Tangerine Road Dove Mountain Boulevard to La Cañada Drive
|
|
- Laurence Stone
- 5 years ago
- Views:
Transcription
1 Tangerine Road Dove Mountain Boulevard to La Cañada Drive PUBLIC MEETING The Highlands at Dove Mountain November 19, 2015
2 PRESENTATION OUTLINE 1. Tangerine Road Corridor in Review Project Need Project Elements Timeline & Funding 2. Segment 1 Design (Dove Mountain to La Cañada) Proposed Improvements Project Design Status 3. Segment 1 Construction (Dove Mountain to La Cañada) Meet the CMAR Tangerine Corridor Constructors TCC Approach to Construction Anticipated Phasing/Sequencing
3 TANGERINE ROAD CORRIDOR I-10 to La Cañada Drive
4 TANGERINE CORRIDOR PROJECT NEED Why improve Tangerine Road? Roadway closes during flooding Some segments nearing capacity limited passing opportunities No pedestrian facilities Need to plan for future growth Photo from AZ Daily Star July 5, 2012
5 TANGERINE CORRIDOR PROJECT ELEMENTS Goal: Improved multi-modal mobility and safety Widening to 4 lanes from I-10 to La Cañada (10 mi) Landscaped median Multi-use lanes, sidewalks Drainage improvements (eliminate dips) Intersection Improvements
6 TANGERINE CORRIDOR PROJECT FUNDING 10 Miles - Traverses Marana, Oro Valley, and Pima County $74.2M budget RTA Funding allocated for $45.3M RTA $21.4 M Marana $6.5M Pima County $1M Oro Valley Additional RTA Linkages funding for wildlife crossings MARANA PIMA COUNTY ORO VALLEY
7 TANGERINE CORRIDOR - IMPLEMENTATION PLAN Prioritize segments based on: Traffic, Utilities, Permitting, Right-of-Way Construction split into 2 segments to match funding Segments 1a and 1b combined; will be constructed together Segment 2 to be designed and constructed in a later RTA period Current Phase SEGMENT 2 (5 MILES) SEGMENT 1B (2 MILES) SEGMENT 1A (3 MILES)
8 TANGERINE CORRIDOR PROJECT TIMELINE Work to date Public Meetings April 2011 March 2012 February 2013 January 2015 Access Management Workshop Technical Studies (Traffic, Drainage, Environmental, etc) Final Design Concept Completed February 2013 Retained a Construction Manager at Risk (CMAR) 90% Design Plans completed for Segment 1
9 SEGMENT 1 DESIGN Dove Mountain Blvd to La Cañada Drive
10 SEGMENT 1 PROPOSED IMPROVEMENTS Widening to 4 lanes from Dove Mountain Blvd to La Cañada Dr (5 mi) Landscaped median Multi-use path, bike lanes Drainage improvements Five wildlife crossings Signalized Intersections Dove Mountain Blvd Thornydale Road La Cholla Blvd Resurfacing of Thornydale Road in Marana Limits approximately 0.4 mi North and 1.0 mi South of Tangerine
11 SEGMENT 1 PROPOSED IMPROVEMENTS Dove Mountain Blvd to Camino de Mañana (1.5 mi) Desert Parkway design Uncurbed, limited access 50 mph speed limit Native Vegetation, water harvesting No impacts to structures
12 SEGMENT 1 PROPOSED IMPROVEMENTS Camino de Mañana to La Cañada Dr (3.5 mi) Arterial design - Curbed median (similar to section east of La Cañada) 45 mph speed limit No impacts to structures
13 SEGMENT 1 PROPOSED IMPROVEMENTS Key Changes since last Public Meeting (January 15) Added dedicated entrance to Tangerine Corridor Park (Marana)
14 SEGMENT 1 PROPOSED IMPROVEMENTS Key Changes since last Public Meeting (January 15) Changed Camino de Oeste from a signal to a HAWK (High-Intensity Activated Crosswalk).
15 SEGMENT 1 PROPOSED IMPROVEMENTS Key Changes since last Public Meeting (January 15) Shifted drainage channels farther from road/pathway Creates space for additional landscaping along pathway 60% Design Current Design
16 SEGMENT 1 PROJECT DESIGN STATUS 100% Plans complete in December Coordinating project design with utility companies Utility relocation designs currently being finalized Relocations to begin as soon as December Property Acquisition Status Arizona State Land right of entry expected by end of 2015 Continuing negotiations with private property owners Coordinating design and construction elements with Construction Manager at Risk (CMAR)
17 SEGMENT 1 PROJECT DESIGN STATUS Recap of CMAR Delivery Method: Quality Uses most qualified contractor, not lowest bidder Contractor brought in during design Design engineer, owner and contractor work together to improve constructability and reduce impacts Contractor can suggest cost and time savings construction methods Can allow early start of some construction activities CMAR for Tangerine Road: Tangerine Corridor Constructors (TCC) (a Granite, Borderland Joint Venture)
18 SEGMENT 1 CONSTRUCTION Dove Mountain Blvd to La Cañada Drive Tangerine Corridor Constructors
19 SEGMENT 1 CONSTRUCTION Meet Tangerine Corridor Constructors (TCC)
20 SEGMENT 1 CONSTRUCTION Our Projects you may be familiar with State Route 77 (Oracle Rd.) Tangerine Rd to Pinal County Line Twin Peaks Rd: Linda Vista Blvd to Tangerine Rd
21 SEGMENT 1 CONSTRUCTION Approach to Construction: Maintain two-way traffic along Tangerine Road Maintain access to all residents and businesses Maintain bicycle/pedestrian access Minimize speed reduction and temporary traffic control devises Methods to maintain traffic/access: Sequence construction to build ½ of new roadway, while traffic is maintained on the existing roadway Temporary Traffic Control (Pavement Markings, Vertical Panels, Barricades, Barriers) Temporary Lane Shifts Temporary Asphalt/Detours
22 SEGMENT 1 CONSTRUCTION TYPICAL DRAINAGE SEQUENCE
23 SEGMENT 1 CONSTRUCTION PHASE ONE Work Sequence Detour Paving EB Drainage (Outlet) Barrier Dividing Traffic and Work Area
24 SEGMENT 1 CONSTRUCTION PHASE TWO Work Sequence Fill/Pave Over EB Drainage Detour Paving Removed WB Drainage Installed
25 SEGMENT 1 CONSTRUCTION PHASE THREE Work Sequence Fill/Pave WB Lanes Remove Temp EB Drainage Paving Flip Traffic to Design WB Lanes
26 SEGMENT 1 CONSTRUCTION PHASE FOUR Work Sequence Fill/Pave EB Lanes Striping For Design Traffic Open Traffic to All Lanes
27 SEGMENT 1 CONSTRUCTION TYPICAL INTERSECTION SEQUENCE
28 SEGMENT 1 CONSTRUCTION PHASE ONE SE Quadrant
29 SEGMENT 1 CONSTRUCTION PHASE TWO SE Quadrant
30 SEGMENT 1 CONSTRUCTION PHASE THREE SE Quadrant
31 SEGMENT 1 CONSTRUCTION PHASE FOUR SE Quadrant
32 SEGMENT 1 CONSTRUCTION Anticipated Construction Phasing/Sequencing: Dependent on utility relocations and right-of-way acquisitions Construct outlet side of new drainage structures first Construct new intersections in quadrants early in project New Westbound Tangerine Rd (Dove Mountain to Thornydale) New Eastbound Tangerine Rd (Dove Mountain to Thornydale) New Westbound Tangerine Rd (Thornydale to La Cañada) New Eastbound Tangerine Rd (Thornydale to La Cañada)
33 PUBLIC PARTICIPATION Comment forms available Sign up for updates and provide comments at:
34 PUBLIC PARTICIPATION Thank you for coming! Please visit the exhibits and provide input