SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

Size: px
Start display at page:

Download "SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )"

Transcription

1 SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) BUDGET - $ 72,000, PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 63% COMPLETE

2 As part of the Bond 2016 Program, Samuel Clemens High School Additions and Renovations will consist of expansion of square footage and renovation of existing spaces to meet current educational/industry standards. Some main points regarding scope of work included in this project: New Event Center (connected to Beard Gym) to house new auditorium, new auxiliary gym, new choir and dance areas, new locker rooms and support spaces. New Career & Technology (CTE) Building (near Baseball Field) to house welding, woodshop, floral design, small animal, and other learning spaces, including new classrooms. The existing Auxiliary Gym will be renovated to include additional CTE classrooms and labs, including a new culinary kitchen, health occupations spaces and other learning areas. The existing auditorium will be removed and the courtyard space will be enlarged. New Front Addition (facing Elbel Rd.) which will include new classrooms and new administration and support spaces. Renovation of JROTC spaces and existing spaces. Additional renovated spaces throughout the building, such as art rooms, teacher work spaces, nurse s clinic. Additional parking space, to include new parking along Elbel and near stadium. ESTIMATED PROJECT COMPLETION SPRING 2020.

3 SCHEDULE ACTION/EVENT FINAL DESIGN APPROVED (BOT) January 2017 PROJECTED DATE BIDS OUT FOR CONTRACTORS February 22, 2017 BIDS RECIEVED March 30, 2017 EVALUATION OF BIDS March 30 April 5, 2017 CONTRACTOR RECOMMENDATION TO BOT April 18, 2017 NOTICE TO PROCEED May 24, 2017 PROJECT COMPLETION February 2020 ONGOING ACTIVITIES CTE Building Exterior Site work Practice Gym Interior floor preparation Exterior limestone block Interior Demolition Event Center (Locker Rm Facilities) Interior/Exterior CMU walls(p Bldg.) Interior paint, tiling, steel & concrete column wraps. Classroom / Admin. Addition Exterior site work Interior finishes Event Center (Auditorium) Roofing MEP rough-ins Exterior Limestone & interior walls

4

5 Classroom and Administration Addition Expected Completion August 2018 New Administration addition. (O&L Bldg.) Wood Ceiling in Lobby foyer & Reception wall finishes. This building will be an addition to the front of the main high school front entry. This building will include nineteen instructional classrooms and support additional administration offices

6 Classroom and Administration Addition Expected Completion August 2018 New Classroom addition (H & A Bldg.) Exterior finish out & site work. This building will be an addition to the front of the main high school front entry. This building will include nineteen instructional classrooms and support additional administration offices

7 SAMUEL CLEMENS ADDITIONS & RENOVATIONS Renovate ROTC Expected Completion August 2018 Renovation of existing ROTC area.

8 Auxiliary Gym Addition Expected Completion August 2018 New Auxiliary Gym Interior athletic floor preparation. Exterior limestone blocking. This building will be an addition to Beard Gym and the future Event Center. New practice gym will seat approximately 300 people.

9 Event Center (Dance, Choir, & Locker Rooms) Expected Completion August 2018 New Event Center Exterior window framing and glazing. Choir sound isolation practice rooms. The New Event Center area will consist of: new auditorium, new dance/cheer studio, new choir room and new locker room facilities.

10 SAMUEL CLEMENS ADDITIONS & RENOVATIONS Event Center (Auditorium) Expected Completion November 2018 New Event Center (Q Bldg.) Auditorium continues with interior walls & A/C ductwork and exterior limestone & waterproofing. The New Event Center area will consist of: new auditorium, new dance/cheer studio, new choir room and new locker room facilities.

11 SAMUEL CLEMENS ADDITIONS & RENOVATIONS Renovated Administration Area Expected Completion December 2018 Interior Demolition The renovated admin area will consist of: Teacher Bullpen & lounge, Mailboxes, Storage & Vault. Nurse s Office & facilities

12 SAMUEL CLEMENS ADDITIONS & RENOVATIONS Interior Demolition Expected Completion August 2019 Area C Demo. Area A 2nd Floor Demo.

13 CTE Building 1. Exterior site work continues Classroom /Admin Addition 1. Interior finish out 2. Site work Two Week Look Ahead Auxiliary Gym 1. Install insulation & metal wall panels 2. Exterior masonry 3. Athletic wood flooring preparation & installation Event Center 1. P Bldg. Interior/Exterior limestone 2. Floor polishing, framing for large format tile, window framing & glazing 3. Q Bldg. MEP rough-ins, roofing 4. Interior/Exterior walls Interior Demolition

14 Samuel Clemens High School Schedule Overview *Schedule is subject to change throughout the construction lifecycle Phase Description Start Date Finish Date 1A Summer 1 (MDF, D-Wing Admin, S-Wing Admin, Utilities, Beard Gym HVAC Units) 6/5/2017 8/25/2017 1B North East Parking Lot 6/5/2017 February New CTE Building 6/5/ /29/2017 3A Classroom and Admin Addition (Front of Building) 6/5/2017 7/31/2018 3B Renovate Existing Admin 6/4/ /28/2018 4A New Auxiliary Gym 6/5/2017 7/31/2018 4B Event Center (Locker Rooms, Choir, Dance, Bridge to B-Wing) 6/5/2017 7/31/2018 4C New Auditorium 6/5/ /1/2018 5A Summer 2 (Renovate ROTC, Campus Lighting Replacement, Terrazzo Floor) 6/4/2018 8/17/2018 5B ROTC Renovation (Start Early) 1/1/2018 8/15/2018 5C Alt #3. Construct New Stair on West Side of Building 6/4/ /28/2018 6A Demo Existing Auditorium and Auxiliary Gym 6/4/2018 8/2/2018 6B Culinary Arts, HOSA, Forensics, Courtyard, Science Renovation, Bridge Addition 8/3/2018 8/16/2019 7A A-Wing Renovation 6/3/2019 8/16/2019 7B B-Wing Renovation 6/3/2019 8/16/2019 7C Remove Portables and Complete Parking Lot Near Schertz Pkwy 6/10/ /31/2019