Lessons Learned from a 60 CIPP Storm Sewer Liner Installation. Robert Stolt, PE Christopher Beranek, PE

Size: px
Start display at page:

Download "Lessons Learned from a 60 CIPP Storm Sewer Liner Installation. Robert Stolt, PE Christopher Beranek, PE"

Transcription

1 Lessons Learned from a 60 CIPP Storm Sewer Liner Installation Robert Stolt, PE Christopher Beranek, PE

2 Presentation Outline 1. CIPP Project Scope 2. CIPP Liner Installation 3. Defects Identified 4. Warranty Repairs 5. Lessons Learned 6. Questions 2

3 Presentation Outline 1. CIPP Project Scope 2. CIPP Liner Installation 3. Defects Identified 4. Warranty Repairs 5. Lessons Learned 6. Questions 3

4 CIPP Project Scope: Norris Yard, Irondale, AL Page 4

5 CIPP Project Scope 60 x 63 RCP storm sewer: Multiple cracks and joint leaks (20+) allowing petroleum-impacted groundwater to seep into the pipe Clean pipe Plug upstream pipe Install bypass pumps, if required Grout soil behind pipe, if required Install a CIPP liner Cure CIPP liner Provide a 1-year liner warranty Page 5

6 CIPP Project Scope CIPP Liner: 1 thick composite material Glass fiber-reinforced felt material impregnated with resin Resin cured with heat Resin Options: Polyester Vinyl Ester Heat Curing Methods: Steam Hot Water Page 6

7 CIPP Project Scope CIPP Liner: 1 thick composite material Glass fiber-reinforced felt material impregnated with resin Resin cured with heat Resin Options: Polyester Vinyl Ester Heat Curing Methods: Steam Hot Water Page 7

8 CIPP Project Scope CIPP Liner: 1 thick composite material Glass fiber-reinforced felt material impregnated with resin Resin cured with heat Resin Options: Polyester Vinyl Ester Heat Curing Methods: Steam Hot Water Page 8

9 Presentation Outline 1. CIPP Project Scope 2. CIPP Liner Installation: 12/5/2013 (after extended dry period) 3. Defects Identified 4. Warranty Repairs 5. Lessons Learned 6. Questions 9

10 CIPP Liner Installation: Junction Chamber Page 10

11 CIPP Liner Installation: 60 x 63 RCP Prior to Installation Page 11

12 CIPP Liner Installation: 60 x 63 RCP Prior to Installation Page 12

13 CIPP Liner Installation: Inversion Frame Page 13

14 CIPP Liner Installation: CIPP & Refrigeration Tractor Trailer Page 14

15 CIPP Liner Installation: Steam Curing of Liner (12/5/2013) Page 15

16 CIPP Liner Installation: End of Cured Liner (12/10/2013) Page 16

17 CIPP Liner Installation: End of Cured Liner (12/27/2013) Page 17

18 Presentation Outline 1. CIPP Project Scope 2. CIPP Liner Installation 3. Defects Identified: 1/15/2014 (following 5-6 rain events after liner installation) 4. Warranty Repairs 5. Lessons Learned 6. Questions 18

19 Defects Identified: Raised Invert or Bubble (1/15/2014) Page 19

20 Defects Identified: Raised Invert or Bubble (1/15/2014) Page 20

21 Defects Identified: Comparison Before/After 12/27/2013 1/15/2014 Page 21

22 Defects Identified: CIPP Liner Inspection (6/6/2014) Page 22

23 Presentation Outline 1. CIPP Project Scope 2. CIPP Liner Installation 3. Defects Identified 4. Warranty Repairs: 1/23/2017 to 2/3/2017 (wet period with high groundwater levels) 5. Lessons Learned 6. Questions 23

24 Warranty Repairs Page 24

25 Warranty Repairs Removed raised top layer of CIPP liner (3/16 thick) with pneumatic tools from 4 o clock to 8 o clock from Junction Chamber to MH 306 Several major water leaks identified, approx. 50 gpm Drilled holes through CIPP liner and RCP into surrounding soil; injected approx. 65 gal. of expanding, hydrophilic, polyurethane foam grout to stop leaks Filled remaining holes with hydraulic cement Applied 100 mils of Raven 405 primer on repaired surfaces Applied mils of Raven 512 top coat Total liner repair thickness: 7/16-9/16 Page 25

26 Warranty Repairs Polyurethane Foam Grout Avanti AV-333 Injectaflex: Single component, mid-range viscosity, moisture activated polyurethane injection resin. Expands 400%- 600% Skimmer Pipe Raven Products 1.5 ft. deep oil baffle; 405 Primer: 100% solids, ultra high build epoxy coating 3.5 ft. gap below baffle 512 Top Coat: Polyurea protective coating, chemically resistant to petroleum products Page 26

27 Warranty Repairs: Removal of defective top layer of liner Improvements: Oil baffle replaced with a 4.25 ft. stainless steel plate Page 27

28 Warranty Repairs: Completed Liner Repair Improvements: Rotating skimmer pipe replaced with drum 2 hydraulically driven drum skimmers Page 28

29 Warranty Repairs: Completed MH 306 Repair Page 29

30 Presentation Outline 1. CIPP Project Scope 2. CIPP Liner Installation 3. Defects Identified 4. Warranty Repairs 5. Lessons Learned 6. Questions 30

31 Lessons Learned Critical Specification Items The project specification allowed the CIPP Liner Company to use their expertise of their product to select the following items: Type of Resin (specification identified diesel fuel and petroleum in groundwater) Resin Curing Method Installation Conditions These three items are believed to be the main reasons for the liner defects. Page 31

32 Lessons Learned Type of Resin: Polyester resin was chosen by the CIPP Liner Company. Polyester resin is not as compatible with petroleum products and diesel fuels as vinyl ester resin. The project specification stated groundwater was impacted by diesel fuel and oil. Require the CIPP Liner Company to provide vinyl ester resin for any installations where the liner will come into contact with petroleum products such as oils and diesel fuels. Page 32

33 Lessons Learned Resin Curing Method: The CIPP Liner Company decided to use steam to cure the liner resin as it is more cost effective. For large pipe diameters, steam may not provide a uniform heating source. Require the CIPP Liner Company to use hot water curing, as it provides a more uniform distribution of heat. Page 33

34 Lessons Learned Installation Conditions: The CIPP liner was installed after an extended dry period and no grouting was done before the liner was installed. Liner repairs were performed during a wet period with active leaks. The liner repair company was forced to stop leaks prior to actual liner repairs were made. Require the CIPP Liner Company to install the liner during a wet period and stop all active leaks prior to the liner installation. Page 34

35 Questions