Structural Breadth Study

Size: px
Start display at page:

Download "Structural Breadth Study"

Transcription

1 Structural Breadth Study Connection Redesign

2 Structural Breadth Study Connection Redesign Existing EIFS Connection The expansion project is a steel frame structure with concrete slab on deck. There is a total of 2200 tons of steel to be erected on the building over a scheduled duration of 22 weeks. A tower crane was placed in the center of the building, inside the main atrium. This was the most logical location for the crane, as it is mostly open space. The budgeted amount for the steel contract is $6.03 million. One important aspect that had to be considered by the designer was how the Exterior Insulation Finish System (EIFS) was going to be attached to the structure of the building. EIFS is used for most of the exterior finish of the hospital. The majority of the EIFS panels are being installed in 27 or 28 sections. The panels are attached to 6 steel studs with mechanical fasteners. Figure 5 below shows a detail of the attachment of the EIFS panels to the structure of the building. The existing detail contains two sets of double channels connected to two 5/16 plates. These plates are bolted to the double channels with a total of six bolts and welded to the W14 beam and the tube steel. The entire assembly was created onsite by the steel erectors. Figure 5: Existing Connection Design There are several disadvantages to constructing this detail. The two sets of double channels are excessive and more difficult to install; two pieces take longer to erect than one. The two 5/16 plates must be welded on the top and the bottom of the channels, which takes a lot of time. The connection is located below the 25 of 97

3 concrete floor and must be accessed from the floor underneath. This would require ladders or lifts, which are inconvenient for the erectors and welders. This connection is inefficient in terms of erection time and labor costs. The connection typically occurs every 27 around the perimeter of the building on several floors. There are 200 occurrences of this detail. The steel erection of the building took 22 weeks to complete, per contract. However, an additional 16 weeks of work was required to complete miscellaneous steel bolt up, welding, and bracing. Proposed EIFS Connection In order to improve the efficiency of the steel erection process, an alternative to this detail will be examined. The proposed design aims to reduce erection time by reducing the number of pieces and the amount of welding. A detail of the proposed connection design is shown in figure 6. The main difference between the existing detail and the proposed detail is the number of pieces in the connection. While the existing included 6 pieces to be installed between the W shape and the tube steel, the proposed design only requires 4. This makes a significant difference in terms of erection time, given that there are 200 of these connections. Another significant difference between the designs is the connections of the pieces. The proposed detail requires less welding than the original and fewer field installed bolts. Normally, fastening bolts takes less time than welding these pieces together. Figure 6: Proposed Connection Design In addition to reducing the number of members, the proposed design will have Angle A, Angle B, and the 5/16 plate prefabricated in the shop prior to delivery. Prefabricating these pieces will significantly reduce the erection time of this process. It will also save money in labor costs for welders and steel erectors. There will be an additional cost for prefabrication and delivery, as they will be more difficult to deliver prefabricated pieces than the individual pieces. 26 of 97

4 The alternative design allows for the same amount of adjustment available in the original. In fact, the connection would be easier to adjust, as there are fewer pieces and fewer connections. The dimensions of the pieces do not change from one design to the other; the only aspect that has changed is the shapes of the pieces. There is no reduction in the structural integrity of the connection. The design calls for ASTM A 325 bolts. The bolts are to be used to hold the pieces in place and to allow for any adjustments to be made. Once the prefabricated pieces are in place, the pieces would be welded in their final position. Below is a comparison of the connections. Full images of the connection can be found in Appendix D. Analysis Results Figure 7: Existing and Proposed Steel Connection A cost analysis was performed to determine the advantages of the proposed design. The majority of the cost savings are in labor, as the proposed design takes much less time to erect. A total of $566 was saved off the budget, along with 6 days on the duration of this activity. The results of the analysis are in figure 8, below. A more detailed analysis can be found in Appendices E and F. 27 of 97

5 Cost Labor + Material + Delivery + Prefab Existing: $5,130 + $8,558 + $389 + N/A = $14,077 Proposed: $1,710 + $7,591 + $1,035 + $3,174 = $13,511 Schedule Cost Savings: $566 Existing: Proposed: 9 days 3 days Schedule Savings: Figure 8: Summary of Proposed Design Savings 6 days The proposed change does not yield significant cost savings. While the erection labor cost was reduced, the added prefabrication costs negate any cost savings. The cost for material was cheaper in the proposed design because fewer pieces of steel were used. The delivery cost of the alternative design was greater than the existing condition, as the pieces would have to be shipped prefabricated, reducing the amount of steel each truck could hold. A value of $75/ton was used to calculate the delivery cost, as opposed to the existing $25/ton. The main benefit of this change is the reduction in the schedule by 6 days. The prefabrication of the pieces reduced the required labor time in the original design. The prefabrication time should not affect the erection time, as they are performed independently. Another example of saved time occurs during the physical installation. The original design would require a considerable amount of layout and coordination, as there are more pieces to be installed. The prefabricated unit would be easier to install and requires less preparatory work. Connection Redesign Conclusion The analysis of the alternative design shows a slight cost savings and a reduction of 6 days from the steel erection schedule. Given the design s restraints, it would be beneficial for the contractor to install this design as opposed to the original design. Assuming the prefabricator can deliver the pieces when needed, it would be beneficial for both the management team and the steel erector. 28 of 97

The building on 250 West Street is a 7-story multi-use that provides space for parking,

The building on 250 West Street is a 7-story multi-use that provides space for parking, December 5, 2002 Thesis Executive Summary The proposal for the investigation of the building on 250 West Street will include an in depth look at the floor and lateral systems. A continuation of the Pro-Con

More information

Kiski Area High School Allegheny Township, PA FLOOR SYSTEM ANALYSIS

Kiski Area High School Allegheny Township, PA FLOOR SYSTEM ANALYSIS FLOOR SYSTEM ANALYSIS Objective The objective of the following breadth study is to determine if an alternative floor system for Building N would be more advantageous than the existing floor system. The

More information

Pro-Con Structural Study of Alternate Floor Systems

Pro-Con Structural Study of Alternate Floor Systems Andrew Covely Structural Dr. Linda Hanagan The Helena New York City, NY October 27, 2004 Pictures courtesy of Fox & Fowle Architects Pro-Con Structural Study of Alternate Floor Systems Executive Summary

More information

Metal Fabricators. Phone DAKA (3252) Fax Serving the Construction Industry and Manufacturers Since 1977

Metal Fabricators. Phone DAKA (3252) Fax Serving the Construction Industry and Manufacturers Since 1977 Metal Fabricators Serving the Construction Industry and Manufacturers Since 1977 Structural Steel, Joists & Deck Miscellaneous & Ornamental Metals, Stairways & Railings OEM Fabrication / Custom Metal Work

More information

DIVISION 5 - STRUCTURAL STEEL AND IRON WORK

DIVISION 5 - STRUCTURAL STEEL AND IRON WORK DIVISION 5 - STRUCTURAL STEEL AND IRON WORK SECTION 05100 STRUCTURAL METAL FRAMING PART 1.00 GENERAL 1.01 SCOPE OF WORK A. Work Included: 1. 2. Structural steel complete in place. Steel joists complete

More information

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact Executive Summary:, located in Pigeon Forge, Tennessee, is designed as a multifunctional space and

More information

Abington Memorial Hospital

Abington Memorial Hospital Presentation Project Information Outline Steel Connection Redesign Mold in Exterior Insulation Finish Systems Green Healthcare Facilities Conclusion, Questions Building Information Building Size: 360,000

More information

SECTION FABRICATED ENGINEERED STRUCTURES. A. Pre-engineered, shop-fabricated structural steel building with formed purlin framing.

SECTION FABRICATED ENGINEERED STRUCTURES. A. Pre-engineered, shop-fabricated structural steel building with formed purlin framing. PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 13 34 00 FABRICATED ENGINEERED STRUCTURES A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1

More information

COURTYARD INFILL STRUCTURE DESIGN

COURTYARD INFILL STRUCTURE DESIGN COURTYARD INFILL STRUCTURE DESIGN Executive Summary The existing design for the courtyard within the G wing is for a cast-in-place concrete structure. The design being proposed within this analysis is

More information

MINIMIZATION OF EXPANSION ANCHORS FOR DESIGN SIMPLICITY AND CONSTRUCTABILITY

MINIMIZATION OF EXPANSION ANCHORS FOR DESIGN SIMPLICITY AND CONSTRUCTABILITY MINIMIZATION OF EXPANSION ANCHORS FOR DESIGN SIMPLICITY AND CONSTRUCTABILITY Daniel W. Golden Westinghouse Electric Company, Monroeville, PA ABSTRACT Westinghouse s next generation nuclear power plant

More information

K. ASTM F436- Standard Specification for Hardened Steel Washers; 2011.

K. ASTM F436- Standard Specification for Hardened Steel Washers; 2011. DIVISION 05 METALS 05 12 00 STRUCTURAL STEEL FRAMING PART 1 GENERAL 1.1 SECTION INCLUDES A. Structural steel framing members, support members. 1.2 RELATED REQUIREMENTS A. Section 05 50 00 - Metal Fabrications:

More information

JONES AIRWAY, LLC CLEVELAND REGIONAL JETPORT SECTION STRUCTURAL STEEL

JONES AIRWAY, LLC CLEVELAND REGIONAL JETPORT SECTION STRUCTURAL STEEL CLEVELAND REGIONAL JETPORT 05 1200-1 PART 1 - GENERAL SECTION 05 1200 STRUCTURAL STEEL 1.1 RELATED SPECIFICATION SECTIONS: A. Bolting of wood to steel, steel anchors for work of other trades, concrete

More information

Temecula Medical Center Temecula, CA

Temecula Medical Center Temecula, CA Temecula Medical Center Temecula, CA Technical Assignment #2 Sean F. Beville The Pennsylvania State University Architectural Engineering Structural Option Senior Thesis Project Student Advisor: Thomas

More information

DIVISION 5 METALS SECTION STRUCTURAL STEEL

DIVISION 5 METALS SECTION STRUCTURAL STEEL DIVISION 5 METALS SECTION 05 12 00 PART 1 GENERAL 1.01 SUMMARY A. Section Includes: All labor and materials required to furnish and install the structural steel shown on the Drawings and required by these

More information

ANALYSIS 2 PREFABRICATED FAÇADE

ANALYSIS 2 PREFABRICATED FAÇADE ANALYSIS 2 PREFABRICATED FAÇADE BACKGROUND The concept of building components to be assembled off site, and shipped onto the project ready for final placement is known as Prefabrication. This concept can

More information

1. Base plates, setting plates and anchor rods for columns. 8. Lintels if connected to structural steel columns.

1. Base plates, setting plates and anchor rods for columns. 8. Lintels if connected to structural steel columns. PAGE 051200-1 SECTION 051200 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,

More information

LIGHT-GAUGE PANELIZED WALL SYSTEMS. Michael Waggoner Mark Schroeder

LIGHT-GAUGE PANELIZED WALL SYSTEMS. Michael Waggoner Mark Schroeder LIGHT-GAUGE PANELIZED WALL SYSTEMS Michael Waggoner Mark Schroeder INTRODUCTION Development of Light-Gauge Panelized Wall Systems Selecting the Right Framing Systems Building Code Design Considerations

More information

Analysis 2 Pre-fabricated Metal Stud Crete Panels-Structural Breadth

Analysis 2 Pre-fabricated Metal Stud Crete Panels-Structural Breadth Analysis 2 Pre-fabricated -Structural Breadth Background The current façade design calls for stick built 3-5/8 masonry on a 7-5/8 metal stud back-up with exterior sheathing board, 1 cavity board insulation

More information

FDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider

FDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider Executive Summary: The FDA-CDRH Laboratory is currently being built on the Food and Drug Administration s White Oak Consolidation Campus. It is a four story building with a full below grade ground floor

More information

DIVISION 5 METALS COLD FORMED METAL FRAMING Structural Metal Stud Framing

DIVISION 5 METALS COLD FORMED METAL FRAMING Structural Metal Stud Framing 05 40 00 COLD FORMED METAL FRAMING 05 41 00 Structural Metal Stud Framing 05 50 00 METAL FABRICATIONS 05 51 00 Metal Stairs 05 51 13 Metal Pan Stairs 05 52 00 Metal Railings 05 52 13 Pipe and Tube Railings

More information

STEEL STRUCTURAL SYSTEMS

STEEL STRUCTURAL SYSTEMS STEEL STRUCTURAL SYSTEMS Steel elements are of two basic types: Structural steel shapes are formed into their final shapes by hot-rolling. This method produces such common elements as wide flange sections,

More information

HOW TO. ESTIMATE the COST CONTENTS O F S T R U C T U R A L S T E E L ROBERT R. BONENFANT, JR. - JULY RATIOS AND ANALYSIS Main CSI Division

HOW TO. ESTIMATE the COST CONTENTS O F S T R U C T U R A L S T E E L ROBERT R. BONENFANT, JR. - JULY RATIOS AND ANALYSIS Main CSI Division HOW TO ESTIMATE the COST O F S T R U C T U R A L S T E E L CONTENTS ROBERT R. BONENFANT, JR. - JULY 2008 1. INTRODUCTION 7. RATIOS AND ANALYSIS Main CSI Division 8. MISCELLANEOUS AND PERTINENT Specific

More information

Installing metal decking, curtain walls, window walls, siding systems, miscellaneous metals, ornamental iron, and similar materials; and

Installing metal decking, curtain walls, window walls, siding systems, miscellaneous metals, ornamental iron, and similar materials; and Steel Erection Plan for Construction Purpose Company Name must meet the requirements of OSHA's Steel Erection standard (29 CFR 1926, Subpart R). This Steel Erection Plan for Construction is our company's

More information

Guide for Inspecting Metal Building Systems. First Edition

Guide for Inspecting Metal Building Systems. First Edition Guide for Inspecting Metal Building Systems First Edition 1 st Edition Guide for Inspecting Metal Building Systems 1300 Sumner Avenue Cleveland, Ohio 44115 Copyright 2016 Metal Building Manufacturers Association,

More information

The Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee

The Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee The Structural Redesign of Boyds Bear Country and its Related Systems Included in this Presentation: Background and Existing System Proposal Problem / Solution Structural System Redesigns Pre-cast Concrete

More information

ITEM 442 METALS FOR STRUCTURES

ITEM 442 METALS FOR STRUCTURES AFTER NOVEMBER 1, 2008 ITEM 442 METALS FOR STRUCTURES 442.1 Description. These specifications shall govern for materials such as structural steel, wrought iron, bronze, and other metals used in structures,

More information

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan Executive Summary: 200 Minuteman Park currently stands as a three story commercial building. The original design was limited to three stories by an industrial zoning law in Andover, Massachusetts. If this

More information

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012)

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012) Gaines Charter Township 8555 Kalamazoo Ave SE Caledonia MI 49316 PH: 616 698-6640 Fax: 616 698-2490 www.gainestownship.org Building Department Statement of Special Inspections Michigan Building Code 2012

More information

1.02 SYSTEM DESCRIPTION

1.02 SYSTEM DESCRIPTION 1 OF 7 MODULAR MEZZANINES GUIDE SPECIFICATIONS FOR PART 1 - GENERAL 1.01 RELATED WORK A. SECTION 03 30 00: Cast in Place Concrete (and Concrete Finishing) 1. The area where mezzanine is installed shall

More information

Case Study of Mercy Health Partners St. Vincent Regional Heart Center. Copyright. Step 1: Design Team Formation

Case Study of Mercy Health Partners St. Vincent Regional Heart Center. Copyright. Step 1: Design Team Formation Maximizing the Impact of Constructability By David I. Ruby, P.E., S.E., SECB and Jay Ruby, P.E. T his article is the third in a series on Constructability. In the first two articles, Constructability was

More information

SECTION STRUCTURAL STEEL FRAMING

SECTION STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 DESCRIPTION SECTION 05 12 00 SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // ---// if not applicable to project. Also delete any other item or paragraph

More information

SENIOR THESIS PROPOSAL STRUCTURAL REDESIGN USING STEEL FRAMING

SENIOR THESIS PROPOSAL STRUCTURAL REDESIGN USING STEEL FRAMING SENIOR THESIS PROPOSAL STRUCTURAL REDESIGN USING STEEL FRAMING THE TOWERS AT THE CITY UNIVERSITY OF NEW YORK NEW YORK CITY, NEW YORK ROBIN SCARAMASTRO AE 481 W DR. MEMARI EXECUTIVE SUMMARY The Towers at

More information

Research Facility Core and Shell (RFCS) Presented by Tim Maffett on April 8 th, 2013

Research Facility Core and Shell (RFCS) Presented by Tim Maffett on April 8 th, 2013 Research Facility Core and Shell (RFCS) Presented by Tim Maffett on April 8 th, 2013 Introduction Presentation Overview Research Facility Core and Shell (RFCS) Presented by Tim Maffett on April 8 th, 2013

More information

Nortrax Section David Manchester Road, Ottawa NON-STRUCTURAL METAL FRAMING 16 May 2014 Page 1

Nortrax Section David Manchester Road, Ottawa NON-STRUCTURAL METAL FRAMING 16 May 2014 Page 1 16 May 2014 Page 1 PART 1 GENERAL 1.1 DESCRIPTION This section specifies steel studs wall systems, shaft wall systems, ceiling or soffit suspended or furred framing, wall furring, fasteners, and accessories

More information

1.02 SYSTEM DESCRIPTION

1.02 SYSTEM DESCRIPTION 1 OF 7 MODULAR MEZZANINES GUIDE SPECIFICATIONS FOR PART 1 - GENERAL 1.01 RELATED WORK A. SECTION 03 30 00: Cast in Place Concrete (and Concrete Finishing) 1. The area where mezzanine is installed shall

More information

SECTION COMPOSITE METAL DECKING

SECTION COMPOSITE METAL DECKING PART 1 GENERAL 1.1 DESCRIPTION SECTION 05 36 00 1. Use this section only for NCA projects. 2. Delete between // ---- // if not applicable to project. Also delete any other item or paragraph not applicable

More information

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Technical Report #2

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Technical Report #2 University at Buffalo CTRC/Incubator Buffalo, New York William McDevitt October 27, 2010 Table of Contents Executive Summary...3 Introduction...4 Structural System Overview...5 Foundation...5 Floor System...5

More information

DIVISION 5 METALS BUSHEY FEIGHT MORIN ARCHITECTS INC. 473 NORTH POTOMAC STREET HAGERSTOWN, MARYLAND FAX:

DIVISION 5 METALS BUSHEY FEIGHT MORIN ARCHITECTS INC. 473 NORTH POTOMAC STREET HAGERSTOWN, MARYLAND FAX: DIVISION 5 METALS BUSHEY FEIGHT MORIN ARCHITECTS INC. 473 NORTH POTOMAC STREET HAGERSTOWN, MARYLAND 21740 301-733-5600 FAX: 301-733-5612 SECTION 05400 - COLD FORMED METAL FRAMING PART 1 GENERAL 1.1 SECTION

More information

The courthouse exterior. Courtesy of NLA/HLM Architects. United States. Courthouse Sacramento, Robert D. McCartney, S.E.

The courthouse exterior. Courtesy of NLA/HLM Architects. United States. Courthouse Sacramento, Robert D. McCartney, S.E. The courthouse exterior. Courtesy of NLA/HLM Architects. United States Courthouse Sacramento, Robert D. McCartney, S.E. CA Modern Steel Construction / November 2001 Public entrances to courtrooms occur

More information

TECH REPORT 3 SANTA ROSA JUNIOR COLLEGE STUDENT CENTER. Alternative Methods Analysis. Dan Vallimont 2009 SENIOR THESIS

TECH REPORT 3 SANTA ROSA JUNIOR COLLEGE STUDENT CENTER. Alternative Methods Analysis. Dan Vallimont 2009 SENIOR THESIS SANTA ROSA JUNIOR COLLEGE STUDENT CENTER Alternative Methods Analysis Dan Vallimont 2009 EXECUTIVE SUMMARY The construction challenges, schedule acceleration scenarios, and value engineering topics of

More information

THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA

THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA Amy Graver, Structural Option - Dr. Hanagan, Advisor 10.21.2002 PRO-CON STRUCTURAL STUDY OF ALTERNATE FLOOR SYSTEMS Executive Summary

More information

Thesis Proposal December 5, 2003

Thesis Proposal December 5, 2003 Executive Summary Thesis Proposal December 5, 2003 Brennan Hall is a five-story office/classroom building. It is located on a slightly sloping site, surrounded by other structures and a small green space.

More information

151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University

151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University November 16 th, 2007 William J. Buchko AE 481w Senior Thesis The Pennsylvania State University Thesis Advisor: Kevin Parfitt Table of Contents Executive Summary... 3 Structural System Overview Foundation...

More information

Steel Expansion. Located along the Grand River in

Steel Expansion. Located along the Grand River in Steel Expansion by Michael Gustafson, P.E. The DeVos Place convention center in Grand Rapids, MI, is undergoing a multi-year expansion featuring steel-framed column-free exhibit space. Located along the

More information

Thesis Proposal. Matthew R Peyton

Thesis Proposal. Matthew R Peyton This Document is for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. S t r u c t u r a l O p t i o n P r o f e s s o r B e h r H o s p i t a l

More information

Abington Memorial Hospital Abington, PA. Project Description

Abington Memorial Hospital Abington, PA. Project Description Project Description Project Description Project Background The expansion is a seven story, 360,000 SF addition with a total project cost of $98 million. Construction began in February 2003 and the project

More information

Structural Breadth. Landmark Façade

Structural Breadth. Landmark Façade Jessica Lucas Hearst Tower Mechanical Option New York, NY Structural Breadth Landmark Façade As mentioned before, the building has two distinct pieces: the historic landmark façade and the new office tower.

More information

East Central College

East Central College SECTION 230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 WORK INCLUDES A. Base Bid and Alternate Bids: 1. Contractor provide the following hangers and supports for HVAC system

More information

SECTION STRUCTURAL STEEL

SECTION STRUCTURAL STEEL PART 1 GENERAL 1.01 SCOPE OF WORK A. The Contractor shall furnish and install all materials, labor, equipment and incidentals required to provide structural steel shown on the Contract Drawings and as

More information

Insulating Cellular Concrete Steel Joists Painting. A. America Society for Testing and Materials (ASTM):

Insulating Cellular Concrete Steel Joists Painting. A. America Society for Testing and Materials (ASTM): SECTION 05120 STRUCTURAL STEEL PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 03342 - Insulating Cellular Concrete. 2. 05210 - Steel Joists. 3. 09900 - Painting. 1.02 REFERENCES A. America Society

More information

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site Installing DELTABEAM Installation of DELTABEAM These DELTABEAM installation instructions are intended to complement the project s erection plan. Peikko s technical support can help with the erection plan

More information

Mansfield University Dormitories Mansfield, Pennsylvania

Mansfield University Dormitories Mansfield, Pennsylvania Mansfield University Dormitories Mansfield, Pennsylvania Michael Mahoney Construction Option Senior Thesis Presentation 2013 The Pennsylvania State University II. III. IV. Modular Setting Precision Project

More information

Project Address: Name of Person Completing Form:

Project Address: Name of Person Completing Form: Statement of Inspections This form is provided as a way to list aspects of the project that require special inspection and testing in accordance with IBC Sections 107.1, 1704, and 1705 and define duties

More information

MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS

MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS PARKERSBURG, WEST VIRGINIA DOMINIC MANNO STRUCTURAL OPTION FACULTY CONSULTANT: DR. ANDRES LEPAGE Technical Report 3 11-21-08 TABLE OF CONTENTS TABLE OF

More information

2012 VIRGINIA TECH SCHEDULE OF SPECIAL INSPECTIONS

2012 VIRGINIA TECH SCHEDULE OF SPECIAL INSPECTIONS 2012 VIRGINIA TECH SCHEDULE OF SPECIAL INSPECTIONS HECO-6 GENERAL Pre-construction conference Preconstruction meeting Scheduled by SI with the Contractor, UBO, A/E, and relevant subs prior to commencement

More information

Structural Steel: An Industry Overview

Structural Steel: An Industry Overview Structural Steel: An Industry Overview A White Paper by the American Institute of Steel Construction October 2017 The United States structural steel industry supplied fabricated and erected structural

More information

2941 Fairview Park Fairview Park. Eric Sobel. Pennsylvania State University Dept. of Architectural Engineering Spring 2003 Structural Option

2941 Fairview Park Fairview Park. Eric Sobel. Pennsylvania State University Dept. of Architectural Engineering Spring 2003 Structural Option Pennsylvania State University Dept. of Architectural Engineering Spring 2003 Structural Option PROJECT TEAM Owner: Developer: Contractor: Architect: Structural: M.E.P.: Envelope: 2941 Fairview L.L.P.

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE # 5A Metal and Structural Steel 09/01/11

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE # 5A Metal and Structural Steel 09/01/11 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: 05 1200 - STRUCTURAL STEEL FRAMING Complete; SECTION: 05 2100 - STEEL JOIST FRAMING Complete;

More information

PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION

PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION An overview of costing strategies for wood framed construction elements CREATING A PROJECT ENDLESS POSSIBILITIES COMPATORS LIST A FLOOR Cast in Place

More information

Penn State Health and Human Development Building State College, PA

Penn State Health and Human Development Building State College, PA Rendering Provided by BCJ Christopher Graziani Advisor: Craig Dubler Construction Management Existing Building Structure Previous View From College Avenue Multi-Use Spaces Rendering Provided by BCJ Rendering

More information

POINT. Making the. The highlights of High Point University s newest academic building are comprised of open volumes, and steel makes them happen.

POINT. Making the. The highlights of High Point University s newest academic building are comprised of open volumes, and steel makes them happen. The highlights of High Point University s newest academic building are comprised of open volumes, and steel makes them happen. Making the POINT BY CHARLES BOWMAN, PE THE NEW COTTRELL HALL, home of the

More information

Analysis and Design of a High Rise Steel Braced Frame Core 60

Analysis and Design of a High Rise Steel Braced Frame Core 60 Analysis and Design of a High Rise Steel Braced Frame Core 60 Construction Management Breadth Study There is a substantial difference between the construction sequence and management of a steel structure

More information

SE APPRENTICE. Today s Speakers. Lateral Load Systems. Lateral Loads

SE APPRENTICE. Today s Speakers. Lateral Load Systems. Lateral Loads Today s Speakers Carrie Bremer, PE Schaefer Stephen Metz, PE SMBH, Inc. Today s Moderators SE APPRENTICE Lecture Two- Systems & Paths Lisa Willard, PE SE Solutions, LLC SE Apprentice Brian Quinn, PE SE

More information

Concrete weighs about 150 pounds per cubic foot

Concrete weighs about 150 pounds per cubic foot At Bassora, where they have no timber, they make arches without any frame. The mason, with a nail and a bit of string, marks a semicircle on the ground, lays his bricks, fastened together with a gypsum

More information

UC Denver Guidelines and Design Standards SECTION STRUCTURAL METAL FRAMING

UC Denver Guidelines and Design Standards SECTION STRUCTURAL METAL FRAMING SECTION 05100 STRUCTURAL METAL FRAMING PART 1 - GENERAL A. This section provides general information standards. PART 2 - PRODUCTS A. Metal Studs- Structural: 1. 18 gauge and heavier units will fabricated

More information

MULTI-RESIDENTIAL BUILDING SOLUTIONS

MULTI-RESIDENTIAL BUILDING SOLUTIONS MULTI-RESIDENTIAL BUILDING SOLUTIONS OUR EXPERTISE AT YOUR SERVICE Canam has been offering owners, real estate developers, architects, engineers and contractors an array of construction solutions since

More information

SECTION ALUMINUM WALKWAY COVERS. A. The requirements of Division 1 specifications shall apply to work specified in the section.

SECTION ALUMINUM WALKWAY COVERS. A. The requirements of Division 1 specifications shall apply to work specified in the section. SECTION 10 5300 ALUMINUM WALKWAY COVERS Part 1 General 1.01 Related Documents A. The requirements of Division 1 specifications shall apply to work specified in the section. 1.02 References A. International

More information

STATEMENT OF SPECIAL INSPECTION FORM

STATEMENT OF SPECIAL INSPECTION FORM Project Title: Permit #: Project Address: STATEMENT OF SPECIAL INSPECTION FORM This Statement of Special Inspections is submitted in fulfillment of the requirements of CBC Sections 1704 and 1705. Special

More information

SPECIFICATIONS Section Cantilevered Walkway Cover

SPECIFICATIONS Section Cantilevered Walkway Cover Part 1: General 1.1 Related Documents SPECIFICATIONS Section 107301 Cantilevered Walkway Cover A. The requirements of Division 1 specifications shall apply to work specified in the section. 1.2 Engineering

More information

Best Buy Corporate Building D (4) Richfield, MN

Best Buy Corporate Building D (4) Richfield, MN Best Buy Corporate Building D (4) Thesis Proposal Professor Boothby December 12 th, 2008 Executive Summary: The Best Buy Corporate Building D is a 6 story building with a total area of 304,610 square feet.

More information

HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT SECTION HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT SECTION HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 13686.00 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 230529-1 SECTION 230529 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 1.1 SUMMARY A. Section Includes: 1. Metal pipe hangers and supports.

More information

Statement of Special Inspections 2013 CBC

Statement of Special Inspections 2013 CBC BUILDIG & SAFET DIVISIO 2729 Prospect Park Drive Rancho Cordova, CA 95670 Phone: (916) 851-8760 Fax: (916) 851-8762 Statement of Special Inspections 2013 CBC PERMIT #: PROJECT ADDRESS: This Statement of

More information

SECTION COLD-FORMED METAL FRAMING

SECTION COLD-FORMED METAL FRAMING The Collective Voice of America s Steel Framing Industry The Steel Framing Industry Association (SFIA) is dedicated to expanding the market for cold-formed steel in construction through programs and initiatives

More information

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options River Tower at Christina Landing Wilmington, DE Joseph Bednarz Structural Option Faculty Advisor: Dr. Boothby Executive Summary January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign

More information

Home Depot Page 1 of 5 HDPB Humacao, PR 10/19/09

Home Depot Page 1 of 5 HDPB Humacao, PR 10/19/09 PART 1 - GENERAL 1.01 SUMMARY A. Types of cold-formed metal framing units include the following: 1. C-shaped steel studs B. Related work specified elsewhere includes but may not be limited to: 1. Section

More information

Thesis Proposal. Office Building. Sayre, PA. Faculty Advisor: Dr. Thomas E. Boothby Revised: January 9, 2013

Thesis Proposal. Office Building. Sayre, PA. Faculty Advisor: Dr. Thomas E. Boothby Revised: January 9, 2013 Faculty Advisor: Dr. Thomas E. Boothby Revised: January 9, 2013 Office Building Sayre, PA Seth M. Moyer Structural Table of Contents Executive Summary 3 Building Introduction 4 Structural Overview..6 Foundations

More information

DIVISION 5 METALS SECTION METAL DECKING

DIVISION 5 METALS SECTION METAL DECKING DIVISION 5 METALS SECTION 05 30 00 PART 1 GENERAL 1.01 SUMMARY A. Section Includes: All labor and materials required to furnish and install metal decking and accessories including shear connectors, closures,

More information

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8 WISCONSIN PLACE RESIDENTIAL TECHNICAL ASSIGNMENT 2 OCTOBER 29, 2007 KURT KRASAVAGE THE PENNSYLVANIA STATE UNIVERSITY STRUCTURAL OPTION FACULTY ADVISOR: DR. ALI MEMARI 1 Table of Contents Table of Contents.2

More information

On Cold-Formed Steel Construction. Light Gauge Steel Engineers Association Washington, D.C Toll Free (866)

On Cold-Formed Steel Construction. Light Gauge Steel Engineers Association Washington, D.C Toll Free (866) TECHNICAL NOTE On Cold-Formed Steel Construction $5.00 Light Gauge Steel Engineers Association Washington, D.C. 20005 Toll Free (866) 465-4732 www.lgsea.com DESIGN OF BY-PASS SLIP CONNECTORS IN COLD-FORMED

More information

Thesis Proposal. Office Building. Sayre, PA. Faculty Advisor: Dr. Thomas E. Boothby Revised: April 1, 2013

Thesis Proposal. Office Building. Sayre, PA. Faculty Advisor: Dr. Thomas E. Boothby Revised: April 1, 2013 Faculty Advisor: Dr. Thomas E. Boothby Revised: April 1, 2013 Office Building Sayre, PA Seth M. Moyer Structural Table of Contents Executive Summary 3 Building Introduction 4 Structural Overview..6 Foundations

More information

SECTION PRE-ENGINEERED METAL BUILDING

SECTION PRE-ENGINEERED METAL BUILDING SECTION 13121 PRE-ENGINEERED METAL BUILDING PART 1 GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required to design, fabricate, deliver to project site, and erect

More information

Item 442 Metal for Structures

Item 442 Metal for Structures Item 442 Metal for Structures 1. DESCRIPTION 2. MATERIALS Provide structural steel, high-strength bolts, forgings, steel castings, iron castings, wrought iron, steel pipe and tubing, aluminum castings

More information

STATE UNIVERSITY CONSTRUCTION FUND. UNIVERSITY CON DIRECTIVE 5-1 Issue date: October 2014

STATE UNIVERSITY CONSTRUCTION FUND. UNIVERSITY CON DIRECTIVE 5-1 Issue date: October 2014 STATE STRUCTION FUND DIRECTIVE 5-1 Issue date: October 2014 STRUCTURAL STEEL 1. General: It is the Fund's policy that the design of the structural steel is the prime responsibility of the project's Structural

More information

Connection Design Assistance Manual

Connection Design Assistance Manual Connection Design Assistance Manual Architectural Precast Concrete Glass Fiber Reinforced Concrete Cast Stone Architectural Precast Association 6710 Winkler Road, Suite 8 Fort Myers, FL 33919 Phone: 239-454-6989

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 052100 - STEEL JOISTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. Drawings and General Provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections

More information

Potential Solutions- Background: Current Designs. Potential Solutions. Goals for Design What are we concerned about?

Potential Solutions- Background: Current Designs. Potential Solutions. Goals for Design What are we concerned about? Potential Solutions Potential Solutions- Background: Current Designs Goals for Design What are we concerned about? Primary Goal: Get the deck on successfully Stability during deck pour Girder plumbness

More information

Introduction to Cambering

Introduction to Cambering Image courtesy of CAMBCO Inc. 35 Introduction to Cambering Cambering is the process of creating an intentional slight curvature in a beam Image courtesy of CAMBCO Inc. 36 18 Introduction to Cambering Camber

More information

TECHNICAL ASSIGNMENT THREE

TECHNICAL ASSIGNMENT THREE TECHNICAL ASSIGNMENT THREE PENN STATE SENIOR AE THESIS New York Police Academy College Point, New York Shawn Sidelinger Construction Management Dr. Robert Leicht Table of Contents Executive Summary...3

More information

SECTION MISCELLANEOUS METALS

SECTION MISCELLANEOUS METALS PART 1 GENERAL 1.1 WORK OF THIS SECTION A. Contractor shall provide all labor, materials, equipment and incidentals as shown, specified and required to furnish and install all miscellaneous metal fabrications

More information

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity System Codes and Criteria Design Codes and Standards The design code used is the Wisconsin Administrative Code along with the State of Wisconsin Department of Commerce-Safety & Buildings Chapters Comm

More information

LAPEYRE STAIR PRODUCT LINE

LAPEYRE STAIR PRODUCT LINE LAPEYRE STAIR PRODUCT LINE Continuously Elevating Standards lapeyrestair.com Leave the stairs to the experts Lapeyre Stair provides a complete outsource solution for stairs with in-house resouces and over

More information

Special Inspection Requirements for Occupancy Permits

Special Inspection Requirements for Occupancy Permits October 2013 - Newsletter Special Inspection Requirements for Occupancy Permits Performing the required special inspections throughout a construction project can help avoid the denial of occupancy permits,

More information

INSTRUCTIONS AND GUIDELINES

INSTRUCTIONS AND GUIDELINES INSTRUCTIONS AND GUIDELINES NOISEBLOCK TM MODULAR PANEL SYSTEMS ENCLOSURES & PRESSURIZED PLENUMS PLANNING HINTS & NOTES: 1. Review the Kinetics Noise Control submittal and installation drawings and bill

More information

. SECTION HANGERS AND SUPPORTS

. SECTION HANGERS AND SUPPORTS . SECTION 230529 - HANGERS AND SUPPORTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division I Specification

More information

A-BEAM W Erection Manual 2

A-BEAM W Erection Manual 2 2 BEAM W Revision 6/2017 Finland 3 TABLE OF CONTENTS 1 ERECTION INSTRUCTIONS... 4 1.1 A-BEAM W... 4 1.2 Codes and standards to be followed during erection... 4 1.3 Documents to be followed in erection

More information

SECTION NON-STRUCTURAL METAL FRAMING

SECTION NON-STRUCTURAL METAL FRAMING SECTION 09 22 16 PART 1 - GENERAL 1.1 DESCRIPTION A. This section specifies steel studs wall systems, shaft wall systems, ceiling or soffit suspended or furred framing, wall furring, fasteners, and accessories

More information

A-BEAM S Erection Manual 2

A-BEAM S Erection Manual 2 2 A-BEAM S Revision 6/2017 Finland 3 TABLE OF CONTENTS 1 ERECTION INSTRUCTIONS... 4 1.1 A-BEAM S... 4 1.2 Codes and standards to be followed during erection work... 4 1.3 Structural plans to be followed

More information

Chuck Brooks, P.E., P.Eng. C&S Engineers

Chuck Brooks, P.E., P.Eng. C&S Engineers Chuck Brooks, P.E., P.Eng C&S Engineers 315-455-2000 cbrooks@cscos.com AGENDA INTRO BASICS KEY CONSIDERATIONS DESIGN CONSTRUCTION Questions to be Explored 1. Concrete Tiltup Panels are designed for the

More information

Special Delivery. A California healthcare complex takes structural engineering collaborative design and integrated project delivery to new heights.

Special Delivery. A California healthcare complex takes structural engineering collaborative design and integrated project delivery to new heights. A California healthcare complex takes structural engineering collaborative design and integrated project delivery to new heights. Special Delivery by Edwin Najarian, S.E., P.E., and Mohammad Aliaari, S.E.,

More information

Daytona Beach Pier Building Renovation Jun 2010

Daytona Beach Pier Building Renovation Jun 2010 SECTION 15060 - HANGERS AND SUPPORTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information