1 School Name: Hugh Sutherland School School Code: 5101 Location: Carstairs Facility Code: 892 Region: Central Superindendent: Mr. Herb Faeder Jurisdiction: Chinook's Edge School Division #73 Contact Person: Mr. Cliff Barr Telephone: (403) Grades: K to 12 School Capacity: 790 Building Section Original Building Year of Compl. No. of Floors Gross Bldg Area (Sq.M.) Type of Construction (i.e., structure, roof, cladding) wood frame construction, flat roof, crawl space, exterior face brick. Description of Mechanical Systems (incl. major upgrades) gas fired boilers serving heating pumps and radiation, air handling units. Comments/Notes Additions/ Expansions masonry construction with exterior brick cladding, flat roof. masonry construction with exterior brick cladding, flat roof. gas fired boilers serving heating pumps and radiation, air handling units. gas fired boilers serving heating pumps and radiation, air handling units. one of two original stand alone buildings. Joined together with 1967 addition masonry construction with exterior brick cladding, flat roof. gas fired boilers serving heating pumps and radiation, air handling units masonry construction with exterior brick cladding, flat roof. gas fired boilers serving heating pumps and radiation, air handling units masonry construction with exterior brick cladding, flat roof. gas fired boilers serving heating pumps and radiation, air handling units. Evaluator's Name: & Company: Burgess Bredo Burgess Bredo Architect Ltd. 1

2 Upgrading/ Modernization (identify whether minor or major) Major upgrading: mechanical and electrical throughout, sprinklers and new ceilings throughout. Significant renovations to portions of 1962 and 1973 phases. Portable Struct. (identify whether attached/perman. or free-standing/ relocatable) No portables. List of Reports/ Supplementary Information Roofing Report: April 1996, (Baxter and Carter Edward's and Associates Ltd.) 2

3 Evaluation Components Summary Assessment 1 Site Conditions Settlement in concrete sidewalks to be repaired. $4, Building Exterior 3 Building Interior Roofing report indicates approximately 62% of roof requires replacement now or within 5 years. Wood windows in 1973 phase require replacement. Miscellaneous repairs. Complete upgrading of finishes throughout school. Replace doors and millwork in 1953 and 1958 phases. A chairlift needs to be provided. Miscellaneous upgrading and repairs. Provide asbestos audit. $239, $320, Mechanical Systems Mechanical system is currently undergoing a major upgrade of the heating and ventilation system. Some of the building washrooms need to be upgraded. In addition, the ventilation system to the Industrial Arts room is poor and needs to be upgraded. 5 Electrical Systems The electrical system in the building is currently undergoing a major upgrade. Parking area is in poor shape and needs to be upgraded. A chair lift needs to be provided. Some lighting remains to be upgraded. $185, $63, Portable Buildings No portables NIL 7 Space Adequacy: 7.1 Classrooms 7.2 Science Rooms/Labs 7.3 Ancillary Areas 7.4 Gymnasium 7.5 Library/Resource Areas 7.6 Administration/Staff Areas 7.7 CTS Areas Excessive Deficient Deficient Deficient Deficient Deficient Deficient Non-Instructional Areas (incl. gross-up) Excessive Overall School Conditions & s Deficient $811,

4 Section 1 Site Conditions Rating Comments/Concerns 1.1 General Site Condions Overall site size. 4 Adequate in size Outdoor athletic areas. 4 Baseball, soccer and football playing field Outdoor playground areas, including condition of equipment and base. 4 Playground equipment in good condition Site landscaping. 4 Trees and lawn landscaping at south and west end of school. Natural grasses in balance Site accessories (i.e., perimeter and other fencing, guard rails, bike stands, flag poles). 4 Chain link fencing around site, bike stands and flag poles Surface drainage conditions (i.e., drains away from building, signs of ponding). 4 Site drains away from building. Catch basin located at south side of 1972 portion Evidence of sub-soil problems. 4 No problems evident Safety and security concerns due to site conditions. 3 Settlement in sidewalks have created small steps +/- 75 mm which create a tripping hazard. Replace or mud jack concrete to eliminate steps. Costed in Access/Drop-Off Areas/Roadways/Bus Lanes Vehicular and pedestrian access points (i.e., size, number, visibility, safety). 4 All access from service road which parallels street (highway) on south edge of school. 4

5 Section 1 Site Conditions Rating Comments/Concerns Surfacing of on-site road network (note whether asphalt or gravel). 4 Service road has gravel surface Bus lanes/drop-off areas (note whether on-site or offsite). 4 Bus drop-off in service road which appears to be off-site Fire vehicle access. 4 Good access to all sites of school Signage. 4 Building signed. Parking signed. 5

6 Section 1 Site Conditions Rating Comments/Concerns 1.3 Parking Lots and Sidewalks Number of parking spaces for staff, students and visitors (including stalls for disabled persons) energized stalls for staff, 16 stalls in temporary lot at west end of school Layout and safety of parking lots. 4 Parking lots well separated from playing fields and playgrounds Surfacing and drainage of parking lots (note whether asphalt or gravel). 4 Gravel surfacing with sufficient drainage at east staff lot. Temporary parking on grass area assumed to be removed Layout and safety of sidewalks. 4 Sidewalks separated from parking and do not cross bus lanes Surfacing and drainage of sidewalks (note type of material). 3 Concrete sidewalks have settled creating hazardous steps. Significant spalling of concrete surfaces. Replace or mud jack sidewalks to eliminate steps. $4, Curb cuts and ramps for barrier free access. 4 Wood ramps to several entrances. Overall Site Conditions & Estimated Costs $4,

7 Section 2 Building Exterior Rating Comments/Concerns 2.1 Overall Structure Bldg. Section Floor structure and beams (i.e., signs of bending, cracking, heaving, settlement, voids, rust, stains). Description/Condition Wood framing over crawl space. Steel and metal deck mezzanines; no problems noted Wall structure and columns (i.e., signs of bending, cracking, settlement, voids, rust, stains) Balance Wood frame construction; no problems noted. Masonry construction; no problems evident Roof structure (i.e., signs of bending, cracking, voids, rust, stains) Wood frame assembly; no problems noted. Steel and metal deck roof assemblies; no problems noted. Balance Glu-lam beams and wood deck over gymnasium, steel beams and wood deck over balance; no problems evident. 7

8 Section 2 Building Exterior Rating Comments/Concerns 2.2 Roofing and Skylights Identify the availability of an up-to-date inspection report or roofing program. Note if roof sections are of different ages and/or in varying states Based on of repair. the inspection report (and to the extent possible, direct observation), assess and rate roof conditions and estimate costs for required improvements (i.e., covering materials, membrane, insulation, other components). Bldg. Section or Roof Section Description/Condition/Age 2 3,6 and 7 Conventional BUR with service life to 1987/93. Replace membrane, gravel stop flashings and plumbing vents while improving drainage pattern (1224 sq.m.). 1,2,4 and 5 Conventional BUR with service life to 1987/93. Replace membrane, gravel stop flashings and plumbing vents while improving drainage pattern (2062 sq.m.) Conventional BUR: service design life up to 2011/13. No work required at this time. Recommendations based on April 1996 roofing report. Refer to report for description of roof areas. $225, Roof accessories (i.e., ladders, stairs, hatches, masts, exhaust hoods, chimneys, gutters, downspouts, splashpads). 4 All Roof accessed by ladder from mechanical room Control of ice and snow falling from roof. 4 All No problems evident Skylights (i.e., signs of distress, leaks, ice build-up, condensation, deteriorated materials/seals). 4 All Original skylights have been roofed over. 8

9 Section 2 Building Exterior Rating Comments/Concerns 2.3 Exterior Walls/Building Envelope Bldg. Section Exterior wall finishes (i.e., signs of deterioration, cracks, brick spalling, effluorescence, water stains). Description/Condition 4 All Face brick; no problems evident Fascias, soffits, parapets (i.e., signs of looseness, stains, rust, peeling paint). 4 All Painted wood fascia, aluminum soffits; no problems evident Building envelope (i.e., evidence of air infiltration/ exfiltration through the exterior wall or ice build up on wall, eaves, canopy). 4 All Painted concrete block/wood frame walls and conventional BUR form primary components of building envelope. No evidence of air infiltration or exfiltration Interface of roof drainage and ground drainage systems. 3 All A number of splash pads below rain water leaders should be re-seated to provide positive drainage away from building. $ Inside faces of exterior walls (i.e., signs of cracks, water stains, dust spots). 4 All Minor cracking and water stains from past leaks. 2.4 Exterior Doors and Windows Bldg. Section Doors (i.e., signs of deterioration, rusting metal, glass cracks, peeling paint, damaged seals, sealed unit failure). Description/Condition 4 All Aluminum entrances set in aluminum frames, hollow metal doors set in pressed steel frames. 9

10 Section 2 Building Exterior Rating Comments/Concerns Door accessories (i.e., latches, hardware, screens, locks, alarms, holders, closers, security devices). 3 All Approximately 50% of exterior doors require new weather stripping $ Exit door hardware (i.e., safety and/or code concerns). 4 All Push bar panic devices performing as required, no concerns Windows (i.e., signs of deterioration, rusting metal, glass cracks, peeling paint, damaged seals, sealed unit failure) Balance Wood window frames in poor condition and drafty. Replace. Aluminum framed windows have replaced original. $12, Window accessories (i.e., latches, hardware, screens, locks, alarms, holders, closers, security devices) Balance Hardware for awning type vents in poor condition; replace. Aluminum insect screens and push bars for hopper type vents functioning as required. Costs in Building envelope (i.e., signs of heavy condensation on doors or windows). 4 All Aluminum windows, wood windows, aluminum entrances and hollow metal doors show no evidence of heavy condensation. Overall Bldg Exterior Condition & Estim Costs $239,

11 Section 3 Building Interior - Overall Conditions Rating Comments/Concerns 3.1 Interior Structure Bldg. Section Description/Condition Interior walls and partitions (i.e., signs of cracks, spalling, paint peeling) ,58 Wood frame with gypsum board finish. Some cracking, repair prior to next re-painting. Balance Concrete block and frame partitions; no problems evident Floors (i.e., signs of cracks, heaving, settlement). 4 All Concrete slab on grade; no problems evident. 3.2 Materials and Finishes Floor materials and finishes Wall materials and finishes , , , , Linoleum and 9 x9 vinyl tiles due for replacement. Gymnasium hardwood floor requires sanding, repair and re-finishing. 9x9 tile to be replaced by June, 2000 in bulk; replace remaining. Gym hardwood flooring requires sanding, repair and re-finishing. Industrial Arts flooring is hardwood and painted concrete; re-finish. Vinyl tile and carpet in good condition. Gypsum board requires re-painting. Concrete block and frame partitions to be upgraded June, Gym and 4 classrooms require repainting. Concrete block; requires re-painting. Painted concrete block in good condition. $82, $60, Ceiling materials and finishes ,58, New acoustic tile in T-bar grid by June, New acoustic tile in T-bar grid by June, 2000 in bulk of areas. New acosutic tile ceiling required in 4 classrooms. $7,

12 Section 3 Building Interior - Overall Conditions Rating Comments/Concerns 3.2 Materials and Finishes (cont'd) Interior doors and hardware. 1953,58 Wood doors set in wood frames; doors, frames and hardware in poor condition; replace ,67, 73 New wood doors and pressed steel frames to be in place by June, $27, Millwork Fixed/wall mounted equipment (i.e., writing boards, tackboards, display boards, signs) , Wood and hollow metal doors set in pressed steel frames; good condition. Painted/clear cabinets with plastic laminate/linoleum countertops; poor condition, replace. Home EC millwork is painted wood in marginal condition; functional layout could be improved, replace. Balance of millwork in this phase to be replaced by June, Bulk of millwork to be replaced by June, Replace in 4 classrooms. Utilitarian work benches in acceptable condition. Clear wood cabinets with plastic laminate countertops, good condition. $110, All Chalkboards to be replaced with whiteboards by June Tackboards throughout in good condition Any other fixed/mounted specialty items (i.e., CTS equipment, gymnasium equipment). 4 All Wide variety of CTS and gymnasium equipment; good condition Washroom materials and finishes Floors: ceramic tile, walls: ceramic tile, ceilings: gypsum board; good condition Floors: quarry tile; replace, walls: masonry, ceilings: gypsum board $5, ,67, Upgraded by June, Acoustic treatment in gymnasium in poor condition; replace Toilet partitions in poor condition replace. $7, All New lockers to be in place in 1962 phase by June,

13 Section 3 Building Interior - Overall Conditions Rating Comments/Concerns 3.3 Health and Safety Concerns --- Intent is to identify renovations considered necessary to meet applicable codes, primarily due to safety concerns. Basis of evaluation should be an up-todate inspection report from the authority having jurisdiction together with direct observations as appropriate. Evaluator should note if in his opinion a comprehensive code evaluation is Building required. construction type - combustible or noncombustible, sprinklered or non-sprinklered. 4 All Combustible and non-combustible construction, sprinklered by June, Complies Fire separations (i.e., between buildings, wings, zones if non-sprinklered). 4 All Building separated into zones with doors set in pressed steel frames; complies Fire resistance rating of materials (i.e., corridor walls and doors) Balance Underside of stage floor assembly is wood and requires gypsum board. Complies. $1, Exiting distances and access to exits. FI 1953 Balance Second floor area should have exit directly to exterior. Complies Barrier-free access. 3 All Path of Travel: 3 of 4 required stair lifts to be in place by June, 2000; provide fourth. Doors and Doorways: power assisted entrance at main entry, balance of doors comply. Washrooms: assumed that new washrooms in current modernization of 1962 phase to comply. $15, Availability of hazardous materials audit (i.e., evidence of safety concerns with respect to asbestos, PCB's, chemicals). 3 All No asbestos audit available, provide. $5, health and safety concerns (i.e., evidence of excessive noise conditions, air quality problems) FI 1958 Toilets sitting up off floor may create hygiene problem. Overall Bldg Interior Condition & Estim Costs $320,

14 Section 4 Mechanical Systems Rating Comments/Concerns 4.1 Mechanical Site Services Site drainage systems (i.e., surface and underground systems, catch basins). 4 All One catch basin to building west side. No problems noted Exterior plumbing systems (i.e., irrigation systems, hose bibs). 4 All A few hose bibs at building exterior. No irrigation. No problems noted Outside storage tanks. 4.2 Fire Suppression Systems Fire hydrants and siamese connections Siamese connection being installed at building south side for service to sprinkler system. New with no problems noted Fire suppression systems (i.e., pumps, sprinklers, piping, reservoirs, hoses, stand pipes, CO2 systems). 5 All Sprinkler system provided throughout building - new Hand extinguishers, blankets and showers (i.e., in CTS areas). 5 All ABC type multi-purpose fire extinguishers provided throughout building - new special situations (e.g., flammable storage areas, science labs, CTS areas). Not required. 14

15 Section 4 Mechanical Systems Rating Comments/Concerns 4.3 Water Supply and Plumbing Systems Domestic water supply (i.e., pressure, volume, quality - note whether municipal or well supply) Municipal service with 152 main water service with 101 mm service to sprinkler system and 101 mm service to water meter and building. No problems noted Water treatment system(s) Pumps and valves (including backflow prevention valves) Backflow prevention provided to sprinkler system. No pumps. Valves all in good condition with no problems noted Piping and fittings. 4 All Copper water supply piping. All piping appears in good condition with no problems noted Plumbing fixtures (i.e., toilets, urinals, sinks) Floor in washrooms appears to be settling and water closets have lifted from floor and fixtures in poor shape - upgrade required. $80, Domestic hot water system (i.e., heater, storage tanks, failure alarms, pressure, volume, recirculation). Balance All other areas have several fixtures in poor shape that require replacement Two State 70 gallon hot water heaters with Taco recirculating pump - new Sanitary and storm sewers, including sumps and pits (note whether sewage system is municipal or septic) Municipal service connection. Portion of sewer line in basement has settled, is filled with water, and plugs on a regular basis. Replace sewer line. $35, Sewage lift station installed at building south side. Complaints of sewer odor from station. Sealing of lift station likely required along with other general repairs. $5,

16 Section 4 Mechanical Systems Rating Comments/Concerns 4.4 Heating Systems Heating capacity and reliability (including backup capacity) Superhot 2760 MBH input boilers and 2 Taco pumps serving heat pumps and some perimeter radiation. Installation is brand new Heating controls (including use of current energy management technology Connected to building energy management system Fresh air for combustion and condition of the combustion chimney Combustion air appears adequate. Chimney constructed of galvanized sheet metal. New installation Treatment of water used in heating systems. 5 All System is new and will be treated with chemicals Low water cutoff/pressure relief valves and failure alarms (i.e., hot water heating) Low water cut-off and pressure relief valves to boilers. Boiler alarm through building energy management system. New installation Heating air filtration systems and filters. 4 All Air filters provided to heat pumps are bulk replaceable type media in wire cages Heating humidification systems and components. None provided and none requested. 16

17 Section 4 Mechanical Systems Rating Comments/Concerns 4.4 Heating Systems (cont'd) Heating distribution systems (i.e., piping, ductwork) and associated components (i.e., diffusers, radiators). 5 All Schedule 40 steel piping to heating system and ductwork for forced air system. Force flow units at entrances. New installation Heating piping, valve and/or duct insulation. 5 All Fresh air ductwork is insulated as well as domestic water lines and hot water heating lines. New installation Heat exchangers Tube style heat exchangers in boilers. New installation Heating mixing boxes, dampers and linkages Heating distribution/circulation in larger spaces (i.e., user comfort, temperature of outside wall surfaces). 4 All Even heating throughout building with no problems noted Zone/unit heaters and controls. 5 All Some radiation, unit heaters, and force flow units. New installation. 17

18 Section 4 Mechanical Systems Rating Comments/Concerns 4.5 Ventilation Systems Air handling units capacity and condition New Engineered Air ventilation unit in basement in excellent condition Under renovation - units not yet delivered to site in excellent condition. $50, Engineered Air MUA unit with marginal ventilation to Industrial Arts Room - upgrade required Outside air for the occupant load (if possible, reference CFM/occupant). 4 All Design requirements unknown. Likely designed at 15 CFM per student. Installation appears satisfactory with no problems noted Air distribution system (if possible, reference number of air changes/hour). 4 All Design requirements unknown. Air flow appears good with no problems noted Exhaust systems capacity and condition Exhaust ventilation in gym change rooms very poor - upgrade required. 3 Balance Exhaust capacity unknown. Exhaust generally provided in building washrooms and building general exhaust with rating of 4 and no major problems noted except for 1962 section. $15, Separation of out flow from air intakes. 4 All Appears to be good separation with no problems noted Special/dedicated ventilation and/or exhaust systems (i.e., kitchen, labs, CTS areas). 4 All Several exhaust fans to Industrial Arts with service to welding, Murphy Dust Collector, general exhaust, and kiln. 18

19 Section 4 Mechanical Systems Rating Comments/Concerns 4.5 Ventilation Systems (cont'd) Note: Only complete the following items if there are separate ventilation and heating systems Ventilation controls (including use of current energy management technology) Air filtration systems and filters Humidification system and components Heat exchangers Ventilation distribution system and components (i.e., ductwork, diffusers, mixing boxes, dampers, linkages). 19

20 Section 4 Mechanical Systems Rating Comments/Concerns 4.6 Cooling Systems Cooling system capacity and condition (i.e., chillers, cooling towers, condensers) Balance Ventilation unit complete with integral condenser. Remainder of building cooled with heat pumps. Installation is generally new Cooling distribution system and components (i.e., ductwork, diffusers, mixing boxes, dampers, linkages) 5 All Piping and ductwork, all appear in good shape with no problems noted Cooling system controls (including use of current energy management technology). 5 All System connected to building energy management system with no problems noted Special/dedicated cooling systems (i.e., labs, CTS areas). 4.7 Building Control Systems Building wide/system wide control systems and/or energy management systems. 4 All Combination of Integrated Controls and Barber Coleman No problems noted. Overall Mech Systems Condition & s $185,

21 Section 5 Electrical Systems Rating Comments/Concerns 5.1 Site Services Primary service capacity and reliability (i.e., access, location, components, installation, bus sizes - note whether overhead or underground) Underground service from pad mounted utility transformer on south side of building. Service appears to have a 1000 amp main circuit breaker, 120/208V/3PH/4W with Siemens switchgear. No problems noted Site and building exterior lighting (i.e., safety concerns). 3 All High pressure sodium light fixtures along portions of the building exterior. Additional light fixtures required in order to provide security lighting. Upgrade required. $8, Vehicle plug-ins (i.e., number, capacity, condition). 3 All Approximately 56 stalls. Most of the parking posts are damaged and not working. Replacement required in order to provide reliable service. $35, Life Safety Systems Fire and smoke alarm systems (i.e., safety concerns, up-to-date technology, regularly tested). 5 All New Mirtone fire alarm system complete with visual strobe lights Emergency lighting systems (i.e., safety concerns, condition). 5 All New DC battery pack units with remote heads Exit lighting and signage (i.e., safety concerns, condition). 5 All New LED type electronic exit signs. 21

22 Section 5 Electrical Systems Rating Comments/Concerns 5.3 Power Supply and Distribution Power service surge protection. 3 All Provide surge protection. $5, Panels and wireways capacity and condition. 4 All Some existing and mostly new panelboards. Wiring installation in building is incomplete. Assumed that panelboards will have some spare capacity for future wiring Emergency generator capacity and condition and/or UPS (if applicable) General wiring devices and methods. 4 All Wiring devices generally in good shape and provided with stainless steel coverplates. No problems noted Motor controls. 4 All Mixture of motor starters with all generally appearing in good shape with no problems noted. 22

23 Section 5 Electrical Systems Rating Comments/Concerns 5.4 Lighting Systems Interior lighting systems and components (i.e., illumination levels, conditions, controls). 3 All Recess mounted T8 style fluorescent light fixtures provided in most areas excluding General Office and Industrial Arts rooms. Where T12 light fixtures are used, they are in poor shape and should be upgraded. $15, Replacement of ballasts (i.e., health and safety concerns). 4 All No health and safety concerns noted Implementation of energy efficiency measures and recommendations. 4 All All rooms generally separately switched. No concerns noted. 23

24 Section 5 Electrical Systems Rating Comments/Concerns 5.5 Network and Communication Systems Telephone system and components (i.e., capacity, reliability, condition). 5 All New telephone system integrated with building intercom system communication systems (i.e., public address, intercom, CCTV, satellite or cable TV). 5 All New Rauland intercom system integrated with building telephone system Network cabling (if available, should be category 5 or better). 4 All Category type 5 wiring with no problems noted Network cabling installation (i.e., in conduit, secured to walls or tables). 4 All Computer installation is under renovation and will be installed in conduit and wireways Wiring and telecommunication closets (i.e., size, security, ventilation/cooling, capacity for growth). 4 All Two hubs each with spare space Provision for dedicated circuits for network equipment (i.e., hubs, switches, computers). 4 All Power wiring to computers and equipment appears in good shape with no problems noted. 24

25 Section 5 Electrical Systems Rating Comments/Concerns 5.6 Miscellaneous Systems Site and building surveillance system (if applicable) Intrusion alarms (if applicable). 4 All General type of security system using motion detectors, magnetic door contacts, alarm keypad, and card access system. System monitored through central monitoring station with no problems noted Master clock system (if applicable). 4 All Class change through Rauland intercom system. No problems noted. 5.7 Elevators/Disabled Lifts (If applicable) Elevator/lift size, access and operating features (i.e., sensing devices, buttons, phones, detectors) new Ram Trus Lifts provided. One additional chair lift required at stairs. Costed in Condition of elevators/lifts Ram Trus Lifts provided are new and in very good condition Lighting and ventilation of elevators/lifts. Overall Elect. Systems Condition & Estim Costs $63,

26 Section 6 Portable Buildings Rating Comments/Concerns Note: Separate sheets can be completed, if necessary, for portable buildings of different ages and/or conditions Foundation and structure (i.e., signs of bending, cracking, settlement, rust, voids, stains) Roof materials and components (i.e., signs of deterioration, leaks, ice build-up) Exterior wall finishes (i.e., signs of deterioration, cracks, water stains) Doors and windows (i.e., signs of deterioration, rusting hardware, glass cracks, peeling paint, damaged seals) Interior finishes (i.e., floors, walls, ceiling) Millwork (i.e., counters, shelving, vanities, cabinets) Fixed/wall mounted equipment (i.e., writing boards, tackboards, display boards, signs) Heating system Ventilation system Electrical, communication and data network systems Health and safety concerns (i.e., fire and smoke alarms, fire protection systems, exiting, fire resistance rating of materials) Barrier-free access. Overall Portable Bldgs Condition & Estim Costs $

27 Section 7 Space Adequacy 7.1 Classrooms This Facility Equiv. New Facility No. Size Total Area No. Size Total Area Surplus/ Deficiency Comments/Concerns Based on Junior High tables, capacity Science Rooms/Labs Ancillary Areas (i.e., Art, Computer Labs, Drama, Music,) Gymnasium (incl. gym storage) Both gyms including storage, showers and stage. 7.5 Library/Resource Areas Administration/Staff, Physical Education, Storage Areas 7.7 CTS Areas Business Education Home Economics Industrial Arts CTS Programs 7.8 Non-Instructional Areas (i.e., circulation, wall area, crush space, wc area) Overall Space Adequacy Assessment