Southwest LRT Management Committee. April 27, 2011
|
|
- Gyles Ramsey
- 5 years ago
- Views:
Transcription
1 Southwest LRT Management Committee April 27, 2011
2 Today s Topics PE/DEIS Status Update Engineering Services Contract Park & Ride Guidelines Cash Flow Needs for Project Office Startup 2
3 PE/DEIS Status Update 3
4 SWLRT Independent Project 4
5 Interchange Independent Project 5
6 Recent Discussions with FTA FTA questioning independent utility March 31 Interchange letter to FTA April 13 SWLRT letter to FTA 6
7 Engineering Services Contract 7
8 Scope of Work Project Management Support Preliminary Engineering Final Design Design Support During Construction 8
9 RFP Development Process Identify Stakeholders Key Technical Issues Complete Scope of Work Assemble Draft RFP Review Draft RFP with Evaluation Panel & Technical Advisors Finalize RFP based on Input 9
10 Engineering Services Evaluation & Recommendation Evaluation Panel Project Office Light Rail Operations Mn/DOT Hennepin County Community Works Technical Advisors Project Office Light Rail Operations Cities 10
11 Tentative Schedule May Key Issues Meetings with Mn/DOT, County, Cities June Review and Comment, & Finalize RFP July Advertise RFP * Contingent upon FTA approval to enter PE by July 1 st 11
12 Park & Ride Guidelines 12
13 Project Office Community Works Southwest LRT Project Office Led by the Council Oversee & Coordinate the LRT Project Planning, Design and Construction Southwest LRT Community Works Led by the County Create Shared Vision & Implementation Strategy Station Area Development & Corridor-Wide Issues 13
14 Project Office Community Works Collaboration SWPO and SWCW will work closely with stakeholders, both independently and in conjunction. Access & Parking Subcommittee To provide formalized input/guidance to the SWPO To ensure that decisions on park-and-ride are integrated with land use/development decisions To ensure that enough parking is provided to support the project To ensure that the parking be sited and/or managed in a manner that supports TOD at station sites 14
15 Twin Cities Regional Travel Demand Model Federally Compliant Approach Tool to Assist Decision-Makers 4-Step Process Trip Generation Trip Distribution Mode Choice Trip Assignment 3,500 spaces spread across 15 of 17 SWLRT stations 15
16 16
17 2030 Park-and-Ride Plan Park-and-Ride Demand Model Methodology Validation Transitways vs. Express Bus Site Selection & Design Criteria 17
18 Lessons Learned: Proximity Ft. Snelling Station (HLRT) 95 th Avenue Park & Ride (Bus) 28 th Ave Station (HLRT) Walkway roughly 370 ft 18
19 Lessons Learned: Spillover Effect Lake St/Midtown Station (HLRT) Apple Valley Transit Station (Bus) 19
20 Lessons Learned: Hide & Ride I-94 & Snelling Ave (Bus) 50 th St Station (HLRT) 20
21 Cash Flow Needs for Project Office 21
22 Pre-PE (May 2010 thru Present) Total Committed Funding for Pre-PE: 338k $138,000 $138,000 FTA 5339 RTC $200,000 Staff Program Director Project Director Senior Project Manager Executive Assistant Intern Tasks Request Entry into PE Submittal Pre-PE Risk Assessment Project Financing Stakeholder Outreach Interim Project Office Formation 22
23 Second Half of 2011 $4,000,000 $3,000,000 $2,000,000 $1,000,000 Recruitment of Deputy Director, 2 Assistant Directors, Transit System Design & Engineering Director, Design Engineer Beginning of Engineering Services Activities Beginning of Environmental Services Activities Establishment of a Permanent Project Office Location $0 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 23
24 First Half of 2012 Continuation of Engineering Services Activities Continuation of Environmental Services Consultant Activities $4,000,000 $3,000,000 $2,000,000 $1,000,000 $0 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 24
25 More Information Mark Fuhrmann, Program Director New Starts Rail Projects Chris Weyer, Project Director - Southwest LRT chris.weyer@metc.state.mn.us 25