1 Purple Line Extension Construction Community Meeting January 19,

2 Agenda Project Construction Updates: Western, La Brea, Fairfax and La Cienega La Brea Station Street Configuration Update Fairfax Decking: Phase I,II, III, Detours, Outreach and Communication La Cienega K-Rail and Pile Installation Eat Shop Play Wilshire Business Interruption Fund Questions & Answers 2

3 Purple Line Extension Project Alignment 3

4 Sections 2 and 3 Status *Subject to change. The PLE project team is working to deliver the project consistent with Measure M Under Construction Forecasted Schedule Section 1 Section 2 Section 3 Length 3.92 Miles 2.59 Miles 2.48 Miles New Stations Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital Pre-Construction Activities Current * Construction * * Operations * 2035* 4

5 PLE Section 1 Alignment 5

6 Purple Line Maintenance Facility 590 S Santa Fe Avenue Located in the Arts District, near 6 th St Bridge Initial excavation and grading ongoing Sanitary sewer and storm drain relocation continues until mid- to late February Design of Building 61S continues Artists selected Design Advisory Group Advisory group composed of Arts District leaders and artists to review and provide input on building s exterior design Next Meeting: March 2017 Backfilling fire hydrant connection trench at Santa Fe Av and Palmetto St (Below) Preparing to install fire hydrant 6

7 Tie-in at Wilshire/Western Station Western Staging Yard Northeast corner of Wilshire Bl and Manhattan Pl one block west of Western Av Soundwall construction substantially completed Remaining work includes gate installation, artwork on walls and widening of driveways Western Yard used intermittently for storage Upcoming Work Jet grouting anticipated to begin February 2017 along: Wilshire Bl between Bronson Av and Wilton Pl Wilshire Bl between Bronson Av and Wilton Pl Wilshire Bl between St. Andrews Pl and Western Requires installation of k-rail (concrete barriers) and lane reductions Median removal date TBD Western Staging Yard 7

8 Crenshaw Yard Staging Site Wilshire/Crenshaw Used throughout Section 1 design-build construction Mitigation efforts and maintenance: Banners replaced with durable vinyl Lorraine Gate temporarily closed until further notice Maintenance inside and outside of yard includes graffiti removal Used for storage of materials New banners on east side of Crenshaw Yard New banner on north side sound wall 8

9 Wilshire/La Brea Station Rendering shows length of the Wilshire/La Brea underground station box on Wilshire Bl from Orange Dr to Detroit St 9

10 Wilshire/La Brea Schedule *As of January 2017, subject to change Activity Name Q2Q3Q4Q1Q2Q3Q4Q1 Q2 Q3 Q4Q1Q2Q3 Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4 ADVANCED UTILITY RELOCATION PILING DECKING STATION EXCAVATION STATION CONSTRUCTION TUNNELING TESTING REVENUE SERVICE 10

11 La Brea Station La Brea Staging Yards Staging Yard Activities and Equipment Yard usage: 7am-11pm, (11pm-7am as needed) Sound wall is ft high Maintenance of equipment Deliveries of materials Removal of excavated soil Mitigations Must comply with City of Los Angeles noise requirements Noise Control Signage Low Impact Back up alarms Acoustical Insulation Metro 5 Step Noise Plan La Brea station, west of Sycamore Av, looking east Installing dewatering system, La Brea North Shaft 12

12 Wilshire/La Brea Work Zone Traffic Control *Dates subject to change This work zone advances the following: Wilshire/La Brea station excavation Utility hanging from the deck Dewatering system installation Maintenance of geotechnical instruments and dewatering wells Restoration of street and sidewalk In place through February 2017 * Work to support excavation from closure on Wilsire Bl in progress 13

13 Deck Openings What: Deck openings are openings of the street-deck for the purpose of delivering materials for underground construction. Deck openings will be done at locations of the deck that are designed to open and close. Deck openings will occur periodically, as needed Deck panels are 8 ft by 14 ft When: Following La Brea decking, late 2016 Throughout the duration of the project How: Off-peak hours (Mon. Fri., 9am-3:30pm, 7pm-6am) and Sat. and Sun. Traffic reduced to one lane each direction Example of a deck opening from underneath the deck 14

14 Wilshire/La Brea Station Center Opening Construction Concept What Establish a material handling shaft in the Wilshire Bl center median between Sycamore Av and Orange Dr, just east of La Brea Av in lieu of multiple intermittent closures and panel openings during excavation Wilshire Bl remains two lanes in each direction between La Brea Av and Mansfield Av Left turns open on Wilshire Bl at La Brea Av and Detroit St in both directions Center opening will resemble jet grouting enclosure When Proposed dates February 2017 thru December 2017 How The work zone would be established using k-rail, fencing and sound blankets Cross-section of center opening being used for excavation 14 14

15 Wilshire/La Brea Station Center Opening Construction Concept Proposed Benefits Handling material in and out of the 1,000 ft station during construction Safest method to accomplish work under deck Limits lane reductions for deck openings, leaving a more consistent traffic pattern More robust noise mitigation for this method rather than for lane closures Assists traffic flow of hauling and decentralizes hauling from the La Brea staging yards; places more truck traffic on Wilshire Bl Expedites station excavation and concrete work Center opening work zone on Wilshire Bl between Sycamore Av and Mansfield Av, Wilshire Bl two lanes in each direction 15

16 Wilshire/La Brea Station Excavation Now through the Fall of 2017 Work hours are 7am-11pm, 11pm-7am as needed Excavation will occur under the concrete deck, with intrinsically safe equipment certified by the State of California Inspector examining welds on power duct hangers 16

17 Jet Grouting Overview Jet grouting is a construction process that uses highpressure air and grout to create a deep soil-concrete block Jet grouting reinforces and strengthens the soil with concrete to support tunneling and cross-passage construction Locations Jet grouting will occur at 16 cross passage locations along Wilshire Bl between La Cienega Bl and Western Av There will be no more than three jet-grouting operations performed at one time (this can make traffic control simpler and safer), in consultation with LADOT Jet grouting requires approximately 8 to 12 weeks at each location, due to traffic control and installation of geotechnical instrumentation for future tunneling Work hours Mon. thru Fri. 7am-9pm, Sat. and Sun. 8am- 6pm Workers pothole to find utilities before jet grouting at Wilshire Bl near Windsor Bl, and workers move k-rail near Windsor Bl 17 17

18 Jet Grouting *Dates and work activities subject to change Schedule Location Wilshire Bl between Rossmore Av and Lucerne Bl Wilshire Bl between Arden Bl and Muirfield Rd Wilshire Bl between Plymouth Bl and Windsor Bl Status In process In process In process Wilshire Bl between Norton Av and Wilton Pl Anticipated February 2017 Wilshire Bl between Gramercy Pl and St. Andrews Pl Anticipated February 2017 *Construction notices will be sent and outreach will be conducted for each location 18 18

19 Jet Grouting Activities and Layout Work Activities Potholing, street level excavation, vertical drilling, trucking, cement silos, pumps, generators Layout Concrete barriers placed on the middle lanes of Wilshire Bl Lanes reduced to two lanes each direction at jet grouting locations Bus stops will be temporarily relocated as required Wilshire BRT lane not enforced in these areas during jet grouting Intermittent material deliveries during off peak hours 19

20 Scientists Find Mastodon Fossil Found at Future La Brea Station Workers discovered what appears to be mastodon or mammoth tusks and teeth on before Thanksgiving 2016 Cogstone paleontologists were onsite (they monitor all excavation) to identify and preserve fossils revealed by construction Cogstone identified a three-foot section of tusk and tooth fragments 15 feet below the surface After Thanksgiving, a partial skull with tusks of a possibly much younger mammoth or mastodon was discovered Other fossils may be found at other stations Paleontologists reveal the tusk and tooth fragments of an ancient ancestor of the modern elephant 20 20

21 Wilshire/Fairfax Station Rendering shows length of the Wilshire/Fairfax underground station box on Wilshire Bl from west of Fairfax Av to just west of Ogden Dr 21

22 Purple Line Extension Wilshire/Fairfax Station Schedule *As of January 2017, subject to change Activity Name Q2Q3Q4Q1Q2Q3Q4Q1 Q2 Q3 Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4 ADVANCED UTILITY RELOCATION PILING DECKING STATION EXCAVATION STATION CONSTRUCTION TUNNELING TESTING REVENUE SERVICE 22

23 Activities & Safety Measures/Mitigations Ogden Staging Yard Grading the surface in Ogden yard Mitigation signage in the Ogden yard Getting ready to drill in front of the Ogden Yard 23

24 Wilshire/Fairfax Station Pile Installation Overview Pile installation includes: Rig to construct 95 ft (L) deep Crane lifting 95 ft (L), 24 Inch H-piles into holes Approximately 460 piles Drilling, pile installation and backfilled concrete completed same day Piling started in August 2016 on the north side of Wilshire and switched to the south side in November 2016 Operation anticipated to take approximately 4-6 months on each side of the street Typical work hours 7am-11pm with potential nighttime work hours from 11pm-7am Wilshire is reduced to two lanes in each direction with left turn restrictions in the area. Directional closures on Fairfax Av and Wilshire Bl will take place on weekends PHOTO Piling on south side of Wilshire Bl 24

25 Station Decking 25

26 Wilshire/Fairfax Station Decking Overview Decking On Wilshire Bl, between Ogden Dr and the 99 Cents Store Construction of a concrete deck, curb to curb Sidewalks be maintained, or pedestrian detours created. Decking will serve as the temporary street surface. Traffic will travel on the installed deck panels while the station is constructed underground Fairfax Station: Approximately 800 ft long Approximately 70 ft wide Approximately 60 ft deep Will follow pile operations; anticipated to begin February 2017 Additional activities under decking closures: piling, temporary civil improvements. Will work closely with First Responders to ensure emergency access 26 26

27 Wilshire/Fairfax Station Decking Schedule February 2017 through Spring 2017 Approximately 18 weekend closures, scheduled in three phases beginning east and moving west on Wilshire Blvd Phase 1: Ogden-Fairfax 10 weekends Phase 2: Wilshire/Fairfax intersection 4 weekends Phase 3: West of Fairfax 4 weekends *Dates and work activities subject to change Friday 8pm: Full closure of Wilshire or Wilshire at Fairfax intersection (Phase 2) Monday 6am: streets open Work occurs continuously throughout weekend Working with City of Los Angeles to implement early lane reductions on Fridays 10am (similar to La Brea). Wilshire Bl will reduce to one lane each direction to allow for the loudest work (breaking of concrete) to be completed during day time hours. 27

28 Wilshire/Fairfax Station Decking Traffic Action Plan This work requires close coordination and approval from City agencies Board of Public Works approval anticipated in January 20, 2017 Traffic Action Plan: Detour routes Proposed Mitigations Signage Signal timing adjustment Traffic Control Officer locations Maintains local access Bus Detours *Dates and work activities subject to change 28

29 Phase 1 Traffic Detour 10 Weekends Wilshire Bl, Ogden Dr Fairfax Av Closure DRAFT Westbound: Northbound La Brea Av to westbound 6th St to southbound Fairfax Av to westbound Wilshire Bl Eastbound: Northbound Fairfax Av to Eastbound 6th St to southbound La Brea Av to Eastbound Wilshire Bl Local access on Wilshire Bl for business and residents will be maintained Lane reductions on Wilshire Bl going eastbound will start: Wilshire Bl/Crescent Heights Bl Lane reductions on Wilshire going westbound will start: Wilshire Bl/Orange Dr Essentials Wilshire Bl reduced to one lane in each direction from Spaulding Av to Fairfax Av on Fridays from 10am-8pm Full closure of Wilshire Bl, from Spaulding Av to Fairfax Av starting at 8pm on Fridays until Mondays at 6am Lane reductions on Fairfax Av for west end work Anticipated duration: 10 weekends 29

30 Phase 2 Traffic Detour 4 Weekends Wilshire Bl/Fairfax Av Intersection DRAFT Westbound: Westbound Wilshire Bl to southbound La Brea Av to westbound Olympic Bl to northbound San Vicente Bl to westbound Wilshire Bl Eastbound: Eastbound Wilshire Bl to southbound La Cienega Bl to eastbound Olympic Bl northbound La Brea Av to eastbound Wilshire Bl Local access on Wilshire Bl for business and residents will be maintained Lane reductions on Wilshire Bl going eastbound will start: Wilshire Bl/Hamilton Dr Hard closure at San Vicente Bl Lane reductions on Wilshire going westbound will start: Wilshire Bl/Orange Dr Essentials Early start lane reductions on Wilshire Bland Fairfax starting on Fridays from 10am until 8pm Full closure of Fairfax Ave. starting at 8pm on Fridays until Monday at 6am Full closure of Wilshire Blvd. starting at 8pm on Fridays until Monday at 6am Anticipated duration: 4 weekends 30

31 Phase 2 Fairfax Av Traffic Detour Fairfax Av/Wilshire Bl Intersection Closure DRAFT Southbound: Southbound Fairfax Av to eastbound 6 th St to southbound La Brea Av to westbound Olympic Bl to southbound Fairfax Av Northbound: Northbound Fairfax Av to eastbound Olympic Bl to northbound La Brea Av to westbound 6 th St St to northbound Fairfax Av Lane reductions on Fairfax Av going northbound will start: Wilshire Bl/Whitworth Dr Lane reductions on Wilshire Bl going southbound will start: Wilshire Bl/Maryland Dr Local access on Fairfax Av for business and residents will be maintained Essentials Early start lane reductions on Wilshire Bl and Fairfax Av starting on Fridays from 10am until 8pm Full closure of Fairfax Av starting at 8pm on Fridays until Monday at 6am Full closure of Wilshire Bl starting at 8pm on Fridays until Monday at 6am Anticipated duration: 4 weekends 31

32 Phase 3 Traffic Detour 4 Weekends Wilshire Bl, West of Fairfax Av DRAFT Westbound: Southbound Fairfax Av to westbound San Vicente Bl to westbound Wilshire Bl Eastbound: Eastbound Wilshire Bl Southbound La Cienega Bl to eastbound Olympic Bl to northbound La Brea Av to eastbound Wilshire Bl Local access on Wilshire Bl for business and residents will be maintained Lane reductions on Wilshire Bl going eastbound will start: Wilshire Bl/Hamilton Dr Hard closure at San Vicente Bl Lane reductions on Wilshire going westbound will start: Wilshire Bl/Orange Dr Essentials Wilshire Bl from Fairfax Av to Crescent Heights Bl reduced to one lane in each direction on Fridays from 10am until 8pm Full closure of Wilshire Bl from 8pm on Fridays until 6am on Mondays Working with City of Los Angeles to address access to buildings between Crescent Heights Bl and Fairfax Av (zone shown in yellow), work zone shown in purple Lane reductions on Fairfax Av to support work on the east end of the closure Anticipated Duration: 4 weekends 32

33 Bus Detours Wilshire and Fairfax Phase I/II: 720/20, 217, LADOT Dash, Antelope Valley Transit Eastbound/Westbound Wilshire Buses will be temporarily suspended between Fairfax Av and La Brea Bl LADOT Dash Bus detours between La Brea Bl and Hauser will be publicized by Dash to their riders Metro will also share the information when received or updated Antelope Valley Transit Authority (AVT) buses will also be temporarily suspended on Wilshire. AVTA will inform their riders of weekend detours Metro will also share the information when received or updated LADOT Dash and AVT Bus Detours will be coordinated with Metro bus operations Detoured Metro local buses will stop at all existing bus stops along the detour route 33

34 Wilshire/Fairfax Station Decking Community Outreach Robust Marketing Campaign Social Media: Facebook, Twitter, Nextdoor Advertising: print, radio, online Media Coverage: press release Business and resident outreach Meetings with local groups, leaders Elected Official Briefings Safety Presentations School Presentations Community Partnerships 34

35 Wilshire/La Cienega Station Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr 35

36 Purple Line Extension Wilshire/La Cienega Schedule *As of January 2017, subject to change Activity Name Q2Q3Q4Q1Q2Q3Q4Q1 Q2 Q3 Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4 ADVANCED UTILITY RELOCATION PILING DECKING STATION EXCAVATION STATION CONSTRUCTION TUNNELING TESTING REVENUE SERVICE 36

37 Advance Utility Relocation (AUR) Major work completed: Fiber, water, sewer, gas, power Utilities: self-performing cable pulling anticipated completion February 2017 Remaining AUR work at Wilshire Bl/La Cienega Bl 37

38 Wilshire/La Cienega Station Gale and La Cienega Staging Yards Photos of preperation work for sound walls in the Wilshire/Gale and La Cienega staging yards Current state of the La Cienega Staging Yard - next step, soundwalls 38

39 Upcoming Work Wilshire/ La Cienega January-February 2017 Instrumentation installation on Wilshire Bl, La Cienega Bl and adjacent streets to start in January 2017 Median removal at Wilshire Bl/San Vicente Bl to occur January/February 2017 Tree removal will take place as needed between La Cienega Bl and Tower Dr K-rail installation and traffic control changes to occur in February 2017 Earliest, February 4 th 2017 Pre-pile activities and instrumentation will be ongoing behind k-rail and throughout the station area Future work Q1 of 2017 pending City of Beverly Hills Approval Piling on the south side of Wilshire Bl Jet grouting at east and west ends of the station Details for all work will be communicated. in construction notices and through outreach to affected businesses, residents and stakeholders 39

40 Upcoming Work Wilshire/La Cienega K-Rail and Traffic Control Installation at Wilshire Bl/La Cienega Bl February 2017 Establish a work zone using k-rail (concrete barriers), fencing, sound blankets to support piling activities K-rail will be installed over one weekend under lane reductions Earliest date is Feb 4, 2017 Work zone will support pre-piling, geotechnical instrumentation and jet grouting Work hours for weekend implementation are under review with City of Beverly Hills Approximate location of south side pile work zones at Wilshire Bl/La Cienega Bl 40

41 Upcoming Work, Pending Approval Wilshire/La Cienega Pile installation, south side of Wilshire between La Cienega Av and Tower Dr Approximately 470 piles total to be installed approx. 166 piles on the south side Work zone delineated by k-rail Station is approximately: 990 ft long 70 ft wide 60 ft deep Piling is projected to start Q pending City of Beverly Hills approval Work hours: 7am-8pm; drilling and setting of piles; 8pm-10pm; breakdown, cleanup, non-drill activities. Cross-section showing work zone and drill rig for pile installation. 41

42 Upcoming Work, Pending Approval Wilshire/La Cienega Jet Grouting, Wilshire/La Cienega Jet grouting is soil reinforcement using a drill rig to support station excavation and tunneling. Additional equipment include generators, pumps and a grout silo Jet grouting will occur within the south side k-rail work zone. Additional jet grouting will happen under lane reductions outside of work zone Anticipated to start in March of 2017 Work hours: 7am-8pm; drilling 8pm-10pm; breakdown, cleanup, non-drill activities. Lane closures will follow permitted hours Pending City of Beverly Hills approval Typical jet grouting operation in middle of Wilshire Bl 42

43 Go Metro Birch and Bone is located at 6130 Wilshire Blvd, Los Angeles CA Find your best route with Trip Planner: socaltransport.org Offering unique floral & botanical designs for your home and special events Business Information Phone: Website: BirchandBone.com 43

44 Winter Promo Campaign Monthly newsletter with business spotlights. 44

45 Lunch Meet-Up with Book My-Lot Food Trucks/Miracle Mile February 7, :30am 1pm 5800 Block of Wilshire Blvd, Los Angeles, CA

46

47 BIF Grant Award Update > Purple Line Extension, Phase 1 > BIF Applications Submitted: 86 > BIF Applications Awarded: 66 > BIF Grant Amount Awarded: $1,303, *11 applications pending completion *9 applicants have been deemed ineligible > Noteworthy Updates: > Of the 40 grantees, 17 have received two or more grants > Average amount per grant: $19,

48 Metro Business Interruption Fund Financial assistance to small mom & pop businesses impacted by Metro transit rail construction along three project areas: Purple Line Extension, Phase 1 Crenshaw/LAX Transit Project Regional Connector, Little Tokyo area & 2nd/Broadway segment Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements Grant amount determined by demonstrated loss of business revenue directly related to the period of construction disruption Maximum annual grant amount per business is $50,000 48

49 BIF Outreach Update > BIF Workshops - Winter 2017 Series Tuesday, January 24, :30am 10:00am La Cienega Park Community Center 8400 Gregory Way Beverly Hills, CA Wednesday, February 22, :00pm 3:30pm Purple Line Extension Office, 4 th Fl Wilshire Blvd. Los Angeles, CA > BIF Business Advisor for PLE > Brian Lazo, PCR at , ext. 240 > Direct outreach to business owners 49

50 Next Meeting Section 1 Construction Community Meeting Thursday, March 16, pm-8pm Location TBD 50