HIDD HEIGHTS PROGRESS REPORT

Size: px
Start display at page:

Download "HIDD HEIGHTS PROGRESS REPORT"

Transcription

1 HIDD HEIGHTS PROGRESS REPORT About the Project: Project Developer Title of Project Project Reference Design & Supervision Consultant Interior Design Consultant Main Contractor Bin Faqeeh Real Estate Investment Company S.P.C. Hidd Heights BFHH/21/ /2019 Salah Alkooheji Dar Al Décor Al Jameel Construction SPC About Progress Report: Title of Document Progress Report of Hidd Heights Reporting Period January 1, 2019 to January 31, 2019 Authors & project role United Arab Construction Co. (UACC) Date February 14, 2019

2 DESCRIPTION PERCENTAGE (%) OF REMARKS COMPLETION SUB STRUCTURE 1. Excavation 100% Completed 2. Dewatering 100% Completed 3. Pile Cutting 100% Completed 4. Back Filling and Compaction for Pile Cap 100% Completed 5. Pile Cap 100% Completed 6. Tie Beam 100% Completed 7. Water Tank 100% Completed 8. Grade Slab 100% Completed 9. Septic Tank 100% Completed 10. Substation 99% In Progress SUPER STRUCTURE Ground Floor 1. Lift Core Wall 100% Completed 2. Column and Shear Wall 100% Completed 3. Ramp and Staircase 100% Completed 4. 1 st Floor Slab 100% Completed 1 st Floor 1. Lift Core Wall 100% Completed 2. Column and Shear Wall 100% Completed 3. Ramp and Staircase 100% Completed 4. 2 nd Floor Slab 100% Completed 2 nd Floor 1. Lift Core Wall 100% Completed 2. Column and Shear Wall 100% Completed 3. Ramp and Staircase 100% Completed 4. 3 rd Floor Slab 100% Completed 3 rd Floor 1. Lift Core Wall 100% Completed 2. Column and Shear Wall 100% Completed 3. Shear Wall 100% Completed 4. 4 th Floor Slab 100% Completed 4 th Floor to 11 th Floor - Column and Shear Wall 100% Completed - Lift Core Wall 100% Completed - 5 th to 12 th Floor Slab 100% Completed

3 12 th Floor - Column 100% Completed - Shear Wall 100% Completed - Lift Core Wall 100% Completed - Roof 100% Completed SUPERSTRUCTURE Block Work - Ground Floor 100% Completed - 1 st Floor to 2 nd Floor 100% Completed - Podium Floor 100% Completed - 1 st to 9 th Typical Floor 100% Completed - Roof 100% Completed Plastering Work - Ground Floor 100% Completed - 1 st Floor to 2 nd Floor 100% Completed - 1 st to 9 th Typical Floor 100% Completed - Podium Floor 100% Completed Painting Work Wall and Ceiling (1 st Primer & 1 st Coat Filler / 2 nd Coat Filler & 1 st Coat Paint) - 1 st Floor to 2 nd Floor 100% Completed - 1 st Typical Floor to 3 rd Typical Floor 100% Completed - 4 th Typical Floor to 9 th Typical floor 100% Completed Painting Work Wall and Ceiling (2 nd Coat Filler / 2 nd Coat Paint) - GF 80% In Progress - 1 st Floor 10% In Progress - 2 nd Floor, Stair 2 & Podium Floor 100% Completed - 1 st Typical to 8 th Typical (Flats) 100% Completed Gypsum Work - 1 st Typical Floor to 9 th Typical Floor (Living, Kitchen, Bedrooms & Toilets) 100% Completed - Podium Floor 100% Completed Wall Cladding - 1 st Typical Floor to 9 th Typical Floor 100% Completed - Ground to Podium Floor 100% Completed Lift Lobby Wall Cladding - 1 st to 9 th Typical Floor 100% Completed - Ground to Podium 100% Completed Floor Tile - 1 st Typical Floor to 9 th Typical Floor 100% Completed - Podium 100% Completed Wall Tile - 1 st to 9 th Typical Floor 100% Completed - Podium 100% Completed

4 Marble Work - GF to 9 th Typical Floor - Corridor 100% Completed WATERPROOFING Toilets - 1 st Typical Floor to 9 th Typical Floor 100% Completed Balcony - 1 st Typical Floor to 9 th Typical Floor - Corridor 100% Completed ROOF WATERPROOFING Roof PU Foam 100% Completed Geotextile covering 100% Completed Light Weight Screed 100% Completed Membrane 100% Completed Screed Concrete 80% In Progress Ground Floor Paving and Curbe Work - Parking in Ground Floor 100% Completed - Parking in Entrance Area 100% Completed Epoxy Floor in Super Structure - 1 st Parking 100% Completed - 2 nd Parking 100% Completed Parking Wheel Stopper & Corner Guard - 1 st and 2 nd Parking 60% In Progress

5 On-site photos: (Structural Elevation)

6 (Front Parking) (Podium Floor Arcade Room) (Podium Floor Game Room)

7 (Play Equipment at Podium Floor Kids Area)

8 (Wall Finishing at Podium Male Gym) (Floor Finishing at Podium Pool Deck Area) (Fixing of Chair at Podium Floor Theater) (Fixing of Corridor Doors at Typical Floors)