Implementation Status & Results Morocco MA-Modernization of Irrigated Agriculture in the Oum Er Rbia Basin (P093719)

Size: px
Start display at page:

Download "Implementation Status & Results Morocco MA-Modernization of Irrigated Agriculture in the Oum Er Rbia Basin (P093719)"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Morocco MA-Modernization of Irrigated Agriculture in the Oum Er Rbia Basin (P093719) Operation Name: MA-Modernization of Irrigated Agriculture in the Oum Er Rbia Project Stage: Implementation Seq.No: 9 Status: ARCHIVED Archive : 19-Aug-2014 Basin (P093719) Country: Morocco Approval FY: 2010 Product Line: IBRD/IDA Region: MIDDLE EAST AND NORTH AFRICA Lending Instrument: Specific Investment Loan Implementing Agency(ies): ORMVA Doukkala, DIAEA, ORMVA Haouz, ORMVA Tadla Key s Board Approval 27-May-2010 Original Closing Planned Mid Term Review 06-Oct-2014 Last Archived ISR 07-Mar-2014 Effectiveness 13-Sep-2010 Revised Closing Actual Mid Term Review Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objective is for participating farmers in the Oum Er Rbia basin to increase the productivity and to promote more sustainable use of irrigation water to overcome current and future water deficits. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) losure Authorized Public Disclosure Authorized Component Name Component Cost Improving the Water Service Supporting farmers 4.45 Supporting Implementing Agencies 5.00 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Implementation Status Overview In the first semester of 2014, project implementation progress has remained satisfactory. The project is on track to meet its development objective before its closing date. As of April 30, 2014, combined technical and financial ratios, as recorded in the M&E system, show overall implementation ratios of 50% for Haouz, 43% for Doukkala and 70% for Tadla. Payment levels have sharply increased. As of April 30, 2014, they reached 43% of commitment levels in Haouz, 30% for Doukkala and 55% for Tadla. Page 1 of 6

2 Progress for the construction of the network infrastructure (Component 1 of the project) is satisfactory. The provision of drip irrigation service could start in September 2014 in two sectors of Tadla and one sector in Doukkala. Implementation of remaining works in other sectors is on track. Last contracts to be procured for works and equipment of remaining sectors are being launched, essentially irrigation outlets construction and connection pipes and equipment. The implementation of activities under component 2, which consists in supporting the implementation agencies support farmers for access to new technologies, markets and financing, has progressed significantly. The relevant TA in each irrigation perimeter focus on supporting farmers in maturing their farming project, encouraging them to structure themselves in associations and to help them prepare the necessary documents to obtain the subsidies from the Fond de Développement Agricole to equip their land with the onfarm irrigation systems. All efforts are being made to minimize the time lag between the date the pressure irrigation networks can be put into operations and the time when farmers can receive the on-farm drip irrigation equipment and convert into drip irrigation, while ensuring that the farmers associations are in the driver's seat of all that concern farm strategy and equipment purchasing. The implementation of activities under Component 3 needs special attention. Environmental baselines have been completed. Environmental monitoring and aquifer water abstraction information gathering is now a high priority, especially in sectors where the modernized irrigation service provision is soon expected to start. Monitoring and evaluation and financial monitoring systems established are operational and give valuable information on the physical and financial progress under the project. With respect to the financial situation, overall Loan disbursement levels in April 2014 reached 42.5% of the loan amount. All implementing agencies have brought or maintained the percentage of disbursement close to the maximum percentage of payments. Nevertheless, an effort needs to be made to accelerate invoice receipt and payment, in order to bring payment levels closer to physical implementation levels. Locations Country First Administrative Division Location Planned Actual Morocco Not Entered Safi Morocco Not Entered Kelaa-Des-Sraghna Morocco Not Entered El-Jadida Morocco Not Entered Beni-Mellal Morocco Not Entered Azilal Morocco Not Entered Marrakech Morocco Not Entered Al-Haouz Results Project Development Objective Indicators Page 2 of 6

3 Indicator Name Core Unit of Measure Baseline Current End Target Water productivity per cubic meter of irrigation Amount(USD) Value water delivered- Average Doukkala-Haouz- 31-Aug-2009 Tadla put into service. Too early to call Water productivity per cubic meter of irrigation Amount(USD) Value water consumed. Average Doukkala-Haouz- 31-Aug-2007 Tadla put into service. Too early to call Reduction in % of the volume of groundwater Percentage Value abstracted. Average Haouz-Tadla 31-Aug Jun-2011 until the groundwater monitoring system is in place. Reduction in % of the volume of groundwater Percentage Value consumed. Average Haouz-Tadla 31-Aug-2007 until the groundwater monitoring system is in place. Agricultural production increase per farm (in Percentage Value %). Average Doukkala-Haouz-Tadla 31-Aug-2009 put into service. Too early to call Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Percentage of participating farmers using drip Percentage Value irrigation. Average Doukkala-Haouz-Tadla 31-Dec-2009 put into service. Page 3 of 6

4 Percentage of project area equipped with drip irrigation. Average Doukkala-Haouz-Tadla Area in hectares of high value-added in project area. Total Doukkala-Haouz-Tadla Number of partnership projects with agribusiness. Total Doukkala-Haouz-Tadla installed (output indicator used during the period of infrastructure construction) Combined technical and financial progress in Tadla (output indicator used during the period of infrastructure construction) Combined technical and financial progress in Doukkala (output indicator used during the period of infrastructure construction) Combined technical and financial progress in Haouz (output indicator used during the period of infrastructure construction) installed in Haouz (output indicator used during the period of infrastructure construction) Percentage Value Dec-2009 put into service. Number Value Aug-2009 Number Value Dec-2009 Information on project areas. Too early to call as modernized irrigation is not in service. Number Value Jan Jun-2014 Overall 87% of the set End Target, 74.7% if considering the additional 90km above the set target in Tadla. Percentage Value Supplemental Percentage Supplemental Percentage Supplemental Number Breakdown Value Value Value Jan % of the End Target, as recorded in the project M&E system 30-Jun-2015 Completion date adjusted based on actual implementation plan Page 4 of 6

5 installed in Doukkala (output indicator used during the period of infrastructure construction) installed in Tadla (output indicator used during the period of infrastructure construction) Number Breakdown Number Breakdown Value Jan % of the End Target, as recorded in the project M&E system 28-Feb-2015 Completion date adjusted based on actual implementation plan Value Jan Jun-2014 Target set exceeded, including connecting pipes to irrigation outlets. Only about 15km remain to be laid in "Annour" area Data on Financial Performance (as of 14-Jul-2014) Financial Agreement(s) Key s Project Ln/Cr/Tf Status Approval Signing Effectiveness Original Closing Revised Closing P IBRD Effective 27-May Jun Sep-2010 P TF Closed 02-Mar Mar Mar Aug Jun-2013 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P IBRD Effective USD P TF Closed USD Disbursement Graph Page 5 of 6

6 Key Decisions Regarding Implementation The majority of the actions agreed during the last mission were met. A revised was action plan was set with explicit deadlines for each agreed measure. It will be monitored by the project coordination and by the World Bank through regular communication. Restructuring History Level two Approved on 11-May-2012 Related Projects P MA-Modernization of Irrigated Agriculture in the Oum Er Rbia Basin AF Page 6 of 6