1 Major environmental impact assessment (EIA) processes in Queensland By Dr Chris McGrath (8 November 2011) Environmental impact assessment (EIA) is the term used to describe a variety of processes used to assess the environmental impacts of a proposal and the ways of mitigating those impacts. One form of EIA is the preparation of an Environmental Impact Statement (EIS), which is a document that generally describes: the proposed development; the relevant environment; potential impacts of the development on the environment; ways of mitigating impacts to the environment; and alternatives to the proposed development. The purpose of EIA is normally to inform the relevant decision-maker of potential environmental impacts and mitigation measures to enable them to decide whether to allow the development to proceed and what conditions, if any, should be placed upon it. Under Queensland law there are a range of EIA processes that may potentially be triggered or required by government decision-makers. The major ones are as follows: Statute 1. Sustainable Planning Act 2009 (Qld) (SPA) ss and Environmental Protection Act 1994 (Qld) (EPA) ss State Development and Public Works Organisation Act 1971 (Qld) (SDPWOA) ss Environment Protection and Biodiversity Conservation Act 1999 (Cth) (EPBC Act), Part 8, ss Summary of EIA provisions Contains a general procedure of information requests for any development application and public notification for any impact assessable development application (Figure 1). A special EIS process for assessing controlled actions under a bilateral agreement for the EPBC Act is provided in Part 2 of Ch 9 (ss ) but is rarely used (Figure 2). Contains an EIS process generally limited to assessing applications for an environmental authority (mining lease) and petroleum extraction (including natural gas extraction) (Figure 3). Linked to the EPBC Act through a bilateral agreement. General power to declare a significant project and require an EIS involving public notification (Figure 4). Procedure over-rides EIA processes under SPA and EPA. Linked to the EPBC Act through a bilateral agreement. Public notice and submissions on all referrals to determine whether they are controlled actions and, in addition, contains six major EIA procedures for assessing impacts of controlled actions (Figure 5): Accredited assessment process; Assessment on referral information; Assessment on preliminary documentation; Public Environment Report; Environmental Impact Statement; Public Inquiry. Accredited assessment processes include a State EIA procedure under a bilateral agreement. A bilateral agreement is in force for Queensland and is typically used whenever an EIS is required. Flowcharts showing the major steps and stages in the SPA information request and EIS processes are provided in Figures 1-2 and for the EIS process in the EPA, SDPWOA, EPBC Act in Figures 3-5. These flowcharts do not include further EIA which may occur during court proceedings regarding the approval processes. 1
2 Figure 1: Information request & public notification process in the integrated development assessment system (IDAS) of the Sustainable Planning Act 2009 (Qld) prepares response to information request(s) >15 BD Development Information Public End of Decision Application request(s) notification notification (s324) (s260) (s276) (for Impact period Assessment (s307) only) (s297) (for Impact Assessment only) Note: BD = business days 2
3 Figure 2: EIS process under Chapter 9 of the Sustainable Planning Act 2009 (Qld) (SPA) requests DLGP to prepare terms of reference (s690) >15BD prepares draft EIS (s693) >30BD changes draft EIS or prepares supplementary EIS if requested Draft terms Public Terms of Public Final day EIS of reference notification Reference notification for assessment prepared by of ToR for EIS of draft EIS submissions report DLGP (s691) finalised (s694) (s697) (s691) (s692) on Terms of Ref. on draft EIS (s695) Note: DLGP = the Queensland Department of Local Government & Planning; and BD = business days 3
4 Figure 3: EIS process under the Environmental Protection Act 1994 (Qld) prepares draft terms of reference (ToR) prepares EIS >30 BD >30 BD amends EIS or prepares supplementary EIS if requested Decision that Public ToR Decision Public Final EIS EIS required notification finalised that EIS notification day for assessment for mining or of draft ToR (s46) complies of EIS submissions report petroleum activity (ss42-43) with ToR (s51) (s52) (s57) (ss162 & 310E); (s49) or voluntary EIS (ss70-72) on ToR on EIS (s54) Note: BD = business days 4
5 Figure 4: EIS process under the State Development and Public Works Organisation Act 1971 (Qld) prepares initial advice statement (s27(a)) prepares EIS prepares supplementary EIS if requested >28 days Declaration of Public Terms of Public Final day Coordinator significant notification Reference notification for sub- General s project by that EIS is for EIS of EIS missions report Coordinator- required & finalised (s33) (s35) General draft ToR (s30) Report (s29) (s26) on Terms of Ref. on EIS (s34) 5
6 Figure 5: EIS process under the Environment Protection and Biodiversity Conservation Act 1999 (Cth) SPA see Figure 2 refers action No further assessment required If Queensland bilateral applies EPA see Figure 3 (No) Yes Accredited assessment process Assessment on referral information Assessment on preliminary documentation SDPWOA see Figure 4 Referral Public Decision Decision (ss 68-70) notice whether on method of referral controlled of assessment (s74) action (s87) (s75) Public Environment Report Environmental Impact Statement Public Inquiry Process if EIS required on referral (s74) prepares draft EIS (s103) >20 BD finalises EIS (s104) List of acronyms BD business days EIS environmental impact statement EPA Environmental Protection Act 1994 (Qld) s section [number in legislation] SDPWOA State Development & Public Works Organisation Act 1971 (Qld) SPA Sustainable Planning Act 2009 (Qld) Minister gives Invitation Final day Department for public for public Secretary EIS guidelines comment comment prepares (s101a) on draft EIS recommendation report (s105) Public comment on draft EIS (s103) 6
COAL AND COAL SEAM GAS REGULATION
COAL AND COAL SEAM GAS REGULATION The Australian Government protects water resources from the impacts of coal and coal seam gas development through the water trigger provisions of the Environment Protection
More informationPART A INTRODUCTION TO THE AEIS 1. PURPOSE OF THE ADDITIONAL
PART A INTRODUCTION TO THE AEIS 1. PURPOSE OF THE ADDITIONAL information to the environmental impact statement 1 1.1. Consultation process since release of the EIS 1 2. ANALYSIS OF SUBMISSIONS 4 2.1. Number
More informationGUIDELINE. environmental management of mining. GUIDELINE 11 - Terms of Reference and Preparation of an Environmental Impact. Statement.
GUIDELINE environmental management of mining GUIDELINE 11 - Terms of Reference and Preparation of an Environmental Impact Statement Content: 1 Introduction 2 Background 3 Objectives page 1 page 1 page
More informationProtection of Ramsar Wetlands under the EPBC Act
Protection of Ramsar Wetlands under the EPBC Act 1. INTRODUCTION The Commonwealth Environmental Protection and Biodiversity Conservation Act 1999 (the EPBC Act ) commenced on 16 July 2000 and brought about
More informationProtection of World Heritage Properties under the EPBC Act
Protection of World Heritage Properties under the EPBC Act 1. INTRODUCTION The Commonwealth Environmental Protection and Biodiversity Conservation Act 1999 (the EPBC Act ) commenced on 16 July 2000 and
More informationCaval Ridge Mine Change Request 8 Accommodation Village Condition Changes
Caval Ridge Mine Change Request 8 Accommodation Village Condition Changes 31 May 2013 Contents Executive Summary... 3 1 Introduction... 5 1.1 Project Background... 6 1.1.1 Bowen Basin Coal Growth Project...
More informationPolicy for Vegetation Management Offsets 30 July 2008
Policy for Vegetation Management Offsets 30 July 2008 Offset History During development of the current vegetation management framework, the Minister gave a commitment to industry stakeholders that a policy
More informationEnvironmental Impact Assessment in Western Australia
Environmental Impact Assessment in Western Australia Fact Sheet Updated February 2011 An introduction to Environmental Impact Assessment in Western Australia Environmental impact assessment under the Environmental
More informationClimate Change and Renewable Energy Bill 2017*
Queensland Climate Change and Renewable Energy Bill 2017* Current DRAFT as at 22 December 2017 *Material in this draft Bill has been excerpted from the Climate Change Act 2017 (Vic) and the Climate Change
More informationLand and Resources Tribunal. REGISTRY: Brisbane NUMBERS: AML 207/2006 ENO 208/2006 TENURE IDENTIFIER: 4761-ASA 2
Land and Resources Tribunal REGISTRY: Brisbane NUMBERS: AML 207/2006 ENO 208/2006 TENURE IDENTIFIER: 4761-ASA 2 Applicant: Respondents: Statutory Party: XSTRATA COAL QUEENSLAND PTY LTD & OTHERS AND QUEENSLAND
More informationRegister of Contaminated Land Consent Conditions
Regional Contaminated Land Capacity Building Program Register of Contaminated Land Consent Conditions AUGUST 2017 Regional Contaminated Land Capacity Building Program This publication was produced by the
More informationClimate Change and Renewable Energy Bill 2017*
Queensland Climate Change and Renewable Energy Bill 2017* Current DRAFT as at 24 November 2017 *Material in this draft Bill has been excerpted from the Climate Change Act 2017 (Vic) and the Climate Change
More informationChapter 4 Planning and statutory requirements. Chapter 4 Planning and statutory requirements
Chapter 4 Planning and statutory requirements Chapter 4 Planning and statutory requirements Contents Page number 4. Planning and statutory requirements 4-1 4.1 Approval under the EPBC Act 4-1 4.1.1 Controlled
More informationaustralian network of environmental defender s offices
australian network of environmental defender s offices Submission on Australia s Native Vegetation Framework Consultation Draft March 31 2010 Contact Us The Australian Network of Environmental Defender
More informationEN V I R O N M E N T PROTECTION AND BIODIVERSITY CO N S E RVAT I O N A C T U S E R S G U I DE
EN V I R O N M E N T PROTECTION AND BIODIVERSITY CO N S E RVAT I O N A C T U S E R S G U I DE Authors: Andrew Macintosh and Lyndall Kennedy Suggested citation: Macintosh, A. and Kennedy L. (2004) EPBC
More informationState Significant Development and State Significant Infrastructure
Planning, Development & Heritage State Significant Development and State Significant Infrastructure Last updated: July 2015 These Fact Sheets are a guide only and are no substitute for legal advice. To
More informationFacilitating Implementation of the Canada-Ontario Agreement on Environmental Assessment Cooperation
Federal/Provincial Environmental Assessment Coordination in Ontario A Guide for Proponents and the Public Facilitating Implementation of the Canada-Ontario Agreement on Environmental Assessment Cooperation
More informationBauxite Hills Project. Supplementary Report to the. Metro Mining. Section 3 Introduction. Environmental Impact Statement
Metro Mining Bauxite Hills Project Supplementary Report to the Environmental Impact Statement Section 3 Introduction 3 Introduction This section refers to submission comments relating to Chapter 1 Introduction
More informationBiodiversity Certification: what it is, how it works
Biodiversity Certification: what it is, how it works Nari Sahukar Senior Policy & Law Reform Solicitor, EDO NSW Leumeah, 16 November 2017 About EDO NSW: Community legal centre Independent from Government
More informationTHORNEY OPPORTUNITIES LTD ACN AUDIT & RISK COMMITTEE CHARTER
ACN 080 167 264 AUDIT & RISK COMMITTEE CHARTER ACN 080 167 264 1. Introduction 1.1 The Audit and Risk Committee (ARC) is a committee of the Board of Directors of Thorney Opportunities Ltd (Company). 1.2
More information2. Project Justification and Feasible Alternatives
2. Project Justification and Feasible Alternatives 2.1 Project Justification Energy intensive industries associated with the coal and gas sectors in the Surat region continue to drive electricity demand
More informationA1 Australian and South Australian Government Guidelines 813. A2 South Australian Government Guidelines 871
Appendix A EIS Guidelines CONTENTS A1 Australian and South Australian Government Guidelines 813 A2 South Australian Government Guidelines 871 A3 Northern Territory Government Guidelines 929 Olympic Dam
More informationPOLLUTION CONTROL LAW:
POLLUTION CONTROL LAW: A factsheet by the ACT EDO 2010 The Environment Protection Act 1997 is the Australian Capital Territory s main legislation for managing pollution. It requires that certain activities
More informationSouth Australian Native Title Services Ltd. Strategic Plan
South Australian Native Title Services Ltd Strategic Plan 2015 2020 This plan establishes the strategic direction of South Australian Native Title Services (SANTS) for the next five years. Native title
More informationParliamentary. Sustainable Ports Development Bill 2015
Parliamentary Sustainable Ports Development Bill 2015 Report No. 6, 55 th Parliament Infrastructure, Planning and Natural Resources Committee September 2015 Infrastructure, Planning and Natural Resources
More informationENVIRONMENTAL DEFENDER S OFFICE (ACT)
Pollution control law ENVIRONMENTAL DEFENDER S OFFICE (ACT) The Environment Protection Act 1997 is the Australian Capital Territory s main legislation for managing pollution. It requires that certain activities
More informationMINISTERIAL DESIGNATION FOR PROPOSED 66/11KV DARTMOUTH STREET ELECTRICITY SUBSTATION
DARTMOUTH STREET ELECTRICITY SUBSTATION PAGE 1 MINISTERIAL DESIGNATION FOR PROPOSED 66/11KV DARTMOUTH STREET ELECTRICITY SUBSTATION TOWN PLANNING ASSESSMENT REPORT PREPARED FOR REF: 111005 DARTMOUTH STREET
More informationAudit Committee Charter
Audit Committee Charter 1. Background The Audit Committee is a Committee of the Board of Directors ( Board ) of Syrah Resources Limited (ACN 125 242 284) ( Syrah or the Company ) that was established under
More informationEnvironmental Impact Assessment and Climate Change Australia
Environmental Impact Assessment and Climate Change Australia What we are hoping to get through today Overview of EIA in Australia Key climate change issues Projects with climate change adaptation issues
More informationREQUEST FOR EXPRESSION OF INTEREST FOR:
REQUEST FOR EXPRESSION OF INTEREST FOR: Gardening and Lawn Service and Maintenance Request Number: EOI 05 Issued By: Townsville Aboriginal and Islander Health Service Closing Time: 1700, 10 th June 2016,
More information31 January Great Barrier Reef Strategic Assessment Public Consultation Manager GPO Box 668 Brisbane QLD 4001
30 Hardgrave Rd WEST END, QLD 4101 tel +61 7 3211 4466 fax +61 7 3211 4655 edoqld@edo.org.au www.edo.org.au/edoqld 31 January 2014 Great Barrier Reef Strategic Assessment Public Consultation Manager GPO
More informationEnvironment Impact Assessment (EIA) Notification 2006
Environment Impact Assessment (EIA) Notification 2006 Information Sources: 1.) Environment Impact Notification 2006; Gazette of India, 14th September, 2006 2.) Green Tapism; Environment Support Group;
More informationPlanning Reform in WA
~ UDIA Luncheon ~ Wednesday, 31 March 2010 Eric Lumsden PSM Director General The Minister released Planning Makes it Happen A Blueprint for Key Priorities : - Major Project Facilitation - DAP s - National
More informationSubmission on the Land Management and Biodiversity Conservation Reforms. June 2017
Submission on the Land Management and Biodiversity Conservation Reforms June 2017 Table of contents Opening 3 Purpose 3 Background 3 General comments 4 1. Sensitive biodiversity values map 5 2. Biodiversity
More informationCoal seam gas, landholder rights and the law
Coal seam gas, landholder rights and the law Sue Higginson Senior Solicitor Lismore 4 September 2012 EDONSW Community Legal Centre Specialises in public interest environmental law matters since 1985 Mission:
More informationCOVER SHEET. Copyright 2004 (The authors) Accessed from:
COVER SHEET Low, Rouhshi and Christensen, Sharon (2004) Electronic signatures and PKI Frameworks in Australia. The Digital Evidence Journal, incorporating the e-signature Law Journal 1(2):pp. 56-59. Copyright
More informationRecords Disposal Schedule Charles Darwin University Procurement Services Charles Darwin University
Records disposal schedule Records Disposal Schedule Charles Darwin University Procurement Services Charles Darwin University Disposal Schedule No. For information and advice, please contact Department
More informationEPA Inquiry: Submission on behalf of Paper Australia Pty Ltd
Our reference AGPAPE16499-9101755/01 567 Collins Street, Melbourne VIC 3000 GPO Box 9925 Melbourne VIC Tel +61 396723000 Fax +61 396723010 www.corrs.com.au CORRS CHAMBERS WESTGARTH lawyers Sydney Melbourne
More informationDepartmental Manual Part 516
Departmental Manual Part 516 Page 1 of 1 U.S. DEPARTMENT OF THE INTERIOR BUREAU OF LAND MANAGEMENT Search BLM National Go What We Do Visit Us Information Center Get Involved Our Offices/Centers Contact
More informationLNP Policy for a Sustainable Coal Seam Gas Industry
LNP POLICY FOR THE DEVELOPMENT OF A SUSTAINABLE COAL SEAM GAS INDUSTRY IN QUEENSLAND INTRODUCTION Queensland is a State rich in energy and resources. A prosperous, well managed resources sector is critical
More informationThe EFGCP Report on The Procedure for the Ethical Review of Protocols for Clinical Research Projects in Europe (Update: April 2011) Ireland
The Procedure for the Ethical Review of Protocols for Clinical Research Projects in Europe (Update: April 2011) Ireland Question 1: What laws or regulations apply to an application for conducting a clinical
More informationThe Methods of Multilateral Diplomacy 1
The Methods of Multilateral Diplomacy 1 Dr Petru Dumitriu and Professor Dietrich Kappeler It is never possible to separate completely multilateral from bilateral diplomatic interaction. In fact, the two
More informationDerbyshire Constabulary GUIDANCE ON POLICE STAFF JOB EVALUATION USING HR PROGRESS POLICY REFERENCE 08/218
Derbyshire Constabulary GUIDANCE ON POLICE STAFF JOB EVALUATION USING HR PROGRESS POLICY REFERENCE 08/218 This guidance is suitable for Public Disclosure Owner of Doc: Head of Department, Human Resources
More informationPROPOSED VOLSPRUIT MINE, MOKOPANE DISTRICT, LIMPOPO PROVINCE. Background Information Document (BID) ESCIENCE ASSOCIATES (PTY) LTD.
ENVIRONMENTAL IMPACT ASSESSMENT (EIA), MINING RIGHT APPLICATION AND OTHER ANCILLARY LICENSING PROCESSES: PROPOSED PLATINUM GROUP METALS MINE & ASSOCIATED INFRASTRUCTURE PROPOSED VOLSPRUIT MINE, MOKOPANE
More informationLooking After Our Environment
Item: 12.06 Subject: DRAFT BIODIVERSITY CERTIFICATION ASSESSMENT AND APPLICATION - PORT MACQUARIE AIRPORT AND SURROUNDING LAND Presented by: Development and Environment Services, Matt Rogers Alignment
More informationTHORNEY TECHNOLOGIES LTD ABN: AUDIT & RISK COMMITTEE CHARTER
ABN: 66 096 782 188 AUDIT & RISK COMMITTEE CHARTER ABN: 66 096 782 188 This policy was approved on 15 November 2016, to have effect from the relisting of Thorney Technologies Ltd (Company) as an ASX Listed
More informationPart 3A Major Projects (Now Repealed)
Planning, Development & Heritage Part 3A Major Projects (Now Repealed) Last updated: August 2013 These Fact Sheets are a guide only and are no substitute for legal advice. To request free initial legal
More informationSTRUCTURAL ENGINEER S SERVICES SCOPE
ROYAL BOROUGH OF GREENWICH STRUCTURAL ENGINEER S SERVICES SCOPE WOOLWICH CREATIVE DISTRICT PROJECT status: R1 purpose: For information version: 1.0 date: 07/03/2016 1 This version Authored by: name: Nick
More informationThe Canadian EIA Process: The Purpose, The Process, The Players and The Pitfalls Part I The Purpose and Process
The Canadian EIA Process: The Purpose, The Process, The Players and The Pitfalls Part I The Purpose and Process Presented by: Teresa Meadows, Senior Associate TODAY S SESSION 1. Why does a project engineer
More informationCalifornia Environmental Quality Act Part 1: CEQA Basics
California Environmental Quality Act Part 1: CEQA Basics California Preservation Foundation Webinar June 10, 2014 Presented by Chris McMorris Partner / Architectural Historian Overview of CEQA California
More informationService Description. nbn Platform Interfacing Service Module. Wholesale Broadband Agreement
Service Description nbn Platform Interfacing Wholesale Broadband Agreement This document forms part of NBN Co s Wholesale Broadband Agreement, which is a Standard Form of Access Agreement for the purposes
More informationInformation on the focal point for the Convention. Information on the point of contact for the Convention
Questionnaire for the REPORT OF MONTENEGRO ON THE IMPLEMENTATION OF THE CONVENTION ON ENVIRONMENTAL IMPACT ASSESSMENT IN A TRANSBOUNDARY CONTEXT in the period 2006 2009 Information on the focal point for
More informationInformation on the focal point for the Convention. Information on the point of contact for the Convention
Questionnaire for the REPORT OF LATVIA ON THE IMPLEMENTATION OF THE CONVENTION ON ENVIRONMENTAL IMPACT ASSESSMENT IN A TRANSBOUNDARY CONTEXT in the period 2006 2009 Information on the focal point for the
More informationManaging land contamination during the mine closure and rehabilitation process NSW Department of Industry Division of Resources & Energy
Managing land contamination during the mine closure and rehabilitation process NSW Department of Industry Division of Resources & Energy Dr David Blackmore Director Environmental Sustainability Unit Nov
More informationErgon Energy Corporation Limited Board Charter. 26 August 2016
Ergon Energy Corporation Limited Board Charter 26 August 2016 Ergon Energy Corporation Limited Board Charter This charter was approved by the board of Ergon Energy Corporation Limited (EECL) on 29 July
More informationFOREST SERVICE MANUAL NATIONAL HEADQUARTERS (WO) WASHINGTON, DC
Page 1 of 9 FOREST SERVICE MANUAL NATIONAL HEADQUARTERS (WO) WASHINGTON, DC Amendment No.: 1900-2012-1 Effective Date: June 12, 2012 Duration: This amendment is effective until superseded or removed. Approved:
More informationImplications of State Significant Projects in Queensland
Gary Owen Garner Lecturer in Property & Urban Development Queensland University of Technology, GPO Box 2434 Brisbane 4001 Australia Email g.garner@qut.edu.au Phone +61 7 3138 5327 Fax +61 7 3138 1170 Abstract
More informationCEQA BASICS. The California Environmental Quality Act. Prepared for: Orange County Department of Education. Prepared by:
The California Environmental Quality Act CEQA BASICS Prepared for: Orange County Department of Education Prepared by: Contact: DWAYNE MEARS, AICP Principal 714.966.9220 dmears@planningcenter.com The Beginning
More informationBulgarian JI Guidelines. 2006, September
Bulgarian JI Guidelines 2006, September Table of Contents BULGARIAN JI GUIDELINES... 1 1. International Requirements... 1 2. JI Process in Bulgaria... 3 3. Participants... 4 Step 6: Request for Letter
More informationAudit report VET Quality Framework
The QCAA uses an exceptions-based model of reporting. This means that the QCAA will only record a comprehensive description of evidence gathered and compliance findings if noncompliance is identified at
More informationB. Stakeholder Guide: Infrastructure and utility providers
B. Stakeholder Guide: Infrastructure and utility providers Why is the Government proposing new legislation? As our population grows, the Government wants to accelerate the building of new communities and
More informationNumber 42 of 2001 YOUTH WORK ACT 2001 REVISED. Updated to 4 June 2014
Number 42 of 2001 YOUTH WORK ACT 2001 REVISED Updated to 4 June 2014 This Revised Act is an administrative consolidation of the. It is prepared by the Law Reform Commission in accordance with its function
More informationAUDIT AND RISK COMMITTEE For Office of the Police Ombudsman for Northern Ireland. Terms of Reference. September 2016
AUDIT AND RISK COMMITTEE For Office of the Police Ombudsman for Northern Ireland Terms of Reference September 2016 This Terms of Reference (TOR) updates the previous Terms of Reference as at May 2014.
More informationBill 36, the Alberta Land Stewardship Act sets the bar for responsible regional planning
April 27, 2009 Bill 36, the Alberta Land Stewardship Act sets the bar for responsible regional planning Proposed Act respects property rights and local decision-making Edmonton... Future development in
More informationNSW Heritage Law. Planning, Development & Heritage. Overview. Last updated: August 2012
Planning, Development & Heritage NSW Heritage Law Last updated: August 2012 These Fact Sheets are a guide only and are no substitute for legal advice. To request free initial legal advice on an environmental
More informationThe World of Restructuring and Redundancies
The World of Restructuring and Redundancies Dr Graham Smith and Stuart Pill Partners, Clayton Utz, Melbourne 16 and 17 May 2013 Clayton Utz 309933391 Overview Universities need to remain flexible to meet
More informationInquiry into Australian Securities and Investment Commission Amendment (Corporations and Markets Advisory Committee Abolition) Bill 2014
3 March 2015 Dr Kathleen Dermody Committee Secretary Senate Standing Committees on Economics PO Box 6100 Parliament House Canberra ACT 2600 T +61 2 9223 5744 F +61 2 9232 7174 E info@governanceinstitute.com.au
More informationSubmission to the Energy Market Reform Working Group Consultation on regulatory implications of New Products and Services in the Electricity Market
Executive Summary Submission to the Energy Market Reform Working Group Consultation on regulatory implications of New Products and Services in the Electricity Market Clean Energy Council (CEC) welcomes
More informationOctober Guide to the Workplace Relations Commission workplacerelations.ie
October 2017 Guide to the Workplace Relations Commission 1890 80 80 90 workplacerelations.ie Contents Introduction... 3 1: Information and Customer Services... 5 2: Advisory Service... 6 3: Conciliation
More informationAGREEMENT ON BALTIC PARLIAMENTARY AND GOVERNMENTAL COOPERATION BETWEEN THE REPUBLIC OF ESTONIA, THE REPUBLIC OF LATVIA AND THE REPUBLIC OF LITHUANIA
AGREEMENT ON BALTIC PARLIAMENTARY AND GOVERNMENTAL COOPERATION BETWEEN THE REPUBLIC OF ESTONIA, THE REPUBLIC OF LATVIA AND THE REPUBLIC OF LITHUANIA The Republic of Estonia, the Republic of Latvia and
More informationDraft European Parliament & European Commission Agreement. on the establishment of a "Transparency Register"
Draft European Parliament & European Commission Agreement on the establishment of a "Transparency Register" (For: Organisations and individuals working as independent engaged in EU policy making and policy
More informationOperating Requirements Manual 11 October 2015 Version 1
Operating Requirements Manual 11 October 2015 Version 1 Contents 1 Introduction 1 2 Interface Risk Management 2 2.1 Interface Risk Assessment 2 2.2 Interface Risk Management Plan 4 2.3 Provision of Assistance
More informationTECHNICAL PROPOSAL GUIDELINES FOREWORD
FOREWORD This document is intended for use by proponents prior to contacting the Ministry of Environment (the ministry) about an approval under The Environmental Assessment Act. It is aimed at helping
More informationThis is a working draft report provided for information purposes only, and may be modified prior to finalisation. It has been prepared on the basis
This is a working draft report provided for information purposes only, and may be modified prior to finalisation. It has been prepared on the basis of the design and engineering work as part of the feasibility
More informationenvironmental defender s office new south wales
environmental defender s office new south wales Submission on the Discussion Paper for the Metropolitan Strategy Review Sydney Towards 2036 30 April 2010 The EDO Mission Statement: To empower the community
More informationENVIRONMENTAL LAW CENTRE. April 19, 1999
CEAA, as well as Alberta resource and environmental protection legislation, serves the interests of Albertans, and, consequently, its terms must be met as framed. AWA, et al. v. Minister of Fisheries and
More informationACHSM MASTER HEALTH SERVICE MANAGEMENT COMPETENCY FRAMEWORK Draft Version 1.7
ACHSM MASTER HEALTH SERVICE MANAGEMENT COMPETENCY FRAMEWORK Draft Version 1.7 Introduction This version of the draft ACHSM Master Health Service Management Competency Framework has been developed by an
More informationProvince - Department of Municipal and Provincial Affairs Nunatsiavut Government. Activities Responsibility Timing
SUBJECT: Consultation on land use laws Activity Sheet: 10-1 OBLIGATION: PARTIES: Consult on land use policy or development regulation in Labrador Inuit Settlement Area (LISA) outside Labrador Inuit Lands
More informationForest Stewardship Council FSC STANDARD. Requirements for sourcing Controlled Wood FSC-STD V 3-0 EN. Controlled Wood
Forest Stewardship Council FSC STANDARD Requirements for sourcing Controlled Wood Controlled Wood Title: Document reference code: Approval date and body: Requirements for sourcing Controlled Wood DRAFT
More informationBULGARIA - WIND FARMS IN BALCHIK AND KALIAKRA (VIA PONTICA)
SUMMARY OF GOVERNMENT REPORT File open: BULGARIA - WIND FARMS IN BALCHIK AND KALIAKRA (VIA PONTICA) Strasbourg, 2 December 2015 Following the Standing Committee Recommendation the Environmental Impact
More informationPollution & Environmental Harm
Pollution & Environmental Harm Fact Sheet 27 Updated December 2010 An introduction to Pollution and Environmental Harm There are a large range of activities that can lead to pollution or cause environmental
More informationNido Petroleum Limited Audit & Risk Management Committee Charter (AS APPROVED 24 MAY 2011)
Nido Petroleum Limited Audit & Risk Management Committee Charter (AS APPROVED 24 MAY 2011) Nido Petroleum Limited Audit & Risk Management Committee Charter Approved 24 May 2011 1. INTRODUCTION This charter
More informationMINERALS COUNCIL OF AUSTRALIA VICTORIAN DIVISION
H MINERALS COUNCIL OF AUSTRALIA VICTORIAN DIVISION SUBMISSION TO THE INDEPENDENT INQUIRY INTO THE VICTORIAN ENVIRONMENTAL PROTECTION AUTHORITY 30 OCTOBER 2015 TABLE OF CONTENTS 1. EXECUTIVE SUMMARY...
More informationIAIAsa August 2014 Betty Mdala Department of Environmental Affairs
D R A F T S TA N D A R D F O R T H E S T O R A G E O R S T O R A G E A N D H A N D L I N G O F D A N G E R O U S G O O D S A N D I D E N T I F I C AT I O N O F A C T I V I T I E S W H I C H M AY C O M
More informationIs ISO14001 Effective? Jessica Crosthwaite October 2015
Is ISO14001 Effective? Jessica Crosthwaite October 2015 Masters research short thesis 2015 Overview Global and local trends in ISO14001 adoption Largest voluntary environmental management system. Fact
More informationCLASSIFICATION REVIEW GUIDELINE FOR STAFF AND SUPERVISORS. Table of Contents
CLASSIFICATION REVIEW GUIDELINE FOR STAFF AND SUPERVISORS Table of Contents 1.0 Context 2 2.0 General Principles 2 3.0 Timeline and Action 3 4.0 Self Guided Formats 4 4.1 Training 4 5.0 Alignment with
More informationTHE TASMANIAN WILDERNESS WORLD HERITAGE AREA: PROTECTED BY THE ENVIRONMENT PROTECTION AND BIODIVERSITY CONSERVATION ACT 1999?
THE TASMANIAN WILDERNESS WORLD HERITAGE AREA: PROTECTED BY THE ENVIRONMENT PROTECTION AND BIODIVERSITY CONSERVATION ACT 1999? TOM BAXTER The theme of the 2008 ALTA Conference, The Law, the Environment,
More informationCEF. Cumulative Effects Framework. Interim Policy. for the Natural Resource Sector. October Cumulative Effects Framework
CEF Cumulative Effects Framework Cumulative Effects Framework Interim Policy for the Natural Resource Sector October 2016 Policy Approval The Cumulative Effects Framework Interim Policy is approved for
More informationCentral NSW Regional Contaminated Land Policy Template
Central NSW Regional Contaminated Land Policy Template Contamination Central: Supporting safe, stable and sustainable redevelopment of land in Central West NSW. Funded by the New South P a g e 1 {Instruction
More informationMSPO Implementation and Voluntary Schemes in Malaysia
MSPO Implementation and Voluntary Schemes in Malaysia ISCC Technical Committee South East Asia Fifth Meeting 5 April 2016 The Hotel Magani & Spa, Bali, Indonesia Ainie Kuntom Malaysian Palm Oil Board Outline
More informationRegulation and Management of Contaminated Land in NSW. NSW EPA, Stephanie Yu CLM Program 18 November 2015
Regulation and Management of Contaminated Land in NSW NSW EPA, Stephanie Yu CLM Program 18 November 2015 1 Overview NSW legislation and Contaminated Land Framework Roles and responsibilities Significantly
More informationLATHOM HIGH SCHOOL. Redundancy and Workforce Planning/Redundancy Policy and Guidelines For Schools with Delegated Budgets
LATHOM HIGH SCHOOL Redundancy and Workforce Planning/Redundancy Policy and Guidelines For Schools with Delegated Budgets June 2015 INDEX Page Number Four Four Five Six Six Seven Seven Seven Redundancy
More informationNHS Milton Keynes Clinical Commissioning Group
NHS Milton Keynes Clinical Commissioning Group Annual Audit Letter for the year ended 31 March 2016 July 2016 Ernst & Young LLP Contents Contents Executive Summary... 2 Purpose... 6 Responsibilities...
More informationConsultation Regulatory Impact Statement
Consultation Regulatory Impact Statement Post Implementation Review of the Industry Levy to fund the petroleum and gas water functions of the Office of Groundwater Impact Assessment December 2016 This
More informationCOUNCIL OF MINISTERS DECREE NO 48/06 OF 1 SEPTEMBER
COUNCIL OF MINISTERS DECREE NO 48/06 OF 1 SEPTEMBER The Petroleum Activities Law (Law 10/04 of 12 November) explicitly accepted the principle of public tendering as a necessary and compulsory system for
More informationThe Australian Consumer Law. An introduction
The Australian Consumer Law An introduction November 2010 Commonwealth of Australia 2010 ISBN 978-0-642-74590-3 This work is copyright. Apart from any use as permitted under the Copyright Act 1968, no
More informationNATIONAL POLLUTION PREVENTION PLANS REGULATIONS THE NATIONAL CLIMATE CHANGE RESPONSE POLICY
NATIONAL POLLUTION PREVENTION PLANS REGULATIONS THE NATIONAL CLIMATE CHANGE RESPONSE POLICY AIR QUALITY GOVERNANCE LEKGOTLA 4 OCTOBER 2016 Purpose of the Presentation Request the 11 th Air Quality Governance
More informationStage 2 Procurement Media Protocols
Stage 2 Procurement Media Protocols Contents Purpose... 3 Applicability... 3 Overview... 3 Gold Coast Light Rail Media Policy... 3 Media Policy during EOI Process... 3 Media Enquiry Procedure... 3 Request
More informationDRAFT SUBMISSION REGARDING
DRAFT SUBMISSION REGARDING Biodiversity Certification Draft Assessment Methodology DATE July 2010 Opening: The Local Government Association of NSW and Shires Association of NSW (the Associations) are the
More informationDetermining Whether a Proposal is Subject to the National Environmental Policy Act (NEPA) Section 102 Updated March
Determining Whether a Proposal is Subject to the National Environmental Policy Act (NEPA) Section 102 Updated March 2005 1 This paper presents some key thresholds to consider when determining whether a