2 Discussion Items Introductions Energy Imbalance Market Updates NITS Implementation, Cites, Videos NITS Supplemental Policy NITS on OASIS Validation/Tips Tariff Filings Action Items 1

3 Energy Imbalance Market Update Topics Covered: EIM Overview New EIM Entities EIM Billing Update BPM Updates EIM Disputes 2

4 EIM Overview - Background Energy Imbalance Market (EIM) The real-time market to manage transmission congestion and optimize energy imbalance (positive or negative) to balance supply and demand deviations for the EIM Area through economic bids submitted by EIM Participating Resource Scheduling Coordinators in the fifteen and five minute markets. 3

5 EIM Overview - EIM Charge Codes to Customers 4

6 EIM Entities 5

7 EIM Entity Billing Update NVE doesn't issue EIM T+3B invoices to customers NVE Monthly EIM T+12B Regular Invoices have been completed through the Month of September 2017 NVE Monthly EIM T+55B True-up Invoices have been completed through the Month of February 2017 NVE EIM T+9M True-up Invoices have been completed through the Month of September 2016 NVE EIM T+18M Invoices are issued only if the incremental change meets the BPM

8 BPM Changes and Update Under Attachment P, section 8.11 of the OATT, the NV EIM Entity may make corresponding changes to the suballocated charges and payments. To prevent the need for suballocating extremely small dollar amounts, the NV EIM Entity will impose a $10,000 materiality threshold to all MO recalculation settlement statements issued after T+9M as follows: MO settlement statements and recalculation statements issued up to T+9M will be sub-allocated in accordance with Attachment P of the OATT. MO recalculation settlement statements issued after T+9M will be sub allocated only if the incremental change from the prior invoice to the NV EIM Entity shows a total difference of a payment or charge greater than $10,000. New post to OASIS 7

9 NVE EIM Entity Dispute Process and Update Disputes Between the MO and NV Energy EIM Entity Related to EIM Charges and Payments from MO. Disputes between the NV Energy EIM Entity and a Transmission Customer or Interconnection Customer Related to Allocation of Charges or Payments from MO. Disputes Regarding MO Charges or Payments to NV Energy EIM Entity Raised by Transmission Customers or Interconnection Customers. File CIDI IMS for T+3B and SDS for T+12B and +T55B with CAISO. NVE Tariff 12.4A.3 Contact your NVE Billing Analyst to start the process. NVE Tariff 12.1, 12.2, 12.3, 12.4 and12.4a.1 Contact your NVE billing analyst to start the process. NVE Tariff 12.4A.4 and the process specified in the MO Tariff. NVE OASIS No Dispute Filed No Dispute Filed No Dispute Filed 8

10 9

11 NITS on OASIS NITS on OASIS - Implementation NAESB NITS on OASIS Cites OATI NITS Videos NITS OATT Requirements NITS Supplemental Policy NITS Template Validations/Checks/Tip 10

12 NITS on OASIS Standards - Adopted FERC adopts Version 003 of the North American Electric Standards Board (NAESB) Standards in Order 676-H Issued September 18, 2014 New customers required to enter NITS information into templates on NITS on OASIS Supplemental NITS required information posted on OASIS 11

13 NAESB WEQ-002 Booklet Information Secondary submission for transmission service 6-NN Transmission must be requested via the NITS on OASIS area Request Summary WEQ Template field description Concomitant requests DNR Termination is contingent on PTP purchase of transmission (or Secondary or new DNR) Submitted on Concomitant Template from Request Summary WEQ Template field description 12

14 NITS on OASIS Videos OATI has created NITS on OASIS videos which can be accessed from their Help icon from either Demo or Production, select certificate, Click on Instructional Videos on left, then Click on NITS folder 13

15 A Completed NITS Application 1. Within 5 business days of placing the Application in NITS on OASIS in the QUEUED Status, the following supplemental information must be completed and provided to the Transmission Provider (attachments available on OASIS): a. The Supplemental Application; b. The Supplemental Designated Network Resource (DNR) Information spreadsheet; c. A deposit approximating the charge for one month of service; d. A Service Agreement found in Attachment F or Attachment F-1, as applicable, of the Tariff; e. A Transmission Reduction Plan; and f. An executed Network Operating Agreement found in Attachment G of the Tariff. 14

16 Supplemental Policy and Documents Supplemental Policy, Supplemental Application and Supplemental DNR are posted to the NEVP OASIS under the NITS on OASIS folder 15

17 Supplemental Policy Requirements for Adding or Modifying a Designated Network Resource: 1. All DNR modifications or submittals must be made in NITS on OASIS 2. Must Complete and provide the Supplemental Designated Network Resource Information spreadsheet to the Transmission Provider. 16

18 Supplemental Policy Requirements for Adding or Modifying a Load: 1. Submit an Application modification or new submittal on NITS on OASIS 2. DNR modifications or submittals to serve the new load must be made in NITS on OASIS 3. Must Complete and provide the Supplemental Application with the load characteristics and the Supplemental Designated Network Resource Information spreadsheet to the Transmission Provider. 17

19 NITS on OASIS Validations - Load Add/Modify Load Template: Forecast required Forecast profile (dates must align) Valid Sink Name (registered in EIR/webRegistry; TSP adds to OASIS) Valid Load Area Point of Delivery (POD) Valid POD to Sink Combination 18

20 NITS on OASIS Validations - Resource Add/Modify NITS Resource: NITS Resource Name exists NITS Resource Forecast Profile NITS Resource Timing 19

21 NITS on OASIS Validations - DNR Add DNR (Daily, Monthly, Yearly): NITS ATC Scheduling Rights exceed ATC NITS DNR Coordinated - Coordinated Group check NITS DNR Attestation No Attestation NITS DNR Capacity Capacity requested is negative; must be positive for new DNR NITS DNR Aux Transmission Required - Off System Title Area (not NEVP); requires Auxiliary Transmission 20

22 NITS on OASIS Validations - DNR Add DNR (Daily, Monthly, Yearly) continued: NITS DNR Generation - Incorrect/Missing Gen Name or Gen Area NITS DNR SR Capacity - SR [Scheduling Rights] Capacity Requested exceeds total DNR Capacity NITS DNR Timing - Timing Validation check NITS POR - Incorrect POR NITS Resource - Resource validation checks NITS Source - Invalid Source 21

23 NITS DNR Templates Compounding Adding to NITS DNR template - compounds current DNR Unique change to the existing DNR Open template from Clipboard on Request Summary display 22

24 NITS DNR Templates Compounding Add NITS DNR template compounds current DNR Enter only the additional positive value when adding capacity to an existing DNR +MW amount for the additional dates Enter the negative value when decrementing the MW amount to an existing DNR -MW amount for the additional dates 23

25 NITS Overwriting Existing Templates Add NITS Load, Generation, and Resource templates overwrite current dates and amounts Open template from Clipboard on Request Summary display and overwrite the values being changed and/or add lines 24

26 Tariff Filings NV Energy will be filing an OATT clean up Remove any inconsistencies in the Tariff Mostly surrounding the LGIP/SGIP and timelines 25

27 Action Items Annual Required Submittals 9.1. The following submittals will be ed to the Transmission Provider pursuant to Attachment G of the Tariff: 1. By January 10th of each year, the Network Customer will submit loads and resource plans. The Transmission Provider requests the 10 year forecast be updated as a part of this submittal in the format approved and provided by the Transmission Provider and uploaded to the NITS on OASIS Load Template. In addition, the Network Customer must provide information on any planned transmission facility additions or upgrades and expected loads, which may affect their Network service. 2. By February 10th of each year, the Network Customer will provide to the Transmission Provider the maintenance schedules and planned outages of each of its designated network generating resources directly interconnected to the Transmission Provider s Transmission System for the next year. Please all submittals to: TransmissionServices@NVEnergy.com 26