1 Project Procurement Management
2 Project Procurement Management Processes necessary to purchase or acquire products, services or results needed from outside the project team.
3 Procurement Management Processes Process Plan Procurements Process Group Planning Conduct Procurements Executing Control Procurements Monitoring and Controlling Close Procurements Closing
4 Plan Procurements Plan Procurements is the process of documenting project purchasing decisions, specifying the approach, and identifying potential sellers
5 Plan Procurements Inputs Tools and Techniques Outputs Project management plan Requirements documentation Teaming agreements Risk Register Project Schedule Activity cost estimates Stakeholder register Enterprise Environmental Factors Organizational Process Assets Make or buy analysis Expert Judgment Market research Meetings Procurement management plan Procurement statements of work Make or buy decisions Procurement documents Source selection criteria Change requests Project document updates
6 Plan Procurements - Inputs Project Management Plan - describes the need, justification, requirements, and current boundaries for the project. It consists of Scope statement, WBS and WBS dictionary. Requirements documentation include Important information about project requirements that is considered during planning for procurements. Risk Register include risk-related information such as identified risk, risk owners and risk responses Activity resource requirements state the type and quantities of resources needed for project activities Project Schedule provides information on project timelines and milestones Activity cost estimates are used to evaluate the price quoted in the bids or proposals received from potential sellers Stakeholder Register describes the details on the participants and their interest in the project
7 Plan Procurements - Inputs Enterprise Environmental Factors includes condition of marketplace, what product and service are available in the market, who is the seller and what are his terms and condition Organizational Process Assets includes policies and procedures, standards,guidelines, performance measurement criteria, defect management procedures, change control procedures and historical information. Some organizations may define certain constraint on procurement decisions. This also include the various types of contractual agreements used by the organization, All legal contractual relationships generally fall into one of two broad families: either fixed price or cost reimbursable. Also, there is a third hybrid type commonly in use called the time and materials contract. The next slides describes the different contract types in details
8 Plan Procurements -Tools and Techniques Types of Contract Time & Material T & M Firm Fixed Price - FFP Fixed Price Incentive Fee FPIF Fixed Price with Economic Price Adjustment Contracts FP-EPA The seller is paid for the amount of time it takes to accomplish the work and he is also reimbursed for the materials used for the project The seller is paid a fixed price for an agreed upon unit of work done by him The seller is paid a fixed price plus an incentive amount for achieving pre-agreed project metrics The seller is paid a fixed price. The contract is reviewed at pre-defined intervals in the project for adjustments to the contract price based on certain parameters
9 Plan Procurements -Tools and Techniques Types of Contract Cost Plus Fixed Fee CPFF Cost Plus Incentive Fee - CPIF Cost Plus Award Fee The contractor is reimbursed its cost plus an additional fixed fee. Not desirable from the buyer s point of view Seller is reimbursed for an agreed upon performance cost along with a preestablished fee plus an incentive bonus. In this case, the buyer and seller share the uncertainty to a certain degree Seller is reimbursed for an agreed upon performance cost plus all legitimate cost
10 Plan Procurements -Tools and Techniques Make or buy analysis helps project management team to decide whether it is beneficial (in terms of cost and quality) to procure a product or service or it can be produced within the organization. Market Research includes examination of industry and specific vendor capabilities. Procurement teams may leverage information gained at conferences, online reviews and a variety of sources to identify market capabilities. Meetings, by collaborating with potential bidders, the organization purchasing the material or service may benefit while supplier can influence a mutually beneficial approach or product.
11 Plan Procurements - Outputs Procurement management plan describes how the procurement process will be managed from planning procurement to close procurement. It contains detail on 1. Types of Contracts to be used 2. Risk management issues 3. Whether independent estimates will be used and whether they are needed as evaluation criteria 4. Standardized procurement documents, if needed 5. Process of managing multiple providers (sellers) 6. Coordination with other project aspects 7. Any constraints and assumptions that could affect planned procurements 8. Handling the long lead times to purchase certain items from sellers and coordinating the extra time needed to procure these items with the development of the project schedule 9. Handling make or buy decision and linking them to the Estimate Activity Resources and Develop schedule process.
12 Plan Procurements - Outputs Procurement statements of work defines the products, services, or result to be procured in details so that the seller can be sure that he can provide appropriate products, services, or results. It is developed from the project scope baseline and defines only that portion of the project scope that needs to be procured and stated in the contract. Procurement documents define the buyer s requirements and facilitate complete and correct response from the prospective sellers in the form of a proposal, which aids in the selection of the seller(s). The most commonly used procurement documents are RFP (Request for Proposal), IFB (Invitation for Bid and RFI (Request for Information
13 Plan Procurements - Outputs Source selection criteria are the set of guidelines on the basis of which a particular seller is selected from among the proposals received. Some of the source selection criteria are seller s understanding of need, overall- life-cycle cost, technical capability, Risk, past performance of the seller, Financial capacity, Warranty etc Make or - Buy Decisions, A make-or- buy analysis results in a decision of whether particular work can best be accomplished by the project team or needs to be purchased from outside sources. Change requests may be there during this process due to updates in the project plan or its subsidiary plan and other components. These changes are reviewed and approved through the integrated change control process. Project Documents Updates that may be updated include requirement documentation, requirements traceability matrix and risk register.
14 Exercise 1: Make or Buy Analysis Practicing Key Concepts You ve been contracted by a construction company to manage their contracting. They have a choice of either buying an excavator or renting it. To buy it, the company would have to pay $105,000, but owning it will require approximately $10,000 in maintenance costs per year. The price to rent the excavator is $5000 per month, with a one-time service charge of $2000. What s the minimum number of months the company needs to use the excavator in order for it to make sense to buy it rather than rent? 1. 8 months months months months
15 Exercise 2: Plan Procurements Which document are we referring below? 1. A type of procurement document used to request proposals from prospective sellers of products or services. 2. A type of procurement document used to request price quotations from prospective sellers of common or standard products or services.
16 Exercise 2: Plan Procurements Which document are we referring below? 1. A type of procurement document used to request proposals from prospective sellers of products or services. RFP 2. A type of procurement document used to request price quotations from prospective sellers of common or standard products or services. RFQ
17 Conduct Procurement Conduct Procurements is the process of obtaining seller responses, selecting a seller, and awarding a contract
18 Conduct Procurement Inputs Tools and Techniques Outputs Project Management Plan Procurement documents Source selection criteria Seller proposals Project documents Make or buy decisions Teaming agreements Organizational Process Assets Bidder conferences Proposal evaluation techniques Independent estimates Expert Judgment Advertising Analytical Techniques Procurement negotiation Selected sellers Agreements Resource calendars Change requests Project management plan updates Project document updates
19 Conduct Procurement - Inputs Project Management Plan contains procurement management plan and this describes how the procurement process will be managed from preparing procurement documentation through close procurements Procurement Documents as explained earlier provide an audit trail for contracts and other agreements Source Selection criteria are set of guidelines, either subjective or objective, that are used by the performing organization to select a particular contract/ vendor (seller) from among the proposals received. Seller proposals are responses to the procurement document package that will be used for selection of the sellers by the organization s evaluation body
20 Conduct Procurement - Inputs Project documents that are important inputs to this process include risk register and risk related contract decisions. Make- or -buy decisions as explained earlier is based on the outcome of Make orbuy- Analysis. The factors that influence the decision making include, core competencies of the organization, value delivered, risk associated with meeting the need in a cost=effective manner and internal capability as compared to the vendor community. Procurement Statement of Work provides suppliers with a clearly stated set of goals, requirements, and outcomes from which they can provide a quantifiable response. The statement of work include Specifications Quantity desired Quality levels Performance data, period of performance, work location and other requirements
21 Conduct Procurement - Inputs Organizational Process Assets that can influence this process include listings of prospective and previously qualified sellers and information on relevant past experience with sellers, prior agreements
22 Conduct Procurement Tools and Techniques Bidder conferences are meetings wherein the prospective supplier (sellers) are called in to ensure that all the supplier have a clear understanding of the work defined in the procurement documents. Proposal evaluation techniques are used to evaluate the proposals by giving a rating score to each proposal Independent estimates are sometimes prepared by the procuring organization using internal expert in estimation or an outside professional estimator Expert Judgment includes a team of experienced and skilled experts for evaluation of proposals under various areas of expertise as mentioned in the procurement documents and contract
23 Conduct Procurement Tools and Techniques Advertising is used by the performing organization to invite the potential sellers to be Contracted Analytical Techniques, procurements involve defining a need in such as way that vendors can bring value through offerings. To ensure that the need can be and is met, analytical techniques can help organizations identify the readiness of a vendor to provide the desired end state. By examining past performance information, teams may identify areas that may have more risk and that need to be monitored closely to ensure success of the project Procurement negotiations between the buyers and the potential sellers are performed with the goal of reaching mutual agreement on the contractual terms and conditions. The goal is to reach a win-win scenario between the buyer and seller.
24 Conduct Procurements Outputs Selected Sellers are those who have met the evaluation criteria and negotiated a draft contract with the buyer, which will become the actual contract when the contract is awarded Agreement is a formal document governing the relationship between the buyer and the seller. The contract describes the work to be performed and perhaps the way in which the work will be performed. An important to include with the contract is how disputes will be resolved. Depending upon the application area, an agreement can also be called an understanding, a contract, a subcontract, or a purchase order. Regardless of the document complexity, a contract is a mutually binding legal agreement that obligates the seller to provide the specific products, services, or results and obligates the buyer to compensate the seller. The major component of agreement are:
25 Conduct Procurements Outputs Major components of an agreement Statement of work or deliverables Schedule baselines Performance reporting Period of performance Roles and responsibilities Seller s place of performance Pricing Payment Terms Place of delivery Inspection and acceptance criteria Warranty Product Support Limitation of liability Fees and retainer
26 Conduct Procurements Outputs Major components of an agreement Penalties Incentives Insurance and performance bonds Subordinate subcontractor approvals Change request handling and Termination clause and alternative dispute resolution (ADR) mechanism. The ADR method can be decided in advance as a part of the procurement award.
27 Conduct Procurements Outputs Resource Calendar state the availability and the quantity of contracted resource and the project period (dates) during which the resources are active or idle Change Requests to the project management pan, its subsidiary plans and other components are processed for review and disposition through the Perform Integrated Change Control process. Project Management Plan Updates, the elements of the project management plan that may be updated include Cost baseline, Scope baseline, Schedule baseline, Communication management plan, and Procurement management plan. Project Document Updates, the project documents that may be updated include, requirement documentation, requirement traceability documentation, risk register and stakeholder register.
28 Conduct Procurements Outputs Selected Sellers are those who have met the evaluation criteria and negotiated a draft contract with the buyer, which will become the actual contract when the contract is awarded Procurement Contract Award is a formal document governing the relationship between the buyer and the seller. The contract describes the work to be performed and perhaps the way in which the work will be performed. An important to include with the contract is how disputes will be resolved. Resource Calendar state the availability and the quantity of contracted resource and the project period (dates) during which the resources are active or idle Change Requests As discussed earlie Project Management Plan Updates As discussed earlier Project Document Updates As discussed earlier
29 Control Procurements Managing procurement relationships, monitoring contract performance and making changes and corrections as needed.
30 Control Procurement Inputs Tools and Techniques Outputs Project Management Plan Procurement documents Agreement Approved change requests Work Performance reports Work performance Data Contract change control system Procurement performance reviews Inspections and audits Performance reporting Payment system Claims administration Records management system Work performance information Change requests Project management plan updates Project document updates Organizational process assets update
31 Control Procurement - Inputs Project Management Plan describes how the procurement process will be managed from developing procurement documentation through contract closure. Procurement documents contain complete supporting records for administration of the procurement processes; this includes procurement contract awards and the statement of work Agreements As Explained earlier Agreements are understanding between parties, including understanding of the duties of each parties. Approved change requests include modifications to the terms and condition of the contract including the procurement statement of work, pricing and the description of the products, services or results.
32 Control Procurement - Inputs Work Performance Reports is a seller performance related documentation that include Technical documentation. Sellers- developed technical documentation and other deliverable information are provided in accordance with the terms of the contract. Work performance information. The seller s performance reports indicate which deliverables have been completed and which have not. Work Performance Data includes information on a regular basis of the performance and status of the seller s project work activities. It includes information such as which deliverables have been completed and which have not, whether the quality standards defined for the project are being adhered to and the payment is being made for the costs that have been stated in the contract.
33 Control Procurement Tools and Techniques Contract change control system is a component of integrated change control system and it describes the process of updating the contract Procurement performance reviews are periodic reviews initiated by the buyer to measure the project s progress against the plan Inspections and audits are done by the buyer and supported by the seller to identify any non-compliance to the project s process or deliverables. Performance reporting provides information to management about how effectively the seller is achieving his contractual objective. Payment system helps to ensure that invoices and payments match up and that the right amount is being invoiced for the right deliverables at the right time.
34 Control Procurement Tools and Techniques Claims administration are basically disagreements (about scope or change request). It is preferred that the claims should be resolved by the parties involved as per the dispute resolution procedure. If not resolved by the parties involved, then the disputes are resolved by the process of Arbitration whereby a third neutral party is given the task of getting the dispute resolved. Records management system is a part of the project management information systems (PMIS). In addition to the documentation, it also consists of processes, control functions, and automated tools. This system should index various documents for their easy retrieval and archival.
35 Control Procurement Outputs Work Performance Information provides a basis for identification of current or potential problems to support later claims or new procurements. By reporting on the performance of a vendor, the organization increases the knowledge of the performance of the procurement, which supports improved forecasting, risk management and decision making. Performance reports also assist in the event there is a dispute with the vendor. Change requests, changes to the project management plan, its subsidiary plans, and other components, such as the cost baseline, schedule baseline, and procurement management plan may result from the control procurement process. Project management plan updates includes update to the procurement management plan,schedule baseline and cost baseline
36 Control Procurement Outputs Project Documents Updates include updates to procurement documentation, it include the procurement contract with all supporting schedules, requested unapproved contract changes, and approved change requests. It also includes any seller developed technical documentation and other work performance information such as deliverable s, seller performance reports and warranties, financial documents including invoices and payment records, and the result of contract related inspections. Organizational process assets updates that will be updated as a result of this process includes documentation related to seller s unsatisfactory performance, request for contract changes or clarifications, payments made by the buyer to the seller and also the documents related to seller s performance.
37 Exercise : Control Procurements Revising Tools and Techniques 1. involves process to change the procurement contract. It can involve the approvals, paperwork and the dispute resolution mechanism required for the change control. 2. system refers to how the payments are made to the seller.
38 Answer to Exercise : Control Procurements Revising Tools and Techniques 1. Contract Change Control System involves process to change the procurement contract. It can involve the approvals, paperwork and the dispute resolution mechanism required for the change control. 2. Payment system refers to how the payments are made to the seller.
39 Close procurements Process of completing each project procurement. It involves administrative activities such as updating the project records with results and archiving the information for future use and finalizing open claims in accordance with the terms and conditions stated in the contract document Close Procurement process closes the procurement applicable to that phase of the project
40 Close procurements Inputs Tools and Techniques Outputs Project Management Plan Procurement documentation Procurement audits Procurement Negotiations Records management system Closed procurements Organizational process assets updates
41 Close procurements- Inputs Project Management Plan Discussed Earlier Procurement documentation includes information on contract schedule, scope, quality and cost performance along with all contract change documentation, payment records and inspection results. This information can be used for lessons learned information and as a basis of evaluating contractors for future contracts.
42 Close procurements- Tools and Techniques Procurement Audits is a structured review of the procurement processes from the plan procurements process through administer contracts process. The purpose of procurement audit is to identify the improvement areas and the flawed procurement processes and/ or procedure. This will assist in reusing the successful/updated procedures in other projects. Procurement Negotiations refers to the settlement for any outstanding issues, claims and disputes through negotiation. Whenever the settlement cannot be achieved through direct negotiation, some form of alternative dispute resolution(adr) including mediation or arbitration can be explored Records Management System is used by the project manager to manage contract and procurement documentation and records. Contract documents and correspondence are archived through the records management system as part of the close procurement process
43 Close procurements- Outputs Closed Procurements is the process in which the buyer s contract administrator sends formal written notice to the seller that the contract is complete. Organizational Process Assets Updates will be updated due to modification in the procurement files and lessons learned documentation. Also, deliverable acceptance and rejection will be stated in the final contract documentation with supporting reasons.
44 Exercise 5: Contract Type Reviewing Associated Risks to Buyers & Sellers Explain the risks from buyer and seller perspective in case of the following types of contracts 1. Firm fixed price 2. Fixed price plus incentive fee (FPIF) 3. Cost plus fixed fee 4. Cost plus award fee 5. Cost plus incentive fee 6. Time and Material (T&M)
45 Project Procurement Management Negotiations Techniques Deadline: imposing a deadline to reach an agreement Stalling: one party may claim that an agreement cannot be finalized because of his limited authority Fair and Responsible: a negotiator may claim that the price for a product is equitable because that s what another company is paying. Delay: are useful when tempers are beginning to flare, to divert from a subject, etc (Ex: arrival of refreshments, request for recess etc) Withdrawal: one party may attack an issue, then retreat
46 Project Procurement Management Negotiations Techniques Arbitration: a third party may be brought in when agreement cannot be reached. (out of court settlement) Fait Accompli: a party may claim that what is being asked for has already been accomplished and cannot be changed
47 Exercise 5: Procurement Management Revising Key Terms : Complete the following 1. An Invitation for is a document that ask sellers for the price of work 2. The buyer selects the selection criteria before contacting potential sellers 3. The contract has high risk to the seller because the seller must cover costs that go beyond the price
48 QUIZ!
Guten Tag. (good day)
Guten Tag (good day) What is the #1 problem many people have on a project? What is the #1 problem many people have on a project? Communication Project Management Process Groups Project 4. Integration Management
More informationPROJECT PROCUREMENT MANAGEMENT. 1 Powered by POeT Solvers Limited
PROJECT PROCUREMENT MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited CONDUCT PROCUREMENT PROCESSES BY PROCESS GROUP Planning Executing Monitoring and controlling Closing 12.1 12.2 12.3 12.4
More informationProject Management Professional (PMP) Exam Review
Project Management Professional (PMP) Exam Review Unauthorized distribution is strictly prohibited. These resources are for 3FOLD Education Centre students. PMI, PMP, PMBOK and the PMI Registered Education
More informationUnit 10: Procurement Management (PMBOK Guide, Chapter 12)
(PMBOK Guide, Chapter 12) This knowledge area addresses the processes for purchasing or acquiring products and services from outside the project team or organization. See course slide #10-1 for an overview
More informationProject Management Process Groups. Monitoring & Controlling. Initiating Planning Executing. Closing. Check & Act. Rita: A project ends here!
(Semaphore) Project Management Process Groups Initiating Planning Executing Monitoring & Controlling Closing Rita: Start Plan Do Check End & Act A project ends here! Project Management Process Groups Initiating
More informationIntroduction to Project Management
Introduction to Project Management Chapter 10 Managing Project Procurement Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 10-1 Two Perspectives
More informationAppendix. Process Inputs and Outputs
3601cA.fm Page 493 Wednesday, October 26, 2005 12:47 AM Appendix A Process and Throughout this book, PMP: Management Professional Study Guide, 3rd Edition, I ve discussed the inputs and outputs to the
More informationProject Management Framework
Project Management Framework What s Project? - Why Project? What s Project Management? - Why Project Management? What s Project Management Professionals? - Why Project Management Professionals? Project
More informationThe 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th
The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th www.pmlead.net PMI, PMP, CAPM and PMBOK Guide are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not
More informationVersion 1.0. The Contract Management Standard Final Edition. Version 1.0
The Management Standard Final Edition 1 Purpose of the Management Standard The purpose of the Management Standard is to describe the nature of contract management in terms of the contract management processes
More informationVersion 1.0. The Contract Management Standard Final Edition. Version 1.0
The Management Standard Final Edition 1 Purpose of the Management Standard The purpose of the Management Standard is to describe the nature of contract management in terms of the contract management processes
More informationCopyright 2013 Pearson Education, Inc. Publishing as Prentice Hall 5-1
Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall -1 Learning objectives Manage the planning process of a project Understand the work breakdown structure of a project Understand different
More informationIntegration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business Case Contract Enterprise environmental factors Project charter Expert judgement 26/02/2013 18:22:56 1 2
More informationLearn best practices with regard to contract administration and management; Identify the various phases of contract administration; Gain practical
Learn best practices with regard to contract administration and management; Identify the various phases of contract administration; Gain practical experience in how to organize the contract administration
More informationSummary of 47 project management processes (PMBOK Guide, 5 th edition, 2013)
Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Integration Management: processes & activities needed to properly coordinate all aspects of the project to meet stakeholder
More informationProject vs Operation. Project Constraints. Pankaj Sharma, Pankaj Sharma,
Project vs Operation PROJECTS OPERATIONS Temporary Ongoing Unique Repetitive Closes after attaining the objectives Objective is to sustain business Prototyping the new car model Assembly line production
More informationThere are a lot of exam objectives for the Closing process group even COPYRIGHTED MATERIAL. Chapter 1: Closing Your Contracts and Your Project
Chapter 1: Closing Your Contracts and Your Project Exam Objectives Confirm that the project scope and deliverables are complete by attaining final acceptance by the project sponsor and customer. Facilitate
More informationIntegration Knowledge Area
Integration Knowledge Area Develop Project Charter Project statement of work Expert judgment Project charter Business case Contract (if third party project) EEF: government/industry standards, organizational
More informationInitiation Group Process. Planning Group Process
Initiation Group Process Develop Project Charter Project statement of work Expert judgment Project charter Business case Contract (if third party project) EEF: government/industry standards, organizational
More informationProject Management Knowledge Areas SECTION III
Project Management Knowledge Areas SECTION III 1 Project Integration Management CHAPTER 4 2 The Key to Overall Project Success: Good Project Integration Management Project managers must coordinate all
More informationNEW HORIZONS ONLINE LIVE. Certified Associate of Project Management (CAPM ) PMBOK Guide, 5th Edition DAY 3
NEW HORIZONS ONLINE LIVE Certified Associate of Project Management (CAPM ) PMBOK Guide, 5th Edition DAY 3 Plan Quality Management 1. Project mgt. 2. Stakeholder register 3. Risk register 4. Requirements
More informationProject Integration Management
Project Integration Management Presented by Project Masters Inc. *Throughout this presentation, we reference and recognize the following trademarks, service marks, and copyrights of the Project Management
More informationCONSTRUCTION MANAGEMENT CORE COMPETENCIES
CONSTRUCTION MANAGEMENT CORE COMPETENCIES A Guide to the Construction Management Core Competencies and their Body of Knowledge CM PROFESSIONAL PRACTICE... 1 CM PROJECT MANAGEMENT... 4 COST MANAGEMENT...
More informationProcurement Policies and Procedures
Center for Economic and Social Development Procurement Policies and Procedures 1. Purpose of procurement standards. The purpose of these standards is to establish procedures for the Center for Economic
More informationPURCHASING AND PROCUREMENT OVERVIEW
Purchasing and Procurement Overview AASBO Certificate Program September 2018 David Smith Executive Director david@aasbo.com 256 585 1511 PURCHASING AND PROCUREMENT OVERVIEW Contract Procurement Law Understanding
More informationCompiled by Rajan Humagai
Compiled by Rajan Humagai www.pavementengineering.com.au Project Processes Inputs, Tools & Techniques and Outputs. (Based on PMBOK 5 th Edition) 1. Project Integration 1. Develop 1. Project Statement Of
More information2016 National Tribal Transportation Conference
Alaska Tribal Technical Assistance Program Center 2016 National Tribal Transportation Conference Construction Management Darrel Williams Introductions Introduction to Construction Administration Construction
More informationPROJECT INTEGRATION MANAGEMENT. 1 Powered by POeT Solvers LImited
PROJECT INTEGRATION MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers LImited MAJOR PROJECT DOCUMENTS Before we begin Integration, let's summarize the project's major documents: ALL are formally approved
More informationPMP MOCK EXAMS BASED ON PMBOK 5TH EDITION
PMP MOCK EXAMS http://www.tutorialspoint.com/pmp-exams/pmp_mock_exams_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 objective type sample questions and their answers are
More informationGLOSSARY. 1. Inclusions and Exclusions. 2. Common Acronyms
GLOSSARY 1. Inclusions and Exclusions This glossary includes terms that are: Unique or nearly unique to project management (e.g., project scope statement, work package, work breakdown structure, critical
More informationProcurement & Contracting
Procurement & Contracting Overview The procurement of goods and services and executing related contracts is a major function of transit management. In addition to seeking to obtain the highest quality
More informationPURCHASE ORDER ATTACHMENT Q-201 SOFTWARE QUALITY SUBCONTRACTOR REQUIREMENTS TASK DESCRIPTIONS - PURCHASE CATEGORY "A"
PURCHASE ORDER ATTACHMENT Q-201 SOFTWARE QUALITY SUBCONTRACTOR REQUIREMENTS TASK DESCRIPTIONS - PURCHASE CATEGORY "A" 1. SOFTWARE QUALITY PROGRAM. This attachment establishes the software quality requirements
More informationProject Management CSC 310 Spring 2018 Howard Rosenthal
Project Management CSC 310 Spring 2018 Howard Rosenthal 1 Notice This course is based on and includes material from the text: A User s Manual To the PMBOK Guide Authors: Cynthia Stackpole Snyder Publisher:
More informationLCS International, Inc. PMP Review. Chapter 9 Conducting Procurements and Sharing Information. Presented by David J.
PMP Review Chapter 9 Conducting Procurements and Sharing Information Presented by David J. Lanners, MBA, PMP These slides are intended to be used only in settings where each viewer has an original copy
More informationContract Administration: Tips for Improving your Contract Administration Process. Jennifer Adling Director of Procurement Services
Contract Administration: Tips for Improving your Contract Administration Process Jennifer Adling Director of Procurement Services Contract Administration Following the award of a contract, the management
More informationMASTERING PROJECT MANAGEMENT - PROJECT MANAGEMENT PROFESSIONAL ( PMP ) CERTIFICATION SEMINAR
MASTERING PROJECT MANAGEMENT - PROJECT MANAGEMENT PROFESSIONAL ( PMP ) CERTIFICATION SEMINAR Monday - Friday June 25-29, 2018 Book and pay before 4 June 2018 and get a discount per delegate. i This course
More informationProcurement Under the New Requirements 1
Requirements 1 Procurement under the New Requirements 1 Why This Session Is Needed New provisions in Uniform Guidance Changes to conflict of interest requirements in Uniform Guidance Distinctions between
More informationConstruction Contracts
Construction Contracts By Dr. Ibrahim Assakkaf Construction Contracts By Dr. Ibrahim Assakkaf 1 The Need Web-based Contracts Supporting scheduling Controlling Regulating Analyzing Auditing the procurement
More informationPMP MOCK EXAMS BASED ON PMBOK 5TH EDITION
PMP MOCK EXAMS http://www.tutorialspoint.com/pmp-exams/pmp_mock_exams_set4.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 objective type sample questions and their answers are
More informationConstruction Family of Documents
Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications
More informationEJCDC Contract Documents for America s Infrastructure Buy online at
EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction
More informationSTUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 4, Lesson 1 Differences between Cost & Price Analysis
STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 4, Lesson 1 Differences between Cost & Price Analysis April 2018 STUDENT PREPARATION Required Student Preparation Read FAR subpart 15.4,
More informationSTUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 4, Lesson 1 Differences between Cost & Price Analysis
STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 4, Lesson 1 Differences between Cost & Price Analysis July 2018 STUDENT PREPARATION Required Student Preparation Read FAR subpart 15.4,
More informationCertKiller.PMP.735q PMP. Project Management Professional v5
CertKiller.PMP.735q Number: PMP Passing Score: 800 Time Limit: 120 min File Version: 36.7 http://www.gratisexam.com/ PMP Project Management Professional v5 Thanks for help VCE,and my 93% marks! This dump
More informationProcurement (Purchasing) Roadmap
Procurement (Purchasing) Roadmap When you are using Federal Funds, all purchases must be competitively procured. The Federal Procurement regulations for Child Nutrition Programs can be found in 2 CFR-
More informationPMBOK Guide Fifth Edition Pre Release Version October 10, 2012
5.3.1 Define Scope: Inputs PMBOK Guide Fifth Edition 5.3.1.1 Scope Management Plan Described in Section 5.1.3.1.The scope management plan is a component of the project management plan that establishes
More informationREQUIREMENTS DOCUMENTATION
REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category Priority Acceptance Criteria REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category
More informationRole of Procurement / Purchasing Within the Authority
Role of Procurement / Purchasing Within the Authority What is Purchasing s Role / Why Is Purchasing Important? The Authorized entity within the Water Authority that procures the goods / services required.
More informationKnowledge Areas According to the PMBOK edition 5. Chapter 4 - Integration
Knowledge Areas According to the PMBOK edition 5 Chapter 4 - Integration 4.1 - Develop Project Charter Process Project statement of work Expert Judgment Project charter Business case Facilitation techniques
More informationEJCDC Contract Documents for America s Infrastructure Buy online at
EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction
More informationFlorida Institute of Technology
Florida Institute of Technology Procurement Policy POLICY SOURCE: Procurement Services POLICY NO.: 5383 SUPERCEDES: 5382 TITLE: Procurement Policy SUBMITTED BY: Purchasing REVISED DATE: May 1, 2017 APPROVED
More informationPMP Exam Preparation Workshop. Chapter # 5 Project Scope Management
PMP Exam Preparation Workshop Chapter # 5 Copyright PMI SOC 2013 1 Learning Objectives By the end of this session you will understand: How scope management processes relate to the process groups Project
More informationBASIC HOST COUNTRY CONSTRUCTION CONTRACTING FOR DEVELOPMENT PROFESSIONALS: A PRIMER
BASIC HOST COUNTRY CONSTRUCTION CONTRACTING FOR DEVELOPMENT PROFESSIONALS: A PRIMER January 2012 This Primer was produced for the United States Agency for International Development (USAID). It was prepared
More informationCOMMUNITY LIVING BRANT POLICY AND PROCEDURE MANUAL
PAGE 1 of 7 FILE UNDER SECTION: 4 EFFECTIVE DATE: January 2012 REVISION DATE: APPROVAL DATE: January 2012 POLICY: This Policy includes the requirements that are set out in the Broader Public Sector (BPS)
More informationEJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center
EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction
More informationBENCHMARKING PPP PROCUREMENT 2017 IN NEPAL
BENCHMARKING PPP PROCUREMENT 2017 IN NEPAL Regulatory and Institutional Framework for PPPs Does the regulatory framework in your country allow procuring PPPs?. specify the relevant regulatory framework
More informationWUPRPM Regulations and Procedures Effective: November 11, 2005 R. Purchasing and Financial Obligations Revision Date: July 1, 2015.
Table of Contents 1. Purpose... 3 2. Definitions... 3 3. Limits and Thresholds... 4 4. Competitive Bidding... 4 5. Request for Quotation/Request for Proposal... 5 6. Bid Information... 5 7. Bid Bonds...
More informationOCEAN COUNTY COLLEGE PURCHASING MANUAL
OCEAN COUNTY COLLEGE PURCHASING MANUAL 1 OCEAN COUNTY COLLEGE PURCHASING MANUAL Issued by the Office of the Vice President of Finance & Administration January 1, 2014 The purpose of this manual is to assist
More informationBusiness Opportunities. and Insurance Board. with the Workplace Safety. Becoming a WSIB Supplier
Business Opportunities with the Workplace Safety and Insurance Board Becoming a WSIB Supplier Business Opportunities with the Workplace Safety and Insurance Board If you are interested in becoming a WSIB
More informationTo Bid or Not To Bid
To Bid or Not To Bid That Should NOT Be a QUESTION When soliciting bids for various purchases, including asphalt and road equipment, townships have a variety of tools at their fingertips. From requests
More informationBraindumps PMP 918q. PMI PMP. Project Management Professional v5
Braindumps PMP 918q Number: PMP Passing Score: 800 Time Limit: 120 min File Version: 26.5 http://www.gratisexam.com/ PMI PMP Project Management Professional v5 This is my first share of braindumps questions.
More informationTestkings PMP 705q. PMI PMP. Project Management Professional v5
Testkings PMP 705q Number: PMP Passing Score: 800 Time Limit: 120 min File Version: 14.5 PMI PMP Project Management Professional v5 This is my first share of braindumps questions. Very helpful study center
More informationAudio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program
Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications
More informationROLES AND RESPONSIBILITIES
Audio Sessions Session 2 ROLES AND RESPONSIBILITIES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org
More informationCONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell:
CONSTRUCTION MANAGEMENT By GREEN PLANET SERVICES Lesley Padayachee Cell: 084 525 4720 Lesley.gpes@gmail.com 5 th FEBRUARY 2013 CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process
More informationProcurement Standards Expectations Document
Procurement Standards Expectations Document Certain of the procurement requirements of 2 CFR 200 are explicit statements of what the University would consider as general expectations of any University
More informationPOLICY MANUAL ROSSBURN MUNICIPALITY MUNICIPAL TENDERING AND PROCUREMENT POLICY
Purpose: To clearly define the tendering and purchasing standards of the Rossburn Municipality and to provide guidance to municipal employees, by means of a comprehensive tendering and purchasing policy
More informationFare Systems Project Management
0 PRESENTATION Fare Systems Project Management 2011 APTA Fare Collection Workshop Fare Collection 101 Miami, FL March 28, 2011 1 Table of Contents Team Formation Project Lifecycle Project Definition Specification
More informationPurchasing and Procurement Policy
Purchasing and Procurement Policy Purpose The purpose of this document is to implement the requirements of state law with regard to procurement and bidding on public contracts for public works, goods,
More informationPMP TRAINING COURSE CONTENT
PMP TRAINING COURSE CONTENT SECTION1: INTRODUCTION PMI, PMP AND PMBOK What is PMI, PMP, and PMBOK? What do I get out of PMP? How do I get certified? Exam qualifications and PM experience Guidelines to
More informationFlexible IT: Contracting Strategies for Infrastructure as-a-service White Paper
Flexible IT: Contracting Strategies for Infrastructure as-a-service White Paper About this Paper: ViON Corporation has provided technology Infrastructure as a Service (IaaS) to government agencies since
More informationSubcontract Management Certification Program (ScMCP ) SUBCONTRACT MANAGEMENT TECHNICAL COMPETENCIES. SUBCONTRACT MANAGER (ScM)
Competency 1. Determination of How Best to Satisfy Requirements for the Mission Area a. Provide proactive business advice on requirements documentation based on analysis of requirements and performance-based
More informationDocument B252TM 2007
Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation
More informationProject Manager s Roadmap We re all smarter together
Version 7.0a Project Manager s Roadmap We re all smarter together Think Top Down! Methodology Checklists Define Plan Execute Close Conflict Resolution Modes Contract Outsource Management Mentoring References
More informationTemplate for ToR for Transaction Advisory Services
Template for ToR for Transaction Advisory Services Addendum 1 Prepared by Genesis Analytics 4 December 2013 PPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services
More informationStrategic Sourcing Guidelines on Requests for Proposals and Invitations for Bid
Strategic Sourcing Guidelines on Requests for Proposals and Invitations for Bid Table of Contents Request for Proposal Overview Slide 3 RFP Timeline estimates Slide 4 Business Owner tasks (RFP) Slide 5
More informationPROJECT MANAGEMENT. By Pompeyo Rios
PROJECT MANAGEMENT By Pompeyo Rios PROJECT A project is a temporary endeavor undertaken to create a unique product, service, or result. Por example, constructing a building or plant, or implementing, improving,
More informationDefinitions. Group Purchasing Services Private for-profit or not-for-profit organizations that purchase goods and services on behalf of members.
Definitions Competitive Proposal* - i.e., a Request for Proposal (RFP), means a method of procurement whereby a technical proposal is solicited that explains how the prospective contractor will meet the
More informationBuilding Contract Closeout. Ahmed Abd Alla Gouda, Chief Contracting Officer
Building Contract Closeout Ahmed Abd Alla Gouda, Chief Contracting Officer Content Construction Contracts Management from Award to Close Out. Barriers to Effective Construction Contract Management. Economy
More informationRecommended Practices for Subcontractor Management
Recommended Practices for Subcontractor Management Athens PM Conference June 18, 2012 Christos Vassilicos Agenda Introduction & Context A Subcontractor Management Case Study Recommended practices across
More informationProcurement Documents for Progressive Design-Build Projects
Procurement Documents for Progressive Design-Build Projects March 22, 2013 John Awezec, P.E., DBIA HDR Engineering, Inc. John Doller, P.E. Carollo Engineers, Inc. Peter Hughes Executive Director WDBC Model
More informationIMPLEMENTING ARRANGEMENT TEMPLATE (Model for Government-to-Government Joint Procurement Procedure)
Appendix A-3 IMPLEMENTING ARRANGEMENT TEMPLATE (Model for Government-to-Government Joint Procurement Procedure) Note: Additional aspects to be considered when performing a Joint Procurement are also found
More informationS.No RFP Particulars Project Management Equipment Planning: Measurement & Payment:
S.No RFP Particulars Project Management Can project initiation approval process be created, 1 planned, managed and tracked in the system? Can different types of project lifecycle be defined and 2 managed
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES OCTOBER 09, 2014 EAST BAY REGIONAL PARK DISTRICT Atlas Road Extension Improvements POINT PINOLE REGIONAL SHORELINE PROPOSALS DUE: 2:00PM, NOVEMBER
More informationLCS International, Inc. PMP Review. Chapter 3 Developing the Project Scope Statement. Presented by David J. Lanners, MBA, PMP
PMP Review Chapter 3 Developing the Project Scope Statement Presented by David J. Lanners, MBA, PMP These slides are intended to be used only in settings where each viewer has an original copy of the Sybex
More informationProcurement Management Processes
Procurement Management Processes Olga Botero PM630-1004A-01 Contracting and procurement in project management Dr. Tony Prensa October 8 th 2010 Project Procurement Management includes the processes necessary
More informationTexas School for the Blind and Visually Impaired Contract Management Guide
Texas School for the Blind and Visually Impaired Contract Management Guide TSBVI Contract Management Guide Page 1 of 9 June 2017 TABLE OF CONTENTS Section Title Page No. 1. INTRODUCTION 3 2. PROCUREMENT
More informationPROJECT INTEGRATION MANAGEMENT. 1 Powered by POeT Solvers Limited
PROJECT INTEGRATION MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROCESSES BY PROCESS GROUP Initiating Planning Executing Monitoring and controlling Closing 4.1 Develop Project Charter
More informationActualTests.CAPM.660Questions. Certified Associate in Project Management (CAPM)
ActualTests.CAPM.660Questions Number: CAPM Passing Score: 800 Time Limit: 120 min File Version: 4.1 http://www.gratisexam.com/ Certified Associate in Project Management (CAPM) I have corrected few questions
More informationAttachment D: Cost Proposal, RFP Section 3.4
ATTACHMENT D: COST PROPOSAL, RFP SECTION 3.4 Instructions: Use this template to comply with Section 3.4, Cost Proposal. Because the requirements of this RFP are part of a portfolio of projects designed
More informationOffice of Business and Financial Services Procurement and Contracts Division Section
2510.2 SUBJECT: PROCUREMENT OF GOODS AND SERVICES :1 OBJECTIVE: To establish uniform procurement policies and procedures for the acquisition of goods and services consistent with the City s Procurement
More informationProcurement Requirements under the Uniform Administrative Guidance
Procurement Requirements under the Uniform Administrative Guidance Purpose: This Technical Assistance Guide has been developed to assist Local Workforce Development Areas (LWDAs) in making informed decisions
More informationThe New Procurement Review for School Nutrition Programs
New Jersey Department of Agriculture 1 The New Procurement Review for School Nutrition Programs What New Jersey schools need to know August 2017 WEBINAR LEARNING OBJECTIVES Participants should be able
More informationCONTRACT MANAGEMENT AND ADMINISTRATION
CONTRACT MANAGEMENT AND ADMINISTRATION KEY ELEMENTS FOR EFFECTIVE C.A: COMMUNICATION Contract that Clearly Identifies what Success looks like Effective Written Communication Track Milestones and Conduct
More informationPROJECT EXECUTION PLANNING FOR COST AND SCHEDULE MANAGERS
PROJECT EXECUTION PLANNING FOR COST AND SCHEDULE MANAGERS ALLEN C. HAMILTON PMP CCE Project Management Associates LLC 3 Totten Way, Suite 110 Morris Plains, New Jersey 07950 USA Telephone: +1 973 984-1853
More informationConstruction Project Management Training Curriculum Integration Map
Construction Project Management Training Curriculum Integration Map Value of the Project Management is being recognized all over the world. Most businesses manage their business by successfully implementing
More informationRequest for Quotation for Subscription Management Services Solicitation Number RFQ Subscription Service
Request for Quotation for Subscription Management Services Solicitation Number 2019-2021 RFQ Subscription Service The Library Network (TLN) seeks price quotations from qualified vendors who will provide
More informationSTUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems
STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems January 2017 CON170, Unit 5 Lesson 1 Cost Analysis Process and Players
More informationControlling Insurance. Accounting/Reporting. "Elements" Programs. Governmental Fund. Leadership,Manage ment and. Acillary Service.
THE EDUCATIONAL ENTERPRISE A. and - Identify and apply various organizational leadership models - Identify techniques for motivating others, delegating authority, decision making, information processing,
More informationUniversity of Kansas Procurement Services
University of Kansas Procurement Services PURCHASING PROCEDURES MANUAL 1 Contents 1.0 DEPARTMENTAL PURCHASING AUTHORITY... 4 1.1 Introduction... 4 1.2 Use of Mandatory Contracts and Preferred Agreements...
More information