Timothy Stokes. PE, MBA Delcan Corp, Senior Principal Denver, CO
|
|
- Laurel Hall
- 5 years ago
- Views:
Transcription
1 Improving Project Management to Realize Successful Outcomes by Focusing on Requirements Management Timothy Stokes. PE, MBA Delcan Corp, Senior Principal Denver, CO
2 Introduction Begin at the beginning, the King said gravely, and go on till you come to the end; then stop. Lewis Carroll, Alice in Wonderland It was a painful lesson to learn, but it was and engineer s dream I had a great time, but, in the end, it taught me a great lesson in business planning. You need to minimize investment as well the risks. We all need to think of business, not straight engineering anymore. Roger Taur
3 Requirements Drive Projects In 1994, the Standish Group found that the top three factors that caused project failure were: 1. Lack of user input, 2. Incomplete requirements 3. Changes to the requirements. Requirements Management was developed primarily in the software industry. Requirements Management is relatively new to the infrastructure industry. It is a process area within project management and systems engineering.
4 Infrastructure Delivery Traditionally delivered projects using a design-bid-build delivery method. New ways to be efficiently deliver projects. Construction management at risk, design-build, and public-privatepartnership models such as designbuild-operate-maintain.
5 Design - Build Design - Bid - Build Paradigm Shift: Design-Bid-Build to Design-Build Construction FACILITY 100% TRACK 100% SYSTEMS 100% Tendering Acceptance / Commissioning Design and Define Requirements Preliminary Design and Requirements Construction FACILITY < 30% 100% Design Support During Construction TRACK < 30% 100% Design Support During Construction SYSTEMS < 30% 100% Design Support During Construction Intense Development of RFQ / RFP Intense Design Review Acceptance / Commissioning Construction Oversight RFIs / Field Requested Design Changes / NCRs Design Tender / Bid Construction Accept / Commission
6 The Need for Requirements Management Requirements are explicit expressions of needs; what a process or product must accomplish. 6 traceability is a key concept
7 Classic V-Model of System Engineering System Requirements Verification and Validation System Integration & Acceptance Sub-System Requirements Construct / Inspect/Test Design Fabrication 7
8 Types of Requirements Functional Requirements What the resulting products or deliverables of the project should do in order to perform their intended function. E.g. design criteria Non-Functional Requirements Qualities, or properties the product must have in order for it to function as intended. E.g. safety and security, maintainability, reliability Project Management Requirements To assure the contractor implements management processes necessary to provide confidence, transparency, and accountability to the owner throughout the project that work is being performed to the satisfaction of the owner. E.g. quality, safety, public information management
9 Stakeholders Stakeholders commonly state their need through formal meetings or written communications. Understanding their needs is important so that they can be translated into technical requirements that are clear and understood by those implementing the project.
10 Requirements are used to Communicate What is Wanted
11 Requirements the Problem Requirements are the what s or the problem statements that are written in a technical manner that need to be addressed.
12 Design- the solution Specifications are the solutions or the how s to ensure that requirements are going to be fulfilled.
13 Design Solutions To Requirements Traditional Design Approach Requirements-Oriented Design Approach Good requirements can lead to more effective solutions. Advantage to develop innovative, optimum solutions. 13
14 Writing High-Quality Requirements Criteria Describes what, not how Traceable Single statement Necessary Clear meaning Correct Unique Consistent Feasible Verifiable Documented and accessible Terminology: shall, should, will 14
15 Requirements Management Process Involves the owner and stakeholders; Involves multiple engineering disciplines working co-operatively; Facilitates the contracted entities to transform a need into a reality; and Enables the owner to verify and validate whether the contractor has incorporated the requirements into the finished product.
16 Preparation of Requirements for a RFP For new rail and transit projects, requirements are communicated by the Request for Proposal (RFP) Transit Owner takes care of the Needs and the What's Design-Builder takes care of the How s If done properly, the owner only needs to confirm that requirements are being met. Should not need to inspect the work.
17 Requirements Management Process A formalized, planned and continually evolving series of activities. Output: Requirements that are incorporated into an RFP or similar document.
18 Needs Identification Approved RFP translates owner, operator, and stakeholder source needs into formal requirements 18
19 Categorization Approved RFP Checks for inconsistency, omission, duplication priority, WBS, responsibility, acceptance 19
20 Categorization WBS Concept
21 Documentation and Storage Approved RFP Inventory control, change history web-based tool with database engine 21
22 Validation with Stakeholders Approved RFP Stakeholders understand, agree, and support the requirements as presented in contracts 22
23 Verification Approved RFP Verify that requirements have been achieved. Traceability for confidence of acceptance.. 23
24 Verification Owner roles during project implementation is verifying or validating that requirements have been fulfilled. Design-Builder implements project management processes, which includes assurance methods (visibility that all work complies with requirements and design specifications, safety, environmental, systems integration, other management processes). Owner should not need to perform inspections (design checking or inspecting at the specification level)
25 Dealing with Changes Changes in scope should result in changes to requirements ensure change management at the requirement level.
26 Dealing with Interfaces Subsystem A Interfaces Subsystem B Develop Interface Requirements - ensure they are requirements - not something else. Verify that the design addresses each requirement, Validate that the construction and/or operations address each requirement.
27 Requirements Management Conclusions Offers a problem statement / solutions paradigm an enhanced way to manage projects. Offers a way to define and verify scope clear understanding of the Work that is traceable back to the overall project goals. Aids program management effort by offering visibility of dependencies, scope deviations, responsibilities and change control.
28
Timothy Stokes, PE, MBA Parsons, Principal Project Manager Denver, Colorado
A SE Approach to Enhance and Support the Acceptance Process for RTD FastTrack's Projects Timothy Stokes, PE, MBA Parsons, Principal Project Manager Denver, Colorado Key Take Away Points 1. Alternative
More informationFlorida Cleanroom Systems
Florida Cleanroom Systems Design Build Projects / Project Quality Control Plan (PQCP) Quality Control / Quality Assurance Manual May 2010 1 TABLE OF CONTENTS Section 1: Introduction 3 1.1 Defining Plan
More information1 Introduction. 20 August 1995; 19:29 1 Master04.Doc
1 Introduction This master thesis concludes the study of computer science at the Rijks Universiteit of Leiden. The mentor for this project is dr. L.P.J. Groenewegen. The topic addressed in this master
More informationA Systems Engineering Approach to Enhance and Support the Acceptance Process for RTD FasTracks Projects
A Systems Engineering Approach to Enhance and Support the Acceptance Process for RTD FasTracks Projects Timothy Stokes, PE Parsons Corp. Denver, CO OVERVIEW Project closeout is often the most neglected
More informationINS QA Programme Requirements
Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued
More informationWORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B
1. Work Plan & IV&V Methodology 1.1 Compass Solutions IV&V Approach The Compass Solutions Independent Verification and Validation approach is based on the Enterprise Performance Life Cycle (EPLC) framework
More informationGENERAL REQUIREMENTS FOR ENGINEERING AND DESIGN
Project Procedures GENERAL REQUIREMENTS FOR ENGINEERING AND DESIGN 07/28/2011 PAGE 1 OF 7 1.0 PURPOSE 1.1 PURPOSE OF ENGINEERING PROJECT PROCEDURES This P-4 series of Engineering Project Procedures provides
More informationDistribution Restriction Statement Approved for public release; distribution is unlimited.
CEMP-ET Engineer Regulation 1110-345-53 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 Engineering and Design STRUCTURAL STEEL CONNECTIONS Distribution Restriction Statement
More informationITER Quality Assurance
US ITER Central Solenoid Vendor Meeting ITER Quality Assurance by John Mashburn USIPO QA Manager 1 QA Topics ITER s Nuclear License Graded Approach Proposal QA Items Quality Plan Specific to Contract Manufacturing
More informationVALUE FOCUSED DELIVERY
VALUE FOCUSED DELIVERY Project Methodology 417 N 2nd Ave. Minneapolis, MN 55401 Table of Contents Project Methodology... 3 Figure 1: - Project Approach... 4 Phase 1 Inception Sprint... 5 Figure 2: Inception
More informationAPPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS
APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS Shared denotes whether a Contractor Resource may be responsible for that in addition to another identified. Contractor Required
More informationAssociation of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017
Company: Prepared By: Date: Changes from previous version highlighted in yellow. Paragraph Element Objective Evidence 2.1 Objective of Quality Assurance Program 2.2 Applicability and Scope 2.3 QA Program
More informationDesign Quality. Indu Lakshman
Design Quality Indu Lakshman Overview New product development (NPD) covers the complete process of bringing a new product to market. In commercial terms, new product development is described in the literature
More informationChapter 6. Software Quality Management & Estimation
Chapter 6 Software Quality Management & Estimation What is Quality Management Also called software quality assurance (SQA) s/w quality:- It is defined as the degree to which a system, components, or process
More informationDesign Compliance Matrix
Waste Treatment Plant Project Design Compliance Matrix Tracy Hawkins WTP Responsible Engineering Specialist 06-August-2015 Design Compliance Matrix (DCM) Overview AGENDA What is the Purpose of a DCM? What
More informationSystems Assurance within the Systems Engineering Lifecycle
Systems Assurance within the Systems Engineering Lifecycle Key Lessons & Benefits Rob Scarbro 12 th February 2013 1 Introduction Overview of Systems Assurance across a Project Life- Cycle Key objectives,
More informationTOPIC DESCRIPTION SUPPLEMENT for the SYSTEMS ENGINEERING SURVEY DESCRIPTION
1 2 Objectives of Systems Engineering 3 4 5 6 7 8 DoD Policies, Regulations, & Guidance on Systems Engineering Roles of Systems Engineering in an Acquisition Program Who performs on an Acquisition Program
More informationCapability Maturity Model for Software (SW-CMM )
PHASE-IV: SYSTEMS IMPLEMENTATION Software Quality Assurance Application Development Installation and Support Software Quality Assurance Capability Maturity Model for Software (SW-CMM ) The Capability Maturity
More informationKeynotes RLGA. QA and QC: Are They Different?
QA and QC: Are They Different? By Ronald L. Geren, AIA, CSI, CCS, CCCA, SCIP Quality assurance (QA) and quality control (QC) are often used interchangeably to mean the same thing or together as if one
More informationQuality System Manual - Section 00
Quality System Manual - Section 00 INDEX AND REVISION STATUS Issued by: Quality Assurance Eff. Date: 00/00/00 Rev.: A Pg. 1 of 4 Organization of this manual is the same as the sectional organization of
More informationBHG Operational Awareness Program May 8, 1998 Configuration Management Revision 0 Page 1 of 11 CONFIGURATION MANAGEMENT
Page 1 of 11 CONFIGURATION MANAGEMENT 1.0 SCOPE This Performance Assessment Guide for Configuration Management will be used to carry out the oversight responsibility of the U.S. Department of Energy (DOE)
More informationISACA Systems Implementation Assurance February 2009
ISACA Pressures Today Pressure to increase realization of value from IT spending Pressure to deliver on IT projects at a time when resources/budgets are constrained Pressure from risk of technology-based
More informationCAPITAL AVIONICS, INC. Quality Manual
CAPITAL AVIONICS, INC. Issued 31 July 2018 Conforms to ISO 9001:2015 2018 ; all rights reserved. This document may contain proprietary information and may only be released to third parties with approval
More informationWhat is Software Engineering?
COSC 3351 Software Software Life Cycle (I) Spring 2008 What is Software Engineering? Real world problems are large and complex. Solving problems requires multiple steps Analyzing: Break the problems into
More informationExpert Design & Support Engineer to work within Diagnostics Division. Technical Specifications
Expert Design & Support Engineer to work within Diagnostics Division Technical Specifications Version 1.0 Date: 17/07/2012 Name Affiliation Author V UDINTSEV CHD / DIAGNOSTICS Reviewers M WALSH CHD/ DIAGNOSTICS
More informationProject Management Auditing Guide
Project Management Auditing Guide Index Page 1.0 Objective 4 2.0 Risks 4 3.0 Safeguards and Controls 3.1.Project Characteristics 4 3.2.Quality in Project Management Process 4 3.3.Strategic Processes 5
More informationWho Am I? Project Basics. Project. Why Project? Alternative (names) Poloya s Method. Computer Science program ISD Datasystem AB (6 years)
Project Basics Anders Hessel Department of Information Technology Uppsala University Who Am I? Computer Science program ISD Datasystem AB (6 years) Developer Technical Project Manager 1 ½ year Ericsson
More informationCMMI for Acquisition Quick Reference
AGREEMENT MANAGEMENT PROJECT MANAGEMENT (ML2) The purpose of Agreement Management (AM) is to ensure that the supplier and the acquirer perform according to the terms of the supplier agreement. SG 1 The
More informationTitle Design Quality Control, Quality Assurance, and Quality Verification on Design-Build Projects
WSDOT Design-Build Guidance Statement Title Design Quality Control, Quality Assurance, and Quality Verification on Design-Build Projects Date October 2, 2006 Format Final Relevant section of WSDOT DB Guidebook
More informationV&V = the Verification and Validation of Deliverables
V&V = the Verification and Validation of Deliverables Verification and validation (V&V) are separated in the PMBOK Guide, but should be viewed as two integrated elements in the process of creating value
More informationPCA ELECTRONICS, INC. Quality Manual
PCA ELECTRONICS, INC. Conforms to ISO 9001:2015 (c) 2018 PCA Electronics, Inc.; all rights reserved. This document may contain proprietary information and may only be released to third parties with approval
More informationISO 9001:2015 QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES
ISO 9001:2015 QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES Origination Date: XXXX Document Identifier: Date: Document Revision: QMS-00 Policies and Procedures Latest Revision Date Abstract: This handbook
More informationBusiness Management System Manual Conforms to ISO 9001:2015 Table of Contents
Table of Contents 1.0 Welcome to Crystalfontz... 3 2.0 About the Crystalfontz Business Systems Manual... 4 3.0 Terms and Conditions... 5 4.0 Context of the Organization... 6 4.1. Understanding the Organization
More informationSMS Elements Veriforce, LLC. All rights reserved.
1. Leadership and Management Commitment 2. Stakeholder Engagement 3. Risk Management 4. Operational Controls 5. Incident Investigation, Evaluation, and Lessons Learned 6. Safety Assurance 7. Management
More informationInformation Systems Development
Information Systems Development Based on Chapter 3 of Whitten, Bentley, and Dittman: Systems Analysis and Design for the Global Enterprise (7th Ed). McGraw Hill. 2007 Wei-Tsong Wang 1 IIM, NCKU 3 Objectives
More informationA Model for CAS Self Assessment
Introduction An effective Contractor Assurance System integrates contractor management, supports corporate parent governance and facilitates government oversight systems. The purpose of a CAS is threefold:
More informationDeveloped by: Steven Jacobs, Eck Doerry
Developed by: Steven Jacobs, Eck Doerry 1 Consequences of Bad Requirements Engineering http://www.knovelblogs.com/2012/08/30/the-importance-of-requirements-engineering/ 2 Building an efficient organization
More informationIndependent Verification and Validation (IV&V)
Independent Verification and Validation (IV&V) 12 th Annual NDIA CMMI Conference November 2012 - Denver, CO The MITRE Corporation The author s affiliation with The MITRE Corporation is provided for identification
More informationINTRODUCTION TO QUALITY ASSURANCE
INTRODUCTION TO QUALITY ASSURANCE Basic Quality Terminology No more definitions...please! Page 1 Quality is the degree to which a specific product conforms to a design or specification H.L. Gilmore Product
More informationVALUE FOCUSED DELIVERY
VALUE FOCUSED DELIVERY 2018 417 N 2nd Ave. Minneapolis, MN 55401 Table of Contents Project Methodology... 3 Figure 1: - Project Approach... 4 Phase 1 The Inception Sprint... 5 Figure 2: Discovery Phase
More information(Insert Firm Name) Quality System Manual
(Insert Firm Name) Quality System Manual Ver. 1.1 (enter implementation/revision date) Controlled Document Created date: Revised date: Revision number: Approved by: Quality System Manual Ver 1.1: (date)
More informationQuality Management Systems in Engineering Practice. Shane R. Beabes, P.E.
Quality Management Systems in Engineering Practice Shane R. Beabes, P.E. ASQ Northern Virginia Section 11 May 2016 Agenda 1. Quality Management System 2. Quality 3. Client Requirements 4. Quality Assurance
More informationISO 9001:2008 Quality Management System QMS Manual
2501 Kutztown Road Reading, PA, 19605 Tel. 610-929-3330 Fax 610-921-6861 ISO 9001:2008 Quality Management System QMS Manual The information contained in this document is Fidelity Technologies Corporation
More informationSAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES
SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:
More informationMBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar
MBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar L2 Project Scope Management www.notes638.wordpress.com Project Scope Management Scope initiation/planning Scope definition Issue
More informationProject Plan. Executive Summary. Project Name: Prepared By: Date: Business Need/Problem Identify business need/problem that needs to be solved.
Project Plan Project Name: Prepared By: Date: A Executive Summary Information in the project summary areas was started during the project concept phase and should be included here. Information includes
More informationExpert Engineer to provide coordination and support for mechanical design and structural analysis within the IC&LH Section. Technical Specification
Expert Engineer to provide coordination and support for mechanical design and structural analysis within the IC&LH Section Technical Specification Version 2.1 Date: 23/02/2012 Name Affiliation Authors
More informationEA-7/04 Legal Compliance as a part of accredited ISO 14001: 2004 certification
Publication Reference EA-7/04 Legal Compliance as a part of Accredited ISO 14001: 2004 certification PURPOSE The text of this document has been produced by a working group in the European co-operation
More informationHSE INTEGRATED MANAGEMENT SYSTEM MANUAL & QUALITY POLICY
HSE INTEGRATED MANAGEMENT SYSTEM MANUAL & QUALITY POLICY Quality, Health, Safety & Environmental Integrated Management System Manual HAZARD : An object, physical effect, or condition with potential to
More informationQuality System Manual - Section 00
Quality System Manual - Section 00 INDEX AND REVISION STATUS Issued by: Quality Assurance Eff. Date: 06/10/2014 Rev.: A Pg. 1 of 4 QUALITY SYSTEM MANUAL SECTION 0 - INDEX AND REVISION STATUS SECTION 1
More informationBELDEN QUALITY SYSTEM OVERVIEW
BELDEN QUALITY SYSTEM OVERVIEW Table of Contents 1.0 Introduction 2.0 Quality Management System 3.0 Resource Management 4.0 Product Realization 5.0 Measurement, Analysis, and Improvement 1.0 Introduction
More information48R06 SCHEDULECONSTRUCTABI
E 48R06 SA M PL SCHEDULECONSTRUCTABI LI TY REVI EW AACE International Recommended Practice No. 48R-06 SCHEDULE CONSTRUCTABILITY REVIEW TCM Framework: 7.2 Schedule Planning and Development 11.5 Value Management
More informationQUALITY ASSURANCE / QUALITY CONTROL POLICY
QUALITY ASSURANCE / QUALITY CONTROL POLICY TABLE OF CONTENTS SI. NO. DETAILS 1. Introduction 2. Quality Policy and Objectives 3. Organization 4. Contract Review 5. Document and Data Control 6. Purchasing
More informationChapter 3. Information Systems Development. McGraw-Hill/Irwin. Copyright 2007 by The McGraw-Hill Companies, Inc. All rights reserved.
Chapter 3 Information Systems Development McGraw-Hill/Irwin Copyright 2007 by The McGraw-Hill Companies, Inc. All rights reserved. Objectives 3-2 Describe the motivation for a system development process
More informationInnovative Improvement Driven Foundation for Denver s Transit Expansion Program
Innovative Improvement Driven Foundation for Denver s Transit Expansion Program Timothy Stokes, PE Delcan Corp. Denver, CO INTRODUCTION The Denver Regional Transportation District (RTD) has embraced managerial
More informationNYSDOT DESIGN BUILD. Design-Build Info/Design-Build Moving forward/roles and Responsibilities 2015 Overview. AGC Conference December 10, 2015
NYSDOT DESIGN BUILD Design-Build Info/Design-Build Moving forward/roles and Responsibilities 2015 Overview AGC Conference December 10, 2015 Where DOT is currently with Design-Build Websites Under procurement
More informationWork Plan and IV&V Methodology
Work Plan and IV&V Methodology Technology initiatives and programs should engage with an IV&V process at the project planning phase in order to receive an unbiased, impartial view into the project planning,
More informationProgram Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
More informationTABLE OF CONTENTS ABBREVIATIONS 1.0 DEFINITIONS PURPOSE AND SCOPE GUIDELINES FOR PRACTICE REFERENCES AND RELATED DOCUMENTS 12
TABLE OF CONTENTS ABBREVIATIONS iii 1.0 DEFINITIONS 1 2.0 PURPOSE AND SCOPE 3 3.0 GUIDELINES FOR PRACTICE 6 3.1 WHAT IS THE PURPOSE OF CHECKING 6 3.2 HOW MUCH CHECKING IS REQUIRED 6 3.2.1 Level of Checking
More informationCMMI V2.0 MODEL AT-A-GLANCE. Including the following views: Development Services Supplier Management. CMMI V2.0 outline BOOKLET FOR print.
CMMI V.0 MODEL AT-A-GLANCE Including the following views: Development Services Supplier Management CMMI V.0 outline BOOKLET FOR print.indd CMMI V.0 An Integrated Product Suite Designed to meet the challenges
More informationExpressions, Musings and Ventures (EM&V) in the Real World
Expressions, Musings and Ventures (EM&V) in the Real World Lori Hermanson, David Thompson and Bruce Folsom, Avista Corporation Chris Ann Dickerson, CAD Consulting Steven Schiller, Schiller Consulting,
More informationENERGY PERFORMANCE PROTOCOL QUALITY ASSURANCE SPECIFICATION
ENERGY PERFORMANCE PROTOCOL QUALITY ASSURANCE SPECIFICATION Version 1.0 April 2015 Table of Contents 1.0 INVESTOR CONFIDENCE PROJECT 1.1 ENERGY EFFICIENCY PERFORMANCE QUALITY ASSURANCE SPECIFICATION 1.2
More information2016 National Tribal Transportation Conference
Alaska Tribal Technical Assistance Program Center 2016 National Tribal Transportation Conference Construction Management Darrel Williams Introductions Introduction to Construction Administration Construction
More information<Full Name> Quality Manual. Conforms to ISO 9001:2015. Revision Date Record of Changes Approved By
Conforms to ISO 9001:2015 Revision history Revision Date Record of Changes Approved By 0.0 [Date of Issue] Initial Issue Control of hardcopy versions The digital version of this document is
More informationChapter 26. Quality Management
Chapter 26 Quality Management - Quality concepts - Software quality assurance - Software reviews - Statistical software quality assurance - Software reliability, availability, and safety - SQA plan (Source:
More informationAutomated System Validation By: Daniel P. Olivier & Curtis M. Egan
Automated System Validation By: Daniel P. Olivier & Curtis M. Egan In today s technical environment validation practices are both a requirement and an important tool in the medical and pharmaceutical industry.
More informationCintipation Corp. CORINTHIAN PROJECT Policy for Requirements Management
Samples of Level 2 Policies Policy for Requirements Management The purpose of Requirements Management is to establish a common understanding between the customer, Cintipation senior management, and the
More informationPHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008)
PHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008) PREPARED BY: Government Audit Services Branch Government of Yukon APPROVED BY: Audit Committee Table of Contents Page PREFACE 3 EXECUTIVE SUMMARY
More informationCORPORATE QUALITY MANUAL
Corporate Quality Manual Preface The following Corporate Quality Manual is written within the framework of the ISO 9001:2008 Quality System by the employees of CyberOptics. CyberOptics recognizes the importance
More informationDeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT
DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY 10550 QUALITY ASSURANCE TABLE OF CONTENTS SECTION I SECTION 2 SECTION 3 SECTION 4 SECTION 5 QUALITY MANAGEMENT SYSTEM MANAGEMENT RESPONSIBILITY RESOURCE
More informationOsprey Technologies, LLC. Quality Manual ISO9001:2008 Rev -
February 8, 2015 1 Osprey Technologies, LLC Quality Manual ISO9001:2008 Rev - February 8, 2015 Released by Dave Crockett President 6100 S. Maple Avenue, Suite 117 Tempe, AZ 85283 www.osprey-tech.com February
More informationProject Management Knowledge Areas SECTION III
Project Management Knowledge Areas SECTION III 1 Project Integration Management CHAPTER 4 2 The Key to Overall Project Success: Good Project Integration Management Project managers must coordinate all
More informationBuilding Owners Cost Engineering Organizational Capability. Tim Mitchell Chevron
Building Owners Cost Engineering Organizational Capability Tim Mitchell Chevron Tim Mitchell Biography Degree B.S. Civil Engineering, 1986 Mississippi State University Professional Field: Upstream Oil
More informationProject Management. Risk Management
Brandt s History of IV&V Success Using over 30 years of experience supporting local, state, and federal agencies, Brandt provides IV&V services using proven, strategic methodologies to ensure project success
More informationQUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES
QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES Origination Date: XXXX Document Identifier: Date: Document Revision: QMS-00 QMS Policies and Procedures Latest Revision Date Abstract: This handbook documents
More information6. Capability Maturity Method (CMM)
WAT IS TE C? 6. aturity ethod (C) Concept: The application of process management and quality improvement concepts to software development and maintenance odel: A model for organizational improvement Guidelines:
More informationSystems Analysis and Design Methods Chapter 3: Information Systems Development
Systems Analysis and Design Methods Chapter 3: Information Systems Development Multiple Choice Questions 1. The act of drawing one or more graphical representations of a system is called. A. modeling B.
More informationQuality Manual. This manual complies with the requirements of the ISO 9001:2015 International Standard.
Quality Manual This manual complies with the requirements of the ISO 9001:2015 International Standard. Northeast Power Systems, Inc. 66 Carey Road Queensbury, New York 12804 Quality Manual Rev 0 Printed
More informationCMMI Conference November 2006 Denver, Colorado
Why Do You Need a Maturity Level 5 Supplier? CMMI Conference November 2006 Denver, Colorado Welcome Why Do You Need an ML 5 Supplier - 2 WelKom Huan Yín Bienvenido Bienvenue Wilkommen ЌАΛΟΣ ΟΡΙΣΑΤΕ Välkommen
More informationREQUIREMENTS DOCUMENTATION
REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category Priority Acceptance Criteria REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category
More informationQUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES
Your Company Name QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES Origination Date: XXXX Document Identifier: Date: Document Revision: QMS-00 QMS Policies and Procedures Latest Revision Date Abstract:
More informationInstrument Control System Project Management
Project Documentation Document PMCS-0021 Revision A Instrument Control System Project Management Bret Goodrich Software September 2015 Advanced Technology Solar Telescope 950 N. Cherry Avenue Tucson, AZ
More informationWM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA. Improving DOE Project Performance Using the DOD Integrated Master Plan 12481
Improving DOE Project Performance Using the DOD Integrated Master Plan 12481 Glen B. Alleman, DOD Programs, Project Time & Cost and Michael R. Nosbisch, Managing Principle, Western Region, Project Time
More informationCQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015
CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 SCOPE This document establishes the minimum quality program requirements for a contractor providing equipment, material,
More informationIN-PILE CREEP RELAXATION AND POST-IRRADIATION THERMAL CREEP TESTING
Page 1 / 11 Ver. 1.3 MANAGEMENT SPECIFICATION FOR THE IN-PILE CREEP RELAXATION AND POST-IRRADIATION THERMAL CREEP TESTING Abstract This document specifies the management requirements: the Supplier shall
More informationQuality Manual Power Engineering & Manufacturing Inc th Lane NE Blaine Minnesota MN 55449
Quality Manual Power Engineering & Manufacturing Inc 1463 94th Lane NE Blaine Minnesota MN 55449 COVER PAGE PD 0002 rev. 3 Section QM 01 Page 1 of 17 This document is approved for use Manual Contents Section
More informationPolicy and Procedure Examples
Appendix 1 Policy and Procedure Examples Four sample documents are shown in this appendix to illustrate the type of administrative guidelines that should be developed in support of project operations within
More informationExplanatory Note on the CSM Assessment Body in Regulation (EU) N 402/2013 and in OTIF UTP GEN-G of on the CSM for risk assessment
Regulation (EU) N 402/2013 and in UTP GEN-G Explanatory note on the CSM Assessment Body referred to in Regulation (EU) N 402/2013 and in UTP GEN-G of 1.1.2014 on the Common Safety Method (CSM) for risk
More informationStudent Services & Classroom Addition
SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for quality assurance and quality control. B. Testing and inspecting services
More informationProject Management Session 6.2. Project Initiation Phase Integration Management
Project Management Session 6.2 Project Initiation Phase Integration Management 1 Project Phases & Knowledge Areas 1. Integration 2. Scope Management 3. Time Management 4. Cost Management 5. Quality Management
More informationPOLICY MANUAL FOR ISO 9001:2008. Document: PM-9001:2008 Date: April 7, Uncontrolled Copy
POLICY MANUAL FOR ISO 9001:2008 Document: PM-9001:2008 Date: April 7, 2015 REVIEWED BY: Tim Powers DATE: 4-7-2015 APPROVED BY: C._Bickford Uncontrolled Copy DATE: 4-7-2015 1.0 GENERAL ISS: 1 REV: E Page:
More informationQP Supplier Quality Requirements Manual. Purchasing. Dearborn Inc. Revision: E Page 1 of PURPOSE
Page 1 of 8 1.0 PURPOSE 1.1 The purpose of this manual is to have a single document which conveys the minimum quality requirements and manufacturing practices expected of suppliers for value added products
More informationPolicy and Procedure on Engaging Externally Contracted Service Providers
Policy and Procedure on Engaging Externally Contracted Service Providers 1. Purpose of this Policy The purpose of this Policy is to set down clear guidelines for the appropriate engagement of externally
More informationIntroduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are:
Introduction Scope Management involves the management of techniques that make sure that the project comprises a Processes included in Scope Management are: 1. Collect Requirements In this process, project
More informationPage 1 / 11. Version 0 June 2014
Page 1 / 11 CORRESPONDENCE MATRIX NQSA NSQ-100 version 0 NUCLEAR SAFETY AND QUALITY MANAGEMENT SYSTEM REQUIREMENTS Model for quality management in design & development, manufacturing, erection, commissioning
More informationDOCUMENT CONTROL INFORMATION
DOCUMENT CONTROL INFORMATION System: Document Title: Document Status: Quality Manual Approved 5 11/5/2014 Current Document Revision Details Formal review. Added section 2, 3. Revised section 5.5.2, 6.2,
More informationSCHEDULE [NUMBER NAME OF WORK UNIT/WORK PACKAGE] TO THE IN-KIND CONTRIBUTION AGREEMENT SIGNED BETWEEN ESS AND PARTNER ON DATE
1 (11) TA Template V3.0 SCHEDULE [NUMBER NAME OF WORK UNIT/WORK PACKAGE] TO THE IN-KIND CONTRIBUTION AGREEMENT SIGNED BETWEEN ESS AND PARTNER ON DATE 1. SCOPE This document describes the Scope of Work
More informationGuidelines for the Preparation of Case Studies
Guidelines for the Preparation of Case Studies Applicants for initial registration are required to demonstrate the following. Principle 1 The applicant must demonstrate that he or she is able to practise
More informationPRECISE INDUSTRIES INC. Quality Manual
PRECISE INDUSTRIES INC Revision N Issued July 5, 2017 Conforms to AS9100 Rev. D and ISO 9001:2015 Copyright Year2017 [PRECISE INDUSTRIES INC]; all rights reserved. This document may contain proprietary
More informationUrban. Initiative. Meeting. Construction. Annual. City of Lynchburg
2014 Urban Construction Initiative Annual Meeting City of Lynchburg Materials Testing Requirements for Locally Administered Projects Don French, P.E. VDOT Lynchburg District District Materials Engineer
More information