1 Oconomowoc Area School District Facility Construction Update July 27, 2018

2 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior curbs and main entrance is complete and the stone has been laid and rolled for the new bus loop. Paving of the bus loop will begin next week, followed by final landscape work. Light poles and the new building sign have also been installed. Inside the new addition, final cleaning is nearly complete and the new kitchen equipment is being installed next week. Inside the existing building, drywall hanging is 95% complete and drywall finishing is scheduled to be completed this week. Painting of the new walls will begin by the end of the week along with new ceiling grid installation. First floor classroom with new opening & drywall Lower level maker-space Lower level hallway with new layout & drywall EXTERIOR AND FINISHING WORK ON THE NEW ADDITION, MAIN BUILDING INTERIOR RENOVATIONS July - August 2018 August 2018 CELEBRATION OF COMPLETION September 23, 2018 View time-lapse photos of the full construction progress at Ixonia Elementary by clicking here.

3 MEADOW VIEW ELEMENTARY SCHOOL It s been an exciting month at the site of the new Meadow View Elementary. Three of the walls for the new gym have been set and underground plumbing rough-in has also begun in the gym area. Masonry work will begin in this area next week as well. Wall footings for the Southwest section of the school are complete and footings for the Northwest section are 40% complete. The new Meadow View gym walls, as seen from the roof of the current Meadow View View time-lapse photos of the full construction progress at Meadow View Elementary by clicking here. BEGAN April 2018 FOOTINGS, FOUNDATION & EXTERIOR WALLS June August 2018 EXTERIOR STRUCTURE, ROOFING, INTERIOR WALLS, ELECTRICAL, PLUMBING, FIRE PROTECTION, CONCRETE, LANDSCAPING & FINISHING WORK August 2018 August 2019 August 2019

4 OCONOMOWOC HIGH SCHOOL: MAIN CAMPUS New ramp inside transportation lab space New openings between manufacturing classrooms DEMOLITION, PLUMBING IMPROVEMENTS, MASONRY WORK, ROOFTOP AIR UNIT REPLACEMENT June July 2018 NEW WINDOW & DOOR INSTALLATION, WALL FRAMING, DRYWALL, PAINTING, INTERIOR FINISHING July August 2018 August 2018 CELEBRATION OF COMPLETION September 30, 2018 Inside the transportation lab New window openings looking out to the back hallway The renovations inside OHS Main Campus are nearing the finishing stages. The classroom floors are being prepped for concrete polishing to begin and painting is set to start next week. Installation of the specialized electrical and HVAC equipment in underway and overhead door installation will begin next week.

5 OCONOMOWOC HIGH SCHOOL: EAST CAMPUS Science classroom cabinet installation Lower level instructional area painting Interior painting and casework installation has begun in the instructional spaces at OHS East Campus and floor finishing will begin next week. New skylights are installed and interior door installation is slated to begin in August. Exterior aluminum paneling installation is nearly complete and roofing repairs are 95% complete as well. Skylights above the bridge walkway DRYWALL & PAINTING COMPLETION, EXTERIOR PANEL INSTALLATION, FINAL PLUMBING & ELECTRICAL INSTALLATION, FINISHING WORK, FURNITURE & TECHNOLOGY INSTALLATION July-August 2018 August 2018 CELEBRATION OF COMPLETION September 30, 2018 First floor instructional area painted Underground electrical lines are being run along the new walking path between Main and East Campus. Stone will be laid along the path starting next week and paving is scheduled for mid-august.

6 OCONOMOWOC HIGH SCHOOL: FAB LAB In spring, the OASD School Board approved bids for the renovation of existing classroom space to create the new Ocon Fab Lab, an engineering, robotics, and fabrication classroom and lab space. The Ocon Fab Lab project is not part of the facility referendum projects and is instead being funded by the OASD. Construction work for the Fab Lab is happening this summer so that the new space can be ready for the school year, consistent with the facility referendum projects. The new Fab Lab is located at the top of the main staircase, near the Field House. It will feature large windows where students and staff can see the innovative work happening inside. All window openings for the new Fab Lab are cut & being finished Window openings from inside the new Fab Lab