Program Evaluation and Review Technique (PERT)
|
|
- Prosper Wilkins
- 6 years ago
- Views:
Transcription
1 Program Evaluation and Review Technique (PERT)
2 PERT Bar charts and CPM networks assume all activity durations are constant or deterministic. The assumption of constant durations may not be realistic because of working conditions. To address the variability of project activities, the Program Evaluation and Review Technique (PERT) was developed. PERT incorporates uncertainty into the project by assuming that the activity durations of some or all of the project activities are variable.
3 PERT Three time estimates are required to compute the parameters of an activity s duration distribution: pessimistic time (t b ) - the time the activity would take if things did not go well most likely time (t m ) - the consensus best estimate of the activity s duration optimistic time (t a ) - the time the activity would take if things did go well Mean (expected time): t e = Variance: V t =δ 2 = t a + 4 t m + t b 6 t b - t a 6 2 Where, t b is the expected duration T b is the most optimistic duration estimate t m is the most likely duration estimate T a is the most pessimistic duration estimate
4 PERT Chart may look like
5 Draw the network PERT ANALYSIS Use PERT formula to calculate the expected duration for each activity of the project Analyze the paths through the network and find the critical path The length of the critical path is the mean of the project duration probability distribution, It follows a normal distribution The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum Probability computations can now be made using the normal distribution
6 Probability computation Determine probability that project is completed within specified time Z = - N where = t p = project mean time = project standard mean time N = (proposed ) specified time
7 Normal Distribution of Project Time Probability Z = t p x Time
8 PERT Example Activity t m t o t b Mean Variance Path 1 = Activity 1,4,8 Mean = 17.5 Variance=3.7 Path 2 = Activity 1,5,6 Mean = 16.5 Variance=3.6 Path 3 = Activity 1,5,7,9 Mean = 17.5 Variance=5.4 Path 4 = Activity 2,6 Mean = 16.0 Variance=2.8 Path 5 = Activity 3,9 Mean = 17.0 Variance=
9 What is the probability that the project can be completed in N days? Z = - N
10
11 Benefits of CPM/PERT Useful at many stages of project management Mathematically simple Give critical path and slack time Provide project documentation Useful in monitoring costs CPM/PERT can answer the following important questions: How long will the entire project take to be completed? What are the risks involved? Which are the critical activities or tasks in the project which could delay the entire project if they were not completed on time? Is the project on schedule, behind schedule or ahead of schedule? If the project has to be finished earlier than planned, what is the best way to do this at the least cost?
12 Limitations to PERT PERT assumes statistically independence between activities. This may not be appropriate PERT consistently underestimates the expected project completion time due to alternate paths becoming critical. The principal cause of this underestimation is a condition known as merge event bias PERT results are too optimistic To overcome the limitation, Monte Carlo simulations can be performed on the network to eliminate the optimistic bias
13 GANTT CHART vs PERT CHART
14 GANTT CHART vs PERT CHART GANTT chart visually shows the duration of Tasks whereas a PERT chart visually shows the sequence dependencies between tasks. GANTT visually shows the Time overlap of Tasks whereas a Network does not show time overlap but does show which tasks could be done in parallel. Some form of GANTT chart can visually show Slack Time available within an Earliest Start and Latest finish time. Most Project Managers find PERT very helpful for scheduling, monitoring and controlling Projects. PERT is recommended for Large Projects with high inter-task dependencies and the GANTT chart for simpler Projects. Most Project Management Case Tools nowadays (eg. MS-Project, Primavera ) allow the best feature of PERT to be incorporated into GANTT Charts.
15 Line of Balance Method
16 Line of Balance Method (LOB) A graphical method for production control integrating bar chart and production curve concepts. This is most suited and efficient for linear constructions and repetitive activities LOB focuses on the planned versus actual progress for individual activities and provides a visual display depicting their difference. LOB enables management to provide accurate control by prioritizing reallocation of resources. This assumes resources are interchangeable
17 Linear Construction Operations Often construction sites have linear properties that influence the production sequence. A road job may be subdivided into many sections. A set of work processes need to be completed in a particular sequence before a section is completed: (1) rough grading, (2) finish grading, (3) aggregate base installation, (4) 5-in.concrete pavement, (5) 9-in. concrete pavement, and (6) curb installation.
18 Linear Construction Operations Each of the 14 sections can be thought of as being processed by crews and equipment representing each of the six work processes. Work is proceeded from section 1, section 2,, to section 14. The six work processes are carried out in sequence. There are work activity overlaps such that several operations are in progress simultaneously during the middle of the job.
19 Many types of projects exhibit a kind of rigid work sequence and have a train effect. High-rise building Each floor has to pass a set of operations: erect formwork, install reinforcing steel and pure concrete. Tunnel Drill, blast, remove muck, and advance drilling shield..
20 There are four Elements of LOB 1. The objective chart 2. The program chart 3. The progress chart 4. The comparison Elements of LOB Objective chart A segmental curve showing cumulative end products to be produced over a calendar time period. Objective chart
21 Program Chart It is a flow process chart of all major activities, illustrating their planned, sequenced interrelationships on a lead-time basis. Three Aspects to Consider in Developing Program Chart (1) Operations to be performed (2) Sequence of operations (3) Processing and assembly lead time
22 Progress Chart Progress chart indicates the cumulative progress or status of actual performance at each monitoring point.
23 Comparison of Actual Progress and Expected Progress
24 LOB Applied to Construction A road project has 40 same sections and each section has 8 activities. Suppose they are balance production. Each week has 40 working hours. The production curve and the lead time are shown as follows. Calculate the LOB values (completed sections) of each control points at the beginning of fifth week. Sections A B C D E F G H hr 14hr 4hr 6hr 16hr 2hr 8hr 8hr Lead time Weeks Hours Production curve
25 40 Planned Progress Chart A B C D E F G H Activity Answer: LOB(1)= LOB(2)= LOB(3)= LOB(4)= LOB(5)= LOB(6)= LOB(7)= LOB(8)= LOB(9)= Section = 20 sections = 21.6 sections 20 = 23.2 sections = 23.6 sections = 26.8 sections 10 = 28 sections = 28.6 sections 0 = 30.7 sections = 31 sections A B C D E F G H Activity Comparative Progress Chart
26 Scheduling with Computer Software
27 Introduction to Computer software Project planning and scheduling are key factors to completing a construction project within budget, on time and with few problems The most efficient way to develop a construction schedule is to use computer programs Computer programs also proved useful in resource allocation. The lesson learned from previous projects could also be stored in historical files. This improved future planning as well as estimating process A wide variety of affordable project management software packages are available for purchase. These packages allow the project manager and project team to plan and control projects in a completely interactive mode.
28 Common features of project management software Create lists of tasks with their estimated durations Establish interdependencies among tasks Work with a variety of time scales, including hours, days, weeks, months, and years Handle certain constrains Track team members, including their pay rates, hours worked thus far on project and upcoming vacation dates Incorporate company holidays, weekends, and team members vacation days into calendaring systems Handle shifts of workers (day, evening, night) Monitor and forecast budgets
29 Common features of project management software Look for conflicts; for example, resource over allocated and time conflicts Generate a wide variety of reports Interface with other software packages such as spread sheets and database Sort information in a variety of ways; for example, by project, by team member, or by work package Handle multiple projects Work on-line and respond quickly to changes in schedule, budget, or personnel Compare actual costs with budgeted costs Display data in a variety of ways, including both Gantt charts and network diagrams
30 Computer Software for Project Management Various computer programs have been established so far with regard to preparing schedules: Microsoft Project Mac Project Power Project Primavera Project Planner Project Scheduler Project Workbench (Microsoft Corp.) (Claris Corp.) (ASTA Development Inc.) (Primavera) (Scitor Corp.) (ABT Corp.) However, out of which Microsoft project and Primavera Project Planner are two popular software programs used in construction industry.
31 Benefits of using project management software Organizing the plan and thinking through the details of what must be done Scheduling deadlines that must be met Scheduling the tasks in the appropriate sequence Assigning resources and costs to tasks and scheduling tasks around resource availability Fine-turning the plan to satisfy time and budget constraint or to accommodate changes Preparing professional looking reports to explain the project to owners, top management, supervisors, workers, subcontractors and the public.
32 Limitations of using project management software Although scheduling software packages have supported resource-loading activities for sometime, they still require manual input of resource information and do not represent the reasons behind the selection of a particular crew and crew size In most cases, computer programs give adequate solutions; however, when resource requirements exceed the resources available, the computer programs do not provide the optimum scheduling solutions.
33
34 Activity Codes Calendars
35 Activity Bar Activity ID Activity Description Activity codes Screen Layout of Project SNP1 in Primavera Project Planner 3.1
36 Relationship between Activities
37 Bar Chart
38 Data for Each Activity in The Project
39 Table of Resources Needed in The Project
40 Layout for Project Reporting
41 PERT or PDM View
42 Graph of Resources which Needed in This Project
43
44 Screen Layout of MS Project
45 Relationship between Activities
46 Assigning Resources Needed in The Project
47 Layout of network diagram
48
Chapter 3 Managing the Information Systems Project
Princess Noura University Computer Science and Information Faculty Information Systems Department IS321 Chapter 3 Managing the Information Systems Project Learning Objectives Discuss skills required to
More informationCambridge International AS & A Level Computer Science
Topic Support Guide Cambridge International AS & A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
More informationProject Time Management
Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use
More information12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish
International Campus Kish Sharif University of Technology Session#11 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,
More informationCOST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL
SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,
More informationEstimating Project Schedule-Time and Cost
Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities
More informationTopic # 12. CIS Project Management: an overview
Topic # 12 CIS Project Management: an overview Project Planning Major Activities during Project Planning: 1) describing project scope, alternatives, and feasibility; 2) dividing the project into manageable
More informationDecember 25, 2017 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE
December 25, 17 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE Chapter Outline 4.1 Background What was the cause of the desperation that lead to the development of the Program Evaluation and
More informationManaging Projects (Course Code: 5927A) Course length: 3 days
Managing Projects (Course Code: 5927A) Course length: 3 days Course Summary: This three-day instructor-led course provides students with the knowledge and skills to build, maintain, and control well-formed
More informationFor the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.
For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com
More informationSPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
More informationMicrosoft Office Project 2007, Managing Projects
Microsoft Office Project 2007, Managing Projects Course 5927A: Three days; Instructor-Led Introduction Elements of this syllabus are subject to change. This three-day instructor-led course provides students
More informationProject Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:
Project Management Dr. Richard Jerz 1 Learning Objectives Describe or Explain: What are projects The role of the project manager Work breakdown structure Project management tools (Gantt, PERT, & CPM) The
More informationIST 302 : Project Time Management
IST 302 : Project Time Management Developing quality schedules is important. 1 Schedule issues are the main reason for conflicts on projects There are five core project time management process groups.
More informationTest your Understanding-The Answers
Table of Contents Module 1 Project management methodology... 2 A. Introduction to Project Management... 2 B. The Phases of Project Management... 2 C. Project Management Methodology questions... 2 Module
More information2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline -
2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline - PREPARED BY: Jake Lilley, PMP President PPM Global Services, Inc. P: 1-800-746-4029 F: 1-800-746-4029 E: jlilley@ppmglobalservices.com
More informationWhite Paper Using S-Curves to improve Project Performance
White Paper Using S-Curves to improve Project Performance Ever increasing pressure on businesses to deliver projects on time and to budget means that accurate monitoring of progress, resources and costs
More informationCourse Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT
Course Outline TEC D 205 Engineering Tech Project Planning Week 1 Chapter 4: DEFINING THE PROJECT 1. Step one: Defining the Project Scope A. Employing a Project Scope Checklist 1. Project objective 2.
More informationMODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM)
MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) Content Writer/Author: Email id: Mrs. RENU ARORA renu214@gmail.com Structure of Module/Syllabus of module(define
More informationRisk Management User Guide
Risk Management User Guide Version 17 December 2017 Contents About This Guide... 5 Risk Overview... 5 Creating Projects for Risk Management... 5 Project Templates Overview... 5 Add a Project Template...
More informationExam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.
Exam Code:74-343 Number: 74-343 Passing Score: 800 Time Limit: 120 min File Version: 35.4 http://www.gratisexam.com/ Exam Code:74-343 Exam Name:Managing Projects with Microsoft Project 2013 Testinside
More informationMicrosoft Office Project 2010 Basic Course 01: Getting Started
Microsoft Office Project 2010 Basic Course 01: Getting Started Slide 1 Topic A Project Management Concepts Slide 2 Project Constraints Slide 3 Phases of Project Management The initial Phase Initiating
More information3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline -
3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline - PREPARED BY: Jessica Summers Virtual Training Coordinator PPM Global Services, Inc. P: 1-800-746-4029 x 310 F: 1-800-746-4029 E:
More informationGuten Tag. (good day)
Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources
More informationCHAPTER 1. Basic Concepts on Planning and Scheduling
CHAPTER 1 Basic Concepts on Planning and Scheduling Eugénio Oliveira Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the and ordering of activities as well
More informationPMI Scheduling Professional (PMI-SP)
PMI Scheduling Professional (PMI-SP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute PMI Scheduling Professional (PMI-SP) Exam Content Outline Published by: Project Management
More informationPlanning & Scheduling
Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1 Planning Successful Project Management depends on continues planning. The activities of Designers,
More informationLessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International
Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Charlie Jackson, PSP, Primavera Certified Trainer Hill International Construction CPM Conference
More informationIndex. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text.
Construction Planning ISBN 978-0-7277-6057-9 ICE Publishing: All rights reserved http://dx.doi.org/10.1680/cp2e.60579.191 Index Page locators in italics and bold respectively refer to figures and tables
More informationExam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.
Exam Code:74-343 Number: 74-343 Passing Score: 800 Time Limit: 120 min File Version: 35.4 http://www.gratisexam.com/ Exam Code:74-343 Exam Name:Managing Projects with Microsoft Project 2013 Examsoon QUESTION
More informationPlanning & Scheduling CSTM 102
Planning & Scheduling CSTM 102 Items Big A Project on Website Thursday Discuss Big A Project next Tuesday April 18, 2011 CPM Scheduling You were the successful bidder! What s next? Procurement/Buy
More informationDeswik.Sched Gantt Chart Scheduling
Deswik.Sched Gantt Chart Scheduling SCHEDULING SOLUTIONS THAT SET US APART A dynamic, modern approach to scheduling From interactive Gantt charts to PERT network diagrams, Deswik.Sched is tailored for
More informationScott M. Francis, P.E., PSP
Scott M. Francis, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Scott M. Francis,
More informationProject Planning, Scheduling and Preparation of Quality Assurance Control Documents
Project Planning, Scheduling and Preparation of Quality Assurance Control Documents J.SHARANYASREENIVAS 1, G.GAJALAKSHMI 2, K.RAVI THEJA 3 1P.G Student M.Tech (Structural Engg. and construction managment),
More informationReview: Simple schedule risk modelling with Safran Risk
Creating value from uncertainty Broadleaf Capital International Pty Ltd ABN 24 054 021 117 www.broadleaf.com.au Review: Simple schedule risk modelling with Safran Risk With a view to exploring alternative
More informationUnderstanding Import & Export with NetPoint 4.2
Understanding Import & Export with NetPoint 4.2 Eric Lowther PMA Consultants 1 Primary Differences Regarding Import/ Export CPM Tools F9 and Early/Late Dates Float & Total Float Gantt Charts (Waterfall
More informationProject Planning and Estimating DJ
Project Planning and Estimating DJ201 0807 Copyright ESI International August 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any
More informationP6 Instructors Sample Presentation
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 to 8.4 Professional and Optional Client 3 day training course PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration Evacuation
More informationBest Practices in Procurement & Contract Management
Best Practices in Procurement & Contract Management Definition: Contract Administration The term is to describe the management functions that are performed after the contract has been signed to assure
More informationDeveloping and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director,
Developing and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director, Risk Integration Management Pty Ltd Presentation Outline
More informationProject Planning and Control Using Oracle Primavera P6 : P8.3, 8.4, 15.2
Primavera Essential Course Contents: 1. Overview Describe the Primavera modules Explain the difference between global and project-specific data Project Portfolio Management Defining the Enterprise Project
More informationWelcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Copyright Eastwood Harris Pty Ltd IMPORTANT POINTS FOR
More informationPrimavera P6 R8.3 Professional Fundamentals Training Course Outline
Course Overview Prescience Technology is an Oracle Platinum Partner and specialist provider of Primavera Services. This Prescience course introduces the user to Oracle Primavera P6 version 8.3 Professional
More informationPrimavera Training - P6 Basic Course (102)
Primavera Training - P6 Basic Course (102) This training session provides hands-on training for Primavera s client/server-based solution, leading participants through the entire project life cycle, from
More informationPMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?
PMP Sample Questions www.techfaq360.com Click here for 1600+ PMP Questions Question No : 1 Which of the following is an output of Define Scope? A. Accepted deliverables B. Change Requests C. Project document
More informationBusiness Intelligence, 4e (Sharda/Delen/Turban) Chapter 2 Descriptive Analytics I: Nature of Data, Statistical Modeling, and Visualization
Business Intelligence, 4e (Sharda/Delen/Turban) Chapter 2 Descriptive Analytics I: Nature of Data, Statistical Modeling, and Visualization 1) One of SiriusXM's challenges was tracking potential customers
More informationMicrosoft Project study guide
Microsoft Project study guide Chap 1 An estimated duration appears with a(n) after the duration. a. pound sign c. question mark b. exclamation point d. red bullet Which of the following tasks in a LAN
More informationSchedule % Complete in Primavera P6
Schedule % Complete in Primavera P6 Schedule % Complete is one of the many percent completes you have in Primavera P6 and we re going to have a complete look at what it is and how it is calculated. Two
More informationMICROSOFT PROJECT 2010 Level 1
MICROSOFT PROJECT 2010 Level 1 Microsoft Project 2010 Level 1 Contents CONTENTS PREFACE - PROJECT MANAGEMENT BASICS... 5 Project Management Overview... 6 Project Definition Techniques... 7 Project Planning
More informationProject Cost Management
PMBOK Overview A Guide to the Body of Knowledge (PMBOK), created by the Institute (PMI), is the sum of knowledge within the profession of project management. The complete Body of Knowledge includes proven
More informationViews and Layouts for Program Management
MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted
More informationProject Planning. COSC345 Software Engineering 2016 Slides by Andrew Trotman given by O K
Project Planning COSC345 Software Engineering 2016 Slides by Andrew Trotman given by O K Overview Assignment: The assignment sheet specifies a minimum Think about what else you should include (the cool
More informationApplication of a PERT-Type System and "Crashing" in a Food Service Operation
Hospitality Review Volume 7 Issue 2 Hospitality Review Volume 7/Issue 2 Article 8 1-1-1989 Application of a PERT-Type System and "Crashing" in a Food Service Operation Glenn A. Leitch Michigan State University,
More informationS O Seminar Objective
Introduction to Project Management Welcome! Presenter: Bob Hull CalACT Conference September 202 S O Seminar Objective To provide an overview of project management processes and provide some skills, tools
More informationConstruction Project Scheduling of MK Apartment Using MS Project 2013
Construction Project Scheduling of MK Apartment Using MS Project 2013 Monish Kumar K 1, Maheshwar S Maregoudru 2, Sparsha B.P 3 1,2 PG Student, Dept. of Civil Engineering, KVGCE, Sullia, Karnataka, India
More informationIMPLEMENTATION, EVALUATION & MAINTENANCE OF MIS:
IMPLEMENTATION, EVALUATION & MAINTENANCE OF MIS: The design of a management information system may seem to management to be an expensive project, the cost of getting the MIS on line satisfactorily may
More informationSCHEDULE RISK ANALYSIS ESSENTIALS FOR PROJECT SUCCESS
SCHEDULE RISK ANALYSIS ESSENTIALS FOR PROJECT SUCCESS CSVA 2011 Conference Toronto, Ontario Nov 14-16, 2011 Laszlo A. Retfalvi P.Eng PMP PMI-RMP Retfalvi and Associates 1 Agenda of Session Key Take Aways
More informationitaskx 3 Project Management User Manual
itaskx 3 Project Management User Manual GET STARTED Basics Recommended workflow Views in itaskx Adjust project options Set working time for the project-calendar 2 Unit 1 Project management basics Learn
More informationResource Allocation Optimization in Critical Chain Method
Annales UMCS Informatica AI XII, 1 (2012) 17 29 DOI: 10.2478/v10065-012-0006-2 Resource Allocation Optimization in Critical Chain Method Grzegorz Pawiński 1, Krzysztof Sapiecha 1 1 Department of Computer
More informationProject Scheduling and Tracking. CIS 375 Bruce R. Maxim UM-Dearborn
Project Scheduling and Tracking CIS 375 Bruce R. Maxim UM-Dearborn 1 What does the customer want to know? Do you understand my needs? Can you design a system to help me? How long will it take? How much
More informationVrije Universiteit Amsterdam Faculty of Exact Sciences. Exam: Software Project Management Version A. Dr. Nelly Condori-Fernandez. Date: May 27, 2015
Vrije Universiteit Amsterdam Faculty of Exact Sciences Exam: Software Project Management Version A Code: Coordinator: X_401093 Dr. Nelly Condori-Fernandez Date: May 27, 2015 Duration: Calculator allowed:
More informationVersion Comparison. Getting Started Project Planning. Feature Key:
Version Comparison Version Comparison The table below introduces the new features of 2010 and Project. It also shows features initially included in previous versions that have been improved in Project
More informationProject Management Concepts, Tools & Techniques
Project Management Concepts, Tools & Techniques Course ISI-1438 5 Days Instructor-led, Hands on Introduction This highly interactive 5 day, instructor-led workshop is designed to give participants a solid
More informationProject Controls Expo 13 th Nov 2013
Project Controls Expo 13 th Nov 2013 Twickenham Stadium, London From Cost Plan To Bid Evaluation To Contract Administration The Earned Value Project Control Cycle Copyright @ 2011. All rights reserved
More informationDescribing DSTs Analytics techniques
Describing DSTs Analytics techniques This document presents more detailed notes on the DST process and Analytics techniques 23/03/2015 1 SEAMS Copyright The contents of this document are subject to copyright
More informationTotal Questions: 370 MODULE QUIZ ANSWER KEY. Fundamentals 1 & 2
Fundamentals 1 & 2 1. Answer: B Process Group. Each project management knowledge area is subdivided into specific process group, each of which is characterized by their inputs, tools and techniques, and
More informationMAKE YOUR SCHEDULE REALISTIC BY USING CALENDARS
1 MAKE YOUR SCHEDULE REALISTIC BY USING CALENDARS Prakash K P, Director of Project Management, Grade Results, Inc. 2 Learning Objectives At the end of this session, you will be able to do the following
More information1.Which of the items listed below is not one of the software engineering layers?
1.Which of the items listed below is not one of the software engineering layers? Process Manufacturing Methods Tools 2.The software quality assurance activity which is performed to check errors in logic,
More informationProject Risk Analysis (with Pertmaster)
Project Risk Analysis (with Pertmaster) AACE Toronto Section October 2, 2008 Brought to you by: Presenter Ian Nicholson, P.Eng. VP Solutions, Emerald Associates Mechanical Engineer Primavera Systems Authorized
More informationDeltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A
Deltek Acumen Planning, Risk, Acceleration Tom Polen Director, Solution Architecture Learning Objectives The 5 steps 1. Capturing uncertainty: calibrating the schedule 2. Identifying risk events: accounting
More informationProject Management using MS PROJECT Middle East College Training Unit
1 Project Management using MS PROJECT 2013 About the course 1 Microsoft Project training course trains you to plan and manage projects more effectively. Microsoft Project is a project management tool
More information13 Project Graphics Introduction
Page 725 13 Project Graphics 13.0 Introduction In Chapter 11, we defined the steps involved in establishing a formal program plan with detailed schedules such that the total program can be effectively
More informationPMI-001 Questions & Answers
PMI-001 Questions & Answers Number: PMI-001 Passing Score: 700 Time Limit: 137 min File Version: 21.2 http://www.gratisexam.com/ PMI-001 Questions & Answers Exam Name: Project Management Professional v5
More informationMS Project Professional 2007 Schedule Leveling: Tips & Tricks. By Lloyd C. Miller III, PMP
MS Project Professional 2007 Schedule Leveling: Tips & Tricks By Lloyd C. Miller III, PMP Agenda What, Where, When & Why Understanding the Options Considering Different Views / Reports Tips & Tricks 2
More informationProject Management Assignment Guidelines Tri 2. Andre Samuel
Project Management Assignment Guidelines 2015 16 Tri 2 Andre Samuel Part A General Overview This component requires the use both theoretical (journals, texts) as well as practitioner references in your
More informationAdvance Course Managing Mega Project using Microsoft Project 2013
Applied Technology Group Sdn Bhd (1012178-W) W-5-3, Subang Square Business Centre, Jalan SS15/4G, 47500 Subang Jaya, Selangor, Malaysia. Tel: (+603) 5634 7905 Fax: (+603) 5637 9945 Email: admin@apptechgroups.net
More informationA COMPARISON OF CPM-BAR CHART AND A HIERARCHICAL GRAPHICAL APPROACH TO PLANNING CONSTRUCTION PROCESSES
A COMPARISON OF CPM-BAR CHART AND A HIERARCHICAL GRAPHICAL APPROACH TO PLANNING CONSTRUCTION PROCESSES By COURTNEY K. ZURICH A THESIS PRESENTED TO THE GRADUATE SCHOOL OF THE UNIVERSITY OF FLORIDA IN PARTIAL
More informationContent Break-up & Methodology for awarding Contact Hours / PDUs
N.I.T.E - Project Management Professional (PMP) Exam Prep Course Content Break-up & Methodology for awarding Contact Hours / PDUs This course is based on Project Management Book of Knowledge PMBOK Guide
More informationPrinciples of Schedule Contingency Management
Principles of Schedule Contingency Management Ted Douglas, CCC, PSP ACTPMA, LLC Consulting 2014 Construction CPM Conference Orlando, Florida Schedule Contingency Management Background Outline of Presentation
More informationRESOURCE OPTIMIZATION IN CONSTRUCTION OF A RESIDENTIAL APARTMENT USING PRIMAVERA P-6 SOFTWARE
RESOURCE OPTIMIZATION IN CONSTRUCTION OF A RESIDENTIAL APARTMENT USING PRIMAVERA P-6 SOFTWARE BHAJANTHRI THIRUMALESHA 1, RAJANI V.AKKI 2,BASAVARAJ BAVI 3 1 P.G. Student, Civil Engineering Department, Shree
More informationMicro Planner X-Pert
Micro Planner X-Pert V3.5.1 Overview Presenter: Patrick Weaver PMI-SP Micro Planning International Asia Pacific Cell:+61 418 53 1111 raf@microplanning.com.au. Arrow Diagram Precedence Diagram Working
More informationDEPARTMENT OF MCA CLASS / YEAR : III MCA SUB. CODE & NAME: MC9252, SOFTWARE PROJECT MANAGEMENT. UNIT I 2 MARKS QUESTIONS & ANSWERS 1. What is software project management? Software project management is
More informationThe Museum Project. 1. Creating the Project
1. Creating the Project The Museum Project You have just come out of a meeting in which you have been given the task to plan and manage a project for the local museum. In the meeting you were told that
More informationMS Project 2007 Overview Table of Contents
Table of Contents Microsoft Project Overview... 1 Terminology... 1 Starting Microsoft Project... 2 Projects on the Web... 2 Toolbars... 2 View Bar... 2 Views... 3 Setting Up the Project... 3 Identifying
More informationProject Management Techniques
Project Management Techniques CHAPTER C Learning Objectives After reading this chapter, you should be able to: Calculate net present value, payback period, and return on investment Chapter Outline Calculating
More informationProject 2003 Intermediate
Microsoft Application Series Project 2003 Intermediate Best STL Courses never cancelled: guaranteed Last minute rescheduling 24 months access to Microsoft trainers 12+ months schedule UK wide delivery
More informationPrimaned Belgium. Oracle Primavera P6 Enterprise Project Portfolio Management Data Sheet. Revision Date 04/08/2017
Primaned Belgium Oracle Primavera P6 Enterprise Project Portfolio Data Sheet Revision Date 04/08/2017 Primaned Belgium Uitbreidingstraat 84/3 2600 Berchem, Belgium PRIMAVERA P6 EPPM Oracle Primavera P6
More informationInfor LN Service User Guide for Service Scheduler Workbench
Infor LN Service User Guide for Service Scheduler Workbench Copyright 2018 Infor Important Notices The material contained in this publication (including any supplementary information) constitutes and contains
More informationWelcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration
More informationCE 115 Introduction to Civil Engineering Graphics and Data Presentation Application in CE Materials
CE 115 Introduction to Civil Engineering Graphics and Data Presentation Application in CE Materials Dr. Fouad M. Bayomy, PE Professor of Civil Engineering University of Idaho Moscow, ID 83844-1022 Graphics
More informationINDUSTRIAL ENGINEERING
1 P a g e AND OPERATION RESEARCH 1 BREAK EVEN ANALYSIS Introduction 5 Costs involved in production 5 Assumptions 5 Break- Even Point 6 Plotting Break even chart 7 Margin of safety 9 Effect of parameters
More informationCommon Tool for Intelligent Scheduling / Critical Chain Project Management for US Navy & Contractor Shipyards
Common Tool for Intelligent Scheduling / Critical Chain Project Management for US Navy & Contractor Shipyards Rob Richards, Ph.D. April 20, 2016 Planning, Production Processes & Facilities Panel (PPP&F)
More informationProject Scheduler for Smart Project Management XLGantt User Manual
Project Scheduler for Smart Project Management XLGantt User Manual Version 1.1.0 http://xlworks.net/ Jun 6, 2017 Contents XLGantt Update History -------------------------------------------------------------
More informationSCHEDULING FOR HIGH-RISE BUILDING CONSTRUCTION USING SIMULATION TECHNIQUES
SCHEDULING FOR HIGH-RISE BUILDING CONSTRUCTION USING SIMULATION TECHNIQUES Arthur W T Leung Division of Building Science and Technology, City University of Hong Kong bsawtl@cityu.edu.hk Dr C M Tam Department
More informationOracle Prime Projects Cloud Service
Oracle Prime Projects Cloud Service Oracle Prime Projects Cloud Service is a complete, cloud-first success platform for all stages of the project lifecycle. It empowers executives, project managers, and
More informationInitiation Group Process. Planning Group Process
Initiation Group Process Develop Project Charter Project statement of work Expert judgment Project charter Business case Contract (if third party project) EEF: government/industry standards, organizational
More informationMicrosoft Specialist Certification Exam
Microsoft Specialist Certification 74-344 Exam Vendor: Microsoft Exam Code: 74-344 Exam Name: Managing Programs and Projects with Project Server 2013 QUESTION 1 Your organization is performing a Portfolio
More informationLesson 15-Planning and Costing
Lesson 15-Planning and Costing Overview The process of making multimedia. Scheduling. Estimating. RFPs and bid proposals. The Process of Making Multimedia Idea analysis. Pre-testing. Task planning. Development.
More informationIntegrated Planning Model (IPM ) Overview
Integrated Planning Model (IPM ) Overview September 2010 Disclaimer This presentation, prepared by ICF under contract with RGGI, Inc., is designed to support ongoing evaluation of state RGGI programs.
More informationInfor ERP LN Project Integration Pack for Microsoft Project
Infor ERP LN 6.1 Projects Infor ERP LN Project Integration Pack for Microsoft Project 98-2000-2002-2003 User s Guide Copyright 2008 Infor All rights reserved. The word and design marks set forth herein
More information