SS 576 : 2012 KEY REQUIREMENTS AND APPLICABLE LEGISLATION. Presented by : Er Joseph Michael

Size: px
Start display at page:

Download "SS 576 : 2012 KEY REQUIREMENTS AND APPLICABLE LEGISLATION. Presented by : Er Joseph Michael"

Transcription

1 SS 576 : 2012 KEY REQUIREMENTS AND APPLICABLE LEGISLATION Presented by : Er Joseph Michael

2 Part 1 - Key Requirements of SS 576 : 2012

3 Identification of Key Stakeholders The Key Stakeholders are defined in Section 3 Definitions of SS 576 : 2012 Transmission Agent Licensee SP PowerGrid Ltd (SPPG); Principal; Contractor; Registered Earthworks Supervisor; Licensed Cable Detection Worker (LCDW); and REO (Registered Excavator Operator) & PREO (Provisional REO). 3

4 General Responsibilities of Key Stakeholders The general responsibilities are outlined in Section 5.1 The Principal, the Contractor and the LCDW : Familiarization with the legislation Electricity Act ( Cap 89A); Familiarization with the process of consultation with the Transmission Agent Licensee with respect to: i) cable detection work; ii) cable diversion; and iii) protection schemes for cables; Familiarization with Table 2; and Response in the event of a cable damage or emergency situation. The Principal and the Contractor : Must put in place a Permit-to-Work System for carrying out earthworks at the worksite. 4

5 Specific Responsibilities of Key Stakeholders Transmission Agent Licensee The responsibilities of the Transmission Agent Licensee are elaborated in Section 5.2 Provide cable route plans upon request; Put in place a system to accept Notice of Commencement of Earthworks (NCEs); Conduct site meetings with Contractor; Issue a Letter of Requirements advising the Contractor of measures to be implemented to prevent damage to high voltage cables; Visit the site periodically; Investigate all cases of cable damage and acts of non-compliance by Contractors; and Submit Investigation Case Files to EMA, the regulator. 5

6 Specific Responsibilities of Key Stakeholders - Principal The responsibilities of the Principal are elaborated in Section 5.3 Specify in the contract documents 1)that their Contractors shall obtain cable route plans from TAL; and 2)engage a LCDW to do cable detection work prior to commencement of earthworks; Include in the contract documents that their Contractors shall consult the TAL whenever they propose to do earthworks; and Implement a Permit-to-Work System to monitor and control earthworks within their site. 6

7 Specific Responsibilities of Key Stakeholders - Contractor The responsibilities of the Contractor are elaborated in Section 5.4 Compliance with the Electricity Act, SS 576 : 2012 and requirements of TAL ; Engagement of the services of the LCDW; Engagement of the services of the REO & PREO; Submission of NCE to TAL for High Voltage cables; Submission of Schedule of Construction Activities to TAL; Do Risk Assessment in compliance with the WSHA; 7

8 Specific Responsibilities of Key Stakeholders - Contractor The responsibilities of the Contractor are elaborated in Section 5.4 Provide free access to TAL to inspect their cables; Conduct briefing sessions for employees; Make Trial Hole Information available to TAL; Make Cable Detection Report available to TAL; and Ensure security of site and that no unauthorized earthworks is carried out. 8

9 Specific Responsibilities of Key Stakeholders- Registered Earthworks Supervisor The responsibilities of the Registered Earthworks Supervisor are elaborated in Section 5.5 Ensure that LCDW marks detected cables on site; Ensure that the Permit-to-Work and the cable detection plans are prominently displayed or readily available for inspection; Ensure that Trial Holes are manually dug; Check that REOs and PREOs have valid registration cards; Conduct periodic checks during excavation works and consult LCDW or TAL when in doubt; 9

10 Specific Responsibilities of Key Stakeholders- Registered Earthworks Supervisor The responsibilities of the Registered Earthworks Supervisor are elaborated in Section 5.5 When a cable damage occurs, Earthworks Supervisor shall stop excavation works immediately and inform TAL, LCDW and the Contractor; Ensure that excavation works can only resume after obtaining clearance from TAL; Consult TAL in the event of overcrossing or undercrossing electricity cables; and Ensure that preventive measures required by TAL are implemented to protect existing electricity cables. 10

11 Specific Responsibilities of Key Stakeholders - LCDW The responsibilities of the Licensed Cable Detection Worker (LCDW) are elaborated in Section 5.6 Submit request for cable route plans and NCD to TAL (Refer Annex E); After cable detection work is complete, advise Contractor to submit NCE to TAL; LCDW shall do the cable detection work personally and mark cable routes on site. LCDW shall specify the number of Trial Holes and where they are to be dug, collate trial hole information and produce a written cable detection report. LCDW shall conduct a briefing for site personnel e.g. PM or CM, Site Supervisors and Excavator Operators on the route and position of cables and preventive measures implemented or to be implemented. When a cable damage occurs, the LCDW shall conduct a site investigation and submit a report on Form ROD (Annex E) to TAL. 11

12 Specific Responsibilities of Key Stakeholders The responsibilities of the Registered Excavator Operator (REO) / Provisional Registered Excavator Operator (PREO) are elaborated in Section 5.7 REO or PREO shall only carry out earthworks with an excavator provided cable detection work has been carried out by LCDW, trial holes have been dug and a Permit-to-Work has been issued; REO or PREO shall establish the position and route of the cable after making reference to the cable detection drawings and markings on the ground; and If HV cables are present underground, REO or PREO shall check with the Earthworks Supervisor if an NCE has been submitted to the TAL. 12

13 Works in the Vicinity of Underground Cables Table 1 Works below ground level in the vicinity of underground cables Types of work below ground level Trench or other excavation works in stable ground conditions up to 1.5 m in depth Trench or other excavation works in stable ground conditions over 1.5 m in and up to 5 m in depth Distance * (m) 3 5 Trench or other excavation works in stable ground conditions over 5 m 10 Vertical penetration including sheet piling, ground investigation and any kind of drilling or core sampling or ramming 3 Welding or other hot works near exposed underground cables 10 * Measurement is taken from both extreme edges of the underground cable or bunch of cables to determine whether works will be considered to be in its vicinity. 13

14 Cable Detection Work & Cable Detection Methods Available Electromagnetic Location; and Radio Frequency Passive Detection. Outcome of cable detection work and trial hole digging is the Written Report by LCDW. The objective of the Written Report is to standardise the contents of the report submitted by the LCDWs to their clients. 14

15 Diversion or Protection of Cables When there is a direct conflict between a proposed civil structure and an existing cable, there are 3 options available to the Principal or Contractor: Option 1 Consider the redesign of the civil structure and relocate it from its originally proposed position; Option 2 If the civil structure cannot be relocated, then the cable has to be diverted; Option 3 If there is sufficient clearance between the civil structure and the cable, then an appropriate protection scheme must be implemented. 15

16 Risk Management Section 9 This section covers compliance with Workplace Safety and Health Act (WSHA) Work sites come within the definition of Workplace in the WSHA; It is therefore mandatory for the Contractor to do a Risk Assessment and put in place appropriate control measures to mitigate the risk; A Risk Assessment report shall be made available to the TAL on request; and The contractor shall communicate the control measures implemented to all personnel at various working levels in the project team. 16

17 Emergency Response Plan Section 9.2 Emergency Response Plan It is good practice for the Contractor to have in place an Emergency Response Plan and review it at appropriate intervals; During the course of earthworks, all site personnel must be vigilant and look out for tell-tale signs of cable damage; When a cable is damaged, the Earthworks Supervisor shall activate the Emergency Response Plan to stop all earthworks activities immediately; The Earthworks Supervisor shall inform relevant parties such as the LCDW and the TAL; The LCDW shall conduct a site investigation and submit a report to TAL on Form ROD ( Annex E ) within 48 hours of the event; The Contractor shall submit an Incident Report to MOM in compliance with WSHA. 17

18 Training & Registration of Earthworks Supervisor To enable the Registered Earthworks Supervisor to discharge his duties effectively, he needs to undergo training. The first run of the Earthworks Supervisor Course is expected to be rolled out in late 2013; SPPG will manage the register of Earthworks Supervisors. 18

19 Part 2 Applicable Legislation

20 The Legislative Hierarchy ACTS REGULATIONS CODES OF PRACTICE STANDARDS 20

21 Sections of the Electricity Act Relating to Cable Damages Section 2 - Definition of Earthworks Section 79 - Applies to carrying out earthworks near LV cables Section 80 - Applies to carrying out earthworks near HV cables Section 85(1) - Offence Clause applying to damage of HV & LV cables Section 85(2) - Offence Clause applying to damage of HV cables 21

22 Section 2 of the Electricity Act - Definition of Earthworks earthworks means (a)any act of excavating earth, rock or other material (by whatever means) in connection with (i) any work for or relating to the construction, reconstruction, extension, renovation, alteration, demolition or repair of any building, road, railway, bridge, viaduct, flyover, sewer or sewage works; (ii) any work for or relating to the laying, inspecting, repairing or renewing of any main, pipe, cable, fitting or other apparatuses; (iii) any soil investigation work; or (iv) such other works as are usually undertaken by a person carrying on business as a contractor in the construction industry or as a professional civil or structural engineer; (b) any act of boring, dredging, jacking, levelling, piling or tunnelling on or under any premises or street by any mechanical means; or (c) the driving or sinking of any earth rod, casing or tube into the ground; 22

23 Section 79 - Cable detection work to be carried out before earthworks Applies to LV cables; Normal Situation Cable Detection Work Digging of Trial Holes Consultation with SPPG Earthworks Notification- NCD LCDW 2 1 Contractor TAL (SPPG) 1 1 SPPG s Contractor

24 Section 79 - Cable detection work to be carried out before earthworks Applies to LV cables; Emergency Situation In the interest of public and private safety Cable Detection Work Earthworks Notification LCDW Contractor 1 Quick scanning No need to engage LCDW 2 3 Notify TAL (SPPG) in writing within 7 days 24

25 Section 80 - Carrying out earthworks within vicinity of high voltage electricity cable Applies to HV cables ( voltage = to or > 6.6kV ) Cable Detection Work Trial Holes Earthworks NCD Notification NCE Notification Consultation with TAL Issue of Letter of Requirements LCDW 2 1 Contractor TAL (SPPG) 6 25

26 Sections 85(1) & 85(2) of the Electricity Act Section 85 Damage to Property of Electricity Licensee Section 85(1) applies to damage of LV and HV cables with wilful intent. Section 85(2) applies to damage of HV cables. (2) Notwithstanding subsection (1), any person who, in the course of carrying out any earthworks, damages or suffers to be damaged any high voltage electricity cable in the transmission network belonging to or under the management or control of an electricity licensee shall be guilty of an offence and shall be liable on conviction to a fine not exceeding $1 million or to imprisonment for a term not exceeding 5 years or to both. 26

27 Electricity Act (Chapter 89A) PENALTIES Section No. Maximum Fine Maximum Imprisonment Remarks 79 $10,000 1 year 80 $100,000 5 years 85(1) $10,000 3 years Doing earthworks near LV cables without first engaging LCDW to do cable detection work. When doing earthworks near HV cables, earthworks contractor fails to: i)purchase cable plan; ii)carry out cable detection; iii)submit NCE to SPPG; and iv)comply with SPPG s Letter of Requirements. Damaging a high or low voltage cable wilfully. 85(2) $1,000,000 5 years Damaging a high voltage cable. 27

28 Thank You