Timothy Stokes. PE, MBA Delcan Corp, Senior Principal Denver, CO

Size: px
Start display at page:

Download "Timothy Stokes. PE, MBA Delcan Corp, Senior Principal Denver, CO"

Transcription

1 Improving Project Management to Realize Successful Outcomes by Focusing on Requirements Management Timothy Stokes. PE, MBA Delcan Corp, Senior Principal Denver, CO

2 Introduction Begin at the beginning, the King said gravely, and go on till you come to the end; then stop. Lewis Carroll, Alice in Wonderland It was a painful lesson to learn, but it was and engineer s dream I had a great time, but, in the end, it taught me a great lesson in business planning. You need to minimize investment as well the risks. We all need to think of business, not straight engineering anymore. Roger Taur

3 Requirements Drive Projects In 1994, the Standish Group found that the top three factors that caused project failure were: 1. Lack of user input, 2. Incomplete requirements 3. Changes to the requirements. Requirements Management was developed primarily in the software industry. Requirements Management is relatively new to the infrastructure industry. It is a process area within project management and systems engineering.

4 Infrastructure Delivery Traditionally delivered projects using a design-bid-build delivery method. New ways to be efficiently deliver projects. Construction management at risk, design-build, and public-privatepartnership models such as designbuild-operate-maintain.

5 Design - Build Design - Bid - Build Paradigm Shift: Design-Bid-Build to Design-Build Construction FACILITY 100% TRACK 100% SYSTEMS 100% Tendering Acceptance / Commissioning Design and Define Requirements Preliminary Design and Requirements Construction FACILITY < 30% 100% Design Support During Construction TRACK < 30% 100% Design Support During Construction SYSTEMS < 30% 100% Design Support During Construction Intense Development of RFQ / RFP Intense Design Review Acceptance / Commissioning Construction Oversight RFIs / Field Requested Design Changes / NCRs Design Tender / Bid Construction Accept / Commission

6 The Need for Requirements Management Requirements are explicit expressions of needs; what a process or product must accomplish. 6 traceability is a key concept

7 Classic V-Model of System Engineering System Requirements Verification and Validation System Integration & Acceptance Sub-System Requirements Construct / Inspect/Test Design Fabrication 7

8 Types of Requirements Functional Requirements What the resulting products or deliverables of the project should do in order to perform their intended function. E.g. design criteria Non-Functional Requirements Qualities, or properties the product must have in order for it to function as intended. E.g. safety and security, maintainability, reliability Project Management Requirements To assure the contractor implements management processes necessary to provide confidence, transparency, and accountability to the owner throughout the project that work is being performed to the satisfaction of the owner. E.g. quality, safety, public information management

9 Stakeholders Stakeholders commonly state their need through formal meetings or written communications. Understanding their needs is important so that they can be translated into technical requirements that are clear and understood by those implementing the project.

10 Requirements are used to Communicate What is Wanted

11 Requirements the Problem Requirements are the what s or the problem statements that are written in a technical manner that need to be addressed.

12 Design- the solution Specifications are the solutions or the how s to ensure that requirements are going to be fulfilled.

13 Design Solutions To Requirements Traditional Design Approach Requirements-Oriented Design Approach Good requirements can lead to more effective solutions. Advantage to develop innovative, optimum solutions. 13

14 Writing High-Quality Requirements Criteria Describes what, not how Traceable Single statement Necessary Clear meaning Correct Unique Consistent Feasible Verifiable Documented and accessible Terminology: shall, should, will 14

15 Requirements Management Process Involves the owner and stakeholders; Involves multiple engineering disciplines working co-operatively; Facilitates the contracted entities to transform a need into a reality; and Enables the owner to verify and validate whether the contractor has incorporated the requirements into the finished product.

16 Preparation of Requirements for a RFP For new rail and transit projects, requirements are communicated by the Request for Proposal (RFP) Transit Owner takes care of the Needs and the What's Design-Builder takes care of the How s If done properly, the owner only needs to confirm that requirements are being met. Should not need to inspect the work.

17 Requirements Management Process A formalized, planned and continually evolving series of activities. Output: Requirements that are incorporated into an RFP or similar document.

18 Needs Identification Approved RFP translates owner, operator, and stakeholder source needs into formal requirements 18

19 Categorization Approved RFP Checks for inconsistency, omission, duplication priority, WBS, responsibility, acceptance 19

20 Categorization WBS Concept

21 Documentation and Storage Approved RFP Inventory control, change history web-based tool with database engine 21

22 Validation with Stakeholders Approved RFP Stakeholders understand, agree, and support the requirements as presented in contracts 22

23 Verification Approved RFP Verify that requirements have been achieved. Traceability for confidence of acceptance.. 23

24 Verification Owner roles during project implementation is verifying or validating that requirements have been fulfilled. Design-Builder implements project management processes, which includes assurance methods (visibility that all work complies with requirements and design specifications, safety, environmental, systems integration, other management processes). Owner should not need to perform inspections (design checking or inspecting at the specification level)

25 Dealing with Changes Changes in scope should result in changes to requirements ensure change management at the requirement level.

26 Dealing with Interfaces Subsystem A Interfaces Subsystem B Develop Interface Requirements - ensure they are requirements - not something else. Verify that the design addresses each requirement, Validate that the construction and/or operations address each requirement.

27 Requirements Management Conclusions Offers a problem statement / solutions paradigm an enhanced way to manage projects. Offers a way to define and verify scope clear understanding of the Work that is traceable back to the overall project goals. Aids program management effort by offering visibility of dependencies, scope deviations, responsibilities and change control.

28

Timothy Stokes, PE, MBA Parsons, Principal Project Manager Denver, Colorado

Timothy Stokes, PE, MBA Parsons, Principal Project Manager Denver, Colorado A SE Approach to Enhance and Support the Acceptance Process for RTD FastTrack's Projects Timothy Stokes, PE, MBA Parsons, Principal Project Manager Denver, Colorado Key Take Away Points 1. Alternative

More information

Florida Cleanroom Systems

Florida Cleanroom Systems Florida Cleanroom Systems Design Build Projects / Project Quality Control Plan (PQCP) Quality Control / Quality Assurance Manual May 2010 1 TABLE OF CONTENTS Section 1: Introduction 3 1.1 Defining Plan

More information

1 Introduction. 20 August 1995; 19:29 1 Master04.Doc

1 Introduction. 20 August 1995; 19:29 1 Master04.Doc 1 Introduction This master thesis concludes the study of computer science at the Rijks Universiteit of Leiden. The mentor for this project is dr. L.P.J. Groenewegen. The topic addressed in this master

More information

A Systems Engineering Approach to Enhance and Support the Acceptance Process for RTD FasTracks Projects

A Systems Engineering Approach to Enhance and Support the Acceptance Process for RTD FasTracks Projects A Systems Engineering Approach to Enhance and Support the Acceptance Process for RTD FasTracks Projects Timothy Stokes, PE Parsons Corp. Denver, CO OVERVIEW Project closeout is often the most neglected

More information

INS QA Programme Requirements

INS QA Programme Requirements Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued

More information

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B 1. Work Plan & IV&V Methodology 1.1 Compass Solutions IV&V Approach The Compass Solutions Independent Verification and Validation approach is based on the Enterprise Performance Life Cycle (EPLC) framework

More information

GENERAL REQUIREMENTS FOR ENGINEERING AND DESIGN

GENERAL REQUIREMENTS FOR ENGINEERING AND DESIGN Project Procedures GENERAL REQUIREMENTS FOR ENGINEERING AND DESIGN 07/28/2011 PAGE 1 OF 7 1.0 PURPOSE 1.1 PURPOSE OF ENGINEERING PROJECT PROCEDURES This P-4 series of Engineering Project Procedures provides

More information

Distribution Restriction Statement Approved for public release; distribution is unlimited.

Distribution Restriction Statement Approved for public release; distribution is unlimited. CEMP-ET Engineer Regulation 1110-345-53 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 Engineering and Design STRUCTURAL STEEL CONNECTIONS Distribution Restriction Statement

More information

ITER Quality Assurance

ITER Quality Assurance US ITER Central Solenoid Vendor Meeting ITER Quality Assurance by John Mashburn USIPO QA Manager 1 QA Topics ITER s Nuclear License Graded Approach Proposal QA Items Quality Plan Specific to Contract Manufacturing

More information

VALUE FOCUSED DELIVERY

VALUE FOCUSED DELIVERY VALUE FOCUSED DELIVERY Project Methodology 417 N 2nd Ave. Minneapolis, MN 55401 Table of Contents Project Methodology... 3 Figure 1: - Project Approach... 4 Phase 1 Inception Sprint... 5 Figure 2: Inception

More information

APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS

APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS Shared denotes whether a Contractor Resource may be responsible for that in addition to another identified. Contractor Required

More information

Association of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017

Association of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017 Company: Prepared By: Date: Changes from previous version highlighted in yellow. Paragraph Element Objective Evidence 2.1 Objective of Quality Assurance Program 2.2 Applicability and Scope 2.3 QA Program

More information

Design Quality. Indu Lakshman

Design Quality. Indu Lakshman Design Quality Indu Lakshman Overview New product development (NPD) covers the complete process of bringing a new product to market. In commercial terms, new product development is described in the literature

More information

Chapter 6. Software Quality Management & Estimation

Chapter 6. Software Quality Management & Estimation Chapter 6 Software Quality Management & Estimation What is Quality Management Also called software quality assurance (SQA) s/w quality:- It is defined as the degree to which a system, components, or process

More information

Design Compliance Matrix

Design Compliance Matrix Waste Treatment Plant Project Design Compliance Matrix Tracy Hawkins WTP Responsible Engineering Specialist 06-August-2015 Design Compliance Matrix (DCM) Overview AGENDA What is the Purpose of a DCM? What

More information

Systems Assurance within the Systems Engineering Lifecycle

Systems Assurance within the Systems Engineering Lifecycle Systems Assurance within the Systems Engineering Lifecycle Key Lessons & Benefits Rob Scarbro 12 th February 2013 1 Introduction Overview of Systems Assurance across a Project Life- Cycle Key objectives,

More information

TOPIC DESCRIPTION SUPPLEMENT for the SYSTEMS ENGINEERING SURVEY DESCRIPTION

TOPIC DESCRIPTION SUPPLEMENT for the SYSTEMS ENGINEERING SURVEY DESCRIPTION 1 2 Objectives of Systems Engineering 3 4 5 6 7 8 DoD Policies, Regulations, & Guidance on Systems Engineering Roles of Systems Engineering in an Acquisition Program Who performs on an Acquisition Program

More information

Capability Maturity Model for Software (SW-CMM )

Capability Maturity Model for Software (SW-CMM ) PHASE-IV: SYSTEMS IMPLEMENTATION Software Quality Assurance Application Development Installation and Support Software Quality Assurance Capability Maturity Model for Software (SW-CMM ) The Capability Maturity

More information

Keynotes RLGA. QA and QC: Are They Different?

Keynotes RLGA. QA and QC: Are They Different? QA and QC: Are They Different? By Ronald L. Geren, AIA, CSI, CCS, CCCA, SCIP Quality assurance (QA) and quality control (QC) are often used interchangeably to mean the same thing or together as if one

More information

Quality System Manual - Section 00

Quality System Manual - Section 00 Quality System Manual - Section 00 INDEX AND REVISION STATUS Issued by: Quality Assurance Eff. Date: 00/00/00 Rev.: A Pg. 1 of 4 Organization of this manual is the same as the sectional organization of

More information

BHG Operational Awareness Program May 8, 1998 Configuration Management Revision 0 Page 1 of 11 CONFIGURATION MANAGEMENT

BHG Operational Awareness Program May 8, 1998 Configuration Management Revision 0 Page 1 of 11 CONFIGURATION MANAGEMENT Page 1 of 11 CONFIGURATION MANAGEMENT 1.0 SCOPE This Performance Assessment Guide for Configuration Management will be used to carry out the oversight responsibility of the U.S. Department of Energy (DOE)

More information

ISACA Systems Implementation Assurance February 2009

ISACA Systems Implementation Assurance February 2009 ISACA Pressures Today Pressure to increase realization of value from IT spending Pressure to deliver on IT projects at a time when resources/budgets are constrained Pressure from risk of technology-based

More information

CAPITAL AVIONICS, INC. Quality Manual

CAPITAL AVIONICS, INC. Quality Manual CAPITAL AVIONICS, INC. Issued 31 July 2018 Conforms to ISO 9001:2015 2018 ; all rights reserved. This document may contain proprietary information and may only be released to third parties with approval

More information

What is Software Engineering?

What is Software Engineering? COSC 3351 Software Software Life Cycle (I) Spring 2008 What is Software Engineering? Real world problems are large and complex. Solving problems requires multiple steps Analyzing: Break the problems into

More information

Expert Design & Support Engineer to work within Diagnostics Division. Technical Specifications

Expert Design & Support Engineer to work within Diagnostics Division. Technical Specifications Expert Design & Support Engineer to work within Diagnostics Division Technical Specifications Version 1.0 Date: 17/07/2012 Name Affiliation Author V UDINTSEV CHD / DIAGNOSTICS Reviewers M WALSH CHD/ DIAGNOSTICS

More information

Project Management Auditing Guide

Project Management Auditing Guide Project Management Auditing Guide Index Page 1.0 Objective 4 2.0 Risks 4 3.0 Safeguards and Controls 3.1.Project Characteristics 4 3.2.Quality in Project Management Process 4 3.3.Strategic Processes 5

More information

Who Am I? Project Basics. Project. Why Project? Alternative (names) Poloya s Method. Computer Science program ISD Datasystem AB (6 years)

Who Am I? Project Basics. Project. Why Project? Alternative (names) Poloya s Method. Computer Science program ISD Datasystem AB (6 years) Project Basics Anders Hessel Department of Information Technology Uppsala University Who Am I? Computer Science program ISD Datasystem AB (6 years) Developer Technical Project Manager 1 ½ year Ericsson

More information

CMMI for Acquisition Quick Reference

CMMI for Acquisition Quick Reference AGREEMENT MANAGEMENT PROJECT MANAGEMENT (ML2) The purpose of Agreement Management (AM) is to ensure that the supplier and the acquirer perform according to the terms of the supplier agreement. SG 1 The

More information

Title Design Quality Control, Quality Assurance, and Quality Verification on Design-Build Projects

Title Design Quality Control, Quality Assurance, and Quality Verification on Design-Build Projects WSDOT Design-Build Guidance Statement Title Design Quality Control, Quality Assurance, and Quality Verification on Design-Build Projects Date October 2, 2006 Format Final Relevant section of WSDOT DB Guidebook

More information

V&V = the Verification and Validation of Deliverables

V&V = the Verification and Validation of Deliverables V&V = the Verification and Validation of Deliverables Verification and validation (V&V) are separated in the PMBOK Guide, but should be viewed as two integrated elements in the process of creating value

More information

PCA ELECTRONICS, INC. Quality Manual

PCA ELECTRONICS, INC. Quality Manual PCA ELECTRONICS, INC. Conforms to ISO 9001:2015 (c) 2018 PCA Electronics, Inc.; all rights reserved. This document may contain proprietary information and may only be released to third parties with approval

More information

ISO 9001:2015 QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES

ISO 9001:2015 QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES ISO 9001:2015 QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES Origination Date: XXXX Document Identifier: Date: Document Revision: QMS-00 Policies and Procedures Latest Revision Date Abstract: This handbook

More information

Business Management System Manual Conforms to ISO 9001:2015 Table of Contents

Business Management System Manual Conforms to ISO 9001:2015 Table of Contents Table of Contents 1.0 Welcome to Crystalfontz... 3 2.0 About the Crystalfontz Business Systems Manual... 4 3.0 Terms and Conditions... 5 4.0 Context of the Organization... 6 4.1. Understanding the Organization

More information

SMS Elements Veriforce, LLC. All rights reserved.

SMS Elements Veriforce, LLC. All rights reserved. 1. Leadership and Management Commitment 2. Stakeholder Engagement 3. Risk Management 4. Operational Controls 5. Incident Investigation, Evaluation, and Lessons Learned 6. Safety Assurance 7. Management

More information

Information Systems Development

Information Systems Development Information Systems Development Based on Chapter 3 of Whitten, Bentley, and Dittman: Systems Analysis and Design for the Global Enterprise (7th Ed). McGraw Hill. 2007 Wei-Tsong Wang 1 IIM, NCKU 3 Objectives

More information

A Model for CAS Self Assessment

A Model for CAS Self Assessment Introduction An effective Contractor Assurance System integrates contractor management, supports corporate parent governance and facilitates government oversight systems. The purpose of a CAS is threefold:

More information

Developed by: Steven Jacobs, Eck Doerry

Developed by: Steven Jacobs, Eck Doerry Developed by: Steven Jacobs, Eck Doerry 1 Consequences of Bad Requirements Engineering http://www.knovelblogs.com/2012/08/30/the-importance-of-requirements-engineering/ 2 Building an efficient organization

More information

Independent Verification and Validation (IV&V)

Independent Verification and Validation (IV&V) Independent Verification and Validation (IV&V) 12 th Annual NDIA CMMI Conference November 2012 - Denver, CO The MITRE Corporation The author s affiliation with The MITRE Corporation is provided for identification

More information

INTRODUCTION TO QUALITY ASSURANCE

INTRODUCTION TO QUALITY ASSURANCE INTRODUCTION TO QUALITY ASSURANCE Basic Quality Terminology No more definitions...please! Page 1 Quality is the degree to which a specific product conforms to a design or specification H.L. Gilmore Product

More information

VALUE FOCUSED DELIVERY

VALUE FOCUSED DELIVERY VALUE FOCUSED DELIVERY 2018 417 N 2nd Ave. Minneapolis, MN 55401 Table of Contents Project Methodology... 3 Figure 1: - Project Approach... 4 Phase 1 The Inception Sprint... 5 Figure 2: Discovery Phase

More information

(Insert Firm Name) Quality System Manual

(Insert Firm Name) Quality System Manual (Insert Firm Name) Quality System Manual Ver. 1.1 (enter implementation/revision date) Controlled Document Created date: Revised date: Revision number: Approved by: Quality System Manual Ver 1.1: (date)

More information

Quality Management Systems in Engineering Practice. Shane R. Beabes, P.E.

Quality Management Systems in Engineering Practice. Shane R. Beabes, P.E. Quality Management Systems in Engineering Practice Shane R. Beabes, P.E. ASQ Northern Virginia Section 11 May 2016 Agenda 1. Quality Management System 2. Quality 3. Client Requirements 4. Quality Assurance

More information

ISO 9001:2008 Quality Management System QMS Manual

ISO 9001:2008 Quality Management System QMS Manual 2501 Kutztown Road Reading, PA, 19605 Tel. 610-929-3330 Fax 610-921-6861 ISO 9001:2008 Quality Management System QMS Manual The information contained in this document is Fidelity Technologies Corporation

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:

More information

MBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar

MBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar MBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar L2 Project Scope Management www.notes638.wordpress.com Project Scope Management Scope initiation/planning Scope definition Issue

More information

Project Plan. Executive Summary. Project Name: Prepared By: Date: Business Need/Problem Identify business need/problem that needs to be solved.

Project Plan. Executive Summary. Project Name: Prepared By: Date: Business Need/Problem Identify business need/problem that needs to be solved. Project Plan Project Name: Prepared By: Date: A Executive Summary Information in the project summary areas was started during the project concept phase and should be included here. Information includes

More information

Expert Engineer to provide coordination and support for mechanical design and structural analysis within the IC&LH Section. Technical Specification

Expert Engineer to provide coordination and support for mechanical design and structural analysis within the IC&LH Section. Technical Specification Expert Engineer to provide coordination and support for mechanical design and structural analysis within the IC&LH Section Technical Specification Version 2.1 Date: 23/02/2012 Name Affiliation Authors

More information

EA-7/04 Legal Compliance as a part of accredited ISO 14001: 2004 certification

EA-7/04 Legal Compliance as a part of accredited ISO 14001: 2004 certification Publication Reference EA-7/04 Legal Compliance as a part of Accredited ISO 14001: 2004 certification PURPOSE The text of this document has been produced by a working group in the European co-operation

More information

HSE INTEGRATED MANAGEMENT SYSTEM MANUAL & QUALITY POLICY

HSE INTEGRATED MANAGEMENT SYSTEM MANUAL & QUALITY POLICY HSE INTEGRATED MANAGEMENT SYSTEM MANUAL & QUALITY POLICY Quality, Health, Safety & Environmental Integrated Management System Manual HAZARD : An object, physical effect, or condition with potential to

More information

Quality System Manual - Section 00

Quality System Manual - Section 00 Quality System Manual - Section 00 INDEX AND REVISION STATUS Issued by: Quality Assurance Eff. Date: 06/10/2014 Rev.: A Pg. 1 of 4 QUALITY SYSTEM MANUAL SECTION 0 - INDEX AND REVISION STATUS SECTION 1

More information

BELDEN QUALITY SYSTEM OVERVIEW

BELDEN QUALITY SYSTEM OVERVIEW BELDEN QUALITY SYSTEM OVERVIEW Table of Contents 1.0 Introduction 2.0 Quality Management System 3.0 Resource Management 4.0 Product Realization 5.0 Measurement, Analysis, and Improvement 1.0 Introduction

More information

48R06 SCHEDULECONSTRUCTABI

48R06 SCHEDULECONSTRUCTABI E 48R06 SA M PL SCHEDULECONSTRUCTABI LI TY REVI EW AACE International Recommended Practice No. 48R-06 SCHEDULE CONSTRUCTABILITY REVIEW TCM Framework: 7.2 Schedule Planning and Development 11.5 Value Management

More information

QUALITY ASSURANCE / QUALITY CONTROL POLICY

QUALITY ASSURANCE / QUALITY CONTROL POLICY QUALITY ASSURANCE / QUALITY CONTROL POLICY TABLE OF CONTENTS SI. NO. DETAILS 1. Introduction 2. Quality Policy and Objectives 3. Organization 4. Contract Review 5. Document and Data Control 6. Purchasing

More information

Chapter 3. Information Systems Development. McGraw-Hill/Irwin. Copyright 2007 by The McGraw-Hill Companies, Inc. All rights reserved.

Chapter 3. Information Systems Development. McGraw-Hill/Irwin. Copyright 2007 by The McGraw-Hill Companies, Inc. All rights reserved. Chapter 3 Information Systems Development McGraw-Hill/Irwin Copyright 2007 by The McGraw-Hill Companies, Inc. All rights reserved. Objectives 3-2 Describe the motivation for a system development process

More information

Innovative Improvement Driven Foundation for Denver s Transit Expansion Program

Innovative Improvement Driven Foundation for Denver s Transit Expansion Program Innovative Improvement Driven Foundation for Denver s Transit Expansion Program Timothy Stokes, PE Delcan Corp. Denver, CO INTRODUCTION The Denver Regional Transportation District (RTD) has embraced managerial

More information

NYSDOT DESIGN BUILD. Design-Build Info/Design-Build Moving forward/roles and Responsibilities 2015 Overview. AGC Conference December 10, 2015

NYSDOT DESIGN BUILD. Design-Build Info/Design-Build Moving forward/roles and Responsibilities 2015 Overview. AGC Conference December 10, 2015 NYSDOT DESIGN BUILD Design-Build Info/Design-Build Moving forward/roles and Responsibilities 2015 Overview AGC Conference December 10, 2015 Where DOT is currently with Design-Build Websites Under procurement

More information

Work Plan and IV&V Methodology

Work Plan and IV&V Methodology Work Plan and IV&V Methodology Technology initiatives and programs should engage with an IV&V process at the project planning phase in order to receive an unbiased, impartial view into the project planning,

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

TABLE OF CONTENTS ABBREVIATIONS 1.0 DEFINITIONS PURPOSE AND SCOPE GUIDELINES FOR PRACTICE REFERENCES AND RELATED DOCUMENTS 12

TABLE OF CONTENTS ABBREVIATIONS 1.0 DEFINITIONS PURPOSE AND SCOPE GUIDELINES FOR PRACTICE REFERENCES AND RELATED DOCUMENTS 12 TABLE OF CONTENTS ABBREVIATIONS iii 1.0 DEFINITIONS 1 2.0 PURPOSE AND SCOPE 3 3.0 GUIDELINES FOR PRACTICE 6 3.1 WHAT IS THE PURPOSE OF CHECKING 6 3.2 HOW MUCH CHECKING IS REQUIRED 6 3.2.1 Level of Checking

More information

CMMI V2.0 MODEL AT-A-GLANCE. Including the following views: Development Services Supplier Management. CMMI V2.0 outline BOOKLET FOR print.

CMMI V2.0 MODEL AT-A-GLANCE. Including the following views: Development Services Supplier Management. CMMI V2.0 outline BOOKLET FOR print. CMMI V.0 MODEL AT-A-GLANCE Including the following views: Development Services Supplier Management CMMI V.0 outline BOOKLET FOR print.indd CMMI V.0 An Integrated Product Suite Designed to meet the challenges

More information

Expressions, Musings and Ventures (EM&V) in the Real World

Expressions, Musings and Ventures (EM&V) in the Real World Expressions, Musings and Ventures (EM&V) in the Real World Lori Hermanson, David Thompson and Bruce Folsom, Avista Corporation Chris Ann Dickerson, CAD Consulting Steven Schiller, Schiller Consulting,

More information

ENERGY PERFORMANCE PROTOCOL QUALITY ASSURANCE SPECIFICATION

ENERGY PERFORMANCE PROTOCOL QUALITY ASSURANCE SPECIFICATION ENERGY PERFORMANCE PROTOCOL QUALITY ASSURANCE SPECIFICATION Version 1.0 April 2015 Table of Contents 1.0 INVESTOR CONFIDENCE PROJECT 1.1 ENERGY EFFICIENCY PERFORMANCE QUALITY ASSURANCE SPECIFICATION 1.2

More information

2016 National Tribal Transportation Conference

2016 National Tribal Transportation Conference Alaska Tribal Technical Assistance Program Center 2016 National Tribal Transportation Conference Construction Management Darrel Williams Introductions Introduction to Construction Administration Construction

More information

<Full Name> Quality Manual. Conforms to ISO 9001:2015. Revision Date Record of Changes Approved By

<Full Name> Quality Manual. Conforms to ISO 9001:2015. Revision Date Record of Changes Approved By Conforms to ISO 9001:2015 Revision history Revision Date Record of Changes Approved By 0.0 [Date of Issue] Initial Issue Control of hardcopy versions The digital version of this document is

More information

Chapter 26. Quality Management

Chapter 26. Quality Management Chapter 26 Quality Management - Quality concepts - Software quality assurance - Software reviews - Statistical software quality assurance - Software reliability, availability, and safety - SQA plan (Source:

More information

Automated System Validation By: Daniel P. Olivier & Curtis M. Egan

Automated System Validation By: Daniel P. Olivier & Curtis M. Egan Automated System Validation By: Daniel P. Olivier & Curtis M. Egan In today s technical environment validation practices are both a requirement and an important tool in the medical and pharmaceutical industry.

More information

Cintipation Corp. CORINTHIAN PROJECT Policy for Requirements Management

Cintipation Corp. CORINTHIAN PROJECT Policy for Requirements Management Samples of Level 2 Policies Policy for Requirements Management The purpose of Requirements Management is to establish a common understanding between the customer, Cintipation senior management, and the

More information

PHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008)

PHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008) PHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008) PREPARED BY: Government Audit Services Branch Government of Yukon APPROVED BY: Audit Committee Table of Contents Page PREFACE 3 EXECUTIVE SUMMARY

More information

CORPORATE QUALITY MANUAL

CORPORATE QUALITY MANUAL Corporate Quality Manual Preface The following Corporate Quality Manual is written within the framework of the ISO 9001:2008 Quality System by the employees of CyberOptics. CyberOptics recognizes the importance

More information

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY 10550 QUALITY ASSURANCE TABLE OF CONTENTS SECTION I SECTION 2 SECTION 3 SECTION 4 SECTION 5 QUALITY MANAGEMENT SYSTEM MANAGEMENT RESPONSIBILITY RESOURCE

More information

Osprey Technologies, LLC. Quality Manual ISO9001:2008 Rev -

Osprey Technologies, LLC. Quality Manual ISO9001:2008 Rev - February 8, 2015 1 Osprey Technologies, LLC Quality Manual ISO9001:2008 Rev - February 8, 2015 Released by Dave Crockett President 6100 S. Maple Avenue, Suite 117 Tempe, AZ 85283 www.osprey-tech.com February

More information

Project Management Knowledge Areas SECTION III

Project Management Knowledge Areas SECTION III Project Management Knowledge Areas SECTION III 1 Project Integration Management CHAPTER 4 2 The Key to Overall Project Success: Good Project Integration Management Project managers must coordinate all

More information

Building Owners Cost Engineering Organizational Capability. Tim Mitchell Chevron

Building Owners Cost Engineering Organizational Capability. Tim Mitchell Chevron Building Owners Cost Engineering Organizational Capability Tim Mitchell Chevron Tim Mitchell Biography Degree B.S. Civil Engineering, 1986 Mississippi State University Professional Field: Upstream Oil

More information

Project Management. Risk Management

Project Management. Risk Management Brandt s History of IV&V Success Using over 30 years of experience supporting local, state, and federal agencies, Brandt provides IV&V services using proven, strategic methodologies to ensure project success

More information

QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES

QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES Origination Date: XXXX Document Identifier: Date: Document Revision: QMS-00 QMS Policies and Procedures Latest Revision Date Abstract: This handbook documents

More information

6. Capability Maturity Method (CMM)

6. Capability Maturity Method (CMM) WAT IS TE C? 6. aturity ethod (C) Concept: The application of process management and quality improvement concepts to software development and maintenance odel: A model for organizational improvement Guidelines:

More information

Systems Analysis and Design Methods Chapter 3: Information Systems Development

Systems Analysis and Design Methods Chapter 3: Information Systems Development Systems Analysis and Design Methods Chapter 3: Information Systems Development Multiple Choice Questions 1. The act of drawing one or more graphical representations of a system is called. A. modeling B.

More information

Quality Manual. This manual complies with the requirements of the ISO 9001:2015 International Standard.

Quality Manual. This manual complies with the requirements of the ISO 9001:2015 International Standard. Quality Manual This manual complies with the requirements of the ISO 9001:2015 International Standard. Northeast Power Systems, Inc. 66 Carey Road Queensbury, New York 12804 Quality Manual Rev 0 Printed

More information

CMMI Conference November 2006 Denver, Colorado

CMMI Conference November 2006 Denver, Colorado Why Do You Need a Maturity Level 5 Supplier? CMMI Conference November 2006 Denver, Colorado Welcome Why Do You Need an ML 5 Supplier - 2 WelKom Huan Yín Bienvenido Bienvenue Wilkommen ЌАΛΟΣ ΟΡΙΣΑΤΕ Välkommen

More information

REQUIREMENTS DOCUMENTATION

REQUIREMENTS DOCUMENTATION REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category Priority Acceptance Criteria REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category

More information

QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES

QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES Your Company Name QUALITY MANAGEMENT SYSTEM POLICIES AND PROCEDURES Origination Date: XXXX Document Identifier: Date: Document Revision: QMS-00 QMS Policies and Procedures Latest Revision Date Abstract:

More information

Instrument Control System Project Management

Instrument Control System Project Management Project Documentation Document PMCS-0021 Revision A Instrument Control System Project Management Bret Goodrich Software September 2015 Advanced Technology Solar Telescope 950 N. Cherry Avenue Tucson, AZ

More information

WM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA. Improving DOE Project Performance Using the DOD Integrated Master Plan 12481

WM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA. Improving DOE Project Performance Using the DOD Integrated Master Plan 12481 Improving DOE Project Performance Using the DOD Integrated Master Plan 12481 Glen B. Alleman, DOD Programs, Project Time & Cost and Michael R. Nosbisch, Managing Principle, Western Region, Project Time

More information

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 SCOPE This document establishes the minimum quality program requirements for a contractor providing equipment, material,

More information

IN-PILE CREEP RELAXATION AND POST-IRRADIATION THERMAL CREEP TESTING

IN-PILE CREEP RELAXATION AND POST-IRRADIATION THERMAL CREEP TESTING Page 1 / 11 Ver. 1.3 MANAGEMENT SPECIFICATION FOR THE IN-PILE CREEP RELAXATION AND POST-IRRADIATION THERMAL CREEP TESTING Abstract This document specifies the management requirements: the Supplier shall

More information

Quality Manual Power Engineering & Manufacturing Inc th Lane NE Blaine Minnesota MN 55449

Quality Manual Power Engineering & Manufacturing Inc th Lane NE Blaine Minnesota MN 55449 Quality Manual Power Engineering & Manufacturing Inc 1463 94th Lane NE Blaine Minnesota MN 55449 COVER PAGE PD 0002 rev. 3 Section QM 01 Page 1 of 17 This document is approved for use Manual Contents Section

More information

Policy and Procedure Examples

Policy and Procedure Examples Appendix 1 Policy and Procedure Examples Four sample documents are shown in this appendix to illustrate the type of administrative guidelines that should be developed in support of project operations within

More information

Explanatory Note on the CSM Assessment Body in Regulation (EU) N 402/2013 and in OTIF UTP GEN-G of on the CSM for risk assessment

Explanatory Note on the CSM Assessment Body in Regulation (EU) N 402/2013 and in OTIF UTP GEN-G of on the CSM for risk assessment Regulation (EU) N 402/2013 and in UTP GEN-G Explanatory note on the CSM Assessment Body referred to in Regulation (EU) N 402/2013 and in UTP GEN-G of 1.1.2014 on the Common Safety Method (CSM) for risk

More information

Student Services & Classroom Addition

Student Services & Classroom Addition SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for quality assurance and quality control. B. Testing and inspecting services

More information

Project Management Session 6.2. Project Initiation Phase Integration Management

Project Management Session 6.2. Project Initiation Phase Integration Management Project Management Session 6.2 Project Initiation Phase Integration Management 1 Project Phases & Knowledge Areas 1. Integration 2. Scope Management 3. Time Management 4. Cost Management 5. Quality Management

More information

POLICY MANUAL FOR ISO 9001:2008. Document: PM-9001:2008 Date: April 7, Uncontrolled Copy

POLICY MANUAL FOR ISO 9001:2008. Document: PM-9001:2008 Date: April 7, Uncontrolled Copy POLICY MANUAL FOR ISO 9001:2008 Document: PM-9001:2008 Date: April 7, 2015 REVIEWED BY: Tim Powers DATE: 4-7-2015 APPROVED BY: C._Bickford Uncontrolled Copy DATE: 4-7-2015 1.0 GENERAL ISS: 1 REV: E Page:

More information

QP Supplier Quality Requirements Manual. Purchasing. Dearborn Inc. Revision: E Page 1 of PURPOSE

QP Supplier Quality Requirements Manual. Purchasing. Dearborn Inc. Revision: E Page 1 of PURPOSE Page 1 of 8 1.0 PURPOSE 1.1 The purpose of this manual is to have a single document which conveys the minimum quality requirements and manufacturing practices expected of suppliers for value added products

More information

Policy and Procedure on Engaging Externally Contracted Service Providers

Policy and Procedure on Engaging Externally Contracted Service Providers Policy and Procedure on Engaging Externally Contracted Service Providers 1. Purpose of this Policy The purpose of this Policy is to set down clear guidelines for the appropriate engagement of externally

More information

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are:

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are: Introduction Scope Management involves the management of techniques that make sure that the project comprises a Processes included in Scope Management are: 1. Collect Requirements In this process, project

More information

Page 1 / 11. Version 0 June 2014

Page 1 / 11. Version 0 June 2014 Page 1 / 11 CORRESPONDENCE MATRIX NQSA NSQ-100 version 0 NUCLEAR SAFETY AND QUALITY MANAGEMENT SYSTEM REQUIREMENTS Model for quality management in design & development, manufacturing, erection, commissioning

More information

DOCUMENT CONTROL INFORMATION

DOCUMENT CONTROL INFORMATION DOCUMENT CONTROL INFORMATION System: Document Title: Document Status: Quality Manual Approved 5 11/5/2014 Current Document Revision Details Formal review. Added section 2, 3. Revised section 5.5.2, 6.2,

More information

SCHEDULE [NUMBER NAME OF WORK UNIT/WORK PACKAGE] TO THE IN-KIND CONTRIBUTION AGREEMENT SIGNED BETWEEN ESS AND PARTNER ON DATE

SCHEDULE [NUMBER NAME OF WORK UNIT/WORK PACKAGE] TO THE IN-KIND CONTRIBUTION AGREEMENT SIGNED BETWEEN ESS AND PARTNER ON DATE 1 (11) TA Template V3.0 SCHEDULE [NUMBER NAME OF WORK UNIT/WORK PACKAGE] TO THE IN-KIND CONTRIBUTION AGREEMENT SIGNED BETWEEN ESS AND PARTNER ON DATE 1. SCOPE This document describes the Scope of Work

More information

Guidelines for the Preparation of Case Studies

Guidelines for the Preparation of Case Studies Guidelines for the Preparation of Case Studies Applicants for initial registration are required to demonstrate the following. Principle 1 The applicant must demonstrate that he or she is able to practise

More information

PRECISE INDUSTRIES INC. Quality Manual

PRECISE INDUSTRIES INC. Quality Manual PRECISE INDUSTRIES INC Revision N Issued July 5, 2017 Conforms to AS9100 Rev. D and ISO 9001:2015 Copyright Year2017 [PRECISE INDUSTRIES INC]; all rights reserved. This document may contain proprietary

More information

Urban. Initiative. Meeting. Construction. Annual. City of Lynchburg

Urban. Initiative. Meeting. Construction. Annual. City of Lynchburg 2014 Urban Construction Initiative Annual Meeting City of Lynchburg Materials Testing Requirements for Locally Administered Projects Don French, P.E. VDOT Lynchburg District District Materials Engineer

More information