Program Evaluation and Review Technique (PERT)

Size: px
Start display at page:

Download "Program Evaluation and Review Technique (PERT)"

Transcription

1 Program Evaluation and Review Technique (PERT)

2 PERT Bar charts and CPM networks assume all activity durations are constant or deterministic. The assumption of constant durations may not be realistic because of working conditions. To address the variability of project activities, the Program Evaluation and Review Technique (PERT) was developed. PERT incorporates uncertainty into the project by assuming that the activity durations of some or all of the project activities are variable.

3 PERT Three time estimates are required to compute the parameters of an activity s duration distribution: pessimistic time (t b ) - the time the activity would take if things did not go well most likely time (t m ) - the consensus best estimate of the activity s duration optimistic time (t a ) - the time the activity would take if things did go well Mean (expected time): t e = Variance: V t =δ 2 = t a + 4 t m + t b 6 t b - t a 6 2 Where, t b is the expected duration T b is the most optimistic duration estimate t m is the most likely duration estimate T a is the most pessimistic duration estimate

4 PERT Chart may look like

5 Draw the network PERT ANALYSIS Use PERT formula to calculate the expected duration for each activity of the project Analyze the paths through the network and find the critical path The length of the critical path is the mean of the project duration probability distribution, It follows a normal distribution The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum Probability computations can now be made using the normal distribution

6 Probability computation Determine probability that project is completed within specified time Z = - N where = t p = project mean time = project standard mean time N = (proposed ) specified time

7 Normal Distribution of Project Time Probability Z = t p x Time

8 PERT Example Activity t m t o t b Mean Variance Path 1 = Activity 1,4,8 Mean = 17.5 Variance=3.7 Path 2 = Activity 1,5,6 Mean = 16.5 Variance=3.6 Path 3 = Activity 1,5,7,9 Mean = 17.5 Variance=5.4 Path 4 = Activity 2,6 Mean = 16.0 Variance=2.8 Path 5 = Activity 3,9 Mean = 17.0 Variance=

9 What is the probability that the project can be completed in N days? Z = - N

10

11 Benefits of CPM/PERT Useful at many stages of project management Mathematically simple Give critical path and slack time Provide project documentation Useful in monitoring costs CPM/PERT can answer the following important questions: How long will the entire project take to be completed? What are the risks involved? Which are the critical activities or tasks in the project which could delay the entire project if they were not completed on time? Is the project on schedule, behind schedule or ahead of schedule? If the project has to be finished earlier than planned, what is the best way to do this at the least cost?

12 Limitations to PERT PERT assumes statistically independence between activities. This may not be appropriate PERT consistently underestimates the expected project completion time due to alternate paths becoming critical. The principal cause of this underestimation is a condition known as merge event bias PERT results are too optimistic To overcome the limitation, Monte Carlo simulations can be performed on the network to eliminate the optimistic bias

13 GANTT CHART vs PERT CHART

14 GANTT CHART vs PERT CHART GANTT chart visually shows the duration of Tasks whereas a PERT chart visually shows the sequence dependencies between tasks. GANTT visually shows the Time overlap of Tasks whereas a Network does not show time overlap but does show which tasks could be done in parallel. Some form of GANTT chart can visually show Slack Time available within an Earliest Start and Latest finish time. Most Project Managers find PERT very helpful for scheduling, monitoring and controlling Projects. PERT is recommended for Large Projects with high inter-task dependencies and the GANTT chart for simpler Projects. Most Project Management Case Tools nowadays (eg. MS-Project, Primavera ) allow the best feature of PERT to be incorporated into GANTT Charts.

15 Line of Balance Method

16 Line of Balance Method (LOB) A graphical method for production control integrating bar chart and production curve concepts. This is most suited and efficient for linear constructions and repetitive activities LOB focuses on the planned versus actual progress for individual activities and provides a visual display depicting their difference. LOB enables management to provide accurate control by prioritizing reallocation of resources. This assumes resources are interchangeable

17 Linear Construction Operations Often construction sites have linear properties that influence the production sequence. A road job may be subdivided into many sections. A set of work processes need to be completed in a particular sequence before a section is completed: (1) rough grading, (2) finish grading, (3) aggregate base installation, (4) 5-in.concrete pavement, (5) 9-in. concrete pavement, and (6) curb installation.

18 Linear Construction Operations Each of the 14 sections can be thought of as being processed by crews and equipment representing each of the six work processes. Work is proceeded from section 1, section 2,, to section 14. The six work processes are carried out in sequence. There are work activity overlaps such that several operations are in progress simultaneously during the middle of the job.

19 Many types of projects exhibit a kind of rigid work sequence and have a train effect. High-rise building Each floor has to pass a set of operations: erect formwork, install reinforcing steel and pure concrete. Tunnel Drill, blast, remove muck, and advance drilling shield..

20 There are four Elements of LOB 1. The objective chart 2. The program chart 3. The progress chart 4. The comparison Elements of LOB Objective chart A segmental curve showing cumulative end products to be produced over a calendar time period. Objective chart

21 Program Chart It is a flow process chart of all major activities, illustrating their planned, sequenced interrelationships on a lead-time basis. Three Aspects to Consider in Developing Program Chart (1) Operations to be performed (2) Sequence of operations (3) Processing and assembly lead time

22 Progress Chart Progress chart indicates the cumulative progress or status of actual performance at each monitoring point.

23 Comparison of Actual Progress and Expected Progress

24 LOB Applied to Construction A road project has 40 same sections and each section has 8 activities. Suppose they are balance production. Each week has 40 working hours. The production curve and the lead time are shown as follows. Calculate the LOB values (completed sections) of each control points at the beginning of fifth week. Sections A B C D E F G H hr 14hr 4hr 6hr 16hr 2hr 8hr 8hr Lead time Weeks Hours Production curve

25 40 Planned Progress Chart A B C D E F G H Activity Answer: LOB(1)= LOB(2)= LOB(3)= LOB(4)= LOB(5)= LOB(6)= LOB(7)= LOB(8)= LOB(9)= Section = 20 sections = 21.6 sections 20 = 23.2 sections = 23.6 sections = 26.8 sections 10 = 28 sections = 28.6 sections 0 = 30.7 sections = 31 sections A B C D E F G H Activity Comparative Progress Chart

26 Scheduling with Computer Software

27 Introduction to Computer software Project planning and scheduling are key factors to completing a construction project within budget, on time and with few problems The most efficient way to develop a construction schedule is to use computer programs Computer programs also proved useful in resource allocation. The lesson learned from previous projects could also be stored in historical files. This improved future planning as well as estimating process A wide variety of affordable project management software packages are available for purchase. These packages allow the project manager and project team to plan and control projects in a completely interactive mode.

28 Common features of project management software Create lists of tasks with their estimated durations Establish interdependencies among tasks Work with a variety of time scales, including hours, days, weeks, months, and years Handle certain constrains Track team members, including their pay rates, hours worked thus far on project and upcoming vacation dates Incorporate company holidays, weekends, and team members vacation days into calendaring systems Handle shifts of workers (day, evening, night) Monitor and forecast budgets

29 Common features of project management software Look for conflicts; for example, resource over allocated and time conflicts Generate a wide variety of reports Interface with other software packages such as spread sheets and database Sort information in a variety of ways; for example, by project, by team member, or by work package Handle multiple projects Work on-line and respond quickly to changes in schedule, budget, or personnel Compare actual costs with budgeted costs Display data in a variety of ways, including both Gantt charts and network diagrams

30 Computer Software for Project Management Various computer programs have been established so far with regard to preparing schedules: Microsoft Project Mac Project Power Project Primavera Project Planner Project Scheduler Project Workbench (Microsoft Corp.) (Claris Corp.) (ASTA Development Inc.) (Primavera) (Scitor Corp.) (ABT Corp.) However, out of which Microsoft project and Primavera Project Planner are two popular software programs used in construction industry.

31 Benefits of using project management software Organizing the plan and thinking through the details of what must be done Scheduling deadlines that must be met Scheduling the tasks in the appropriate sequence Assigning resources and costs to tasks and scheduling tasks around resource availability Fine-turning the plan to satisfy time and budget constraint or to accommodate changes Preparing professional looking reports to explain the project to owners, top management, supervisors, workers, subcontractors and the public.

32 Limitations of using project management software Although scheduling software packages have supported resource-loading activities for sometime, they still require manual input of resource information and do not represent the reasons behind the selection of a particular crew and crew size In most cases, computer programs give adequate solutions; however, when resource requirements exceed the resources available, the computer programs do not provide the optimum scheduling solutions.

33

34 Activity Codes Calendars

35 Activity Bar Activity ID Activity Description Activity codes Screen Layout of Project SNP1 in Primavera Project Planner 3.1

36 Relationship between Activities

37 Bar Chart

38 Data for Each Activity in The Project

39 Table of Resources Needed in The Project

40 Layout for Project Reporting

41 PERT or PDM View

42 Graph of Resources which Needed in This Project

43

44 Screen Layout of MS Project

45 Relationship between Activities

46 Assigning Resources Needed in The Project

47 Layout of network diagram

48

Chapter 3 Managing the Information Systems Project

Chapter 3 Managing the Information Systems Project Princess Noura University Computer Science and Information Faculty Information Systems Department IS321 Chapter 3 Managing the Information Systems Project Learning Objectives Discuss skills required to

More information

Cambridge International AS & A Level Computer Science

Cambridge International AS & A Level Computer Science Topic Support Guide Cambridge International AS & A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains

More information

Project Time Management

Project Time Management Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use

More information

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish International Campus Kish Sharif University of Technology Session#11 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

Estimating Project Schedule-Time and Cost

Estimating Project Schedule-Time and Cost Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities

More information

Topic # 12. CIS Project Management: an overview

Topic # 12. CIS Project Management: an overview Topic # 12 CIS Project Management: an overview Project Planning Major Activities during Project Planning: 1) describing project scope, alternatives, and feasibility; 2) dividing the project into manageable

More information

December 25, 2017 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE

December 25, 2017 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE December 25, 17 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE Chapter Outline 4.1 Background What was the cause of the desperation that lead to the development of the Program Evaluation and

More information

Managing Projects (Course Code: 5927A) Course length: 3 days

Managing Projects (Course Code: 5927A) Course length: 3 days Managing Projects (Course Code: 5927A) Course length: 3 days Course Summary: This three-day instructor-led course provides students with the knowledge and skills to build, maintain, and control well-formed

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

Microsoft Office Project 2007, Managing Projects

Microsoft Office Project 2007, Managing Projects Microsoft Office Project 2007, Managing Projects Course 5927A: Three days; Instructor-Led Introduction Elements of this syllabus are subject to change. This three-day instructor-led course provides students

More information

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain: Project Management Dr. Richard Jerz 1 Learning Objectives Describe or Explain: What are projects The role of the project manager Work breakdown structure Project management tools (Gantt, PERT, & CPM) The

More information

IST 302 : Project Time Management

IST 302 : Project Time Management IST 302 : Project Time Management Developing quality schedules is important. 1 Schedule issues are the main reason for conflicts on projects There are five core project time management process groups.

More information

Test your Understanding-The Answers

Test your Understanding-The Answers Table of Contents Module 1 Project management methodology... 2 A. Introduction to Project Management... 2 B. The Phases of Project Management... 2 C. Project Management Methodology questions... 2 Module

More information

2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline -

2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline - 2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline - PREPARED BY: Jake Lilley, PMP President PPM Global Services, Inc. P: 1-800-746-4029 F: 1-800-746-4029 E: jlilley@ppmglobalservices.com

More information

White Paper Using S-Curves to improve Project Performance

White Paper Using S-Curves to improve Project Performance White Paper Using S-Curves to improve Project Performance Ever increasing pressure on businesses to deliver projects on time and to budget means that accurate monitoring of progress, resources and costs

More information

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT Course Outline TEC D 205 Engineering Tech Project Planning Week 1 Chapter 4: DEFINING THE PROJECT 1. Step one: Defining the Project Scope A. Employing a Project Scope Checklist 1. Project objective 2.

More information

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM)

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) Content Writer/Author: Email id: Mrs. RENU ARORA renu214@gmail.com Structure of Module/Syllabus of module(define

More information

Risk Management User Guide

Risk Management User Guide Risk Management User Guide Version 17 December 2017 Contents About This Guide... 5 Risk Overview... 5 Creating Projects for Risk Management... 5 Project Templates Overview... 5 Add a Project Template...

More information

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4. Exam Code:74-343 Number: 74-343 Passing Score: 800 Time Limit: 120 min File Version: 35.4 http://www.gratisexam.com/ Exam Code:74-343 Exam Name:Managing Projects with Microsoft Project 2013 Testinside

More information

Microsoft Office Project 2010 Basic Course 01: Getting Started

Microsoft Office Project 2010 Basic Course 01: Getting Started Microsoft Office Project 2010 Basic Course 01: Getting Started Slide 1 Topic A Project Management Concepts Slide 2 Project Constraints Slide 3 Phases of Project Management The initial Phase Initiating

More information

3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline -

3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline - 3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline - PREPARED BY: Jessica Summers Virtual Training Coordinator PPM Global Services, Inc. P: 1-800-746-4029 x 310 F: 1-800-746-4029 E:

More information

Guten Tag. (good day)

Guten Tag. (good day) Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources

More information

CHAPTER 1. Basic Concepts on Planning and Scheduling

CHAPTER 1. Basic Concepts on Planning and Scheduling CHAPTER 1 Basic Concepts on Planning and Scheduling Eugénio Oliveira Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the and ordering of activities as well

More information

PMI Scheduling Professional (PMI-SP)

PMI Scheduling Professional (PMI-SP) PMI Scheduling Professional (PMI-SP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute PMI Scheduling Professional (PMI-SP) Exam Content Outline Published by: Project Management

More information

Planning & Scheduling

Planning & Scheduling Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1 Planning Successful Project Management depends on continues planning. The activities of Designers,

More information

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Charlie Jackson, PSP, Primavera Certified Trainer Hill International Construction CPM Conference

More information

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text.

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text. Construction Planning ISBN 978-0-7277-6057-9 ICE Publishing: All rights reserved http://dx.doi.org/10.1680/cp2e.60579.191 Index Page locators in italics and bold respectively refer to figures and tables

More information

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4. Exam Code:74-343 Number: 74-343 Passing Score: 800 Time Limit: 120 min File Version: 35.4 http://www.gratisexam.com/ Exam Code:74-343 Exam Name:Managing Projects with Microsoft Project 2013 Examsoon QUESTION

More information

Planning & Scheduling CSTM 102

Planning & Scheduling CSTM 102 Planning & Scheduling CSTM 102 Items Big A Project on Website Thursday Discuss Big A Project next Tuesday April 18, 2011 CPM Scheduling You were the successful bidder! What s next? Procurement/Buy

More information

Deswik.Sched Gantt Chart Scheduling

Deswik.Sched Gantt Chart Scheduling Deswik.Sched Gantt Chart Scheduling SCHEDULING SOLUTIONS THAT SET US APART A dynamic, modern approach to scheduling From interactive Gantt charts to PERT network diagrams, Deswik.Sched is tailored for

More information

Scott M. Francis, P.E., PSP

Scott M. Francis, P.E., PSP Scott M. Francis, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Scott M. Francis,

More information

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents Project Planning, Scheduling and Preparation of Quality Assurance Control Documents J.SHARANYASREENIVAS 1, G.GAJALAKSHMI 2, K.RAVI THEJA 3 1P.G Student M.Tech (Structural Engg. and construction managment),

More information

Review: Simple schedule risk modelling with Safran Risk

Review: Simple schedule risk modelling with Safran Risk Creating value from uncertainty Broadleaf Capital International Pty Ltd ABN 24 054 021 117 www.broadleaf.com.au Review: Simple schedule risk modelling with Safran Risk With a view to exploring alternative

More information

Understanding Import & Export with NetPoint 4.2

Understanding Import & Export with NetPoint 4.2 Understanding Import & Export with NetPoint 4.2 Eric Lowther PMA Consultants 1 Primary Differences Regarding Import/ Export CPM Tools F9 and Early/Late Dates Float & Total Float Gantt Charts (Waterfall

More information

Project Planning and Estimating DJ

Project Planning and Estimating DJ Project Planning and Estimating DJ201 0807 Copyright ESI International August 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any

More information

P6 Instructors Sample Presentation

P6 Instructors Sample Presentation Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 to 8.4 Professional and Optional Client 3 day training course PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration Evacuation

More information

Best Practices in Procurement & Contract Management

Best Practices in Procurement & Contract Management Best Practices in Procurement & Contract Management Definition: Contract Administration The term is to describe the management functions that are performed after the contract has been signed to assure

More information

Developing and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director,

Developing and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director, Developing and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director, Risk Integration Management Pty Ltd Presentation Outline

More information

Project Planning and Control Using Oracle Primavera P6 : P8.3, 8.4, 15.2

Project Planning and Control Using Oracle Primavera P6 : P8.3, 8.4, 15.2 Primavera Essential Course Contents: 1. Overview Describe the Primavera modules Explain the difference between global and project-specific data Project Portfolio Management Defining the Enterprise Project

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Copyright Eastwood Harris Pty Ltd IMPORTANT POINTS FOR

More information

Primavera P6 R8.3 Professional Fundamentals Training Course Outline

Primavera P6 R8.3 Professional Fundamentals Training Course Outline Course Overview Prescience Technology is an Oracle Platinum Partner and specialist provider of Primavera Services. This Prescience course introduces the user to Oracle Primavera P6 version 8.3 Professional

More information

Primavera Training - P6 Basic Course (102)

Primavera Training - P6 Basic Course (102) Primavera Training - P6 Basic Course (102) This training session provides hands-on training for Primavera s client/server-based solution, leading participants through the entire project life cycle, from

More information

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

PMP Sample Questions  Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope? PMP Sample Questions www.techfaq360.com Click here for 1600+ PMP Questions Question No : 1 Which of the following is an output of Define Scope? A. Accepted deliverables B. Change Requests C. Project document

More information

Business Intelligence, 4e (Sharda/Delen/Turban) Chapter 2 Descriptive Analytics I: Nature of Data, Statistical Modeling, and Visualization

Business Intelligence, 4e (Sharda/Delen/Turban) Chapter 2 Descriptive Analytics I: Nature of Data, Statistical Modeling, and Visualization Business Intelligence, 4e (Sharda/Delen/Turban) Chapter 2 Descriptive Analytics I: Nature of Data, Statistical Modeling, and Visualization 1) One of SiriusXM's challenges was tracking potential customers

More information

Microsoft Project study guide

Microsoft Project study guide Microsoft Project study guide Chap 1 An estimated duration appears with a(n) after the duration. a. pound sign c. question mark b. exclamation point d. red bullet Which of the following tasks in a LAN

More information

Schedule % Complete in Primavera P6

Schedule % Complete in Primavera P6 Schedule % Complete in Primavera P6 Schedule % Complete is one of the many percent completes you have in Primavera P6 and we re going to have a complete look at what it is and how it is calculated. Two

More information

MICROSOFT PROJECT 2010 Level 1

MICROSOFT PROJECT 2010 Level 1 MICROSOFT PROJECT 2010 Level 1 Microsoft Project 2010 Level 1 Contents CONTENTS PREFACE - PROJECT MANAGEMENT BASICS... 5 Project Management Overview... 6 Project Definition Techniques... 7 Project Planning

More information

Project Cost Management

Project Cost Management PMBOK Overview A Guide to the Body of Knowledge (PMBOK), created by the Institute (PMI), is the sum of knowledge within the profession of project management. The complete Body of Knowledge includes proven

More information

Views and Layouts for Program Management

Views and Layouts for Program Management MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted

More information

Project Planning. COSC345 Software Engineering 2016 Slides by Andrew Trotman given by O K

Project Planning. COSC345 Software Engineering 2016 Slides by Andrew Trotman given by O K Project Planning COSC345 Software Engineering 2016 Slides by Andrew Trotman given by O K Overview Assignment: The assignment sheet specifies a minimum Think about what else you should include (the cool

More information

Application of a PERT-Type System and "Crashing" in a Food Service Operation

Application of a PERT-Type System and Crashing in a Food Service Operation Hospitality Review Volume 7 Issue 2 Hospitality Review Volume 7/Issue 2 Article 8 1-1-1989 Application of a PERT-Type System and "Crashing" in a Food Service Operation Glenn A. Leitch Michigan State University,

More information

S O Seminar Objective

S O Seminar Objective Introduction to Project Management Welcome! Presenter: Bob Hull CalACT Conference September 202 S O Seminar Objective To provide an overview of project management processes and provide some skills, tools

More information

Construction Project Scheduling of MK Apartment Using MS Project 2013

Construction Project Scheduling of MK Apartment Using MS Project 2013 Construction Project Scheduling of MK Apartment Using MS Project 2013 Monish Kumar K 1, Maheshwar S Maregoudru 2, Sparsha B.P 3 1,2 PG Student, Dept. of Civil Engineering, KVGCE, Sullia, Karnataka, India

More information

IMPLEMENTATION, EVALUATION & MAINTENANCE OF MIS:

IMPLEMENTATION, EVALUATION & MAINTENANCE OF MIS: IMPLEMENTATION, EVALUATION & MAINTENANCE OF MIS: The design of a management information system may seem to management to be an expensive project, the cost of getting the MIS on line satisfactorily may

More information

SCHEDULE RISK ANALYSIS ESSENTIALS FOR PROJECT SUCCESS

SCHEDULE RISK ANALYSIS ESSENTIALS FOR PROJECT SUCCESS SCHEDULE RISK ANALYSIS ESSENTIALS FOR PROJECT SUCCESS CSVA 2011 Conference Toronto, Ontario Nov 14-16, 2011 Laszlo A. Retfalvi P.Eng PMP PMI-RMP Retfalvi and Associates 1 Agenda of Session Key Take Aways

More information

itaskx 3 Project Management User Manual

itaskx 3 Project Management User Manual itaskx 3 Project Management User Manual GET STARTED Basics Recommended workflow Views in itaskx Adjust project options Set working time for the project-calendar 2 Unit 1 Project management basics Learn

More information

Resource Allocation Optimization in Critical Chain Method

Resource Allocation Optimization in Critical Chain Method Annales UMCS Informatica AI XII, 1 (2012) 17 29 DOI: 10.2478/v10065-012-0006-2 Resource Allocation Optimization in Critical Chain Method Grzegorz Pawiński 1, Krzysztof Sapiecha 1 1 Department of Computer

More information

Project Scheduling and Tracking. CIS 375 Bruce R. Maxim UM-Dearborn

Project Scheduling and Tracking. CIS 375 Bruce R. Maxim UM-Dearborn Project Scheduling and Tracking CIS 375 Bruce R. Maxim UM-Dearborn 1 What does the customer want to know? Do you understand my needs? Can you design a system to help me? How long will it take? How much

More information

Vrije Universiteit Amsterdam Faculty of Exact Sciences. Exam: Software Project Management Version A. Dr. Nelly Condori-Fernandez. Date: May 27, 2015

Vrije Universiteit Amsterdam Faculty of Exact Sciences. Exam: Software Project Management Version A. Dr. Nelly Condori-Fernandez. Date: May 27, 2015 Vrije Universiteit Amsterdam Faculty of Exact Sciences Exam: Software Project Management Version A Code: Coordinator: X_401093 Dr. Nelly Condori-Fernandez Date: May 27, 2015 Duration: Calculator allowed:

More information

Version Comparison. Getting Started Project Planning. Feature Key:

Version Comparison. Getting Started Project Planning. Feature Key: Version Comparison Version Comparison The table below introduces the new features of 2010 and Project. It also shows features initially included in previous versions that have been improved in Project

More information

Project Management Concepts, Tools & Techniques

Project Management Concepts, Tools & Techniques Project Management Concepts, Tools & Techniques Course ISI-1438 5 Days Instructor-led, Hands on Introduction This highly interactive 5 day, instructor-led workshop is designed to give participants a solid

More information

Project Controls Expo 13 th Nov 2013

Project Controls Expo 13 th Nov 2013 Project Controls Expo 13 th Nov 2013 Twickenham Stadium, London From Cost Plan To Bid Evaluation To Contract Administration The Earned Value Project Control Cycle Copyright @ 2011. All rights reserved

More information

Describing DSTs Analytics techniques

Describing DSTs Analytics techniques Describing DSTs Analytics techniques This document presents more detailed notes on the DST process and Analytics techniques 23/03/2015 1 SEAMS Copyright The contents of this document are subject to copyright

More information

Total Questions: 370 MODULE QUIZ ANSWER KEY. Fundamentals 1 & 2

Total Questions: 370 MODULE QUIZ ANSWER KEY. Fundamentals 1 & 2 Fundamentals 1 & 2 1. Answer: B Process Group. Each project management knowledge area is subdivided into specific process group, each of which is characterized by their inputs, tools and techniques, and

More information

MAKE YOUR SCHEDULE REALISTIC BY USING CALENDARS

MAKE YOUR SCHEDULE REALISTIC BY USING CALENDARS 1 MAKE YOUR SCHEDULE REALISTIC BY USING CALENDARS Prakash K P, Director of Project Management, Grade Results, Inc. 2 Learning Objectives At the end of this session, you will be able to do the following

More information

1.Which of the items listed below is not one of the software engineering layers?

1.Which of the items listed below is not one of the software engineering layers? 1.Which of the items listed below is not one of the software engineering layers? Process Manufacturing Methods Tools 2.The software quality assurance activity which is performed to check errors in logic,

More information

Project Risk Analysis (with Pertmaster)

Project Risk Analysis (with Pertmaster) Project Risk Analysis (with Pertmaster) AACE Toronto Section October 2, 2008 Brought to you by: Presenter Ian Nicholson, P.Eng. VP Solutions, Emerald Associates Mechanical Engineer Primavera Systems Authorized

More information

Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A

Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A Deltek Acumen Planning, Risk, Acceleration Tom Polen Director, Solution Architecture Learning Objectives The 5 steps 1. Capturing uncertainty: calibrating the schedule 2. Identifying risk events: accounting

More information

Project Management using MS PROJECT Middle East College Training Unit

Project Management using MS PROJECT Middle East College Training Unit 1 Project Management using MS PROJECT 2013 About the course 1 Microsoft Project training course trains you to plan and manage projects more effectively. Microsoft Project is a project management tool

More information

13 Project Graphics Introduction

13 Project Graphics Introduction Page 725 13 Project Graphics 13.0 Introduction In Chapter 11, we defined the steps involved in establishing a formal program plan with detailed schedules such that the total program can be effectively

More information

PMI-001 Questions & Answers

PMI-001 Questions & Answers PMI-001 Questions & Answers Number: PMI-001 Passing Score: 700 Time Limit: 137 min File Version: 21.2 http://www.gratisexam.com/ PMI-001 Questions & Answers Exam Name: Project Management Professional v5

More information

MS Project Professional 2007 Schedule Leveling: Tips & Tricks. By Lloyd C. Miller III, PMP

MS Project Professional 2007 Schedule Leveling: Tips & Tricks. By Lloyd C. Miller III, PMP MS Project Professional 2007 Schedule Leveling: Tips & Tricks By Lloyd C. Miller III, PMP Agenda What, Where, When & Why Understanding the Options Considering Different Views / Reports Tips & Tricks 2

More information

Project Management Assignment Guidelines Tri 2. Andre Samuel

Project Management Assignment Guidelines Tri 2. Andre Samuel Project Management Assignment Guidelines 2015 16 Tri 2 Andre Samuel Part A General Overview This component requires the use both theoretical (journals, texts) as well as practitioner references in your

More information

Advance Course Managing Mega Project using Microsoft Project 2013

Advance Course Managing Mega Project using Microsoft Project 2013 Applied Technology Group Sdn Bhd (1012178-W) W-5-3, Subang Square Business Centre, Jalan SS15/4G, 47500 Subang Jaya, Selangor, Malaysia. Tel: (+603) 5634 7905 Fax: (+603) 5637 9945 Email: admin@apptechgroups.net

More information

A COMPARISON OF CPM-BAR CHART AND A HIERARCHICAL GRAPHICAL APPROACH TO PLANNING CONSTRUCTION PROCESSES

A COMPARISON OF CPM-BAR CHART AND A HIERARCHICAL GRAPHICAL APPROACH TO PLANNING CONSTRUCTION PROCESSES A COMPARISON OF CPM-BAR CHART AND A HIERARCHICAL GRAPHICAL APPROACH TO PLANNING CONSTRUCTION PROCESSES By COURTNEY K. ZURICH A THESIS PRESENTED TO THE GRADUATE SCHOOL OF THE UNIVERSITY OF FLORIDA IN PARTIAL

More information

Content Break-up & Methodology for awarding Contact Hours / PDUs

Content Break-up & Methodology for awarding Contact Hours / PDUs N.I.T.E - Project Management Professional (PMP) Exam Prep Course Content Break-up & Methodology for awarding Contact Hours / PDUs This course is based on Project Management Book of Knowledge PMBOK Guide

More information

Principles of Schedule Contingency Management

Principles of Schedule Contingency Management Principles of Schedule Contingency Management Ted Douglas, CCC, PSP ACTPMA, LLC Consulting 2014 Construction CPM Conference Orlando, Florida Schedule Contingency Management Background Outline of Presentation

More information

RESOURCE OPTIMIZATION IN CONSTRUCTION OF A RESIDENTIAL APARTMENT USING PRIMAVERA P-6 SOFTWARE

RESOURCE OPTIMIZATION IN CONSTRUCTION OF A RESIDENTIAL APARTMENT USING PRIMAVERA P-6 SOFTWARE RESOURCE OPTIMIZATION IN CONSTRUCTION OF A RESIDENTIAL APARTMENT USING PRIMAVERA P-6 SOFTWARE BHAJANTHRI THIRUMALESHA 1, RAJANI V.AKKI 2,BASAVARAJ BAVI 3 1 P.G. Student, Civil Engineering Department, Shree

More information

Micro Planner X-Pert

Micro Planner X-Pert Micro Planner X-Pert V3.5.1 Overview Presenter: Patrick Weaver PMI-SP Micro Planning International Asia Pacific Cell:+61 418 53 1111 raf@microplanning.com.au. Arrow Diagram Precedence Diagram Working

More information

DEPARTMENT OF MCA CLASS / YEAR : III MCA SUB. CODE & NAME: MC9252, SOFTWARE PROJECT MANAGEMENT. UNIT I 2 MARKS QUESTIONS & ANSWERS 1. What is software project management? Software project management is

More information

The Museum Project. 1. Creating the Project

The Museum Project. 1. Creating the Project 1. Creating the Project The Museum Project You have just come out of a meeting in which you have been given the task to plan and manage a project for the local museum. In the meeting you were told that

More information

MS Project 2007 Overview Table of Contents

MS Project 2007 Overview Table of Contents Table of Contents Microsoft Project Overview... 1 Terminology... 1 Starting Microsoft Project... 2 Projects on the Web... 2 Toolbars... 2 View Bar... 2 Views... 3 Setting Up the Project... 3 Identifying

More information

Project Management Techniques

Project Management Techniques Project Management Techniques CHAPTER C Learning Objectives After reading this chapter, you should be able to: Calculate net present value, payback period, and return on investment Chapter Outline Calculating

More information

Project 2003 Intermediate

Project 2003 Intermediate Microsoft Application Series Project 2003 Intermediate Best STL Courses never cancelled: guaranteed Last minute rescheduling 24 months access to Microsoft trainers 12+ months schedule UK wide delivery

More information

Primaned Belgium. Oracle Primavera P6 Enterprise Project Portfolio Management Data Sheet. Revision Date 04/08/2017

Primaned Belgium. Oracle Primavera P6 Enterprise Project Portfolio Management Data Sheet. Revision Date 04/08/2017 Primaned Belgium Oracle Primavera P6 Enterprise Project Portfolio Data Sheet Revision Date 04/08/2017 Primaned Belgium Uitbreidingstraat 84/3 2600 Berchem, Belgium PRIMAVERA P6 EPPM Oracle Primavera P6

More information

Infor LN Service User Guide for Service Scheduler Workbench

Infor LN Service User Guide for Service Scheduler Workbench Infor LN Service User Guide for Service Scheduler Workbench Copyright 2018 Infor Important Notices The material contained in this publication (including any supplementary information) constitutes and contains

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration

More information

CE 115 Introduction to Civil Engineering Graphics and Data Presentation Application in CE Materials

CE 115 Introduction to Civil Engineering Graphics and Data Presentation Application in CE Materials CE 115 Introduction to Civil Engineering Graphics and Data Presentation Application in CE Materials Dr. Fouad M. Bayomy, PE Professor of Civil Engineering University of Idaho Moscow, ID 83844-1022 Graphics

More information

INDUSTRIAL ENGINEERING

INDUSTRIAL ENGINEERING 1 P a g e AND OPERATION RESEARCH 1 BREAK EVEN ANALYSIS Introduction 5 Costs involved in production 5 Assumptions 5 Break- Even Point 6 Plotting Break even chart 7 Margin of safety 9 Effect of parameters

More information

Common Tool for Intelligent Scheduling / Critical Chain Project Management for US Navy & Contractor Shipyards

Common Tool for Intelligent Scheduling / Critical Chain Project Management for US Navy & Contractor Shipyards Common Tool for Intelligent Scheduling / Critical Chain Project Management for US Navy & Contractor Shipyards Rob Richards, Ph.D. April 20, 2016 Planning, Production Processes & Facilities Panel (PPP&F)

More information

Project Scheduler for Smart Project Management XLGantt User Manual

Project Scheduler for Smart Project Management XLGantt User Manual Project Scheduler for Smart Project Management XLGantt User Manual Version 1.1.0 http://xlworks.net/ Jun 6, 2017 Contents XLGantt Update History -------------------------------------------------------------

More information

SCHEDULING FOR HIGH-RISE BUILDING CONSTRUCTION USING SIMULATION TECHNIQUES

SCHEDULING FOR HIGH-RISE BUILDING CONSTRUCTION USING SIMULATION TECHNIQUES SCHEDULING FOR HIGH-RISE BUILDING CONSTRUCTION USING SIMULATION TECHNIQUES Arthur W T Leung Division of Building Science and Technology, City University of Hong Kong bsawtl@cityu.edu.hk Dr C M Tam Department

More information

Oracle Prime Projects Cloud Service

Oracle Prime Projects Cloud Service Oracle Prime Projects Cloud Service Oracle Prime Projects Cloud Service is a complete, cloud-first success platform for all stages of the project lifecycle. It empowers executives, project managers, and

More information

Initiation Group Process. Planning Group Process

Initiation Group Process. Planning Group Process Initiation Group Process Develop Project Charter Project statement of work Expert judgment Project charter Business case Contract (if third party project) EEF: government/industry standards, organizational

More information

Microsoft Specialist Certification Exam

Microsoft Specialist Certification Exam Microsoft Specialist Certification 74-344 Exam Vendor: Microsoft Exam Code: 74-344 Exam Name: Managing Programs and Projects with Project Server 2013 QUESTION 1 Your organization is performing a Portfolio

More information

Lesson 15-Planning and Costing

Lesson 15-Planning and Costing Lesson 15-Planning and Costing Overview The process of making multimedia. Scheduling. Estimating. RFPs and bid proposals. The Process of Making Multimedia Idea analysis. Pre-testing. Task planning. Development.

More information

Integrated Planning Model (IPM ) Overview

Integrated Planning Model (IPM ) Overview Integrated Planning Model (IPM ) Overview September 2010 Disclaimer This presentation, prepared by ICF under contract with RGGI, Inc., is designed to support ongoing evaluation of state RGGI programs.

More information

Infor ERP LN Project Integration Pack for Microsoft Project

Infor ERP LN Project Integration Pack for Microsoft Project Infor ERP LN 6.1 Projects Infor ERP LN Project Integration Pack for Microsoft Project 98-2000-2002-2003 User s Guide Copyright 2008 Infor All rights reserved. The word and design marks set forth herein

More information