FACTS ON CONTAMINATED SITES Highlights of Legislation and Regulations January 2009 Comprehensive contaminated sites legislation was passed by the BC legislature in June 1993. It came into effect on April
More information(8 December 2014 to date) NATIONAL ENVIRONMENTAL MANAGEMENT ACT 107 OF 1998
(8 December 2014 to date) NATIONAL ENVIRONMENTAL MANAGEMENT ACT 107 OF 1998 (Gazette No. 19519, Notice No. 1540. Commencement date: 29 January 1999 [Proc. No. 8, Gazette No. 19703]) ENVIRONMENTAL IMPACT
More informationConsultation Regulatory Impact Statement
Consultation Regulatory Impact Statement Post Implementation Review of the Industry Levy to fund the petroleum and gas water functions of the Office of Groundwater Impact Assessment December 2016 This
More informationDOCUMENT REVISION RECORD
DOCUMENT REVISION RECORD REV No. ISSUE DATE DESCRIPTION PREPARED CHECKED AUTHORISE D 0.1 24/04/06 Initial draft A ter Kuile T Reynolds A T Rakai 1.0 27/04/07 Issued for use A ter Kuile H Kuhn A T Rakai
More informationReclamation: Legislative / Regulatory Requirements
Reclamation: Legislative / Regulatory Requirements Shane Patterson Science and Technology Specialist Land Conservation and Reclamation Policy Branch Outline Conservation & Reclamation 1) Legislation Environmental
More informationUranium mining licensing A South Australian perspective
South Australia s Environment Protection Authority Uranium mining licensing A South Australian perspective Keith Baldry Director Mining Radiation and Regulatory Support IAEA Seminar on Governance of Uranium
More information5 Contaminated Sites
5 Contaminated Sites 5.1 Introduction For the purpose of this Plan, a contaminated site is a site at which hazardous substances occur at concentrations above background levels and where assessment indicates
More informationPOLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)
Established 1907 POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) DATE: JULY 2018 Version Date Section Modified 1 July 2018 All Reason for Modification Original Management Plan Review Team MCC Environmental,
More informationPublic Consultation Guidelines - Electricity, Gas & Water Licences and Electricity & Gas Standard Form Contracts
Public Consultation Guidelines - Electricity, Gas & Water Licences and Electricity & Gas Standard Form Contracts April 2016 Public Consultation Guidelines - Electricity, Gas & Water Licences and Electricity
More information2018 SA ELECTION ENVIRONMENTAL LAW REFORM PRIORITIES PAPER
2018 SA ELECTION ENVIRONMENTAL LAW REFORM PRIORITIES PAPER INTRODUCTION This paper sets out the law reform priorities for South Australia as identified by the state s leading non-government environmental
More informationCity of Greater Sudbury Infrastructure Background Study APPENDIX A.1. Guideline for Sewage and Water Services
City of Greater Sudbury Infrastructure Background Study APPENDIX A.1 Guideline for Sewage and Water Services GUIDELINE D-5 Planning for Sewage & Water Services Legislative Authority: Environmental Protection
More informationGUIDELINES FOR. Mine Closure. Planning. in Queensland
GUIDELINES FOR Mine Closure Planning in Queensland Preface The Queensland Mining Council (QMC) is the peak representative organisation of the Queensland minerals industry. The council's membership encompasses
More informationAppendix X.6 Queensland Government CSG Water Management Policy
Appendix X.6 Queensland Government CSG Water Management Policy Coal Seam Gas Water Management Policy June 2010 Tomorrow s Queensland: strong, green, smart, healthy and fair Purpose The purpose of this
More informationNATIONAL ENVIRONMENTAL MANAGEMENT: WASTE ACT 59 OF 2008
NATIONAL ENVIRONMENTAL MANAGEMENT: WASTE ACT 59 OF 2008 National Environmental Management: Waste Act 59 of 2008 National Environmental Management: Waste Amendment Act 26 of 2014 National Environmental
More informationMine closure, rehabilitation and retention of financial provision (s43)
Mine closure, rehabilitation and retention of financial provision (s43) A personal experience in Sierra Leone After large companies disappeared Open access small mining digging pits and washing ores Clearing
More informationContaminated Land Auditing Charting Complex Waters
Presentation to Environmental Health Association Perth, September 2013 Contaminated Land Auditing Charting Complex Waters Roger Parker Principal Accredited Contaminated Site Auditor Content of Presentation
More informationTHE ENERGY DEVELOPMENT CYCLE
THE ENERGY DEVELOPMENT CYCLE PRE-PROJECT EXPLORATION APPRAISAL & DEVELOPMENT OPERATION CLOSURE USE Risks & Opportunities Across the Development Cycle Activities prior to the start of the individual project
More informationTo license or not to license? Listed or Unlisted? Presented by: Stuart Gower-Jackson
To license or not to license? Listed or Unlisted? Presented by: Stuart Gower-Jackson Order of proceedings 1. Classification of activities and an easy explanation on how to determine which activities qualify
More informationStep 1: Potential ASS risk zone
February 2018 This document provides guidance on the identification and assessment of potential environmental risks associated with acid sulfate soils (ASS). This guideline applies to Adelaide Airport,
More informationMINERALS COUNCIL OF AUSTRALIA
MINERALS COUNCIL OF AUSTRALIA SUBMISSION TO SENATE ENVIRONMENT AND COMMUNICATIONS REFERENCE COMMITTEE INQUIRY INTO THE REHABILITATION OF MINING AND RESOURCES PROJECTS AS IT RELATES TO COMMONWEALTH RESPONSIBILITIES
More informationDraft State Planning Policy Road and Rail Noise
Submission December 2017 Draft State Planning Policy 5.4 - Road and Rail Noise Submission to the Western Australian Planning Commission Contact Caroline Cherry C.Cherry@cmewa.com The Chamber of Minerals
More informationManaging land contamination during the mine closure and rehabilitation process NSW Department of Industry Division of Resources & Energy
Managing land contamination during the mine closure and rehabilitation process NSW Department of Industry Division of Resources & Energy Dr David Blackmore Director Environmental Sustainability Unit Nov
More informationAlberta Energy Regulator Mandate and Roles Document
Alberta Energy Regulator Mandate and Roles Document Contents 1.0 Preamble... 3 1.1 Context... 3 2.0 Mandate... 3 2.1 Background and Legislation... 3 2.2 Mandate... 5 2.3 Adjudicative Functions... 5 3.0
More informationRegulatory Compliance and Enforcement Framework
Contents 1. About us... 3 1.1 Our Mission and Values... 3 2. Relevant Legislation and Obligations... 4 3. Approach to Regulatory Compliance and Enforcement... 4 3.1 Our Approach... 4 3.2 Working with Stakeholders...
More informationConditions of Approval for the MDP for the brickworks at Perth Airport
Conditions of Approval for the MDP for the brickworks at Perth Airport Definitions In this document, unless a contrary intention appears, the terms below have the meanings given to them: AES means Airport
More informationUrban Development Institute of Australia Western Australian Division Incorporated
Our ref: 27.17 31 March 2006 Tracy McQue City of Swan PO Box 196, MIDLAND WA 6936 Dear Ms McQue CITY OF SWAN DRAFT URBAN GROWTH POLICIES Thank you for the opportunity to provide industry comment on the
More informationConditions of Award. Royal Society Funding Schemes
Conditions of Award Royal Society Funding Schemes These Conditions of Award set out the standard terms and conditions for all Royal Society Awards. The Conditions of Award should be read in conjunction
More informationConditions of Award. Royal Society Newton International Fellowships funded under the Newton Fund
Conditions of Award Royal Society Newton International Fellowships funded under the Newton Fund These Conditions of Award set out the standard terms and conditions for all Royal Society Newton International
More informationSouth Australian Public Health (Wastewater) Regulations 2013
Version: 1.7.2017 South Australia South Australian Public Health (Wastewater) Regulations 2013 under the South Australian Public Health Act 2011 Contents Part 1 Preliminary 1 Short title 3 Interpretation
More informationCentral NSW Regional Contaminated Land Policy Template
Central NSW Regional Contaminated Land Policy Template Contamination Central: Supporting safe, stable and sustainable redevelopment of land in Central West NSW. Funded by the New South P a g e 1 {Instruction
More informationOrica Australia Pty Ltd A.C.N MATRAVILLE NSW 2036
ENVIRONMENTALLY HAZARDOUS CHEMICALS ACT 1985 Licence No: 26 EPA File No: EF13/2466 Name of licensee: Address of licensee: Commencement Date: 20 July 2018 In force until: 20 July 2021 Orica Australia Pty
More informationPROOF/ÉPREUVE A ISO INTERNATIONAL STANDARD. Environmental management systems Specification with guidance for use
INTERNATIONAL STANDARD ISO 14001 First edition 1996-09-01 Environmental management systems Specification with guidance for use Systèmes de management environnemental Spécification et lignes directrices
More informationFact Sheet: Anglesea Power Station and Mine Rehabilitation Overview
Fact Sheet: Anglesea Power Station and Mine Rehabilitation Overview After 46 years of operation Alcoa s Anglesea Power Station and Coal Mine was permanently shut down on 31 August 2015. The planning for
More information1 Potential forms of competition Competition can take a number of forms. It is important to distinguish between:
Appendix A What is competition in the urban water sector? At a general level, it is clear that competition in the provision of services can lead to significant benefits. As observed by IPART in its Discussion
More informationMemorandum of Understanding
Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation July 2016 MoU between Sydney Water and NSW Ministry of Health - July 2016 Page 1 of 11 1. Introduction and purpose
More informationin brief corrs Policy What it means for developments in april 2012
corrs in brief april 2012 Delivery of the Strategic Regional Land Use Policy What it means for developments in regional areas The NSW Government has recently released a number of draft plans, policies
More informationGUIDELINES FOR PREPARATION OF MINE CLOSURE PLAN
Preamble : GUIDELINES FOR PREPARATION OF MINE CLOSURE PLAN 1. The Central Government vide Notification No. GSR 329 (E) dated 10.04.2003 and No. GSR 330 (E) dated 10.04.2003 amended the Mineral Concession
More informationAssessment of Environmental Liabilities of Historically Reclaimed Sites
Assessment of Environmental Liabilities of Historically Reclaimed Sites About the BC Oil and Gas Commission The BC Oil and Gas Commission is an independent, single-window regulatory agency with responsibilities
More informationCity of Edmonton Oil and Gas Facilities Policy Review Implementation Plan
City of Edmonton Oil and Gas Facilities Policy Review Implementation Plan Approved by Council January 30, 2008 Table of Contents 1.0 Roles and Responsibilities 1.1.1 Oil and Gas Liaison Officer 1.1.2 Internal
More informationMine Closure & Rehabilitation: From Dereliction to Accountability? Caroline Digby 5 May 2016
Mine Closure & Rehabilitation: From Dereliction to Accountability? Caroline Digby 5 May 2016 Accountability and Responsible Mining Achieve zero harm Realise net positive environmental impact Improve social
More informationJemena Asset Management Pty Ltd Submission - "Review of Victoria's Electricity and Gas Network Safety Framework" - Interim Report - October 2017
Jemena Asset Management Pty Ltd Submission - "Review of Victoria's Electricity and Gas Network Safety Framework" - Interim Report - October 2017 Public 27 November 2017 An appropriate citation for this
More information2008/09 Annual Performance Report Electricity Retailers
2008/09 Annual Performance Report Electricity Retailers February 2010 Important Notice This document has been compiled in good faith by the (the Authority). The document contains information supplied to
More informationThe Board of Finance of Baltimore City Department of Finance Bureau of Treasury Management
The Board of Finance of Baltimore City Department of Finance Bureau of Treasury Management Tax Increment Financing Policy and Project Submission Requirements January 23, 2012 PART I: TAX INCREMENT FINANCING
More information2006/07 Annual Performance Report Electricity Retailers
2006/07 Annual Performance Report Electricity Retailers January 2008 Important Notice This document has been compiled in good faith by the Economic Regulation Authority (the Authority). The document contains
More informationProcedure. Work Health and Safety Contractor Management. Document number: PRO Rev no. Description Process Owner Approved for issue
Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority
More informationMoU2017v1. Memorandum of Understanding between the Department of Health and Water Corporation for Drinking Water
MoU2017v1 Memorandum of Understanding between the Department of Health and Water Corporation for Drinking Water Contents 1.0 Foreword 1 1.1 Design of the MoU 2 2.0 Interpretation 3 3.0 Role of the Department
More informationENVIRONMENTAL CONTAMINATION ORDINANCE
ENVIRONMENTAL CONTAMINATION ORDINANCE AN ORDINANCE ESTABLISHING PUBLIC HEALTH PROTECTION RELATED TO LEAD, CADMIUM, TRICHLORO-ETHYLENE AND OTHER IDENTIFIED CONTAMINANTS SECTION 1. PURPOSE. The purpose of
More informationAUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS
AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS This document is available from the Economic Regulation Authority website www.era.wa.gov.au. For further
More information19 GENETICALLY MODIFIED ORGANISMS
19 GENETICALLY MODIFIED ORGANISMS CONTEXT Genetic modification (GM) refers to a set of techniques that alter genetic makeup by adding, deleting or moving genes (within or between species) to produce new
More informationIndian and Northern Affairs Canada. Affaires indiennes et du Nord Canada MINE SITE RECLAMATION POLICY FOR THE NORTHWEST TERRITORIES
Indian and Northern Affairs Canada Affaires indiennes et du Nord Canada MINE SITE RECLAMATION POLICY FOR THE NORTHWEST TERRITORIES Published under the authority of the Minister of Indian Affairs and Northern
More informationE37. Genetically modified organisms [CIV : Federated Farmers of New Zealand Incorporated]
E37. Genetically modified organisms [CIV-2016-404-002299: Federated Farmers of New Zealand Incorporated] E37.1. Background The outdoor use of genetically modified organisms has the potential to cause adverse
More informationLicence Details Number: 6830 Anniversary Date: 15-February. Licensee ABLE LIQUID WASTE PTY LTD PO BOX 307 LANE COVE NSW 1595
Licence Details Number: 6830 Anniversary Date: 15-February Licensee ABLE LIQUID WASTE PTY LTD PO BOX 307 LANE COVE NSW 1595 Licence Type Transporter of Waste Scheduled Activity Transport of trackable waste
More information5. Contaminated Sites
5. Contaminated Sites 5.1 Issues What is a Contaminated Site? A contaminated site is: A site at which hazardous substances occur at concentrations above background levels and where assessment indicates
More informationDepartment of Environment, Land, Water and Planning Smart Planning Level 5, 1 Spring Street MELBOURNE VIC December 1, 2017
Department of Environment, Land, Water and Planning Smart Planning Level 5, 1 Spring Street MELBOURNE VIC 3000 December 1, 2017 Dear Policy and Strategy Team Discussion paper - Reforming the Victoria Planning
More informationElectricity Supply Agreement
Electricity Supply Agreement 1. General 1.1 Mazoon Electricity Company SAOC (the Supplier) shall on or from the Start Date, subject to the satisfactory completion of a Supply Application Form, provide
More informationMACKENZIE RIVER BASIN BILATERAL WATER MANAGEMENT AGREEMENT. Between the. Government of Alberta. And the. Government of the Northwest Territories
MACKENZIE RIVER BASIN BILATERAL WATER MANAGEMENT AGREEMENT Between the Government of Alberta And the Government of the Northwest Territories 2015-02-23 FINAL Pursuant to the Mackenzie River Basin Transboundary
More informationRegulatory Approach to Maintaining Local Security of Supply in Electricity
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Regulatory Approach to Maintaining Local Security of Supply in Electricity Information Paper Reference: CRU17346 Date Published: 18/12/2017
More informationMINERALS COUNCIL OF AUSTRALIA VICTORIAN DIVISION
H MINERALS COUNCIL OF AUSTRALIA VICTORIAN DIVISION SUBMISSION TO THE INDEPENDENT INQUIRY INTO THE VICTORIAN ENVIRONMENTAL PROTECTION AUTHORITY 30 OCTOBER 2015 TABLE OF CONTENTS 1. EXECUTIVE SUMMARY...
More informationFORESTRY AND LAND MANAGEMENT (SCOTLAND) BILL
FORESTRY AND LAND MANAGEMENT (SCOTLAND) BILL EXPLANATORY NOTES INTRODUCTION 1. As required under Rule 9.3.2A of the Parliament s Standing Orders, these Explanatory Notes are published to accompany the
More informationInquiry into reform of business licensing in Western Australia
Inquiry into reform of business licensing in Western Australia Consultation paper 2: Analytical framework and guideline 19 February 2018 Inquiry into reform of business licensing in Western Australia:
More informationREPUBLIC OF LITHUANIA
REPUBLIC OF LITHUANIA Law on The Management of Radioactive Waste* adopted on 20 May 1999 No. VIII-1190 Chapter I GENERAL PROVISIONS Article 1 Purpose of the Law This Law shall regulate relations of legal
More informationRevised functions for Resource Management Act 1991 decision-makers
RESOURCE LEGISLATION AMENDMENTS 2017 FACT SHEET 2 Revised functions for Resource Management Act 1991 decision-makers This is part of a series of 16 fact sheets that give an overview of recent resource
More informationHOUSE BILL NO. HB0065. Municipal solid waste landfill remediation. Sponsored by: Joint Minerals, Business and Economic Development Interim Committee
0 STATE OF WYOMING LSO-0 HOUSE BILL NO. HB00 Municipal solid waste landfill remediation. Sponsored by: Joint Minerals, Business and Economic Development Interim Committee A BILL for AN ACT relating to
More informationAPEC ENGINEER FRAMEWORK
PART 1 APEC ENGINEER FRAMEWORK 1. Purpose The APEC Engineer Manual provides overall guidance to participating APEC economies for the operation of APEC Engineer Registers. The Manual includes a description
More informationIbstock plc. (the Company) Audit Committee - Terms of Reference
Ibstock plc (the Company) Audit Committee - Terms of Reference 1. PURPOSE 1.1 The role of the Audit Committee (the Committee) is to: monitor the integrity of the financial statements and related announcements
More informationENVIRONMENTAL AND PLANNING REGULATION
ENVIRONMENTAL AND PLANNING REGULATION Chapter 17 Environmental and Planning Regulation The Australian Government and the governments of each Australian state and territory have enacted detailed laws regulating:
More informationAudit report VET Quality Framework
The QCAA uses an exceptions-based model of reporting. This means that the QCAA will only record a comprehensive description of evidence gathered and compliance findings if noncompliance is identified at
More informationENVIRONMENTAL MANAGEMENT STRATEGY
CORAKI QUARRY ENVIRONMENTAL MANAGEMENT STRATEGY Prepared for: Quarry Solutions Pty Ltd Date: November 2017 File Ref: 1837_610_006 R1 Resources Environment Planning Laboratories www.groundwork.com.au Page
More informationAustralian National Report. Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management.
Commonwealth of Australia Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management Australian National Report July 2003 AUSTRALIAN RADIATION PROTECTION
More informationDevolution of Fisheries Administrative Services in New Zealand A Case Study
Devolution of Fisheries Administrative Services in New Zealand A Case Study Russell Burnard, Service Delivery Manager, Ministry of Fisheries, New Zealand Lesley Campbell, General Manager, FishServe, Wellington,
More information(24 July 2015 to date) NATIONAL ENVIRONMENTAL MANAGEMENT: WASTE ACT 59 OF 2008
(24 July 2015 to date) NATIONAL ENVIRONMENTAL MANAGEMENT: WASTE ACT 59 OF 2008 (Gazette No. 32000, Notice No. 278. Commencement date: 1 July 2009 save for sections 28(7)(a), sections 35 to 41 and section
More informationService Standards for Western Power Corporation s South West Interconnected System
Service Standards for Western Power Corporation s South West Interconnected System Report prepared for Economic Regulation Authority Western Australia Contents 1 Executive summary 3 2 Introduction 7 2.1
More informationAS/NZS 4804:2001. Occupational health and safety management systems. General guidelines on principles, systems and supporting techniques
Australian/New Zealand Standard Occupational health and safety management systems General guidelines on principles, systems and supporting techniques This Joint Australian/New Zealand Standard was prepared
More informationMALIN CORPORATION PLC CORPORATE GOVERNANCE GUIDELINES. Adopted on 3 March 2015 and Amended on 26 May 2015
MALIN CORPORATION PLC CORPORATE GOVERNANCE GUIDELINES Adopted on 3 March 2015 and Amended on 26 May 2015 The following Corporate Governance Guidelines (the "Guidelines") and Schedule of Matters reserved
More informationEXTENDED PRODUCER RESPONSIBILITY
EXTENDED PRODUCER RESPONSIBILITY POLICY STATEMENT 29 June 2005 A new approach to waste reduction The Government is committed to a more sustainable future for Western Australia and to a new approach towards
More informationCOAL AND COAL SEAM GAS REGULATION
COAL AND COAL SEAM GAS REGULATION The Australian Government protects water resources from the impacts of coal and coal seam gas development through the water trigger provisions of the Environment Protection
More informationTNT Pallet and Equipment Policy Sept 2016
1. Definitions: Approved Status has the meaning defined in Clause 3.2 Bulk Shipment means a Shipment consigned to TNT where: all items comprising the Shipment are to be delivered to the same receiver;
More informationENVIRONMENTAL APPROVALS
SOUTH AUSTRALIAN MINING ACT (1971) ENVIRONMENTAL APPROVALS Prominent Hill Copper Gold Mine, 2011 Erik Lock Principal i Mining i Assessment Officer DMITRE Outline Honeymoon Uranium Mine, 2011 Regulatory
More informationMANAGING TRADE WASTE WHAT SHOULD BEST PRACTICE LOOK LIKE? Rosemary Bissett. City West Water
MANAGING TRADE WASTE WHAT SHOULD BEST PRACTICE LOOK LIKE? Paper Presented by: Rosemary Bissett Authors: Rosemary Bissett, Manager Environmental Strategy & Services, Keith Green, General Manager Service
More informationDo Australian Clean Up Projects Currently Accord with the Concept of Sustainable Remediation?
Do Australian Clean Up Projects Currently Accord with the Concept of Sustainable Remediation? Peter Nadebaum Australasian Land and Groundwater Association SuRF Australia, CRC CARE, GHD Pty Ltd Clean Up
More informationPART H: Management systems
PART H: Management systems 8. Iluka EHSMS 8.1 Introduction Iluka has an Environment, Health and Safety Management System (EHSMS) made up of various standards, guidelines and forms. The key elements of
More informationExplosives Regulation in Australia
Submission September 2015 Explosives Regulation in Australia Discussion Paper and Consultation Regulation Impact Statement Contact Adrienne LaBombard a.labombard@cmewa.com The Chamber of Minerals and Energy
More informationSubmission on the Landfill Levy Review
Submission on the Landfill Levy Review Status of this submission This submission has been prepared through the Municipal Waste Advisory Council (MWAC) for the Western Australian Local Government Association
More informationCOAG DECISION REGULATION IMPACT STATEMENT
COAG DECISION REGULATION IMPACT STATEMENT PROPOSAL FOR NATIONAL LICENSING OF THE REFRIGERATION AND AIR-CONDITIONING OCCUPATIONS QUEENSLAND CONSULTATION This document highlights some of the key differences
More information(B) "Facility," for the purposes of this rule, means:
3745-27-13 Procedure to engage in filling, grading, excavating, building, drilling, or mining on land where a hazardous waste facility or solid waste facility was operated. (A) No person shall, without
More informationLEPs and SEPPs. Planning, Development & Heritage. Local environmental plans (LEPs) Last updated: January 2013
Planning, Development & Heritage LEPs and SEPPs Last updated: January 2013 These Fact Sheets are a guide only and are no substitute for legal advice. To request free initial legal advice on an environmental
More informationBryah Secures Option over Historic Manganese Mine
ASX Announcement 7 May 2018 Bryah Secures Option over Historic Manganese Mine HIGHLIGHTS Bryah Resources secures exclusive 1 year option to purchase Mining Lease covering the historical Horseshoe South
More informationApplication of the Actual Costs Saved and Avoided Costs Saved Standards
12 April 2005 374895 FINAL THE COMMISSION S VIEW ON THE ACTUAL COSTS SAVED AND AVOIDED COSTS SAVED STANDARDS: APPLICATION OF THE FINAL PRICING PRINCIPLE FOR RESALE OF TELECOM RETAIL SERVICES Executive
More informationVirgin Australia Board Charter and Statement of Delegated Authority
Virgin Australia Board Charter and Statement of Delegated Authority 1. Purpose The purpose of this policy statement is to establish an appropriate, practicable and consistent framework of control for the
More informationIAP the road forward // Intelligent Access Program Overview Guideline
IAP the road forward // Intelligent Access Program Overview Guideline IAP the road forward // Intelligent Access Program Overview Guideline TCA-G01-2.00 First published November 2005 Transport Certification
More information6 November Dear Ms Armytage RE: INDEPENDENT INQUIRY INTO THE EPA
6 November 2015 Ms Penny Armytage CHAIRPERSON Ministerial Advisory Committee PO BOX 21428 Little Lonsdale Street MELBOURNE VIC 8011 info@epa-inquiry.vic.gov.au Dear Ms Armytage RE: INDEPENDENT INQUIRY
More information(The Ohio Estate Law Blog (Kohrman, Jackson, & Krantz)
Tax Increment Financing (TIF), An Overview (The Ohio Estate Law Blog (Kohrman, Jackson, & Krantz) www.ohiorelaw.com/2008/07/tax-increment-financing-tif-overview.html) Special thanks to Matthew Galan, a
More informationChain of Responsibility
INFORMATION BULLETIN INTRODUCTION This bulletin provides information on the pioneering chain of responsibility laws being progressed by the National Road Transport Commission in conjunction with the road
More informationEnvironmental Management Plan Introduction Environmental Management Objectives Structure, Implementation and Review
Environmental Management Plan Introduction This Environmental Management Plan (EMP) has been prepared for SEF Energy Co. Ltd. for the purpose of providing a stand-alone plan for managing the potential
More information