HIDD HEIGHTS PROGRESS REPORT

Size: px
Start display at page:

Download "HIDD HEIGHTS PROGRESS REPORT"

Transcription

1 HIDD HEIGHTS PROGRESS REPORT About the Project: Project Developer Title of Project Project Reference Design & Supervision Consultant Interior Design Consultant Main Contractor Bin Faqeeh Real Estate Investment Company S.P.C. Hidd Heights BFHH/20/ /2018 Salah Alkooheji Dar Al Décor Al Jameel Construction SPC About Progress Report: Title of Document Progress Report of Hidd Heights Reporting Period September 1, 2018 to September 30, 2018 Authors & project role United Arab Construction Co. (UACC) Date October 7, 2018

2 DESCRIPTION PERCENTAGE (%) OF REMARKS COMPLETION SUB STRUCTURE 1. Excavation 100% Completed 2. Dewatering 100% Completed 3. Pile Cutting 100% Completed 4. Back Filling and Compaction for Pile Cap 100% Completed 5. Pile Cap 100% Completed 6. Tie Beam 100% Completed 7. Water Tank 100% Completed 8. Grade Slab 100% Completed 9. Septic Tank 100% Completed 10. Substation 99% In Progress SUPER STRUCTURE Ground Floor 3. Ramp and Staircase 100% Completed 4. 1 st Floor Slab 100% Completed 1 st Floor 3. Ramp and Staircase 100% Completed 4. 2 nd Floor Slab 100% Completed 2 nd Floor 3. Ramp and Staircase 100% Completed 4. 3 rd Floor Slab 100% Completed 3 rd Floor 3. Shear Wall 100% Completed 4. 4 th Floor Slab 100% Completed 4 th Floor to 11 th Floor - Column and Shear Wall 100% Completed - Lift Core Wall 100% Completed - 5 th to 12 th Floor Slab 100% Completed

3 12 th Floor - Column 100% Completed - Shear Wall 100% Completed - Lift Core Wall 100% Completed - Roof 100% Completed SUPERSTRUCTURE Block Work - Ground Floor 100% Completed - 1 st Floor to 2 nd Floor 100% Completed - Podium Floor 100% Completed - 1 st to 9 th Typical Floor 99% In Progress - Roof 100% Completed Plastering Work - Ground Floor 100% Completed - 1 st Floor to 2 nd Floor 100% Completed - 1 st to 5 th Typical Floor 99% In Progress - 6 th Typical Floor 99% In Progress - 7 th Typical Floor 99% In Progress - 8 th to 9 th Typical Floor 99% In Progress - Podium Floor 99% In Progress Painting Work Wall and Ceiling - 1 st Floor to 2 nd Floor 99% In Progress - 1 st Typical Floor to 3 rd Typical Floor 100% Completed - 4 th Typical Floor to 9 th Typical floor 98% In Progress Gypsum Work - 1 st Typical Floor to 9 th Typical Floor (Living and Bedrooms) 100% Completed - Podium Floor 85% In Progress Wall Tile Work - 1 st Typical Floor to 7 th Typical Floor 100% Completed - 8 th Typical Floor to 9 th Typical Floor 98% In Progress Lift Lobby Wall Cladding - 1 st to 9 th Typical Floor 100% Completed - Ground to Podium 95% In Progress Floor Tile - 1 st Typical Floor to 9 th Typical Floor 100% Completed Wall Tile - 1 st to 7 th Typical Floor 100% Completed - 8 th Typical Floor 98% In Progress - 9 th Typical Floor 100% Completed

4 Marble Work - GF to 9 th Typical Floor - Corridor 100% Completed WATERPROOFING Toilets - 1 st Typical Floor to 9 th Typical Floor 100% Completed Balcony - 1 st Typical Floor to 9 th Typical Floor - Corridor 100% Completed ROOF WATERPROOFING Roof PU Foam 100% Completed Geotextile covering 100% Completed Light Weight Screed 100% Completed Membrane 100% Completed Screed Concrete 80% In Progress On-site photos: (Structural Elevation)

5 (Structural Elevation) (GF Paving compaction)

6 (Corridor Ceiling Painting at Floor) (Male Gym Screed Concrete) (Swimming pool Tile works) (Pool deck area Lightweight concrete)

7 (Corridor Ceiling Painting at Floor) (2 nd Parking Epoxy preparation work)