Purple Line Extension. Section 1 Construction Community Meeting March 17, 2016

Size: px
Start display at page:

Download "Purple Line Extension. Section 1 Construction Community Meeting March 17, 2016"

Transcription

1 Purple Line Extension Section 1 Construction Community Meeting March 17, 2016

2 Agenda Western look ahead: Demo and sound wall construction La Brea Piling Update La Brea Decking phases l, ll,lll Fairfax look ahead: Sound wall construction, tree/ median removal, piling La Cienega look ahead: Advance utility relocation, building demo Eat Shop Play Wilshire Art Program Update Metro s Plan to Ease Traffic & Potential Ballot Measure Question & Answer 2

3 Purple Line Extension Project Alignment 3 3

4 Section 2 and 3 Status Under Construction Forecasted Schedule Section 1 Section 2 Section 3 Length 3.9 Miles 2.55 Miles 2.48 Miles New Stations Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital Pre-Construction Activities Current Construction Operations

5 PLE Section 1 Alignment 5 5

6 Purple Line Maintenance Facility Butterfield Property 590 S Santa Fe Avenue Located in Arts District downtown, near 6 th St Bridge Continuation of Abatement work Monday thru Saturday Work Hours: 7am to 4:30pm 6

7 Tie-in at Western Station Future Western Staging Yard Northeast corner of Wilshire and Manhattan Place one block east of Western Demolition activities underway. Maintenance and debris removal remain. Work Hours: 7am to 4pm, Monday thru Friday Fencing and signage placed at site Sound wall construction will follow building demolition. Additional activities in Western area include pot holing and street restoration -M-F, 9am-3:30pm -Sat-Sun, 8am-6pm Demolition Activities 7

8 Crenshaw Yard Staging Site Wilshire/Crenshaw Used throughout Section 1 utility relocation and construction Mitigation efforts and maintenance: Crenshaw Gate Entrance re-worked and improvements made Temporary fence with sound blankets in place Lorraine Gate temporarily closed until further notice No Metro Contractor Parking on City Street signs Noise awareness training, nightly noise readings Maintenance inside and outside of yard Signage at the Crenshaw Yard and Storm Drain Barriers 8 8

9 La Brea Station Rendering shows length of the La Brea underground station box on Wilshire Blvd from Orange Dr to Detroit St 9

10 Purple Line Extension La Brea Schedule *As of October Subject to Change 10

11 La Brea Station Pile Installation On Wilshire from Orange Dr. to Detroit St. Pile installation includes: Rig to construct 95ft (L) deep Crane lifting 95Ft (L), 24 Inch H-piles into holes 1-2 piles per day, 390 piles total Drilling, pile installation and backfilled concrete completed same day All work occurs behind a k-rail (concrete barriers). Operation anticipated to take approximately 4-6 months on each side of the street. Typical work hours 7am-11pm with potential nighttime work hours from 11pm to 7am. Wilshire is reduced to two lanes in each direction Additional closures may be needed. 11

12 La Brea Station Construction Pre-Trenching and Pile Installation for North side of Wilshire Continuous thru April 2016* Orange Dr to Detroit St Work hours: 7am to 11pm with potential nighttime work hours from 11pm to 7am. La Brea intersection Work hours: 9pm Friday to 6am Monday, lane reductions Pre-Trenching and Pile Installation for South side of Wilshire April 2016-July 2016* Orange Dr to Detroit St Work hours: 7am to 11pm with potential nighttime work hours from 11pm to 7am. Transition to south side may require a weekend closure or lane reductions of Wilshire Blvd from Detroit to Highland. * Will require directional closures on La Brea and intermittent closures of Orange Dr and Sycamore *Dates and work activities subject to change 12

13 La Brea Station Appendage Piles Appendage piles are the ancillary piles for the structures on the sides of the station box. Located on the north and south side of Wilshire Blvd Appendage structures include: Vent shafts, exit stairwells, and station entrance at La Brea Appendage piles are smaller and shorter (40-60ft.) than the station box piles. 112 Appendage Piles 13

14 Appendage Piles Schedule North side of Wilshire Appendage piles February-March 2016 North side Orange Dr. appendages: 2 weeks-currently underway North side La Brea Ave. appendages: 2 weeks-currently underway North side Sycamore Ave. appendages: 3 weeks South side of Wilshire Appendage Piles South side appendage structures to start May 2016 Traffic control Side streets will be closed to thru traffic at Wilshire Access from 6 th, 8 th, and alleys will be maintained Sycamore Ave. and Orange Dr. will not be fully closed concurrently at any time Intermittent sidewalk closures Appendage Pile Work at Orange Dr 14

15 La Brea Station La Brea Staging Yards Staging Yard Activities and Equipment Daytime operation: 7am to 4pm Majority of wall work completed except at location where pile installation and decking occur Sound wall is 20 feet high Maintenance of equipment Deliveries Mitigations Must comply with COLA noise requirements Noise Control Signage Low Impact Back up alarms Acoustical Insulation Metro 5 Step Noise Plan Eat Shop Play promotions and construction phase artwork N La Brea Staging Yard Pile Work 15

16 La Brea Station Decking Overview Decking On Wilshire, between Orange Dr. and Detroit St. Construction of a concrete deck, curb to curb Sidewalks be maintained, or pedestrian detours created Decking will serve as the temporary street surface Traffic will travel on the installed deck panels while the station is constructed underground La Brea Station: Approx. 1,000 feet long Approx. 70 feet wide Approx. 60 feet deep Will follow pile operations; anticipated to begin June 2016 Will work closely with First Responders on emergency access and safety 16 16

17 La Brea Station Decking Weekend Closures Start June 2016 Purple: La Brea to Detroit Phase 1: Three weekends, Detroit to La Brea Phase 2: Three weekends, La Brea intersection Green: La Brea to Highland Phase 3: 16 weekends 17

18 La Brea Station Decking Schedule *Dates and work activities subject to change June 2016 through Fall 2016 Approximately 22 weekend closures (no work 4 th of July or Labor Day weekends) Work scheduled in three phases. Fridays 10am: Wilshire (Phase 1 and 3) or La Brea (Phase 2) reduced to one lane each direction Friday 8pm: Full closure of Wilshire (Phase 1 and 3) or La Brea (Phase 2) Monday 6am: Streets open Work occurs 24/7 Phase 1: Three weekends, Detroit to La Brea Phase 2: Three weekends, La Brea intersection Phase 3: 16 weekends, La Brea to Highland 18

19 La Brea Decking Phase 1 3 Weekends-Detroit St to La Brea 19

20 Phase 1 Detour Detroit-La Brea Closure DRAFT WB: Westbound Wilshire to northbound La Brea to westbound 6th St to southbound Fairfax to Wilshire EB: Eastbound Wilshire to northbound Fairfax to eastbound 6 th St to southbound La Brea to Wilshire 20

21 La Brea Decking Phase 2 3 Weekends, La Brea Intersection 21

22 Phase 2 Westbound Detour La Brea/Wilshire Intersection Closure DRAFT WB: Westbound Wilshire to northbound Highland to westbound 6th St westbound to southbound Fairfax to Wilshire 22

23 Phase 2 Eastbound Detour La Brea/Wilshire Intersection Closure DRAFT EB: Eastbound Wilshire to northbound Fairfax to eastbound 6th St to southbound Highland to Wilshire 23

24 La Brea Decking, Phase 3 16 Weekends: La Brea to Highland 24

25 Phase 3 Detour La Brea to Highland DRAFT EB: Eastbound Wilshire to northbound La Brea to eastbound 6th St to southbound Highland to Wilshire WB: Westbound Wilshire to northbound Highland to westbound 6 th St to southbound La Brea to Wilshire 25

26 La Brea Station Decking Community Outreach Robust Marketing Campaign Social Media: Facebook, Twitter, Nextdoor Advertising: print, radio, online Media Coverage: press release Business and resident outreach Meetings with local groups, leaders Elected Official Briefings Safety Presentations School Presentations Community Partnerships Board of Public Works Approval - April I-405 Freeway Closure Carmageddon 26

27 Jet Grouting Jet grouting is a construction process that uses high-pressure air and grout to create a deep soil-concrete block. The purpose of jet grouting is to reinforce and strengthen the soil with concrete to support tunneling and cross-passage excavation. 27

28 Jet Grouting Locations *Dates and work activities subject to change Jet Grouting will occur at 16 locations along Wilshire between La Cienega and Western. There will be no more than two jetgrouting operations being performed at one time. Approximately 6 weeks at each location. 1. On Wilshire between Rossmore and Arden 2. On Wilshire between Arden and Lucerne 3. On Wilshire between Citrus and Mansfield 4. On Wilshire between Highland and McCadden Pl 5. On Wilshire between Cochran and Cloverdale 6. On Wilshire between Plymouth and Windsor 7. On Wilshire between Norton and Bronson 8. On Wilshire between St Andrews and Grammercy 9. On Wilshire between Crenshaw and Lorraine 10. On Wilshire between Wilton and Van Ness 11. On Wilshire between La Jolla and Sweetzer 12. On Wilshire between La Jolla and Sweetzer 13. On Wilshire between Crescent Heights and La Jolla 14. On Wilshire between Burnside and Dunsmuir 15. On Wilshire between Spaulding and Ogden 16. On Wilshire between Fairfax and Crescent Heights 28

29 Jet Grouting Layout & Activities Potholing, street level excavation Vertical drilling Trucking Cement silos, pumps, generators 29

30 Jet Grouting Layout Lanes reduced to two lanes each direction at Jet grouting locations 30

31 Jet Grout Schedule *Dates and work activities subject to change A jet grout soil test began this past week behind concrete barriers at Wilshire/Detroit and will occur in the staging yard at Fairfax/Ogden in Spring Jet grouting will start on Wilshire Blvd in the La Brea area in June Wilshire between Rossmore and Arden Wilshire between Arden and Lucerne Construction notices will be sent and outreach will be conducted for each location 31

32 Deck Openings What: Deck openings are openings of the streetdeck for the purpose of delivering materials for underground construction. Deck openings will be done at locations of the deck that are designed to open and close. Deck openings will occur periodically, on an as needed basis. Deck panels are 8ftx14ft When: Following decking, late summer/early fall of Through the duration of the project. How: Off-peak hour (M-F, 9am-3:30pm) lane closures to allow the removal of panels. 32

33 Deck Openings Construction Activities Requiring Concrete placement Maintenance of deck beams, panels and utilities Deliveries into excavation/station - rebar, struts, lumber, MEP equipment, shoring and formwork panels, construction equipment, ventilation, utilities, waterproofing Station backfilling Installation of new and replacement utilities 33

34 Fairfax Station Rendering shows length of the Fairfax underground station box on Wilshire Blvd from west of Fairfax to just west of Ogden Dr. 34

35 Fairfax Station Schedule *Schedule is subject to change. Updated as of January

36 Fairfax Station Advance Utility Relocation Remaining AUR telecommunication work Potholing continues Work hours: o o o Monday thru Friday: 9am-3:30pm Friday: 10pm-8am Saturday: 8am-5pm Photos of recent AUR work for Fairfax Station Photos of recent AUR work at Wilshire/Fairfax 36

37 Fairfax Station Demolition at Ogden Staging Yard Next Steps: Sound wall and driveway construction begins in April 37

38 Ogden Staging Yard Sound Wall Construction Construction of sound wall and driveways scheduled to start in April Work hours: 7am-5pm Sound wall is ft Eat Shop Play promotions and construction phase artwork will be added to the walls 38

39 Ogden Sound Wall Height & Plans 39

40 Ogden Yard Safety Measures & Mitigations. Examples fromwilshire/la Brea Staging Yard 40

41 Fairfax Tree and Median Removal Tree removal starts in April, estimated 1 week duration Median removal starts after tree removal, 3 weeks Work hours: 9:00am-3:30pm M-F, 8:00am-6:00pm Sat/Sun 38 street trees will be removed. Potential to protect in place 3 of 38. Trees replaced at a ratio of 2:1 at the end of the project Banner highlighting future landscape will be place on Ogden sound wall 3 medians to be removed from Fairfax to Spaulding. 41

42 Wilshire/Fairfax Street & Median Tree Removal Locations 42

43 Wilshire Street & Median Tree Removal Locations 43

44 Fairfax Median Removal Locations 44

45 Future Landscape Medians at Fairfax 45

46 Wilshire/Fairfax Bus Stop Relocations 46

47 Food Truck Relocation April 1 st - relocation for food trucks 1 block east of current location Existing food truck location 47

48 Fairfax Traffic Reconfiguration Piling Preparation Earliest start is June 2016 (if construction stars align!) Start date depends on DWP cable pulling, 3 rd party relocations. Install traffic reconfiguration over a single weekend implementing lane reductions. Ogden crosswalk to shift from west leg to east leg. Piling anticipated to start on North side of Wilshire Blvd between Ogden and San Diego Way. Wilshire will be reduced to two lanes in each direction. Potential off-peak lane reductions to one lane in each direction. All left turn pockets will remain open at Wilshire and Fairfax during north side pile operations only. 48

49 Fairfax Station Pile Installation Overview Pile installation includes: Rig to construct 95ft (L) deep Crane lifting 95Ft (L), 24 Inch H-piles into holes 1-2 piles per day, approx. 370 piles Drilling, pile installation and backfilled concrete completed same day All work occurs behind a k-rail (concrete barriers). Operation anticipated to take approximately 4-6 months on each side of the street. Typical work hours 7am-11pm with potential nighttime work hours from 11pm to 7am. Wilshire is reduced to two lanes in each direction Additional closures may be needed. PHOTO 47 49

50 La Cienega Station Rendering shows length of the La Cienega underground station box on Wilshire Blvd from La Cienega to Tower Dr. 50

51 La Cienega Utility Relocation 30 Months *Schedule is subject to change. Updated as of January

52 La Cienega Station Advanced Utility Relocation Electrical, Water, Sewer, Storm Drain and Gas work continues along the alignment on Wilshire from La Cienega to San Vicente. Photos of recent AUR work for the La Cienega Station 52

53 La Cienega Station Advanced Utility Relocation Current AUR activities continue during daytime and evening hours. Days and Hours* o o o Monday thru Friday: 7am 4pm Saturday or Sunday: 8am 6pm Night Time Hours: 8pm 6am or 12am 7am * Hours vary for events at The Saban Theatre 53

54 La Cienega Station Gale Yard Demolition of buildings on Gale and Wilshire May 2016 Future Gale Staging Yard Beverly Hills Fire Department may use abated properties for fire drill exercises prior to demolition Updates will be provided to the community when drills are scheduled 54

55 La Cienega Station La Cienega Yard Future La Cienega Staging Yard Buildings to be demolished, anticipated May

56 La Cienega Station Weekend Work January 16th thru May 28th work occurs in intersection at Wilshire and La Cienega Weekends, Friday thru Sunday Detours and turning restriction will depend on location of construction. Wilshire, at least one lane open in each direction La Cienega, at least one lane open in each direction Days and Hours o o Start: Friday 10pm or 1am* End: Sunday by 6pm *start time depends on the Saban Theatre performance schedule Photo 56

57 Eat, Shop, Play Wilshire ESP Spotlight- East Segment Hancock Park Veterinary Clinic 5178 Wilshire Blvd. Los Angeles, CA (One block from future La Brea Station.) They provide superior customer service, excellent medicine and fantastic bedside manner to all pets. The team displays unrivaled commitment to clients through continuing education, technological advances in veterinary medicine and service, and most importantly, administering compassionate care to all pets entrusted to them. Metro Discount: Mention Metro or Purple Line Extension and receive $20 off exam fee. More Information: Please visit HancockParkVetClinic.com or call

58 Eat, Shop, Play Wilshire ESP Spotlight- West Segment Prospect Gourmand Prospect Gourmand is a farm to table concept, using local farmers market ingredients to enhance the palate with the flavors of the season. This American eclectic cuisine is balanced with French technique, and seasonal California fare. Go Metro 272 S. La Cienega Blvd, Beverly Hills, CA Mention Metro for a complimentary nonalcoholic beverage with your meal! For more info visit: 58

59 Eat, Shop, Play Wilshire Quarterly Drawing Next drawing will occur March 29, 2016 Spend $25 at participating business Win cash prizes La Brea and Wilshire Business Stroll Saturday, April 2, am to 10pm SPONSORED BY: 59

60 Eat, Shop, Play Wilshire Fortune Fridays Support local businesses & spread the word on social media about your positive experience for a chance to win $50! Participation is easy! Use #EatShopPlay and #Wilshire in your positive social media posts. Like & Follow our pages to see the winner announcements every Friday! 60

61 61

62 Upcoming BIF Workshops Purple Line Extension, Phase 1 Wednesday, April 20, :30pm -7:30pm RED Real Estate (1st Floor) 5150 Wilshire Blvd., Los Angeles, CA *Street Parking Only For more information visit or contact Angela Winston, Program Manager at , ext 223 Wednesday, June 29, :30am -12:30pm BREATHE LA (1st Floor, Conference Room) 5858 Wilshire Blvd., Los Angeles, CA *Street Parking Only 62

63 Metro s Plan to Ease Traffic March

64 Metro s Unique Role 1,433-square mile service area across 88 cities From the desert to the beaches, Metro provides transportation to a region the size of Rhode Island that s 10 million Angelenos Provides funding for local streets, city improvements 86

65 Metro s Progress in Easing Traffic Metro provides 450 million rides a year 99 miles of rail and subway 2,200 buses providing service on through 170 routes Metro is expanding through the public s investment Two rail lines opening in 2016 Three additional rail lines in construction Several highway improvements underway Metro has a strong foundation to plan for future transportation needs 87

66 Still Much More to Do LA County expected to grow by another 750,000 people in the next 10 years Expanding LA County s transportation network: More highway and transit alternatives, local improvements, and resources to keep services in good operating condition It ll take a combination of local, federal and private dollars to fund future transportation improvements 88

67 More Local Investment Paves the Way Additional local sales tax investment will allow Metro to deliver more projects sooner rather than later The Governor recently signed into law SB767, authorizing Metro to put a sales tax measure on a future ballot Metro is considering pursuing a sales tax election in November for an additional ½ cent 89

68 What This Means for You 5 cents on a $10 purchase $50 a year to invest in easing traffic Buying a coffee drink once a week costs $260/year Eating fast food once a week costs $420/year Modest investment will bring major benefits More transportation alternatives More ways to connect through technology More community improvements More quality time, more time for you 90

69 Why Now? We spend an average of 70 hours a year stuck in traffic Time is money the longer it takes to build out transportation improvements the more expensive it will be If we don t plan now for future growth, gains of recent years will give way to more traffic congestion 91

70 Annual Revenue Assumptions New ½ cent tax = $860 million/year FY18-FY39 ½ cent building on top of existing Measure R New ½ cent and Measure R together $1.7 billion/year FY40-FY57 1 cent replaces Measure R tax rate New revenues would begin in FY18 $120 billion in YOE dollars would be generated over the 40-year program 92

71 Potential Ballot Measure Transforming transportation will include projects in all sub-regions of Los Angeles County Metro conducted a bottoms-up process with the nine sub-regions of the county, which submitted projects for evaluation 93

72 Potential Ballot Measure Metro is evaluating the major transit and highway projects through established Performance Metrics These metrics are based on industry best practices and reflects feedback from Board Members and regional stakeholders 94

73 Proposed Performance Metrics Themes & Weights Improve travel times and reliability; increase active transportation Increase service to the transit dependent, cyclists, youths, pedestrians, seniors, and people with disabilities; increase those served by Metro; improve first-last mile Enhance personal and public safety; reduce incidents Create jobs; increase goods movement; invest in disadvantaged communities Reduce greenhouse gases; improve air quality; positively impact public health 95

74 Project Evaluation Process The evaluation process will be the foundation for developing the Expenditure Plan The plan will include cost estimates and schedules for the major construction projects This process provides an opportunity to potentially accelerate some Measure R projects while keeping other existing projects on their current schedule 96

75 Next Steps Project Evaluation and Financial Modeling December 2015-March 2016 Expenditure Plan Recommendation to Board March Public Comment March-June Board Decision on November Tax Vote June 97

76 Thank you 98

77 Next Meeting Section 1 Construction Community Meeting Thursday, May 19, :30-8:30pm John Burroughs Middle School Auditorium 600 S. McCadden Pl., Los Angeles, CA Beverly Hills Specific Community Meeting Tuesday, March 29, 2016 La Cienega Tennis Center 5:30-7:00pm 99

78 Stay in Touch twitter.com/purplelineext facebook.com/purplelineext